  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    01.00.00 OBRAS PROVISIONALES01.01.00 Cartel de indentificacin de Obra de 3.60 x 8.50 m. und

    01.02.00 Alquiler de Almacn y Oficina mes

    02.00.00 PAVIMENTOS

    02.01.00 TRABAJOS PRELIMINARES02.01.01 Limpieza de Terreno Manual m2

    Jr. Ricardo Palma

    Jr. Abrahan Valdelomar

    Jr. Jos Glvez

    Av. Mariano Melgar

    Jr. Pedro Ruz

    02.01.02 Trazo, Nivel y Replanteo m2Jr. Ricardo Palma

    Jr. Abrahan Valdelomar

    Jr. Jos Glvez

    Av. Mariano Melgar

    Jr. Pedro Ruz

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    02.02.00 MOVIMIENTO DE TIERRAS02.02.01 Corte con Maquinaria en terreno natural hasta H=1.00 m m3

    02.02.02 Perfilado, Nivelacin y compactacin de la subrasante en zonas de corte m2Jr. Ricardo Palma

    Jr. Abrahan Valdelomar

    Jr. Jos Glvez

    Av. Mariano Melgar

    Jr. Pedro Ruz

    02.02.03 Mejoramiento de subrasante con over menor a 4" e=20cm m2Jr. Ricardo Palma

    Jr. Abrahan Valdelomar

    Jr. Jos Glvez

    Av. Mariano Melgar

    Jr. Pedro Ruz

    02.02.04 Base Granular e=20cm m2Jr. Ricardo Palma

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    Jr. Abrahan Valdelomar

    Jr. Jos Glvez

    Av. Mariano Melgar

    Jr. Pedro Ruz

    02.03.00 CONCRETO SIMPLE02.03.01 Losa de Rodadura, Concreto f'c = 210 Kg/cm2, e=0.20 m. m2

    Jr. Ricardo Palma

    Jr. Abrahan Valdelomar

    Jr. Jos Glvez

    Av. Mariano Melgar

    Jr. Pedro Ruz

    02.03.02 Concreto en Uas para Pavimento Rgido, Concreto f'c = 210 Kg/cm2 m3Jr. Ricardo Palma

    cuadra 06

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    cuadra 070.50

    Jr. Abrahan Valdelomar

    0.40

    cuadra 060.25

    Jr. Jos Glvez

    cuadra 06

    Av. Mariano Melgar

    cuadra 14

    cuadra 15

    cuadra 15

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    Jr. Pedro Ruz

    cuadra 03

    02.03.03 Encofrado y Desencofrado de Losa de Rodadura m2Jr. Ricardo Palma

    cuadra 06

    cuadra 07

    Jr. Abrahan Valdelomar

    cuadra 06

    Jr. Jos Glvez

    cuadra 06

    Av. Mariano Melgar

    cuadra 14

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    cuadra 15

    cuadra 16

    Jr. Pedro Ruz

    cuadra 03

    02.03.04 Levantamiento de Buzones Existentes a nivel de rasante und

    BUZONES 7 AOS DE ANTIGEDADAV. MARIANO MELGARJR. PEDRO RUIZJR. ABRAHAN VALDELOMARJR. RICARDO PALMA

    BUZONES 4 AOS DE ANTIGEDADJR. JOSE GALVEZMARIANO MELGAR - PEDRO RUIZJR- RICARDO PALMA

    02.04.00 CURADO02.04.01 Curado de Losa de Rodadura, durante 7 dias - 4 veces x dia m2

    02.05.00 JUNTAS02.05.01 Juntas de contraccin e=6mm m

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    02.05.02 Juntas de contruccin de 3/4" c/ pasajuntas m

    AV. MARIANO MELGARC 14 - 15 - 16

    JR. JOSE GALVEZC-4

    JR. PEDRO RUIZC-5; C-4; C-3

    JR. A. VALDELOMAR

    JR. RICARDO PALMA

    02.05.03 Juntas de contruccin de 3/4" sin pasajuntas en la interseccin de calles m

    INTERS. M- MELGAR - JOSE B. ALCEDO

    INTERS. M. MELGAR - JOSE GALVEZ

    INTERS. M. MELGAR - F. VILLARREAL

    INTERS. M. MELGAR - PEDRO RUIZ

    INTERS. PEDRO RUIZ - A. VALDELOMAR

    INTERS. PEDRO RUIZ - RICARDO PALMA

    INTERS. PEDRO RUIZ - AV. CHACHAPOYAS

    INTERS. R. PALMA - F. VILLARREAL

    INTERS. A. VALDELOMAR - F. VILLARREAL

    02.05.04 Juntas asflticas en pavimentos h=20 cm, e=1" m

    M. MELGAR C-14M. MELGAR C-15M. MELGAR C-16JOSE GALVEZPEDRO RUIZ C -5PEDRO RUIZ C -4

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    PEDRO RUIZ C -3A. VALDELOMAR C-6RICARDO PALMA

    02.06.00 ACERO LISO02.06.01 Dowels transversales con acero liso de 3/4" m

    AV. MARIANO MELGAR

    JR. JOSE GALVEZ

    JR. F. VILLARREAL

    JR. PEDRO RUIZ

    JR. A. VALDELOMAR

    JR. RICARDO PALMA

    02.06.02 Barras de amarre longitudinal con acero corrugado de 3/4" m

    AV. MARIANO MELGAR C-14C-15C-16

    JR. JOSE GALVEZC-4

    JR. F. VILLAREAL

    JR . PEDRO RUIZC-5C-4; C-3

    JR. A VLADELOMARC-6

    JR. RICARDO PALMAC-6C-7

    02.07.00 SEALIZACION02.07.01 SEALIZACION HORIZONTAL

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    02.07.01.01 Pintado de Franjas en Pavimento - Sealizacion m2

    LINEA CONTINUAAV. MARIANO MELGAR C.14AV. MARIANO MELGAR C.15AV. MARIANO MELGAR C.16JR. JOSE GALVEZ C. 4JR.PEDRO RUIZ 5JR.PEDRO RUIZ 4JR.PEDRO RUIZ 3JR.ABRAHAM VALDELOMAR C.6JR.RICARDO PALMA C.6JR.RICARDO PALMA C.7

    LINEAS DE PASO PEATONALAV. MARIANO MELGAR C.14AV. MARIANO MELGAR C.15AV. MARIANO MELGAR C.16JR. JOSE GALVEZ C. 4JR.PEDRO RUIZ 5JR.PEDRO RUIZ 4JR.PEDRO RUIZ 3JR.ABRAHAM VALDELOMAR C.6JR.RICARDO PALMA C.6JR.RICARDO PALMA C.7

    LINEA DE PAREAV. MARIANO MELGAR C.14

    AV. MARIANO MELGAR C.15

    AV. MARIANO MELGAR C.16

    JR. JOSE GALVEZ C. 4

    JR.PEDRO RUIZ 5

    JR.PEDRO RUIZ 4

    JR.PEDRO RUIZ 3

    JR.ABRAHAM VALDELOMAR C.6

    JR.RICARDO PALMA C.6

    JR.RICARDO PALMA C.7

    FLECHAS DIRECCIONALES CON GIROAV. MARIANO MELGAR C.14AV. MARIANO MELGAR C.15

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    AV. MARIANO MELGAR C.16JR. JOSE GALVEZ C. 4JR.PEDRO RUIZ 5JR.PEDRO RUIZ 4JR.PEDRO RUIZ 3JR.ABRAHAM VALDELOMAR C.6JR.RICARDO PALMA C.6JR.RICARDO PALMA C.7

    02.07.02 SEALIZACION VERTICAL02.07.02.01 Sealizacin Preventiva de lado 0.60 x 0.60 und

    AV. MARIANO MELGAR C.14AV. MARIANO MELGAR C.15AV. MARIANO MELGAR C.16JR. JOSE GALVEZ C. 4JR.PEDRO RUIZ 5JR.PEDRO RUIZ 4JR.PEDRO RUIZ 3JR.ABRAHAM VALDELOMAR C.6JR.RICARDO PALMA C.6JR.RICARDO PALMA C.7

    02.08.00 ELIMINACION DE MATERIAL EXCEDENTE02.08.01 Eliminacin de Material Excedente a una Distancia = 5 Km + 25% esponjamiento c/ volquete m3

    03.00.00 VEREDAS

    03.01.00 TRABAJOS PRELIMINARES03.01.01 Limpieza de Terreno Manual m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-A

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    AV. MARIANO MELGAR C.14-A

    AV. MARIANO MELGAR C.14-B

    AV. MARIANO MELGAR C.15-A

    AV. MARIANO MELGAR C.15-B

    AV. MARIANO MELGAR C.16-A

    AV. MARIANO MELGAR C.16-B

    JR. JOSE GALVEZ C. 4-A

    JR. JOSE GALVEZ C. 4-B

    JR.PEDRO RUIZ 5-A

    JR.PEDRO RUIZ 5-B

    JR.PEDRO RUIZ 4-A

    JR.PEDRO RUIZ 4-B

    JR.PEDRO RUIZ 3-A

    JR.PEDRO RUIZ 3-B

    JR.ABRAHAM VALDELOMAR C.6-A

    JR.ABRAHAM VALDELOMAR C.6-B

    JR.RICARDO PALMA C.6-A

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR.RICARDO PALMA C.6-B

    JR.RICARDO PALMA C.7-A

    JR.RICARDO PALMA C.7-B

    03.01.02 Trazo, Nivel y Replanteo m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    AV. MARIANO MELGAR C.14-A

    AV. MARIANO MELGAR C.14-B

    AV. MARIANO MELGAR C.15-A

    AV. MARIANO MELGAR C.15-B

    AV. MARIANO MELGAR C.16-A

    AV. MARIANO MELGAR C.16-B

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR. JOSE GALVEZ C. 4-A

    JR. JOSE GALVEZ C. 4-B

    JR.PEDRO RUIZ 5-A

    JR.PEDRO RUIZ 5-B

    JR.PEDRO RUIZ 4-A

    JR.PEDRO RUIZ 4-B

    JR.PEDRO RUIZ 3-A

    JR.PEDRO RUIZ 3-B

    JR.ABRAHAM VALDELOMAR C.6-A

    JR.ABRAHAM VALDELOMAR C.6-B

    JR.RICARDO PALMA C.6-A

    JR.RICARDO PALMA C.6-B

    JR.RICARDO PALMA C.7-A

    JR.RICARDO PALMA C.7-B

    03.01.03 Demolicin de Vereda existente de concreto simple m2

    CA. MARIANO MELGAR CUADRA 14Lado Izquierdo (A1)Lado Derecho (A2 + A3 + A4)A2A3

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    A4

    CA. MARIANO MELGAR CUADRA 15Lado Izquierdo (A12 +A13)A12A13Lado Derecho (A14 + A15)A14A15

