Dr. Agustin Zúñiga Gamarra Departamento de Cálculo Análisis y Seguridad
Centro Nuclear RACSO Huarangal, 30 de noviembre de 2012
![Page 2: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/2.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 2
![Page 3: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/3.jpg)
reacciones nucleares de fisión autosostenida ...... puesta a crítico)
partida de nacimiento,
R1
• El experimento • El método • Las configuraciones • Anécdotas
A.ZUÑIGA 24 ANIVERSARIO RP10 3
![Page 4: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/4.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10
Relanciamiento del RP10
Vigilancia y Prospectiva
4
![Page 5: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/5.jpg)
Reacciones de fisión controladas
A.ZUÑIGA 24 ANIVERSARIO RP10 5
![Page 6: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/6.jpg)
Reacción Nuclear de Fisión en Cadena
neutrón
neutrón
Radiaciones Ionizantes neutrón
U - 235
Fragmento de Fisión
Fragmento de Fisión
CALOR a b g
¿Qué necesitamos para mantenerla bajo control?
Barra de control
Absorbente de
neutrones (Cd, B)
En el reactor nuclear, la reacción en cadena es manejada a fin de mantener un ritmo de fisión constante (durante la operación comercial)
A.ZUÑIGA 24 ANIVERSARIO RP10 23 Aniv
6
![Page 7: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/7.jpg)
Factor de Multiplicación
A.ZUÑIGA 24 ANIVERSARIO RP10 7
![Page 8: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/8.jpg)
• ¿El neutrón térmico qué camino sigue hasta que vuelve a ser térmico?
• ¿ Si al inicio hay N1 neutrones y al final hay N2: cómo se define la razón: N2/N1?
• ¿Cuándo se daría la situación para que en todo tiempo: N2 = N1?
• ¿ Qué es crítico, o supercrítico, o subcrítico?
• ¿Qué es la MULTIPLICACIÓN? A.ZUÑIGA 24 ANIVERSARIO RP10 8
![Page 9: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/9.jpg)
Enrico Fermi: 02-12-1942
A.ZUÑIGA 24 ANIVERSARIO RP10 9
![Page 10: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/10.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10
AoD
10
![Page 11: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/11.jpg)
Ref. Lectura
A.ZUÑIGA 24 ANIVERSARIO RP10 11
![Page 12: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/12.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 12
![Page 13: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/13.jpg)
Programa PES : cumplen con las especificaciones contractuales
A.ZUÑIGA 24 ANIVERSARIO RP10 13
![Page 14: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/14.jpg)
Planificar la puesta en servicio del RP-10, con la finalidad que durante dicho proceso se logre: } Verificar que la instalación de las estructuras, sistemas, componentes
e instrumentación es adecuada, comenzando por la aceptación de los componentes instalados y probando luego los sistemas individualmente y pasando seguidamente a las pruebas de sistemas integrados.
} Demostrar la idoneidad de los procedimientos y pruebas para la explotación de la instalación en condiciones de seguridad.
} Estas acciones, en lo posible deberán dar lugar a que el personal de explotación de cada una de las instalaciones objeto de este documento, se familiarice con las características de funcionamiento y con los procedimientos propuestos para tal fin, así como con las operaciones de mantenimiento y pruebas proyectadas.
} Demostrar que las instalaciones cumplen con las especificaciones contractuales.
