02 Presupuesto Analitico Huaccaychaca

3
1 2.6.23.24 PERSONAL S/. 1,368,663.00 CARGO UNID. P.U. CANTIDAD SUB TOTAL TÉCNICO TOPOGRAFO B-1 (ZONA 1) HH 14.74 57.19 842.98 OPERADOR B-2 (ZONA 1) HH 14.74 25,490.52 325,004.13 AUXILIAR B-3 (ZONA 1) HH 12.75 28,298.62 417,121.66 AYUDANTE B-4 (ZONA 1) HH 11.46 54,598.10 625,694.23 1,368,663.00 2.6.23.25 BIENES S/. 5,888,409.11 MATERIALES DE CONSTRUCCION DESCRIPCION UNID. P.U. CANTIDAD TOTAL ABRAZADERA DE PLANCHA METALICA PZA 75.00 60.00 4,500.00 ACELERANTE DE FRAGUA GLN 29.00 1,408.44 40,844.76 ACERO CORRUGADO 1/2" KG 36.10 246.00 8,880.60 ACERO DE REFUERZO FY=4200 kg/cm2 GRADO 60 KG 3.10 159,169.57 493,425.67 ADITIVO EXPANSIVO DE CONCRETO KG 55.00 0.06 3.30 AGUA M3 1.20 2,000.63 2,400.76 ALAMBRE NEGRO # 8 KG 4.80 2,345.85 11,260.08 ALAMBRE NEGRO # 16 KG 4.80 9,089.85 43,631.28 ANFO KG 5.00 1,145.83 5,729.15 ANGULAR 100 x 100 X 10 mm M 52.26 158.40 8,277.98 ANGULAR 100 x 100 X 12 mm M 55.00 1,472.70 80,998.50 ANGULAR 3" x 3" X 1/4" M 25.52 4,247.76 108,402.84 ANGULO DE FIERRO 1" x 1" x 3/16" M 8.00 65.32 522.56 ARENA FINA M3 150.00 0.49 73.50 ARENA GRUESA M3 150.00 1,943.68 291,552.00 ARMADO Y LANZAMIENTO DE CUADROS UND 150.00 30.00 4,500.00 ARMES DE SEGURIDAD PERSONAL UND 95.00 16.00 1,520.00 ASFALTO RC-250 GLN 16.00 5.92 94.72 BARANDA RIGIDA EN BORDE DE TALUD M.L 25.00 200.00 5,000.00 BARRENO DE PERFORACION 7/8" X 1.7 MTS PZA 155.00 0.78 120.90 BOTAS DE JEBE PAR 28.00 80.00 2,240.00 BOTIQUIN CON MEDICINA BASICA DE EMERGENCIA PZA 600.00 1.00 600.00 CABLE 12 AWG x 100 m rll 150.00 10.00 1,500.00 CABLE 8 AWG x100 m rll 350.00 5.00 1,750.00 CABLE DE ACERO Ø 1/2" M 65.00 585.90 38,083.50 CABLE ESTURION Ø 2" M 300.00 487.20 146,160.00 CABLE NEGRO TIPO BOA Ø 1" M 180.00 404.00 72,720.00 CALAMINA PLN 18.00 565.30 10,175.40 CAPACITACION EN SEGURIDAD Y SALUD und 3,000.00 1.00 3,000.00 CASCOS DE PROTECCION PZA 27.00 80.00 2,160.00 CEMENTO PORTLAND TIPO I (42.5 kg) BOL 23.50 45,718.10 1,074,375.35 CHALECOS DE IDENTIFICACION PZA 35.00 80.00 2,800.00 CINTA SEÑALIZADORA RLL 55.00 5.00 275.00 CLAVOS KG 4.50 112.36 505.62 CLAVOS PARA MADERA C/C 1" KG 9.00 1.00 9.00 CLAVOS PARA MADERA C/C 3" KG 4.50 2,947.27 13,262.72 CLAVOS PARA MADERA C/C 4" KG 4.50 17.87 80.42 COLOCACION DE LARGUEROS UND 12.00 210.00 2,520.00 COLOCADO DE MADERAMEN M2 15.00 145.00 2,175.00 COLOCADO DE MONTURAS UND 120.00 4.00 480.00 CONTENEDOR PZA 1,000.00 4.00 4,000.00 CURSO DEL PROGRAMA DE EDUCACION AMBIENTAL GLB 1,000.00 6.00 6,000.00 DESMOLDADOR PARA ENCOFRADO C/V GLN 40.00 484.32 19,372.80 DESMONTAJE DE CAMPAMENTO GLB 5,000.00 1.00 5,000.00 DESMONTAJE DE FALSO PUENTE GLB 125,000.00 1.00 125,000.00 DESMONTAJE DE PASARELA GLB 13,000.00 1.00 13,000.00 DINAMITA KG 30.00 220.10 6,603.00 DISCO DE CORTE PZA 15.00 755.11 11,326.65 DISEÑO DE CONCRETO U 550.00 7.00 3,850.00 DISOLVENTE GLN 25.00 1.89 47.25 DOWEL ACERO Ø 1/2" M 15.00 19.50 292.50 DRISSA DE NYLON 3/4" M 1.50 400.00 600.00 ELIMINACION DE ESTRUCTURAS DE CONCRETO M3 45.00 179.27 8,067.15 ESTRIBO DE ACERO PORTA VIGUETAS UND 82.00 60.00 4,920.00 FIBRA DE VIDRIO DE 4 mm ACABADO M2 198.32 11.22 2,225.14 FLETE TERRESTRE TON 200.00 2,485.11 497,022.00 FOCO PAR 100 W PZA 35.00 20.00 700.00 FULMINANTE UND 2.50 2,653.24 6,633.10 DESAGREGADO DEL PRESUPUESTO ANALÍTICO COSTO DIRECTO TOTAL