    CA. MARIANO MELGAR CUADRA 16Lado Izquierdo (A16)Lado Derecho (A17)

    CA. JOSE GALVEZ CUADRA 4 Lado Izquierdo (A5 +A6 +A7)A5A6A7

    Lado Derecho (A8 +A9 +A10 +A11)A8A9A10A11

    CA. PEDRO RUIZ CUADRA 3 Lado Izquierdo (A37 + A38)A37A38Lado Derecho (A39)A39

    CA. PEDRO RUIZ CUADRA 4Lado Izquierdo (A28)Lado Derecho (A29 + A430)A29A30

    CA. PEDRO RUIZ CUADRA 5Lado Izquierdo (A19 +A20 + A21 )A19A20A21Lado Derecho (A22 )

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    CA. ABRAHAM VALDEROMAR CUADRA 6Lado Izquierdo (A26 +A27)A26A27Lado Derecho (A25)

    CA. RICARDO PALMA CUADRA 6Lado Izquierdo (A33)Lado Derecho (A31 +A32)A31A32

    CA. RICARDO PALMA CUADRA 7Lado Izquierdo (A36)Lado Derecho (A34 + A35)A34A35

    03.01.04 Demolicin de Vereda existente de concreto simple con una H= 1.00 m m2

    CA. MARIANO MELGAR CUADRA 16Lado Derecho (A18)

    Lado Derecho (A23 + A24 )A23A24

    03.02.00 MOVIMIENTO DE TIERRAS03.02.01 Corte manual de terreno m3

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-B

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    03.02.02 Nivelacion y Apisonado en Veredas m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    03.02.03 Relleno Compactado C/ Material de prestamo (Afirmado) para base de vereda m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-A

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    03.03.00 CONCRETO SIMPLE03.03.01 Concreto f'c=175 Kg/cm2 en veredas, acabado frot., inc. brua. m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    03.03.02 Concreto f'c=175 Kg/cm2 en rampas m2

    AV. MARIANO MELGAR C.14-A

    AV. MARIANO MELGAR C.14-B

    AV. MARIANO MELGAR C.15-A

    AV. MARIANO MELGAR C.15-B

    AV. MARIANO MELGAR C.16-A

    AV. MARIANO MELGAR C.16-B

    JR. JOSE GALVEZ C. 4-A

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR. JOSE GALVEZ C. 4-B

    JR.PEDRO RUIZ 5-A

    JR.PEDRO RUIZ 5-B

    JR.PEDRO RUIZ 4-A

    JR.PEDRO RUIZ 4-B

    JR.PEDRO RUIZ 3-A

    JR.PEDRO RUIZ 3-B

    JR.ABRAHAM VALDELOMAR C.6-A

    JR.ABRAHAM VALDELOMAR C.6-B

    JR.RICARDO PALMA C.6-A

    JR.RICARDO PALMA C.6-B

    JR.RICARDO PALMA C.7-A

    JR.RICARDO PALMA C.7-B

    03.03.03 Encofrado, descencofrado de Vereda. m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-A

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    AV. MARIANO MELGAR C.14-A

    AV. MARIANO MELGAR C.14-B

    AV. MARIANO MELGAR C.15-A

    AV. MARIANO MELGAR C.15-B

    AV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-B

    JR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-B

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR.PEDRO RUIZ 4-A

    JR.PEDRO RUIZ 4-B

    JR.PEDRO RUIZ 3-A

    JR.PEDRO RUIZ 3-B

    JR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-B

    03.04.00 JUNTAS Y BRUADO03.04.01 Junta de dilatacin 1" x 4" de concreto asfltico a 3.0 m m

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    03.04.02 Bruado de veredas m

    AV. MARIANO MELGAR C.14-A

    AV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-A

    JR. JOSE GALVEZ C. 4-B

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR.PEDRO RUIZ 5-A

    JR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-A

    JR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-A

    JR.PEDRO RUIZ 3-B

    JR.ABRAHAM VALDELOMAR C.6-A

    JR.ABRAHAM VALDELOMAR C.6-B

    JR.RICARDO PALMA C.6-A

    JR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-A

    JR.RICARDO PALMA C.7-B

    MARTILLOS EN OCHAVOSINTERS. M- MELGAR - JOSE B. ALCEDO

    INTERS. M. MELGAR - JOSE GALVEZ

    INTERS. M. MELGAR - F. VILLARREAL

    INTERS. M. MELGAR - PEDRO RUIZ

    INTERS. PEDRO RUIZ - A. VALDELOMAR

    INTERS. PEDRO RUIZ - RICARDO PALMA

    INTERS. PEDRO RUIZ - AV. CHACHAPOYAS

    INTERS. R. PALMA - F. VILLARREAL

    INTERS. A. VALDELOMAR - F. VILLARREAL

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    03.04.03 Bruado de rampas m

    AV. MARIANO MELGAR C.14-A

    AV. MARIANO MELGAR C.14-B

    AV. MARIANO MELGAR C.15-A

    AV. MARIANO MELGAR C.15-B

    AV. MARIANO MELGAR C.16-A

    AV. MARIANO MELGAR C.16-B

    JR. JOSE GALVEZ C. 4-A

    JR. JOSE GALVEZ C. 4-B

    JR.PEDRO RUIZ 5-A

    JR.PEDRO RUIZ 5-B

    JR.PEDRO RUIZ 4-A

    JR.PEDRO RUIZ 4-B

    JR.PEDRO RUIZ 3-A

    JR.PEDRO RUIZ 3-B

    JR.ABRAHAM VALDELOMAR C.6-A

    JR.ABRAHAM VALDELOMAR C.6-B

    JR.RICARDO PALMA C.6-A

    JR.RICARDO PALMA C.6-B

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR.RICARDO PALMA C.7-A

    JR.RICARDO PALMA C.7-B

    03.05.00 CURADO03.05.01 Curado de vereda con arena fina , durante 7 dias - 4 veces x da m2

    03.06.00 SUMINISTRO Y COLOCACION DE CAJAS PARA AGUA Y DESAGUE03.06.01 Suministro y colocacin de encimado de cajas para agua und

    LOTES EN TOTAL

    03.06.02 Suministro y colocacin de encimado de cajas para desague undLOTES EN TOTAL

    03.07.00 ELIMINACION DE MATERIAL EXCEDENTE03.07.01 Eliminacin de Material Excedente a una Distancia = 5 Km + 25% esponjamiento c/ volquete m3

    04.00.00 SARDINEL

    04.01.00 TRABAJOS PRELIMINARES04.01.01 Limpieza de Terreno Manual m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-A

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    04.01.02 Trazo, Nivel y Replanteo m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    04.02.00 MOVIMIENTO DE TIERRAS04.02.01 Excavacion de sardineles hasta h=60 cm m3

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-A

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    04.03.00 CONCRETO SIMPLE 04.03.01 Concreto f'c = 175 Kg/cm2 vaceado con mezcladora m3

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    04.03.02 Encofrado y Desencofrado m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    04.03.03 Acero Corrugado 3/8", fy=4200 kg/cm2 kg

    04.03.04 Relleno de Juntas de Dilatacin con concreto asfaltico 1"x2" m en sardinel m

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    04.03.05 Tarrajeo pulido en sardineles m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    04.03.06 Curado de sardinel con arena fina, durante 7 dias - 4 veces x da m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    04.04.00 ELIMINACION DE MATERIAL EXCEDENTE04.04.01 Eliminacin de Material Excedente a una Distancia = 5 Km + 25% esponjamiento c/ volquete m3

    05.00.00 CUNETAS RECTANGULARES

    05.01.00 TRABAJOS PRELIMINARES05.01.00 Limpieza de Terreno Manual m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BUNION DE AV. M.M. C 14-A Y BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BUNION DE AV. M.M. C 15 -A Y BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BUNION DE AV. M.M. C 16 -A Y BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BUNION DE AV.J.G. C 4 -A Y BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BUNION DE JR.PEDRO RUIZ 4-A Y 5-AUNION DE JR.PEDRO RUIZ 4-B Y 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-B

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BUNION DE JR.PEDRO RUIZ 4-A Y 3-AUNION DE JR.PEDRO RUIZ 4-B Y 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BUNION JR.ABRAHAM VALDELOMAR C.6-A Y BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-BUNION JR.RICARDO PAL,A C.7-A Y B

    05.02.00 Trazo, Nivel y Replanteo m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BUNION DE AV. M.M. C 14-A Y BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BUNION DE AV. M.M. C 15 -A Y BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BUNION DE AV. M.M. C 16 -A Y BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BUNION DE AV.J.G. C 4 -A Y BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BUNION DE JR.PEDRO RUIZ 4-A Y 5-AUNION DE JR.PEDRO RUIZ 4-B Y 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BUNION DE JR.PEDRO RUIZ 4-A Y 3-AUNION DE JR.PEDRO RUIZ 4-B Y 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BUNION JR.ABRAHAM VALDELOMAR C.6-A Y BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-BUNION JR.RICARDO PAL,A C.7-A Y B

    05.02.00 MOVIMIENTO DE TIERRAS05.02.01 Excavacion de cunetas rectangulares hasta h=60 cm m3

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-B

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    UNION DE AV. M.M. C 14-A Y BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BUNION DE AV. M.M. C 15 -A Y BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BUNION DE AV. M.M. C 16 -A Y BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BUNION DE AV.J.G. C 4 -A Y BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BUNION DE JR.PEDRO RUIZ 4-A Y 5-AUNION DE JR.PEDRO RUIZ 4-B Y 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BUNION DE JR.PEDRO RUIZ 4-A Y 3-AUNION DE JR.PEDRO RUIZ 4-B Y 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BUNION JR.ABRAHAM VALDELOMAR C.6-A Y BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-BUNION JR.RICARDO PAL,A C.7-A Y B

    05.03.00 CONCRETO SIMPLE05.03.01 Concreto f'c = 175 Kg/cm2 vaceado con mezcladora m3

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BUNION DE AV. M.M. C 14-A Y BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BUNION DE AV. M.M. C 15 -A Y BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BUNION DE AV. M.M. C 16 -A Y BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BUNION DE AV.J.G. C 4 -A Y BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BUNION DE JR.PEDRO RUIZ 4-A Y 5-AUNION DE JR.PEDRO RUIZ 4-B Y 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-B

