Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

226

Click here to load reader

Transcript of Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

Page 1: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

GUIA PARA EL ANALISIS

DE COSTOS DE EDIFICACIONES

E INDICE DE PRECIOS

EN SANTO DOMINGO, REP. DOMINICANA

7MA. EDICION

PROPUESTA DEL

ARQ. JOSE ALEJANDRO GARCIA SIMO-M.Ave. México 26, 2da. Planta, esq. Rosa Duarte, Don Bosco

Ofic 809 685-8088 - Cel 809 519-3340 - Res 809 565-9492

5 MAYO 2010

PRECIO BASICO EN CD RD$800.00

PRECIO BASICO DEL FOLLETO RD$900.00

PRECIO CD EN EL INTERIOR RD$1,000.00

PRECIO DEL FOLLETO EN EL INTERIOR RD$1,100.00

PRECIO VIA INTERNET RD$800.00

E-MAIL: [email protected]

Page 2: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

DE COSTOS DE EDIFICACIONES

EN SANTO DOMINGO, REP. DOMINICANA

ARQ. JOSE ALEJANDRO GARCIA SIMO-M.Ave. México 26, 2da. Planta, esq. Rosa Duarte, Don Bosco

Ofic 809 685-8088 - Cel 809 519-3340 - Res 809 565-9492

[email protected]

Page 3: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 1

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

16.00%ORDENADO ALFABETICAMENTE

INSUMOS (TODOS los precios con ITBIS incluido)

INACE 50000 ACEROS Y ALAMBRE GALVANIZADO:INACE 50001 Hache Acero ¼" qq 1,025.00INACE 50002 Hache Acero grado 40, 3/8" x 20' qq 1,865.00INACE 50003 Hache Acero grado 40, 3/8" x 25' qq 1,865.00INACE 50004 Hache Acero grado 40, ½" x 20' qq 1,865.00INACE 50005 Hache Acero grado 40, ½" x 25' qq 1,865.00INACE 50006 Hache Acero grado 40, ¾" qq 1,865.00INACE 50007 Hache Acero grado 40, 1" qq 1,865.00INACE 50008 Ferret. Americ. 052472 Acero grado 60, 3/8" x 20' qq 1,970.20INACE 50009 Ferret. Americ. 052473 Acero grado 60, 3/8" x 25' qq 1,970.20INACE 50010 Ferret. Americ. 052475 Acero grado 60, ½" x 20' qq 1,970.20INACE 50011 Ferret. Americ. 052476 Acero grado 60, ½" x 25' qq 1,970.20INACE 50012 Ferret. Americ. 052478 Acero grado 60, ¾" x 20' qq 1,970.20INACE 50013 Ferret. Americ. 023422 Acero grado 60, 1" x 20' qq 1,970.20INACE 50014 Ferret. Americ. 023934 Alambre galv. Calibre 14 (Para reforzar encofrados) lb 25.44INACE 50015 Ferret. Americ. 066278 Alambre galv. Calibre 18 lb 25.44INACE 50016 Ferret. Americ. 148366 Acero malla (D2.3 x D2.3, 100 x 100,Rollo 2.40 x 40.00 m., 4.85 qq) rollo 11,863.92INACE 50017 Ferret. Americ. 023401 Acero malla (D2.3 x D2.3, 150 x 150,Rollo 2.40 x 40.00 m., 3.32 qq) rollo 8,181.89INACE 50018 Ferret. Americ. 066663 Acero malla (D2.3 x D2.3, 200 x 200,Rollo 2.40 x 40.00 m., 2.48 qq) rollo 5,920.09INACE 50019 MC Acero malla (D2.5 x D2.5, 100 x 100,Rollo 2.40 x 40.00 m., 5.35 qq) rollo 13,417.00INACE 50020 MC Acero malla (D2.5 x D2.5, 150 x 150,Rollo 2.40 x 40.00 m., 3.66 qq) rollo 8,943.99INACE 50021 MC Acero malla (D2.5 x D2.5, 200 x 200,Rollo 2.40 x 40.00 m., 2.74 qq) rollo 6,842.00INACE 50022 Ferret. Americ. 126750 Acero malla (D2.7 x D2.7, 100 x 100,Rollo 2.40 x 40.00 m., 5.87 qq) rollo 13,933.58INACE 50023 MC Acero malla (D2.7 x D2.7, 150 x 150,Rollo 2.40 x 40.00 m., 3.90 qq) rollo 8,517.33INACE 50024 MC Acero malla (D2.9 x D2.9, 100 x 100,Rollo 2.40 x 40.00 m., 6.21 qq) rollo 14,929.20INACE 50025 MC Acero malla (D2.9 x D2.9, 150 x 150,Rollo 2.40 x 40.00 m., 4.25 qq) rollo 9,402.96INACE 50026 MC Acero malla (D2.9 x D2.9, 200 x 200,Rollo 2.40 x 40.00 m., 3.18 qq) rollo 6,935.18

INACE 70000 AGREGADOS, BOTES, ETC.: (Domingo López, Cel. 750-8895)INACE 70001 Arena fina para empañete m3 820.00INACE 70002 Arena gruesa lavada m3 820.00INACE 70003 Arena itabo de mina m3 750.00INACE 70004 Arena triturada y lavada, azul (Para hormigón) m3 1,100.00INACE 70005 Bote de materiales (Con paleros) m3 300.00INACE 70006 Bote de materiales (Con equipo) m3 199.50INACE 70007 Caliche m3 280.00INACE 70008 Cascajo de mina m3 750.00INACE 70009 Granzote fino m3 500.00INACE 70010 Granzote grueso m3 425.00INACE 70011 Grava ¾" - ½" triturada m3 750.00INACE 70012 Tierra negra m3 750.00

INASC 90000 ASCENSORES:INASC 90001 Ascensor 8 personas, 8 niv., 3 ph. "Mitsubishi" u 2,631,981.87INACE 90002 Ascensor para 10 personas, 6 niv., Gen2 Confort, 1 m/seg., 3 ph. "Otis" u 1,626,190.50

INBOV 110000 BOVEDILLAS DE "FOAM"INBOV 110001 Bovedilla de .40 x .15 x 1.00 m., macizas, "EHI" m 204.32INBOV 110002 Transporte bovedillas macizas .40 x .15, "EHI" % 4.00%

INBAL 130000 BALAUSTRES Y PASAMANOS: Precios estimadosINBAL 130001 Balaustre 45 cms. Gris u 125.29INBAL 130002 Balaustre 45 cms. Bco. Cep. u 196.03INBAL 130003 Balaustre 50 cms. Gris u 137.81INBAL 130004 Balaustre 50 cms. Bco. Cep. u 218.87INBAL 130005 Balaustre 55 cms. Gris u 149.61INBAL 130006 Balaustre 55 cms. Bco. Cep. u 237.30INBAL 130007 Balaustre 64 cms. Gris u 173.19INBAL 130008 Balaustre 64 cms. Bco. Cep. u 277.10INBAL 130009 Balaustre 67 cms. Gris u 182.77INBAL 130010 Balaustre 67 cms. Bco. Cep. u 287.42INBAL 130011 Balaustre 72 cms. Gris u 190.13INBAL 130012 Balaustre 72 cms. Bco. Cep. u 305.84INBAL 130013 Balaustre 74 cms. Gris Cep. u 205.61INBAL 130014 Balaustre 74 cms. Bco. Cep. u 328.68INBAL 130015 Pasamano bco. Cep. 30 bocel cuadrado m 550.26INBAL 130016 Pasamano bco. Cep. 30 bocel redondo m 641.97INBAL 130017 Pasamano bco. Pul. 30 bocel cuadrado m 651.80INBAL 130018 Pasamano bco. Pul. 30 bocel redondo m 709.94INBAL 130019 Pasamano super bocel cuadrado m 678.83INBAL 130020 Pasamano super bocel redondo m 799.19INBAL 130021 Transp. balaustre u 2.32INBAL 130022 Transp. pasamano m 9.28

INBAÑ 150000 BAÑOS, FREGADEROS , CALENTADORES ELECT. Y ACCESORIOS:INBAÑ 150001 Ferret. Americ. 190762 Accesorios 5 piezas, Bco., porcelana u 1,465.00INBAÑ 150002 Ferret. Americ. 077336 Accesorios 5 piezas, cromo, corriente, sup. u 406.00INBAÑ 150003 Ferret. Americ. 253788 Accesorios 6 piezas, cromo, sup., 5706 u 1,345.60INBAÑ 150004 Ferret. Americ. 015472 Arandela plástica 3" ó 4", para inodoro u 27.26INBAÑ 150005 Ferret. Americ. 134247 Aro Oimpia Tatay 63071-6 u 269.87INBAÑ 150006 Ferret. Americ. 072792 Asiento p/inod., Bone redondo, D60 J. V., "Sadosa" u 300.00INBAÑ 150007 Ferret. Americ. Bañera hierro fundido, color, "Naple" sin mescl. y sin ducha u 12,180.00INBAÑ 150008 Ferret. Americ. Bañera hierro fundido, blanca, "Naple" sin mescl. y sin ducha u 13,304.78

Page 4: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 2

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INBAÑ 150009 Ferret. Americ. 251447 Bañera hidroneumasaje blanca con asiento y reclinacabeza u 44,822.40INBAÑ 150010 Ferret. Americ. 008229 Bañera liviana, color, sin mescl. y sin ducha u 6,142.20INBAÑ 150011 Ferret. Americ. 008230 Bañera liviana, blanca, sin mescl. y sin ducha u 5,974.00INBAÑ 150012 Ferret. Americ. 162389 Bañera PVC blanca, 1.4 m., "Virgo" u 6,198.75INBAÑ 150013 Ferret. Americ. 136473 Bañera PVC color, 1.4 m., "Virgo" u 6,198.75INBAÑ 150014 Ferret. Americ. 253503 Barra de seguridad 16", cromo, JOFEL AV-40400 u 1,483.29INBAÑ 150015 Ferret. Americ. 253502 Barra de seguridad 24",cromo, JOFEL AV-40600 u 1,682.15INBAÑ 150016 Ferret. Americ. 015237 Barra para cortina de baño, 6 pies u 225.91INBAÑ 150017 Ferret. Americ. 007726 Bidet a color "Royal", sin mescl. y sin acces. u 2,734.33INBAÑ 150018 Ferret. Americ. 157985 Bidet bco. "Royal", sin mescl. y sin acces. u 2,989.32INBAÑ 150019 Ferret. Americ. 106599 Boquilla lavamanos, automática, cromo, "Price Pfister" u 247.83INBAÑ 150020 Ferret. Americ. 015053 Boquilla lavamanos, pvc, sencilla u 70.30INBAÑ 150021 Ferret. Americ. 015025 Boquilla fregadero, 4 ½", cromo (c/u) u 137.75INBAÑ 150022 Ferret. Americ. 015026 Boquilla lavadero, cromo, con tapón u 88.16INBAÑ 150023 Ferret. Americ. 015040 Boquilla lavadero 2 ½", pvc, con tapón u 89.00INBAÑ 150024 Ferret. Americ. 064329 Botiquín 1 pta., 2 luces, cromo, corriente, R1102 u 2,534.60INBAÑ 150025 Ferret. Americ. Botiquín 1 pta, Bco., mad. prens., Danubio 700, 27 ½"x26 ½", "Salgar" u 5,351.00INBAÑ 150026 Ferret. Americ. 008020 Botiquín 2 ptas., 2 luces, cromo, Salgar, (Bot 48) u 4,314.01INBAÑ 150027 Ferret. Americ. 065262 Botiquín 2 ptas., 2 luces, cromo, 3 cajones (Bot 90 C/cajones) u 2,440.93INBAÑ 150028 Ferret. Americ. Botiquín 2 pta, Bco., mad. prens., Danubio 850, 33 ½"x26 ½", "Salgar" u 7,132.00INBAÑ 150029 Ferret. Americ. Botiquín 3 ptas., 2 luces, cromo, Salgar, (Bot 60) u 4,100.60INBAÑ 150030 Ferret. Americ. 056385 Calent. eléct. 6 gls., Criollo "Temp Quip" u 4,268.00INBAÑ 150031 Ferret. Americ. 055727 Calent. eléct. 8 gls., Criollo "Temp Quip" u 5,328.17INBAÑ 150032 Ferret. Americ. 056386 Calent. eléct. 12 gls., Criollo "Temp Quip" u 4,716.00INBAÑ 150033 Ferret. Americ. 061437 Calent. eléct. 20 gls., Criollo, f. de vidrio u 7,585.00INBAÑ 150034 Ferret. Americ. 280023 Calent. eléct. 30 gls., Criollo, f. de vidrio u 13,180.00INBAÑ 150035 Ferret. Americ. 007983 Calent. eléct. 20 gls., importado u 20,725.67INBAÑ 150036 Ferret. Americ. 051491 Calent. eléct. 30 gls., importado u 21,329.50INBAÑ 150037 Ferret. Americ. 015176 Calent. eléct. 40 gls., importado u 18,596.25INBAÑ 150038 Ferret. Americ. 286612 Calent. eléct. 80 gls., importado u 27,377.00INBAÑ 150039 Ferret. Americ. 239864 Calent. de gas 10 litros por minuto, "Min Chuang" u 11,742.00INBAÑ 150040 Ferret. Americ. 131842 Calent. de gas 14 litros por minuto, "Splendid" u 13,906.00INBAÑ 150041 Ferret. Americ. 262392 Cepillera clásica II, sup., cromo 207 u 701.00INBAÑ 150042 Ferret. Americ. 213529 Cepillera Nuva cristal, sup., cromo 9107_C u 2,688.88INBAÑ 150043 Ferret. Americ. 015052 Cola ext. lavamanos 1 ¼"x6", cromo u 148.00INBAÑ 150044 Ferret. Americ. 023194 Cola ext. fregadero 1 ½"x8", pvc u 62.00INBAÑ 150045 Ferret. Americ. 015029 Cola ext. fregadero 1 ½"x8", pvc, 10-8w u 23.93INBAÑ 150046 Ferret. Americ. 015828 Cubrefalta 3/8", cromo, HP323F D-382A u 6.88INBAÑ 150047 Ferret. Americ. 028014 Cubrefalta ½", cromo, HP323F D-382B u 7.12INBAÑ 150048 Ferret. Americ. 015826 Cubrefalta ¾", cromo u 21.98INBAÑ 150049 Ferret. Americ. 014829 Desagüe bañera, "Price Pfister", pvc u 2,302.99INBAÑ 150050 Ferret. Americ. 171351 Desagüe jacuzzi de cable, pvc u 2,778.00INBAÑ 150051 Ferret. Americ. 015469 Desagüe fregadero, 1 ½"x16, pvc, doble, 130-16 u 139.00INBAÑ 150052 Ferret. Americ. 235424 Dispensador papel sanit., gris, Jofel AE43000 u 1,570.35INBAÑ 150053 Ferret. Americ. 244246 Dispensador papel toalla, bco., Jofel AG16000 u 3,366.61INBAÑ 150054 Ferret. Americ. 235419 Dispensador papel toalla, gris, Jofel AG15000 u 3,675.17INBAÑ 150055 Ferret. Americ. 018779 Dosificador jabón líquido, bco., Jofel 400ML u 809.97INBAÑ 150056 Ferret. Americ. 257542 Dosificador jabón líquido, inox., Jofel AC21100 u 1,077.14INBAÑ 150057 Ferret. Americ. 025860 Ducha "Price Pfister", Ref. 413-0100, cromo u 869.00INBAÑ 150058 Ferret. Americ. 015070 Ducha plástica completa, cromo u 81.55INBAÑ 150059 Ferret. Americ. 066022 Fregadero sencillo p/bar, a. inox, 20"x21", sin mescl. y sin acces. u 1,381.91INBAÑ 150060 Ferret. Americ. 116623 Fregadero sencillo a. inox, 25"x22", sin mescl. y sin acces. u 1,614.43INBAÑ 150061 Ferret. Americ. 194331 Fregadero doble a. inox, 33"x22", sin mescl. y sin acces. u 1,316.89INBAÑ 150062 Ferret. Americ. 265428 Gabinete contra incendio, 1 ½" x 33 metros u 7,830.00INBAÑ 150063 Ferret. Americ. 254199 Gancho cromo sencillo "Tatay" 64230-6 u 358.15INBAÑ 150064 Ferret. Americ. 164960 Inodoro bco., alargado, tapa, sin acces, "Royal" u 4,796.48INBAÑ 150065 Ferret. Americ. 143237 Inodoro bco., tapa, sin acces, "Simplex" u 2,943.00INBAÑ 150066 Ferret. Americ. 143238 Inodoro color, tapa, sin acces, "Simplex" u 2,920.00INBAÑ 150067 Ferret. Americ. 143236 Inodoro bco., tapa, sin acces, "Taino" u 1,850.20INBAÑ 150068 Ferret. Americ. 196873 Inodoro color, alargado, tapa, sin acces, "Royal" u 6,431.01INBAÑ 150069 Ferret. Americ. 151716 Inodoro color, corriente, tapa, sin acces, "Azteca" u 3,786.29INBAÑ 150070 Ferret. Americ. 176476 Inodoro natural, silencioso, tapa, sin acces, "Ellisse natural" u 25,386.00INBAÑ 150071 Ferret. Americ. 137291 Inodoro natural, silencioso, tapa, sin acces, "Petit Garson" u 14,215.80INBAÑ 150072 Ferret. Americ. 008097 Inodoro fluxómetro bco., sin tapa, sin válvula, "Royal" u 3,814.02INBAÑ 150073 Ferret. Americ. 253783 Jabonera bañera, sin agarradera, cromo, corriente, Ref. 5759 u 249.01INBAÑ 150074 Ferret. Americ. 235306 Jabonera líquida, cromo, corriente (sin el jabón) u 464.00INBAÑ 150075 Ferret. Americ. 213528 Jabonera Nuva senc. cristal, Jofel cromo 9108-C u 2,688.88INBAÑ 150076 Ferret. Americ. 262393 Jabonera sencilla Clásica II, sup., cromo 208 u 353.00INBAÑ 150077 Ferret. Americ. 202021 Jacuzzi beige, acces. cromo, con bomba, "Cadenza" u 35,837.04INBAÑ 150078 Ferret. Americ. Juego baño 3 pzas color, sin acces. jgo 11,530.48INBAÑ 150079 Ferret. Americ. Juego baño 3 pzas, bco., sin acces. jgo 11,958.44INBAÑ 150080 Ferret. Americ. 015722 Junta de cera u 37.00INBAÑ 150081 Ferret. Americ. 197578 Lavamanos color, 19"x"17", sin mescl. y sin acces, "Embajador" u 1,601.99INBAÑ 150082 Ferret. Americ. 163190 Lavamanos Pedestal, color ovalado, sin mescl. y sin acces, "Royal" u 1,697.08INBAÑ 150083 Ferret. Americ. 008206 Lavamanos bco., 19"x"17", sin mescl. y sin acces, "Isabela" u 1,187.96INBAÑ 150084 Ferret. Americ. 128366 Lavamanos bco., pequeño, 1 hoyo, sin acces, "Simplex" u 719.99INBAÑ 150085 Ferret. Americ. 008188 Lavamanos ovalado color, 4" sin mescl. y sin acces, "Saona" u 2,302.60INBAÑ 150086 Ferret. Americ. 014997 Lavamanos ovalado bco., 8" sin mescl. y sin acces, "Saona" u 2,188.00INBAÑ 150087 Ferret. Americ. 185340 Llave angular ½" ó 3/8", "USA" u 165.00INBAÑ 150088 Ferret. Americ. 015280 Llave chorro ½", "Urrea" u 338.99INBAÑ 150089 Ferret. Americ. 015279 Llave chorro ¾", "Urrea" u 388.99INBAÑ 150090 Ferret. Americ. 015074 Llave empotrar de ½", cromo, "Urrea" u 482.40INBAÑ 150091 Ferret. Americ. 015067 Llave lavamanos peq., sencilla cromo, "Urrea" u 586.03INBAÑ 150092 Ferret. Americ. 165055 Manguera negra ¾" con tuercas, p/montar calentador u 292.32INBAÑ 150093 Ferret. Americ. 008062 Mezcl. baño, 1ra., desagüe, cromo, 01-311 "Bedford" u 4,794.58INBAÑ 150094 Ferret. Americ. 201804 Mezcl. baño, 3 puños, desagüe, "Sayco" u 3,611.00INBAÑ 150095 Ferret. Americ. 270989 Mezcl. baño Monom., Nuva, cromo HM211028C u 14,696.01INBAÑ 150096 Ferret. Americ. Mezcl. bidet, completa, monomando, "Salus" u 578.00

Page 5: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 3

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INBAÑ 150097 Ferret. Americ. Mezcl. freg. con manguera, H35-121 "Price Pfister" u 2,047.01INBAÑ 150098 Ferret. Americ. Mezcl. freg. Monom., cuello largo, cromo 034-1NCC "Price Pfister" u 3,746.00INBAÑ 150099 Ferret. Americ. 128016 Mezcl. Lavam., boquilla, "Sayco" u 1,760.00INBAÑ 150100 Ferret. Americ. 008061 Mezcl. Lavam., boquilla, 1ra., H43-128 "Bedford" u 2,969.00INBAÑ 150101 Ferret. Americ. 214012 Mezcl. Lavam. Cachera Albatros, 4", cromo HM15C u 3,339.00INBAÑ 150102 Ferret. Americ. 214057 Mezcl. Lavam. Nuva E2006, 8", cromo HL1531C u 5,446.20INBAÑ 150103 Ferret. Americ. 175628 Mescl. Orinal, Llave cromo completa u 555.59INBAÑ 150104 Ferret. Americ. 015851 Niple 3/8"x2 ½", cromo u 28.65INBAÑ 150105 Ferret. Americ. 007732 Orinal pequeño, bco., sin la llave "Simplex" Ozama 15510 u 2,420.60INBAÑ 150106 Ferret. Americ. 007626 Orinal ½ falda flux., , bco., sin llave y sin válvula "Yaque" u 9,784.00INBAÑ 150107 Ferret. Americ. Orinal falda entera, bco., sin llave y sin válvula "Eljer" u 9,092.20INBAÑ 150108 Ferret. Americ. 015835 Palometa doble alum., fijar lavamanos par 80.01INBAÑ 150109 Ferret. Americ. 262396 Papelera Clásica II, sup., cromo 215 u 1,522.00INBAÑ 150110 Ferret. Americ. 213530 Papelera Nuva sencillaI, sup., cromo 9117_C u 2,865.20INBAÑ 150111 Ferret. Americ. 253781 Porta papel de inodoro, cromo, superficie, Ref. 5756 u 406.00INBAÑ 150112 Ferret. Americ. 248018 Porta servilletas, bco., Jofel AH-31000 u 1,019.35INBAÑ 150113 Ferret. Americ. 235425 Porta servilletas, gris, Jofel AH-32000 u 1,060.12INBAÑ 150114 Ferret. Americ. 014897 Rejilla 3"x2" para piso, sencilla, cromo, HP350A R-407B u 68.32INBAÑ 150115 Ferret. Americ. 014894 Rejilla 4 5/8" para piso, aluminio u 28.65INBAÑ 150116 Ferret. Americ. 223231 Secador de manos Standard, bco., Jofel AA-11000 u 7,961.95INBAÑ 150117 Ferret. Americ. Borrar Sifón fregadero doble 1 ½", pvc u 134.68INBAÑ 150118 Ferret. Americ. 015503 Sifón fregadero sencillo 1 ½", pvc u 83.52INBAÑ 150119 Ferret. Americ. Sifón lavamanos, 1 ¼", cromo, completo, USA u 475.60INBAÑ 150120 Ferret. Americ. 015468 Sifón lavamanos, 1 ¼", cromo, completo, corriente 300-SN u 526.00INBAÑ 150121 Ferret. Americ. 015503 Sifón lavamanos, 1 ¼", pvc u 78.00INBAÑ 150122 Ferret. Americ. 015429 Tapa p/Cisterna, 27"x27", aluminio u 2,529.09INBAÑ 150123 Ferret. Americ. 015831 Tornillos p/bacineta, ¼"x2 ½", HP167 R-801AA jgo 13.70INBAÑ 150124 Ferret. Americ. 253785 Toallero 24" cromo, 5724 u 464.00INBAÑ 150125 Ferret. Americ. 040152 Toallero 24" cromo, corriente u 133.72INBAÑ 150126 Ferret. Americ. 213511 Toallero 24" sencillo Barra Elegance, cromo 8105 C u 3,002.00INBAÑ 150127 Ferret. Americ. 213531 Toallero 24" sencillo Barra Nuva, cromo 9105 C u 2,865.20INBAÑ 150128 Ferret. Americ. 213521 Toallero 24" Mult. Barra Elegance, cromo 8124 C u 5,005.40INBAÑ 150129 Ferret. Americ. 213532 Toallero 8 ½" Nuva, sencillo, cromo 9109_C u 1,465.66INBAÑ 150130 Ferret. Americ. 109733 Tubo flexible para lavamanos, tuerca, ½"x3/8" 40 cm., EVL-B40 u 125.23INBAÑ 150131 Ferret. Americ. 109735 Tubo flexible para inodoro, tuerca, 3/8"x7/8" 50 cm., EVS-B50 u 136.65INBAÑ 150132 Ferret. Americ. 028824 Tubo flexible para lavamanos, económico 1/2"x3/8"x20, P806-20 u 253.46INBAÑ 150133 Ferret. Americ. 014926 Válvula seg. p/calentador, bronce u 266.80INBAÑ 150134 Ferret. Americ. 015464 Válvula flux. ¾" para inodoro 402 NVB REXDELANY u 3,849.00INBAÑ 150135 Ferret. Americ. 015465 Válvula flux. ¾" para orinal, 451-NVB u 3,849.00

INBAR 170000 BARRO, PRODUCTOS:INBAR 170001 Alfarería Domin. BL2 Bloques de barro 4" u 29.00INBAR 170002 Alfarería Domin. BL3 Bloques de barro 6" u 33.11INBAR 170003 Alfarería Domin. BL4 Bloques de barro 8" u 39.00INBAR 170004 Alfarería Domin. CA2 Caballete triangular oscuro (3.5 caballetes en 1.00 metro) u 71.43INBAR 170005 Alfarería Domin. BL5 Calados corrientes de barro en 6"x6"x6" u 35.00INBAR 170006 Alfarería Domin. Calados corrientes de barro en 8"x8"x6" u 35.00INBAR 170007 Alfarería Domin. L01 Ladrillos macisos 2"x4"x8" u 12.50INBAR 170008 Alfarería Domin. L04 Ladrillos biscochos 2"x2"x8" (ya no lo fabrican) u 8.50INBAR 170009 Alfarería Domin. Losa de barro 8"x8"x1" m2 243.00INBAR 170010 Alfarería Domin. LO02 Losa de barro tipo FERIA grande (28 unid. en 1.00 metro) u 9.67INBAR 170011 Alfarería Domin. LO01 Losa de barro tipo FERIA pequeña (58 unid. en 1.00 metro) u 4.64INBAR 170012 Alfarería Domin. LO05 Losa de barro exagonal grande (ya no la fabrican) u 12.85INBAR 170013 Alfarería Domin. LO04 Losa de barro exagonal pequeña (50 unid. en 1.00 metro) u 5.41INBAR 170014 Alfarería Domin. T01 Teja criolla curva 16" x 7" (28 unid. en 1.00 metro) u 12.97INBAR 170015 Alfarería Domin. T02 Teja criolla curva 16" x 7", oscura (28 unid. en 1.00 metro) u 16.56INBAR 170016 Alfarería Domin. T09 Teja Francesa plana (ya no la fabrican) u 45.83INBAR 170017 Alfarería Domin. T10 Teja Francesa plana, oscura (ya no la fabrican) u 62.19INBAR 170018 Alfarería Domin. T13 Tejas tipo S", criolla (12 unid. en 1.00 metro) u 36.83INBAR 170019 Alfarería Domin. LO21 Zócalos de barro de 10 ½"x3" u 8.43INBAR 170020 Alfarería Domin. Transp. Mínimo Sto. Dgo. vje 458.20INBAR 170021 Alfarería Domin. Transp. Teja 16" 5,000 unid. Sto. Dgo. vje 2,692.36INBAR 170022 Alfarería Domin. Transp. Teja 16" al interior u 2.02

INBLC 190000 BLOQUES DE CEMENTO: (INDUSTRIAS AGUAYO 533-3161)INBLC 190001 Inudst. Aguayo Blintel 6"x8"x 8" liso, medio bloque u 30.10INBLC 190002 Indust. Aguayo Blintel 8"x8"x 8" liso, medio bloque u 37.51INBLC 190003 Indust. Aguayo Bloque 4"x8"x16" liso u 27.84INBLC 190004 Indust. Aguayo Bloque 5"x8"x16" liso u 28.42INBLC 190005 Indust. Aguayo Bloque 6"x8"x 8", liso (½ bloque 6") u 26.10INBLC 190006 Indust. Aguayo Bloque 6"x8"x16" liso u 26.10INBLC 190007 Indust. Aguayo Bloque 6"x8"x16", texturizado u 26.60INBLC 190008 Indust. Aguayo Bloque 8"x8"x 8", liso (½ bloque 8") u 32.00INBLC 190009 Indust. Aguayo Bloque 8"x8"x16" liso u 33.66INBLC 190010 Indust. Aguayo Bloque 8"x8"x16", texturizado u 32.54INBLC 190011 Indust. Aguayo Bloque 12"x8"x 8", liso (½ bloque 12") u 87.00INBLC 190012 Indust. Aguayo Bloque 12"x8"x16" liso u 100.60INBLC 190013 Indust. Aguayo Bloque calado 6"x8"x16" tipo persiana u 72.24INBLC 190014 Indust. Aguayo Bloque decorativo 6"x8"x16", gris, ranuras u 32.97INBLC 190015 Indust. Aguayo Bloque decorativo 8"x8"x16", gris, ranuras u 39.81INBLC 190016 Indust. Aguayo Bloviga 6"x8"x16" u 32.70INBLC 190017 Indust. Aguayo Bloviga 8"x8"x16" u 55.68INBLC 190018 Indust. Aguayo Transp. Bintel 6"x8"x 8", medio bloque u 1.08INBLC 190019 Indust. Aguayo Transp. Bintel 8"x8"x 8", medio bloque u 1.44INBLC 190020 Indust. Aguayo Transp. Bloque 4"x8"x16" u 1.44INBLC 190021 Indust. Aguayo Transp. Bloque 5"x8"x16" u 1.80INBLC 190022 Indust. Aguayo Transp. Bloque 6"x8"x 8", liso (½ bloque 6") u 1.08INBLC 190023 Indust. Aguayo Transp. Bloque 6"x8"x16" u 2.15

Page 6: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 4

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INBLC 190024 Indust. Aguayo Transp. Bloque 6"x8"x16", texturizado u 2.15INBLC 190025 Indust. Aguayo Transp. Bloque 8"x8"x 8", liso (½ bloque 8") u 1.44INBLC 190026 Indust. Aguayo Transp. Bloque 8"x8"x16" u 2.87INBLC 190027 Indust. Aguayo Transp. Bloque 8"x8"x16", texturizado u 2.87INBLC 190028 Indust. Aguayo Transp. Bloque 12"x8"x 8", liso (½ bloque 12") u 2.15INBLC 190029 Indust. Aguayo Transp. Bloque 12"x8"x16" u 4.31INBLC 190030 Indust. Aguayo Transp. Bloque calado 6" tipo persiana u 2.15INBLC 190031 Indust. Aguayo Transp. Bloque decorativo 6"x8"x16" u 2.15INBLC 190032 Indust. Aguayo Transp. Bloque decorativo 8"x8"x16" u 2.87INBLC 190033 Indust. Aguayo Transp. Bloviga 6"x8"x16" u 2.15INBLC 190034 Indust. Aguayo Transp. Bloviga 8"x8"x16" u 2.87INBLC 190035 Indust. Aguayo Transporte mínimo por viaje vje 1,508.00

INBLV 210000 BLOQUES DE VIDRIO:INBLV 210001 Ferret. Americ. 176204 Bloque de vidrio 20 x 20, clear lb 109.62

INBOM 230000 BOMBAS DE AGUA Y TANQUES DE PRESION :INBOM 230001 Ferret. Americ. 010914 Bomba ½ HP, "Myers" 110/220 v, HR50S, sin tanque u 6,904.00INBOM 230002 Ferret. Americ. 010942 Bomba ¾ HP, "Myers" 110/220 v, HJ75S, sin tanque u 7,135.00INBOM 230003 Ferret. Americ. 035996 Bomba 1 HP, "Myers" 110/220 v, sin tanque u 10,058.23INBOM 230004 Ferret. Americ. 034994 Bomba 5 HP, "Myers" 230 v 1PH,200M-5FA, sin tanque u 40,403.00INBOM 230005 Ferret. Americ. Bomba sumerg. 1 HP, "Myers" 3ST102-20 + caja control u 17,981.00INBOM 230006 Ferret. Americ. 034919 Bomba sumerg. 1 HP, "Myers" 3ST102-20 sin caja control u 16,116.00INBOM 230007 Ferret. Americ. Bomba sumerg. 1 ½ HP, "Myers" 3ST152-20 + caja control u 28,384.99INBOM 230008 Ferret. Americ. 034914 Bomba sumerg. 1 ½ HP, "Myers" 3ST152-20 sin caja control u 26,000.00INBOM 230009 Ferret. Americ. Bomba sumerg. 2 HP, "Myers" J2025B/SS20-25 + caja control u 19,250.00INBOM 230010 Ferret. Americ. 155863 Bomba sumerg. 2 HP, "Myers" J2025B/SS20-25 sin caja control u 15,912.00INBOM 230011 Ferret. Americ. Bomba sumerg. 5 HP, "Myers" J5050B/SS50-50 + caja control u 38,470.00INBOM 230012 Ferret. Americ. 155865 Bomba sumerg. 5 HP, "Myers" J5050B/SS50-50 sin caja control u 31,620.00INBOM 230013 Ferret. Americ. 034962 Caja control 1 "Myers" HP SMC-CR1021 u 1,865.00INBOM 230014 Ferret. Americ. 034966 Caja control 1 1/2HP "Myers" SMC-CR1521 u 2,384.99INBOM 230015 Ferret. Americ. 005374 Caja control 2HP M-CJ20-21 u 3,338.00INBOM 230016 Ferret. Americ. 005371 Caja control 5HP M-CJ50-21 u 6,850.00INBOM 230017 Ferret. Americ. 123967 Tanque hidr. 42 gls., criollo, fibra, Economax u 3,650.00INBOM 230018 Ferret. Americ. 012288 Tanque hidr. 42 gls., USA, "Well-x-Troll" "WX-202P" u 6,364.99INBOM 230019 Ferret. Americ. 123969 Tanque hidr. 82 gls., criollo, fibra, Economax u 7,314.99INBOM 230020 Ferret. Americ. 147763 Tanque hidr. 82 gls., USA, "Well-x-Troll" "WX-203P" u 10,195.74INBOM 230021 Ferret. Americ. 177402 Tanque hidr. 120 gls., criollo, fibra, Economax u 11,209.98INBOM 230022 Ferret. Americ. 144854 Tanque hidr. 120 gls., USA, "Well-x-Troll" "WX-250P" u 13,800.00INBOM 230023 Ferret. Americ. 131849 Tanque hidr. 180 gls., USA, "Well-x-Troll" "WX-302P" u 17,575.00

INCEM 250000 CEMENTOS, CAL, ADITIVOS, CURADORES, ENDURECEDORES, SELLADORES:INCEM 250001 Vinaldom Aditivo impermeabilizante "SX-PEL", 5 gl. gl 304.50INCEM 250002 Vinaldom Aditivo retardante "SX-KRETE-R", 5 gl. gl 304.50INCEM 250003 Ferret. Americ. 052396 Cal "Perla-Pomier" económica o similar (20 Kilos) fda 285.00INCEM 250004 Ferret. Americ. 052388 Cemento Bco. (40 kilos) fda 600.00INCEM 250005 Ferret. Americ. 080496 Cemento Gris "Portland", a crédito, incluye transporte fda 250.00INCEM 250006 Vinaldom Curador-sellador "SUPRACURE PLUS", 1 gl., 20 m2/gl. gl 894.00INCEM 250007 Vinaldom Endur. Met. / pisos "DURAPLATE NR", 100 lb., .10 m2/lb., Fda.=55 lb. fda 2,233.00INCEM 250008 Hache Mezcla "Antillana" normal para bloques, 94 lb. fda 187.95INCEM 250009 Ferret. Americ. 207403 Mezcla "Antillana" para empañete, 94 lb., para 2 m2 fda 208.80INCEM 250010 Vinaldom Resina epóxica "Pro-flex" para junta de piso, 231 pulg.3/gl. 3 gl 3,329.50INCEM 250011 Vinaldom Sellador hormigón visto "SUPRACURE PX", 1gl., 20 m2/gl. gl 713.98

INCER 270000 CERAMICAS:INCER 270001 Cerámica criolla tipo 01 m2 353.03INCER 270002 Cerámica criolla tipo 02 m2 382.45INCER 270003 Cerámica criolla tipo 03 m2 411.88INCER 270004 Cerámica criolla tipo 04 m2 470.72INCER 270005 Cerámica criolla tipo 05 m2 588.40INCER 270006 Cerámica importada tipo 06 m2 647.23INCER 270007 Cerámica importada tipo 07 m2 764.92INCER 270008 Cerámica importada tipo 08 m2 882.59INCER 270009 Cerámica importada tipo 09 m2 1,000.27INCER 270010 Cerámica importada tipo 10 m2 1,088.53INCER 270011 Cerámica importada tipo 11 m2 1,176.79INCER 270012 Cerámica importada tipo 12 m2 1,294.47INCER 270013 Corte de chazos de cerámica u 7.05INCER 270014 Derretido (rinde 25 m2/fda.) fda 417.81INCER 270015 Ferret. Americ. 023936 Estopa lb 63.80INCER 270016 Listelo 8x20, import., serie Trama u 129.44INCER 270017 Pegamento K18 (rinde 6.5 m2/fda.) fda 500.13INCER 270018 Perfil esquinero PVC, 2.5 m. u 176.52INCER 270019 Zócalo cerámica 8x34, import. u 58.85

INCEJ 290000 CERRAJERIA:INCEJ 290001 Ferret. Americ. 009555 Arandela plana ½" lb 90.36INCEJ 290002 Ferret. Americ. 145468 Bisagras ''Stanley'' 2 ½''x2 ½'', tipo libro, doradas par 58.00INCEJ 290003 Ferret. Americ. 009974 Bisagras ''Stanley'' 3''x3'', tipo libro, doradas par 61.48INCEJ 290004 Ferret. Americ. 009975 Bisagras "Stanley" 3 ½"x3 ½", tipo libro, doradas 82-100 par 69.60INCEJ 290005 Ferret. Americ. 009976 Bisagras ''Stanley'' 4''x4'', tipo libro, doradas par 104.40INCEJ 290006 Ferret. Americ. 051815 Bisagra "Vaivén" de piso, Spartan u 523.45INCEJ 290007 Ferret. Americ. 023100 Cable de acero 3/8" (10 mm) con forro, 7x19 pie 25.35INCEJ 290008 Ferret. Americ. 036949 Cadena galv. 5/16" (8mm) pie 40.22INCEJ 290009 Ferret. Americ. 008410 Candado 50 mm "Corbin". u 495.90INCEJ 290010 Ferret. Americ. 260646 Diferencial eléctrico 2SS-1G-15 151067, 2,000 kilos u 118,749.99INCEJ 290011 Ferret. Americ. Falleba 3/8" x 9", cromo u 119.00INCEJ 290012 Ferret. Americ. Falleba 3/8" x 12", cromo u 127.99