Transcript of 02 Presupuesto Analitico Huaccaychaca

  • 12.6.23.24 PERSONAL S/. 1,368,663.00

    CARGO UNID. P.U. CANTIDAD SUB TOTALTCNICO TOPOGRAFO B-1 (ZONA 1) HH 14.74 57.19 842.98OPERADOR B-2 (ZONA 1) HH 14.74 25,490.52 325,004.13AUXILIAR B-3 (ZONA 1) HH 12.75 28,298.62 417,121.66AYUDANTE B-4 (ZONA 1) HH 11.46 54,598.10 625,694.23

    1,368,663.00

    2.6.23.25 BIENES S/. 5,888,409.11

    MATERIALES DE CONSTRUCCION

    DESCRIPCION UNID. P.U. CANTIDAD TOTALABRAZADERA DE PLANCHA METALICA PZA 75.00 60.00 4,500.00ACELERANTE DE FRAGUA GLN 29.00 1,408.44 40,844.76ACERO CORRUGADO 1/2" KG 36.10 246.00 8,880.60ACERO DE REFUERZO FY=4200 kg/cm2 GRADO 60 KG 3.10 159,169.57 493,425.67ADITIVO EXPANSIVO DE CONCRETO KG 55.00 0.06 3.30AGUA M3 1.20 2,000.63 2,400.76ALAMBRE NEGRO # 8 KG 4.80 2,345.85 11,260.08ALAMBRE NEGRO # 16 KG 4.80 9,089.85 43,631.28ANFO KG 5.00 1,145.83 5,729.15ANGULAR 100 x 100 X 10 mm M 52.26 158.40 8,277.98ANGULAR 100 x 100 X 12 mm M 55.00 1,472.70 80,998.50ANGULAR 3" x 3" X 1/4" M 25.52 4,247.76 108,402.84ANGULO DE FIERRO 1" x 1" x 3/16" M 8.00 65.32 522.56ARENA FINA M3 150.00 0.49 73.50ARENA GRUESA M3 150.00 1,943.68 291,552.00ARMADO Y LANZAMIENTO DE CUADROS UND 150.00 30.00 4,500.00ARMES DE SEGURIDAD PERSONAL UND 95.00 16.00 1,520.00ASFALTO RC-250 GLN 16.00 5.92 94.72BARANDA RIGIDA EN BORDE DE TALUD M.L 25.00 200.00 5,000.00BARRENO DE PERFORACION 7/8" X 1.7 MTS PZA 155.00 0.78 120.90BOTAS DE JEBE PAR 28.00 80.00 2,240.00BOTIQUIN CON MEDICINA BASICA DE EMERGENCIA PZA 600.00 1.00 600.00CABLE 12 AWG x 100 m rll 150.00 10.00 1,500.00CABLE 8 AWG x100 m rll 350.00 5.00 1,750.00CABLE DE ACERO 1/2" M 65.00 585.90 38,083.50CABLE ESTURION 2" M 300.00 487.20 146,160.00CABLE NEGRO TIPO BOA 1" M 180.00 404.00 72,720.00CALAMINA PLN 18.00 565.30 10,175.40CAPACITACION EN SEGURIDAD Y SALUD und 3,000.00 1.00 3,000.00CASCOS DE PROTECCION PZA 27.00 80.00 2,160.00CEMENTO PORTLAND TIPO I (42.5 kg) BOL 23.50 45,718.10 1,074,375.35CHALECOS DE IDENTIFICACION PZA 35.00 80.00 2,800.00CINTA SEALIZADORA RLL 55.00 5.00 275.00CLAVOS KG 4.50 112.36 505.62CLAVOS PARA MADERA C/C 1" KG 9.00 1.00 9.00CLAVOS PARA MADERA C/C 3" KG 4.50 2,947.27 13,262.72CLAVOS PARA MADERA C/C 4" KG 4.50 17.87 80.42COLOCACION DE LARGUEROS UND 12.00 210.00 2,520.00COLOCADO DE MADERAMEN M2 15.00 145.00 2,175.00COLOCADO DE MONTURAS UND 120.00 4.00 480.00CONTENEDOR PZA 1,000.00 4.00 4,000.00CURSO DEL PROGRAMA DE EDUCACION AMBIENTAL GLB 1,000.00 6.00 6,000.00DESMOLDADOR PARA ENCOFRADO C/V GLN 40.00 484.32 19,372.80DESMONTAJE DE CAMPAMENTO GLB 5,000.00 1.00 5,000.00DESMONTAJE DE FALSO PUENTE GLB 125,000.00 1.00 125,000.00DESMONTAJE DE PASARELA GLB 13,000.00 1.00 13,000.00DINAMITA KG 30.00 220.10 6,603.00DISCO DE CORTE PZA 15.00 755.11 11,326.65DISEO DE CONCRETO U 550.00 7.00 3,850.00DISOLVENTE GLN 25.00 1.89 47.25DOWEL ACERO 1/2" M 15.00 19.50 292.50DRISSA DE NYLON 3/4" M 1.50 400.00 600.00ELIMINACION DE ESTRUCTURAS DE CONCRETO M3 45.00 179.27 8,067.15ESTRIBO DE ACERO PORTA VIGUETAS UND 82.00 60.00 4,920.00FIBRA DE VIDRIO DE 4 mm ACABADO M2 198.32 11.22 2,225.14FLETE TERRESTRE TON 200.00 2,485.11 497,022.00FOCO PAR 100 W PZA 35.00 20.00 700.00FULMINANTE UND 2.50 2,653.24 6,633.10