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    UNION DE JR.PEDRO RUIZ 4-A Y 3-AUNION DE JR.PEDRO RUIZ 4-B Y 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BUNION JR.ABRAHAM VALDELOMAR C.6-A Y BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-BUNION JR.RICARDO PAL,A C.7-A Y B

    05.03.02 Acero Corrugado 3/8", fy=4200 kg/cm2 kg

    05.03.03 Encofrado y Desencofrado M2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BUNION DE AV. M.M. C 14-A Y BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BUNION DE AV. M.M. C 15 -A Y BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BUNION DE AV. M.M. C 16 -A Y BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BUNION DE AV.J.G. C 4 -A Y BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BUNION DE JR.PEDRO RUIZ 4-A Y 5-AUNION DE JR.PEDRO RUIZ 4-B Y 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BUNION DE JR.PEDRO RUIZ 4-A Y 3-AUNION DE JR.PEDRO RUIZ 4-B Y 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BUNION JR.ABRAHAM VALDELOMAR C.6-A Y BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-BUNION JR.RICARDO PAL,A C.7-A Y B

    05.03.04 Tarrajeo pulido en Canaletas m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-B

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    UNION DE AV. M.M. C 14-A Y BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BUNION DE AV. M.M. C 15 -A Y BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BUNION DE AV. M.M. C 16 -A Y BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BUNION DE AV.J.G. C 4 -A Y BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BUNION DE JR.PEDRO RUIZ 4-A Y 5-AUNION DE JR.PEDRO RUIZ 4-B Y 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BUNION DE JR.PEDRO RUIZ 4-A Y 3-AUNION DE JR.PEDRO RUIZ 4-B Y 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BUNION JR.ABRAHAM VALDELOMAR C.6-A Y BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-BUNION JR.RICARDO PAL,A C.7-A Y B

    05.03.05 Curado de sardinel y canaletas, durante 7 dias - 4 veces x da m2

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BUNION DE AV. M.M. C 14-A Y BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BUNION DE AV. M.M. C 15 -A Y BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BUNION DE AV. M.M. C 16 -A Y BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BUNION DE AV.J.G. C 4 -A Y BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BUNION DE JR.PEDRO RUIZ 4-A Y 5-AUNION DE JR.PEDRO RUIZ 4-B Y 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BUNION DE JR.PEDRO RUIZ 4-A Y 3-A

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    UNION DE JR.PEDRO RUIZ 4-B Y 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BUNION JR.ABRAHAM VALDELOMAR C.6-A Y BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-BUNION JR.RICARDO PAL,A C.7-A Y B

    05.03.06 Tapas de concreto para Cunetas Rectangulares m3

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BUNION DE AV. M.M. C 14-A Y BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BUNION DE AV. M.M. C 15 -A Y BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BUNION DE AV. M.M. C 16 -A Y BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BUNION DE AV.J.G. C 4 -A Y BJR.PEDRO RUIZ 5-AJR.PEDRO RUIZ 5-BUNION DE JR.PEDRO RUIZ 4-A Y 5-AUNION DE JR.PEDRO RUIZ 4-B Y 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BUNION DE JR.PEDRO RUIZ 4-A Y 3-AUNION DE JR.PEDRO RUIZ 4-B Y 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BUNION JR.ABRAHAM VALDELOMAR C.6-A Y BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-BUNION JR.RICARDO PAL,A C.7-A Y B

    05.04.00 ELIMINACION DE MATERIAL EXCEDENTE05.04.01 Eliminacin de Material Excedente a una Distancia = 5 Km + 25% esponjamiento c/ volquete m3

    06.00.00 MURO DE CONTENCION06.01.00 TRABAJOS PRELIMINARES

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    06.01.01 Limpieza de Terreno Manual m2

    AV. MARIANO MELGAR C.16-A

    JR. JOSE GALVEZ C. 4-A

    06.01.02 Trazo, Nivel y Replanteo m2

    AV. MARIANO MELGAR C.16-A

    JR. JOSE GALVEZ C. 4-A

    06.02.00 MOVIMIENTO DE TIERRAS06.02.01 Corte de Terreno Manual para Muro de Contencin m3

    MARIANO MELGAR CDA 16LADO IZQUIERDO MURO H=1.00MJR.JOSE GALVEZLADO IZQUIERDO

    06.02.02 Relleno con material de prstamo en Muro de Contencin m3

    MARIANO MELGAR CDA 16LADO IZQUIERDO MURO H=1.00MJR.JOSE GALVEZLADO IZQUIERDO

    06.03.00 CONCRETO SIMPLE06.03.01 Solado 1:10; C:A e = 4" m2

    MARIANO MELGAR CDA 16LADO IZQUIERDO MURO H=1.00MJR.JOSE GALVEZLADO IZQUIERDO

    06.04.00 CONCRETO ARMADO06.04.01 Encofrado y Desencofrado de Muro de contencin m2

    MARIANO MELGAR CDA 16LADO IZQUIERDO MURO H=1.00MJR.JOSE GALVEZLADO IZQUIERDO

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    06.04.02 ACERO CORRUGADO, fy = 4200 Kg/cm2 -Muro de Contencion kg

    06.04.03 Concreto f'c = 210 Kg/cm2 en muro de contencin m3

    MARIANO MELGAR CDA 16LADO IZQUIERDO MURO H=1.00MMURO H=1.00MJR.JOSE GALVEZLADO IZQUIERDO

    06.05.00 JUNTAS06.05.01 Juntas de Dilatacin en Muro y Losa Inferior con water stop 6" cada 9.00 m. m

    06.06.00 ELIMINACION DE MATERIAL EXCEDENTE06.06.01 Eliminacin de Material Excedente a una Distancia = 5 Km + 25% esponjamiento c/ volquete m3

    07.00.00 AREAS VERDES07.01.00 Corte superficial para jardineras hasta 0.20 m m2

    07.02.00 Acarreo de material excedente dp

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR. JOSE GALVEZC-4 - AC-4 - AC-4 - BC-4 - B

    JR. PEDRO RUIZC-5 - AC-5 - AC-5 - BC-5 - B

    C-4 - AC-4 - AC-4 - BC-4 - B

    C-3 - AC-3 - AC-3 - BC-3 - B

    JR. A. VALDELOMARC-6 - AC-6 - AC-6 - BC-6 - B

    JR. RICARDO PALMAC-6 - AC-6 - AC-6 - BC-6 - B

    C-7 - AC-7 - AC-7 - BC-7 - B

    07.05.00 Arborizacion con plantones und

    AV. MARIANO MELGAR C.14-AAV. MARIANO MELGAR C.14-BAV. MARIANO MELGAR C.15-AAV. MARIANO MELGAR C.15-BAV. MARIANO MELGAR C.16-AAV. MARIANO MELGAR C.16-BJR. JOSE GALVEZ C. 4-AJR. JOSE GALVEZ C. 4-BJR.PEDRO RUIZ 5-A

  • PLANILLA DE METRADOS

    OBRA CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    PROP. : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBAUBIC. : BAGUA GRANDEFECHA : JUNIO 2015

    PART. DESCRIPCIN UND

    JR.PEDRO RUIZ 5-BJR.PEDRO RUIZ 4-AJR.PEDRO RUIZ 4-BJR.PEDRO RUIZ 3-AJR.PEDRO RUIZ 3-BJR.ABRAHAM VALDELOMAR C.6-AJR.ABRAHAM VALDELOMAR C.6-BJR.RICARDO PALMA C.6-AJR.RICARDO PALMA C.6-BJR.RICARDO PALMA C.7-AJR.RICARDO PALMA C.7-B

    07.06.00 Eliminacin de Material Excedente a una Distancia = 5 Km + 25% esponjamiento c/ volquete m3Acarreo de material excedente

    08.00.00 VARIOS

    08.01.00 Limpieza final de obra m2

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1.00 1.00 1.00 1.00

    1.00 1.00 1.00 4.00

    1.00 1.00 6007.371.00 Area = 494.92 494.921.00 Area = 459.13 459.13

    1.00 Area = 482.96 482.961.00

    1.00 Area = 492.09 492.091.00

    1.00 Area = 727.07 727.071.00 Area = 754.20 754.20

    Area = 784.23 784.23

    1.00 Area = 488.53 488.531.00 Area = 650.80 650.80

    Area = 673.44 673.44

    1.00 1.00 6007.371.00 Area = 494.92 494.921.00 Area = 459.13 459.13

    1.00 Area = 482.96 482.961.00

    1.00 Area = 492.09 492.091.00

    1.00 Area = 727.07 727.071.00 Area = 754.20 754.20

    Area = 784.23 784.23

    1.00 Area = 488.53 488.531.00 Area = 650.80 650.80

    Area = 673.44 673.44

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1.00 1.00 7282.14

    1.00 1.00 7282.14 7282.14

    1.00 1.00 6007.371.00 Area = 494.92 494.921.00 Area = 459.13 459.13

    1.00 Area = 482.96 482.961.00

    1.00 Area = 492.09 492.091.00

    1.00 Area = 727.07 727.071.00 Area = 754.20 754.20

    Area = 784.23 784.23

    1.00 Area = 488.53 488.531.00 Area = 650.80 650.80

    Area = 673.44 673.44

    1.00 6007.371.00 Area = 494.92 494.921.00 Area = 459.13 459.13

    1.00 Area = 482.96 482.961.00

    1.00 Area = 492.09 492.091.00

    1.00 Area = 727.07 727.071.00 Area = 754.20 754.20

    Area = 784.23 784.23

    1.00 Area = 488.53 488.531.00 Area = 650.80 650.80

    Area = 673.44 673.44

    1.00 6007.371.00 Area = 494.92 494.921.00 Area = 459.13 459.13

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1.00 Area = 482.96 482.961.00

    1.00 Area = 492.09 492.091.00

    1.00 Area = 727.07 727.071.00 Area = 754.20 754.20

    Area = 784.23 784.23

    1.00 Area = 488.53 488.531.00 Area = 650.80 650.80

    Area = 673.44 673.44

    1.00 6007.371.00 Area = 494.92 494.921.00 Area = 459.13 459.13

    1.00 Area = 482.96 482.961.00

    1.00 Area = 492.09 492.091.00

    1.00 Area = 727.07 727.071.00 Area = 754.20 754.20

    Area = 784.23 784.23

    1.00 Area = 488.53 488.531.00 Area = 650.80 650.80

    Area = 673.44 673.44

    1.00 263.260.38 0.40 0.15 1755.06 263.26

    1.00 7.681.00 76.321.00 8.101.00 7.681.00 76.601.00 8.10

    1.00 8.091.00 77.59

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1.00 8.0377.91

    1.00 7.851.00 74.301.00 7.851.00 8.021.00 7.741.00 74.791.00 8.141.00 7.691.00 1.271.00 0.86