Page 7: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 5

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INCEJ 290013 Ferret. Americ. 045301 Hoja de segueta "Roja" u 35.26INCEJ 290014 Ferret. Americ. 161135 Llavín corriente, doble puño, llave y seguro, "Yale" u 484.88INCEJ 290015 Ferret. Americ. 248090 Llavín de calidad, doble puño, llave y seguro, ref. 640, "Weslock" CLS-NS u 1,388.52INCEJ 290016 Ferret. Americ. 038596 Llavín de seguridad "Yale" Der c/f 63000401 (630.40) u 1,267.30INCEJ 290017 Ferret. Americ. 124642 Pestillo 60 MM corriente u 28.65INCEJ 290018 Ferret. Americ. 145483 Pestillo de cadena st. 4" 75-7030 u 352.64INCEJ 290019 Ferret. Americ. 004027 Portacandado 4" corriente u 24.24INCEJ 290020 Ferret. Americ. 054375 Tarugo de plomo ½" u 7.98INCEJ 290021 Ferret. Americ. 019544 Tarugos plásticos 1/4"x1", verde u 0.50INCEJ 290022 Ferret. Americ. 028399 Tarugos plásticos 3/8"x2 ½", mamey u 1.50INCEJ 290023 Ferret. Americ. 128962 Tensor zincado anilla-anilla TAA110 u 2.03INCEJ 290024 Ferret. Americ. 023955 Tornillos 3"x16 u 3.20INCEJ 290025 Ferret. Americ. 009674 Tornillos 3"x3/8" electro galv. Cabeza exagonal u 9.42INCEJ 290026 Ferret. Americ. 009629 Tornillo cabeza exag. ½"x4" u 22.04INCEJ 290027 Ferret. Americ. 013576 Tornillo de ojo 3/8"x4", c/tuerca u 22.04INCEJ 290028 Ferret. Americ. 009421 Tornillo tirafondo 1 ½"x14, estriado u 1.65

INCOM 310000 COMBUSTIBLES Y LUBRICANTES:INCOM 310001 Gasoil Premium gl 138.20INCOM 310002 Gasoil regular gl 133.20INCOM 310003 Gasolina Premium gl 167.80INCOM 310004 Gasolina regular gl 158.30INCOM 310005 Ferret. Americ. 116898 Lubricantes Aceite Citgo Supergard Sae 40, 1/4 gl. 1/4 gl 184.00

INDIV 330000 DIVISAS:INDIV 330001 Divisa USA, US$1.00 comprado en el mercado local $ 36.85INDIV 330002 EURO$1.00 comprado en el mercado local $ 48.45

INEBA 350000 EBANISTERIA:INEBA 350001 Ferret. Americ. 145445 Barra p/armario, zinc St. 18"-30" u 198.36INEBA 350002 Ferret. Americ. 145446 Barra p/armario, zinc St. 30"-48" u 225.91INEBA 350003 Ferret. Americ. 246459 Barra p/armario, zinc St. 48"-72" u 253.46INEBA 350004 Ferret. Americ. 145449 Barra p/armario, zinc St. 72"-96" u 402.23INEBA 350005 Ferret. Americ. Clavos de acero 1½", caja con 100 unidades caja 35.00INEBA 350006 Ferret. Americ. Cola amarilla para madera gl 350.00INEBA 350007 Cortar y preparar media caña 1"x1", hasta 0.50 m2 por tramo u 39.44INEBA 350008 Cortar y preparar tramos p/closets, hasta 0.50 m2 por tramo u 39.44INEBA 350009 Gabinete pared en Caoba, 2 pie de alto, ¾" p 2,700.00INEBA 350010 Gabinete pared en Caoba y "Plywood", 2 pie de alto, ¾" p 1,760.00INEBA 350011 Gabinete pared en Pino p 1,050.00INEBA 350012 Gabinete pared en Pino y "Plywood" p 875.00INEBA 350013 Gabinete piso en Caoba p 2,940.00INEBA 350014 Gabinete piso en Caoba y "Plywood" p 1,940.00INEBA 350015 Gabinete piso en Pino p 1,290.00INEBA 350016 Gabinete piso en Pino y "Plywood" p 1,050.00INEBA 350017 Instalar tramos de closets, hasta 0.50 m2 por tramo u 134.56INEBA 350018 Marco en caoba 1 ½"x4" p 136.00INEBA 350019 Marco en pino 1 ½"x4" p 44.00INEBA 350019 Pintar con sellador tramos closets, hasta 0.50 m2 por tramo u 106.72INEBA 350020 Puerta Caoba panelada especial p2 575.00INEBA 350021 Puerta Caoba panelada sencilla p2 528.00INEBA 350022 Puerta Caoba tipo francesa p2 550.00INEBA 350023 Puerta "Plywood" 3/16" p2 85.00INEBA 350024 Puerta Pino panelada p2 154.00INEBA 350025 Puerta Pino con marco, hueco .80 X 2.10 m., 2 paneles (medida fija) u 2,225.00INEBA 350026 Puerta Pino con marco, hueco .80 X 2.10 m., 4-6 paneles (medida fija) u 2,640.00INEBA 350027 Puerta Plegable sin marco, color caoba o bco., hueco: 0.865 x 2.03 m., cristales u 2,760.00INEBA 350028 Tope marmolite, Sánchez 547-8920, Cel. 330-3872 p2 232.00INEBA 350029 Transporte mínimo en camioneta desde taller a obra u 638.00

INELL 370000 ELECTRICIDAD (LAMPARAS Y GLOBOS):INELL 370001 Ferret. Americ. 217302 Globo 6", cristal u 278.01INELL 370002 Ferret. Americ. 197037 Base p/globo, blanca u 180.88INELL 370003 Ferret. Americ. 122753 Lámpara flluor. 2'x2', p/plafón, dif. Parabólico, sin tubos u 3,915.00INELL 370004 Ferret. Americ. 224839 Lámpara flluor. 2'x4', p/plafón, dif. Parabólico, sin tubos u 3,480.00INELL 370005 Ferret. Americ. 202215 Lámpara flluor. 2'x4', p/plafón, sin tubos u 2,850.12INELL 370006 Ferret. Americ. Lámpara fluor. 2x32 w., superficie, difusor transp., "Stanca" u 1,097.00INELL 370007 Ferret. Americ. Ojos de buey halógeno", aluminio, para plafón u 504.39INELL 370008 Ferret. Americ. 005561 Tubo fluorescente 4', 40 w., 2 patas u 48.72

INELR 390000 ELECTRICIDAD RESIDENCIAL (MATERIALES):INELR 390001 Ferret. Americ. 002291 Abrazadera ¾" h.g. para pvc u 14.56INELR 390002 Ferret. Americ. 002292 Abrazadera 1" h.g. para pvc u 21.00INELR 390003 Ferret. Americ. 002302 Abrazadera 1½" EMT u 12.06INELR 390004 Ferret. Americ. 002303 Abrazadera 2" h.g. para pvc u 26.49INELR 390005 Ferret. Americ. 002313 Abrazadera 3" h.g. para pvc u 98.60INELR 390006 Ferret. Americ. 032933 Alambre THHW-/THHN # 1/0, Str. p 69.60INELR 390007 Ferret. Americ. 032934 Alambre THHW-/THHN # 2/0, Str. p 91.06INELR 390008 Ferret. Americ. 032935 Alambre THHW-/THHN # 3/0, Str. p 108.55INELR 390009 Ferret. Americ. 032936 Alambre THHW-/THHN # 4/0, Str. p 146.16INELR 390010 Ferret. Americ. 309324 Alambre THHW-/THHN # 2, Str. p 45.32INELR 390011 Ferret. Americ. 309328 Alambre THHW-/THHN # 4, Str. p 29.30INELR 390012 Ferret. Americ. 302759 Alambre THHW-/THHN # 6, Str. p 18.40INELR 390013 Ferret. Americ. 302768 Alambre THHW-/THHN # 8, Str. p 11.77INELR 390014 Ferret. Americ. 302769 Alambre THHW-/THHN #10, Str., bco. p 7.34INELR 390015 Ferret. Americ. 302774 Alambre THHW-/THHN #12, Str., bco. p 4.65INELR 390016 Ferret. Americ. 302783 Alambre THHW-/THHN #14, Str. p 3.12INELR 390017 Ferret. Americ. 040866 Alambre duplo #18, Str. p 3.03

Page 8: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 6

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INELR 390018 Ferret. Americ. 001834 Bombillo incandescente, 60 w. (2 unid.) u 75.01INELR 390019 Ferret. Americ. 255735 Botón timbre "Bticino" u 136.17INELR 390020 Ferret. Americ. 005465 Breakers 15 - 30 amp, 1 ph , GE u 133.40INELR 390021 Ferret. Americ. 005502 Breakers 40 amp, 2ph, doble, GE u 330.60INELR 390022 Ferret. Americ. 005515 Breakers 60 amp, 2ph, doble, GE u 377.00INELR 390023 Ferret. Americ. 077932 Caja octagonal de ½-¾", americana u 32.48INELR 390024 Ferret. Americ. 000949 Caja metal 2"x4" de ½", americana u 40.50INELR 390025 Ferret. Americ. 000948 Caja metal 2"x4" de ¾", americana u 31.32INELR 390026 Ferret. Americ. 077931 Caja metal 4"x4" de ½-¾", americana u 52.00INELR 390027 Ferret. Americ. 103937 Cinta de peligro, rollo 3"x1000' u 319.00INELR 390028 Ferret. Americ. 005555 Codo pvc eléct. ½" x 90º u 4.58INELR 390029 Ferret. Americ. 005554 Codo pvc eléct. ¾" x 90º u 5.75INELR 390030 Ferret. Americ. 005551 Codo pvc eléct. 1" x 90º u 10.75INELR 390031 Ferret. Americ. 005553 Codo pvc eléct. 1 ½" x 90º u 27.84INELR 390032 Ferret. Americ. 005552 Codo pvc eléct. 2" x 90º u 31.32INELR 390033 Ferret. Americ. 005550 Codo pvc eléct. 3" x 90º u 126.00INELR 390034 Ferret. Americ. 005549 Codo pvc eléct. 4" x 90º u 200.10INELR 390035 Ferret. Americ. 000965 Condulet ¾" u 103.00INELR 390036 Ferret. Americ. 000966 Condulet 1" u 141.00INELR 390037 Ferret. Americ. 000980 Condulet 1½" u 226.00INELR 390038 Ferret. Americ. 000981 Condulet 2" u 299.00INELR 390039 Ferret. Americ. 000993 Condulet 3" u 1,736.00INELR 390040 Ferret. Americ. 000994 Condulet 4" u 707.00INELR 390041 Ferret. Americ. 006173 Conector 5/8" para varilla de tierra u 58.00INELR 390042 Ferret. Americ. 006220 Interruptor 1 sencillo, sin tapa, "Leviton" 1451-ICP u 33.78INELR 390043 Ferret. Americ. 006221 Interruptor 2 doble, sin tapa, "Leviton" u 121.29INELR 390044 Ferret. Americ. 047737 Interruptor 2 doble, sin tapa, "Bticino", Modus 1200MM u 94.77INELR 390045 Ferret. Americ. 231942 Interruptor 3 triple, sin tapa, "Bticino", Modus plus 1313MM u 144.33INELR 390046 Ferret. Americ. 231938 Interruptor 3 vías, sencillo "Bticino", Modus plus 1101MAB u 70.12INELR 390047 Ferret. Americ. 129478 Interruptor 4 vías, sencillo sin tapa, "Leviton" 1204-2w u 343.50INELR 390048 Ferret. Americ. 006194 Interruptor piloto crema, sin tapa, "Leviton" 5226-I u 158.72INELR 390049 Ferret. Americ. 000934 Interruptor seg. 30 a, 2 polos, 250 v., GE u 1,767.00INELR 390050 Ferret. Americ. 000924 Interruptor seg. 30 a, 3 polos, 250 v., GE u 1,584.00INELR 390051 Ferret. Americ. 000934 Interruptor seg. 60 a, 2 polos, 250 v., GE u 1,767.00INELR 390052 Ferret. Americ. 000944 Interruptor seg. 100 a, 2 polos 250 v., GE u 3,594.00INELR 390053 Ferret. Americ. Motor eléctrico para portón corredizo, ame" 800 Kg. u 29,768.00INELR 390054 Ferret. Americ. Panel contador ELECTRO, "breakers" 60 amp., 2 ph. u 1,706.00INELR 390055 Ferret. Americ. Panel contador ELECTRO, "breakers" 100 amp., 2 ph. u 2,635.89INELR 390056 Ferret. Americ. 002282 Panel distrib. 1 ph, 2 a 4 ctos., 40 amp. u 411.80INELR 390057 Ferret. Americ. 002304 Panel distrib. 1 ph, 4 a 8 ctos., 125 amp. u 527.80INELR 390058 Ferret. Americ. 002315 Panel distrib. 1 ph, 6 a 12 ctos., 125 amp. u 1,121.00INELR 390059 Ferret. Americ. 002324 Panel distrib. 1 ph, 8 a 16 ctos., 125 amp. u 1,238.00INELR 390060 Ferret. Americ. 002341 Panel distrib. 1 ph, 12 a 24 ctos., 125 amp. u 1,780.60INELR 390061 Ferret. Americ. Panel distrib. 3 ph, 30 espacios, 150 amp. u 5,963.00INELR 390062 Ferret. Americ. Portero electrónico "Bticino" (Kit video de 2 piezas) u 18,733.01INELR 390063 Ferret. Americ. 077931 Registro 4"x4", ko ½" - ¾", galv. USA u 52.00INELR 390064 Ferret. Americ. Registro 5"x5", ko 1 ¼", galv. USA u 98.00INELR 390065 Ferret. Americ. 001852 Registro 6"x6"x4", galv. criollo u 99.76INELR 390066 Ferret. Americ. 224939 Registro 8"x8"x4", galv. criollo u 385.00INELR 390067 Ferret. Americ. 001934 Registro 10"x10"x4", galv. criollo u 274.92INELR 390068 Ferret. Americ. 002072 Registro 12"x12"x4", galv. criollo u 399.04INELR 390069 Ferret. Americ. CAJRN124246 Registro 24"x24"x4", galv. criollo p 2,693.26INELR 390070 Ferret. Americ. Registro 24"x24"x6", galv. criollo p 2,693.26INELR 390071 Ferret. Americ. 006369 Roseta "Leviton" 9875, porcelana americana u 34.68INELR 390072 Ferret. Americ. Sistema Intercom vía telefónica, micro cámara 1/4" "Quaddrix" u 69,024.42INELR 390073 Ferret. Americ. Tapa 2"x4" ciega ko ½", metálica. u 15.31INELR 390074 Ferret. Americ. 105583 Tapa 2"x4" ciega o para interruptor, crema "Leviton" PVC. u 16.18INELR 390075 Ferret. Americ. 006417 Tapa 2"x4" ciega o para tomacorriente, crema "Leviton" PVC. u 14.24INELR 390076 Ferret. Americ. 001001 Tapa 2"x4" para tomacorriente, metálica. u 14.76INELR 390077 Ferret. Americ. 000802 Tape vinyl ''3M'', No. 23, ¾" u 527.80INELR 390078 Ferret. Americ. 000800 Tape vinyl "3M", super 33T u 157.76INELR 390079 Ferret. Americ. Tarugo plastico ¼" x 1" c/perno tirafondo u 10.95INELR 390080 Ferret. Americ. 041488 Timbre "Bticino" 73Z, "Din-Don" u 603.20INELR 390081 Ferret. Americ. 235736 Timbre corriente, tipo chicharra u 414.12INELR 390082 Ferret. Americ. 120469 Tomacorriente doble, 110 v., 15 A., de piso u 696.00INELR 390083 Ferret. Americ. 006218 Tomacorriente doble, 110 v., 15 A. "Leviton" 5320-ICP u 24.59INELR 390084 Ferret. Americ. 006243 Tomacorriente sencillo, 220 v., 15 A., "Leviton" 5029-I u 70.83INELR 370009 Ferret. Americ. 005525 Varilla de puesta a tierra, 5/8" x 6' sin Conector u 475.60

INELA 410000 ELECTRICIDAD ALTA TENSION (MATERIALES):INELA 410001 THW-URD/1/3CON Alambre URD No. 2, 33% neutro, concéntrico p 116.79INELA 410002 THQL2160 Breakers 2/p. 60 a., grueso, GE 1/5 u 448.39INELA 410003 THQL32040 Breakers 3/p. 40 a., GE u 1,609.20INELA 410004 THQL32060 Breakers 3/p. 60 a., GE 1/3 u 1,609.20INELA 410005 TQD22100WL Breakers Industrial 2 ph 100 amp., 240 v., GE, 1/1 u 2,135.15INELA 410006 TEB132100WL Breakers Industrial 3 ph 100 amp., 240 v., GE, 1/1 u 3,594.89INELA 410007 TJD432500WL Breakers Industrial 3 ph 500 amp., 240 v., GE, 1/1 u 30,460.86INELA 410008 E68 Codo 3" IMC, galvanizado 1/1 u 1,877.60INELA 410009 E70 Codo 4" IMC, galvanizado 1/1 u 3,290.84INELA 410010 QTII5601 Cono de alivio exterior #2 u 2,128.70INELA 410011 E695 Conector empalme #2, Topaz (Split B 1/25) u 77.85INELA 410012 STR # 3/0 Conector empalme #3/0 1/25 u 248.47INELA 410013 E693 Conector empalme #4, Topaz (Split 1/25) u 48.40INELA 410014 RKS17 Conector p/empalme #6AWG Split Volt) 1/25 u 53.20INELA 410015 STR # 8 Conector p/empalme #8 1/100 u 12.76INELA 410016 9U01AAD633 Conector URD #2, T/codo 90r 1/1 u 1,886.72INELA 410017 TOP-60 Coupling IMC 4", galvanizado 1/4 u 503.56INELA 410018 279C601A12 Cut Out 200 a., 15 kv ABB 1/1 u 4,259.64

Page 9: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 7

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INELA 410019 279C601A12 Elbow Conector u 1,465.58INELA 410020 ESP2 Espiga p/Terminación #2, 10' Ext. 1/5 u 680.32INELA 410021 SHB8K23 Fusible tipo cartucho, 8 amp., 1/25 u 74.47INELA 410022 Grúa, alquiler hr 4,285.33INELA 410023 Módulo contador, 22 zóc., 500/3 a.,208 v., 1 zóc. 100/3, 21 zóc. 100/2 u 140,558.82INELA 410024 217259-7224 Pararrayo polimérico 9 KV HUBBELL u 1,743.71INELA 410025 Piezas p/soporte estructura mediana tensión u 2,203.88INELA 410026 N-1945 Soporte simple unidad Cutout/Pararrayo CL u 1,102.58INELA 410027 Transformador 150 kva, Pad Mounted, 7200, 120/204/240 v. u 296,960.00INELA 410028 Transformador 225 kva, Pad Mounted, 7200, 120/204/240 v. u 336,400.00INELA 410029 E5208 Tubería 3"x10', BX 1/25 p 191.26INELA 410030 IMC400 Tubería 4"x10', BX u 4,628.67INELA 410031 LT 3 Tubería 3", Liquid Tight p 466.76INELA 410032 LT 4 Tubería 4", Liquid Tight pINELA 410033 IMC400 Tubo 4"x10' IMC, galvanizado 1/1 u 4,628.67

INEQU 430000 EQUIPOS DE CONSTRUCCION:INEQU 430001 Ferret. Americ. 101065 Cabo para zapapico, natural, 33", Ref. 1556/94 1565/94 u 197.20INEQU 430002 Ferret. Americ. 275080 Carretilla metal "Jeep", "Surtek", 5.5 p3, Mexicana u 2,175.00INEQU 430003 Ferret. Americ. 032819 Cincel criollo largo, c/punta u 116.00INEQU 430004 Ferret. Americ. 227655 Cincel criollo largo, plano u 154.28INEQU 430005 Ferret. Americ. 006062 Cubeta plástica 5 gl., con tapa, para agua u 246.00INEQU 430006 Ferret. Americ. Cubo de goma #8 u 161.00INEQU 430007 Ferret. Americ. 001361 Cubo de goma #10 u 139.20INEQU 430008 Ferret. Americ. Escoba plástica para hojas, 16" u 139.00INEQU 430009 Ferret. Americ. Hilo de "nylon" No. 8, (1 lbr) u 139.58INEQU 430010 Ferret. Americ. 205965 Ligadora hidráulica, 2 fundas u 113,899.99INEQU 430011 Ferret. Americ. 061941 Mandarria "Stanley" 2 lb., Ref. 6456-399 u 325.09INEQU 430012 Ferret. Americ. 075482 Manguera reforzada p/jardín ¾" x 75' u 1,179.14INEQU 430013 Ferret. Americ. 001359 Pala cuadrada "Tramontina", Ref. 77472/424 u 220.40INEQU 430014 Ferret. Americ. 123972 Pala redonda "Tramontina", Ref. 77470/424 u 185.60INEQU 430015 Ferret. Americ. 123968 Rastrillo para piedras, 14 dientes, USA u 192.85INEQU 430016 Ferret. Americ. Tanque plástico de 55 gl., para agua u 436.18INEQU 430017 Ferret. Americ. 001366 Zapapico "Tramontina", 5 lb., sin cabo, Ref. 77303/503, 5 lb. u 319.00INEQU 430018 Ferret. Americ. Winche (elevador) 2,000 kilos u 265,152.16

INESC 450000 ESCALONES Y MESETAS GRANITO: (Precios sin ITBIS)INESC 450001 H. y C. H., 2 y 3, fondo bco., 0.34x1.10 m. + 0.17x1.10 m. + Transp. u 928.00INESC 450002 H. y C. H., Granimármol, 0.34x1.10 m. + 0.17x1.10 m. + Transp. u 928.00INESC 450003 H. y C. H., Mármol aglom., Perlatto Royal, 0.34x1.10 m. + 0.17x1.10 m. + Transp. u 1,044.00INESC 450004 H. y C. H. super chapa, fondo bco. + Transp. m 1,740.00INESC 450005 Meseta, 2 y 3, fondo bco. + Transp. m2 2,088.00INESC 450006 Meseta Granito super chapa, fondo bco. + Transp. m2 1,740.00INESC 450007 Transporte lavadero doble (12 unid. Mínimo) u 116.00INESC 450008 Transporte lavadero sencillo (20 unid. Mínimo) u 58.00INESC 450009 Transporte por viaje vje 1,160.00INESC 450010 Transporte Vertedero (20 unid. Mínimo) u 58.00INESC 450011 Zócalo escalón, 2 y 3, bco. + Transp. p 185.60INESC 450012 Zócalo escalón, Super Chapa + Transp. p 203.00

INEST 470000 ESTRUCTURA METALICA Y PUERTA ENROLLABLE:INEST 470001 Acero Estrella Bajantes pluviales en aluzinc m 651.11INEST 470002 Acero Estrella Caballete p/aluzinc 8'x14" m2 223.07INEST 470003 Acero Estrella Caballete p/aluzinc 8'x21" m2 297.31INEST 470004 Acero Estrella Caballete p/aluzinc 8'x24" m2 372.48INEST 470005 Acero Estrella Correa metálica 2"x6"x1/16" galv. m2 866.52INEST 470006 Acero Estrella Correa metálica 3"x8"x1/16" galv. m2 1,056.76INEST 470007 Acero Estrella Colectores pluviales en aluzinc m 770.59INEST 470008 Acero Estrella Cubierta "Aluzinc", calibre 26 (m2) m2 1,655.32INEST 470009 Acero Estrella Cubierta "Aluzinc", calibre 26 (pie2) p2 153.82INEST 470010 Acero Estrella m2 11,741.84INEST 470011 Acero Estrella Planchas traslúcidas de 11 pies u 3,841.78INEST 470012 Acero Estrella Puerta Enrollable (hueco: 3.00 ancho x 2.70 m. alto = 8.10 m2) m2 7,054.23INEST 470013 Innovación Ventilador eólico 18" galv. (turbina circular) u 10,039.92

INHER 490000 HERRERIA:INHER 490001 Ml. Fdez. Glez. Angular ½"x1/8"x20' u 968.99INHER 490002 Ml. Fdez. Glez. Angular ½"x3/16"x20' u 1,418.00INHER 490003 Ferret. Americ. 044732 Angular ¾"x1/8"x20' u 278.40INHER 490004 Ml. Fdez. Glez. Angular ¾"x3/16"x20' u 1,416.70INHER 490005 Ferret. Americ. 044733 Angular 1"x1/8"x20' u 319.00INHER 490006 Ferret. Americ. Angular 1"x¼"x20' u 1,070.32INHER 490007 Ferret. Americ. 044741 Angular 1 ½"x¼"x20' u 1,479.00INHER 490008 Ferret. Americ. 044744 Angular 2"x¼"x20' u 1,650.00INHER 490009 Ferret. Americ. 044747 Angular 2 ½"x¼"x20' u 2,001.00INHER 490010 Ferret. Americ. 044750 Angular 3"x¼"x20' u 1,682.00INHER 490011 Ferret. Americ. 044852 Barras cuadradas ½"x20' u 336.54INHER 490012 Ferret. Americ. 044853 Barras cuadradas 5/8"x20' u 527.10INHER 490013 Ferret. Americ. 044854 Barras cuadradas ¾"x20' u 754.31INHER 490014 Ferret. Americ. 199180 Barrote forjado 11 1/2"x39", P-1417 u 1,150.00INHER 490015 Ferret. Americ. 202593 Empalme forjado cuadr. 1/2", 219 u 17.75INHER 490016 Ferret. Americ. 202595 Empalme forjado redondo 1/2", Q-19 u 22.01INHER 490017 Ferret. Americ. 055398 Malla tipo piñonate, 4' x 8' de 3/8" u 968.31INHER 490018 Ferret. Americ. 044690 Planchuela ½"x1/8"x20' u 69.60INHER 490019 Ferret. Americ. 044691 Planchuela ½"x3/16"x20' u 92.80INHER 490020 Ferret. Americ. 044694 Planchuela ¾"x3/16"x20' u 251.78INHER 490021 Ml. Fdez. Glez. Planchuela ¾"x¼"x20' u 3,756.00INHER 490022 Ferret. Americ. 044709 Planchuela 1 ½"x¼"x20' u 747.01

Estruct. (col., vigas, correas 3"x8", cub.) ancho 15, x 24 m. fondo, Alto=7.65m Pend.=15% Area Cub. 374.40 m2

Page 10: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 8

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INHER 490023 Ferret. Americ. 044714 Planchuela 2"x¼"x20' u 896.15INHER 490024 Ferret. Americ. 044720 Planchuela 3"x¼"x20' u 951.20INHER 490025 Ferret. Americ. Planchuela 4"x¼"x20' u 2,098.94INHER 490026 Rejas livianas, diseño sencillo p2 220.40INHER 490027 Rejas reforzadas, diseño sencillo p2 353.80INHER 490028 Ferret. Americ. 199162 Roseta forjada 10", RO-1620 u 524.00INHER 490029 Ferret. Americ. 199160 Roseta forjada 15", RO-1610 u 821.00INHER 490030 Ferret. Americ. 047609 Rueda para portón corredizo, tipo caja de bola 3" u 264.48INHER 490031 Ferret. Americ. 008573 Soldadura Universal lb 28.03INHER 490032 Ferret. Americ. 202617 Terminal forjado cuadr. 1/2", 215 u 12.25INHER 490033 Ferret. Americ. Terminal forjado cuadr. 1/2", 217 u 10.50INHER 490034 Ferret. Americ. 202615 Terminal forjado cuadr. 1/2", Q-96 u 30.00INHER 490035 Ferret. Americ. 202606 Terminal forjado cuadr. 5/8", 227 u 18.75INHER 490036 Ferret. Americ. 202613 Terminal forjado cuadr. 5/8", A-10 u 29.50INHER 490037 Ferret. Americ. 199179 Tope forjado completo 36"x9 3/4", GT-2200 u 1,960.01INHER 490038 Ferret. Americ. 199211 Tope forjado completo 56 3/4"x14", GT-2204 u 2,818.00INHER 490039 Ferret. Americ. 181802 Tubo redondo negro 2"x20' u 2,799.00INHER 490040 Ferret. Americ. 181859 Tubo redondo negro 3"x20' u 4,640.00INHER 490041 Ml. Fdez. Glez. Tubo redondo negro 4"x20' u 7,928.00INHER 490042 Ferret. Americ. 052451 Perfil ¾"x¾"x20', 1.2 mm., galv. u 330.60INHER 490043 Ferret. Americ. 151279 Perfil 1"x1"x20' 1.6 mm, negro u 377.00INHER 490044 Ferret. Americ. 052447 Perfil 1"x2"x20', 1.6 mm, negro u 522.00INHER 490045 Ferret. Americ. 071723 Perfil 1 ½"x1 ½"x20' u 551.00INHER 490046 Ferret. Americ. 064440 Perfil 1 ½"x1 ½"x20', 1.6 mm, galv. u 838.88INHER 490047 Ferret. Americ. 052442 Perfil 2"x2"x20' 1.6 mm, negro u 783.00INHER 490048 Ferret. Americ. 052454 Perfil 2"x2"x20', 1.6 mm., galv. u 1,090.40INHER 490049 Ferret. Americ. 052449 Perfil 2"x3"x20' 1.6 mm, negro u 962.80INHER 490050 Ferret. Americ. 052458 Perfil 2"x3"x20', 1.6 mm., galv. u 1,392.00INHER 490051 Ferret. Americ. 052450 Perfil 2"x4"x20' u 1,146.08INHER 490052 Ferret. Americ. 052443 Perfil 3"x3"x20', 1.6 mm, negro u 1,397.01INHER 490053 Ferret. Americ. 052444 Perfil 4"x4"x20', negro u 2,860.00

INHOR 510000 HORMIGONES INDUSTRIALES Y VACIADOS: (SINERCON)INHOR 510001 Agua, camión 2,000 gls. gl 0.35 INHOR 510002 Horm. América Horm. 100 kg/cm2 m3 4,408.00INHOR 510003 Horm. América Horm. 140 kg/cm2 m3 4,582.00INHOR 510004 Horm. América Horm. 160 kg/cm2 m3 4,698.00INHOR 510005 Horm. América Horm. 180 kg/cm2 m3 4,872.00INHOR 510006 Horm. América Horm. 210 kg/cm2 m3 5,104.00INHOR 510007 Horm. América Horm. 240 kg/cm2 m3 5,336.00INHOR 510008 Horm. América Horm. 250 kg/cm2 m3 5,452.00INHOR 510009 Horm. América Horm. 260 kg/cm2 m3 5,626.00INHOR 510010 Horm. América Horm. 280 kg/cm2 m3 5,800.00INHOR 510011 Horm. América Horm. 300 kg/cm2 m3 5,974.00INHOR 510012 Horm. América Horm. 350 kg/cm2 m3 6,438.00INHOR 510013 Horm. América Horm. 400 kg/cm2 m3 6,960.00INHOR 510014 Horm. América Vaciado con bomba, 10 m3 10m3 5,220.00INHOR 510015 Horm. América Vaciado con bomba, 10.50 m3 en adelante m3 522.00INHOR 510016 Horm. América Vaciado con bomba adicional p/planta después 4to. Nivel. m3 23.20

INIMP 530000 IMPERMEABILIZANTES:INIMP 530001 ALM, lata de 5 gl. lta 3,034.40INIMP 530002 Bitupol inst., 2.5 mm., 5 años gar. m2 324.80INIMP 530003 Bitupol inst., 3 mm., reforz. con poliester, 10 años gar. m2 396.98INIMP 530004 Bitupol inst., 4 mm., reforz. con poliester, 10 años gar. m2 505.24INIMP 530005 Ferret. Americ. 053886 Sellador de techo "Popular" gl 552.00INIMP 530006 Ferret. Americ. 022657 Sellador de techo "Domatecho", Bco., lata 5 gl. lta 2,540.01INIMP 530007 Ferret. Americ. 041107 Sellador de techo "Lanco", import., lata 5 gl. lta 2,694.00INIMP 530008 Ferret. Americ. 291342 Sellador de techo "Ultra Siliconizer", lata 5 gl. lta 4,100.00

INLAB 550000 LABORATORIO MECANICA DE SUELOS>INLAB 550001 Rotura de probetas y análisis de resultados u 474.44

INLAV 570000 LAVADEROS Y VERTEDEROS DE GRANITO:INLAV 570001 Lavadero doble granito, 1.50x0.50 m. u 3,617.37INLAV 570002 Lavadero sencillo granito, 1.25x0.50 m. u 2,305.86INLAV 570003 Tina o vertedero granito, hasta 0.60x0.60 m., gris u 1,794.50INLAV 570004 Tina o vertedero granito, hasta 0.60x0.60 m., blanco u 2,154.32INLAV 570005 Transp. lavadero y tina u 128.06

INLLA 590000 LLAVES DE PASO, VALVULAS, CHEQUES Y TAPAS CISTERNA: INLLA 590001 Ferret. Americ. 015272 Cheque horiz. ½" "Urrea", 85N-13 u 513.00INLLA 590002 Ferret. Americ. 068190 Cheque horiz. ¾" "Urrea", 85N-19 u 707.99INLLA 590003 Ferret. Americ. 155044 Cheque horiz. 1" "Urrea", 85N-25 u 1,129.00INLLA 590004 Ferret. Americ. 007784 Cheque horiz. 1 ½" "Urrea", 85N-38 u 1,760.00INLLA 590005 Ferret. Americ. 090603 Cheque horiz. 2" "Urrea", 85N-51 u 2,662.20INLLA 590006 Ferret. Americ. 015302 Cheque horiz. 2 ½" "Europa", 100 ITAP u 3,037.09INLLA 590007 Ferret. Americ. 015301 Cheque horiz. 3" "Europa", 100 ITAP u 4,595.00INLLA 590008 Ferret. Americ. 015309 Cheque horiz. 4" "Europa" u 8,123.00INLLA 590009 Ferret. Americ. 015316 Cheque vert. ¾" "Europa" u 412.00INLLA 590010 Ferret. Americ. 015306 Cheque vert. 1" "Europa" u 473.00INLLA 590011 Ferret. Americ. 015313 Cheque vert. 1 ½" "Europa" u 1,189.00INLLA 590012 Ferret. Americ. 015541 Cheque vert. 2" "Europa" u 1,783.00INLLA 590013 Ferret. Americ. 015311 Cheque vert. 2 ½" "Europa", 105 ITAP u 2,964.00INLLA 590014 Ferret. Americ. 015310 Cheque vert. 3" "Europa", 105 ITAP u 5,728.00INLLA 590015 Ferret. Americ. 015309 Cheque vert. 4" "Europa", 105 ITAP u 8,550.00INLLA 590016 Ferret. Americ. 066154 Llave de paso ½" de bola, 090 ITAP u 188.00INLLA 590017 Ferret. Americ. 066155 Llave de paso ¾" de bola, 090 ITAP u 301.00

Page 11: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 9

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INLLA 590018 Ferret. Americ. 070998 Llave de paso 1" de bola, 090 ITAP u 446.99INLLA 590019 Ferret. Americ. 015287 Llave de paso 1 ½" "Urrea" u 1,405.05INLLA 590020 Ferret. Americ. 105385 Llave de paso 2" de bola, 090 ITAP u 1,487.70INLLA 590021 Ferret. Americ. 015259 Llave de paso 2 ½" de bola, 111 ITAP u 2,790.00INLLA 590022 Ferret. Americ. 013157 Llave de paso 3" de bola, 111 ITAP u 4,258.13INLLA 590023 Ferret. Americ. 176955 Tapa cisterna 24''x24'', tola verde u 1,679.68INLLA 590024 Ferret. Americ. 015429 Tapa cisterna 27"x27", aluminio u 2,662.20INLLA 590025 Ferret. Americ. 089055 Tapa cisterna 30''x30'', acero inox. u 6,061.00INLLA 590026 Ferret. Americ. 183609 Tapa cisterna 30"x30", tola u 2,396.85INLLA 590027 Ferret. Americ. 015366 Válvula cisterna, ½" "Urrea", 04N-13 u 232.00INLLA 590028 Ferret. Americ. 015367 Válvula cisterna, ¾" "Urrea", 04N-19 u 453.00INLLA 590029 Ferret. Americ. 015368 Válvula cisterna, 1" "Urrea" u 1,001.88INLLA 590030 Ferret. Americ. 015465 Válvula ¾", orinal fluxómetro, 451-NVB u 3,849.00INLLA 590031 Ferret. Americ. 014926 Válvula ¾", seguridad p/calentador tw, R-125C u 266.80INLLA 590032 Ferret. Americ. 015464 Válvula 1", inodoro fluxómetro, 402-NVB u 3,849.00

INMAD 610000 MADERAS, CLAVOS, ZINC Y OTROS:INMAD 610001 Caoba bruta, larga (Valiente Fernández) pt 135.00INMAD 610002 Ferret. Americ. 162425 Caballete de zinc 6', cal. 34 u 91.28INMAD 610003 Ferret. Americ. 162424 Caballete de zinc 6', cal. 29 u 134.56INMAD 610004 Cedro bruto, largo con olor (Vicente Valiente) pt 143.00INMAD 610005 Ferret. Americ. 023120 Clavo corriente, metalizado c/cabeza 2 ½"x10 lb 24.79INMAD 610006 Ferret. Americ. 037055 Clavo de acero 1 ½" u 0.52INMAD 610007 Ferret. Americ. 022978 Clavo de acero 2 ½" lb 45.24INMAD 610008 Ferret. Americ. 022973 Clavo de zinc 2 ½" lb 33.76INMAD 610009 Ferret. Americ. 022966 Clavo galv. ¾" para cartón lb 47.56INMAD 610010 Ferret. Americ. Clavo galv. 2 ½"x9 c/cabeza lb 39.20INMAD 610011 Ferret. Americ. 050703 Pino amer. 1"x4"x10' bruto (3.33 pt) pt 29.00INMAD 610012 Ferret. Americ. Pino amer. 1"x4"x10' bruto tratado (3.33 pt) pt 37.15INMAD 610013 Ferret. Americ. 050704 Pino amer. 1"x4"x12' hasta 1"x10"x12' bruto (10 pt) pt 29.00INMAD 610014 Ferret. Americ. 050741 Pino amer. 1"x12"x12' bruto (12 pt) pt 32.48INMAD 610015 Ferret. Americ. Pino amer. 1"x12"x12' bruto tratado (12 pt) pt 42.00INMAD 610016 Ferret. Americ. 050767 Pino amer. 2"x4" hasta 2"x12"x12' bruto (24 pt) pt 32.48INMAD 610017 Ferret. Americ. Pino amer. 3"x4" hasta 3"x12"x12' bruto (36 pt) pt 34.80INMAD 610018 Ferret. Americ. Pino amer. 3"x6"x10' bruto (15 pt) pt 27.84INMAD 610019 Ferret. Americ. Pino amer. 3"x8"x12' bruto tratado (24 pt) pt 38.01INMAD 610020 Ferret. Americ. 057786 Pino amer. 4"x4"x12' bruto (16 pt) pt 38.11INMAD 610021 Ferret. Americ. Pino amer. 4"x4"x12' bruto tratado (16 pt) pt 34.80INMAD 610022 Ferret. Americ. 000484 Plywood brasil 4'x8'x¼", 6 mm., plancha u 475.99INMAD 610023 Ferret. Americ. 000486 Plywood brasil 4'x8'x½", plancha u 847.00INMAD 610024 Ferret. Americ. 000483 Plywood brasil 4'x8'x3/16", plancha u 469.01INMAD 610025 Ferret. Americ. 000485 Plywood brasil 4'x8'x3/8", plancha u 707.99INMAD 610026 Ferret. Americ. 000487 Plywood brasil 4'x8'x¾", plancha u 1,218.00INMAD 610027 Ferret. Americ. 000493 Plywood Formaleta 4'x8'x¾" USA, una cara, plancha u 1,150.00INMAD 610028 Regla para empañete (Preparada) pt 154.28INMAD 610029 Roble brasileño bruto, largo (INDOMACA) pt 130.00INMAD 610030 Ferret. Americ. 056313 Tratamiento madera pt 3.00INMAD 610031 Ferret. Americ. 023447 Zinc acanalado, 3'x6', cal. 34 u 218.08INMAD 610032 Ferret. Americ. 023449 Zinc acanalado, 3'x6', cal. 27 u 425.05INMAD 610033 Ferret. Americ. 023441 Zinc acanalado, 3'x6', cal. 26 u 498.80INMAD 610034 Ferret. Americ. 023442 Zinc acanalado, 3'x6', cal. 24 u 471.61