    DESAGREGADO DEL PRESUPUESTO ANALTICO

    COSTO DIRECTO

    TOTAL

  • 2GENERADOR ELECTRICO DIESEL DE 20 KVA und 10,500.00 2.00 21,000.00GIGANTOGRAFA M2 25.00 12.50 312.50GUANTES DE CUERO PAR 8.00 80.00 640.00GUARDA CABLES UND 135.00 8.00 1,080.00GUIA DE SEGURIDAD M 2.00 2,653.24 5,306.48HORMIGON M3 150.00 1,963.14 294,471.00INSTALACION PROVISIONAL DE AGUA PARA LA CONSTRUCCIO GLB 4,500.00 1.00 4,500.00INSTALACION PROVISIONAL DE DESAGUE PARA LA CONSTRUCCION GLB 3,500.00 1.00 3,500.00LAMINA REFLECTIVA ALTA INTENSIDAD m2 325.00 11.22 3,646.50LANZADO DE CABLE NEGRO TIPO BOA DE 1 1/4" M 15.00 661.00 9,915.00LENTES DE PROTECCION PZA 8.00 80.00 640.00LETREROS DE AVISO PZA 150.00 6.00 900.00LISTONES DE MADERA 3"X4" P2 3.50 18,111.09 63,388.82MADERA P2 3.50 11,236.30 39,327.05MADERA 11/2" X 8" X 3 M PZA 45.00 300.00 13,500.00MADERA 4"X5"X2.20 M PZA 48.11 210.00 10,103.10MADERA 4"x6"x3,00M PZA 78.72 30.00 2,361.60MADERA CORRIENTE 2"x 8" P2 3.50 13,123.21 45,931.24MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA P2 3.50 105,470.08 369,145.28MADERA ROLLIZA DE 3" x 3,00 M PZA 18.00 5.58 100.44MADERA ROLLIZO DE 6" p/m 15.00 1,123.63 16,854.45MADERA ROLLIZO DE 8" M 10.00 3,148.74 31,487.40MALLA DE ALAMB.GALV.# 12,COCADA 3/4X3/4" M2 38.00 120.00 4,560.00MALLAS DE SEGURIDAD M2 8.00 200.00 1,600.00MATERIAL DE CANTERA M3 25.00 3,339.44 83,486.00MONITOREO AMBIENTAL GLB 1,000.00 18.00 18,000.00MONTAJE DE ARCOS PRINCIPALES Y DE ARRIOSTRE GLB 300,000.00 1.00 300,000.00MONTURA METALICA DE DILATACION UND 560.00 4.00 2,240.00MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 117,629.00 1.00 117,629.00PENDOLAS DE FIERRO LISO DE 1/2" M 12.00 209.93 2,519.16PERNO C/TUERCA-ARANDELA 10" UND 15.00 420.00 6,300.00PERNOS 5/8" X 10" PZA 5.00 760.00 3,800.00PERNOS 5/8" X 3" PZA 2.00 44.00 88.00PETROLEO GLN 13.00 568.43 7,389.59PIEDRA M3 