    1.00 7.861.00 75.721.00 7.851.00 8.311.00 75.391.00 7.84

    1.00 7.851.00 72.671.00 7.751.00 72.731.00 7.86

    1.00 7.641.00 75.891.00 7.871.00 75.721.00 7.93

    1.00 7.801.00 71.291.00 7.781.00 7.781.00 7.881.00 71.571.00 7.921.00 7.741.00 1.581.00 2.36

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1.00 7.831.00 75.561.00 7.851.00 75.141.00 76.501.00 76.751.00 79.401.00 80.84

    1.00 3504.61

    1.00 76.32 76.321.00 76.60 76.60

    1.00 77.59 77.591.00 77.91 77.91

    1.00 177.93 177.9330.00 2.00 6.00 360.00

    1.00 74.30 74.301.00 74.79 74.79

    30.00 1.00 6.00 180.00

    1.00 75.72 75.721.00 75.39 75.39

    30.00 1.00 6.00 180.00

    1.00 72.67 72.671.00 72.73 72.73

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1.00 75.89 75.891.00 75.72 75.72

    1.00 71.29 71.291.00 71.57 71.57

    30.00 3.00 6.00 540.00

    1.00 75.56 75.56

    1.00 75.14 75.141.00 76.50 76.501.00 76.75 76.751.00 79.40 79.401.00 80.84 80.84

    30.00 3.00 6.00 540.00

    14.00

    3.00 3.004.00 4.002.00 2.001.00 1.00

    2.00 2.001.00 1.001.00 1.00

    1.00 6007.371.00 6007.37 6007.37

    1.00 1.00 2292.49

    1.00 1372.80 1372.80

    1.00 919.69 919.69

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1.00 1.00 254.40

    12.00 7.20 86.40

    4.00 6.00 24.00

    14.00 6.00 84.00

    3.00 6.00 18.00

    7.00 6.00 42.00

    1.00 1.00 418.62

    2.00 13.27 26.54

    4.00 12.33 49.322.00 6.00 12.00

    4.00 12.08 48.322.00 6.00 12.00

    4.00 13.23 52.922.00 7.20 14.40

    4.00 12.82 51.282.00 6.00 12.00

    4.00 13.00 52.002.00 6.00 12.00

    2.00 12.39 24.78

    2.00 11.69 23.38

    2.00 13.84 27.68

    1.00 1.00 1902.45

    Repeciticiones N de veces1.00 217.77 217.771.00 200.42 200.421.00 209.11 209.111.00 182.16 182.161.00 192.80 192.801.00 170.16 170.16

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1.00 200.27 200.271.00 188.57 188.571.00 182.13 182.131.00 159.06 159.06

    1.00 1.00 1372.80Repeciticiones N de veces

    11.00 5.00 7.20 396.008.00 7.20 57.601.00 7.20 7.20

    21.00 6.00 126.00

    2.00 6.00 12.00

    13.00 5.00 6.00 390.003.00 6.00 18.00

    4.00 5.00 6.00 120.001.00 6.00 6.008.00 5.00 6.00 240.00

    1.00 1.00 919.69

    Repeciticiones N de veces

    1.00 85.77 85.771.00 91.73 91.731.00 85.08 85.081.00 7.05 7.05

    1.00 85.79 85.791.00 5.60 5.60

    1.00 6.13 6.131.00 5.50 5.50

    0.001.00 104.11 104.111.00 182.90 182.90

    1.00 84.60 84.601.00 5.96 5.96

    1.00 86.60 86.601.00 82.87 82.87

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    441.20

    9.00 3.00 0.10 2.70 29.710.00 3.00 0.10 3.00

    9.00 3.00 0.10 2.7010.00 3.00 0.10 3.0011.00 3.00 0.10 3.3010.00 3.00 0.10 3.0010.00 3.00 0.10 3.0010.00 3.00 0.10 3.0010.00 3.00 0.10 3.0010.00 3.00 0.10 3.00

    18.00 4.00 0.50 36.00 33218.00 4.00 0.50 36.0018.00 4.00 0.50 36.0016.00 4.00 0.50 32.0016.00 4.00 0.50 32.0016.00 4.00 0.50 32.0016.00 4.00 0.50 32.0016.00 4.00 0.50 32.0016.00 4.00 0.50 32.0016.00 4.00 0.50 32.00

    2.00 0.50 3.75 3.75 43.94.00 0.10 4.20 1.682.00 0.50 3.75 3.752.00 0.10 3.50 0.702.00 0.50 3.75 3.752.00 0.10 5.10 1.022.00 0.50 3.00 3.002.00 0.10 6.70 1.342.00 0.50 3.15 3.152.00 0.10 4.95 0.992.00 0.50 3.15 3.152.00 0.10 5.00 1.002.00 0.50 3.15 3.152.00 0.10 3.90 0.782.00 0.50 3.15 3.152.00 0.10 5.60 1.122.00 0.50 3.15 3.152.00 0.10 5.60 1.122.00 0.50 3.15 3.152.00 0.10 5.00 1.00

    2.00 1.78 3.56 35.602.00 1.78 3.56

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    2.00 1.78 3.562.00 1.78 3.562.00 1.78 3.562.00 1.78 3.562.00 1.78 3.562.00 1.78 3.562.00 1.78 3.562.00 1.78 3.56

    16.00

    3.00 3.002.00 2.001.00 1.001.00 1.001.00 1.001.00 1.002.00 2.002.00 2.002.00 2.001.00 1.00

    1.00 1.00 9102.68

    factor de esponjamiento 1.25 7282.14 9102.68

    1.00 1.00 2741.672741.67

    133.99131.10140.83119.30120.14124.02109.34132.63118.70170.15152.76149.56138.50151.49117.03122.51110.56

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    117.6093.7497.87

    1.00 2.36 1.20 2.83 2.831.00 1.90 1.20 2.28 2.281.00 2.02 1.20 2.42 2.421.00 2.55 1.20 3.06 3.061.00 2.26 1.20 2.71 2.711.00 2.13 1.20 2.56 2.561.00 2.24 1.20 2.69 2.691.00 2.21 1.20 2.65 2.651.00 2.76 1.20 3.31 3.311.00 2.09 1.20 2.51 2.511.00 1.80 1.20 2.16 2.161.00 1.54 1.20 1.85 1.851.00 1.70 1.20 2.04 2.041.00 1.47 1.20 1.76 1.761.00 2.48 1.20 2.98 2.981.00 2.20 1.20 2.64 2.641.00 1.10 1.20 1.32 1.321.00 1.80 1.20 2.16 2.161.00 1.50 1.20 1.80 1.801.00 2.00 1.20 2.40 2.401.00 1.85 1.20 2.22 2.221.00 1.81 1.20 2.17 2.171.00 1.73 1.20 2.08 2.081.00 2.93 1.20 3.52 3.521.00 2.56 1.20 3.07 3.071.00 2.66 1.20 3.19 3.191.00 4.13 1.20 4.96 4.961.00 3.53 1.20 4.24 4.241.00 2.84 1.20 3.41 3.411.00 2.68 1.20 3.22 3.221.00 2.58 1.20 3.10 3.101.00 2.46 1.20 2.95 2.951.00 2.64 1.20 3.17 3.171.00 2.83 1.20 3.40 3.401.00 3.02 1.20 3.62 3.621.00 2.55 1.20 3.06 3.061.00 2.64 1.20 3.17 3.171.00 2.84 1.20 3.41 3.411.00 2.92 1.20 3.50 3.501.00 2.31 1.20 2.77 2.771.00 AREA 20.76 20.76 20.761.00 2.61 1.20 3.13 3.131.00 2.52 1.20 3.02 3.021.00 2.42 1.20 2.90 2.901.00 2.61 1.20 3.13 3.131.00 2.51 1.20 3.01 3.011.00 2.41 1.20 2.89 2.891.00 2.38 1.20 2.86 2.86

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1.00 2.59 1.20 3.11 3.111.00 2.76 1.20 3.31 3.311.00 2.80 1.20 3.36 3.361.00 2.79 1.20 3.35 3.351.00 2.77 1.20 3.32 3.321.00 2.63 1.20 3.16 3.161.00 2.68 1.20 3.22 3.221.00 2.71 1.20 3.25 3.251.00 2.66 1.20 3.19 3.191.00 2.45 1.20 2.94 2.941.00 2.99 1.20 3.59 3.59

    1.00 1.00 2741.672551.82

    133.99131.10140.83119.30120.14124.02109.34132.63118.70170.15152.76149.56138.50151.49117.03122.51110.56117.6093.7497.87

    189.851.00 2.36 1.20 2.831.00 1.90 1.20 2.281.00 2.02 1.20 2.421.00 2.55 1.20 3.061.00 2.26 1.20 2.711.00 2.13 1.20 2.561.00 2.24 1.20 2.691.00 2.21 1.20 2.651.00 2.76 1.20 3.311.00 2.09 1.20 2.511.00 1.80 1.20 2.161.00 1.54 1.20 1.851.00 1.70 1.20 2.041.00 1.47 1.20 1.761.00 2.48 1.20 2.981.00 2.20 1.20 2.64

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1.00 1.10 1.20 1.321.00 1.80 1.20 2.161.00 1.50 1.20 1.801.00 2.00 1.20 2.401.00 1.85 1.20 2.221.00 1.81 1.20 2.171.00 1.73 1.20 2.081.00 2.93 1.20 3.521.00 2.56 1.20 3.071.00 2.66 1.20 3.191.00 4.13 1.20 4.961.00 3.53 1.20 4.241.00 2.84 1.20 3.411.00 2.68 1.20 3.221.00 2.58 1.20 3.101.00 2.46 1.20 2.951.00 2.64 1.20 3.171.00 2.83 1.20 3.401.00 3.02 1.20 3.621.00 2.55 1.20 3.061.00 2.64 1.20 3.171.00 2.84 1.20 3.411.00 2.92 1.20 3.501.00 2.31 1.20 2.771.00 AREA 20.76 20.761.00 2.61 1.20 3.131.00 2.52 1.20 3.021.00 2.42 1.20 2.901.00 2.61 1.20 3.131.00 2.51 1.20 3.011.00 2.41 1.20 2.891.00 2.38 1.20 2.861.00 2.59 1.20 3.111.00 2.76 1.20 3.311.00 2.80 1.20 3.361.00 2.79 1.20 3.351.00 2.77 1.20 3.321.00 2.63 1.20 3.161.00 2.68 1.20 3.221.00 2.71 1.20 3.251.00 2.66 1.20 3.191.00 2.45 1.20 2.941.00 2.99 1.20 3.59