A.ZUÑIGA 24 ANIVERSARIO RP10 14
![Page 15: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/15.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10
Carga del Núcleo
15
![Page 16: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/16.jpg)
Aproximación a crítico y núcleo de arranque del RP10
A.ZUÑIGA 24 ANIVERSARIO RP10 16
![Page 17: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/17.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 17
![Page 18: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/18.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 18
![Page 19: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/19.jpg)
El método de aproximación a crítico
A.ZUÑIGA 24 ANIVERSARIO RP10 19
![Page 20: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/20.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 20
![Page 21: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/21.jpg)
Fuente
Detector
Combustible
...... 32 ++++= efefef kSkSkSSTotal
S n/s
kef
kef :Factor de multiplicación efectiva de la configuración
( ) MSkkkSContaje efefef ....1 32 =++++=
( )efkM -= 11
SubcríticokcoSupercrítik
Críticok
ef
ef
ef
:1
:1
:1
á
ñ
=
CONFIGURACIÓN DEL NÚCLEO
M (U235)
1/C
m1 m2 m3 mcrit
Masa crítica estimada
0
si Kefà1 entonces 1/C à0
A.ZUÑIGA 24 ANIVERSARIO RP10 21
![Page 22: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/22.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 22
![Page 23: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/23.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 23
![Page 24: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/24.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 24
![Page 25: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/25.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 25
![Page 26: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/26.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 26
![Page 27: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/27.jpg)
C ( 1
/s)
t (s)
Figura 1
Figura 2
A.ZUÑIGA 24 ANIVERSARIO RP10 27
![Page 28: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/28.jpg)
Figura 3
A.ZUÑIGA 24 ANIVERSARIO RP10 28
![Page 29: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/29.jpg)
Aproximación crítica y de arranque
A.ZUÑIGA 24 ANIVERSARIO RP10 29
![Page 30: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/30.jpg)
PRIMERA PUESTA A CRÍTICO DEL RP10
COLUMNA TERMICA
A B C D E F G H I J
1
2NN006 NN005 NN007
3CF2 BS2
NC02NN001 BC1
NC02
4NN013 NN002 PI
FNNN003
5NN014 BC2
NC02NN004 BS3
NC02
6NN008 NN009 NN010 CF3
7NN011 BS1
NC01NN012
8CF1
9
10
CONDUCTO TANGENCIAL
NN NCNUCLEO 1: FECHA: 25/11/1988 HORA: 15:00 horasNUCLEO 2: FECHA: 26/11/1988 HORA: 11:44 horasNUCLEO 3: FECHA: 26/11/1988 HORA: 15:33 horasNUCLEO 4: FECHA: 28/11/1988 HORA: 10:20 horasNUCLEO 5: FECHA: 28/11/1988 HORA: 15:40 horasNUCLEO 6: FECHA: 29/11/1988 HORA: 10:01 horasNUCLEO 7: FECHA: 29/11/1988 HORA: 14:01 horasNUCLEO 8: FECHA: 29/11/1988 HORA: 10:36 horasNUCLEO 9: FECHA: 30/11/1988 HORA: 15:41 horasCRITICO FECHA: 30/11/1988 HORA: 17:45 horas
A.ZUÑIGA 24 ANIVERSARIO RP10 30
![Page 31: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/31.jpg)
PRIMERA PUESTA A CRÍTICO DEL RP10
COLUMNA TERMICA
A B C D E F G H I J
1
2NN006 NN005 NN007
3CF2 BS2
NC02NN001 BC1
NC02
4NN013 NN002 PI
FNNN003
5NN014 BC2
NC02NN004 BS3
NC02
6NN008 NN009 NN010 CF3
7NN011 BS1
NC01NN012
8CF1
9
10
CONDUCTO TANGENCIAL
NN NCNUCLEO 1: FECHA: 25/11/1988 HORA: 15:00 horasNUCLEO 2: FECHA: 26/11/1988 HORA: 11:44 horasNUCLEO 3: FECHA: 26/11/1988 HORA: 15:33 horasNUCLEO 4: FECHA: 28/11/1988 HORA: 10:20 horasNUCLEO 5: FECHA: 28/11/1988 HORA: 15:40 horasNUCLEO 6: FECHA: 29/11/1988 HORA: 10:01 horasNUCLEO 7: FECHA: 29/11/1988 HORA: 14:01 horasNUCLEO 8: FECHA: 29/11/1988 HORA: 10:36 horasNUCLEO 9: FECHA: 30/11/1988 HORA: 15:41 horasCRITICO FECHA: 30/11/1988 HORA: 17:45 horas
A.ZUÑIGA 24 ANIVERSARIO RP10 31
![Page 32: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/32.jpg)
COLUMNA TERMICA
A B C D E F G H I J
1 G G
2 G NN006 NN005 NN007 G
3 CF2 BS2 NC02
NN001 BC1 NC02
4 G NN013 NN002 PI FN
NN003 NN015 G
5 G NN014 BC2 NC02
NN004 BS3 NC02
NN016 G
6 NN008 NN009 NN010 CF3
7 G NN011 BS1 NC01
NN012 G
8 G G G
9 CF110
CONDUCTO TANGENCIAL
Ref. 2
A.ZUÑIGA 24 ANIVERSARIO RP10 32
![Page 33: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/33.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 33
![Page 34: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/34.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 34
![Page 35: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/35.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10
Ref. Factor Pico N14
35
![Page 36: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/36.jpg)
30 de noviembre de 1988
A.ZUÑIGA 24 ANIVERSARIO RP10 36
![Page 37: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/37.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 37
Este es el acta de la configuración previa a la siguiente que sería la que alcance al criticidad.
![Page 38: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/38.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 38
![Page 39: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/39.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 39
Jefe del Reactor: E. Porro Jefe de Operación: E. Arena Operadores: Gutierrez y Castillo Auxiliares: Villegas y Castro. Oficial de Radioprotección: F. García.