80.00 1,250.39 100,031.20PIEDRA CHANCADA DE 1/2" M3 200.00 5.57 1,114.00PIEDRA CHANCADA DE 3/4" M3 200.00 2,205.78 441,156.00PIEDRA GRANDE DE 8" M3 80.00 334.13 26,730.40PIEDRA MEDIANA M3 80.00 86.48 6,918.40PINTURA ANTICORROSIVA GLN 48.00 80.15 3,847.20PINTURA DE TRAFICO GLN 55.00 7.08 389.40PINTURA ESMALTE GLN 48.00 27.51 1,320.48PLANCHA DE ACERO DE 0,20 x 0,30 m, E=1/2" UND 35.00 190.00 6,650.00PLATINA 0.20 x 2.27 m, E= 3/8" UND 239.24 190.00 45,455.60PLATINA 0.25 x 1.10 m, E=3/8" UND 108.57 190.00 20,628.30PLATINA DE FIERRO 20 x 20 x 1/ 2" PZA 21.31 48.00 1,022.88POSTE PROVISIONAL DE MADERA PZA 500.00 8.00 4,000.00PROTECCION AUDITIVA TAPONES ULTRA FIT C/CORDON UND 8.50 80.00 680.00PRUEBA DE CARGA GLB 35,000.00 1.00 35,000.00PRUEBA DE DENSIDAD DE COMPACTACION UND 40.00 396.00 15,840.00PRUEBAS DE CALIDAD DE CONCRETO ROTURA UND 45.00 300.00 13,500.00PRUEBAS PROCTOR MODIFICADO UND 250.00 4.00 1,000.00PUNTOS DE ANCLAJE UND 25.00 200.00 5,000.00RECURSO MEDICO-ADMINISTRATIVO GLB 6,000.00 1.00 6,000.00REFLECTOR AL. FUNDIDO LUZ HALOGENA 1500W UND 600.00 4.00 2,400.00RESPIRADOR MEDIA CARA 2 VIAS UND 45.00 80.00 3,600.00RIELES M 250.00 40.00 10,000.00SEAL NOCTURNA (LUZ DE EMERGENCIA) EQU 1,500.00 1.00 1,500.00SOLDADURA KG 17.85 999.02 17,831.25SOPORTE DE FIERRO PARA LAMPARAS UND 420.00 8.00 3,360.00TABLERO ELECTRICO BLINDADO 3 X 35A PZA 800.00 1.00 800.00TECKNOPORT E= 1" M2 8.00 40.50 324.00TENSOR DE 2"x 80 CM PZA 4,500.00 12.00 54,000.00TINTA XEROGRAFICA NEGRA UND 90.00 1.70 153.00TRANQUERA UND 200.00 6.00 1,200.00TRIPLAY DE 19 mm PLN 125.00 1,951.24 243,905.00TUBERIA PVC 3/4" M 2.50 684.08 1,710.20TUBERIA PVC-SAP DE 3" M 26.50 423.98 11,235.47TUBO F G 2 1/2" M 37.00 802.56 29,694.72TUBO F G 3" M 59.00 267.52 15,783.68TUBO FG 4" M 110.00 60.48 6,652.80TUBO PVC SAL 6" M 27.00 24.00 648.00YESO DE 28 Kg BOL 9.80 71.49 700.60