    1.00 1.00 945.16

    945.16

    10.13 10.13

    4.1318.23 34.99

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO12.63

    46.71 67.6820.97

    27.99 38.8710.88

    11.92 35.3223.40

    7.2510.21 28.3410.88

    33.196.00 50.305.076.04

    50.12 89.1939.07

    54.17 54.17

    67.79 67.79

    44.70 53.658.95

    7.97 30.715.2617.483.90 3.90

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    47.45 51.454.0075.84 75.84

    85.82 85.82

    66.75 71.714.96

    33.99 33.99

    36.60 61.3124.71

    1.00 1.00 62.90

    62.9010.02 10.02

    26.44 52.8813.5012.94

    1.00 1.00 1100.780.40 2751.95 1100.78

    133.99131.10140.83119.30120.14124.02109.34132.63118.70180.43152.76149.56138.50151.49117.03122.51

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    110.56117.6093.7497.87

    rampas 189.85

    2751.952751.95 2751.95

    133.99131.10140.83119.30120.14124.02109.34132.63118.70180.43152.76149.56138.50151.49117.03122.51110.56117.6093.7497.87

    rampas 189.85

    2751.952751.95

    133.99131.1

    140.83119.3

    120.14124.02109.34132.63118.7

    180.43152.76149.56138.5

    151.49117.03122.51110.56

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    117.693.7497.87

    rampas 189.85

    2562.10

    133.99 2562.10131.1

    140.83119.3

    120.14124.02109.34132.63118.7

    180.43152.76149.56138.5

    151.49117.03122.51110.56117.693.7497.87

    189.85

    189.851.00 2.36 1.20 2.831.00 1.90 1.20 2.281.00 2.02 1.20 2.421.00 2.55 1.20 3.061.00 2.26 1.20 2.711.00 2.13 1.20 2.561.00 2.24 1.20 2.691.00 2.21 1.20 2.651.00 2.76 1.20 3.311.00 2.09 1.20 2.511.00 1.80 1.20 2.161.00 1.54 1.20 1.851.00 1.70 1.20 2.041.00 1.47 1.20 1.761.00 2.48 1.20 2.981.00 2.20 1.20 2.641.00 1.10 1.20 1.321.00 1.80 1.20 2.16

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1.00 1.50 1.20 1.801.00 2.00 1.20 2.401.00 1.85 1.20 2.221.00 1.81 1.20 2.171.00 1.73 1.20 2.081.00 2.93 1.20 3.521.00 2.56 1.20 3.071.00 2.66 1.20 3.191.00 4.13 1.20 4.961.00 3.53 1.20 4.241.00 2.84 1.20 3.411.00 2.68 1.20 3.221.00 2.58 1.20 3.101.00 2.46 1.20 2.951.00 2.64 1.20 3.171.00 2.83 1.20 3.401.00 3.02 1.20 3.621.00 2.55 1.20 3.061.00 2.64 1.20 3.171.00 2.84 1.20 3.411.00 2.92 1.20 3.501.00 2.31 1.20 2.771.00 AREA 20.76 20.761.00 2.61 1.20 3.131.00 2.52 1.20 3.021.00 2.42 1.20 2.901.00 2.61 1.20 3.131.00 2.51 1.20 3.011.00 2.41 1.20 2.891.00 2.38 1.20 2.861.00 2.59 1.20 3.111.00 2.76 1.20 3.311.00 2.80 1.20 3.361.00 2.79 1.20 3.351.00 2.77 1.20 3.321.00 2.63 1.20 3.161.00 2.68 1.20 3.221.00 2.71 1.20 3.251.00 2.66 1.20 3.191.00 2.45 1.20 2.941.00 2.99 1.20 3.59

    1970.10

    lado n0172.27 0.30 21.68171.72 0.30 21.51675.23 0.30 22.56974.05 0.30 22.21573.7 0.30 22.1171.48 0.30 21.44475.24 0.30 22.572

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO75.28 0.30 22.58478.55 0.30 23.56578.23 0.30 23.46974.54 0.30 22.36275.39 0.30 22.61774.82 0.30 22.44675.36 0.30 22.60872.94 0.30 21.88273.59 0.30 22.07776.07 0.30 22.82176.12 0.30 22.83677.02 0.30 23.10676.66 0.30 22.998

    1498.26 0.30 449.478

    71.41 0.30 21.42373.01 0.30 21.90374.43 0.30 22.32974.84 0.30 22.45275.78 0.30 22.73472.68 0.30 21.80474.31 0.30 22.29373.23 0.30 21.96979.09 0.30 23.72779.73 0.30 23.91974.24 0.30 22.27275.71 0.30 22.71376.24 0.30 22.87274.02 0.30 22.20672.87 0.30 21.86172.79 0.30 21.83774.99 0.30 22.49776.42 0.30 22.92676.35 0.30 22.90579.32 0.30 23.796

    1501.46 0.30 450.438

    perimetro 19.34 0.30 5.80219.19 0.30 5.75719.24 0.30 5.77218.39 0.30 5.51717.86 0.30 5.35822.23 0.30 6.66918.45 0.30 5.53519.94 0.30 5.98220.38 0.30 6.11419.35 0.30 5.80516.13 0.30 4.83920.04 0.30 6.01229.67 0.30 8.90121.74 0.30 6.522

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO20.31 0.30 6.09321.85 0.30 6.55520.04 0.30 6.01220.04 0.30 6.01219.38 0.30 5.81419.57 0.30 5.87120.79 0.30 6.23723.81 0.30 7.14317.74 0.30 5.32221.05 0.30 6.31521.14 0.30 6.34220.45 0.30 6.13516.9 0.30 5.0722.54 0.30 6.762

    625.20

    25.00 1.20 30.0025.00 1.20 30.0026.00 1.20 31.2026.00 1.20 31.2027.00 1.20 32.4025.00 1.20 30.0026.00 1.20 31.2025.00 1.20 30.0027.00 1.20 32.4027.00 1.20 32.4026.00 1.20 31.2026.00 1.20 31.2027.00 1.20 32.4026.00 1.20 31.2026.00 1.20 31.2026.00 1.20 31.2026.00 1.20 31.2026.00 1.20 31.2027.00 1.20 32.4026.00 1.20 31.20

    5503.00

    23.00 9.60 220.801.00 7.42 7.4224.00 9.60 230.4025.00 9.60 240.0025.00 9.60 240.0023.00 9.60 220.8023.00 9.60 220.8024.00 9.60 230.402.00 3.95 7.9021.00 9.50 199.50

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    2.00 9.70 19.401.00 14.00 14.001.00 8.40 8.4025.00 9.60 240.001.00 10.72 10.721.00 5.90 5.9026.00 9.60 249.6024.00 9.60 230.401.00 7.00 7.0025.00 9.60 240.0024.00 9.60 230.401.00 4.76 4.7624.00 9.60 230.401.00 6.72 6.7223.00 9.60 220.801.00 12.16 12.1619.00 9.60 182.401.00 12.35 12.352.00 11.10 22.202.00 12.05 24.1025.00 9.60 240.001.00 4.32 4.3225.00 9.60 240.0025.00 9.60 240.00

    25.00 9.60 240.001.00 4.32 4.32

    2.00 26.94 53.88

    4.00 29.70 118.80

    4.00 30.95 123.80

    1.00 20.00 20.001.00 27.35 27.352.00 6.80 13.60

    4.00 28.56 114.24

    4.00 28.90 115.60

    2.00 26.50 53.00

    2.00 23.63 47.26

    2.00 28.55 57.10

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    890.40

    11.00 1.20 13.209.00 1.20 10.809.00 1.20 10.8012.00 1.20 14.4011.00 1.20 13.2010.00 1.20 12.0010.00 1.20 12.0011.00 1.20 13.2013.00 1.20 15.6010.00 1.20 12.009.00 1.20 10.807.00 1.20 8.408.00 1.20 9.607.00 1.20 8.4012.00 1.20 14.4011.00 1.20 13.205.00 1.20 6.008.00 1.20 9.607.00 1.20 8.409.00 1.20 10.808.00 1.20 9.609.00 1.20 10.808.00 1.20 9.6014.00 1.20 16.8012.00 1.20 14.4012.00 1.20 14.4020.00 1.20 24.0018.00 1.20 21.6013.00 1.20 15.6013.00 1.20 15.6013.00 1.20 15.6011.00 1.20 13.2012.00 1.20 14.4014.00 1.20 16.8012.00 1.20 14.4012.00 1.20 14.4013.00 1.20 15.6013.00 1.20 15.6014.00 1.20 16.8011.00 1.20 13.2012.00 7.20 86.4012.00 1.20 14.4013.00 1.20 15.6011.00 1.20 13.2012.00 1.20 14.4012.00 1.20 14.4011.00 1.20 13.2011.00 1.20 13.2013.00 1.20 15.6013.00 1.20 15.6014.00 1.20 16.80

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    14.00 1.20 16.8014.00 1.20 16.8012.00 1.20 14.4012.00 1.20 14.4013.00 1.20 15.6014.00 1.20 16.8014.00 1.20 16.8014.00 1.20 16.80

    2751.95

    area 2562.10 2562.10area 189.85 189.85

    149.00149.00 149.00

    149.00149.00 149.00

    1031.98

    1.25 2751.95 0.30 1031.98

    389.50

    75.39 0.25 18.8576.73 0.25 19.1879.63 0.25 19.9177.08 0.25 19.2744.51 0.25 11.1374.19 0.25 18.5576.92 0.25 19.2376.25 0.25 19.0685.6 0.25 21.4087.93 0.25 21.9880.29 0.25 20.0782.53 0.25 20.6381.29 0.25 20.32

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO72.47 0.25 18.1278.76 0.25 19.6978.63 0.25 19.6681.12 0.25 20.2883.08 0.25 20.7782.71 0.25 20.6882.87 0.25 20.72

    389.50

    75.39 0.25 18.8576.73 0.25 19.1879.63 0.25 19.9177.08 0.25 19.2744.51 0.25 11.1374.19 0.25 18.5576.92 0.25 19.2376.25 0.25 19.0685.6 0.25 21.4087.93 0.25 21.9880.29 0.25 20.0782.53 0.25 20.6381.29 0.25 20.3272.47 0.25 18.1278.76 0.25 19.6978.63 0.25 19.6681.12 0.25 20.2883.08 0.25 20.7782.71 0.25 20.6882.87 0.25 20.72