INMAL 630000 MALLAS CICLONICAS Y ACCESORIOS:INMAL 630001 Ferret. Americ. 081460 Abrazadera redonda 1 ½", galv. u 16.53INMAL 630002 Ferret. Americ. 081463 Abrazadera redonda 2 ½", galv. u 13.22INMAL 630003 Ferret. Americ. 012826 Alambre de púas #14x110 m, galv., rollo u 804.45INMAL 630004 Ferret. Americ. 012825 Alambre de púas #16x110 m, galv., rollo u 474.41INMAL 630005 Ferret. Americ. 078065 Barra tensora de 4', galv. u 55.10INMAL 630006 Ferret. Americ. 078066 Barra tensora de 6', galv. u 99.18INMAL 630007 Ferret. Americ. 078068 Barra tensora de 7', galv. u 148.77INMAL 630008 Ferret. Americ. 078069 Barra tensora de 10', galv. u 159.79INMAL 630009 Ferret. Americ. 054700 Copa final 2", galv. u 30.86INMAL 630010 Ferret. Americ. 023167 Grapas 1" para alambre de púas lb 27.50INMAL 630011 Ferret. Americ. 054675 Malla ciclónica 6' cal. 9, galv. pie 80.94INMAL 630012 Ferret. Americ. 054674 Malla ciclónica 7' cal. 9, galv. pie 101.37INMAL 630013 Ferret. Americ. 054705 Palometa 1 ½"x1 ¼", 3 cuerdas, sencilla, galv. u 77.14INMAL 630014 Ferret. Americ. 054707 Palometa 1 ½"x1 ¼", 3 cuerdas, doble, galv. u 123.42INMAL 630015 Ferret. Americ. 054697 Terminal de 1 ¼", galv. u 27.55INMAL 630016 Ferret. Americ. 054684 Tubo 1 ½"x15', galv. ligero u 457.33INMAL 630017 Ferret. Americ. 054685 Tubo 1 ¼"x20', galv. ligero u 511.56

INMAT 650000 MATERIALES INSTALADOS:INMAT 650001 Caballete en teja asfáltica inst. todo costo m 114.81INMAT 650002 Ferret. Americ. 024723 Felpa impermeable, 3' ancho x 15' de largo pie 11.99INMAT 650003 Línea doble teja asfáltica inst. todo costo, en bordes m 114.81INMAT 650004 Ferret. Americ. 198879 Plafón Fibra Mineral 2'x2'x9/16", Futura u 139.00INMAT 650005 Ferret. Americ. Plafón PVC cruadrado 2'x2', instalado a todo costo m2 745.51INMAT 650006 Ferret. Americ. Plafón PVC machiembrado, instalado a todo costo m2 1,124.92INMAT 650007 Ferret. Americ. 218637 Plafón PVC rectangular 2'x4' bco., instalado a todo costo m2 221.00INMAT 650008 Teja asfáltica 3'x1' inst. todo costo m2 324.10INMAT 650009 Ferret. Americ. 024722 Teja asfáltica 3'x1', gris, paq. 26 piezas de 1'x3', 3.07 m2) paq 1,088.00INMAT 650010 Ferret. Americ. 024699 Teja asfáltica 3'x1', marrón, paq. 26 piezas de 1'x3', 3.07 m2) paq 1,095.01INMAT 650011 Ferret. Americ. 024712 Teja asfáltica 3'x1', roja, paq. 26 piezas de 1'x3', 3.07 m2) paq 1,095.01INMAT 650012 Ferret. Americ. 211351 Teja asfáltica 3'x1', verde claro, paq. 26 piezas de 1'x3', 3.07 m2) paq 995.00INMAT 650013 Ferret. Americ. 024701 Teja asfáltica 3'x1', verde, paq. 26 piezas de 1'x3', 3.07 m2) paq 1,095.01

INPIE 670000 PIEDRAS EN LAJAS PARA PISOS:INPIE 670001 Piedra color claro m2 245.00

Page 12: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 10

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INPIE 670002 Piedra color gris m2 675.00INPIE 670003 Piedra coralina biselada m2 1,102.00INPIE 670004 Piedra coralina sin bisel m2 914.64

INPIN 690000 PINTURAS:INPIN 690001 Ferret. Americ. 005079 Acrílica "Popular" blanco 50 gl 458.00INPIN 690002 Ferret. Americ. 043577 Acrílica, Tropical, Violeta claro (colores preparados) gl 719.00INPIN 690003 Ferret. Americ. 039537 Aguarrás "Popular" gl 319.00INPIN 690004 Ferret. Americ. 023387 Blanco de España lb 11.60INPIN 690005 Ferret. Americ. 004892 Epóxica gl 1,292.00INPIN 690006 Ferret. Americ. 235127 Latex "Económica" o "Pintex" gl 191.01INPIN 690007 Ferret. Americ. 038809 Mantenimiento "Popular" blanco 50 gl 651.00INPIN 690008 Ferret. Americ. 004987 Oxido Rojo "Popular" k-09 gl 448.00INPIN 690009 Ferret. Americ. 004758 Sellador de poros a la madera, plywood, etc. (Sealer Tropical) gl 609.00INPIN 690010 Ferret. Americ. 042177 "Thinner" AAA-500 "Popular" gl 423.40

INPIS 710000 PISOS Y ADOQUINES:INPIS 710001 Indust. Aguayo Adoquín 500-80 8x10x20 cm. gris m2 1,572.99INPIS 710002 Indust. Aguayo Adoquín 500-80 8x10x20 cm. rojo m2 2,038.00INPIS 710003 Indust. Aguayo Adoquín 511 gris m2 1,400.00INPIS 710004 Indust. Aguayo Adoquín 511 rojo m2 1,645.00INPIS 710005 Indust. Aguayo Adoquín 604 6x20.2x20.2 cm. gris m2 1,165.00INPIS 710006 Indust. Aguayo Adoquín 604 6x20.2x20.2 cm. rojo m2 1,388.52INPIS 710007 Baldosas de G. Baldosa p/exterior 30x30, Crema y Aurora, tipo Vibrazo m2 545.14INPIS 710008 Baldosas de G. Baldosa p/exterior 30x30, Gris, tipo Vibrazo m2 382.75INPIS 710009 Baldosas de G. Baldosa p/exterior 30x30, Verde, tipo Vibrazo m2 772.10INPIS 710010 Baldosas de G. Baldosa p/exterior 40x40, Laja Gris m2 574.20INPIS 710011 Baldosas de G. Borde p/pavimento y jardinería GPVT, espesor = .08 m. m 455.88INPIS 710012 Corte chazos 25 u 8.12INPIS 710013 Corte chazos 30 u 9.28INPIS 710014 Corte chazos 40 u 12.76INPIS 710015 Corte ladrillos y adoquines u 30.16INPIS 710016 Corte zócalos u 5.80INPIS 710017 Baldosas de G. Derretido blanco fda 806.20INPIS 710018 Baldosas de G. Derretido gris fda 382.80INPIS 710019 Baldosas de G. Derretido verde fda 806.20INPIS 710020 Baldosas de G. Granimármol 30x30 fondo blanco m2 545.14INPIS 710021 Baldosas de G. Granimármol 40x40 fondo blanco m2 639.30INPIS 710022 Baldosas de G. Granito 1 2 y 3 30x30 fondo blanco m2 371.15INPIS 710023 Baldosas de G. Granito 1 2 y 3 30x30 fondo gris m2 315.49INPIS 710024 Baldosas de G. Granito 1 2 y 3 40x40 fondo blanco m2 537.81INPIS 710025 Baldosas de G. Granito 1 2 y 3 40x40 fondo gris m2 391.43INPIS 710026 Baldosas de G. Mármol 30x60 Travertino m2 1,162.32INPIS 710027 Baldosas de G. Mármol 40x40 Aglomerado Perlatto Royal m2 638.00INPIS 710028 Baldosas de G. Mármol 40x40 Crema Marfil bruto m2 1,295.23INPIS 710029 Baldosas de G. Mármol 40x60 Crema Marfil bruto m2 1,373.82INPIS 710030 Indust. Aguayo Mosaico 25x25 rojo m2 807.97INPIS 710031 Indust. Aguayo Paragomas u 743.47INPIS 710032 Indust. Aguayo Piedra p/pavimento G3 espesor = .045 m., 12 adoquines integrados m2 1,157.68INPIS 710033 Indust. Aguayo Piedra p/pavimento G15 espesor = .045 m., 5 adoquines inseparables m2 1,095.04INPIS 710034 Indust. Aguayo Piedra p/pavim. DGVE 2.5 espesor = .045 m., 3 losas Galo-Romanas m2 684.40INPIS 710035 Indust. Aguayo Tableta 2"x8"x16" gris m2 506.00INPIS 710036 Indust. Aguayo Tableta 2"x8"x16" roja m2 553.00INPIS 710037 Indust. Aguayo Transp. adoquín 500-80 u 0.92INPIS 710038 Indust. Aguayo Transp. adoquín 511 u 0.72INPIS 710039 Indust. Aguayo Transp. adoquín 604 u 0.89INPIS 710040 Indust. Aguayo Transp. Baldosa 30x30 u 0.90INPIS 710041 Indust. Aguayo Transp. Baldosa 40x40 u 1.30INPIS 710042 Indust. Aguayo Transp. Baldosa 40x60 u 1.95INPIS 710043 Indust. Aguayo Transp. Mosaico 25X25 u 0.75INPIS 710044 Indust. Aguayo Transp. Paragomas u 44.73INPIS 710045 Indust. Aguayo Transp. tableta u 0.85INPIS 710046 Indust. Aguayo Transp. zócalo granito y mosaico u 0.88INPIS 710047 Baldosas de G. Zócalo Granimármol 30x07 m 65.32INPIS 710048 Baldosas de G. Zócalo Granimármol 40x07 m 64.96INPIS 710049 Baldosas de G. Zócalo Granito 1 2 y 3 30x07 fondo blanco m 70.73INPIS 710050 Baldosas de G. Zócalo Granito 1 2 y 3 30x07 fondo gris m 44.38INPIS 710051 Baldosas de G. Zócalo Granito 1 2 y 3 40x07 fondo blanco m 79.09INPIS 710052 Baldosas de G. Zócalo Granito 1 2 y 3 40x07 fondo gris m 58.00INPIS 710053 Baldosas de G. Zócalo Mármol 30x07 Crema Marfil recto m 496.14INPIS 710054 Baldosas de G. Zócalo Mármol 30x10 Crema Marfil recto m 419.30INPIS 710055 Baldosas de G. Zócalo Mármol 40x07 Crema Marfil recto m 496.14INPIS 710056 Baldosas de G. Zócalo Mármol 40x10 Crema Marfil recto m 419.30INPIS 710057 Baldosas de G. Zócalo Mármol 60x10 Crema Marfil recto m 426.33INPIS 710058 Baldosas de G. Zócalo Marmol aglomerado Perlatto Royal 40x07 redondeado m 183.28INPIS 710059 Baldosas de G. Zócalo Marmol aglomerado Perlatto Royal 40x07 recto m 102.28INPIS 710060 Indust. Aguayo Zócalo Mosaico rojos 25x07 u 123.75

INPLA 730000 PLANTAS ELECTRICAS:INPLA 730001 Ferret. Americ. Planta 60 Kilos 3 ph, Kholer, silenciosa u 634,692.61

INPOZ 750000 POZOS FILTRANTE:INPOZ 750001 Pozo filtrante 8" + camisa 6" x 10', PVC SDR-26 u 14,599.76INPOZ 750002 Pozo filtrante 10" + camisa 8" x 10', PVC SDR-26 u 16,820.00

INPUE 770000 PUERTAS DE ALUMINIO:INPUE 770001 Ferret. Americ. 038593 Cerradura eléctrica "Yale" 67400401 (674-40) u 3,132.00INPUE 770002 Induca PC9015-00 Cierre botella grande p/puerta com. normal (alum. nat.) u 1,475.16

Page 13: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 11

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INPUE 770003 Induca PC9014-00 Cierre botella pequeño p/puerta com. normal (alum. nat.) u 1,051.12INPUE 770004 Induca PC9014-11 Cierre botella pequeño p/puerta com. normal (alum. bce.) u 965.20INPUE 770005 Induca PC9003-00 Cilindros p/puerta comercial (2 unid.) u 390.70INPUE 770006 Induca PC9009-00 Componento eléctrico p/puerta com. u 1,738.91INPUE 770007 Induca PC9006-00 Cubre falta p/cerradura eléctrica normal u 38.89INPUE 770008 Induca PCORR Pta. corred. alum. anod. normal, v. claro (w2.86 x h2.1 m.) m2 2,591.02INPUE 770009 Induca PCORR Pta. corred. alum. anod. normal, v. claro mart. (w2.86 x h2.1 m.) m2 2,561.20INPUE 770010 Induca PCORR Pta. corred. alum. anod. normal, v. bce. liso (w2.86 x h2.1 m.) m2 2,688.24INPUE 770011 Induca PCORR Pta. corred. alum. anod. normal, v. bce. mart. (w2.86 x h2.1 m.) m2 2,652.82INPUE 770012 Induca PCORR Pta. corred. alum. anod. normal, v. "Bluegreen" (w2.86 x h2.1 m.) m2 2,914.00INPUE 770013 Induca PCORR Pta. corred. alum. anod. normal, v. reflect. claro (w2.86 x h2.1 m.) m2 3,058.70INPUE 770014 Induca PCORR Pta. corred. alum. anod. normal, con espejo (w2.86 x h2.1 m.) m2 3,326.09INPUE 770015 Induca PCORR Pta. corred. alum. anod. bce., v. claro (w2.86 x h2.1 m.) m2 2,257.51INPUE 770016 Induca PCORR Pta. corred. alum. anod. bce., v. claro mart. (w2.86 x h2.1 m.) m2 2,227.76INPUE 770017 Induca PCORR Pta. corred. alum. anod. bce., v. bce. liso (w2.86 x h2.1 m.) m2 2,354.80INPUE 770018 Induca PCORR Pta. corred. alum. anod. bce., v. bce. mart. (w2.86 x h2.1 m.) m2 2,323.77INPUE 770019 Induca PCORR Pta. corred. alum. anod. bce., v. reflect. claro (w2.86 x h2.1 m.) m2 2,725.18INPUE 770020 Induca PCORR Pta. corred. alum. anod. bce., con espejos (w2.86 x h2.1 m.) m2 2,992.58INPUE 770021 Induca PCORR Pta. corred. alum. bco., v. claro (w2.86 x h2.1 m.) m2 2,532.44INPUE 770022 Induca PCORR Pta. corred. alum. bco., v. claro mart. (w2.86 x h2.1 m.) m2 2,499.07INPUE 770023 Induca PCORR Pta. corred. alum. bco., v. bce. liso (w2.86 x h2.1 m.) m2 2,629.67INPUE 770024 Induca PCORR Pta. corred. alum. bco., v. bce. mart. (w2.86 x h2.1 m.) m2 2,595.02INPUE 770025 Induca PCORR Pta. corred. alum. bco., v. "Bluegreen" (w2.86 x h2.1 m.) m2 2,855.43INPUE 770026 Induca PCORR Pta. corred. alum. bco., v. reflect. claro (w2.86 x h2.1 m.) m2 3,000.12INPUE 770027 Induca PCORR Pta. corred. alum. bco., con espejo (w2.86 x h2.1 m.) m2 3,251.57INPUE 770028 Induca PCORR Pta. com. 1 hoja, 1 m.,7', alum. anod. normal, v. claro u 13,337.18INPUE 770029 Induca PCORR Pta. com. 1 hoja, 1 m.,7', alum. anod. normal, v. claro mart. u 13,161.42INPUE 770030 Induca PCORR Pta. com. 1 hoja, 1 m.,7', alum. anod. normal, v. bce. liso u 13,512.02INPUE 770031 Induca PCORR Pta. com. 1 hoja, 1 m.,7', alum. anod. normal, v. bce. mart. u 13,333.96INPUE 770032 Induca PCORR Pta. com. 1 hoja, 1 m.,7', alum. anod. bce., v. claro u 13,147.38INPUE 770033 Induca PCORR Pta. com. 1 hoja, 1 m.,7', alum. anod. bce., v. claro mart. u 12,974.12INPUE 770034 Induca PCORR Pta. com. 1 hoja, 1 m.,7', alum. anod. bce., v. bce. liso u 13,322.65INPUE 770035 Induca PCORR Pta. com. 1 hoja, 1 m.,7', alum. anod. bce., v. bce. mart. u 13,147.08INPUE 770036 Induca PCORR Pta. com. 1 hoja, 1 m., 7', alum. Bco, v. claro u 14,257.93INPUE 770037 Induca PCORR Pta. com. 1 hoja, 1 m., 7', alum. Bco, v. claro mart. u 14,070.03INPUE 770038 Induca PCORR Pta. com. 1 hoja, 1 m., 7', alum. Bco, v. bce. liso u 14,432.75INPUE 770039 Induca PCORR Pta. com. 1 hoja, 1 m., 7', alum. Bco, v. bce. mart. u 14,242.56INPUE 770040 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. anod. normal, v. claro u 17,339.91INPUE 770041 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. anod. normal, v. mart. u 17,111.40INPUE 770042 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. anod. normal, v. bce. liso u 17,736.60INPUE 770043 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. anod. normal, v. bce. mart. u 17,502.86INPUE 770044 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. anod. bce., v. claro u 16,589.30INPUE 770045 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. anod. bce., v. claro mart. u 16,370.69INPUE 770046 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. anod. bce., v. bce. liso u 16,985.97INPUE 770047 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. anod. bce., v. bce. mart. u 16,762.13INPUE 770048 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. Bco., v. claro u 18,447.04INPUE 770049 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. Bco., v. claro mart. u 18,203.94INPUE 770050 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. Bco., v. bce. liso u 18,843.72INPUE 770051 Induca PCORR Pta. com. 2 hojas, 2 m., 7', alum. Bco., v. bce. mart. u 18,595.39INPUE 770052 Induca PC9012-00 Puño anodizado normal p/puerta eléctrica u 329.15INPUE 770053 Induca PC9019-00 Push boton p/cerradura eléctrica normal u 251.78INPUE 770054 Induca PC9010-00 Transformador p/puerta com. eléctrica u 1,036.59INPUE 770055 Induca Transporte e instalación (Porcentaje sobre el costo) % 12.00%

INTIN 790000 TINACOS:INTIN 790001 Ferret. Americ. Tinaco 150 gl. "Aquaplástica" u 2,108.72INTIN 790002 Ferret. Americ. 178290 Tinaco 265 gl. "Tinacom" u 3,873.92INTIN 790003 Ferret. Americ. 203729 Tinaco 400 gl. "Tinacom" u 7,043.52INTIN 790004 Ferret. Americ. Tinaco 500 gl."Aquaplástica" u 5,719.99INTIN 790005 Ferret. Americ. 178291 Tinaco 530 gl. "Tinacom" u 8,029.61INTIN 790006 Ferret. Americ. Tinaco 1000 gl "Tinacom" u 11,779.80INTIN 790007 Ferret. Americ. Tornillo exag. p/madera, h.g. ¼"x4" (23 unid/lb) u 8.99

INTCP 810000 TUBERIAS Y PIEZAS CPVC:INTCP 810001 Ferret. Americ. 015932 Adaptador hembra ½" cpvc u 27.40INTCP 810002 Ferret. Americ. 015914 Adaptador hembra ¾" cpvc u 42.98INTCP 810003 Ferret. Americ. 015931 Adaptador macho ½" cpvc u 8.92INTCP 810004 Ferret. Americ. 015913 Adaptador macho ¾" cpvc u 16.62INTCP 810005 Ferret. Americ. 089957 Cemento cpvc, 8 onzas, pinta u 420.96INTCP 810006 Ferret. Americ. 089959 Cemento cpvc, 32 onzas u 443.12INTCP 810007 Ferret. Americ. 028003 Codo ½''x90, cpvc u 7.93INTCP 810008 Ferret. Americ. 028004 Codo ¾''x90, cpvc u 18.25INTCP 810009 Ferret. Americ. 098158 Limpiador tubo cpvc, 8 onzas, pinta u 123.42INTCP 810010 Ferret. Americ. 176954 Limpiador tubo cpvc, 16 onzas u 252.00INTCP 810011 Ferret. Americ. 015934 Reduc. bushing ¾"x½", cpvc u 9.50INTCP 810012 Ferret. Americ. 128008 Reduc. bushing 1'' x ¾", cpvc u 27.55INTCP 810013 Ferret. Americ. 015930 Tee ½'', cpvc u 11.57INTCP 810014 Ferret. Americ. 028005 Tee ¾'', cpvc u 25.35INTCP 810015 Ferret. Americ. 015151 Tubo ½''x10', cpvc u 127.83INTCP 810016 Ferret. Americ. 015152 Tubo ¾''x10', cpvc u 203.87

INTHG 830000 TUBERIAS Y PIEZAS H.G. (HIERRO GALVANIZADO):INTHG 830001 Ferret. Americ. 015354 Codo ½"x90, h.g. u 15.10INTHG 830002 Ferret. Americ. 015355 Codo ¾"x90, h.g. u 14.50INTHG 830003 Ferret. Americ. 015356 Codo 1"x90, h.g. u 18.75INTHG 830004 Ferret. Americ. 015357 Codo 1 ¼"x90, h.g. u 59.00INTHG 830005 Ferret. Americ. 015358 Codo 1 ½"x90, h.g. u 52.69INTHG 830006 Ferret. Americ. 015359 Codo 2"x90, h.g. u 73.00

Page 14: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 12

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INTHG 830007 Ferret. Americ. 015360 Codo 2 ½"x90, h.g. u 118.00INTHG 830008 Ferret. Americ. 015361 Codo 3"x90, h.g. u 123.42INTHG 830009 Ferret. Americ. 015362 Codo 4"x90, h.g. u 320.53INTHG 830010 Ferret. Americ. 015405 Codo niple ½", h.g. u 11.99INTHG 830011 Ferret. Americ. 015406 Codo niple ¾", h.g. u 16.50INTHG 830012 Ferret. Americ. 015407 Codo niple 1", h.g. u 25.00INTHG 830013 Ferret. Americ. 015408 Codo niple 1 ¼", h.g. u 72.00INTHG 830014 Ferret. Americ. 033956 Codo niple 1 ½", h.g. u 58.00INTHG 830015 Ferret. Americ. 015409 Codo niple 2", h.g. u 111.00INTHG 830016 Ferret. Americ. 062080 Codo niple 2 ½", h.g. u 108.00INTHG 830017 Ferret. Americ. Codo niple 3", h.g. u 233.03INTHG 830018 Ferret. Americ. Codo niple 4", h.g. u 250.82INTHG 830019 Ferret. Americ. 015336 Coupling ½" h.g. u 12.75INTHG 830020 Ferret. Americ. 015337 Coupling ¾" h.g. u 15.37INTHG 830021 Ferret. Americ. 015338 Coupling 1" h.g. u 21.00INTHG 830022 Ferret. Americ. 015340 Coupling 1 ½" h.g. u 35.99INTHG 830023 Ferret. Americ. 015341 Coupling 2" h.g. u 97.44INTHG 830024 Ferret. Americ. 015342 Coupling 2 ½" h.g. u 112.40INTHG 830025 Ferret. Americ. 015343 Coupling 3" h.g. u 176.32INTHG 830026 Ferret. Americ. 015344 Coupling 4" h.g. u 282.00INTHG 830027 Ferret. Americ. 016040 Niple ½"x4", h.g. u 42.00INTHG 830028 Ferret. Americ. 016007 Niple ¾"x4", h.g. u 42.00INTHG 830029 Ferret. Americ. 016019 Niple 1"x4", h.g. u 64.99INTHG 830030 Ferret. Americ. 015994 Niple 1 ¼"x4", h.g. u 86.00INTHG 830031 Ferret. Americ. 016010 Niple 1 ½"x3 ½", h.g. u 76.00INTHG 830032 Ferret. Americ. 015972 Niple 1 ½"x6" h.g. u 104.49INTHG 830033 Ferret. Americ. Niple 1 ½"x8" h.g. u 150.80INTHG 830034 Ferret. Americ. 016001 Niple 2"x4", h.g. u 97.44INTHG 830035 Ferret. Americ. 016015 Niple 2"x6" h.g. u 151.99INTHG 830036 Ferret. Americ. Niple 2 ½"x3 ½", h.g. u 417.60INTHG 830037 Ferret. Americ. Niple 3"x3 ½" h.g. u 609.00INTHG 830038 Ferret. Americ. Niple 3"x4" h.g. u 533.60INTHG 830039 Ferret. Americ. Niple 3"x6" h.g. u 162.24INTHG 830040 Ferret. Americ. Niple 3"x12" h.g. u 870.00INTHG 830041 Ferret. Americ. Niple 4"x3 ½", h.g. u 667.00INTHG 830042 Ferret. Americ. 015216 Reduc. "bushing" ½"x3/8", h.g. u 8.31INTHG 830043 Ferret. Americ. 015220 Reduc. "bushing" ¾"x½", h.g. u 12.06INTHG 830044 Ferret. Americ. 015196 Reduc. "bushing" 1"x¾", h.g. u 16.00INTHG 830045 Ferret. Americ. 015179 Reduc. "bushing" 1 ½"x1", h.g. u 22.50INTHG 830046 Ferret. Americ. 015183 Reduc. "bushing" 2"x¾", h.g. u 60.00INTHG 830047 Ferret. Americ. 016091 Reduc. "bushing" 2"x1", h.g. u 47.50INTHG 830048 Ferret. Americ. 015162 Reduc. "bushing" 2 ½"x1", h.g. u 57.00INTHG 830049 Ferret. Americ. Reduc. "bushing" 3"x2 ½", h.g. u 301.60INTHG 830050 Ferret. Americ. 015225 Reduc. copa ½"x3/8", h.g. u 11.75INTHG 830051 Ferret. Americ. 015228 Reduc. copa ¾"x½", h.g. u 19.15INTHG 830052 Ferret. Americ. 015205 Reduc. copa 1"x¾", h.g. u 15.75INTHG 830053 Ferret. Americ. 015191 Reduc. copa 2"x¾", h.g. u 47.50INTHG 830054 Ferret. Americ. 015167 Reduc. copa 2"x1 ½", h.g. u 55.10INTHG 830055 Ferret. Americ. 015170 Reduc. copa 2 ½"x1", h.g. u 35.50INTHG 830056 Ferret. Americ. 015071 Rollo teflón ¾" u 9.25INTHG 830057 Ferret. Americ. 015413 Tapón hembra ½", h.g. u 16.50INTHG 830058 Ferret. Americ. 015414 Tapón hembra ¾", h.g. u 9.76INTHG 830059 Ferret. Americ. 015415 Tapón hembra 1", h.g. u 14.24INTHG 830060 Ferret. Americ. 015434 Tapón hembra 1 ½", h.g. u 36.60INTHG 830061 Ferret. Americ. 015433 Tapón hembra 2", h.g. u 44.00INTHG 830062 Ferret. Americ. Tapón hembra 2 ½", h.g. u 112.11INTHG 830063 Ferret. Americ. 015431 Tapón hembra 3", h.g. u 108.30INTHG 830064 Ferret. Americ. 015430 Tapón hembra 4", h.g. u 214.99INTHG 830065 Ferret. Americ. 015385 Tapón macho ½", h.g. u 7.25INTHG 830066 Ferret. Americ. 015386 Tapón macho ¾", h.g. u 10.50INTHG 830067 Ferret. Americ. 015387 Tapón macho 1", h.g. u 14.50INTHG 830068 Ferret. Americ. 015404 Tapón macho 1 ½", h.g. u 26.00INTHG 830069 Ferret. Americ. 015403 Tapón macho 2", h.g. u 39.00INTHG 830070 Ferret. Americ. 015402 Tapón macho 2 ½", h.g. u 31.51INTHG 830071 Ferret. Americ. 015401 Tapón macho 3", h.g. u 116.00INTHG 830072 Ferret. Americ. 008002 Tapón macho 4", h.g. u 209.00INTHG 830073 Ferret. Americ. 015372 Tee ½", h.g. u 17.86INTHG 830074 Ferret. Americ. 015373 Tee ¾", h.g. u 22.01INTHG 830075 Ferret. Americ. 015374 Tee 1", h.g. u 48.87INTHG 830076 Ferret. Americ. 015375 Tee 1 ¼", h.g. u 62.00INTHG 830077 Ferret. Americ. 015376 Tee 1 ½", h.g. u 69.99INTHG 830078 Ferret. Americ. 015377 Tee 2", h.g. u 148.77INTHG 830079 Ferret. Americ. 015378 Tee 2 ½", h.g. u 116.00INTHG 830080 Ferret. Americ. 015379 Tee 3", h.g. u 315.00INTHG 830081 Ferret. Americ. 015380 Tee 4", h.g. u 293.00INTHG 830082 Ferret. Americ. 023459 Tubo ½"x20', h.g., mamey u 522.00INTHG 830083 Ferret. Americ. 023460 Tubo ¾"x20', h.g. mamey u 693.68INTHG 830084 Ferret. Americ. 023461 Tubo 1"x20', h.g. mamey u 980.00INTHG 830085 Ferret. Americ. 023462 Tubo 1 ¼"x20', h.g. mamey u 1,160.00INTHG 830086 Ferret. Americ. 023463 Tubo 1 ½"x20', h.g. mamey u 1,531.00INTHG 830087 Ferret. Americ. 023464 Tubo 2"x20', h.g. mamey u 1,788.00INTHG 830088 Ferret. Americ. 023465 Tubo 2 ½"x20', h.g. mamey u 2,900.00INTHG 830089 Ferret. Americ. 023466 Tubo 3"x20', h.g. mamey u 3,375.60INTHG 830090 Ferret. Americ. 058844 Tubo 4"x20', h.g. mamey u 5,005.40INTHG 830091 Ferret. Americ. 015392 Unión univ. ½", h.g. u 32.64INTHG 830092 Ferret. Americ. 015393 Unión univ. ¾", h.g. u 58.00INTHG 830093 Ferret. Americ. 015394 Unión univ. 1", h.g. u 80.23INTHG 830094 Ferret. Americ. 015395 Unión univ. 1 ¼", h.g. u 122.00

Page 15: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 13

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INTHG 830095 Ferret. Americ. 015396 Unión univ. 1 ½", h.g. u 142.00INTHG 830096 Ferret. Americ. 015397 Unión univ. 2", h.g. u 197.20INTHG 830097 Ferret. Americ. 015398 Unión univ. 2 ½", h.g. u 178.00INTHG 830098 Ferret. Americ. 015399 Unión univ. 3", h.g. u 672.00INTHG 830099 Ferret. Americ. 015400 Unión univ. 4", h.g. u 797.00

INTDR 850000 TUBERIAS Y PIEZAS PVC DRENAJE:INTDR 850001 Ferret. Americ. 001346 Cemento pvc criollo, 1 gl. Cano u 921.01INTDR 850002 Ferret. Americ. 136312 Cemento pvc criollo, ¼ gl., Cano u 238.00INTDR 850003 Ferret. Americ. 080389 Cemento pvc criollo, 1/32 gl., pinta, Cano u 43.00INTDR 850004 Ferret. Americ. 075407 Cemento pvc USA 920 gr., Tangit u 1,282.55INTDR 850005 Ferret. Americ. 075406 Cemento pvc USA 460 gr., Tangit u 554.48INTDR 850006 Ferret. Americ. 001503 Cemento pvc USA 240 gr., Tangit u 493.52INTDR 850007 Ferret. Americ. 001345 Cemento pvc USA 125 gr. Tubo, Tangit u 194.88INTDR 850008 Ferret. Americ. 015479 Codo 2"x90, pvc dren. u 13.06INTDR 850009 Ferret. Americ. 015478 Codo 3"x90, pvc dren. u 35.31INTDR 850010 Ferret. Americ. 028826 Codo 4"x90, pvc dren. u 60.32INTDR 850011 Ferret. Americ. 045157 Codo 6"x90, pvc dren. u 285.00INTDR 850012 Ferret. Americ. 015476 Codo 2"x45, pvc dren. u 8.35INTDR 850013 Ferret. Americ. 015475 Codo 3"x45, pvc dren. u 26.13INTDR 850014 Ferret. Americ. 015474 Codo 4"x45, pvc dren. u 40.62INTDR 850015 Ferret. Americ. 015532 Codo 6"x45, pvc dren. u 377.00INTDR 850016 Ferret. Americ. Red. 3"x1 ½", pvc dren. u 34.93INTDR 850017 Ferret. Americ. 015490 Red. 3"x2", pvc dren. u 15.29INTDR 850018 Ferret. Americ. 015482 Red. 4"x2", pvc dren. u 29.00INTDR 850019 Ferret. Americ. 015481 Red. 4"x3", pvc dren. u 29.58INTDR 850020 Ferret. Americ. 227620 Red. 6"x4", pvc dren. u 600.00INTDR 850021 Ferret. Americ. 015503 Sifón 1 ½", p/lav., pvc u 83.52INTDR 850022 Ferret. Americ. 015506 Sifón 2", pvc dren. u 78.40INTDR 850023 Ferret. Americ. 015505 Sifón 3", pvc dren. u 175.00INTDR 850024 Ferret. Americ. Sifón 4", pvc dren. u 1,762.21INTDR 850025 Ferret. Americ. 028832 Tapón reg. 2", pvc dren. u 13.92INTDR 850026 Ferret. Americ. 015500 Tapón reg. 3", pvc dren. u 43.45INTDR 850027 Ferret. Americ. 015499 Tapón reg. 4", pvc dren. u 69.69INTDR 850028 Ferret. Americ. 015488 Tee 2"x 2", pvc dren. u 19.88INTDR 850029 Ferret. Americ. 015487 Tee 3"x3", pvc dren. u 55.01INTDR 850030 Ferret. Americ. 015486 Tee 4"x4", pvc dren. u 78.88INTDR 850031 Ferret. Americ. 015531 Tee 6"x6", pvc dren. u 980.20INTDR 850032 Ferret. Americ. 015485 Tee red. 3"x2", pvc dren. u 38.64INTDR 850033 Ferret. Americ. 015483 Tee red. 4"x3", pvc dren. u 52.20INTDR 850034 Ferret. Americ. 015484 Tee red. 4"x2", pvc dren. u 50.27INTDR 850035 Ferret. Americ. Tee red. 6"x3", pvc dren. u 2,116.12INTDR 850036 Ferret. Americ. Tee red. 6"x4", pvc dren. u 2,382.11INTDR 850037 Ferret. Americ. 178224 Tubo 1 ½"x19', pvc dren. u 136.78INTDR 850038 Ferret. Americ. 178229 Tubo 2"x19', pvc dren. u 129.92INTDR 850039 Ferret. Americ. 178234 Tubo 3"x19', pvc dren. u 243.60INTDR 850040 Ferret. Americ. 178239 Tubo 4"x19', pvc dren. u 340.24INTDR 850041 Ferret. Americ. 178245 Tubo 6"x19', pvc dren. u 860.72INTDR 850042 Ferret. Americ. 178251 Tubo 8"x19', pvc dren. u 1,842.08INTDR 850043 Ferret. Americ. 178232 Tubo 2"x19', pvc SDR-21 u 407.16INTDR 850044 Ferret. Americ. 178265 Tubo 3"x19', pvc SDR-21 u 970.00INTDR 850045 Ferret. Americ. 178243 Tubo 4"x19', pvc SDR-21 u 1,498.72INTDR 850046 Ferret. Americ. 178249 Tubo 6"x19', pvc SDR-21 u 3,230.60INTDR 850047 Ferret. Americ. 178255 Tubo 8"x19', pvc SDR-21 u 5,463.60INTDR 850048 Ferret. Americ. 178214 Tubo ½"x19', pvc SDR-26 u 50.87INTDR 850049 Ferret. Americ. 178217 Tubo ¾"x19', pvc SDR-26 u 71.00INTDR 850050 Ferret. Americ. 178263 Tubo 1"x19', pvc SDR-26 u 123.84INTDR 850051 Ferret. Americ. 178226 Tubo 1 ½"x19', pvc SDR-26 u 214.01INTDR 850052 Ferret. Americ. 178231 Tubo 2"x19', pvc SDR-26 u 256.04INTDR 850053 Ferret. Americ. 178237 Tubo 3"x19', pvc SDR-26 u 676.26INTDR 850054 Ferret. Americ. 178242 Tubo 4"x19', pvc SDR-26 u 1,067.20INTDR 850055 Ferret. Americ. 178248 Tubo 6"x19', pvc SDR-26 u 2,387.28INTDR 850056 Ferret. Americ. 178254 Tubo 8"x19', pvc SDR-26 u 4,253.72INTDR 850057 Ferret. Americ. 225211 Tubo 2"x19', pvc SDR-32.5 u 263.92INTDR 850058 Ferret. Americ. 178236 Tubo 3"x19', pvc SDR-32.5 u 583.62INTDR 850059 Ferret. Americ. 178241 Tubo 4"x19', pvc SDR-32.5 u 892.36INTDR 850060 Ferret. Americ. 178247 Tubo 6"x19', pvc SDR-32.5 u 1,917.48INTDR 850061 Ferret. Americ. 178253 Tubo 8"x19', pvc SDR-32.5 u 3,254.96INTDR 850062 Ferret. Americ. 178230 Tubo 2"x19', pvc SDR-41 u 209.65INTDR 850063 Ferret. Americ. 178235 Tubo 3"x19', pvc SDR-41 u 428.04INTDR 850064 Ferret. Americ. 178240 Tubo 4"x19', pvc SDR-41 u 264.04INTDR 850065 Ferret. Americ. 178246 Tubo 6"x19', pvc SDR-41 u 1,490.60INTDR 850066 Ferret. Americ. 178252 Tubo 8"x19', pvc SDR-41 u 2,459.20INTDR 850067 Ferret. Americ. 015497 Yee 2"x2", pvc dren. u 17.45INTDR 850068 Ferret. Americ. 015496 Yee 3"x3", pvc dren. u 55.97INTDR 850069 Ferret. Americ. 015495 Yee 4"x4", pvc dren. u 59.14INTDR 850070 Ferret. Americ. 015529 Yee 6"x6", pvc dren. u 883.91INTDR 850071 Ferret. Americ. 015494 Yee red. 3"x2", pvc dren. u 32.83INTDR 850072 Ferret. Americ. 035991 Yee red. 4"x2", pvc dren. u 59.00INTDR 850073 Ferret. Americ. 015492 Yee red. 4"x3", pvc dren. u 70.04INTDR 850074 Ferret. Americ. 015528 Yee red. 6"x4", pvc dren. u 822.00

INTPR 870000 TUBERIAS Y PIEZAS PVC PRESION:INTPR 870001 Ferret. Americ. 015871 Adapt. hembra ½", pvc presión u 2.53INTPR 870002 Ferret. Americ. 015872 Adapt. hembra ¾", pvc presión u 3.55INTPR 870003 Ferret. Americ. 015873 Adapt. hembra 1", pvc presión u 6.50INTPR 870004 Ferret. Americ. 015874 Adapt. hembra 1 ½", pvc presión u 11.11INTPR 870005 Ferret. Americ. 015875 Adapt. hembra 2", pvc presión u 15.81

