Adicional deductivo 01

8
PRESUPUESTO DEDUCTIVO VINCULANTE N°01 ITEM DESCRIPCION UND METRADO P.U PARCIAL 02.00.00 TRABAJOS PRELIMINARES 2.01 LIMPIEZA DE TERRENO MANUAL M2 2,687.27 0.46 1,236.14 2.03 TRAZO NIVELES Y REPLANTEO DE VIAS M2 2,687.27 0.77 2,069.20 03.00.00 MOVIMIENTO DE TIERRAS 3.01 EXCAVACION A NIVEL DE SUB RASANTE M3 788.44 2.42 1,908.02 3.02 PERFILADO Y COMPACTADO DE SUB RASANTE M2 1,478.00 1.54 2,276.12 3.03 SUB BASE GRANULAR H=0.20 M. M2 1,478.00 5.35 7,907.30 3.04 BASE GRANULAR H=0.20 M. M2 1,478.00 6.06 8,956.68 3.05 CARGUIO, Y TRANSPORTE DE BASE Y SUB BASE M3 591.20 6.60 3,901.92 3.06 ELIMINACION DE MATERIAL EXCEDENTE M3 739.00 13.35 9,865.65 04.00.00 PAVIMENTOS FLEXIBLES 4.02 IMPRIMACION ASFALTICA M2 1,478.00 5.11 7,552.58 4.02 CARPETA ASFALTICA EN CALIENTE E=2" M2 1,343.63 31.96 42,942.41 4.03 SELLADO ASFALTICO M2 1,343.63 6.06 8,142.40 05.00.00 SARDINEL 5.01 SARDINEL ENCOFRADO Y DESENCOFRADO M2 179.15 20.66 3,701.24 5.02 SARDINEL CONCRETO F'C=175 KG/CM2 M3 33.59 246.23 8,270.87 06.00.00 DRENAJE PLUVIAL 6.01 CUNETA ENCOFRADO Y DESENCOFRADO M2 67.18 20.66 1,387.94 6.02 CUNETA CONCRETO F'C=175 KG/CM2 M3 13.44 260.66 3,503.27 COSTO DIRECTO GASTOS GENERALES 7% UTILIDAD 3% SUB TOTAL IGV 18% PRESUPUESTO TOTAL

description

Adicional deductivo

Transcript of Adicional deductivo 01

Deductivo contrat.PRESUPUESTO DEDUCTIVO VINCULANTE N01ITEMDESCRIPCIONUNDMETRADOP.UPARCIALCOSTO

02.00.00TRABAJOS PRELIMINARES3,305.342.01LIMPIEZA DE TERRENO MANUALM22,687.270.461,236.142.03TRAZO NIVELES Y REPLANTEO DE VIASM22,687.270.772,069.20

03.00.00MOVIMIENTO DE TIERRAS34,815.693.01EXCAVACION A NIVEL DE SUB RASANTEM3788.442.421,908.023.02PERFILADO Y COMPACTADO DE SUB RASANTEM21,478.001.542,276.123.03SUB BASE GRANULAR H=0.20 M.M21,478.005.357,907.303.04BASE GRANULAR H=0.20 M.M21,478.006.068,956.683.05CARGUIO, Y TRANSPORTE DE BASE Y SUB BASEM3591.206.603,901.923.06ELIMINACION DE MATERIAL EXCEDENTEM3739.0013.359,865.65

04.00.00PAVIMENTOS FLEXIBLES58,637.394.02IMPRIMACION ASFALTICAM21,478.005.117,552.584.02CARPETA ASFALTICA EN CALIENTE E=2"M21,343.6331.9642,942.414.03SELLADO ASFALTICOM21,343.636.068,142.40

05.00.00SARDINEL11,972.115.01SARDINEL ENCOFRADO Y DESENCOFRADOM2179.1520.663,701.245.02SARDINEL CONCRETO F'C=175 KG/CM2M333.59246.238,270.87

06.00.00DRENAJE PLUVIAL4,891.216.01CUNETA ENCOFRADO Y DESENCOFRADOM267.1820.661,387.946.02CUNETA CONCRETO F'C=175 KG/CM2M313.44260.663,503.27

COSTO DIRECTO113,621.74GASTOS GENERALES7%7,953.52UTILIDAD3%3,408.65SUB TOTAL124,983.91IGV18%22,497.10PRESUPUESTO TOTAL147,481.01

Deductivo superv.PRESUPUESTO DEDUCTIVO VINCULANTE N01ITEMDESCRIPCIONUNDMETRADOP.UPARCIALCOSTO

Longitud130.50Ancho de calzada6.00Ancho de base6.60Ancho de seccion vial12.00

02.00.00TRABAJOS PRELIMINARES1,926.182.01LIMPIEZA DE TERRENO MANUALM21,566.000.46720.362.03TRAZO NIVELES Y REPLANTEO DE VIASM21,566.000.771,205.82