    233.70

    75.39 0.25 0.60 11.3176.73 0.25 0.60 11.5179.63 0.25 0.60 11.9477.08 0.25 0.60 11.5644.51 0.25 0.60 6.6874.19 0.25 0.60 11.1376.92 0.25 0.60 11.5476.25 0.25 0.60 11.4485.6 0.25 0.60 12.8487.93 0.25 0.60 13.1980.29 0.25 0.60 12.0482.53 0.25 0.60 12.3881.29 0.25 0.60 12.1972.47 0.25 0.60 10.8778.76 0.25 0.60 11.8178.63 0.25 0.60 11.7981.12 0.25 0.60 12.17

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO83.08 0.25 0.60 12.4682.71 0.25 0.60 12.4182.87 0.25 0.60 12.43

    194.75

    75.39 0.125 9.4276.73 0.125 9.5979.63 0.125 9.9577.08 0.125 9.6444.51 0.125 5.5674.19 0.125 9.2776.92 0.125 9.6276.25 0.125 9.5385.6 0.125 10.7087.93 0.125 10.9980.29 0.125 10.0482.53 0.125 10.3281.29 0.125 10.1672.47 0.125 9.0678.76 0.125 9.8578.63 0.125 9.8381.12 0.125 10.1483.08 0.125 10.3982.71 0.125 10.3482.87 0.125 10.36

    2025.37

    75.39 1.30 98.0176.73 1.30 99.7579.63 1.30 103.5277.08 1.30 100.2044.51 1.30 57.8674.19 1.30 96.4576.92 1.30 100.0076.25 1.30 99.1385.6 1.30 111.2887.93 1.30 114.3180.29 1.30 104.3882.53 1.30 107.2981.29 1.30 105.6872.47 1.30 94.2178.76 1.30 102.3978.63 1.30 102.2281.12 1.30 105.4683.08 1.30 108.0082.71 1.30 107.5282.87 1.30 107.73

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    6006.3872 6006.39

    130.25

    25.00 0.25 6.2525.00 0.25 6.2526.00 0.25 6.5026.00 0.25 6.5027.00 0.25 6.7525.00 0.25 6.2526.00 0.25 6.5025.00 0.25 6.2527.00 0.25 6.7527.00 0.25 6.7526.00 0.25 6.5026.00 0.25 6.5027.00 0.25 6.7526.00 0.25 6.5026.00 0.25 6.5026.00 0.25 6.5026.00 0.25 6.5026.00 0.25 6.5027.00 0.25 6.7526.00 0.25 6.50

    467.39

    75.39 0.30 22.6276.73 0.30 23.0279.63 0.30 23.8977.08 0.30 23.1244.51 0.30 13.3574.19 0.30 22.2676.92 0.30 23.0876.25 0.30 22.8885.6 0.30 25.6887.93 0.30 26.3880.29 0.30 24.0982.53 0.30 24.7681.29 0.30 24.3972.47 0.30 21.7478.76 0.30 23.6378.63 0.30 23.5981.12 0.30 24.3483.08 0.30 24.9282.71 0.30 24.8182.87 0.30 24.86

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    623.19

    75.39 0.40 30.1676.73 0.40 30.6979.63 0.40 31.8577.08 0.40 30.8344.51 0.40 17.8074.19 0.40 29.6876.92 0.40 30.7776.25 0.40 30.5085.6 0.40 34.2487.93 0.40 35.1780.29 0.40 32.1282.53 0.40 33.0181.29 0.40 32.5272.47 0.40 28.9978.76 0.40 31.5078.63 0.40 31.4581.12 0.40 32.4583.08 0.40 33.2382.71 0.40 33.0882.87 0.40 33.15

    292.12

    esponjamiento 1.25 233.70 292.12

    1019.15

    70.06 0.60 42.0471.72 0.60 43.0321.22 0.60 12.7371.88 0.60 43.1372.7 0.60 43.6222.93 0.60 13.7669.2 0.60 41.5270.15 0.60 42.0922.96 0.60 13.7872.96 0.60 43.7871.88 0.60 43.1319.92 0.60 11.9577.74 0.60 46.6476.73 0.60 46.0417.43 0.60 10.4618.24 0.60 10.9474.24 0.60 44.5474.04 0.60 44.42

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO79.54 0.60 47.7278.46 0.60 47.0818.31 0.60 10.9918.69 0.60 11.2171.52 0.60 42.9171.44 0.60 42.8622.03 0.60 13.2284.09 0.60 50.4586.72 0.60 52.0375.01 0.60 45.0175.31 0.60 45.1921.46 0.60 12.88

    1019.15

    70.06 0.60 42.0471.72 0.60 43.0321.22 0.60 12.7371.88 0.60 43.1372.7 0.60 43.6222.93 0.60 13.7669.2 0.60 41.5270.15 0.60 42.0922.96 0.60 13.7872.96 0.60 43.7871.88 0.60 43.1319.92 0.60 11.9577.74 0.60 46.6476.73 0.60 46.0417.43 0.60 10.4618.24 0.60 10.9474.24 0.60 44.5474.04 0.60 44.4279.54 0.60 47.7278.46 0.60 47.0818.31 0.60 10.9918.69 0.60 11.2171.52 0.60 42.9171.44 0.60 42.8622.03 0.60 13.2284.09 0.60 50.4586.72 0.60 52.0375.01 0.60 45.0175.31 0.60 45.1921.46 0.60 12.88

    509.57

    70.06 0.60 0.50 21.0271.72 0.60 0.50 21.52

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO21.22 0.60 0.50 6.3771.88 0.60 0.50 21.5672.7 0.60 0.50 21.8122.93 0.60 0.50 6.8869.2 0.60 0.50 20.7670.15 0.60 0.50 21.0522.96 0.60 0.50 6.8972.96 0.60 0.50 21.8971.88 0.60 0.50 21.5619.92 0.60 0.50 5.9877.74 0.60 0.50 23.3276.73 0.60 0.50 23.0217.43 0.60 0.50 5.2318.24 0.60 0.50 5.4774.24 0.60 0.50 22.2774.04 0.60 0.50 22.2179.54 0.60 0.50 23.8678.46 0.60 0.50 23.5418.31 0.60 0.50 5.4918.69 0.60 0.50 5.6171.52 0.60 0.50 21.4671.44 0.60 0.50 21.4322.03 0.60 0.50 6.6184.09 0.60 0.50 25.2386.72 0.60 0.50 26.0275.01 0.60 0.50 22.5075.31 0.60 0.50 22.5921.46 0.60 0.50 6.44

    212.32

    70.06 0.125 8.7671.72 0.125 8.9721.22 0.125 2.6571.88 0.125 8.9972.7 0.125 9.0922.93 0.125 2.8769.2 0.125 8.6570.15 0.125 8.7722.96 0.125 2.8772.96 0.125 9.1271.88 0.125 8.9919.92 0.125 2.4977.74 0.125 9.7276.73 0.125 9.5917.43 0.125 2.1818.24 0.125 2.2874.24 0.125 9.2874.04 0.125 9.2679.54 0.125 9.9478.46 0.125 9.81

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO18.31 0.125 2.2918.69 0.125 2.3471.52 0.125 8.9471.44 0.125 8.9322.03 0.125 2.7584.09 0.125 10.5186.72 0.125 10.8475.01 0.125 9.3875.31 0.125 9.4121.46 0.125 2.68

    4871.438 4871.44

    2038.30 2038.30

    70.06 PERIMETRO= 1.2 84.0771.72 PERIMETRO= 1.2 86.0621.22 PERIMETRO= 1.2 25.4671.88 PERIMETRO= 1.2 86.2672.7 PERIMETRO= 1.2 87.2422.93 PERIMETRO= 1.2 27.5269.2 PERIMETRO= 1.2 83.0470.15 PERIMETRO= 1.2 84.1822.96 PERIMETRO= 1.2 27.5572.96 PERIMETRO= 1.2 87.5571.88 PERIMETRO= 1.2 86.2619.92 PERIMETRO= 1.2 23.9077.74 PERIMETRO= 1.2 93.2976.73 PERIMETRO= 1.2 92.0817.43 PERIMETRO= 1.2 20.9218.24 PERIMETRO= 1.2 21.8974.24 PERIMETRO= 1.2 89.0974.04 PERIMETRO= 1.2 88.8579.54 PERIMETRO= 1.2 95.4578.46 PERIMETRO= 1.2 94.1518.31 PERIMETRO= 1.2 21.9718.69 PERIMETRO= 1.2 22.4371.52 PERIMETRO= 1.2 85.8271.44 PERIMETRO= 1.2 85.7322.03 PERIMETRO= 1.2 26.4484.09 PERIMETRO= 1.2 100.9186.72 PERIMETRO= 1.2 104.0675.01 PERIMETRO= 1.2 90.0175.31 PERIMETRO= 1.2 90.3721.46 PERIMETRO= 1.2 25.75

    2123.23

    70.06 1.25 87.5871.72 1.25 89.65

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO21.22 1.25 26.5371.88 1.25 89.8572.7 1.25 90.8822.93 1.25 28.6669.2 1.25 86.5070.15 1.25 87.6922.96 1.25 28.7072.96 1.25 91.2071.88 1.25 89.8519.92 1.25 24.9077.74 1.25 97.1876.73 1.25 95.9117.43 1.25 21.7918.24 1.25 22.8074.24 1.25 92.8074.04 1.25 92.5579.54 1.25 99.4378.46 1.25 98.0818.31 1.25 22.8918.69 1.25 23.3671.52 1.25 89.4071.44 1.25 89.3022.03 1.25 27.5484.09 1.25 105.1186.72 1.25 108.4075.01 1.25 93.7675.31 1.25 94.1421.46 1.25 26.83

    2972.52

    70.06 1.75 122.6171.72 1.75 125.5121.22 1.75 37.1471.88 1.75 125.7972.7 1.75 127.2322.93 1.75 40.1369.2 1.75 121.1070.15 1.75 122.7622.96 1.75 40.1872.96 1.75 127.6871.88 1.75 125.7919.92 1.75 34.8677.74 1.75 136.0576.73 1.75 134.2817.43 1.75 30.5018.24 1.75 31.9274.24 1.75 129.9274.04 1.75 129.5779.54 1.75 139.2078.46 1.75 137.3118.31 1.75 32.04

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO18.69 1.75 32.7171.52 1.75 125.1671.44 1.75 125.0222.03 1.75 38.5584.09 1.75 147.1686.72 1.75 151.7675.01 1.75 131.2775.31 1.75 131.7921.46 1.75 37.56