Page 16: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 14

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INTPR 870006 Ferret. Americ. 015095 Adapt. hembra 3", pvc presión u 32.89INTPR 870007 Ferret. Americ. 015876 Adapt. hembra 4", pvc presión u 35.55INTPR 870008 Ferret. Americ. Adapt. hembra 6", pvc presión uINTPR 870009 Ferret. Americ. 015864 Adapt. macho ½", pvc presión u 2.00INTPR 870010 Ferret. Americ. 015865 Adapt. macho ¾", pvc presión u 3.02INTPR 870011 Ferret. Americ. 015866 Adapt. macho 1", pvc presión u 5.07INTPR 870012 Ferret. Americ. 015867 Adapt. macho 1 ½", pvc presión u 11.99INTPR 870013 Ferret. Americ. 015868 Adapt. macho 2", pvc presión u 14.65INTPR 870014 Ferret. Americ. 015869 Adapt. macho 3", pvc presión u 43.43INTPR 870015 Ferret. Americ. 015870 Adapt. macho 4", pvc presión u 64.96INTPR 870016 Ferret. Americ. 102417 Adapt. macho 6", pvc presión u 316.38INTPR 870017 Ferret. Americ. 015877 Codo ½"x90, pvc presión u 3.54INTPR 870018 Ferret. Americ. 015878 Codo ¾"x90, pvc presión u 5.05INTPR 870019 Ferret. Americ. 015879 Codo 1"x90, pvc presión u 8.09INTPR 870020 Ferret. Americ. 015880 Codo 1 ½"x90, pvc presión u 14.65INTPR 870021 Ferret. Americ. 015881 Codo 2"x90, pvc presión u 25.38INTPR 870022 Ferret. Americ. 015882 Codo 3"x90, pvc presión u 71.21INTPR 870023 Ferret. Americ. 015883 Codo 4"x90, pvc presión u 114.84INTPR 870024 Ferret. Americ. 015533 Codo 6"x90, pvc presión u 869.00INTPR 870025 Ferret. Americ. 015895 Reduc. bushing ¾"x½", pvc presión u 3.07INTPR 870026 Ferret. Americ. 015896 Reduc. bushing 1" x ¾'', pvc presión u 2.53INTPR 870027 Ferret. Americ. 015899 Reduc. bushing 1 ½"x1", pvc presión u 24.48INTPR 870028 Ferret. Americ. 015902 Reduc. bushing 2"x1", pvc presión u 41.02INTPR 870029 Ferret. Americ. 082369 Reduc. bushing 3" x 1 ½'', pvc presión u 70.69INTPR 870030 Ferret. Americ. 082206 Reduc. bushing 4"x2", pvc presión u 176.32INTPR 870031 Ferret. Americ. 082207 Reduc. bushing 4"x3", pvc presión u 185.14INTPR 870032 Ferret. Americ. 015904 Tee ½", pvc presión u 4.55INTPR 870033 Ferret. Americ. 015905 Tee ¾", pvc presión u 5.56INTPR 870034 Ferret. Americ. 015906 Tee 1", pvc presión u 9.59INTPR 870035 Ferret. Americ. 015907 Tee 1 ½", pvc presión u 20.20INTPR 870036 Ferret. Americ. 015908 Tee 2", pvc presión u 30.30INTPR 870037 Ferret. Americ. 015909 Tee 3", pvc presión u 86.36INTPR 870038 Ferret. Americ. 015910 Tee 4", pvc presión u 103.24INTPR 870039 Ferret. Americ. 062281 Tee 6", pvc presión u 1,252.16INTPR 870040 Ferret. Americ. 178216 Tubo ½"x19', pvc SCH-40 u 119.48INTPR 870041 Ferret. Americ. 178220 Tubo ¾"x19', pvc SCH-40 u 157.76INTPR 870042 Ferret. Americ. 178223 Tubo 1"x19', pvc SCH-40 u 264.34INTPR 870043 Ferret. Americ. 178228 Tubo 1 ½"x19', pvc SCH-40 u 359.60INTPR 870044 Ferret. Americ. 178233 Tubo 2"x19', pvc SCH-40 u 487.20INTPR 870045 Ferret. Americ. 178238 Tubo 3"x19', pvc SCH-40 u 1,194.80INTPR 870046 Ferret. Americ. 178244 Tubo 4"x19', pvc SCH-40 u 1,433.76INTPR 870047 Ferret. Americ. 178250 Tubo 6"x19', pvc SCH-40 u 2,603.04INTPR 870048 Ferret. Americ. 015959 Unión univ. ½", pvc presión u 18.00INTPR 870049 Ferret. Americ. 015963 Unión univ. ¾", pvc presión u 26.00INTPR 870050 Ferret. Americ. 015964 Unión univ. 1", pvc presión u 24.91INTPR 870051 Ferret. Americ. 028007 Unión univ. 1 ½", pvc presión u 87.00INTPR 870052 Ferret. Americ. 028008 Unión univ. 2", pvc presión u 156.99INTPR 870053 Ferret. Americ. 036793 Unión univ. 3", pvc presión u 242.44INTPR 870054 Ferret. Americ. 055394 Unión univ. 4", pvc presión u 706.00

INVEN 890000 VENTANAS DE ALUMINIO:INVEN 890001 Ferret. Americ. 291395 Masilla blanca siliconada, tubo u 83.09INVEN 890002 Induca MS9017-11 Masilla bce. siliconada, tubo u 86.35INVEN 890003 Induca VF0001-11 Molduras alum. bce., base, para vidrios fijos. 19 pies m 99.55INVEN 890004 Induca PC0010-11 Molduras alum. bce., tapa, para vidrios fijos. 19 pies m 60.29INVEN 890005 Induca VS9002-00 Operador p/vent. manig. AA alum. nat. u 102.59INVEN 890006 Induca VS9002-11 Operador p/vent. manig. AA alum. bce. u 103.02INVEN 890007 Induca VS9005-00 Operador ojo p/vent. "standard" alum. nat. u 28.21INVEN 890008 Induca Palo de 6' para operadores u 178.27INVEN 890009 Induca MS9002-00 "Silicone" claro en tubo u 176.11INVEN 890010 Induca Transporte e instalación (Porcentaje sobre el costo) % 12.00%INVEN 890011 Induca PC0006-11 Tubular 4"x1 ¾" alum. anodiz. bce., 19 pie m 438.85INVEN 890012 Induca PC0006-03 Tubular 4"x1 ¾" alum. anodiz. normal, 19 pie m 433.24INVEN 890013 Induca PC0006-26 Tubular 4"x1 ¾" alum. bco., 19 pie m 494.93INVEN 890014 Induca VABIS Vent. abisagr. alum. anod. normal, v. claro mart. (w2.5 x h1.2 m.) m2 2,943.63INVEN 890015 Induca VABIS Vent. abisagr. alum. anod. normal, v. bce. mart. (w2.5 x h1.2 m.) m2 2,993.93INVEN 890016 Induca VABIS Vent. abisagr. alum. anod. bce., v. claro mart. (w2.5 x h1.2 m.) m2 3,020.57INVEN 890017 Induca VABIS Vent. abisagr. alum. anod. bce., v. bce. mart. (w2.5 x h1.2 m.) m2 3,071.02INVEN 890018 Induca VCORR Vent. corred. alum. anod. normal, v. claro mart. (w2.5 x h1.2 m.) m2 3,134.85INVEN 890019 Induca VCORR Vent. corred. alum. anod. normal, v. bce. mart. (w2.5 x h1.2 m.) m2 3,182.73INVEN 890020 Induca VCORR Vent. corred. alum. anod. normal, v. "Bluegreen" (w2.5 x h1.2 m.) m2 3,481.95INVEN 890021 Induca VCORR Vent. corred. alum. anod. normal, v. reflect. claro (w2.5 x h1.2 m.) m2 3,820.78INVEN 890022 Induca VCORR Vent. corred. alum. anod. normal, con espejo (w2.5 x h1.2 m.) m2 3,626.57INVEN 890023 Induca VCORR Vent. corred. alum. anod. bce., v. claro mart. (w2.5 x h1.2 m.) m2 2,724.63INVEN 890024 Induca VCORR Vent. corred. alum. anod. bce., v. bce. mart. (w2.5 x h1.2 m.) m2 2,772.50INVEN 890025 Induca VCORR Vent. corred. alum. anod. bce., v. reflectivo (w2.5 x h1.2 m.) m2 3,410.56INVEN 890026 Induca VCORR Vent. corred. alum. anod. bce., con espejo (w2.5 x h1.2 m.) m2 3,216.49INVEN 890027 Induca VCORR Vent. corred. alum. bco., v. claro (w2.5 x h1.2 m.) m2 3,171.75INVEN 890028 Induca VCORR Vent. corred. alum. bco., v. bce. liso (w2.5 x h1.2 m.) m2 3,267.36INVEN 890029 Induca VCORR Vent. corred. alum. bco., v. "Bluegreen" (w2.5 x h1.2 m.) m2 3,489.50INVEN 890030 Induca VCORR Vent. corred. alum. bco., v. reflect. claro (w2.5 x h1.2 m.) m2 3,631.84INVEN 890031 Induca VCORR Vent. corred. alum. bco., con espejo (w2.5 x h1.2 m.) m2 3,634.12INVEN 890032 Induca VPROYALD Vent. proyect. alum. anod. normal, v. claro mart. (w2.73 x h1.47 m.) m2 2,016.14INVEN 890033 Induca VPROYALD Vent. proyect. alum. anod. normal, v. bce. mart. (w2.73 x h1.47 m.) m2 2,067.79INVEN 890034 Induca VPROYALD Vent. proyect. alum. bce., v. claro mart. (w2.73 x h1.47 m.) m2 2,248.56INVEN 890035 Induca VPROYALD Vent. proyect. alum. bce., v. bce. mart. (w2.73 x h1.47 m.) m2 2,300.22INVEN 890036 Induca VSSALM Vent. Salom AA manig, alum. blanco (w0.83 x h1.2 m.) m2 3,226.55INVEN 890037 Induca VSSALM Vent. Salom AA manig, alum. Blanco, reforzada (w0.83 x h1.2 m.) m2 5,402.91

Page 17: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 15

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA SUPLIDOR CODIGO D E S C R I P C I O N U. P.U. + ITBIS

INVEN 890038 Induca VSSALM Vent. Salom AA manig, alum. bce., reforzada (w0.83 x h1.2 m.) m2 5,521.36INVEN 890039 Induca VSSALM Vent. Salom AA manig, alum. bce. (w0.83 x h1.2 m.) m2 3,345.00INVEN 890040 Induca VSSALM Vent. Salom AA manig, alum. nat. (w0.83 x h1.2 m.) m2 2,069.49INVEN 890041 Induca VSSALM Vent. Salom AA manig, alum nat. v. claro (w0.83 x h1.2 m.) m2 3,787.11INVEN 890042 Induca VSSALM Vent. Salom AA manig, alum nat., v. claro mart. (w0.83 x h1.2 m.) m2 3,642.85INVEN 890043 Induca VSSALM Vent. Salom AA manig, alum nat., v. bce. mart. (w0.83 x h1.2 m.) m2 3,414.53INVEN 890044 Induca VSSALM Vent. Salom AA manig, alum bco., v. claro (w0.83 x h1.2 m.) m2 3,549.72INVEN 890045 Induca VSSALM Vent. Salom AA manig, alum bco., v. bce. mart. (w0.83 x h1.2 m.) m2 3,414.53INVEN 890046 Induca VSSALM Vent. Salom AA manig, alum bce., vidrio claro mart. (w0.83 x h1.2 m.) m2 3,761.73INVEN 890047 Induca VSSALM Vent. Salom AA manig, alum bce., vidrio bce. mart. (w0.83 x h1.2 m.) m2 3,533.41INVEN 890048 Induca VSSALM Vent. Salom AA manig, alum bce. v. bce. liso (w0.83 x h1.2 m.) m2 3,783.19INVEN 890049 Induca VSEALM Vent. Salom BB Pal. alum. blanco (w0.83 x h1.2 m.) m2 3,232.99INVEN 890050 Induca VSEALM Vent. Salom BB Pal. alum. bce. (w0.83 x h1.2 m.) m2 2,077.21INVEN 890051 Induca VSEALM Vent. Salom BB Pal. alum. nat. (w0.83 x h1.2 m.) m2 2,340.73INVEN 890052 Induca VSEALM Vent. Salom BB Pal. alum. bco., v. bce. mart. (w0.83 x h1.2 m.) m2 2,896.94INVEN 890053 Induca VSEALM Vent. Salom BB Pal. alum. bco., v. claro mart. (w0.83 x h1.2 m.) m2 3,125.26INVEN 890054 Induca VSEALM Vent. Salom BB Pal. alum. bce., v. bce. mart. (w0.83 x h1.2 m.) m2 2,372.92INVEN 890055 Induca VSEALM Vent. Salom BB Pal. alum. bce., v. claro mart. (w0.83 x h1.2 m.) m2 2,601.24INVEN 890056 Induca VSEALM Vent. Salom BB Pal. alum. nat., v. claro (w0.83 x h1.2 m.) m2 2,770.76INVEN 890057 Induca VSEALM Vent. Salom BB Pal. alum. nat., v. claro mart. (w0.83 x h1.2 m.) m2 2,902.09INVEN 890058 Induca VSEALM Vent. Salom BB Pal. alum. nat., v. bce. mart. (w0.83 x h1.2 m.) m2 2,635.15INVEN 890059 Induca Vidiro bce. transp. o mart. de ¼" m2 891.27INVEN 890060 Induca Vidiro claro transp. o mart. de ¼" m2 776.98

Page 18: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 16

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 16.00%

88.36% 1,160.00112.41% 1,659.09112.41% 1,659.09112.41% 1,659.09112.41% 1,659.09112.41% 1,659.09112.41% 1,659.09106.50% 1,849.99106.50% 1,849.99106.50% 1,849.99106.50% 1,849.99106.50% 1,849.99106.50% 1,849.99100.00% 25.44100.00% 25.44112.99% 10,500.00116.69% 7,011.83112.01% 5,285.2795.86% 13,997.0095.28% 9,387.0095.36% 7,174.99

104.58% 13,322.8298.47% 8,649.5298.62% 15,138.0098.42% 9,553.7698.92% 7,010.58

100.00% 820.00100.00% 820.00100.00% 750.00100.00% 1,100.00100.00% 300.00100.00% 199.50100.00% 280.00100.00% 750.00100.00% 500.00100.00% 425.00100.00% 750.00100.00% 750.00

100.27% 2,624,839.45100.27% 1,621,777.50

100.26% 203.78100.00% 4.00%

100.00% 125.29100.00% 196.03100.00% 137.81100.00% 218.87100.00% 149.61100.00% 237.30100.00% 173.19100.00% 277.10100.00% 182.77100.00% 287.42100.00% 190.13100.00% 305.84100.00% 205.61100.00% 328.68100.00% 550.26100.00% 641.97100.00% 651.80100.00% 709.94100.00% 678.83100.00% 799.19100.00% 2.32100.00% 9.28

100.00% 1,465.00100.00% 406.00100.00% 1,345.60100.00% 27.26100.00% 269.87100.00% 300.00100.00% 12,180.00100.00% 13,304.78

Page 19: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 17

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 44,822.40100.00% 6,142.20100.00% 5,974.00100.00% 6,198.75100.00% 6,198.75100.00% 1,483.29100.00% 1,682.15100.00% 225.91100.00% 2,734.33100.00% 2,989.32100.00% 247.83100.00% 70.30100.00% 137.75100.00% 88.16100.00% 89.00100.00% 2,534.60100.00% 5,351.00100.00% 4,314.01100.00% 2,440.93100.00% 7,132.00100.00% 4,100.60100.00% 4,268.00100.00% 5,328.17100.00% 4,716.00100.00% 7,585.00100.00% 13,180.00100.00% 20,725.67100.00% 21,329.50100.00% 18,596.25100.00% 27,377.00100.00% 11,742.00100.00% 13,906.00100.00% 701.00100.00% 2,688.88100.00% 148.00100.00% 62.00100.00% 23.93100.00% 6.88100.00% 7.12100.00% 21.98100.00% 2,302.99100.00% 2,778.00100.00% 139.00100.00% 1,570.35100.00% 3,366.61100.00% 3,675.17100.00% 809.97100.00% 1,077.14100.00% 869.00100.00% 81.55100.00% 1,381.91100.00% 1,614.43100.00% 1,316.89100.00% 7,830.00100.00% 358.15100.00% 4,796.48100.00% 2,943.00100.00% 2,920.00100.00% 1,850.20100.00% 6,431.01100.00% 3,786.29100.00% 25,386.00100.00% 14,215.80100.00% 3,814.02100.00% 249.01100.00% 464.00100.00% 2,688.88100.00% 353.00100.00% 35,837.04100.00% 11,530.48100.00% 11,958.44100.00% 37.00100.00% 1,601.99100.00% 1,697.08100.00% 1,187.96100.00% 719.99100.00% 2,302.60100.00% 2,188.00100.00% 165.00100.00% 338.99100.00% 388.99100.00% 482.40100.00% 586.03100.00% 292.32100.00% 4,794.58100.00% 3,611.00100.00% 14,696.01100.00% 578.00

Page 20: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 18

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 2,047.01100.00% 3,746.00100.00% 1,760.00100.00% 2,969.00100.00% 3,339.00100.00% 5,446.20100.00% 555.59100.00% 28.65100.00% 2,420.60100.00% 9,784.00100.00% 9,092.20100.00% 80.01100.00% 1,522.00100.00% 2,865.20100.00% 406.00100.00% 1,019.35100.00% 1,060.12100.00% 68.32100.00% 28.65100.00% 7,961.95100.00% 134.68100.00% 83.52100.00% 475.60100.00% 526.00100.00% 78.00100.00% 2,529.09100.00% 13.70100.00% 464.00100.00% 133.72100.00% 3,002.00100.00% 2,865.20100.00% 5,005.40100.00% 1,465.66100.00% 125.23100.00% 136.65100.00% 253.46100.00% 266.80100.00% 3,849.00100.00% 3,849.00

100.00% 29.00100.00% 33.11100.00% 39.00100.00% 71.43100.00% 35.00100.00% 35.00100.00% 12.50100.00% 8.50100.00% 243.00100.00% 9.67100.00% 4.64100.00% 12.85100.00% 5.41100.00% 12.97100.00% 16.56100.00% 45.83100.00% 62.19100.00% 36.83100.00% 8.43100.00% 458.20100.00% 2,692.36100.00% 2.02

100.00% 30.10100.00% 37.51100.00% 27.84100.00% 28.42100.00% 26.10100.00% 26.10100.00% 26.60100.00% 32.00100.00% 33.66100.00% 32.54100.00% 87.00100.00% 100.60100.00% 72.24100.00% 32.97100.00% 39.81100.00% 32.70100.00% 55.68100.00% 1.08100.00% 1.44100.00% 1.44100.00% 1.80100.00% 1.08100.00% 2.15

Page 21: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 19

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 2.15100.00% 1.44100.00% 2.87100.00% 2.87100.00% 2.15100.00% 4.31100.00% 2.15100.00% 2.15100.00% 2.87100.00% 2.15100.00% 2.87100.00% 1,508.00

100.00% 109.62

100.00% 6,904.00100.00% 7,135.00100.00% 10,058.23100.00% 40,403.00100.00% 17,981.00100.00% 16,116.00100.00% 28,384.99100.00% 26,000.00100.00% 19,250.00100.00% 15,912.00100.00% 38,470.00100.00% 31,620.00100.00% 1,865.00100.00% 2,384.99100.00% 3,338.00100.00% 6,850.00100.00% 3,650.00100.00% 6,364.99100.00% 7,314.99100.00% 10,195.74100.00% 11,209.98100.00% 13,800.00100.00% 17,575.00

100.00% 304.50100.00% 304.50100.00% 285.00100.00% 600.00100.00% 250.00100.00% 894.00100.00% 2,233.00100.00% 187.95100.00% 208.80100.00% 3,329.50100.00% 713.98

100.00% 353.03100.00% 382.45100.00% 411.88100.00% 470.72100.00% 588.40100.00% 647.23100.00% 764.92100.00% 882.59100.00% 1,000.27100.00% 1,088.53100.00% 1,176.79100.00% 1,294.47100.00% 7.05100.00% 417.81100.00% 63.80100.00% 129.44100.00% 500.13100.00% 176.52100.00% 58.85

100.00% 90.36100.00% 58.00100.00% 61.48100.00% 69.60100.00% 104.40100.00% 523.45100.00% 25.35100.00% 40.22100.00% 495.90100.00% 118,749.99100.00% 119.00100.00% 127.99

Page 22: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 20

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 35.26100.00% 484.88100.00% 1,388.52100.00% 1,267.30100.00% 28.65100.00% 352.64100.00% 24.24100.00% 7.98100.00% 0.50100.00% 1.50100.00% 2.03100.00% 3.20100.00% 9.42100.00% 22.04100.00% 22.04100.00% 1.65

101.39% 136.30101.45% 131.30101.15% 165.90101.54% 155.90100.00% 184.00

100.27% 36.7598.38% 49.25

100.00% 198.36100.00% 225.91100.00% 253.46100.00% 402.23100.00% 35.00100.00% 350.00100.00% 39.44100.00% 39.44100.00% 2,700.00100.00% 1,760.00100.00% 1,050.00100.00% 875.00100.00% 2,940.00100.00% 1,940.00100.00% 1,290.00100.00% 1,050.00100.00% 134.56100.00% 136.00100.00% 44.00100.00% 106.72100.00% 575.00100.00% 528.00100.00% 550.00100.00% 85.00100.00% 154.00100.00% 2,225.00100.00% 2,640.00100.00% 2,760.00100.00% 232.00100.00% 638.00

100.00% 278.01100.00% 180.88100.00% 3,915.00100.00% 3,480.00100.00% 2,850.12100.00% 1,097.00100.00% 504.39100.00% 48.72

100.00% 14.56100.00% 21.00100.00% 12.06100.00% 26.49100.00% 98.60100.00% 69.60100.00% 91.06100.00% 108.55100.00% 146.16100.00% 45.32100.00% 29.30100.00% 18.40100.00% 11.77100.00% 7.34100.00% 4.65100.00% 3.12100.00% 3.03

Page 23: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 21

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 75.01100.00% 136.17100.00% 133.40100.00% 330.60100.00% 377.00100.00% 32.48100.00% 40.50100.00% 31.32100.00% 52.00100.00% 319.00100.00% 4.58100.00% 5.75100.00% 10.75100.00% 27.84100.00% 31.32100.00% 126.00100.00% 200.10100.00% 103.00100.00% 141.00100.00% 226.00100.00% 299.00100.00% 1,736.00100.00% 707.00100.00% 58.00100.00% 33.78100.00% 121.29100.00% 94.77100.00% 144.33100.00% 70.12100.00% 343.50100.00% 158.72100.00% 1,767.00100.00% 1,584.00100.00% 1,767.00100.00% 3,594.00100.00% 29,768.00100.00% 1,706.00100.00% 2,635.89100.00% 411.80100.00% 527.80100.00% 1,121.00100.00% 1,238.00100.00% 1,780.60100.00% 5,963.00100.00% 18,733.01100.00% 52.00100.00% 98.00100.00% 99.76100.00% 385.00100.00% 274.92100.00% 399.04100.00% 2,693.26100.00% 2,693.26100.00% 34.68100.00% 69,024.42100.00% 15.31100.00% 16.18100.00% 14.24100.00% 14.76100.00% 527.80100.00% 157.76100.00% 10.95100.00% 603.20100.00% 414.12100.00% 696.00100.00% 24.59100.00% 70.83100.00% 475.60

100.00% 116.79100.00% 448.39100.00% 1,609.20100.00% 1,609.20100.00% 2,135.15100.00% 3,594.89100.00% 30,460.86100.00% 1,877.60100.00% 3,290.84100.00% 2,128.70100.00% 77.85100.00% 248.47100.00% 48.40100.00% 53.20100.00% 12.76100.00% 1,886.72100.00% 503.56100.00% 4,259.64

Page 24: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 22

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 1,465.58100.00% 680.32100.00% 74.47100.00% 4,285.33100.00% 140,558.82100.00% 1,743.71100.00% 2,203.88100.00% 1,102.58100.00% 296,960.00100.00% 336,400.00100.00% 191.26100.00% 4,628.67100.00% 466.76

100.00% 4,628.67

100.00% 197.20100.00% 2,175.00100.00% 116.00100.00% 154.28100.00% 246.00100.00% 161.00100.00% 139.20100.00% 139.00100.00% 139.58100.00% 113,899.99100.00% 325.09100.00% 1,179.14100.00% 220.40100.00% 185.60100.00% 192.85100.00% 436.18100.00% 319.00100.00% 265,152.16

100.00% 928.00100.00% 928.00100.00% 1,044.00100.00% 1,740.00100.00% 2,088.00100.00% 1,740.00100.00% 116.00100.00% 58.00100.00% 1,160.00100.00% 58.00100.00% 185.60100.00% 203.00

100.27% 649.37100.26% 222.49100.24% 296.61100.25% 371.55100.25% 864.32100.26% 1,053.98100.27% 768.50100.28% 1,650.68100.31% 153.35100.26% 11,710.81100.26% 3,831.63100.26% 7,035.60100.00% 10,039.92

100.00% 968.99100.00% 1,418.00100.00% 278.40100.00% 1,416.70100.00% 319.00100.00% 1,070.32100.00% 1,479.00100.00% 1,650.00100.00% 2,001.00100.00% 1,682.00100.00% 336.54100.00% 527.10100.00% 754.31100.00% 1,150.00100.00% 17.75100.00% 22.01100.00% 968.31100.00% 69.60100.00% 92.80100.00% 251.78100.00% 3,756.00100.00% 747.01

Page 25: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 23

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 896.15100.00% 951.20100.00% 2,098.94100.00% 220.40100.00% 353.80100.00% 524.00100.00% 821.00100.00% 264.48100.00% 28.03100.00% 12.25100.00% 10.50100.00% 30.00100.00% 18.75100.00% 29.50100.00% 1,960.01100.00% 2,818.00100.00% 2,799.00100.00% 4,640.00100.00% 7,928.00100.00% 330.60100.00% 377.00100.00% 522.00100.00% 551.00100.00% 838.88100.00% 783.00100.00% 1,090.40100.00% 962.80100.00% 1,392.00100.00% 1,146.08100.00% 1,397.01100.00% 2,860.00

100.00% 0.35 100.00% 4,408.00100.00% 4,582.00100.00% 4,698.00100.00% 4,872.00100.00% 5,104.00100.00% 5,336.00100.00% 5,452.00100.00% 5,626.00100.00% 5,800.00100.00% 5,974.00100.00% 6,438.00100.00% 6,960.00100.00% 5,220.00100.00% 522.00100.00% 23.20

100.00% 3,034.40100.00% 324.80100.00% 396.98100.00% 505.24100.00% 552.00100.00% 2,540.01100.00% 2,694.00100.00% 4,100.00

100.25% 473.28

100.00% 3,617.37100.00% 2,305.86100.00% 1,794.50100.00% 2,154.32100.00% 128.06

100.00% 513.00100.00% 707.99100.00% 1,129.00100.00% 1,760.00100.00% 2,662.20100.00% 3,037.09100.00% 4,595.00100.00% 8,123.00100.00% 412.00100.00% 473.00100.00% 1,189.00100.00% 1,783.00100.00% 2,964.00100.00% 5,728.00100.00% 8,550.00100.00% 188.00100.00% 301.00

Page 26: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 24

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 446.99100.00% 1,405.05100.00% 1,487.70100.00% 2,790.00100.00% 4,258.13100.00% 1,679.68100.00% 2,662.20100.00% 6,061.00100.00% 2,396.85100.00% 232.00100.00% 453.00100.00% 1,001.88100.00% 3,849.00100.00% 266.80100.00% 3,849.00

100.00% 135.00100.00% 91.28100.00% 134.56100.00% 143.00100.00% 24.79100.00% 0.52100.00% 45.24100.00% 33.76100.00% 47.56100.00% 39.20100.00% 29.00100.00% 37.15100.00% 29.00100.00% 32.48100.00% 42.00100.00% 32.48100.00% 34.80100.00% 27.84100.00% 38.01100.00% 38.11100.00% 34.80100.00% 475.99100.00% 847.00100.00% 469.01100.00% 707.99100.00% 1,218.00100.00% 1,150.00100.00% 154.28100.00% 130.00100.00% 3.00100.00% 218.08100.00% 425.05100.00% 498.80100.00% 471.61

100.00% 16.53100.00% 13.22100.00% 804.45100.00% 474.41100.00% 55.10100.00% 99.18100.00% 148.77100.00% 159.79100.00% 30.86100.00% 27.50100.00% 80.94100.00% 101.37100.00% 77.14100.00% 123.42100.00% 27.55100.00% 457.33100.00% 511.56

100.00% 114.81100.00% 11.99100.00% 114.81100.00% 139.00100.00% 745.51100.00% 1,124.92100.00% 221.00100.00% 324.10100.00% 1,088.00100.00% 1,095.01100.00% 1,095.01100.00% 995.00100.00% 1,095.01

100.00% 245.00

Page 27: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 25

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 675.00100.00% 1,102.00100.00% 914.64

100.00% 458.00100.00% 719.00100.00% 319.00100.00% 11.60100.00% 1,292.00100.00% 191.01100.00% 651.00100.00% 448.00100.00% 609.00100.00% 423.40

100.00% 1,572.99100.00% 2,038.00100.00% 1,400.00100.00% 1,645.00100.00% 1,165.00100.00% 1,388.52100.00% 545.14100.00% 382.75100.00% 772.10100.00% 574.20100.00% 455.88100.00% 8.12100.00% 9.28100.00% 12.76100.00% 30.16100.00% 5.80100.00% 806.20100.00% 382.80100.00% 806.20100.00% 545.14100.00% 639.30100.00% 371.15100.00% 315.49100.00% 537.81100.00% 391.43100.00% 1,162.32100.00% 638.00100.26% 1,291.81100.26% 1,370.19100.00% 807.97100.00% 743.47100.00% 1,157.68100.00% 1,095.04100.00% 684.40100.00% 506.00100.00% 553.00100.00% 0.92100.00% 0.72100.00% 0.89100.00% 0.90100.00% 1.30100.00% 1.95100.00% 0.75100.00% 44.73100.00% 0.85100.00% 0.88100.00% 65.32100.00% 64.96100.00% 70.73100.00% 44.38100.00% 79.09100.00% 58.00100.26% 494.83100.27% 418.19100.26% 494.83100.27% 418.19100.27% 425.20100.00% 183.28100.00% 102.28100.00% 123.75

100.27% 632,970.24

100.00% 14,599.76100.00% 16,820.00

100.00% 3,132.00100.27% 1,471.16

Page 28: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 26

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.27% 1,048.27100.27% 962.59100.27% 389.64100.27% 1,734.19100.26% 38.79100.27% 2,583.99100.27% 2,554.25100.27% 2,680.95100.27% 2,645.61100.27% 2,906.09100.27% 3,050.39100.27% 3,317.07100.27% 2,251.39100.27% 2,221.71100.27% 2,348.41100.27% 2,317.46100.27% 2,717.79100.27% 2,984.46100.27% 2,525.58100.27% 2,492.29100.27% 2,622.53100.27% 2,587.97100.27% 2,847.68100.27% 2,991.98100.27% 3,242.75100.27% 13,300.99100.27% 13,125.70100.27% 13,475.35100.27% 13,297.76100.27% 13,111.71100.27% 12,938.92100.27% 13,286.49100.27% 13,111.40100.27% 14,219.23100.27% 14,031.85100.27% 14,393.59100.27% 14,203.91100.27% 17,292.86100.27% 17,064.97100.27% 17,688.47100.27% 17,455.37100.27% 16,544.28100.27% 16,326.26100.27% 16,939.89100.27% 16,716.64100.27% 18,396.97100.27% 18,154.53100.27% 18,792.58100.27% 18,544.92100.27% 328.26100.27% 251.09100.27% 1,033.78100.00% 12.00%

100.00% 2,108.72100.00% 3,873.92100.00% 7,043.52100.00% 5,719.99100.00% 8,029.61100.00% 11,779.80100.00% 8.99

100.00% 27.40100.00% 42.98100.00% 8.92100.00% 16.62100.00% 420.96100.00% 443.12100.00% 7.93100.00% 18.25100.00% 123.42100.00% 252.00100.00% 9.50100.00% 27.55100.00% 11.57100.00% 25.35100.00% 127.83100.00% 203.87

100.00% 15.10100.00% 14.50100.00% 18.75100.00% 59.00100.00% 52.69100.00% 73.00

Page 29: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 27

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 118.00100.00% 123.42100.00% 320.53100.00% 11.99100.00% 16.50100.00% 25.00100.00% 72.00100.00% 58.00100.00% 111.00100.00% 108.00100.00% 233.03100.00% 250.82100.00% 12.75100.00% 15.37100.00% 21.00100.00% 35.99100.00% 97.44100.00% 112.40100.00% 176.32100.00% 282.00100.00% 42.00100.00% 42.00100.00% 64.99100.00% 86.00100.00% 76.00100.00% 104.49100.00% 150.80100.00% 97.44100.00% 151.99100.00% 417.60100.00% 609.00100.00% 533.60100.00% 162.24100.00% 870.00100.00% 667.00100.00% 8.31100.00% 12.06100.00% 16.00100.00% 22.50100.00% 60.00100.00% 47.50100.00% 57.00100.00% 301.60100.00% 11.75100.00% 19.15100.00% 15.75100.00% 47.50100.00% 55.10100.00% 35.50100.00% 9.25100.00% 16.50100.00% 9.76100.00% 14.24100.00% 36.60100.00% 44.00100.00% 112.11100.00% 108.30100.00% 214.99100.00% 7.25100.00% 10.50100.00% 14.50100.00% 26.00100.00% 39.00100.00% 31.51100.00% 116.00100.00% 209.00100.00% 17.86100.00% 22.01100.00% 48.87100.00% 62.00100.00% 69.99100.00% 148.77100.00% 116.00100.00% 315.00100.00% 293.00100.00% 522.00100.00% 693.68100.00% 980.00100.00% 1,160.00100.00% 1,531.00100.00% 1,788.00100.00% 2,900.00100.00% 3,375.60100.00% 5,005.40100.00% 32.64100.00% 58.00100.00% 80.23100.00% 122.00

Page 30: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 28

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 142.00100.00% 197.20100.00% 178.00100.00% 672.00100.00% 797.00

100.00% 921.01100.00% 238.00100.00% 43.00100.00% 1,282.55100.00% 554.48100.00% 493.52100.00% 194.88100.00% 13.06100.00% 35.31100.00% 60.32100.00% 285.00100.00% 8.35100.00% 26.13100.00% 40.62100.00% 377.00100.00% 34.93100.00% 15.29100.00% 29.00100.00% 29.58100.00% 600.00100.00% 83.52100.00% 78.40100.00% 175.00100.00% 1,762.21100.00% 13.92100.00% 43.45100.00% 69.69100.00% 19.88100.00% 55.01100.00% 78.88100.00% 980.20100.00% 38.64100.00% 52.20100.00% 50.27100.00% 2,116.12100.00% 2,382.11100.00% 136.78100.00% 129.92100.00% 243.60100.00% 340.24100.00% 860.72100.00% 1,842.08100.00% 407.16100.00% 970.00100.00% 1,498.72100.00% 3,230.60100.00% 5,463.60100.00% 50.87100.00% 71.00100.00% 123.84100.00% 214.01100.00% 256.04100.00% 676.26100.00% 1,067.20100.00% 2,387.28100.00% 4,253.72100.00% 263.92100.00% 583.62100.00% 892.36100.00% 1,917.48100.00% 3,254.96100.00% 209.65100.00% 428.04100.00% 264.04100.00% 1,490.60100.00% 2,459.20100.00% 17.45100.00% 55.97100.00% 59.14100.00% 883.91100.00% 32.83100.00% 59.00100.00% 70.04100.00% 822.00

100.00% 2.53100.00% 3.55100.00% 6.50100.00% 11.11100.00% 15.81

Page 31: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 29

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.00% 32.89100.00% 35.55

100.00% 2.00100.00% 3.02100.00% 5.07100.00% 11.99100.00% 14.65100.00% 43.43100.00% 64.96100.00% 316.38100.00% 3.54100.00% 5.05100.00% 8.09100.00% 14.65100.00% 25.38100.00% 71.21100.00% 114.84100.00% 869.00100.00% 3.07100.00% 2.53100.00% 24.48100.00% 41.02100.00% 70.69100.00% 176.32100.00% 185.14100.00% 4.55100.00% 5.56100.00% 9.59100.00% 20.20100.00% 30.30100.00% 86.36100.00% 103.24100.00% 1,252.16100.00% 119.48100.00% 157.76100.00% 264.34100.00% 359.60100.00% 487.20100.00% 1,194.80100.00% 1,433.76100.00% 2,603.04100.00% 18.00100.00% 26.00100.00% 24.91100.00% 87.00100.00% 156.99100.00% 242.44100.00% 706.00

100.00% 83.09100.27% 86.12100.28% 99.27100.28% 60.12100.27% 102.31100.27% 102.74100.25% 28.14100.27% 177.79100.27% 175.64100.00% 12.00%100.27% 437.66100.27% 432.07100.27% 493.59100.27% 2,935.65100.27% 2,985.81100.27% 3,012.38100.27% 3,062.68100.27% 3,126.34100.27% 3,174.08100.27% 3,472.49100.27% 3,810.41100.27% 3,616.73100.27% 2,717.24100.27% 2,764.99100.27% 3,401.31100.27% 3,207.77100.27% 3,163.15100.27% 3,258.50100.27% 3,480.03100.27% 3,621.98100.27% 3,624.26100.27% 2,010.66100.27% 2,062.19100.27% 2,242.45100.27% 2,293.97100.27% 3,217.79100.27% 5,388.25

Page 32: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 30

GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. INSUMOSINDICE ABR 2010

100.27% 5,506.38100.27% 3,335.93100.27% 2,063.87100.27% 3,776.83100.27% 3,632.97100.27% 3,405.26100.27% 3,540.09100.27% 3,405.26100.27% 3,751.52100.27% 3,523.82100.27% 3,772.92100.27% 3,224.22100.27% 2,071.57100.27% 2,334.37100.27% 2,889.08100.27% 3,116.78100.27% 2,366.48100.27% 2,594.18100.27% 2,763.25100.27% 2,894.22100.27% 2,627.99100.27% 888.86100.27% 774.87

Page 33: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 15

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. REND. MAT.REFERENCIA D E S C R I P C I O N U. REND.