03.00.00MOVIMIENTO DE TIERRAS20,010.593.01EXCAVACION A NIVEL DE SUB RASANTEM3344.522.42833.743.02PERFILADO Y COMPACTADO DE SUB RASANTEM2861.301.541,326.403.03SUB BASE GRANULAR H=0.20 M.M2861.305.354,607.963.04BASE GRANULAR H=0.20 M.M2861.306.065,219.483.05CARGUIO, Y TRANSPORTE DE BASE Y SUB BASEM3344.526.602,273.833.06ELIMINACION DE MATERIAL EXCEDENTEM3430.6513.355,749.18

04.00.00PAVIMENTOS FLEXIBLES34,170.904.02IMPRIMACION ASFALTICAM2861.305.114,401.244.02CARPETA ASFALTICA EN CALIENTE E=2"M2783.0031.9625,024.684.03SELLADO ASFALTICOM2783.006.064,744.98

05.00.00SARDINEL6,978.085.01SARDINEL ENCOFRADO Y DESENCOFRADOM2104.4020.662,156.905.02SARDINEL CONCRETO F'C=175 KG/CM2M319.58246.234,821.18

06.00.00DRENAJE PLUVIAL2,849.816.01CUNETA ENCOFRADO Y DESENCOFRADOM239.1520.66808.846.02CUNETA CONCRETO F'C=175 KG/CM2M37.83260.662,040.97

COSTO DIRECTO65,935.56GASTOS GENERALES7%4,615.49UTILIDAD3%1,978.07SUB TOTAL72,529.12IGV18%13,055.24PRESUPUESTO TOTAL85,584.36

ResumenCUADRO COMPARATIVO DE COSTOSADICIONAL DE OBRA N01DEDUCTIVO VINCULANTE DE OBRA N01CONTRATISTACONTRATISTA

ITEMCOMPONENTEPRECIOITEMCOMPONENTEPRECIO1MURO SECO20,694.591TRABAJOS PRELIMINARES3,305.342SISTEMA DE DRENAJE SUB TERRANEO6,332.782MOVIMIENTO DE TIERRAS34,815.693CONSTRUCCION DE GRADERIAS11,785.813PAVIMENTOS FLEXIBLES58,637.394CONSTRUCCION DE SARDINEL SUMERGIDO4,994.044SARDINEL11,972.115BADEN2,024.075DRENAJE PLUVIAL4,891.216ALCANTARILLADO PLUVIAL44,153.157PAVIMENTACION23,636.72

COSTO DIRECTO113,621.16COSTO DIRECTO113,621.74GASTOS GENERALES7%7953.48GASTOS GENERALES7%7953.52UTILIDAD3%3408.63UTILIDAD3%3408.65SUB TOTAL124,983.27SUB TOTAL124,983.91IGV18%22496.99IGV18%22497.1PRESUPUESTO TOTAL147,480.26PRESUPUESTO TOTAL147,481.01LONGITUD DE PAVIMENTACION=223.94A DISMINUIR

CUADRO COMPARATIVO DE COSTOSADICIONAL DE OBRA N01DEDUCTIVO VINCULANTE DE OBRA N01MUNICIPALIDAD DISTRITAL DE PUCARAMUNICIPALIDAD DISTRITAL DE PUCARA

ITEMCOMPONENTEPRECIOITEMCOMPONENTEPRECIO5BADEN2,024.071TRABAJOS PRELIMINARES1,926.186ALCANTARILLADO PLUVIAL40,253.322MOVIMIENTO DE TIERRAS20,010.597PAVIMENTACION23,636.723PAVIMENTOS FLEXIBLES34,170.904SARDINEL6,978.085DRENAJE PLUVIAL2,849.81

COSTO DIRECTO65,914.11COSTO DIRECTO65,935.56GASTOS GENERALES7%4613.99GASTOS GENERALES7%4615.49UTILIDAD3%1977.42UTILIDAD3%1978.07SUB TOTAL72,505.52SUB TOTAL72,529.12IGV18%13050.99IGV18%13055.24PRESUPUESTO TOTAL85,556.51PRESUPUESTO TOTAL85,584.36LONGITUD DE PAVIMENTACION=130.50A DISMINUIR*El presupuesto obtenido es referencial, debido a que existen costos excesivos en los insumos que se detallan en el analisis de costos unitarios, que deben ser corregidos.

*Opinion favorable por parte de la Supervision en su primeta etapa de ejecucion.