    41.62

    70.06 0.35 0.07 1.7271.72 0.35 0.07 1.7621.22 0.35 0.07 0.5271.88 0.35 0.07 1.7672.7 0.35 0.07 1.7822.93 0.35 0.07 0.5669.2 0.35 0.07 1.7070.15 0.35 0.07 1.7222.96 0.35 0.07 0.5672.96 0.35 0.07 1.7971.88 0.35 0.07 1.7619.92 0.35 0.07 0.4977.74 0.35 0.07 1.9076.73 0.35 0.07 1.8817.43 0.35 0.07 0.4318.24 0.35 0.07 0.4574.24 0.35 0.07 1.8274.04 0.35 0.07 1.8179.54 0.35 0.07 1.9578.46 0.35 0.07 1.9218.31 0.35 0.07 0.4518.69 0.35 0.07 0.4671.52 0.35 0.07 1.7571.44 0.35 0.07 1.7522.03 0.35 0.07 0.5484.09 0.35 0.07 2.0686.72 0.35 0.07 2.1275.01 0.35 0.07 1.8475.31 0.35 0.07 1.8521.46 0.35 0.07 0.53

    636.97

    esponjamiento 1.25 509.57 636.9675

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    90.48

    35.24 2.00 70.48

    10.00 2.00 20.00

    90.48

    35.24 2.00 70.48

    10.00 2.00 20.00

    25.44

    1.00 35.24 0.58 20.44

    1.00 10.00 0.50 5.00

    9.05

    1.00 35.24 0.20 7.05

    1.00 10.00 0.20 2.00

    45.24

    1.00 35.24 1.00 35.24

    1.00 10.00 1.00 10.00

    56.55

    1.00 35.24 1.25 44.05

    1.00 10.00 1.25 12.50

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    1097.9136 1097.91

    20.36

    1.00 35.24 0.20 1.00 7.051.00 35.24 1.00 0.25 8.81

    1.00 10.00 0.20 1.00 2.001.00 10.00 1.00 0.25 2.50

    5 1 5 5.00

    21.80 21.80

    2504.15AREA 2504.15

    500.83AREA 2504.15 0.20 500.83 500.83

    2504.15AREA 2504.15 2504.15

    2504.15

    AREA 54.31 54.31AREA 40.81 40.81AREA 63.85 63.85AREA 50.87 50.87

    AREA 63.59 63.59AREA 53.57 53.57AREA 51.03 51.03AREA 34.42 34.42

    AREA 27.56 27.56AREA 39.87 39.87AREA 40.8 40.8AREA 38.3 38.3

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    AREA 31.2 31.2AREA 43.82 43.82AREA 34.09 34.09AREA 48.41 48.41

    AREA 66.47 66.47AREA 83.28 83.28AREA 113.31 113.31AREA 100.76 100.76

    AREA 74.59 74.59AREA 63.66 63.66AREA 74.93 74.93AREA 84.53 84.53

    AREA 59.87 59.87AREA 75.5 75.5AREA 62.62 62.62AREA 64.31 64.31

    AREA 64.07 64.07AREA 67.56 67.56AREA 60.02 60.02AREA 71.31 71.31

    AREA 67.23 67.23AREA 72.52 72.52AREA 69.54 69.54AREA 87.89 87.89

    AREA 85.38 85.38AREA 72.52 72.52AREA 77.07 77.07AREA 68.71 68.71

    227.00

    11.00 11.0011.00 11.0012.00 12.0011.00 11.007.00 7.0011.00 11.0012.00 12.0012.00 12.0013.00 13.00

  • PLANILLA DE METRADOS

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

    : MUNICIPALIDAD PROVINCIAL DE UTCUBAMBA: BAGUA GRANDE

    CANT PIEZAMEDIDAS

    AREA PESO PARCIAL TOTALLONG. ANCHO ALTO

    12.00 12.0011.00 11.0012.00 12.0012.00 12.0011.00 11.0012.00 12.0011.00 11.0011.00 11.0012.00 12.0012.00 12.0011.00 11.00

    626.04500.83 1.25 626.04

    12226.44area 12,226.44 12,226.44

  • RESUMEN DE METRADOSOBRA

    Item Descripcin Und.

    01.00.00 OBRAS PROVISIONALES01.01.00 Cartel de indentificacin de Obra de 3.60 x 8.50 m. und01.02.00 Alquiler de Almacn y Oficina mes

    02.00.00 PAVIMENTOS02.01.00 TRABAJOS PRELIMINARES02.01.01 Limpieza de Terreno Manual m202.01.02 Trazo, Nivel y Replanteo m202.02.00 MOVIMIENTO DE TIERRAS02.02.01 Corte con Maquinaria en terreno natural hasta H=1.00 m m302.02.02 Perfilado, Nivelacin y compactacin de la subrasante en zonas de corte m202.02.03 Mejoramiento de subrasante con over menor a 6" e=20cm m202.02.04 Base Granular e=20cm m202.03.00 CONCRETO SIMPLE02.03.01 Losa de Rodadura, Concreto f'c = 210 Kg/cm2, e=0.20 m. m202.03.02 Concreto en Uas para Pavimento Rgido, Concreto f'c = 210 Kg/cm2 m302.03.03 Encofrado y Desencofrado de Losa de Rodadura m202.03.04 Levantamiento de Buzones Existentes a nivel de rasante und02.04.00 CURADO02.04.01 Curado de Losa de Rodadura, durante 7 dias - 4 veces x dia m202.05.00 JUNTAS02.05.01 Juntas de contraccin e=6mm m02.05.02 Juntas de contruccin de 3/4" c/ pasajuntas m02.05.03 Juntas de contruccin de 3/4" sin pasajuntas en la interseccin de calles m02.05.04 Juntas asflticas en pavimentos h=20 cm, e=1" m02.06.00 ACERO LISO02.06.01 Dowels transversales con acero liso de 3/4" m02.06.02 Barras de amarre longitudinal con acero corrugado de 3/4" m02.07.00 SEALIZACION02.07.01 SEALIZACION HORIZONTAL02.07.01.01 Pintado de Franjas en Pavimento - Sealizacion m202.07.02 SEALIZACION VERTICAL02.07.02.01 Sealizacin Preventiva de lado 0.60 x 0.60 und02.08.00 ELIMINACION DE MATERIAL EXCEDENTE

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

  • Item Descripcin Und.

    02.08.01 Eliminacin de Material Excedente a una Distancia = 5 Km + 25% esponjamiento c/ volquete m3

    03.00.00 VEREDAS03.01.00 TRABAJOS PRELIMINARES03.01.01 Limpieza de Terreno Manual m203.01.02 Trazo, Nivel y Replanteo m203.01.03 Demolicin de Vereda existente de concreto simple m203.01.04 Demolicin de Vereda existente de concreto simple con una H= 1.00 m m203.02.00 MOVIMIENTO DE TIERRAS03.02.01 Corte manual de terreno m303.02.02 Nivelacion y Apisonado en Veredas m203.02.03 Relleno Compactado C/ Material de prestamo (Afirmado) para base de vereda m203.03.00 CONCRETO SIMPLE03.03.01 Concreto f'c=175 Kg/cm2 en veredas, acabado frot., inc. brua. m203.03.02 Concreto f 'c=175 kg/cm2 en Rampas m203.03.03 Encofrado, descencofrado de Vereda. m203.04.00 JUNTAS Y BRUADO03.04.01 Junta de dilatacin 1" x 4" de concreto asfltico a 3.0 m m03.04.02 Bruado de veredas m03.04.03 Bruado de rampas m03.05.00 CURADO03.05.01 Curado de vereda con arena fina , durante 7 dias - 4 veces x da m203.06.00 SUMINISTRO Y COLOCACION DE CAJAS PARA AGUA Y DESAGUE03.06.01 Suministro y colocacin de encimado de cajas para agua und03.06.02 Suministro y colocacin de encimado de cajas para desague und03.07.00 ELIMINACION DE MATERIAL EXCEDENTE03.07.01 Eliminacin de Material Excedente a una Distancia = 5 Km + 25% esponjamiento c/ volquete m3

    04.00.00 SARDINEL04.01.00 TRABAJOS PRELIMINARES04.01.01 Limpieza de Terreno Manual m204.01.02 Trazo, Nivel y Replanteo m204.02.00 MOVIMIENTO DE TIERRAS04.02.01 Excavacion de sardineles hasta h=60 cm m304.03.00 CONCRETO SIMPLE 04.03.01 Concreto f'c = 175 Kg/cm2 vaceado con mezcladora m304.03.02 Encofrado y Desencofrado m204.03.03 Acero Corrugado 3/8", fy=4200 kg/cm2 kg04.03.04 Relleno de Juntas de Dilatacin con concreto asfaltico 1"x2" m en sardinel m04.03.05 Tarrajeo pulido en sardineles m204.03.06 Curado de sardinel con arena fina, durante 7 dias - 4 veces x da m204.04.00 ELIMINACION DE MATERIAL EXCEDENTE

    04.04.01 Eliminacin de Material Excedente a una Distancia = 5 Km + 25% esponjamiento c/ volquete m3

  • Item Descripcin Und.

    05.00.00 CUNETAS RECTANGULARES05.01.00 TRABAJOS PRELIMINARES05.01.00 Limpieza de Terreno Manual m205.02.00 Trazo, Nivel y Replanteo m205.02.00 MOVIMIENTO DE TIERRAS05.02.01 Excavacion de cunetas rectangulares hasta h=60 cm m305.03.00 CONCRETO SIMPLE05.03.01 Concreto f'c = 175 Kg/cm2 vaceado con mezcladora m305.03.02 Acero Corrugado 3/8", fy=4200 kg/cm2 kg05.03.03 Encofrado y Desencofrado M205.03.04 Tarrajeo pulido en Cunetas rectangulares m205.03.05 Curado de sardinel y canaletas, durante 7 dias - 4 veces x da m205.03.06 Tapas de concreto para Cunetas Rectangulares m305.04.00 ELIMINACION DE MATERIAL EXCEDENTE

    05.04.01 Eliminacin de Material Excedente a una Distancia = 5 Km + 25% esponjamiento c/ volquete m3

    06.00.00 MURO DE CONTENCION06.01.00 TRABAJOS PRELIMINARES06.01.01 Limpieza de Terreno Manual m206.01.02 Trazo, Nivel y Replanteo m206.02.00 MOVIMIENTO DE TIERRAS06.02.01 Corte de Terreno Manual para Muro de Contencin m306.02.02 Relleno con material de prstamo en Muro de Contencin m306.03.00 CONCRETO SIMPLE06.03.01 Solado 1:10; C:A e = 4" m206.04.00 CONCRETO ARMADO06.04.01 Encofrado y Desencofrado de Muro de contencin m206.04.02 ACERO CORRUGADO, fy = 4200 Kg/cm2 -Muro de Contencion kg06.04.03 Concreto f'c = 210 Kg/cm2 en muro de contencin m306.05.00 JUNTAS06.05.01 Juntas de Dilatacin en Muro y Losa Inferior con water stop 6" cada 9.00 m. m06.06.00 ELIMINACION DE MATERIAL EXCEDENTE

    06.06.01 Eliminacin de Material Excedente a una Distancia = 5 Km + 25% esponjamiento c/ volquete m3

    07.00.00 AREAS VERDES07.01.00 Corte superficial para jardineras hasta 0.20 m m207.02.00 Acarreo de material excedente dp

  • Item Descripcin Und.