5000000 RENDIMIENTO DE MATERIALES

5020000 ACEROS Y ALAMBRES GALVANIZADOS:5020100 m / lb 26.715020200 Alambre galv. #18, 1.00 lb. (Diám.=0.385 m., Vueltas=22) m / lb 26.715020300 Atado varillas redondas 3/8" x 20' 20 qq 22.265020301 Atado varillas redondas 3/8" x 25' 25 qq 22.285020302 Atado varillas redondas 3/8" x 30' 30 qq 22.115020303 Atado varillas redondas 3/8" x 35' 35 qq5020304 Atado varillas redondas 3/8" x 40' 40 qq 22.265020305 Atado varillas redondas 3/8" x 45' 45 qq5020306 Atado varillas redondas 3/8" x 50' 50 qq5020400 Atado varillas redondas 1/2" x 20' 20 qq 22.185020401 Atado varillas redondas 1/2" x 25' 25 qq 22.215020402 Atado varillas redondas 1/2" x 30' 30 qq 22.245020403 Atado varillas redondas 1/2" x 35' 35 qq 22.215020404 Atado varillas redondas 1/2" x 40' 40 qq 22.185020405 Atado varillas redondas 1/2" x 45' 45 qq5020406 Atado varillas redondas 1/2" x 50' 50 qq5020500 Atado varillas redondas 3/4" x 20' 20 qq 22.235020501 Atado varillas redondas 3/4" x 25' 25 qq 22.535020502 Atado varillas redondas 3/4" x 30' 30 qq 22.535020503 Atado varillas redondas 3/4" x 35' 35 qq 22.085020504 Atado varillas redondas 3/4" x 40' 40 qq 22.235020505 Atado varillas redondas 3/4" x 45' 45 qq 22.305020506 Atado varillas redondas 3/4" x 50' 50 qq 22.535020600 Atado varillas redondas 1" x 20' 20 qq 22.435020601 Atado varillas redondas 1" x 25' 25 qq 22.705020602 Atado varillas redondas 1" x 30' 30 qq 22.435020603 Atado varillas redondas 1" x 35' 35 qq 22.435020604 Atado varillas redondas 1" x 40' 40 qq 22.435020605 Atado varillas redondas 1" x 45' 45 qq 22.835020606 Atado varillas redondas 1" x 50' 50 qq5020700 Cant. varillas redondas por Atado 3/8" x 20' 20 u 2965020701 Cant. varillas redondas por Atado 3/8" x 25' 25 u 2375020702 Cant. varillas redondas por Atado 3/8" x 30' 30 u 1965020703 Cant. varillas redondas por Atado 3/8" x 35' 35 u5020704 Cant. varillas redondas por Atado 3/8" x 40' 40 u 1485020705 Cant. varillas redondas por Atado 3/8" x 45' 45 u5020706 Cant. varillas redondas por Atado 3/8" x 50' 50 u5020800 Cant. varillas redondas por Atado 1/2" x 20' 20 u 1665020801 Cant. varillas redondas por Atado 1/2" x 25' 25 u 1335020802 Cant. varillas redondas por Atado 1/2" x 30' 30 u 1115020803 Cant. varillas redondas por Atado 1/2" x 35' 35 u 955020804 Cant. varillas redondas por Atado 1/2" x 40' 40 u 835020805 Cant. varillas redondas por Atado 1/2" x 45' 45 u5020806 Cant. varillas redondas por Atado 1/2" x 50' 50 u5020900 Cant. varillas redondas por Atado 3/4" x 20' 20 u 745020901 Cant. varillas redondas por Atado 3/4" x 25' 25 u 605020902 Cant. varillas redondas por Atado 3/4" x 30' 30 u 505020903 Cant. varillas redondas por Atado 3/4" x 35' 35 u 425020904 Cant. varillas redondas por Atado 3/4" x 40' 40 u 375020905 Cant. varillas redondas por Atado 3/4" x 45' 45 u 335020906 Cant. varillas redondas por Atado 3/4" x 50' 50 u 305021000 Cant. varillas redondas por Atado 1" x 20' 20 u 425021001 Cant. varillas redondas por Atado 1" x 25' 25 u 345021002 Cant. varillas redondas por Atado 1" x 30' 30 u 285021003 Cant. varillas redondas por Atado 1" x 35' 35 u 245021004 Cant. varillas redondas por Atado 1" x 40' 40 u 215021005 Cant. varillas redondas por Atado 1" x 45' 45 u 195021006 Cant. varillas redondas por Atado 1" x 50' 50 u5021100 Cant. varillas redondas por Quintal 3/8" x 20' 20 u 13.305021101 Cant. varillas redondas por Quintal 3/8" x 25' 25 u 10.645021102 Cant. varillas redondas por Quintal 3/8" x 30' 30 u 8.875021103 Cant. varillas redondas por Quintal 3/8" x 35' 35 u 7.605021104 Cant. varillas redondas por Quintal 3/8" x 40' 40 u 6.655021105 Cant. varillas redondas por Quintal 3/8" x 45' 45 u 5.915021106 Cant. varillas redondas por Quintal 3/8" x 50' 50 u 5.325021200 Cant. varillas redondas por Quintal 1/2" x 20' 20 u 7.495021201 Cant. varillas redondas por Quintal 1/2" x 25' 25 u 5.995021202 Cant. varillas redondas por Quintal 1/2" x 30' 30 u 4.995021203 Cant. varillas redondas por Quintal 1/2" x 35' 35 u 4.285021204 Cant. varillas redondas por Quintal 1/2" x 40' 40 u 3.745021205 Cant. varillas redondas por Quintal 1/2" x 45' 45 u 3.335021206 Cant. varillas redondas por Quintal 1/2" x 50' 50 u 2.995021300 Cant. varillas redondas por Quintal 3/4" x 20' 20 u 3.335021301 Cant. varillas redondas por Quintal 3/4" x 25' 25 u 2.665021302 Cant. varillas redondas por Quintal 3/4" x 30' 30 u 2.225021303 Cant. varillas redondas por Quintal 3/4" x 35' 35 u 1.905021304 Cant. varillas redondas por Quintal 3/4" x 40' 40 u 1.665021305 Cant. varillas redondas por Quintal 3/4" x 45' 45 u 1.485021306 Cant. varillas redondas por Quintal 3/4" x 50' 50 u 1.335021400 Cant. varillas redondas por Quintal 1" x 20' 20 u 1.875021401 Cant. varillas redondas por Quintal 1" x 25' 25 u 1.505021402 Cant. varillas redondas por Quintal 1" x 30' 30 u 1.255021403 Cant. varillas redondas por Quintal 1" x 35' 35 u 1.075021404 Cant. varillas redondas por Quintal 1" x 40' 40 u 0.945021405 Cant. varillas redondas por Quintal 1" x 45' 45 u 0.83

Alambre galv. #14, 1.00 lb. (Diám.=0.385 m., Vueltas=22)

Page 34: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 16

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. REND. MAT.REFERENCIA D E S C R I P C I O N U. REND.

5021406 Cant. varillas redondas por Quintal 1" x 50' 50 u 0.755021500 Peso en Quintales, varillas redondas 3/8" x 20' 20 u 0.07525021501 Peso en Quintales, varillas redondas 3/8" x 25' 25 u 0.09405021502 Peso en Quintales, varillas redondas 3/8" x 30' 30 u 0.11285021503 Peso en Quintales, varillas redondas 3/8" x 35' 35 u 0.13165021504 Peso en Quintales, varillas redondas 3/8" x 40' 40 u 0.15045021505 Peso en Quintales, varillas redondas 3/8" x 45' 45 u 0.16925021506 Peso en Quintales, varillas redondas 3/8" x 50' 50 u 0.18805021600 Peso en Quintales, varillas redondas 1/2" x 20' 20 u 0.13365021601 Peso en Quintales, varillas redondas 1/2" x 25' 25 u 0.16705021602 Peso en Quintales, varillas redondas 1/2" x 30' 30 u 0.20045021603 Peso en Quintales, varillas redondas 1/2" x 35' 35 u 0.23385021604 Peso en Quintales, varillas redondas 1/2" x 40' 40 u 0.26725021605 Peso en Quintales, varillas redondas 1/2" x 45' 45 u 0.30065021606 Peso en Quintales, varillas redondas 1/2" x 50' 50 u 0.33405021700 Peso en Quintales, varillas redondas 3/4" x 20' 20 u 0.30045021701 Peso en Quintales, varillas redondas 3/4" x 25' 25 u 0.37555021702 Peso en Quintales, varillas redondas 3/4" x 30' 30 u 0.45065021703 Peso en Quintales, varillas redondas 3/4" x 35' 35 u 0.52575021704 Peso en Quintales, varillas redondas 3/4" x 40' 40 u 0.60085021705 Peso en Quintales, varillas redondas 3/4" x 45' 45 u 0.67595021706 Peso en Quintales, varillas redondas 3/4" x 50' 50 u 0.75105021800 Peso en Quintales, varillas redondas 1" x 20' 20 u 0.53405021801 Peso en Quintales, varillas redondas 1" x 25' 25 u 0.66755021802 Peso en Quintales, varillas redondas 1" x 30' 30 u 0.80105021803 Peso en Quintales, varillas redondas 1" x 35' 35 u 0.93455021804 Peso en Quintales, varillas redondas 1" x 40' 40 u 1.06805021805 Peso en Quintales, varillas redondas 1" x 45' 45 u 1.20155021806 Peso en Quintales, varillas redondas 1" x 50' 50 u 1.3350

5040000 BLOQUES:5040001 Bloques de cualquier tipo 20 x 40 cms. u / m2 12.505040002 Medios Bloques 20 x 20 cms. u / m2 25.00

5060000 CAL, CEMENTOS, ADITIVOS, CURADORES, ENDURECEDORES, SELLADORES:5060001 Aditivo imperm. P/horm. 180 kg/cm2 "SX-PEL", 5 gl. gl / m3 0.265060002 Aditivo imperm. P/horm. 210 kg/cm2 "SX-PEL", 5 gl. gl / m35060003 Aditivo imperm. P/horm. 240 kg/cm2 "SX-PEL", 5 gl. gl / m35060004 Aditivo imperm. P/horm. 280 kg/cm2 "SX-PEL", 5 gl. gl / m35060005 Aditivo retard. "SX-KRETE-R", 5 gl. gl / m3 0.20635060006 Cal "Pomier" o similar, 50 lbs. (en mortero empañete) fda / m3 3.065060007 Curad., sellad. "SUPRACURE PLUS", 5 gl., 20 m2/gl. gl / m2 0.055060008 Curad., sellad., endur. "SUPRACURE", 5gls., 20 m2/gl. gl / m2 0.055060009 Endur. Met. / pisos "DURAPLATE NR", 100 lb., .10 m2/lb. Lb / m2 0.105060010 Resina epóxica "Pro-flex" para junta de piso, 231 pulg.3/gl. gl / pulg3 0.0043295060011 Sellad. horm. visto "SUPRACURE PX", 5gl., 20 m2/gl. gl / m2 0.05

5080000 CEMENTO PVC (NUMERO DE JUNTAS POR GL.):5080001 En ½" juntas 2,800.005080002 En ¾" juntas 1,600.005080003 En 1" juntas 1,200.005080004 En 1 ½" juntas 640.005080005 En 2" juntas 360.005080006 En 3" juntas 280.005080007 En 4" juntas 200.005080008 En 6" juntas 64.005080009 En 8" juntas 32.005080010 En 10" juntas 24.005080011 En 12" juntas 16.00

5100000 CEMENTO PVC (NUMERO DE JUNTAS POR KILO):5100001 En ½" juntas 700.005100002 En ¾" juntas 400.005100003 En 1" juntas 300.005100004 En 1 ½" juntas 160.005100005 En 2" juntas 90.005100006 En 3" juntas 70.005100007 En 4" juntas 50.005100008 En 6" juntas 16.005100009 En 8" juntas 8.005100010 En 10" juntas 6.005100011 En 12" juntas 4.00

5120000 CEMENTO PVC (NUMERO DE JUNTAS POR PINTA):5120001 En ½" juntas 350.005120002 En ¾" juntas 200.005120003 En 1" juntas 150.005120004 En 1 ½" juntas 80.005120005 En 2" juntas 45.005120006 En 3" juntas 35.005120007 En 4" juntas 25.005120008 En 6" juntas 8.005120009 En 8" juntas 4.005120010 En 10" juntas 3.005120011 En 12" juntas 2.00

5140000 CLAVOS (CANTIDAD x LIBRA):5140001 Clavos acero 1" lb 445.00

Page 35: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 17

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. REND. MAT.REFERENCIA D E S C R I P C I O N U. REND.

5140002 Clavos acero 1 ½" lb 137.005140003 Clavos acero 2" lb 105.005140004 Clavos acero 2 ½" lb 75.005140005 Clavos acero 3" lb 67.005140006 Clavos acero 4" lb 52.005140007 Clavos corrientes ¾" lb 2,064.005140008 Clavos corrientes 1" lb 1,513.005140009 Clavos corrientes 1 ½" lb 445.005140010 Clavos corrientes 2" lb 206.005140011 Clavos corrientes 2 ½" lb 87.005140012 Clavos corrientes 3" lb 63.005140013 Clavos corrientes 4" lb 29.005140014 Clavos galv. para cartón ¾" lb 322.005140015 Clavos de zinc 2 ½" lb 56.00

5160000 IMPERMEABILIZANTES:5160001 ALM, lata de 5 gl. gl / m2 0.095160002 Bitupol instalado, 3 mm., reforz. fibra vidrio, 5 años gar. rollo / m25160003 Bitupol instalado, 3 mm., reforz. con poliester, 10 años gar. rollo / m25160004 Bitupol instalado, 4 mm., reforz. con poliester, 10 años gar. rollo / m25160005 Sellador de techo "Popular" gl / m2 0.095160006 Sellador de techo "Sureseal", import., lata 5 gl. gl / m2 0.095160007 Sellador de techo "Lanco", import., lata 5 gl. gl / m2 0.095160008 Silicool, lata 5 gl., Criollo, (2 manos) gl / m2 0.09

5180000 MATERIALES INSTALADOS:5180001 Caballete en teja asfáltica instalado a todo costo rollo / m5180002 Línea doble teja asfáltica instalada a todo costo, en bordes rollo / m5180003 Teja asfáltica 3' x 1' instalada todo costo rollo / m2

5200000 PINTURAS:5200001 Acrílica, 2 manos gl / m2 0.1005200002 Aguarrás en 2 manos pintura mantenimiento gl / m2 0.0805200003 Epóxica gl / m2 0.0805200004 Latex "Económica" o "Pintex", 2 manos gl / m2 0.1005200005 Mantenimiento, 2 manos gl / m2 0.0805200006 Oxido Rojo, 2 manos gl / m2 0.0805200007 "Thinner" en 2 manos pintura mantenimiento gl / m2 0.130

5220000 PISOS, ADOQUINES Y TABLETAS:5220001 Adoquín 500-80 AGUAYO 10 x 20 cm. aprox. u / m2 50.0005220002 Adoquín 511 AGUAYO tipo paleta u / m2 39.0005220003 Adoquín 604 AGUAYO 10.20 x 20.20 cm. aprox. u / m2 48.5305220004 Adoquín clásico 10x20x20 cm. u / m2 25.0005220005 Adoquín colonial 05x20x20 cm. u / m2 50.0005220006 Adoquín mediterraneo gris u / m2 36.6505220007 Adoquín olympus 08x12x23 cm. u / m2 36.2305220008 Derretido p/pisos de granito fda / m2 0.031255220009 Baldosa de .10 x .10 m. u / m2 100.0005220010 Baldosa de .125 x .20 m. u / m2 40.0005220011 Baldosa de .125 x .25 m. u / m2 32.0005220012 Baldosa de .15 x .15 m. u / m2 44.4405220013 Baldosa de .15 x .20 m. u / m2 33.3335220014 Baldosa de .20 x .20 m. u / m2 25.0005220015 Baldosa de .20 x .25 m. u / m2 20.0005220016 Baldosa de .20 x .30 m. u / m2 16.6675220017 Baldosa de .20 x .40 m. u / m2 12.5005220018 Baldosa de .20 x .50 m. u / m2 10.0005220019 Baldosa de .25 x .25 m. u / m2 16.0005220020 Baldosa de .25 x .30 m. u / m2 13.3335220021 Baldosa de .25 x .40 m. u / m2 10.0005220022 Baldosa de .25 x .50 m. u / m2 8.0005220023 Baldosa de .30 x .30 m. u / m2 11.1105220024 Baldosa de .30 x .40 m. u / m2 8.3335220025 Baldosa de .30 x .50 m. u / m2 6.6675220026 Baldosa de .30 x .60 m. u / m2 5.5505220027 Baldosa de .40 x .40 m. u / m2 6.2505220028 Baldosa de .40 x .50 m. u / m2 5.0005220029 Baldosa de .40 x .60 m. u / m2 4.1705220030 Baldosa de .40 x .80 m. u / m2 3.1255220031 Baldosa de .50 x .50 m. u / m2 4.0005220032 Baldosa de .50 x .60 m. u / m2 3.3335220033 Baldosa de .50 x .70 m. u / m2 2.8575220034 Baldosa de .50 x .80 m. u / m2 2.5005220035 Baldosa de .50 x .90 m. u / m2 2.2225220036 Baldosa de .50 x 1.00 m. u / m2 2.0005220037 Tabletas 20 x 40 cm. u / m2 12.5005220038 Zócalos de cualquier alto x .15 m. u / m 6.6675220039 Zócalos de cualquier alto x .20 m. u / m 5.0005220040 Zócalos de cualquier alto x .25 m. u / m 4.0005220041 Zócalos de cualquier alto x .30 m. u / m 3.3335220042 Zócalos de cualquier alto x .33 m. u / m 3.0005220043 Zócalos de cualquier alto x .40 m. u / m 2.5005220044 Zócalos de cualquier alto x .50 m. u / m 2.0005220045 Zócalos de cualquier alto x .60 m. u / m 1.6675220046 Zócalos de cualquier alto x .70 m. u / m 1.4305220047 Zócalos de cualquier alto x .80 m. u / m 1.2505220048 Zócalos de cualquier alto x .90 m. u / m 1.111

Page 36: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 18

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. REND. MAT.REFERENCIA D E S C R I P C I O N U. REND.

5220049 Zócalos de cualquier alto x 1.00 m. u / m 1.0005220050 Derretido p/cerámica (rinde 25 m2/fda.) fda / m2 0.1505220051 Pegamento K18 fda / m2 6.5005220052 Perfil esquinero PVC u / m 0.400

5240000 TEFLON: Diám. Tub. # Vueltas Unid. Long.5240001 Rollo teflón (Longitud del rollo) m 4.8005240002 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 1 rollo 0.0000005240003 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 2 rollo 0.0598475240004 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 3 rollo 0.0897715240005 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 4 rollo 0.1196955240006 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 5 rollo 0.1496185240007 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 6 rollo 0.1795425240008 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 7 rollo 0.2094665240009 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 8 rollo 0.2393895240010 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 9 rollo 0.2693135240011 Rollo teflón (Rend. según diámetro y # de vueltas) 3/8 10 rollo 0.2992375240012 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 1 rollo 0.0398985240013 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 2 rollo 0.0797965240014 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 3 rollo 0.1196955240015 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 4 rollo 0.1595935240016 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 5 rollo 0.1994915240017 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 6 rollo 0.2393895240018 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 7 rollo 0.2792885240019 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 8 rollo 0.3191865240020 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 9 rollo 0.3590845240021 Rollo teflón (Rend. según diámetro y # de vueltas) 1/2 10 rollo 0.3989825240022 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 1 rollo 0.0598475240023 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 2 rollo 0.1196955240024 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 3 rollo 0.1795425240025 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 4 rollo 0.2393895240026 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 5 rollo 0.2992375240027 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 6 rollo 0.3590845240028 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 7 rollo 0.4189315240029 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 8 rollo 0.4787795240030 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 9 rollo 0.5386265240031 Rollo teflón (Rend. según diámetro y # de vueltas) 3/4 10 rollo 0.5984735240032 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1 rollo 0.0797965240033 Rollo teflón (Rend. según diámetro y # de vueltas) 1 2 rollo 0.1595935240034 Rollo teflón (Rend. según diámetro y # de vueltas) 1 3 rollo 0.2393895240035 Rollo teflón (Rend. según diámetro y # de vueltas) 1 4 rollo 0.3191865240036 Rollo teflón (Rend. según diámetro y # de vueltas) 1 5 rollo 0.3989825240037 Rollo teflón (Rend. según diámetro y # de vueltas) 1 6 rollo 0.4787795240038 Rollo teflón (Rend. según diámetro y # de vueltas) 1 7 rollo 0.5585755240039 Rollo teflón (Rend. según diámetro y # de vueltas) 1 8 rollo 0.6383725240040 Rollo teflón (Rend. según diámetro y # de vueltas) 1 9 rollo 0.7181685240041 Rollo teflón (Rend. según diámetro y # de vueltas) 1 10 rollo 0.7979655240042 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 1 rollo 0.0997465240043 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 2 rollo 0.1994915240044 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 3 rollo 0.2992375240045 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 4 rollo 0.3989825240046 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 5 rollo 0.4987285240047 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 6 rollo 0.5984735240048 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 7 rollo 0.6982195240049 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 8 rollo 0.7979655240050 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 9 rollo 0.8977105240051 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/4 10 rollo 0.9974565240052 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 1 rollo 0.1196955240053 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 2 rollo 0.2393895240054 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 3 rollo 0.3590845240055 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 4 rollo 0.4787795240056 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 5 rollo 0.5984735240057 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 6 rollo 0.7181685240058 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 7 rollo 0.8378635240059 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 8 rollo 0.9575575240060 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 9 rollo 1.0772525240061 Rollo teflón (Rend. según diámetro y # de vueltas) 1 1/2 10 rollo 1.1969475240062 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1 rollo 0.1595935240063 Rollo teflón (Rend. según diámetro y # de vueltas) 2 2 rollo 0.3191865240064 Rollo teflón (Rend. según diámetro y # de vueltas) 2 3 rollo 0.4787795240065 Rollo teflón (Rend. según diámetro y # de vueltas) 2 4 rollo 0.6383725240066 Rollo teflón (Rend. según diámetro y # de vueltas) 2 5 rollo 0.7979655240067 Rollo teflón (Rend. según diámetro y # de vueltas) 2 6 rollo 0.9575575240068 Rollo teflón (Rend. según diámetro y # de vueltas) 2 7 rollo 1.1171505240069 Rollo teflón (Rend. según diámetro y # de vueltas) 2 8 rollo 1.2767435240070 Rollo teflón (Rend. según diámetro y # de vueltas) 2 9 rollo 1.4363365240071 Rollo teflón (Rend. según diámetro y # de vueltas) 2 10 rollo 1.5959295240072 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 1 rollo 0.1994915240073 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 2 rollo 0.3989825240074 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 3 rollo 0.5984735240075 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 4 rollo 0.7979655240076 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 5 rollo 0.9974565240077 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 6 rollo 1.1969475240078 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 7 rollo 1.3964385240079 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 8 rollo 1.5959295240080 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 9 rollo 1.7954205240081 Rollo teflón (Rend. según diámetro y # de vueltas) 2 1/2 10 rollo 1.9949115240082 Rollo teflón (Rend. según diámetro y # de vueltas) 3 1 rollo 0.239389

Page 37: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 19

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM. REND. MAT.REFERENCIA D E S C R I P C I O N U. REND.

5240083 Rollo teflón (Rend. según diámetro y # de vueltas) 3 2 rollo 0.4787795240084 Rollo teflón (Rend. según diámetro y # de vueltas) 3 3 rollo 0.7181685240085 Rollo teflón (Rend. según diámetro y # de vueltas) 3 4 rollo 0.9575575240086 Rollo teflón (Rend. según diámetro y # de vueltas) 3 5 rollo 1.1969475240087 Rollo teflón (Rend. según diámetro y # de vueltas) 3 6 rollo 1.4363365240088 Rollo teflón (Rend. según diámetro y # de vueltas) 3 7 rollo 1.6757265240089 Rollo teflón (Rend. según diámetro y # de vueltas) 3 8 rollo 1.9151155240090 Rollo teflón (Rend. según diámetro y # de vueltas) 3 9 rollo 2.1545045240091 Rollo teflón (Rend. según diámetro y # de vueltas) 3 10 rollo 2.3938945240092 Rollo teflón (Rend. según diámetro y # de vueltas) 4 1 rollo 0.3191865240093 Rollo teflón (Rend. según diámetro y # de vueltas) 4 2 rollo 0.6383725240094 Rollo teflón (Rend. según diámetro y # de vueltas) 4 3 rollo 0.9575575240095 Rollo teflón (Rend. según diámetro y # de vueltas) 4 4 rollo 1.2767435240096 Rollo teflón (Rend. según diámetro y # de vueltas) 4 5 rollo 1.5959295240097 Rollo teflón (Rend. según diámetro y # de vueltas) 4 6 rollo 1.9151155240098 Rollo teflón (Rend. según diámetro y # de vueltas) 4 7 rollo 2.2343015240099 Rollo teflón (Rend. según diámetro y # de vueltas) 4 8 rollo 2.5534875240100 Rollo teflón (Rend. según diámetro y # de vueltas) 4 9 rollo 2.8726725240101 Rollo teflón (Rend. según diámetro y # de vueltas) 4 10 rollo 3.1918585240102 Rollo teflón (Rend. según diámetro y # de vueltas) 6 1 rollo 0.4787795240103 Rollo teflón (Rend. según diámetro y # de vueltas) 6 2 rollo 0.9575575240104 Rollo teflón (Rend. según diámetro y # de vueltas) 6 3 rollo 1.4363365240105 Rollo teflón (Rend. según diámetro y # de vueltas) 6 4 rollo 1.9151155240106 Rollo teflón (Rend. según diámetro y # de vueltas) 6 5 rollo 2.3938945240107 Rollo teflón (Rend. según diámetro y # de vueltas) 6 6 rollo 2.8726725240108 Rollo teflón (Rend. según diámetro y # de vueltas) 6 7 rollo 3.3514515240109 Rollo teflón (Rend. según diámetro y # de vueltas) 6 8 rollo 3.8302305240110 Rollo teflón (Rend. según diámetro y # de vueltas) 6 9 rollo 4.3090085240111 Rollo teflón (Rend. según diámetro y # de vueltas) 6 10 rollo 4.7877875240112 Rollo teflón (Rend. según diámetro y # de vueltas) 8 1 rollo 0.6383725240113 Rollo teflón (Rend. según diámetro y # de vueltas) 8 2 rollo 1.2767435240114 Rollo teflón (Rend. según diámetro y # de vueltas) 8 3 rollo 1.9151155240115 Rollo teflón (Rend. según diámetro y # de vueltas) 8 4 rollo 2.5534875240116 Rollo teflón (Rend. según diámetro y # de vueltas) 8 5 rollo 3.1918585240117 Rollo teflón (Rend. según diámetro y # de vueltas) 8 6 rollo 3.8302305240118 Rollo teflón (Rend. según diámetro y # de vueltas) 8 7 rollo 4.4686015240119 Rollo teflón (Rend. según diámetro y # de vueltas) 8 8 rollo 5.1069735240120 Rollo teflón (Rend. según diámetro y # de vueltas) 8 9 rollo 5.7453455240121 Rollo teflón (Rend. según diámetro y # de vueltas) 8 10 rollo 6.383716

5260000 TRANSPORTE BLOQUES / VIAJE5260001 Bintel 6"x8"x 8", medio bloque u 1,400.0005260002 Bintel 8"x8"x 8", medio bloque u 1,050.0005260003 Bloque 4"x8"x16" u 1,050.0005260004 Bloque 5"x8"x16" u 840.0005260005 Bloque 6"x8"x 8", liso (½ bloque 6") u 1,400.0005260006 Bloque 6"x8"x16" u 700.0005260007 Bloque 6"x8"x16", texturizado u 700.0005260008 Bloque 8"x8"x 8", liso (½ bloque 8") u 1,050.0005260009 Bloque 8"x8"x16" u 525.0005260010 Bloque 8"x8"x16", texturizado u 525.0005260011 Bloque 12"x8"x 8", liso (½ bloque 12") u 700.0005260012 Bloque 12"x8"x16" u 350.0005260013 Bloque calado 6" tipo persiana u 700.0005260014 Bloque decorativo 6"x8"x16" u 700.0005260015 Bloque decorativo 8"x8"x16" u 525.0005260016 Bloviga 6"x8"x16" u 700.0005260017 Bloviga 8"x8"x16" u 525.000

5280000 TRANSPORTE PIEZAS DE GRANITO / VIAJE5280001 Lavaderos dobles (1.40 m. hasta 1.60 m.) u 12.0005280002 Lavaderos sencillos (0.80 m. hasta 1.20 m.) u 20.0005280003 Vertederos (0.40 m. hasta 0.60 m.) u 20.000

Page 38: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 20

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

SALARIO MENSUAL MINIMO EN RD$ 5,865.00 115.00%

ORDENADO ALFABETICAMENTE

MANO DE OBRA (Agregar ITBIS en Subcontratos, si no lo incluye)MOAL 6000000 MANO DE OBRA ALBAÑILERIA

MOAL 6000100 M.O. ALB., ACCESORIOS DE BAÑOS, INST.:MOAL 6000101 Montar accesorio atornillado 132.50 100.00% u 10.00 1MOAL 6000102 Montar accesorio empotrado 189.29 100.00% u 7.00 1MOAL 6000103 Montar botiquín corriente empotrado 530.00 100.00% u 2.50 1MOAL 6000104 Montar botiquín corriente, superficie 147.22 100.00% u 9.00 1MOAL 6000105 Montar botiquín lujo empotrado 1,325.00 100.00% u 1.00 1MOAL 6000106 Montar botiquín lujo superficie 883.33 100.00% u 1.50 1MOAL 6000107 Montar papelera porta servilletas 132.50 100.00% u 10.00 1MOAL 6000108 Montar repisa corriente para baño 220.83 100.00% u 6.00 1

MOAL 6000200 M.O. ALB., ACERA Y CONTENES:MOAL 6000201 Base para contenes Telford con mezcla 314.29 100.00% m3 3.50 1MOAL 6000202 Const. acera frot., viol., .10 m. esp., coloc. horm. 1,073.17 100.00% m3 2.05 1MOAL 6000203 Contén con bordillo 25x15 cm 100.00 100.00% m 22.00 1MOAL 6000204 Contén con bordillo 30x8x10 cm 68.75 100.00% m 32.00 1MOAL 6000205 Contén con bordillo 40 cm alto x 20 cm ancho 169.23 100.00% m 13.00 1MOAL 6000206 Contén de 55x30x15 cm 111.68 100.00% m 19.70 1

MOAL 6000300 M.O. ALB., ADICIONAL P/PLANTA, COLOC.:MOAL 6000301 Albañilería por cada piso (según unid de cada partida) 5.00% u

MOAL 6000400 M.O. ALB., BADENES Y COLECTORES:

MOAL 6000401 880.00 100.00% m3 2.50 1

MOAL 6000402 880.00 100.00% m3 2.50 1

MOAL 6000202 Conf. anillo de filtrante 608.33 100.00% u 3.00 1

MOAL 6000203 1,013.89 100.00% u 1.80 1

MOAL 6000204 P. A.

MOAL 6000205 Conf. tragante de hasta 50 cm long. 414.77 100.00% u 4.40 1MOAL 6000203 Const. pozo séptico, incluyendo terminación P. A. uMOAL 6000204 Const zapatas y piso colector horm., envarillado y frotado 880.00 100.00% m3 2.50 1

MOAL 6000500 M.O. ALB., BLOQUES, COLOCACIONMOAL 6000501 Coloc. bloque 4x 8 x16 pulgs. 13.20 100.00% u 125.00 1MOAL 6000502 Coloc. bloque 5x8x16 pulgs. 10.31 100.00% u 160.00 1MOAL 6000503 Coloc. bloque 6x8x16 pulgs. 11.00 100.00% u 150.00 1MOAL 6000504 Coloc. bloque 6x8x18 pulgs. 12.22 100.00% u 135.00 1MOAL 6000505 Coloc. bloque 8x8x16 pulgs. 12.22 100.00% u 135.00 1MOAL 6000506 Coloc. bloque 12x8x16 pulgs. 22.50 100.00% u 90.00 1MOAL 6000507 Coloc. bloque ornamental 5x25x20 pulgs. 18.67 100.00% u 75.00 1MOAL 6000508 Coloc. bloque ornamental barro o cemento 24.09 100.00% u 55.00 1MOAL 6000509 Coloc. bloque cristal 66.25 100.00% u 20.00 1MOAL 6000510 Coloc. bloque irregular 24.56 100.00% u 57.00 1MOAL 6000511 Violinar junta horiz. y vert. con regla (cada cara) 1.46 100.00% u 785.00 1

MOAL 6000600 M.O. ALB., DESAGÜES:MOAL 6000601 Conf. desagüe 20x20 cm cubierto 191.67 100.00% u 6.00 1MOAL 6000602 Conf. desagüe 20x20 cm descubierto 115.00 100.00% u 10.00 1

MOAL 6000700 M.O. ALB., EMPAÑETES, TERM. PAREDES Y TECHOS:MOAL 6000701 Bajo relieve, incluye canto 153.33 100.00% m 7.50 1MOAL 6000702 Canto 38.33 100.00% m 30.00 1MOAL 6000703 Capitel 20 a 30 cm P. A. u 1MOAL 6000704 Careteo con llana 20.91 100.00% m2 55.00 1MOAL 6000705 Cornisa, hasta 12 cm, cemento 202.78 100.00% m 9.00 1MOAL 6000706 Empañete columnas desde 20 cm ancho en adelante 163.33 100.00% m2 15.00 1 1MOAL 6000707 Empañete ext., maestrado, a plomo (sin andamios) 111.36 100.00% m2 22.00 1 1MOAL 6000708 Empañete HI-RIB, 3 capas 182.50 100.00% m2 10.00 1MOAL 6000709 Empañete int., en paredes, maestrado, a plomo 87.50 100.00% m2 28.00 1 1MOAL 6000710 Empañete pulido a color 107.35 100.00% m2 17.00 1MOAL 6000711 Empañete pulido sin color 96.05 100.00% m2 19.00 1MOAL 6000712 Empañete rasgado 152.08 100.00% m2 12.00 1MOAL 6000713 Empañete rateado horiz. y vertical, punta llana 39.29 100.00% m2 42.00 1MOAL 6000714 Empañete techos y vigas 113.75 100.00% m2 20.00 1 1MOAL 6000715 Empañete techos, maestrado, a nivel, 2 cm Mín. 125.86 100.00% m2 14.50 1MOAL 6000716 Enpañete en ladrillos P. A. m2 1MOAL 6000717 Estría 71.88 100.00% m 16.00 1MOAL 6000718 Fragüache con escoba 13.41 100.00% m2 69.00MOAL 6000719 Gotero colgante 88.46 100.00% m 13.00 1MOAL 6000720 Gotero en ranura 76.67 100.00% m 15.00 1MOAL 6000721 Lágrima en cemento 165.63 100.00% m2 8.00 1MOAL 6000722 Marmolina con piedras 228.13 100.00% m2 8.00 1MOAL 6000723 Marmolina frotada 182.50 100.00% m2 10.00 1MOAL 6000724 Natilla 50.96 100.00% m2 26.00 1MOAL 6000725 Perrilla 182.50 100.00% m2 10.00 1MOAL 6000726 Repello maestrado paredes 52.27 100.00% m2 22.00 1

Badén ciclópeo hasta 40 cm ancho, 10 a 20 cm esp., frotado, pulido en centro (sin varillas)

Badén ciclópeo hasta 40 cm ancho, > 20 cm esp., frotado, pulido en centro (sin varillas)

Conf. tapa colector o pozo séptico, encofrado, envarillado, vaciado, coloc. tapa, hasta 2.00 metros cuadrados

Conf. tapa colector o pozo séptico, encofrado, envarillado, vaciado, coloc. tapa, > 2.00 m2 (Precio proporc.)

Page 39: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 21

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

MOAL 6000727 Repello maestrado techo, hasta 2 cm esp. 87.50 100.00% m2 16.00 1MOAL 6000728 Repello sin maestrar 25.00 100.00% m2 46.00 1MOAL 6000729 Resane con goma 31.73 100.00% m2 52.00 1MOAL 6000730 Resane frotado 19.83 100.00% m2 58.00 1MOAL 6000731 Rústico con escoba, plana o llana (sin repello) 66.25 100.00% m2 20.00 1MOAL 6000732 Rústico en decoraciones P. A. m2MOAL 6000733 Term medio punto o arcos hasta 40 cm, 2 caras, fondo, cantos 608.33 100.00% m 3.00 1MOAL 6000734 Vuelo aistlado de .80 hasta 2.00 m. 161.97 100.00% m 7.10 1

MOAL 6000800 M.O. ALB., ESCALONES:MOAL 6000801 Confección escalón y revestir en ladrillo 339.74 100.00% m 3.90 1MOAL 6000802 Escalón revestido cerám. criolla, H. y C. H. y vuelo 357.14 100.00% m 4.90 1MOAL 6000803 Escalón revestido cerám. import., H. y C. H. y vuelo 437.50 100.00% m 4.00 1MOAL 6000804 Escalón revestido en mezcla 143.75 100.00% m 8.00 1MOAL 6000805 Montar escalón en accesos de granito 189.29 100.00% m 7.00 1MOAL 6000806 Montar escalón escalera (H. y C. H.) 165.63 100.00% m 8.00 1MOAL 6000807 Revestir escalón en ladrillo 278.95 100.00% m 4.75 1MOAL 6000808 Revestir escalón en mosaico 139.47 100.00% m 9.50 1MOAL 6000809 Terminar escalón de cemento 85.19 100.00% m 13.50 1

MOAL 6000900 M.O. ALB., INST. VENTANAS: (ITBIS incluido por subcontrato)MOAL 6000901 Inst. ventana alum., altura normal 8.41 100.00% p2 100.00 1MOAL 6000902 Inst. ventana alum. con escalera o andamio 10.13 100.00% p2 83.00 1

MOAL 6001000 M.O. ALB., LABORES VARIAS:MOAL 6001001 Acuñe de marco 121.05 100.00% u 9.50 1MOAL 6001002 Coloc. caballete de tejas 182.50 100.00% m 10.00 1MOAL 6001003 Coloc. Teja 228.13 100.00% m2 8.00 1MOAL 6001004 Corte y amarre varilla bloques a 020 m. 1.46 100.00% u 785.00 1MOAL 6001005 Corte y amarre varilla bloques a 0.40 m. 0.98 100.00% u 1,175.00 1MOAL 6001006 Corte y amarre varilla bloques a 0.60 m. 0.73 100.00% u 1,565.00 1MOAL 6001007 Corte y amarre varilla bloques a 0.80 m. 0.49 100.00% u 2,350.00 1MOAL 6001008 Llenar hueco bloque a 020 m. 3.65 100.00% u 315.00 1MOAL 6001009 Llenar hueco bloque a 0.40 m. 1.97 100.00% u 585.00 1MOAL 6001010 Llenar hueco bloque a 0.60 m. 1.46 100.00% u 785.00 1MOAL 6001011 Llenar hueco bloque a 0.80 m. 0.98 100.00% u 1,175.00 1MOAL 6001012 Montura "Brissoleil" de 05x40x200 m. 508.33 100.00% m2 3.00 1

MOAL 6001100 M.O. ALB., LADRILLOS:MOAL 6001101 Arco de ladrillo P. A.MOAL 6001102 Ladrillo limpio 1 cara 6.63 100.00% u 200.00 1MOAL 6001103 Ladrillo limpio 2 caras 8.44 100.00% u 157.00 1MOAL 6001104 Ladrillo no especificado 6.31 100.00% u 210.00 1MOAL 6001105 Ladrillo para empañetar en muros 4.65 100.00% u 285.00 1MOAL 6001106 Ladrillo refractario 5x10x25 cm 6.97 100.00% u 190.00 1

MOAL 6001200 M.O. ALB., LAVADEROS Y VERT.:MOAL 6001201 Lavadero pulido hasta .60x1.5 m., Const. 2,025.00 100.00% u 1.00 1 1MOAL 6001202 Lavadero pulido, > 1.5 m., adicional / recipiente, Const. 1,012.50 100.00% u 2.00 1 1MOAL 6001203 Lavadero, 1 y 2 bocas, con azulejos arriba, Const. P. A.MOAL 6001204 Vertedero 60x60 cm, azulejos, Conf. 1,700.00 100.00% u 1.00 1MOAL 6001205 Vertedero 60x60 cm, pulido, Conf. 766.67 100.00% u 1.50 1

MOAL 6001300 M.O. ALB., MALLA CICLONICA (ZAB., TUBOS, MALLA, PALOMETAS, ALAMBRE PUAS):MOAL 6001301 Coloc. malla ciclónica 3' 215.00 100.00% m 10.00 1MOAL 6001302 Coloc. malla ciclónica 4' 238.89 100.00% m 9.00 1MOAL 6001303 Coloc. malla ciclónica 6' 252.94 100.00% m 8.50 1MOAL 6001304 Coloc. malla ciclónica 7' 265.43 100.00% m 8.10 1MOAL 6001305 Coloc. malla ciclónica 10' 277.06 100.00% m 7.76 1

MOAL 6001400 M.O. ALB., MARMOL:MOAL 6001401 Mármol criollo en escaleras 331.25 100.00% m 4.00 1MOAL 6001402 Mármol criollo en revest. paredes 530.00 100.00% m2 2.50 1MOAL 6001403 Marmol en pedazos 441.67 100.00% m2 3.00 1MOAL 6001404 Mármol fachaico en 1sola pieza 530.00 100.00% m2 2.50 1MOAL 6001405 Mármol import. en escaleras 407.69 100.00% m 3.25 1MOAL 6001406 Mármol import. en revest. paredes 616.28 100.00% m2 2.15 1MOAL 6001407 Mármol picado 1,019.23 100.00% m2 1.30 1MOAL 6001408 Marmol travertino en tiritas 662.50 100.00% m2 2.00 1

MOAL 6001500 M.O. ALB., PIEDRA:MOAL 6001501 Piedra caliza aserrada 378.57 100.00% m2 3.50 1MOAL 6001502 Piedra caliza labrada 331.25 100.00% m2 4.00 1MOAL 6001503 Piedra blanca (San Cristóbal, Cambita, Azulada, La Cumbre, Callao de rio, etc.) 378.57 100.00% m2 3.50 1MOAL 6001504 Roca o cantos rodados, muros mampost., con fines decor. 1,394.74 100.00% m3 0.95 1MOAL 6001505 Roca o cantos rodados en muros mampostería 489.36 100.00% m3 2.35 1