![Page 40: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/40.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 40
El equipo de Física de Reactores, estuvo presidida por la Licenciada en Física Srta. Maria Teresa Bang (q.e.d), y lo integrábamos: J. Avila, J. Lamas, E. Cerrón y A. Zuñiga
![Page 41: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/41.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 41
![Page 42: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/42.jpg)
Tabla 1
A.ZUÑIGA 24 ANIVERSARIO RP10 42
Ricardo Waldman
Los tres canales de arranque, estuvieron divididos en equipos: CF1: J. Avila y A. Zuñiga CF2: M. Bang CF3: R. Waldman Se extrajeron: • Las barras de seguridad y se
midieron solo tres puntos • Luego se extrajo la barra de control
BC2 saliendo el 100% • Luego se extrajo la barra de control
BC1 solo tres puntos: • BC1-Extrapolada (Crítico): 19.4 %
![Page 43: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/43.jpg)
Figura 1
Extracción de fuente de neutrones
C ( 1
/s)
t (s)
Figura 1
A.ZUÑIGA 24 ANIVERSARIO RP10 43
Se extrae la fuentes de neutrones y luego de caer comienza a subir el contaje en los detectores.
![Page 44: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/44.jpg)
Figura 2
Función de reactividad (X%)
2)( 2
2
)( BBxsenxxF -=
A.ZUÑIGA 24 ANIVERSARIO RP10 44
![Page 45: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/45.jpg)
Posición: F(x) = 8.48
19.4%
A.ZUÑIGA 24 ANIVERSARIO RP10 45
![Page 46: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/46.jpg)
Tabla 2
La masa crítica: 4954,60 g (U-235)
A.ZUÑIGA 24 ANIVERSARIO RP10 46
![Page 47: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/47.jpg)
30/11/2012 24 ANIVERSARIO RP10
Contaje (cps): CF1: 11605, CF2: 36426, CF3:23436
Relación flujo – potencia (cálculo) : 7.6 x 10 (6) nv = 1W
Sensibilidad neutrónica CF: 0.26 cps / nv
Flujo neutrónico en CF2: 36426 / 0.26 = 1.4 X 10 (5) nv
Potencia: 1.4 x 10(5) / 7.6 x 10 (6) = 18 mW
47
![Page 48: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/48.jpg)
} La partida de nacimiento del reactor RP1O es el 30 de noviembre de 1988.
} El 2013, se cumple 25 años LAS BODAS DE PLATA: ¿Qué debemos hacer?. ¿Dejarlo pasar?. O, organizarnos para que sea una “fiesta”, científica y tecnológica. Trabajar duro durante 2013, para convertirla en un RELANZAMIENTO DEL REACTOR y en un encuentro latinoamericano en CYT NUCLEAR.
} Saludar a los colegas que estuvieron en ese nacimiento: unos no están, otros murieron, y también a los que todavía continuamos.
A.ZUÑIGA 24 ANIVERSARIO RP10 48
![Page 49: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/49.jpg)
Sala Experimental
Cúpula del RP10
Potencia: 10 MW
Columna térmica
Haz de neutrografia
Tubo neumático
A.ZUÑIGA 24 ANIVERSARIO RP10
23 Aniv
49
![Page 50: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/50.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10
14 continúan. 2 fallecidos
50
![Page 51: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/51.jpg)
} Os pido un minuto de silencio, por los Ingenieros Eleuterio Alvarez y Manuel Nieto.
} Igualmente brindemos un voto de aplausos
por el Ing. Arturo Ramón, quién se jubila el próximo año y no estará con nosotros en el siguiente aniversario.
A.ZUÑIGA 24 ANIVERSARIO RP10 51
![Page 52: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/52.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 52
![Page 53: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/53.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 53
![Page 54: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/54.jpg)
} Emilio Veramendi } Fernando Delgado } Agustin Zúñiga } Pedro Escudero } Arturo Ramón } Visitante
Argentino } Conrado
Seminario } César Pizarro } Constantino León } José Castro } Iván LLamas
A.ZUÑIGA 24 ANIVERSARIO RP10 54
Sala de Control del Reactor Nuclear RP10
![Page 55: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/55.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 55
Ing. Alberto Salazar Ing. Rolando Arrieta
![Page 56: 24 ANIVERSRIO PRIMERA PUESTA A CRITICO REACTOR NUCLEAR RP10 30-11-2012](https://reader033.fdocuments.es/reader033/viewer/2022052904/5583a777d8b42aff058b4764/html5/thumbnails/56.jpg)
A.ZUÑIGA 24 ANIVERSARIO RP10 56
Ing. David Carrillo Jefe de la División de Reactores
Nucleares
Ing. Manuel Castro Presidente del IPEN
Ing. Jacinto Valencia Director Ejecutivo del IPEN
Dr. Agustin Zúñiga. Expositor Jefe del Departamento de Cálculo
Análisis y Seguridad Nuclear