    08.00.00 VARIOS08.01.00 Limpieza final de obra m2

  • RESUMEN DE METRADOS

    Metrado

    1.004.00

    6,007.376,007.37

    7,282.146,007.376,007.376,007.37

    6,007.37263.26

    3,504.6114.00

    6,007.37

    2,292.49254.40418.62

    1,902.45

    1,372.80919.69

    441.20

    16.00

    CONSTRUCCION DE PISTAS Y VEREDAS EN EL BARRIO SAN MARTIN ALTO - PROVINCIA DE UTCUBAMBA - AMAZONAS

  • Metrado

    9,102.68

    2,741.672,741.67945.1662.90

    1,100.782,751.952,751.95

    2,562.10189.85

    1,970.10

    625.205503.00890.40

    2,751.95

    149.00149.00

    1,031.98

    389.50389.50

    233.70

    194.752,025.376,006.39130.25467.39623.19

    292.12

  • Metrado

    1,019.151,019.15

    509.57

    212.324871.442,038.302,123.232972.52

    41.62

    636.97

    90.4890.48

    25.449.05

    45.24

    56.551,097.91

    20.36

    5.00

    21.80

    2504.15500.83

    2504.152504.15227.00

    626.04

  • Metrado

    12226.44

  • METRADO DE ACERO -MURO DE CONTENCION

    N de Descripcin del Diseo de AceroPartida Elemento Estructural en el elemento estructural

    MURO DE CONTENCIONACERO FY=4200 KG/CM2

    0.3L= 40.00 39.92

    0.10 0.10

    0.1

    1.50

    0.2

    MURO DE CONTENCIONACERO FY=4200 KG/CM2

    0.3 0.25L= 40.00 39.92

    0.10 0.10

    0.1

    1.50

    0.2

    MURO DE CONTENCIONACERO FY=4200 KG/CM2

    0.25L= 40.00 39.92

    0.10 0.10

    0.2

    1.00

    0.2

    MURO DE CONTENCIONACERO FY=4200 KG/CM2

    0.2L= 40.00 39.92

    3/8" @

    3/8" @ 3/8" @

    3/8" @

    3/8" @

  • 0.10 0.10

    0.2

    1.00

    0.2

  • METRADO DE ACERO -MURO DE CONTENCION

    Dimetro Longitud porRepeticioneCantidad de Elemento LONGITUD POR DIAMETRO DE VARILLA EN ML.varilla diseo del diseo Estructurales 1/4 3/8 1/2 5/8

    3/8 40.12 6.00 1.00 240.72

    3/8 1.80 134.00 1.00 241.20

    3/8 40.12 6.00 1.00 240.72

    3/8 1.80 161.00 1.00 289.80

    3/8 40.12 5.00 1.00 200.60

    3/8 1.40 161.00 1.00 225.40

    3/8 40.12 6.00 1.00 240.72

  • 3/8 1.40 201.00 1.00 281.40

    Peso en kilogramos por metro lineal 0.22 0.56 0.99 1.55 Longitud total por dimetro, en metros lineales - 1,960.56 - - Total en kilogramos por dimetro - 1,097.91 - -

  • METRADO DE ACERO -MURO DE CONTENCION

    LONGITUD POR DIAMETRO DE VARILLA EN ML.3/4 1

  • 2.24 3.97 Total en kg - - - - 1,097.91

  • METRADO DE ACERO - CUNETAS RECTANGULARES

    N de Descripcin del Diseo de AceroPartida Elemento Estructural en el elemento estructural

    AV.MARIANO MELGARACERO FY=4200 KG/CM2

    0.15L= 426.13 426.05

    0.10 0.10

    0.50 0.5

    0.45

    JR.JOSE GALVEZ0.15

    L= 145.00 144.92

    0.10 0.10

    0.50 0.5

    0.45

    JR.RICARDO PALMA0.15

    L= 343.00 342.92

    0.10 0.10

    0.50 0.5

    0.45

    JR.PEDRO RUIZ0.15

    L= 496.00 495.92

    0.10 0.10

    1/4" @

    1/4" @

    1/4" @

    1/4" @

  • 0.50 0.5

    0.45

    JR.ABRAHAM0.15

    L= 142.94 142.86

    0.10 0.10

    0.50 0.5

    0.45

    OTROS AV0.15

    L= 66.21 66.13

    0.10 0.10

    0.50 0.5

    0.45

    1/4" @

    1/4" @

  • METRADO DE ACERO - CUNETAS RECTANGULARES

    Diseo de Acero Dimetro Longitud porRepeticioneCantidad de Elemento LONGITUD POR DIAMETRO DE VARILLA EN ML.en el elemento estructural varilla diseo del diseo Estructurales 1/4 3/8 1/2

    1/4 426.25 4 1 1,705.00

    1/4 1.45 2842 1 4,120.90

    1/4 145.12 4 1 580.48

    1/4 1.45 968 1 1,403.60

    1/4 343.12 4 1 1,372.48

    1/4 1.45 2288 1 3,317.60

    1/4 496.12 4 1 1,984.48

  • 1/4 1.45 3308 1 4,796.60

    1/4 143.06 4 1 572.24

    1/4 1.45 954 1 1,383.30

    1/4 66.33 4 1 265.32

    1/4 1.45 442 1 640.90

    Peso en kilogramos por metro lineal 0.22 0.56 0.99 Longitud total por dimetro, en metros lineales 22,142.90 - - Total en kilogramos por dimetro 4,871.44 - -

  • METRADO DE ACERO - CUNETAS RECTANGULARES

    LONGITUD POR DIAMETRO DE VARILLA EN ML.5/8 3/4 1

  • 1.55 2.24 3.97 Total en kg - - - - - - 4,871.44

  • Pgina 93

    METRADO DE ACERO - SARDINELES

    N de Descripcin del Diseo de Acero Dimetro Longitud porRepeticioneCantidad de ElementoPartida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales

    SARDINELAV.MARIANO MELGAR

    0.15L= 430.00 429.92 1/4 430.12 11.00 1.00

    0.10 0.10

    1/4 1.70 2,868.00 1.00

    1.50

    0.2

    JR.JOSE GALVEZACERO FY=4200 KG/CM2

    0.15L= 154.00 153.92 1/4 154.12 11.00 1.00

    0.10 0.10

    1/4 1.70 1,028.00 1.00

    1.50

    0.2

    JR.PEDRO RUIZACERO FY=4200 KG/CM2

    1/4" @

    1/4" @

  • Pgina 94

    METRADO DE ACERO - SARDINELES

    N de Descripcin del Diseo de Acero Dimetro Longitud porRepeticioneCantidad de ElementoPartida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales

    0.15L= 404.50 404.42 1/4 404.62 8.00 1.00

    0.10 0.10

    1/4 1.20 2,698.00 1.00

    1.00

    0.2

    JR.ABRAHAM VALDELOMARACERO FY=4200 KG/CM2

    0.15L= 156.00 155.92 1/4 156.12 8.00 1.00

    0.10 0.10

    1/4 1.20 1,041.00 1.00

    1.00

    0.2

    JR.RICARDO PALMAACERO FY=4200 KG/CM2

    0.15L= 329.78 329.70 1/4 329.90 8.00 1.00

    1/4" @

    1/4" @

    1/4" @

  • Pgina 95

    METRADO DE ACERO - SARDINELES

    N de Descripcin del Diseo de Acero Dimetro Longitud porRepeticioneCantidad de ElementoPartida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales

    0.10 0.10

    1/4 1.20 2,200.00 1.00

    1.00

    0.2

    Peso en kilogramos por metro linealLongitud total por dimetro, en metros linealesTotal en kilogramos por dimetro

  • Pgina 96

    METRADO DE ACERO - SARDINELES

    LONGITUD POR DIAMETRO DE VARILLA EN ML.1/4 3/8 1/2 5/8 3/4 1

    4,731.32 4,875.60 1,695.32 1,747.60

  • Pgina 97

    METRADO DE ACERO - SARDINELES

    LONGITUD POR DIAMETRO DE VARILLA EN ML.1/4 3/8 1/2 5/8 3/4 1

    3,236.96 3,237.60 1,248.96 1,249.20 2,639.20

  • Pgina 98

    METRADO DE ACERO - SARDINELES

    LONGITUD POR DIAMETRO DE VARILLA EN ML.1/4 3/8 1/2 5/8 3/4 1

    2,640.00

    0.22 0.56 0.99 1.55 2.24 3.97 Total en kg 27,301.76 - - - - - 6,006.39 - - - - - 6,006.39

  • Pgina 99

    METRADO DE ACERO - TAPAS DE CANALETAS

    N de Descripcin del Diseo de Acero Dimetro Longitud porRepeticioneCantidad de ElementoPartida Elemento Estructural en el elemento estructural varilla diseo del diseo Estructurales

    TAPAS DE CUNETASAV.MARIANO MELGAR

    0.15L= 1698.58 1698.50 1/4 1,698.50 3.00 1.00

    1/4 0.35 11325.00 1.00

    0.35

    Peso en kilogramos por metro linealLongitud total por dimetro, en metros linealesTotal en kilogramos por dimetro

    1/4" @

  • Pgina 100

    METRADO DE ACERO - TAPAS DE CANALETAS

    LONGITUD POR DIAMETRO DE VARILLA EN ML.1/4 3/8 1/2 5/8 3/4 1

    5,095.50 3,963.75 0.22 0.56 0.99 1.55 2.24 3.97 Total en kg 9,059.25 - - - - - 1,993.04 - - - - - 1,993.04

    METRADOS DETALLADOSRESUMEN DE METRADOSA MURO CONTENCIONA CANALETASA SARDINELESA TAPA DE CUNETAS