MOAL 6001506 130.68 100.00% m2 8.80 1

MOAL 6001507 344.16 100.00% m2 3.85 1

MOAL 6001600 M.O. ALB., PISOS Y ZOCALOS:MOAL 6001601 Piso Adoquines 60.23 100.00% m2 22.00 1MOAL 6001602 Piso Cemento pulido (fino solo) 52.27 100.00% m2 22.00 1MOAL 6001603 Piso Cerám. criolla 15x15 hasta 20x20 cm, sin base y nivel 220.83 100.00% m2 6.00 1MOAL 6001604 Piso Cerám. criolla 15x15 hasta 20x20 cm, + base y nivel 265.00 100.00% m2 5.00 1MOAL 6001605 Piso Cerám. criolla 30x30 hasta 40x40 cm, sin base y nivel 252.38 100.00% m2 5.25 1

Roca o cantos rodados, tipo encache, 20 a 30 cm espesor, revest. terraplenes, canales y cunetas

Roca o cantos rodados, tipo encache, 20 a 30 cm espesor, revest. terraplenes, con fines decorativos

Page 40: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 22

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

MOAL 6001606 Piso Cerámica criolla 30x30 hasta 40x40 cm, + base y nivel 308.14 100.00% m2 4.30 1MOAL 6001607 Piso Cerámica import. 15x15 hasta 20x20 cm, sin base y nivel 232.46 100.00% m2 5.70 1MOAL 6001608 Piso Cerámica import. 15x15 hasta 20x20 cm, + base y nivel 278.95 100.00% m2 4.75 1MOAL 6001609 Piso Cerámica import. 30x30 hasta 40x40 cm, sin base y nivel 288.04 100.00% m2 4.60 1MOAL 6001610 Piso Cerámica import. 30x30 hasta 40x40 cm, + base y nivel 331.25 100.00% m2 4.00 1MOAL 6001611 Piso Horm. ESTAMPADO, terminación superficie 196.36 100.00% m2 10.3125 1MOAL 6001612 Piso Horm. frotado 10 cm esp. 84.38 100.00% m2 24.00 1MOAL 6001613 Piso Horm. frotado y violinado, 10 cm esp. 112.50 100.00% m2 18.00 1MOAL 6001614 Piso Horm. pulido, violinado, 10 cm esp. 119.12 100.00% m2 17.00 1MOAL 6001615 Piso Loseta ladrillo 12 ½x25 cm 150.57 100.00% m2 8.80 1MOAL 6001616 Piso Loseta ladrillo 15x15 y 20x20 cm 150.57 100.00% m2 8.80 1MOAL 6001617 Piso Loseta ladrillo o cemento / pisos exagonales, ferias y otros 194.85 100.00% m2 6.80 1MOAL 6001618 Piso Loseta mármol criollo, base y nivel 318.18 100.00% m2 4.40 1MOAL 6001619 Piso Loseta mármol imp., base y nivel 368.42 100.00% m2 3.80 1MOAL 6001620 Piso Mosaico 20x20 cm y 25x25 cm, corriente 121.67 100.00% m2 15.00 1MOAL 6001621 Piso Mosaico en cartabón 165.91 100.00% m2 11.00 1MOAL 6001622 Piso Mosaico en plumilla 165.91 100.00% m2 11.00 1MOAL 6001623 Piso Mosaico granito 25x25 cm 130.36 100.00% m2 14.00 1MOAL 6001624 Piso Mosaico granito 30x30 cm 140.38 100.00% m2 13.00 1MOAL 6001625 Piso Mosaico granito 33x33 cm 140.38 100.00% m2 13.00 1MOAL 6001626 Piso Mosaico granito 40x40 cm 165.91 100.00% m2 11.00 1MOAL 6001627 Piso Mosaico granito 50x50 cm 173.81 100.00% m2 10.50 1MOAL 6001628 Piso Mosaico granito en plumilla o cartabón 173.81 100.00% m2 10.50 1MOAL 6001629 Piso Mosaico gravilla 20x20 cm 121.67 100.00% m2 15.00 1MOAL 6001630 Piso Mosaico gravilla 25x25 cm 121.67 100.00% m2 15.00 1MOAL 6001631 Piso Mosaico gravilla 30x30 cm 130.36 100.00% m2 14.00 1MOAL 6001632 Piso Mosaico gravilla 40x40 cm 140.38 100.00% m2 13.00 1MOAL 6001633 Piso Mosaico gravilla 50x50 cm 165.91 100.00% m2 11.00 1MOAL 6001634 Piso Rejonado pulido, sin color 84.38 100.00% m2 24.00 1MOAL 6001635 Piso Rejonado pulido y marcado a hilo, color 112.50 100.00% m2 18.00 1MOAL 6001636 Piso Rejonado sin pulir 72.32 100.00% m2 28.00 1MOAL 6001637 Piso Torcho 20x20 y 25x25 cm 121.67 100.00% m2 15.00 1MOAL 6001638 Piso Vibrazo (parques y terrazas) 146.00 100.00% m2 12.50 1MOAL 6001639 Quicio y entre puertas 100.00 100.00% m 13.25 1MOAL 6001640 Zócalo corriente 44.17 100.00% m 30.00 1MOAL 6001641 Zócalo corriente en escalera 77.94 100.00% m 17.00 1MOAL 6001642 Zócalo granito en escalera 101.92 100.00% m 13.00 1MOAL 6001643 Zócalo granito en piso 60.23 100.00% m 22.00 1

MOAL 6001700 M.O. ALB., PULIMENTO Y BRILLADO PISOS: (ITBIS incluido por subcontrto)MOAL 6001701 Cristalizado pisos (40 m2 mínimo) 92.36 100.00% m2 20.41 1MOAL 6001702 Limpieza escalón 75.40 100.00% m 25.00 1MOAL 6001703 Limpieza zócalos 52.52 100.00% m 35.89 1MOAL 6001704 Limpieza, sal y cera 105.54 100.00% m2 17.86 1MOAL 6001705 Pulimento básico 169.67 100.00% m2 11.11 1MOAL 6001706 Pulimento escalón 203.56 100.00% m 9.26 1MOAL 6001707 Pulimento mesetas 186.82 100.00% m2 10.09 1MOAL 6001708 Pulimento Super Chapa 226.29 100.00% m2 8.33 1MOAL 6001709 Pulimento y cristalizado 262.17 100.00% m2 7.19 1MOAL 6001710 Pulimento y reparación piso viejo 282.61 100.00% m2 6.67 1

MOAL 6001800 M.O. ALB., REGISTROS Y TRAMPA GRASA:MOAL 6001801 Conf. registro hasta 60x60 cm (medida interior) 766.67 100.00% u 1.50 1MOAL 6001802 Conf. registro más de 60x60 cm (medida interior) 920.00 100.00% u 1.25 1MOAL 6001803 Conf. trampa de grasa 1,525.00 100.00% u 1.00 1

MOAL 6001900 M.O. ALB., REVESTIMIENTO PAREDES:MOAL 6001901 Azulejo 10x10 cm, plumilla 530.00 100.00% m2 2.50 1MOAL 6001902 Azulejo 10x10 cm, junta corrida 441.67 100.00% m2 3.00 1MOAL 6001903 Azulejo 15x15 cm, junta corrida 252.38 100.00% m2 5.25 1MOAL 6001904 Azulejo 15x15 cm, junta trabada 265.00 100.00% m2 5.00 1MOAL 6001905 Azulejo en combinación 308.14 100.00% m2 4.30 1MOAL 6001906 Bañera cónica P. A.MOAL 6001907 Bañera empotrada revestida cerámica criolla P. A.MOAL 6001908 Bañera empotrada revestida cerámica import. P. A.MOAL 6001909 Bañera revest. 30 cm alto, 1.56 hasta 180 m. largo 2,038.46 100.00% u 0.65 1MOAL 6001910 Bañera revest. 30 cm alto hasta 1.55 m. largo 1,766.67 100.00% u 0.75 1MOAL 6001911 Base para bañera 220.83 100.00% u 6.00 1MOAL 6001912 Cerámica criolla 15x15 hasta 29x29 cm 252.38 100.00% m2 5.25 1MOAL 6001913 Cerámica criolla 30x30 hasta 40x40 cm 331.25 100.00% m2 4.00 1MOAL 6001914 Cerámica import. 15x15 hasta 29x29 cm 278.95 100.00% m2 4.75 1MOAL 6001915 Cerámica import. 30x30 hasta 40x40 cm 378.57 100.00% m2 3.50 1MOAL 6001916 Fachaico 255.56 100.00% m2 4.50 1MOAL 6001917 Loseta 5x20 cm en revest. muro 441.67 100.00% m2 3.00 1MOAL 6001918 Loseta 8x20 cm en revest. muro 378.57 100.00% u 3.50 1MOAL 6001919 Loseta de cemento 12.5x25 cm 165.63 100.00% m2 8.00 1MOAL 6001920 Loseta ornamental en paredes 331.25 100.00% m2 4.00 1MOAL 6001921 Meseta de baño 576.09 100.00% u 2.30 1MOAL 6001922 Mocheta en azulejo 165.63 100.00% m 8.00 1MOAL 6001923 Mocheta en cerámica criolla 189.29 100.00% m 7.00 1MOAL 6001924 Mocheta en cerámica import. 203.85 100.00% m 6.50 1MOAL 6001925 Prep. superficie p/colocar piso 30.11 100.00% m2 44.00 1

MOAL 6002000 M.O. ALB., SUBIR MATERIALES / PLANTA:MOAL 6002001 Subir arena por meseta un nivel 79.69 100.00% m3 16.00MOAL 6002002 Subir arena por polea 2do nivel 127.50 100.00% m3 10.00MOAL 6002003 Subir arena por polea 3er nivel 182.14 100.00% m3 7.00MOAL 6002004 Subir arena por polea 4to nivel 255.00 100.00% m3 5.00

Page 41: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 23

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

MOAL 6002005 Subir arena por polea 5to nivel 318.75 100.00% m3 4.00MOAL 6002006 Subir arena por polea 6to nivel 425.00 100.00% m3 3.00MOAL 6002007 Subir bloques 4" por meseta 2do nivel 0.71 100.00% u 1,800.00MOAL 6002008 Subir bloques 4" por meseta 3er nivel 0.85 100.00% u 1,500.00MOAL 6002009 Subir bloques 4" por meseta 4to nivel 1.13 100.00% u 1,125.00MOAL 6002010 Subir bloques 4" por meseta 5to nivel 1.42 100.00% u 900.00MOAL 6002011 Subir bloques 4" por meseta 6to nivel 1.70 100.00% u 750.00MOAL 6002012 Subir bloques 4" por polea 2do nivel 1.16 100.00% u 1,100.00MOAL 6002013 Subir bloques 4" por polea 3er nivel 1.96 100.00% u 650.00MOAL 6002014 Subir bloques 4" por polea 4to nivel 2.55 100.00% u 500.00MOAL 6002015 Subir bloques 4" por polea 5to nivel 3.64 100.00% u 350.00MOAL 6002016 Subir bloques 4" por polea 6to nivel 4.25 100.00% u 300.00MOAL 6002017 Subir bloques 6" por meseta 2do nivel 0.85 100.00% u 1,500.00MOAL 6002018 Subir bloques 6" por meseta 3er nivel 1.28 100.00% u 1,000.00MOAL 6002019 Subir bloques 6" por meseta 4to nivel 1.70 100.00% u 750.00MOAL 6002020 Subir bloques 6" por meseta 5to nivel 2.13 100.00% u 600.00MOAL 6002021 Subir bloques 6" por meseta 6to nivel 2.55 100.00% u 500.00MOAL 6002022 Subir bloques 6" por polea 2do nivel 1.42 100.00% u 900.00MOAL 6002023 Subir bloques 6" por polea 3er nivel 2.13 100.00% u 600.00MOAL 6002024 Subir bloques 6" por polea 4to nivel 2.83 100.00% u 450.00MOAL 6002025 Subir bloques 6" por polea 5to nivel 3.92 100.00% u 325.00MOAL 6002026 Subir bloques 6" por polea 6to nivel 4.64 100.00% u 275.00MOAL 6002027 Subir bloques 8" por meseta 2do nivel 1.06 100.00% u 1,200.00MOAL 6002028 Subir bloques 8" por meseta 3er nivel 1.59 100.00% u 800.00MOAL 6002029 Subir bloques 8" por meseta 4to nivel 2.13 100.00% u 600.00MOAL 6002030 Subir bloques 8" por meseta 5to nivel 2.66 100.00% u 480.00MOAL 6002031 Subir bloques 8" por meseta 6to nivel 3.19 100.00% u 400.00MOAL 6002032 Subir bloques 8" por polea 2do nivel 1.80 100.00% u 710.00MOAL 6002033 Subir bloques 8" por polea 3er nivel 2.68 100.00% u 475.00MOAL 6002034 Subir bloques 8" por polea 4to nivel 3.59 100.00% u 355.00MOAL 6002035 Subir bloques 8" por polea 5to nivel 4.47 100.00% u 285.00MOAL 6002036 Subir bloques 8" por polea 6to nivel 5.43 100.00% u 235.00MOAL 6002037 Subir bloques 10" por meseta 2do nivel 1.28 100.00% u 1,000.00MOAL 6002038 Subir bloques 10" por meseta 3er nivel 1.92 100.00% u 665.00MOAL 6002039 Subir bloques 10" por meseta 4to nivel 2.55 100.00% u 500.00MOAL 6002040 Subir bloques 10" por meseta 5to nivel 3.19 100.00% u 400.00MOAL 6002041 Subir bloques 10" por meseta 6to nivel 3.81 100.00% u 335.00MOAL 6002042 Subir bloques 10" por polea 2do nivel 2.13 100.00% u 600.00MOAL 6002043 Subir bloques 10" por polea 3er nivel 3.19 100.00% u 400.00MOAL 6002044 Subir bloques 10" por polea 4to nivel 4.25 100.00% u 300.00MOAL 6002045 Subir bloques 10" por polea 5to nivel 5.31 100.00% u 240.00MOAL 6002046 Subir bloques 10" por polea 6to nivel 6.38 100.00% u 200.00MOAL 6002047 Subir bloques 12" por meseta 2do nivel 1.50 100.00% u 850.00MOAL 6002048 Subir bloques 12" por meseta 3er nivel 2.32 100.00% u 550.00MOAL 6002049 Subir bloques 12" por meseta 4to nivel 3.07 100.00% u 415.00MOAL 6002050 Subir bloques 12" por meseta 5to nivel 3.81 100.00% u 335.00MOAL 6002051 Subir bloques 12" por meseta 6to nivel 4.55 100.00% u 280.00MOAL 6002052 Subir bloques 12" por polea 2do nivel 2.55 100.00% u 500.00MOAL 6002053 Subir bloques 12" por polea 3er nivel 3.81 100.00% u 335.00MOAL 6002054 Subir bloques 12" por polea 4to nivel 5.10 100.00% u 250.00MOAL 6002055 Subir bloques 12" por polea 5to nivel 6.38 100.00% u 200.00MOAL 6002056 Subir bloques 12" por polea 6to nivel 7.73 100.00% u 165.00MOAL 6002057 Subir fundas tipo cem. por polea 2do nivel 5.31 100.00% fda 240.00MOAL 6002058 Subir fundas tipo cem. por polea 3er nivel 8.50 100.00% fda 150.00MOAL 6002059 Subir fundas tipo cem. por polea 4to nivel 11.59 100.00% fda 110.00MOAL 6002060 Subir fundas tipo cem. por polea 5to nivel 15.00 100.00% fda 85.00MOAL 6002061 Subir fundas tipo cem. por polea 6to nivel 19.62 100.00% fda 65.00MOAL 6002062 Subir grava por meseta un nivel 106.25 100.00% m3 12.00MOAL 6002063 Subir grava por polea 2do nivel 159.38 100.00% m3 8.00MOAL 6002064 Subir grava por polea 3er nivel 255.00 100.00% m3 5.00MOAL 6002065 Subir grava por polea 4to nivel 318.75 100.00% m3 4.00MOAL 6002066 Subir grava por polea 5to nivel 425.00 100.00% m3 3.00MOAL 6002067 Subir grava por polea 6to nivel 579.55 100.00% m3 2.20

MOAL 6002100 M.O. ALB., TECHOS, TERMINACION:MOAL 6002101 Capa atérmica, sin subir mat. 53.00 100.00% m2 25.00 1MOAL 6002102 Fino techo Bermuda, cantos, sin subir mat. 188.46 100.00% m2 13.00 1 1MOAL 6002103 Fino techo horiz., sin subir mat. 76.56 100.00% m2 16.00 1MOAL 6002104 Fino techo inclinado, sin subir mat. 47.12 100.00% m2 26.00 1MOAL 6002105 Zabaleta en piso 27.22 100.00% m 45.00 1MOAL 6002106 Zabaleta en techo 40.83 100.00% m 30.00 1

MOAL 6002200 M.O. ALB., VACIADOS:MOAL 6002201 Vaciado y ligado a mano (Ver análisis) 532.66 90.93% m3MOAL 6002202 Vaciado y ligado con ligadora (Ver análisis) 242.59 98.99% m3

MOAL 6002300 M.O. ALB., YESO A TODO COSTO:MOAL 6002301 Capitel (anillo en columna) 1,894.27 100.00% u 2.27 1 1 1 1MOAL 6002302 Cornisa 252.94 100.00% m 17.00 1 1 1 1MOAL 6002303 Pandereta 1,580.88 100.00% m2 2.72 1 1 1 1MOAL 6002304 Plafón (directo sobre techo horm.) 252.94 100.00% m2 17.00 1 1 1 1MOAL 6002305 Plafón en láminas 1,580.88 100.00% m2 2.72 1 1 1 1MOAL 6002306 Roseta 16" 316.18 100.00% u 13.60 1 1 1 1MOAL 6002307 Roseta 24" 474.09 100.00% u 9.07 1 1 1 1

MOCA 6100000 MANO DE OBRA CARPINTERIA:

Page 42: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 24

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

MOCA 6100100 M.O. CARPINT., COL. CONICAS Y RED., CONF.:MOCA 6100001 Col. cónica diám. hasta 50 cm 388.00 100.00% m 4.897 1MOCA 6100002 Col. redonda diám. hasta 50 cm 299.56 100.00% m 6.3427 1MOCA 6100003 Col. cón. o red. adic. p/c 10 cm diám. > 50 cm 20.00% 100.00% m

MOCA 6100200 M.O. CARPINT., COL. CONICAS Y RED., INST.:MOCA 6100201 Col. cónica diám. hasta 50 cm 158.33 100.00% m 12.000 1MOCA 6100202 Col. redonda diám. hasta 50 cm 158.33 100.00% m 12.000 1MOCA 6100203 Col. cón. o red. adic. p/c 10 cm diám. > 50 cm 20.00% 100.00% m

MOCA 6100300 M.O. CARPINT., COL. CUADRADAS O RECTANG., CONF.:MOCA 6100301 Col. 20x20 hasta 30x30 cm 106.98 100.00% m 17.760 1MOCA 6100302 Col. >30x30 hasta 40x40 cm 122.68 100.00% m 15.488 1MOCA 6100303 Col. >40x40 hasta 50x50 cm 141.22 100.00% m 13.454 1MOCA 6100304 Col. >50x50 hasta 60x60 cm 176.88 100.00% m 10.742 1MOCA 6100305 Col. >60x60 hasta 70x70 cm 211.11 100.00% m 9.000 1MOCA 6100306 Col. >70x70 hasta 80x80 cm 246.79 100.00% m 7.6990 1MOCA 6100307 Col. >80x80 hasta 1.00x1.00 m. 281.02 100.00% m 6.7610 1

MOCA 6100400 M.O. CARPINT., COL. CUADRADAS O RECTANG., INST.:MOCA 6100401 Col. 20x20 hasta 30x30 cm 122.68 100.00% m 15.488 1MOCA 6100402 Col. >30x30 hasta 40x40 cm 158.33 100.00% m 12.000 1MOCA 6100403 Col. >40x40 hasta 50x50 cm 176.88 100.00% m 10.742 1MOCA 6100404 Col. >50x50 hasta 60x60 cm 281.02 100.00% m 6.7610 1MOCA 6100405 Col. >60x60 hasta 70x70 cm 318.10 100.00% m 5.9729 1MOCA 6100406 Col. >70x70 hasta 80x80 cm 350.91 100.00% m 5.4145 1MOCA 6100407 Col. >80x80 hasta 1.00x1.00 m. 422.23 100.00% m 4.4999 1

MOCA 6100500 M.O. CARPINT., COL., TAPAS, CONF. E INST.:MOCA 6100501 Col. 2 tapas c/retalle >2 hasta 10 cm 141.22 100.00% m 13.454 1MOCA 6100502 Col. 2 tapas c/retalle >10 hasta 20 cm 158.33 100.00% m 12.000 1MOCA 6100503 Col. 2 tapas c/retalle >20 hasta 30 cm 176.88 100.00% m 10.742 1MOCA 6100504 Col. Tapa y tapa hasta 30 cm ancho 88.44 100.00% m 21.483 1MOCA 6100505 Col. Tapa y tapa >30 hasta 40 cm ancho 106.98 100.00% m 17.760 1MOCA 6100506 Col. Tapa y tapa >40 hasta 50 cm ancho 122.68 100.00% m 15.488 1

MOCA 6100600 M.O. CARPINT., DESENCOFRADOS (AREA CONTACTO FORRO-CONCRETO):MOCA 6100601 Columna 18.54 100.00% m2 102.459 1MOCA 6100602 Arco 21.40 100.00% m2 88.798 1MOCA 6100603 Dintel 21.40 100.00% m2 88.798 1MOCA 6100604 Falso Piso, hasta 2.75 m. alt. 22.82 100.00% m2 83.248 1MOCA 6100605 Falso Piso, >2.75 m. alt., p/c m. adic. 1.75 100.00% m2 1,083.33 1MOCA 6100606 Viga 21.40 100.00% m2 88.798 1

MOCA 6100700 M.O. CARPINT., ESTRUCT. VARIAS, INST. (HASTA 4 M. ALTURA):MOCA 6100701 Caballete asbesto, inst. alto 4 m. 37.09 100.00% u 51.227 1MOCA 6100702 Caballete zinc, inst. alto 4 m. 37.27 100.00% u 37.567 1MOCA 6100703 Plancha asb. cem. 3'x6', con enlatado, inst. alto 4 m. 52.78 100.00% u 35.998 1MOCA 6100704 Plancha asb. cem. 3'x6', sin enlatado, inst. alto 4 m. 41.37 100.00% u 45.928 1MOCA 6100705 Plancha asb. cem. 3'x8', con enlatado, inst. alto 4 m. 59.91 100.00% u 31.712 1MOCA 6100706 Plancha asb. cem. 3'x8', sin enlatado, inst. alto 4 m. 52.78 100.00% u 35.998 1MOCA 6100707 Plancha Sisal cemento 3'x2', con enlatado, inst. alto 4 m. 88.44 100.00% u 21.483 1MOCA 6100708 Plancha zinc, con enlatado, inst. alto 4 m. 47.08 100.00% u 40.361 1MOCA 6100709 Plancha zinc, sin enlatado, inst. alto 4 m. 28.53 100.00% u 66.596 1MOCA 6100710 Tijerilla atornillada p/c p2 madera utiliz., conf. e inst. 37.09 100.00% p2 51.227 1MOCA 6100711 Tijerilla clavada p/c p2 madera utiliz., conf. e inst. 21.40 100.00% p2 88.794 1

MOCA 6100800 M.O. CARPINT., FALSO PISO, HECHURA:MOCA 6100801 Falso piso >2.75 hasta 3.00 m. alto o vuelo cont. 122.68 100.00% m2 15.488 1MOCA 6100802 Falso piso >3.00 hasta 4.00 m. alto o vuelo cont. 141.22 100.00% m2 13.454 1MOCA 6100803 Falso piso >4.00 hasta 5.00 m. alto o vuelo cont. 158.33 100.00% m2 12.000 1MOCA 6100804 Falso piso >5.00 hasta 6.00 m. alto o vuelo cont. 176.88 100.00% m2 10.742 1MOCA 6100805 Falso piso 3 ó más aguas. 278.25 100.00% m2 6.8285 1MOCA 6100806 Falso piso forma especial P. A. m2 1MOCA 6100807 Falso piso hasta 2.75 m. alto o vuelo cont. 106.98 100.00% m2 17.7600 1MOCA 6100808 Vuelo 10 cm (no cont. fallso piso) 37.09 100.00% m 51.227 1MOCA 6100809 Vuelo 20 cm (no cont. fallso piso) 74.18 100.00% m 25.6135 1MOCA 6100810 Vuelo 30 cm (no cont. fallso piso) 111.27 100.00% m 17.0757 1MOCA 6100811 Vuelo 40 cm (no cont. fallso piso) 148.36 100.00% m 12.8068 1MOCA 6100812 Vuelo 50 hasta 90 cm (no cont. fallso piso) 185.45 100.00% m 10.2454 1MOCA 6100813 Vuelo 1.00 m. en adelante = Falso piso 106.98 100.00% m2 17.7600 1MOCA 6100814 Vuelo con ménsula P. A. 1

MOCA 6100900 M.O. CARPINT., MUROS, CONF. E INST. MOLDE:MOCA 6100901 Molde pref. múlt., transp. mecán., c/cara instalada 23.38 100.00% m2 81.250 1MOCA 6100902 Muro H.A. c/cara lisa, confección 128.38 100.00% m2 14.800 1MOCA 6100903 Muro H.A. c/cara lisa, instalación 161.19 100.00% m2 11.787 1

MOCA 6101000 M.O. CARPINT., OTROS, CONF. E INST. MOLDE:MOCA 6101001 Antepecho hasta 50 cm; cada 10 cm altura, conf. 37.09 100.00% m 51.230 1MOCA 6101002 Arco hasta 20 fondo y hasta 30 cm radio, conf. e inst. 350.91 100.00% m2 5.4145 1MOCA 6101003 Otros arcos P. A. 1MOCA 6101004 Rampa lisa 350.91 100.00% m2 5.4145 1MOCA 6101005 Rampa otro tipo no especif. P. A. u 1

MOCA 6101100 M.O. CARPINT., TODO COSTO: (ITBIS incluido por subcontrto)MOCA 6101101 Andamios 68.95 100.00% m2 63.932 2MOCA 6101102 Encof. y desenc. antepecho 177.30 100.00% m 24.862 2

Page 43: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 25

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

MOCA 6101103 Encof. y desenc. Cisterna (mínimo 10.00 m2) 3,046.30 100.00% u 1.447 2MOCA 6101104 Encof. y desenc. Col. 40 hasta 50 cm 467.89 100.00% m 9.421 2MOCA 6101105 Encof. y desenc. Col. cilíndrica 20 cm diám., c/ coloc. molde 949.18 100.00% molde 4.644 2MOCA 6101106 Encof. y desenc. Col. cilíndrica 30 cm diám., c/ coloc. molde 1,208.00 100.00% molde 3.649 2MOCA 6101107 Encof. y desenc. Col. cilíndrica 40 cm diám. 863.30 100.00% m 5.106 2MOCA 6101108 Encof. y desenc. Col. hasta 30x30 cm 372.42 100.00% m 11.836 2MOCA 6101109 Encof. y desenc. Col. y viga amarre 177.30 100.00% m 24.862 2MOCA 6101110 Encof. y desenc. Corniza en losa, c/cara 132.74 100.00% m 33.209 2MOCA 6101111 Encof. y desenc. Dintel 20 ó 30 cm, hasta 2.00 m. 198.57 100.00% m 22.199 2MOCA 6101112 Encof. y desenc. Guardera en losa 86.19 100.00% m 51.145 2MOCA 6101113 Encof. y desenc. Guardera en platea hasta 20 cm 103.42 100.00% m 42.621 2MOCA 6101114 Encof. y desenc. Losa 3 ó más aguas 553.42 100.00% m2 7.965 2MOCA 6101115 Encof. y desenc. Losa inclinada 1 dirección, hasta 3 m. alt. 261.98 100.00% m2 16.826 2MOCA 6101116 Encof. y desenc. Losa inclinada 2 direcciones, hasta 3 m. alt. 284.48 100.00% m2 15.495 2MOCA 6101117 Encof. y desenc. Losa plana, hasta 2.75 m. alto 258.82 100.00% m2 17.031 2MOCA 6101118 Encof. y desenc. Muro / cara 606.16 100.00% m2 7.272 2MOCA 6101119 Encof. y desenc. Pérgola hasta 20 x 40 cm 344.75 100.00% m 12.786 2MOCA 6101120 Encof. y desenc. Rampa escalera 3,191.89 100.00% rampa 1.381 2MOCA 6101121 Encof. y desenc. Viga 20x40 cm, hasta 3.6 m. 344.03 100.00% m 12.813 2MOCA 6101122 Encof. y desenc. Viga 30x50 cm, hasta 3.6 m. 457.55 100.00% m 9.634 2MOCA 6101123 Encof. y desenc. Viga 30x60 cm, hasta 3.6 m. 510.72 100.00% m 8.631 2MOCA 6101124 Encof. y desenc. Viga 40x80 cm, hasta 3.6 m. 677.22 100.00% m 6.509 2MOCA 6101125 Encof. y desenc. Viga de amarre hasta 30 cm 198.25 100.00% m 22.234 2MOCA 6101126 Encof. y desenc. Viga inv. >20 ancho, adic. c/cm hasta 50 cm, >50 cm = muro 10.34 100.00% m 426.212 2MOCA 6101127 Encof. y desenc. Viga inv. hasta 20x>40 alt., adic. c/cm hasta 80 cm 10.34 100.00% m 426.212 2MOCA 6101128 Encof. y desenc. Viga inv. hasta 20 x hasta 40 cm alt. 322.36 100.00% m 13.674 2MOCA 6101129 Encof. y desenc. Viga sobre muro >30 cm Hasta 50 cm 284.48 100.00% m 15.495 2MOCA 6101130 Encof. y desenc. Viga sobre muro hasta 30 cm 224.12 100.00% m 19.668 2MOCA 6101131 Encof. y desenc. Vuelo >3 m. alt., adic. c/50 cm hasta 6.00 m. alt. 32.75 100.00% m 134.594 2MOCA 6101132 Encof. y desenc. Vuelo inclinado losa >3 direcciones, hasta 3 m. alt. 517.13 100.00% m 8.524 2MOCA 6101133 Encof. y desenc. Vuelo inclinado losa 1 dirección, hasta 3 m. alt. 261.98 100.00% m 16.826 2MOCA 6101134 Encof. y desenc. Vuelo inclinado losa 2 direcciones, hasta 3 m. alt. 284.48 100.00% m 15.495 2MOCA 6101135 Encof. y desenc. Vuelo inclinado losa 3 direcciones, hasta 3 m. alt. 322.36 100.00% m 13.674 2MOCA 6101136 Encof. y desenc. Vuelo plano hasta 2.60 m. alt. 224.12 100.00% m 19.668 2

MOCA 6101200 M.O. CARPINT., TRABAJOS DE TERMINACION:MOCA 6101201 Cielo raso de asbesto en cuadros 2'x2' 192.58 100.00% m2 9.866 1MOCA 6101202 Cielo raso de cartón acústico, encostillado 192.58 100.00% m2 9.866 1MOCA 6101203 Cielo raso de plywood en cuadros 2'x2' 176.89 100.00% m2 10.741 1MOCA 6101204 Cielo raso de plywood o cartón piedra 141.22 100.00% m2 13.454 1MOCA 6101205 Conf. Puerta biselada clavada 41.37 100.00% u 45.928 1MOCA 6101206 Conf. Puerta clavada 21.40 100.00% p2 88.794 1MOCA 6101207 Conf. Puerta en plumilla 41.37 100.00% p2 45.928 1MOCA 6101208 Conf. Puerta forrada en zinc 52.78 100.00% p2 35.998 1MOCA 6101209 División plywood, 1 lado 122.68 100.00% m2 15.487 1MOCA 6101210 División plywood, 2 lados 176.89 100.00% m2 10.741 1MOCA 6101211 Montar cerradura corriente 262.48 100.00% u 7.2387 1MOCA 6101212 Montar marco mad. corriente 41.37 100.00% u 45.928 1MOCA 6101213 Montar marco mad. preciosa 52.78 100.00% u 35.998 1MOCA 6101214 Montar marco metal 69.90 100.00% u 27.182 1MOCA 6101215 Montar puerta panelada corriente 0.9x2.10 m. 439.37 100.00% u 4.3244 1MOCA 6101216 Montar puerta pino 0.9x2.10 m. 350.92 100.00% u 5.4143 1MOCA 6101217 Montar puerta plegadiza corredera 0.9x2.10 m. 527.81 100.00% u 3.5998 1MOCA 6101218 Montar puerta plegadiza moldura o cubrefalta 0.9x2.10 m. 703.26 100.00% u 2.7017 1MOCA 6101219 Montar puerta plumilla con cáncamo 0.9x2.10 m. 703.26 100.00% u 2.7017 1MOCA 6101220 Montar puerta plywood 0.9x2.10 m. 350.92 100.00% u 5.4143 1MOCA 6101221 Montar puerta vaivén 0.9x2.10 m. 527.81 100.00% u 3.5998 1

MOCA 6101300 M.O. CARPINT., VIGAS Y DINTELES, CONF. E INST. MOLDE:MOCA 6101301 Dintel 2 m. largo, hasta 20 cm, conf. e inst. 176.88 100.00% m 10.742 1MOCA 6101302 Dintel >2 m. largo, conf. e inst. = Vigas ver Vigas mMOCA 6101303 Dintel hasta 2 m. largo, >20 hasta 40 cm, conf. e inst. 246.78 100.00% m 7.6992 1MOCA 6101304 Viga invertida, c/10 cm alto, 2 caras, conf. e inst. 52.78 100.00% m 36.000 1MOCA 6101305 Viga amarre 15 ó 20x20 cm alto, conf. e inst. 106.98 100.00% m 17.760 1MOCA 6101306 Viga amarre 15 ó 20x30 cm alto, conf. e inst. 122.68 100.00% m 15.488 1MOCA 6101307 Viga amarre 15 ó 20x40 cm alto, conf. e inst. 141.22 100.00% m 13.454 1MOCA 6101308 Viga amarre 15 ó 20x50 cm alto, conf. e inst. 158.33 100.00% m 12.000 1MOCA 6101309 Viga, c/10 cm alto, apunt. >3.6, adic. c/m. conf. e inst. 20.00% 100.00% mMOCA 6101310 Viga, c/10 cm alto, apunt. hasta 3.6 m., conf. e inst. 37.09 100.00% m 51.230 1MOCA 6101311 Viga, c/10 cm Fondo 25.68 100.00% m 73.998 1MOCA 6101312 Viga zap. hasta 40x40 cm, conf. e inst. 128.38 100.00% m 14.800 1MOCA 6101313 Viga zap. >40x40 hasta 50x50 cm, conf. e inst. 88.44 100.00% m 21.483 1MOCA 6101314 Viga zap. >50x50 hasta 60x60 cm, conf. e inst. 106.98 100.00% m 17.760 1

MODE 6200000 MANO DE OBRA DEMOLICIONES:MODE 6200001 Cimiento de horm. armado 850.00 100.00% m3 0.50MODE 6200002 Cimiento de piedra 283.33 100.00% m3 1.50MODE 6200003 Cimiento viejo de horm. simple 500.00 100.00% m3 0.85MODE 6200004 Murs de horm. armado 850.00 100.00% m3 0.50MODE 6200005 Muro de piedra 242.86 100.00% m3 1.75MODE 6200006 Muro de tapia 106.25 100.00% m3 4.00MODE 6200007 Techo de tejas 42.50 100.00% m2 10.00MODE 6200008 Techo horm. armado con mallas 106.25 100.00% m2 4.00MODE 6200009 Techo horm. armado con varillas 212.50 100.00% m2 2.00

*Acero recuperable: 0.50 quintal por cada metro cúbico

MOEB 6300000 MANO DE OBRA EBANISTERIA:MOEB 6300001 Aplicar laca, todo costo (2 caras) 1,464.29 100.00% m2 1.40 1

Page 44: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 26

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

MOEB 6300002 Montar puerta, marco y llavín 1,025.00 100.00% u 2.00 1

MOEL 6400000 MANO DE OBRA ELECTRICIDAD:

MOEL 6400100 M.O. ELECTRICIDAD, CONEXIÓN APARATOS:MOEL 6400001 Aire acond. hasta 2 hp (montura sin materiales) 1,045.31 100.00% u 1.9133 1MOEL 6400002 Aire acond., si corriente está distante, cobrar inst. eléct. aparte P. A. u 1MOEL 6400003 Aire acond., si requiere reformas constr., cobrar estas aparte P. A. u 1MOEL 6400004 Breaker, instalación 87.70 100.00% u 22.8054 1MOEL 6400005 Cada número de los cuadros de timbres 175.40 100.00% u 11.4027 1MOEL 6400006 Calentador 110 v sin estar provisto un plot y cordón 347.97 100.00% u 5.7477 1MOEL 6400007 Calentador 220 v sin estar provisto un plot y cordón 523.37 100.00% u 3.8214 1MOEL 6400008 Estufa eléctrica 220 v. 523.37 100.00% u 3.8214 1MOEL 6400009 Extractor de aire 110 v. 347.97 100.00% u 5.7477 1MOEL 6400010 Pago mínimo por visita, hecho o no el trabajo, motivo ajeno elect. 115.94 100.00% u 17.2500 1MOEL 6400011 Moledor de desperdicios 110 v. 347.97 100.00% u 5.7477 1MOEL 6400012 Regulador de intensidad (dimmer) 278.66 100.00% u 7.1773 1MOEL 6400013 Reparar a domicilio y de apar. Eléctr. Según el caso requiera P. A. u 1MOEL 6400014 Timbre campana de 4 notas 523.37 100.00% u 3.8214 1

MOEL 6400200 M.O. ELECTRICIDAD, INTERRUPTOR DE SEGURIDAD:MOEL 6400201 Interruptor seg. inst. en los paneles, por cada 10 amp. 90.53 100.00% u 22.0927 1MOEL 6400202 Interruptor seg. 30 amp. 271.62 100.00% u 7.3632 1MOEL 6400203 Interruptor seg. 60 amp. 543.17 100.00% u 3.6821 1MOEL 6400204 Interruptor seg. 100 amp. 905.26 100.00% u 2.2093 1MOEL 6400205 Interruptor seg. 125 amp. 1,131.61 100.00% u 1.7674 1MOEL 6400206 Interruptor seg. 150 amp. 1,357.96 100.00% u 1.4728 1MOEL 6400207 Interruptor seg. 200 amp. 1,809.79 100.00% u 1.1051 1MOEL 6400208 Interruptor seg. 250 amp. 2,263.21 100.00% u 0.8837 1

MOEL 6400300 M.O. ELECTRICIDAD, SALIDAS DE TIMBRES, TELEF. Y CABLE:MOEL 6400301 Timbre, Teléf. y Cable en la misma tub. de conduct. 387.57 100.00% u 5.1603 1MOEL 6400302 Timbre, Teléf. y Cable en tub. 1/2" independiente 469.62 100.00% u 4.2588 1MOEL 6400303 Timbre, Teléf. y Cable en tub. 3/4" independiente 611.02 100.00% u 3.2732 1MOEL 6400304 Timbre, Teléf. y Cable en tub. 1" independiente 752.53 100.00% u 2.6577 1

MOEL 6400400 M.O. ELECTRICIDAD, RESIDENCIAS ECONOMICAS EN SERIE :MOEL 6400401 Similares a casas "A" y "B" en tub. 1/2" 297.04 100.00% u 6.7330 1MOEL 6400402 Similares a casas "C" y "D" en tub. 1/2" 257.72 100.00% u 7.7605 1

MOEL 6400403 u

MOEL 6400500 M.O. ELECTRICIDAD, SALIDAS EN TUB. EXTERIOR VISIBLE:MOEL 6400501 Salida ext. visible tipo industrial, 1/2" 550.77 100.00% u 3.6313 1MOEL 6400502 Salida ext. visible tipo industrial, 1/2" con registro tipo letra 666.71 100.00% u 2.9998 1MOEL 6400503 Salida ext. visible tipo industrial, 3/4" 716.00 100.00% u 2.7933 1MOEL 6400504 Salida ext. visible tipo industrial, 3/4" con registro tipo letra 831.95 100.00% u 2.4040 1MOEL 6400505 Salida ext. visible tipo industrial, 1" 881.21 100.00% u 2.2696 1MOEL 6400506 Salida ext. visible tipo industrial, 1" con registro tipo letra 997.16 100.00% u 2.0057 1