    5,828,775.36

    HERRAMIENTAS

    DESCRIPCION UNID. P.U. CANTIDAD TOTALHERRAMIENTAS VARIAS GLB 1.00 59,633.75 59,633.75

    59,633.75

    TOTAL

    TOTAL

  • 32.6.23.26 SERVICIOS S/. 618,997.28

    MANTENIMIENTO DE MAQUINARIA Y EQUIPO

    DESCRIPCION UNID. P.U. CANTIDAD SUB TOTALAMOLADORA HM 2.00 5,832.40 11,664.80

    ANDAMIO HE 2.00 45.00 90.00

    CAMION CISTERNA 4X2 (AGUA) 1,500 GAL. HM 190.00 146.51 27,836.90

    CAMION PLATAFORMA 4x2 122 HP 8 TON. HM 220.00 72.00 15,840.00

    CAMION VOLQUETE 6 X 4 330 HP 10 m3 HM 110.00 9.81 1,079.10

    CARGADOR SOBRE LLANTAS 125-155 HP 3 yd3 HM 200.00 289.99 57,998.00

    CIZALLA ELECTRICA HM 3.00 29.86 89.58

    COMPRESORA HM 10.00 1,028.60 10,286.00

    COMPRESORA NEUMATICA 196 HP 600-690 PCM HM 120.00 209.65 25,158.00

    EQUIPO DE SOLDAR HM 12.00 1,653.00 19,836.00

    ESTACION TOTAL HM 15.00 57.19 857.85

    MACHETES PZA 35.00 12.00 420.00

    MARTILLO NEUMATICO DE 25 kg HM 12.00 429.75 5,157.00

    MEZCLADORA CONCRETO TAMBOR 11 P3-18 HP HM 15.00 2,963.70 44,455.50

    MOTO PERFORADORA (PIONJER) HM 10.00 29.86 298.60

    MOTOBOMBA 17 HP 6" HM 10.00 4,796.96 47,969.60

    MOTONIVELADORA DE 125 HP HM 200.00 16.00 3,200.00

    MOTOSIERRA HM 5.30 19.20 101.76

    NIVEL TOPOGRAFICO HM 7.93 57.19 453.68

    RETROEXCAVADOR SOBRE ORUGA 325 HP 2-3.8 yd3 HM 280.00 445.99 124,877.20

    RODILLO LISO VIBR AUTOP 101-135HP 10-12T HM 200.00 179.70 35,940.00

    TECLE 5 TON-TRIPODE HH 10.00 82.21 822.10

    TRACTOR DE ORUGAS DE 190-240 HP HM 320.00 3.97 1,270.40

    VIBRADOR DE CONCRETO 4 HP 2.40" HM 7.00 2,582.48 18,077.36

    VOLQUETE DE 10 m3 HM 100.00 698.11 69,811.00

    WINCHE DE DOS BALDES (350KG) 3.6HP HM 35.00 2,725.91 95,406.85

    618,997.28

    S/. 7,876,069.39

    TOTAL

    COSTO DIRECTO TOTAL