MOEL 6400600 M.O. ELECTRICIDAD, SALIDAS EN TUB. OCULTA:MOEL 6400601 Salida Botón de timbre, 1/2" 387.57 100.00% u 5.1603 1MOEL 6400602 Salida en tub. de 1/2" 387.57 100.00% u 5.1603 1MOEL 6400603 Salida Interruptor piloto, 1/2" 469.62 100.00% u 4.2588 1MOEL 6400604 Salida Interruptor 1, 1/2" 387.57 100.00% u 5.1603 1MOEL 6400605 Salida Interruptor 2, 1/2" 469.62 100.00% u 4.2588 1MOEL 6400606 Salida Interruptor 3, 1/2" 523.37 100.00% u 3.8214 1MOEL 6400607 Salida Interruptor 3 vías, 1/2" 469.62 100.00% u 4.2588 1MOEL 6400608 Salida Interruptor 4 vías, 1/2" 575.71 100.00% u 3.4740 1MOEL 6400609 Salida Luces, 1/2" 387.57 100.00% u 5.1603 1MOEL 6400610 Salida Tomacorriente 110 v., 1/2" 387.57 100.00% u 5.1603 1MOEL 6400611 Salida Tomacorriente 220 v., 3/4" 441.17 100.00% u 4.5334 1MOEL 6400612 Panel distribución 543.17 100.00% u 3.6821 1MOEL 6400613 Por cada 1/4" superior a 1/2", hasta 1", 30% adic. al precio 115.99 100.00% u 17.2431 1MOEL 6400614 Por cada switch adic. o de combinación, 50% adic. al precio 193.79 100.00% u 10.3207 1

MOEL 6400700 M.O. ELECTRICIDAD, SALIDAS TIPO ECONOMICO EN TUB.:MOEL 6400701 Salida sin tub. exteriormente visible 175.40 100.00% u 11.4027 1MOEL 6400702 Salida sin tub. oculta en plafón, cielo raso, etc. 257.72 100.00% u 7.7605 1

MOEL 6400800 M.O. ELECTRICIDAD, SALIDAS WATERPROOF Y EXPLOTIONPROOF:MOEL 6400801 Estas salidas se cobrará un precio convencional superior a todas P. A. u 1

MOEX 6500000 MANO DE OBRA EXCAVACIONES Y CORTES CON EQUIPO:MOEX 6500001 Corte con PALA MECANICA en tierra 150.00 100.00% m3MOEX 6500002 Exc. Caliche a mano 3.00 m. prof. 382.65 100.00% m3 0.98MOEX 6500003 Exc. Caliche a mano 3.01 - 5.00 m. prof. 421.35 100.00% m3 0.89MOEX 6500004 Exc. Caliche a mano 5.01 - 7.00 m. prof. 462.96 100.00% m3 0.81MOEX 6500005 Exc. Horm. armado, 3.00 m. prof. 974.03 100.00% m3 0.77MOEX 6500006 Exc. Roca blanda a mano 3.00 m. prof. 614.75 100.00% m3 0.61MOEX 6500007 Exc. Roca blanda a mano 3.01 - 5.00 m. prof. 646.55 100.00% m3 0.58MOEX 6500008 Exc. Roca blanda a mano 5.01 - 7.00 m. prof. 707.55 100.00% m3 0.53MOEX 6500009 Exc. Roca compresor 3.00 m. prof. 1,635.30 101.57% m3MOEX 6500010 Exc. Roca compresor 3.01 - 5.00 m. prof. 1,798.83 101.57% m3MOEX 6500011 Exc. Roca compresor 5.01 - 7.00 m. prof. 1,962.36 101.57% m3MOEX 6500012 Exc. Roca dura a mano 3.00 m. prof. 781.25 100.00% m3 0.48MOEX 6500013 Exc. Roca dura a mano 3.01 - 5.00 m. prof. 815.22 100.00% m3 0.46

Estas casas con timbres, teléf., cable, ext. visible, waterp., explotionp., pagar según establecen los demás renglones

Según aplique

Page 45: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 27

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

MOEX 6500014 Exc. Roca dura a mano 5.01 - 7.00 m. prof. 872.09 100.00% m3 0.43MOEX 6500015 Exc. Roca tosca a mano 3.00 m. prof. 528.17 100.00% m3 0.71MOEX 6500016 Exc. Roca tosca a mano 3.01 - 5.00 m. prof. 559.70 100.00% m3 0.67MOEX 6500017 Exc. Roca tosca a mano 5.01 - 7.00 m. prof. 604.84 100.00% m3 0.62MOEX 6500018 Exc. Tierra a mano 3.00 m. prof. 235.85 100.00% m3 1.59MOEX 6500019 Exc. Tierra a mano 3.01 - 5.00 m. prof. 264.08 100.00% m3 1.42MOEX 6500020 Exc. Tierra a mano 5.01 - 7.00 m. prof. 288.46 100.00% m3 1.30

JORNAL JORNAL JORNAL

MOJO 6600000 MANO DE OBRA JORNALES DIARIOS: DIARIO INDICE U. / HORA MENSUAL

MOJO 6600001 Ayudante (AY) 500.00 100.00% día 62.500 11,915.00MOJO 6600002 Brigada topográfica, Estación Total (BT) 4,600.00 100.00% día 575.000 109,618.00MOJO 6600003 Maestro de área (MA) 1,125.00 100.00% día 140.625 26,808.75MOJO 6600004 Operario primera categoría (OP1) 900.00 100.00% día 112.500 21,447.00MOJO 6600005 Operario Segunda categoría (OP2) 725.00 100.00% día 90.625 17,276.75MOJO 6600006 Operario tercera categoría - Terminador (OP3) 625.00 100.00% día 78.125 14,893.75MOJO 6600007 Técnico calificado (TC) 425.00 100.00% día 53.125 10,127.75MOJO 6600008 Técnico no calificado o PEON (TNC) 375.00 100.00% día 46.875 8,936.25

MOPI 6700000 MANO DE OBRA PINTURA:MOPI 6700001 Barniz, 1ra. mano 19.26 100.00% m2 84.375 1MOPI 6700002 Barniz, 2da. mano 19.26 100.00% m2 84.375 1MOPI 6700003 Cal y Carburo, 1ra. mano 10.83 100.00% m2 150.000 1MOPI 6700004 Cal y Carburo, 2da. mano 7.22 100.00% m2 225.000 1MOPI 6700005 Cornisa 24.07 100.00% m 67.500 1MOPI 6700006 De agua, 1ra. mano, p. LISA, masilla, lija y piedra 18.06 100.00% m2 90.000 1MOPI 6700007 De agua, 2da. mano, pared LISA 12.04 100.00% m2 135.000 1MOPI 6700008 De agua, 2 manos, p. LISA, masilla, lija, piedra 30.09 100.00% m2 54.000 1MOPI 6700009 De agua, 1ra. mano, pared RUSTICA 30.09 100.00% m2 54.000 1MOPI 6700010 De agua, 2da. mano, pared RUSTICA 25.28 100.00% m2 64.286 1MOPI 6700011 De agua, 2 manos, pared RUSTICA 55.37 100.00% m2 29.348 1MOPI 6700012 Imperm., 1ra. Mano, limpieza y sellar grietas 20.46 100.00% m2 79.410 1MOPI 6700013 Impermeabilizante, 2da. mano 12.04 100.00% m2 135.000 1MOPI 6700014 Mant., 1ra. mano, p. LISA, masilla, lija sin piedra 19.26 100.00% m2 84.375 1MOPI 6700015 Mant., 2da. mano, pared LISA, sin piedra 18.06 100.00% m2 90.000 1MOPI 6700016 Mant., 2 manos, p. LISA, masilla, lija sin piedra 37.32 100.00% m2 43.548 1MOPI 6700017 Oxido de Zinc, 1ra. mano 14.44 100.00% m2 112.50 1MOPI 6700018 Oxido de Zinc, 2da. mano 10.83 100.00% m2 150.000 1MOPI 6700019 Piedra sobre paredes 6.25 100.00% m2 80.000MOPI 6700020 Rapilla total y/o parcial 25.00 100.00% m2 20.000MOPI 6700021 Volutas en ventanas y en muros 20.46 100.00% m 79.410 1

MOPL 6800000 MANO DE OBRA PLOMERIA:

MOPL 6800100 M.O. PLOMERIA, ACOMETIDA URBANA, INCLUYE LLAVE CHORO:MOPL 6800001 Acomet. ½" y ¾", hasta 8.00 m. tub. h.g. 668.06 100.00% u 2.43243 1MOPL 6800002 Acomet. ½" y ¾", hasta 12.00 m. tub. h.g. 327.41 100.00% u 4.96324 1MOPL 6800003 Acomet. ½" y ¾", hasta 12.00 m. tub. pvc y h.g. en extr. 252.78 100.00% u 6.42857 1

MOPL 6800100 M.O. PLOMERIA, ARRASTRE DOMIC. Y PLUVIAL:MOPL 6800101 Arrastre, tub. 2" 32.50 100.00% m 50.00000 1MOPL 6800102 Arrastre, tub. 3" ó 4" 39.72 100.00% m 40.90909 1MOPL 6800103 Arrastre, tub. 5" 66.20 100.00% m 24.54545 1MOPL 6800104 Arrastre, tub. 6" 83.06 100.00% m 19.56522 1

MOPL 6800200 M.O. PLOMERIA, AUMENTO POR PLANTA EN EDIFICIOS:MOPL 6800201 Valor adic. 2da. planta 5.00% 100.00% uMOPL 6800202 Valor adic. 3ra. planta 10.00% 100.00% uMOPL 6800203 Valor adic. 4ta. hasta 7ma. Planta 20.00% 100.00% uMOPL 6800204 Valor adic. 7ma. hasta 10ma. planta 25.00% 100.00% uMOPL 6800205 Valor adic. 10ma. Planta y siguientes / piso 35.00% 100.00% u

MOPL 6800300 M.O. PLOMERIA, BAJANTE O VENTILACION / PLANTA:MOPL 6800301 Bajante o vent. dren. 2" 518.80 100.00% u 3.13225 1MOPL 6800302 Bajante o vent. dren. 3" 593.43 100.00% u 2.73834 1MOPL 6800303 Bajante o vent. dren. 4" 668.06 100.00% u 2.43243 1MOPL 6800304 Bajante o vent. dren. 5" o más 889.54 100.00% u 1.82679 1

MOPL 6800400 M.O. PLOMERIA, BOMBA DE AGUA, INST. CIRCUITO COMPLETO:MOPL 6800401 Montar bomba c/circ. tub. ¾"-1" 5,931.85 100.00% u 0.27395 1MOPL 6800402 Montar bomba c/circ. tub. 1 ¼ en adelante 5,931.85 100.00% u 0.27395 1

MOPL 6800500 M.O. PLOMERIA, BOMBA DE AGUA, SIN EL CIRCUITO:MOPL 6800501 Montar bomba s/circ. tub. ¾" 2,031.25 100.00% u 0.80 1MOPL 6800502 Montar bomba s/circ. tub. 1"-1 ¼" 2,954.55 100.00% u 0.55 1MOPL 6800503 Montar bomba s/circ. tub. 1 ½"-2" 4,062.50 100.00% u 0.40 1

MOPL 6800600 M.O. PLOMERIA, CALENTADOR DE AGUA EXCLUSIV.:MOPL 6800601 Montar calent. de gas 1,625.00 100.00% u 1.00 1MOPL 6800602 Montar calent. eléct. hasta 12 gl. 1,186.85 100.00% u 1.36917 1MOPL 6800603 Montar calent. eléct. 18-50 gl. 1,425.44 100.00% u 1.14 1MOPL 6800604 Montar calent. industrial P. A. u 1

MOPL 6800700 M.O. PLOMERIA, COL. ABASTECER AGUA, COBRE, POR PLANTA:MOPL 6800701 Col. agua ½" cobre , soldada o roscada, 742.69 100.00% u 2.188006 1

Page 46: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 28

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

MOPL 6800702 Col. agua ¾" cobre , soldada o roscada, 1,038.80 100.00% u 1.564311 1MOPL 6800703 Col. agua 1" cobre, soldada o roscada, 1,186.85 100.00% u 1.36917 1MOPL 6800704 Col. agua 1 ¼" en adelante, cobre, soldar o rosca P. A. u 1

MOPL 6800800 M.O. PLOMERIA, COL. ABASTECER AGUA, H.G., POR PLANTA:MOPL 6800801 Col. agua ½" ó ¾", h.g. o pve 250.00 100.00% u 6.50 1MOPL 6800802 Col. agua 1" ó 1 ¼", h.g. o pve 285.09 100.00% u 5.70 1MOPL 6800803 Col. agua 1 ½", h.g. o pve 445.37 100.00% u 3.65 1MOPL 6800804 Col. agua 2", h.g. o pve 518.80 100.00% u 3.13225 1MOPL 6800805 Col. agua 3", h.g. o pve 593.43 100.00% u 2.73834 1MOPL 6800806 Col. agua 4", h.g. o pve 742.69 100.00% u 2.18800 1MOPL 6800807 Col. agua 5" o más, h.g. o pve 889.54 100.00% u 1.82679 1

MOPL 6800900 M.O. PLOMERIA, COL. DESAGÜE PLUVIAL, POR PLANTA:MOPL 6800901 Col. desagüe pluvial 2" 445.37 100.00% u 3.65 1MOPL 6800902 Col. desagüe pluvial 3" 518.80 100.00% u 3.13225 1MOPL 6800903 Col. desagüe pluvial 4" 593.43 100.00% u 2.73834 1MOPL 6800904 Col. desagüe pluvial 5" ó 6" 742.69 100.00% u 2.18800 1

MOPL 6801000 M.O. PLOMERIA, CONEXION AL SEPTICO Y FILTRANTE:MOPL 6801001 Conextar a cloaca 812.50 100.00% u 2.00 1MOPL 6801002 Conectar séptico 1 cám. y filt., tub. 4" 2,668.62 100.00% u 0.60893 1MOPL 6801003 Conectar séptico 1 cám. y filt., tub. 5" 2,668.62 100.00% u 0.60893 1MOPL 6801004 Conectar séptico 1 cám. y filt., tub. 6" 2,965.92 100.00% u 0.54789 1MOPL 6801005 Conectar séptico 1 cám. y filt., tub. 8" 3,262.04 100.00% u 0.498155 1MOPL 6801006 Conectar séptico 2 cám. y filt., tub. 4" 3,334.26 100.00% u 0.487365 1MOPL 6801007 Conectar séptico 2 cám. y filt., tub. 5" 3,334.26 100.00% u 0.487365 1MOPL 6801008 Conectar séptico 2 cám. y filt., tub. 6" 3,707.41 100.00% u 0.43831 1MOPL 6801009 Conectar séptico 2 cám. y filt., tub. 8" 4,080.56 100.00% u 0.39823 1

MOPL 6801100 M.O. PLOMERIA, DESAGÜE APARATOS, POR SALIDA:MOPL 6801101 Desagüe 2" 518.80 100.00% u 3.13225 1MOPL 6801102 Desagüe 3" y 4" 668.06 100.00% u 2.43243 1MOPL 6801103 Desagüe inodoro de pared 814.91 100.00% u 1.99 1MOPL 6801104 Desagüe piso 2", con parrilla 593.43 100.00% u 2.74 1MOPL 6801105 Desagüe piso 3" y 4", con parrilla 668.06 100.00% u 2.43243 1

MOPL 6801200 M.O. PLOMERIA, DESMONTAR APARATOS:MOPL 6801201 Desmontar cualquier aparato 50.00% u

MOPL 6801300 M.O. PLOMERIA, EMPALME A TUB. AGUA EXIST.:MOPL 6801301 Empalme tub. ½" ó ¾" 593.43 100.00% u 2.73834 1MOPL 6801302 Empalme tub. 1" 742.68 100.00% u 2.18801 1MOPL 6801303 Empalme tub. 1 ¼" - 1 ½" 889.54 100.00% u 1.82679 1MOPL 6801305 Empalme tub. 2" 1,038.80 100.00% u 1.564311 1MOPL 6801304 Empalme tub. 2 ½" en adelante P. A. u 1

MOPL 6801400 M.O. PLOMERIA, EMPALME A TUB. ARRASTRE EXIST.:MOPL 6801401 Empalme tub. 2" 445.37 100.00% u 3.64865 1MOPL 6801402 Empalme tub. 3" 593.43 100.00% u 2.73834 1MOPL 6801403 Empalme tub. 4" 742.68 100.00% u 2.18801 1MOPL 6801404 Empalme tub. 6" 889.54 100.00% u 1.82679 1

MOPL 6801500 M.O. PLOMERIA, INST. CAJA DE VALVULA:MOPL 6801501 Inst. caja válvula sencillas 83.06 100.00% u 19.56522 1MOPL 6801502 Inst. caja válvula telescópica 98.70 100.00% u 16.46341 1

MOPL 6801600 M.O. PLOMERIA, INST. HIDRANTE:MOPL 6801601 Instalación hidrante 2,521.76 100.00% u 0.64439 1

MOPL 6801700 M.O. PLOMERIA, INST. LAVADORA:MOPL 6801701 Inst. lavadora automát., doméstica 1,186.85 100.00% u 1.36917 1MOPL 6801702 Inst. lavadora automát., Industriales o comerciales P. A. u 1

MOPL 6801800 M.O. PLOMERIA, INST. LLAVE PASO Y CHORRO:MOPL 6801801 Inst. llave chorro ½" ó ¾", línea máx. 3.00 m. 668.06 100.00% u 2.43243 1MOPL 6801802 Inst. llave paso ½", cobre 889.54 100.00% u 1.82679 1MOPL 6801803 Inst. llave paso ¾", cobre 1,038.80 100.00% u 1.564311 1MOPL 6801804 Inst. llave paso 1" ó 1 ¼", cobre 1,111.02 100.00% u 1.46262 1MOPL 6801805 Inst. llave paso 1 ½", cobre 1,186.85 100.00% u 1.36917 1MOPL 6801806 Inst. llave paso 2" en adelante, cobre P. A. u 1MOPL 6801807 Inst. llave paso ½", h.g. o pvc 296.11 100.00% u 5.48781 1MOPL 6801808 Inst. llave paso ¾", h.g. o pvc 445.37 100.00% u 3.64865 1MOPL 6801809 Inst. llave paso 1" ó 1 ¼", h.g. o pvc 814.90 100.00% u 1.9941 1

MOPL 6801900 M.O. PLOMERIA, INST. MANGA O NIPLE:MOPL 6801901 Inst. manga o niple 2" de diámetro de tub. 83.06 100.00% u 19.56522 1MOPL 6801902 Inst. manga o niple 3" de diámetro de tub. 98.70 100.00% u 16.46341 1MOPL 6801903 Inst. manga o niple 4" de diámetro de tub. 162.50 100.00% u 10.00000 1MOPL 6801904 Inst. manga o niple 6" de diámetro de tub. 327.41 100.00% u 4.96324 1MOPL 6801905 Inst. manga o niple 8" de diámetro de tub. 415.28 100.00% u 3.91304 1

MOPL 6802000 M.O. PLOMERIA, INST. MEDIDOR DE AGUA:MOPL 6802001 Inst. medidor en tub. ¾" 281.67 100.00% u 5.76923 1MOPL 6802002 Inst. medidor en tub. 1" 327.41 100.00% u 4.96324 1MOPL 6802003 Inst. medidor en tub. 1 ½" 356.30 100.00% u 4.56082 1MOPL 6802004 Inst. medidor en tub. 2" 399.63 100.00% u 4.06627 1MOPL 6802005 Inst. medidor en tub. 3" 518.80 100.00% u 3.13225 1

Page 47: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 29

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

MOPL 6802006 Inst. medidor en tub. 4" 814.91 100.00% u 1.99409 1

MOPL 6802100 M.O. PLOMERIA, INST. NEVERA, BEBEDERO Y FILTRO:MOPL 6802101 Inst. bebedero animales 325.00 100.00% u 5.00 1MOPL 6802102 Inst. filtro doméstico 433.33 100.00% u 3.75 1MOPL 6802103 Inst. Nevera de pie, de tomar agua 464.29 100.00% u 3.50 1

MOPL 6802200 M.O. PLOMERIA, INST. PIEZA ESP., CAMPANA, POR DIAM., C/BOCA:MOPL 6802201 Inst. campana 3" 66.20 100.00% u 24.54545 1MOPL 6802202 Inst. campana 4" 74.63 100.00% u 21.77419 1MOPL 6802203 Inst. campana 6" 83.06 100.00% u 19.56522 1MOPL 6802204 Inst. campana 8" 103.52 100.00% u 15.69767 1MOPL 6802205 Inst. campana 10" 162.50 100.00% u 10.00000 1MOPL 6802206 Inst. campana 12" 195.00 100.00% u 8.33333 1MOPL 6802207 Inst. campana 16" 252.78 100.00% u 6.42857 1MOPL 6802208 Inst. campana 20" 281.67 100.00% u 5.76923 1

MOPL 6802300 M.O. PLOMERIA, INST. PIEZA ESP., GIBAULT, POR DIAM., C/BOCA:MOPL 6802301 Inst. Gibault 2" 50.56 100.00% u 32.14286 1MOPL 6802302 Inst. Gibault 3" 56.57 100.00% u 28.72340 1MOPL 6802303 Inst. Gibault 4" 56.57 100.00% u 28.72340 1MOPL 6802304 Inst. Gibault 6" 66.20 100.00% u 24.54545 1MOPL 6802305 Inst. Gibault 8" 119.17 100.00% u 13.63636 1MOPL 6802306 Inst. Gibault 10" 133.61 100.00% u 12.16216 1MOPL 6802307 Inst. Gibault 12" 162.50 100.00% u 10.00000 1MOPL 6802308 Inst. Gibault 16" 195.00 100.00% u 8.33333 1MOPL 6802309 Inst. Gibault 20" 252.78 100.00% u 6.42857 1

MOPL 6802400 M.O. PLOMERIA, INST. PIEZA ESP., PVC, POR DIAM., C/BOCA:MOPL 6802401 Inst. pieza especial pvc 1" 10.83 100.00% u 150.00000 1MOPL 6802402 Inst. pieza especial pvc 1 ¼" 15.65 100.00% u 103.84615 1MOPL 6802403 Inst. pieza especial pvc 1 ½" 15.65 100.00% u 103.84615 1MOPL 6802404 Inst. pieza especial pvc 2" 15.65 100.00% u 103.84615 1MOPL 6802405 Inst. pieza especial pvc 3" 19.26 100.00% u 84.37500 1MOPL 6802406 Inst. pieza especial pvc 4" 24.07 100.00% u 67.50000 1MOPL 6802407 Inst. pieza especial pvc 6" 28.89 100.00% u 56.25000 1MOPL 6802408 Inst. pieza especial pvc 8" 39.72 100.00% u 40.90909 1MOPL 6802409 Inst. pieza especial pvc 10" 50.56 100.00% u 32.142857 1MOPL 6802410 Inst. pieza especial pvc 12" 56.57 100.00% u 28.72340 1MOPL 6802411 Inst. pieza especial pvc 16" 66.20 100.00% u 24.54545 1MOPL 6802412 Inst. pieza especial pvc 20" 83.06 100.00% u 19.56522 1

MOPL 6802500 M.O. PLOMERIA, INST. PIEZA ESP., ROSCA, POR DIAM., C/BOCA:MOPL 6802501 Inst. pieza especial con rosca 1" 24.07 100.00% u 67.50000 1MOPL 6802502 Inst. pieza especial con rosca 1 ¼" 32.50 100.00% u 50.00000 1MOPL 6802503 Inst. pieza especial con rosca 1 ½" 39.72 100.00% u 40.90909 1MOPL 6802504 Inst. pieza especial con rosca 2" 50.56 100.00% u 32.14286 1MOPL 6802505 Inst. pieza especial con rosca 3" 56.57 100.00% u 28.72340 1MOPL 6802506 Inst. pieza especial con rosca 4" 66.20 100.00% u 24.54545 1MOPL 6802507 Inst. pieza especial con rosca 6" 98.70 100.00% u 16.46341 1MOPL 6802508 Inst. pieza especial con rosca 8" 162.50 100.00% u 10.00000 1MOPL 6802509 Inst. pieza especial con rosca 10" 195.00 100.00% u 8.33333 1MOPL 6802510 Inst. pieza especial con rosca 12" 252.78 100.00% u 6.42857 1

MOPL 6802600 M.O. PLOMERIA, INST. TINACO DE AGUA:MOPL 6802601 Inst. tinaco 2,708.33 100.00% u 0.60 1

MOPL 6802700 M.O. PLOMERIA, INST. TRAMPA GRASA Y CAMARA INSP.:MOPL 6802701 Inst. cámara insp., tub. 2" 814.90 100.00% u 1.9941 1MOPL 6802702 Inst. cámara insp., tub. 3" y 4" 814.90 100.00% u 1.9941 1MOPL 6802703 Inst. cámara insp. tub. 5" y 6" 1,086.52 100.00% u 1.4956 1MOPL 6802704 Inst. trampa de grasa 1 cámara 1,336.11 100.00% u 1.22 1MOPL 6802705 Inst. trampa de grasa 2 cámaras 2,076.39 100.00% u 0.78 1

*Para + de 2 entradas, 20% adic. por entrada extra

MOPL 6802800 M.O. PLOMERIA, INST. VALVULA DE AIRE:MOPL 6802801 Inst. válvula de aire + Clamps y acces. 593.43 100.00% u 2.73834 1

MOPL 6802900 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, CAMPANA:MOPL 6802901 Inst. válvula compuerta, campana 2" 252.78 100.00% u 6.42857 1MOPL 6802902 Inst. válvula compuerta, campana 3" 281.67 100.00% u 5.769231 1MOPL 6802903 Inst. válvula compuerta, campana 4" 356.30 100.00% u 4.5608 1MOPL 6802904 Inst. válvula compuerta, campana 6" 652.41 100.00% u 2.490775 1MOPL 6802905 Inst. válvula compuerta, campana 8" 814.91 100.00% u 1.99409 1MOPL 6802906 Inst. válvula compuerta, campana 10" 1,142.31 100.00% u 1.42255 1MOPL 6802907 Inst. válvula compuerta, campana 12" 1,632.22 100.00% u 0.995575 1MOPL 6802908 Inst. válvula compuerta, campana 16" 2,076.39 100.00% u 0.78261 1

MOPL 6803000 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, PLATILLO:MOPL 6803001 Inst. válvula compuerta, platillo 2" 195.00 100.00% u 8.33333 1MOPL 6803002 Inst. válvula compuerta, platillo 3" 252.78 100.00% u 6.42857 1MOPL 6803003 Inst. válvula compuerta, platillo 4" 327.41 100.00% u 4.9632 1MOPL 6803004 Inst. válvula compuerta, platillo 6" 415.28 100.00% u 3.913040 1MOPL 6803005 Inst. válvula compuerta, platillo 8" 593.43 100.00% u 2.73834 1MOPL 6803006 Inst. válvula compuerta, platillo 10" 652.41 100.00% u 2.490775 1MOPL 6803007 Inst. válvula compuerta, platillo 12" 814.91 100.00% u 1.99409 1MOPL 6803008 Inst. válvula compuerta, platillo 16" 1,185.65 100.00% u 1.37056 1

Page 48: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 30

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

MOPL 6803100 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, ROSCA:MOPL 6803101 Inst. válvula compuerta, rosca 2" 133.61 100.00% u 12.16216 1MOPL 6803102 Inst. válvula compuerta, rosca 3" 195.00 100.00% u 8.33333 1MOPL 6803103 Inst. válvula compuerta, rosca 4" 252.78 100.00% u 6.42857 1MOPL 6803104 Inst. válvula compuerta, rosca 6" 327.41 100.00% u 4.9632 1MOPL 6803105 Inst. válvula compuerta, rosca 8" 415.28 100.00% u 3.913040 1

MOPL 6803200 M.O. PLOMERIA, MONTAR BAÑERA Y DUCHA:MOPL 6803201 Montar bañera de hierro, especial 1,661.77 100.00% u 1.88053 1MOPL 6803202 Montar bañera de hierro, corriente 1,186.85 100.00% u 1.36917 1MOPL 6803203 Montar bañera pesada de hierro 1,250.00 100.00% u 2.5000 1MOPL 6803204 Montar bañera plástica o vidriada 814.90 100.00% u 1.9941 1MOPL 6803205 Montar ducha tipo teléfono 296.11 100.00% u 5.4878 1MOPL 6803206 Montar llave empotrada para ducha 296.11 100.00% u 5.4878 1MOPL 6803207 Montar mezcladora de baño 518.80 100.00% u 3.13225 1MOPL 6803208 Terminación de baño 162.50 100.00% u 10.00 1

MOPL 6803300 M.O. PLOMERIA, MONTAR FREGADERO Y LAVAPLATO:MOPL 6803301 Montar freg. acero inox. 1 cámara 742.69 100.00% u 2.188 1MOPL 6803302 Montar freg. acero inox., 2 cámaras 950.93 100.00% u 1.70886 1MOPL 6803303 Montar freg. corriente 742.69 100.00% u 2.188 1MOPL 6803304 Montar freg. especial 1 cámara 814.90 100.00% u 1.9941 1MOPL 6803305 Montar freg. especial 2 cámara 1,038.80 100.00% u 1.56431 1MOPL 6803306 Montar lavaplato automático, deméstico 1,186.85 100.00% u 1.36917 1MOPL 6803307 Montar lavaplato automático, industrial o comercial P. A. u 1MOPL 6803308 Montar trituradora de hueso, doméstica 1,632.22 100.00% u 0.995575 1MOPL 6803309 Montar trituradora de hueso, industrial o comercial P. A. u 1

MOPL 6803400 M.O. PLOMERIA, MONTAR INODORO:MOPL 6803401 Montar inodoro corriente dos cuerpos 593.43 100.00% u 2.73833 1MOPL 6803402 Montar inodoro especial, 1 cuerpo 814.90 100.00% u 1.9941 1MOPL 6803403 Montar inodoro especial, 2 cuerpos 1,336.11 100.00% u 1.21622 1MOPL 6803404 Montar inodoro especial, pared 1,336.11 100.00% u 1.21622 1MOPL 6803405 Montar inodoro fluxómetro o automát. 979.81 100.00% u 1.65848 1

MOPL 6803500 M.O. PLOMERIA, MONTAR LAVAMANOS Y BIDET:MOPL 6803501 Montar bidet 889.54 100.00% u 1.82679 1MOPL 6803502 Montar lavamanos clínico, unidad conjunto 4,448.89 100.00% u 0.36526 1MOPL 6803503 Montar lavamanos c/patas 722.22 100.00% u 2.25 1MOPL 6803504 Montar lavamanos s/patas 593.43 100.00% u 2.73833 1MOPL 6803505 Montar lavamanos empotrado 1,038.80 100.00% u 1.56431 1MOPL 6803506 Montar lavamanos especial c/patas 1,038.80 100.00% u 1.56431 1MOPL 6803507 Montar lavamanos especial s/patas 814.90 100.00% u 1.9941 1MOPL 6803508 Montar lavamanos pedestal 812.50 100.00% u 2.00 1MOPL 6803509 Montar lavamanos salón de belleza 1,038.80 100.00% u 1.56431 1

MOPL 6803600 M.O. PLOMERIA, MONTAR ORINAL:MOPL 6803601 Montar orinal ½ falda 668.06 100.00% u 2.43243 1MOPL 6803602 Montar orinal de cemento, terminación 370.74 100.00% u 4.3831 1MOPL 6803603 Montar orinal falda completa 1,038.80 100.00% u 1.56431 1MOPL 6803604 Montar orinal sencillo 742.69 100.00% u 2.188 1

MOPL 6803700 M.O. PLOMERIA, SALIDAS DE AGUA, APARATO SANIT., COBRE:MOPL 6803701 Salida tub. ½", cobre, soldada o roscada 742.69 100.00% u 2.188006 1MOPL 6803702 Salida tub. ¾", cobre, soldada o roscada 889.54 100.00% u 1.82679 1MOPL 6803703 Salida tub. 1", cobre, soldada o roscada 1,038.80 100.00% u 1.56431 1MOPL 6803704 Salida tub. 1 ¼" en adelante, cobre, soldada o roscada P. A. u 1

MOPL 6803800 M.O. PLOMERIA, SALIDAS DE AGUA, APARATO SANIT., H. G. o PVC:MOPL 6803801 Montar filtro de agua, domiciliario 668.06 100.00% u 2.43243 1MOPL 6803802 Montar filtro de agua, industrial o comercial P. A. u 1MOPL 6803803 Salida de agua tub. ½", h.g. o pvc 518.80 100.00% u 3.13225 1MOPL 6803804 Salida de agua tub. ¾", h.g. o pvc 518.80 100.00% u 3.13225 1MOPL 6803805 Salida de agua fria y caliente calentador domestico 668.06 100.00% u 2.43243 1MOPL 6803806 Salida de agua fria y caliente calentador industrial P. A. u 1MOPL 6803807 Salida de agua inodoro corriente 668.06 100.00% u 2.43243 1MOPL 6803808 Salida de agua inodoro y orinal fluxómetro 1,038.80 100.00% u 1.56431 1MOPL 6803809 Salida de agua orinal de falda completa, no fluxómetro 668.06 100.00% u 2.43243 1MOPL 6803810 Salida de agua tub. 1", h.g. o pvc 1,038.80 100.00% u 1.56431 1MOPL 6803811 Salida de agua tub. 1 ¼", h.g. o pvc 1,038.80 100.00% u 1.56431 1MOPL 6803812 Salida de agua tub. 1 ½", h.g. o pvc 1,038.80 100.00% u 1.56431 1MOPL 6803813 Salida de agua tub. 2", h.g. o pvc 1,154.22 100.00% u 1.40788 1

Nota: Salida agua colgante, pagar 35% del costo establecido

MOPL 6803900 M.O. PLOMERIA, TERM. LAVADERO Y VERTEDERO:MOPL 6803901 Term. lavadero 1 cám. c/vert. 814.90 100.00% u 1.9941 1MOPL 6803902 Term. lavadero 1 cám. s/vert. 518.80 100.00% u 3.13225 1MOPL 6803903 Term. lavadero 2 cám. c/vert. 814.90 100.00% u 1.9941 1MOPL 6803904 Term. lavadero 2 cám. s/vert. 668.06 100.00% u 2.43243 1MOPL 6803905 Term. vertedero de cem. o granito 149.26 100.00% u 10.8871 1MOPL 6803906 Term. vertedero de hierro 814.90 100.00% u 1.9941 1

MOPL 6804000 M.O. PLOMERIA, TUB. ALCANTARILLADO SANIT. Y PLUVIAL PROF. HASTA 3.00 M.:MOPL 6804001 Tub. alcant., 6" 40.07 100.00% m 53.0303 1MOPL 6804002 Tub. alcant., 8" 51.00 100.00% m 41.6667 1MOPL 6804003 Tub. alcant., 12" 57.59 100.00% m 54.26 1MOPL 6804004 Tub. alcant., 15" 75.98 100.00% m 41.13 1MOPL 6804005 Tub. alcant., 21" 140.94 100.00% m 22.173 1

Page 49: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 31

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N P. UNIT. INDICE U. REND./DIA MA OP1 OP2 OP3

MOPL 6804006 Tub. alcant., 24" 198.52 100.00% m 15.7411 1MOPL 6804007 Tub. alcant., 30" 286.77 100.00% m 10.8974 1MOPL 6804008 Tub. alcant., 36" 333.33 100.00% m 9.375 1

*Bajar tub. hasta 8" al fondo zanja y colocar asiento arena corre por plomeros. Diámetro mayor corre por patrono o empleador

MOPL 6804100 M.O. PLOMERIA, TUB. ALCANTARILLADO SANIT. Y PLUVIAL PROF. MAYOR DE 3.00 M.:MOPL 6804101 Tub. alcant., 6" 57.07 100.00% m 37.23404 1MOPL 6804102 Tub. alcant., 8" 66.79 100.00% m 31.81818 1MOPL 6804103 Tub. alcant., 12" 75.98 100.00% m 41.13 1MOPL 6804104 Tub. alcant., 15" 91.91 100.00% m 34.00 1MOPL 6804105 Tub. alcant., 21" 165.44 100.00% m 18.89 1MOPL 6804106 Tub. alcant., 24" 257.35 100.00% m 12.143 1MOPL 6804107 Tub. alcant., 30" 333.33 100.00% m 9.375 1MOPL 6804108 Tub. alcant., 36" 425.25 100.00% m 7.3487 1

*Bajar tub. hasta 8" al fondo zanja y colocar asiento arena corre por plomeros. Diámetro mayor corre por patrono o empleador

MOPL 6804200 M.O. PLOMERIA, TUB. ASBESTO CEMENTO:MOPL 6804201 Tub. 3" asbesto cemento 19.26 100.00% m 84.375 1MOPL 6804202 Tub. 4" asbesto cemento 19.26 100.00% m 84.375 1MOPL 6804203 Tub. 6" asbesto cemento 26.48 100.00% m 61.36 1MOPL 6804204 Tub. 8" asbesto cemento 32.50 100.00% m 50.00 1MOPL 6804205 Tub. 12" asbesto cemento 40.44 100.00% m 77.27 1MOPL 6804206 Tub. 16" asbesto cemento 67.41 100.00% m 46.36 1MOPL 6804207 Tub. 20" asbesto cemento 84.56 100.00% m 36.955 1

*Tub. 3" y 4" serán bajados al fondo zanja por plomeros. Diám. Mayor corre por patrono o empleador

MOPL 6804300 M.O. PLOMERIA, TUB. HIERRO FUNDIDO O ACERO:MOPL 6804301 Tub. 3" hierro fudido o acero 32.50 100.00% m 50.00 1MOPL 6804302 Tub. 4" hierro fudido o acero 39.72 100.00% m 40.90909 1MOPL 6804303 Tub. 6" hierro fudido o acero 50.56 100.00% m 32.14286 1MOPL 6804304 Tub. 8" hierro fudido o acero 56.57 100.00% m 28.7234 1MOPL 6804305 Tub. 10" hierro fudido o acero 78.43 100.00% m 39.845 1MOPL 6804306 Tub. 12" hierro fudido o acero 121.32 100.00% m 25.758 1

*Tub. 3" y 4" serán bajados al fondo zanja por plomeros. Diám. Mayor corre por patrono o empleador

MOPL 6804400 M.O. PLOMERIA, TUB. HIERRO GALV.:MOPL 6804401 Tub. ½" galv. 10.83 100.00% m 150.00 1MOPL 6804402 Tub. ¾" galv. 13.24 100.00% m 122.72727 1MOPL 6804403 Tub. 1" a 1 ½" galv. 19.26 100.00% m 84.375 1MOPL 6804404 Tub. 2" galv. 24.07 100.00% m 67.50 1MOPL 6804405 Tub. 2 ½" galv. 28.89 100.00% m 56.25 1MOPL 6804406 Tub. 3" galv. 32.50 100.00% m 50.00 1MOPL 6804407 Tub. 4" galv. 39.72 100.00% m 40.90909 1MOPL 6804408 Tub. 6" galv. 50.56 100.00% m 32.14286 1MOPL 6804409 Tub. 8" galv. 56.57 100.00% m 28.72340 1MOPL 6804410 Tub. 10" galv. 63.72 100.00% m 49.04 1MOPL 6804411 Tub. 12" galv. P. A. m 1

*Tub. Hasta 6" serán bajados al fondo zanja por plomeros. Diám. Mayor corre por patrono o empleador

MOPL 6804500 M.O. PLOMERIA, TUB. PVC:MOPL 6804501 Tub. ½" pvc y ¾" pvc 4.39 100.00% m 369.86301 1MOPL 6804502 Tub. ¾" pvc 8.79 100.00% m 184.93150 1MOPL 6804503 Tub. 1 ¼" y 1 ½" pvc 10.99 100.00% m 147.86418 1MOPL 6804504 Tub. 2" pvc 10.99 100.00% m 147.86418 1MOPL 6804505 Tub. 3" pvc 15.65 100.00% m 103.84615 1MOPL 6804506 Tub. 4" pvc 18.06 100.00% m 90.00 1MOPL 6804507 Tub. 6" pvc 21.97 100.00% m 73.97260 1MOPL 6804508 Tub. 8" pvc 24.07 100.00% m 67.50 1MOPL 6804509 Tub. 10" pvc 29.41 100.00% m 106.25 1MOPL 6804510 Tub. 12" pvc 31.86 100.00% m 98.09 1

MOVA 6900000 MANO DE OBRA VARILLEROS:MOVA 6900001 Coloc. acero ¼" en piso o losa 320.86 100.00% qq 6.389 1MOVA 6900002 Coloc. acero alta resistencia 323.23 100.00% qq 7.889 1MOVA 6900003 Coloc. acero col. 3/8" ó ½", hasta 6 de ½" 71.30 100.00% m 28.750 1MOVA 6900004 Coloc. acero col. Redonda 6 de ½" hasta 4 de ¾" 106.95 100.00% m 19.167 1MOVA 6900005 Coloc. acero dintel y v. Amarre hasta 20x.40 y ½" ó 3/8" 71.30 100.00% m 28.750 1MOVA 6900006 Coloc. Acero fuera ciudad (30 km. o más) (25% adic.) P. A.MOVA 6900007 Coloc. acero losa con Lima Hoya o Lima Tesa (50% adic.) 323.23 100.00% qq 7.889 1MOVA 6900008 Coloc. acero malla electrosoldada 320.86 100.00% qq 6.389 1MOVA 6900009 Coloc. acero normal 213.92 100.00% qq 9.583 1MOVA 6900010 Coloc. acero rampa escalera corriente 2,125.00 100.00% rampa 1.200 1MOVA 6900011 Coloc. acero viga 6 de ½" ó ¾", 2 de 1" y 2 de ¾", 25x40 71.83 100.00% m 35.500 1MOVA 6900012 Coloc. acero viga postens. y pórticos en col. 341.37 100.00% qq 7.470 1MOVA 6900013 Coloc. acero zapata de muros 71.30 100.00% m 28.750 1MOVA 6900014 Subir acero techo 2do. Nivel (10%) 21.43 100.00% qq 70.000MOVA 6900015 Subir acero techo 3er. Nivel (15%) 32.14 100.00% qq 46.667MOVA 6900016 Subir acero techo 4to. Nivel (20%) 42.86 100.00% qq 35.000MOVA 6900017 Subir acero techo 5to. Nivel (25%) 53.57 100.00% qq 28.000MOVA 6900018 Subir acero techo 6to. Nivel (30%) 64.29 100.00% qq 23.333MOVA 6900019 Trasladar acero distancia > 10 m. (10% adicional) 10.00% 100.00% qq

MOVO 7000000 MANO DE OBRA VARIOS:MOVO 7000001 Ascensor, instalación qq 1

Page 50: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 32

MANO DE OBRAAY TC TNC ABR 2010

5,100.00

1 132.501 189.291 530.001 147.221 1,325.001 883.331 132.501 220.83

1 314.291 1 1 1,073.171 1 1 100.001 1 1 68.751 1 1 169.231 1 1 111.68

5.00%

1 1 1 880.00

1 1 1 880.00

1 1 608.33

1 1 1,013.89

P. A.

1 1 414.77P. A.

1 1 1 880.00

1 1 13.201 1 10.311 1 11.001 1 12.221 1 12.221 1 1 22.501 18.67

1 24.091 66.25

1 24.561 1.46

1 191.671 115.00

1 153.331 38.331 P. A.1 20.91

1 1 202.781 1 163.331 1 111.361 1 182.501 1 87.501 1 107.351 1 96.051 1 152.081 1 39.291 1 113.751 1 125.861 1 P. A.

1 71.881 1 13.41

1 88.461 76.671 165.63

1 1 228.131 1 182.50

1 50.961 1 182.50

1 52.27

Page 51: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 33

MANO DE OBRAAY TC TNC ABR 2010

1 87.501 25.00

1 1 31.731 19.831 66.25

P. A.1 1 608.33

1 161.97

1 339.742 357.142 437.501 143.751 189.291 165.631 278.951 139.471 85.19

8.4110.13

1 121.051 1 182.501 1 228.13

1 1.461 0.981 0.731 0.491 3.651 1.971 1.461 0.981 1 508.33

P. A.1 6.631 8.441 6.311 4.651 6.97

1 2,025.001 1,012.50

P. A.1 1 1,700.001 766.67

1 2 215.001 2 238.891 2 252.941 2 265.431 2 277.06

1 331.251 530.001 441.671 530.001 407.691 616.281 1,019.231 662.50

1 378.571 331.251 378.571 1,394.741 489.36

1 130.68

1 344.16

1 60.231 52.271 220.831 265.001 252.38

Page 52: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 34

MANO DE OBRAAY TC TNC ABR 2010

1 308.141 232.461 278.951 288.041 331.25

1 1 1 196.361 1 1 84.381 1 1 112.501 1 1 119.12

1 150.571 150.571 194.85

1 318.181 368.421 1 121.671 1 165.911 1 165.911 1 130.361 1 140.381 1 140.381 1 165.911 1 173.811 1 173.811 1 121.671 1 121.671 1 130.361 1 140.381 1 165.911 1 1 84.381 1 1 112.501 1 1 72.321 1 121.671 1 146.00

1 100.001 44.171 77.941 101.921 60.23

1 92.361 75.401 52.521 105.541 169.671 203.561 186.821 226.291 262.171 282.61

1 766.671 920.001 1 1,525.00

1 530.001 441.671 252.381 265.001 308.14

P. A.P. A.P. A.

1 2,038.461 1,766.671 220.831 252.381 331.251 278.951 378.571 255.561 441.671 378.571 165.631 331.251 576.091 165.631 189.291 203.851 30.11

3 79.693 127.503 182.143 255.00

Page 53: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 35

MANO DE OBRAAY TC TNC ABR 2010

3 318.753 425.003 0.713 0.853 1.133 1.423 1.703 1.163 1.963 2.553 3.643 4.253 0.853 1.283 1.703 2.133 2.553 1.423 2.133 2.833 3.923 4.643 1.063 1.593 2.133 2.663 3.193 1.803 2.683 3.593 4.473 5.433 1.283 1.923 2.553 3.193 3.813 2.133 3.193 4.253 5.313 6.383 1.503 2.323 3.073 3.813 4.553 2.553 3.813 5.103 6.383 7.733 5.313 8.503 11.593 15.003 19.623 106.253 159.383 255.003 318.753 425.003 579.55

1 53.001 1 188.461 76.561 47.121 27.221 40.83

585.82245.06

1 1 1,894.271 1 252.941 1 1,580.881 1 252.941 1 1,580.881 1 316.181 1 474.09

Page 54: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 36

MANO DE OBRAAY TC TNC ABR 2010

2 388.002 299.56

20.00%

2 158.332 158.33

20.00%

2 106.982 122.682 141.222 176.882 211.112 246.792 281.02

2 122.682 158.332 176.882 281.022 318.102 350.912 422.23

2 141.222 158.332 176.882 88.442 106.982 122.68

2 18.542 21.402 21.402 22.822 1.752 21.40

2 37.091 37.272 52.782 41.372 59.912 52.782 88.442 47.082 28.532 37.092 21.40

2 122.682 141.222 158.332 176.882 278.252 P. A.2 106.982 37.092 74.182 111.272 148.362 185.452 106.982 P. A.

2 23.382 128.382 161.19

2 37.092 350.912 P. A.2 350.912 P. A.

4 68.954 177.30

Page 55: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 37

MANO DE OBRAAY TC TNC ABR 2010

4 3,046.304 467.894 949.184 1,208.004 863.304 372.424 177.304 132.744 198.574 86.194 103.424 553.424 261.984 284.484 258.824 606.164 344.754 3,191.894 344.034 457.554 510.724 677.224 198.254 10.344 10.344 322.364 284.484 224.124 32.754 517.134 261.984 284.484 322.364 224.12

2 192.582 192.582 176.892 141.222 41.372 21.402 41.372 52.782 122.682 176.892 262.482 41.372 52.782 69.902 439.372 350.922 527.812 703.262 703.262 350.922 527.81

2 176.88ver Vigas

2 246.782 52.782 106.982 122.682 141.222 158.33

20.00%2 37.092 25.682 128.382 88.442 106.98

1 850.001 283.331 500.001 850.001 242.861 106.251 42.501 106.251 212.50

1 1 1,464.29

Page 56: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 38

MANO DE OBRAAY TC TNC ABR 2010

1 1 1,025.00

1 1 1,045.311 1 P. A.1 1 P. A.1 1 87.701 1 175.401 1 347.971 1 523.371 1 523.371 1 347.971 1 115.941 1 347.971 1 278.661 1 P. A.1 1 523.37

1 1 90.531 1 271.621 1 543.171 1 905.261 1 1,131.611 1 1,357.961 1 1,809.791 1 2,263.21

1 1 387.571 1 469.621 1 611.021 1 752.53

1 1 297.041 1 257.72

1 1 550.771 1 666.711 1 716.001 1 831.951 1 881.211 1 997.16

1 1 387.571 1 387.571 1 469.621 1 387.571 1 469.621 1 523.371 1 469.621 1 575.711 1 387.571 1 387.571 1 441.171 1 543.171 1 115.991 1 193.79

1 1 175.401 1 257.72

1 1 P. A.

150.001 382.651 421.351 462.962 974.031 614.751 646.551 707.55

1,610.001,771.001,932.00

1 781.251 815.22

Según aplique

Page 57: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 39

MANO DE OBRAAY TC TNC ABR 2010

1 872.091 528.171 559.701 604.841 235.851 264.081 288.46

JORNAL JORNAL

MENSUAL DIARIO

11,915.00 500.00

109,618.00 4,600.00

26,808.75 1,125.00

21,447.00 900.00

17,276.75 725.00

14,893.75 625.00

10,127.75 425.00

8,936.25 375.00

1 19.261 19.261 10.831 7.221 24.071 18.061 12.041 30.091 30.091 25.281 55.371 20.461 12.041 19.261 18.061 37.321 14.441 10.831 6.251 25.001 20.46

1 668.061 327.411 252.78

1 32.501 39.721 66.201 83.06

5.00%10.00%20.00%25.00%35.00%

1 518.801 593.431 668.061 889.54

1 5,931.851 5,931.85

1 2,031.251 2,954.551 4,062.50

1 1,625.001 1,186.851 1,425.441 P. A.

1 742.69

Page 58: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 40

MANO DE OBRAAY TC TNC ABR 2010

1 1,038.801 1,186.851 P. A.

1 250.001 285.091 445.371 518.801 593.431 742.691 889.54

1 445.371 518.801 593.431 742.69

1 812.501 2,668.621 2,668.621 2,965.921 3,262.041 3,334.261 3,334.261 3,707.411 4,080.56

1 518.801 668.061 814.911 593.431 668.06

50.00%

1 593.431 742.681 889.541 1,038.801 P. A.

1 445.371 593.431 742.681 889.54

1 83.061 98.70

1 2,521.76

1 1,186.851 P. A.

1 668.061 889.541 1,038.801 1,111.021 1,186.851 P. A.1 296.111 445.371 814.90

1 83.061 98.701 162.501 327.411 415.28

1 281.671 327.411 356.301 399.631 518.80

Page 59: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 41

MANO DE OBRAAY TC TNC ABR 2010

1 814.91

1 325.001 433.331 464.29

1 66.201 74.631 83.061 103.521 162.501 195.001 252.781 281.67

1 50.561 56.571 56.571 66.201 119.171 133.611 162.501 195.001 252.78

1 10.831 15.651 15.651 15.651 19.261 24.071 28.891 39.721 50.561 56.571 66.201 83.06

1 24.071 32.501 39.721 50.561 56.571 66.201 98.701 162.501 195.001 252.78

1 2,708.33

1 814.901 814.901 1,086.521 1,336.111 2,076.39

1 593.43

1 252.781 281.671 356.301 652.411 814.911 1,142.311 1,632.221 2,076.39

1 195.001 252.781 327.411 415.281 593.431 652.411 814.911 1,185.65

Page 60: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 42

MANO DE OBRAAY TC TNC ABR 2010

1 133.611 195.001 252.781 327.411 415.28

1 4 1,661.771 1,186.851 4 1,250.001 814.901 296.111 296.111 518.801 162.50

1 742.691 950.931 742.691 814.901 1,038.801 1,186.851 P. A.1 1,632.221 P. A.

1 593.431 814.901 1,336.111 1,336.111 979.81

1 889.541 4,448.891 722.221 593.431 1,038.801 1,038.801 814.901 812.501 1,038.80

1 668.061 370.741 1,038.801 742.69

1 742.691 889.541 1,038.801 P. A.

1 668.061 P. A.1 518.801 518.801 668.061 P. A.1 668.061 1,038.801 668.061 1,038.801 1,038.801 1,038.801 1,154.22

1 814.901 518.801 814.901 668.061 149.261 814.90

2 40.072 51.004 57.594 75.984 140.94

Page 61: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 43

MANO DE OBRAAY TC TNC ABR 2010

4 198.524 286.774 333.33

2 57.072 66.794 75.984 91.914 165.444 257.354 333.334 425.25

1 19.261 19.261 26.481 32.504 40.444 67.414 84.56

1 32.501 39.721 50.561 56.574 78.434 121.32

1 10.831 13.241 19.261 24.071 28.891 32.501 39.721 50.561 56.574 63.724 P. A.

1 4.391 8.791 10.991 10.991 15.651 18.061 21.971 24.074 29.414 31.86

1 1 320.862 1 323.231 1 71.301 1 106.951 1 71.30

P. A.2 1 323.231 1 320.861 1 213.922 1 2,125.002 1 71.832 1 341.371 1 71.30

4 21.434 32.144 42.864 53.574 64.29

10.00%

1 1

Page 62: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 32

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

* 10000000 ANALISIS DE COSTOS (Con ITBIS incluido)

*ACE 10010000 A C E R O S

*ACE 10010100 ACERO DE ¼":1 Acero ¼" 1.00 qq 1,025.00 1,025.002 Alambre #18 2.50 lb 25.44 63.60

QQ $1,088.60*ACE 10010101 ACERO GRADO 40, 3/8" x 20':

1 Acero 3/8" 1.00 qq 1,865.00 1,865.002 Alambre #18 2.00 lb 25.44 50.88

QQ $1,915.88*ACE 10010102 ACERO GRADO 40, 3/8" x 25':

1 Acero 3/8" 1.00 qq 1,865.00 1,865.002 Alambre #18 2.00 lb 25.44 50.88

QQ $1,915.88*ACE 10010103 ACERO GRADO 40, ½" x 20':

1 Acero ½" 1.00 qq 1,865.00 1,865.002 Alambre #18 2.00 lb 25.44 50.88

QQ $1,915.88*ACE 10010104 ACERO GRADO 40, ½" x 25':

1 Acero ½" 1.00 qq 1,865.00 1,865.002 Alambre #18 2.00 lb 25.44 50.88

QQ $1,915.88*ACE 10010105 ACERO GRADO 40, ¾":

1 Acero ¾" 1.00 qq 1,865.00 1,865.002 Alambre #18 2.00 lb 25.44 50.88

QQ $1,915.88*ACE 10010106 ACERO GRADO 40, DE 1":

1 Acero 1" 1.00 qq 1,865.00 1,865.002 Alambre #18 2.00 lb 25.44 50.88

QQ $1,915.88*ACE 10010107 ACERO GRADO 60, 3/8" x 20':

1 Acero 3/8" 1.00 qq 1,970.20 1,970.202 Alambre #18 2.00 lb 25.44 50.88

QQ $2,021.08*ACE 10010108 ACERO GRADO 60, 3/8" x 25':

1 Acero 3/8" 1.00 qq 1,970.20 1,970.202 Alambre #18 2.00 lb 25.44 50.88

QQ $2,021.08*ACE 10010109 ACERO GRADO 60, ½" x 20':

1 Acero ½" 1.00 qq 1,970.20 1,970.202 Alambre #18 2.00 lb 25.44 50.88

QQ $2,021.08*ACE 10010110 ACERO GRADO 60, ½" x 25':

1 Acero ½" 1.00 qq 1,970.20 1,970.202 Alambre #18 2.00 lb 25.44 50.88

QQ $2,021.08*ACE 10010111 ACERO GRADO 60, ¾":

1 Acero ¾" 1.00 qq 1,970.20 1,970.202 Alambre #18 2.00 lb 25.44 50.88

QQ $2,021.08*ACE 10010112 ACERO GRADO 60, DE 1":

1 Acero 1" 1.00 qq 1,970.20 1,970.202 Alambre #18 2.00 lb 25.44 50.88

QQ $2,021.08

*BLO 10030000 BLOQUES, MUROS DE

*BLO 10030001 BLOQUES HORM. 4", ¼" A .80 M.:1 Bloques horm. + 3% desp. 12.875 u 29.28 376.982 Mortero 1:3 en juntas + 30% desp. 0.0200 m3 3,932.52 78.653 Horm. en cámaras + 2% desp. 0.0092 m3 3,572.06 32.864 Acero ¼" + 20% desp. 0.0112 qq 1,088.60 12.195 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 29.00 0.076 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 900.00 20.707 Corte y amarre varilla 13.00 u 0.49 6.378 Llenado huecos 13.00 u 0.98 12.749 Coloc. bloques 13.00 u 13.20 171.60

M2 $712.16*BLO 10030002 BLOQUES HORM. 5", 3/8" A .80 M.:

1 Bloques horm. + 3% desp. 12.875 u 30.22 389.082 Mortero 1:3 en juntas + 30% desp. 0.0260 m3 3,932.52 102.253 Horm. en cámaras + 2% desp. 0.0200 m3 3,572.06 71.444 Acero 3/8" x 20' grado 40 + 20% desp. 0.0247 qq 1,915.88 47.325 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 29.00 0.076 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 900.00 20.707 Corte y amarre varilla 13.00 u 0.49 6.378 Llenado huecos 13.00 u 0.98 12.749 Coloc. bloques 13.00 u 11.00 143.00

M2 $792.97*BLO 10030003 BLOQUES HORM. 6", 3/8" A .40 M.:

1 Bloques horm. + 3% desp. 12.875 u 28.25 363.722 Mortero 1:3 en juntas + 30% desp. 0.0312 m3 3,932.52 122.693 Horm. en cámaras + 2% desp. 0.0480 m3 3,572.06 171.464 Acero 3/8" x 20' grado 40 + 20% desp. 0.0493 qq 1,915.88 94.455 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 29.00 0.076 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 900.00 20.70

Page 63: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 33

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

7 Corte y amarre varilla 13.00 u 0.98 12.748 Llenado huecos 13.00 u 1.97 25.619 Coloc. bloques 13.00 u 11.00 143.00

M2 $954.44*BLO 10030004 BLOQUES HORM. 6", 3/8" A .80 M.:

1 Bloques horm. + 3% desp. 12.875 u 28.25 363.722 Mortero 1:3 en juntas + 30% desp. 0.0312 m3 3,932.52 122.693 Horm. en cámaras + 2% desp. 0.0240 m3 3,572.06 85.734 Acero 3/8" x 20' grado 40 + 20% desp. 0.0247 qq 1,915.88 47.325 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 29.00 0.076 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 900.00 20.707 Corte y amarre varilla 13.00 u 0.49 6.378 Llenado huecos 13.00 u 0.98 12.749 Coloc. bloques 13.00 u 11.00 143.00

M2 $802.34*BLO 10030005 BLOQUES HORM. 6" VIOL. 2 CARAS, 3/8" A .80 M.:

1 Bloques horm. + 3% desp. 12.875 u 28.25 363.722 Mortero de juntas + 30% desp. 0.0312 m3 3,932.52 122.693 Horm. en cámaras + 2% desp. 0.0240 m3 3,572.06 85.734 Acero 3/8" x 20' grado 40 + 20% desp. 0.0247 qq 1,915.88 47.325 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 29.00 0.076 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 900.00 20.707 Corte y amarre varilla 13.00 u 0.49 6.378 Llenado huecos 13.00 u 0.98 12.749 Coloc. bloques + violinado ambas caras. 13.00 u 13.92 180.96

M2 $840.30*BLO 10030006 BLOQUES 8", 3/8" A .20 M. + 2 HORIZ. DE 3/8" CADA 0.40 M.: 9.15 M2

1 Bloques horm. + 3% desp. 12.875 u 36.53 470.322 Mortero 1:3 en juntas + 30% desp. 0.0390 m3 3,932.52 153.373 Horm. en cámaras + 2% desp. 0.0916 m3 3,572.06 327.204 Acero horiz. 3/8" x 20' grado 40 + 20% desp. 0.0740 qq 1,915.88 141.785 Acero vert. 3/8" x 20' grado 60 + 20% desp. 0.0678 qq 2,021.08 137.036 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 29.00 0.077 Andamios. 0.1818 pt 29.00 5.278 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 900.00 20.709 Corte y amarre varilla. 13.00 u 1.88 24.4110 Llenado huecos. 13.00 u 1.97 25.6111 Coloc. bloques. 13.00 u 12.22 158.86

M2 $1,464.62*BLO 10030007 BLOQUES HORM. 8", 3/8" A .20 M.:

1 Bloques horm. + 3% desp. 12.875 u 36.53 470.322 Mortero 1:3 en juntas + 30% desp. 0.0390 m3 3,932.52 153.373 Horm. en cámaras + 2% desp. 0.0916 m3 3,572.06 327.204 Acero 3/8" x 20' grado 40 + 20% desp. 0.0740 qq 1,915.88 141.785 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 29.00 0.076 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 900.00 20.707 Corte y amarre varilla 13.00 u 1.46 18.988 Llenado huecos 13.00 u 3.65 47.459 Coloc. bloques 13.00 u 12.22 158.86

M2 $1,338.73*BLO 10030008 BLOQUES HORM. 8", 3/8" A .40 M.:

1 Bloques horm. + 3% desp. 12.875 u 36.53 470.322 Mortero 1:3 en juntas + 30% desp. 0.0390 m3 3,932.52 153.373 Horm. en cámaras + 2% desp. 0.0612 m3 3,572.06 218.614 Acero 3/8" x 20' grado 40 + 20% desp. 0.0493 qq 1,915.88 94.455 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 29.00 0.076 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 900.00 20.707 Corte y amarre varilla 13.00 u 0.98 12.748 Llenado huecos 13.00 u 1.97 25.619 Coloc. bloques 13.00 u 12.22 158.86

M2 $1,154.73*BLO 10030009 BLOQUES HORM. 8", 3/8" A .80 M.:

1 Bloques horm. + 3% desp. 12.875 u 36.53 470.322 Mortero 1:3 en juntas + 30% desp. 0.0390 m3 3,932.52 153.373 Horm. en cámaras + 2% desp. 0.0306 m3 3,572.06 109.314 Acero 3/8" x 20' grado 40 + 20% desp. 0.0247 qq 1,915.88 47.325 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 29.00 0.076 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 900.00 20.707 Corte y amarre varilla 13.00 u 0.49 6.378 Llenado huecos 13.00 u 0.98 12.749 Coloc. bloques 13.00 u 12.22 158.86

M2 $979.06*BLO 10030010 BLOQUES HORM. 8", C. LLENAS, 3/8" A 0.40 M.:

1 Bloques horm. + 3% desp. 12.875 u 36.53 470.322 Mortero 1:3 en juntas + 30% desp. 0.0390 m3 3,932.52 153.373 Horm. en cámaras + 2% desp. 0.0916 m3 3,572.06 327.204 Acero 3/8" x 20' grado 40 + 20% desp. 0.0493 qq 1,915.88 94.455 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 29.00 0.076 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 900.00 20.707 Corte y amarre varilla 13.00 u 0.98 12.748 Llenado huecos 13.00 u 1.96 25.489 Coloc. bloques 13.00 u 12.22 158.86

M2 $1,263.19*BLO 10030011 BLOQUES HORM. 12", 3/8" A .80 M.:

1 Bloques horm. + 3% desp. 12.875 u 104.91 1,350.722 Mortero 1:3 en juntas + 30% desp. 0.0593 m3 3,932.52 233.203 Horm. en cámaras + 2% desp. 0.0178 m3 3,572.06 63.584 Acero 3/8" x 20' grado 40 + 20% desp. 0.0247 qq 1,915.88 47.32

Page 64: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 34

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

5 Madera para andamios (1.091 pt / 6 usos) 0.0023 pt 29.00 0.076 Conf. Andamios (0.018 hora peón / m2) 0.0230 día 900.00 20.707 Corte y amarre varilla 13.00 u 0.49 6.378 Llenado huecos 13.00 u 0.98 12.749 Coloc. bloques 13.00 u 22.50 292.50

M2 $2,027.20*BLO 10030012 BLOQUES CALADOS LADRILLO 6"x6"x6":

1 Mortero 1:4 para empañete + 10% desp. 0.0180 m3 4,710.27 84.782 Bloques calados + 5% desp. 46.67 u 36.08 1,683.623 Colocación bloques calados. 46.67 u 24.09 1,124.28

M2 $2,892.68*BLO 10030013 BLOQUES CALADOS LADRILLO 8"x8"x6":

1 Mortero 1:4 para empañete + 10% desp. 0.0116 m3 4,710.27 54.642 Bloques calados + 5% desp. 26.25 u 36.61 961.083 Colocación bloques calados. 26.25 u 24.09 632.36

M2 $1,648.08*BLO 10030014 BLOQUES CALADOS TIPO PERSIANA 15x20x40:

1 Mortero 1:4 para empañete + 10% desp. 0.0086 m3 4,710.27 40.512 Bloques calados + 5% desp. 13.13 u 74.39 976.743 Colocación bloques calados. 13.13 u 24.09 316.30

M2 $1,333.55

*BOR 10050000 BORDILLOS DE BLOQUES DE HORM.

*BOR 10050001 BORDILLO 4", 2 LINEAS, 1:2:4, ZAP. .20x.15 M.)1 Excavación (1.00 x .20 x .55 m.) 0.11 m3 235.85 25.942 Relleno de reposición 0.0400 m3 198.77 7.953 Bote material excavado sobrante 0.0900 m3 300.00 27.004 Horm. 1:2:4 en zapata (2 de 3/8" + 3/8 a .30 m.) 0.0300 m3 8,632.15 258.965 Bloques de 4" 0.4000 m2 712.16 284.866 Empañete 0.7000 m2 220.88 154.627 Cantos 1.10 m 72.49 79.748 Pintura acrílica 0.70 m2 112.63 78.84

M $917.91*BOR 10050002 BORDILLO 6", 2 LINEAS, 1:2:4, ZAP. .30x.15 M.)

1 Excavación (1.00 x .30 x .55 m.) 0.17 m3 235.85 40.092 Relleno de reposición 0.0636 m3 198.77 12.653 Bote material excavado sobrante 0.1400 m3 300.00 42.004 Horm. 1:2:4 en zapata (2 de 3/8" + 3/8 a .30 m.) 0.0500 m3 7,157.50 357.885 Bloques de 6" 0.4000 m2 802.34 320.946 Empañete 0.8000 m2 220.88 176.707 Cantos 1.10 m 72.49 79.748 Pintura acrílica 0.80 m2 112.63 90.10

M $1,120.10*BOR 10050003 BORDILLO 6", 2 LINEAS, 1:2:4, ZAP. .40x.15 M.)

1 Excavación (1.00 x .40 x .55 m.) 0.22 m3 235.85 51.892 Relleno de reposición 0.0800 m3 198.77 15.903 Bote material excavado sobrante 0.1800 m3 300.00 54.004 Horm. 1:2:4 en zapata (2 de 3/8" + 3/8 a .30 m.) 0.0600 m3 6,421.75 385.315 Bloques de 6" 0.4000 m2 979.06 391.626 Empañete 0.8000 m2 220.88 176.707 Cantos 1.10 m 72.49 79.748 Pintura acrílica 0.80 m2 112.63 90.10

M $1,245.26

*CAS 10070000 CASETAS DE MATERIALES

*CAS 10070001 CASETA MAT. 12'x16', P/200 F. CEMENTO:Area de caseta 17.86 m2Parales pino bruto amer. (14 de 2"x4"x12') 112.00 ptDurmientes pino bruto amer. (7 de 2"x4"x8') 37.33 ptCargaderas pino bruto amer. (5 de 2"x4"x14') 18.67 ptEnlates pino bruto amer. (5 de 2"x4"x18') 24.00 ptPuerta pino bruto amer. (4 de 1"x4"x8') 10.67 pt

1 Total pino bruto amer. (4 usos + 25% desp.) 63.33 pt 29.00 1,836.572 Plywood 4'x8'x¾", 2 caras, 6 usos (13 unid.) 2.17 u 1,150.00 2,495.503 Puerta en Plywood 4'x8'x¾", 2 caras, 6 usos (1 unid.) 0.17 u 1,150.00 195.504 Zinc acanalado 3'x7' cal. 26, 4 usos (14 / 4) 3.50 u 498.80 1,745.805 Clavos corrientes (5 lb. / 100 pie madera) 10.13 lb 24.79 251.216 Clavos de zinc + 5% desp. (.133 lb. / plancha) 1.86 lb 33.76 62.797 Bisagras 3 ½" x 3 ½" 2.00 pares 69.60 139.208 Pestillo 1.00 u 28.65 28.659 Portacandado 1.00 u 24.24 24.2410 Candado 1.00 u 495.90 495.9011 Salida luces 2.00 u 842.96 1,685.9212 Salida interruptor sencillo 2.00 u 857.00 1,714.0013 Salida tomacorrientes 110 v. 1.00 u 963.07 963.0714 Replanteo y excavación 14 hoyos de .2x.2x.3 m. 14.00 u 37.50 525.0015 Carpintero 2da., montar y desmontar 4.00 días 725.00 2,900.0016 Ayudante carpintero, montar y desmontar 4.00 días 500.00 2,000.00

Unid. $17,063.35M2 $955.39

*CAS 10070002 CASETA MAT. 12'x32', P/500 F. CEMENTO:Area de la caseta 33.67 m2Parales pino bruto amer. (4 de 4"x4"x12') 64.00 ptParales pino bruto amer. (5 de 4"x4"x10') 66.67 ptParales pino bruto amer. (12 de 2"x4"x12') 96.00 ptParales pino bruto amer. (5 de 2"x4"x10') 33.33 pt

Page 65: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 35

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

Durmientes pino bruto amer. (9 de 2"x4"x14') 84.00 ptDurmientes pino bruto amer. (18 de 2"x4"x12') 144.00 ptCargaderas pino bruto amer. (9 de 2"x4"x16') 96.00 ptCorreas pino bruto amer. (7 de 1"x4"x18') 42.00 ptCorreas pino bruto amer. (7 de 1"x4"x16') 37.33 ptEnlates pino bruto amer. (3 de 1"x4"x14') 14.00 ptEnlates pino bruto amer. (5 de 1"x4"x12') 20.00 ptEnlates pino bruto amer. (2 de 1"x4"x10') 6.67 ptEnlates pino bruto amer. (2 de 1"x4"x8') 5.33 ptPuertas (2), pino bruto amer. (8 de 1"x4"x8') 21.33 ptVentanas (5 de 4'x4'), pino bruto amer. (15 de 1"x8"x8') 80.00 ptVentanas (5 de 4'x4'), pino bruto amer. (5 de 1"x4"x8') 13.33 ptVentanas (5 de 4'x4'), pino bruto amer. (5 de 1"x4"x6') 10.00 pt

1 Total pino bruto amer. (4 usos + 25% desp.) 260.62 pt 29.00 7,557.982 Plywood 4'x8'x¾", 2 caras, 6 usos (17 unid.) 2.83 u 1,150.00 3,254.503 Puerta en Plywood 4'x8'x¾", 2 caras, 6 usos (2 unid.) 0.33 u 1,150.00 379.504 Zinc acanalado 3'x7' cal. 26, 4 usos (27 / 4) 6.75 u 425.05 2,869.095 Clavos corrientes (5 lb. / 100 pie madera) 41.70 lb 24.79 1,033.736 Clavos de zinc + 5% desp. (.133 lb. / plancha) 3.59 lb 33.76 121.207 Bisagras 3 ½" x 3 ½" 8.00 pares 69.60 556.808 Pestillo 7.00 u 28.65 200.559 Portacandado 2.00 u 24.24 48.4810 Candado 2.00 u 495.90 991.8011 Salida luces 3.00 u 842.96 2,528.8812 Salida interruptor sencillo 3.00 u 857.00 2,571.0013 Salida tomacorrientes 110 v. 1.00 u 963.07 963.0714 Replanteo y excavación 14 hoyos de .2x.2x.3 m. 26.00 u 37.50 975.0015 Carpintero 2da., montar y desmontar 8.00 días 725.00 5,800.0016 Ayudante carpintero, montar y desmontar 8.00 días 500.00 4,000.00

Unid. $33,851.58M2 $1,005.39

*CON 10090000 CONTEN (TELFORD)Area de sección: 0.10 m2Volumen / metro: 0.10 m3Vol. analizado: 1.00 m3Longitud total: 10.00 m

1 Madera (110 p2 / 10 usos + 10% desp.). 12.10 pt 29.00 350.902 Clavos (5 lb. / 100 p2) 5.50 lb 24.79 136.353 Hormigón 1:3:5 contén + 2% desp. 1.02 m3 3,572.06 3,643.504 Base horm. 1:3:5 + 85% de piedras, 0.15 m. espesor + 10% desp. 0.74 m3 1,173.31 868.255 Mortero 1:2 para pulido. 0.10 m3 6,371.00 637.106 Base contén (mano de obra solamente). 0.08 m3 314.29 25.147 Construcción contén. 10.00 m 111.68 1,116.80

M3 $6,778.04M $677.80

*DES 10110000 DESAGÜES PLUVIALES

*DES 10110001 DESAGÜES PLUVIALES 3": (Vivienda de un nivel)1 Tubo 3"x20' PVC SDR-26 + 10% desp. 0.500 tubo 676.26 338.132 Codo 3" PVC drenaje 1.00 u 35.31 35.313 Cemento PVC + 25% desp. (¼ galón). 0.040 u 238.00 9.524 Ttapado ranura ambas caras en la pared. 0.20 día 375.00 75.005 Mano de obra plomero 1.00 u 518.80 518.80

Unid. $976.76*DES 10110002 DESAGÜES PLUVIALES 4":: (Vivienda de un nivel)

1 Tubo 4"x20' PVC SDR-26 + 10% desp. 0.500 tubo 1,067.20 533.602 Codo 4" PVC drenaje 1.00 u 35.31 35.313 Cemento PVC + 25% desp. (¼ galón). 0.040 u 238.00 9.524 Ttapado ranura ambas caras en la pared. 0.20 día 375.00 75.005 Mano de obra plomero 1.00 m 593.43 593.43

Unid. $1,246.86

*EMP 10130000 EMPAÑETES

*EMP 10130001 CANTOS:1 Mortero 1:4 p/empañete + 10% desp., 1.67 cm. 0.00367 m3 4,710.27 17.292 Reglas (2 de 1"x4"x3.28' / 10 usos) 0.1093 pt 154.28 16.873 Mano de obra 1.00 m 38.33 38.33

M $72.49*EMP 10130002 CARETEO CON LLANA, SIN ANDAMIOS:

1 Mortero 1:4 p/empañete + 30% desp., 1.5 mm. esp. 0.00195 m3 4,710.27 9.192 Mano de obra 1.00 m2 20.91 20.91

M2 $30.10*EMP 10130003 EMPAÑETE maestrado COLUMNAS:

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. esp. 0.02171 m3 4,710.27 102.262 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 154.28 5.143 Andamios (1.091 p2 / 6 usos) 0.1820 pt 29.00 5.284 Conf. andamios 0.0230 día 900.00 20.705 Mano de obra 1.00 m2 163.33 163.33

M2 $296.71*EMP 10130004 EMPAÑETE maestrado EXTERIOR:

1 Mortero 1:4 p/empañete + 30% desp., 2.0 cm. esp. 0.02600 m3 4,710.27 122.472 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 154.28 5.143 andamios 1.4402 pt 29.00 41.774 Conf. andamios 0.0703 día 900.00 63.275 Clavos corrientes 0.1590 lb 24.79 3.946 Mano de obra 1.00 m2 111.36 111.36

Page 66: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 36

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

M2 $347.95*EMP 10130005 EMPAÑETE maestrado INTERIOR:

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. esp. 0.02171 m3 4,710.27 102.262 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 154.28 5.143 Andamios (1.091 p2 / 6 usos) 0.1820 pt 29.00 5.284 Conf. andamios 0.0230 día 900.00 20.705 Mano de obra 1.00 m2 87.50 87.50

M2 $220.88*EMP 10130006 EMPAÑETE maestrado TECHOS Y VIGAS:

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. esp. 0.02171 m3 4,710.27 102.262 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 154.28 5.143 Andamios (.25 planchas plywood / 10 usos) 0.0250 u 1,150.00 28.754 Conf. andamios 0.0703 día 900.00 63.275 Clavos corrientes 0.1590 lb 24.79 3.946 Mano de obra 1.00 m2 125.86 125.86

M2 $329.22*EMP 10130007 EMPAÑETE PULIDO SIN COLOR:

1 Mortero 1:4 p/empañete + 30% desp., 1.52 cm. esp. 0.01976 m3 4,710.27 93.072 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 154.28 5.143 Andamios (1.091 p2 / 6 usos) 0.1820 pt 29.00 5.284 Conf. andamios 0.0230 día 900.00 20.705 Cemento 2da. capa + 30% desp. 0.0530 fda 250.00 13.256 Mano de obra 1.00 m2 96.05 96.05

M2 $233.49*EMP 10130008 EMPAÑETE RASGADO:

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. esp. 0.02171 m3 4,710.27 102.262 Regla (2 de 1"x4"x10' / 100 usos) 0.0667 pt 154.28 10.293 andamios 1.4402 pt 29.00 41.774 Conf. andamios 0.0703 día 900.00 63.275 Clavos corrientes 0.1590 lb 24.79 3.946 Mano de obra 1.00 m2 111.36 111.36

M2 $332.89*EMP 10130009 EMPAÑETE RUSTICO (ESCOBA, PAPEL O BROCHA):

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. esp. 0.02171 m3 4,710.27 102.262 Andamios (1.091 p2 / 6 usos) 1.4402 pt 154.28 222.193 Conf. andamios 0.0703 día 900.00 63.274 Clavos corrientes 0.1590 lb 24.79 3.945 Mano de obra 1.00 m2 66.25 66.25

M2 $457.91*EMP 10130010 ESTRIAS:

1 Mortero 1:4 p/empañete + 30% desp., 1.67 cm. 0.00868 m3 4,710.27 40.892 Reglas (1 de 1"x1"x3.28'). 0.2700 pt 154.28 41.663 Mano de obra 1.00 m 71.88 71.88

M $154.43*EMP 10130011 FRAGÜACHE, SIN ANDAMIOS:

1 Mortero 1:4 p/empañete + 50% desp., 0.5 mm. esp. (Rend. 200 m2 / m3) 0.00750 m3 4,710.27 35.332 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 154.28 5.143 Mano de obra 1.00 m2 13.41 13.41

M2 $53.88*EMP 10130012 GOTEROS COLGANTES:

1 Mortero 1:4 p/empañete + 30% desp. 0.00954 m3 4,710.27 44.942 Reglas (2 de 1"x4"x3.28' / 10 usos) 0.2180 pt 154.28 33.633 Mano de obra 1.00 m 88.46 88.46

M $167.03*EMP 10130013 GOTEROS DE RANURA:

1 Mortero 1:4 p/empañete + 30% desp. 0.00477 m3 4,710.27 22.472 Reglas (1 de 1"x4"x3.28' / 10 usos) 0.1090 pt 154.28 16.823 Mano de obra 1.00 m 76.67 76.67

M $115.96*EMP 10130014 LECHADA CEMENTO BLANCO:

1 Cemento gris +20% desp. (50 m2 / funda) 0.02400 m3 600.00 14.402 Agua 0.11229 gl 0.35 0.04

M2 $14.44*EMP 10130015 LECHADA CEMENTO GRIS:

1 Cemento blanco +20% desp. (50 m2 / funda) 0.02400 m3 250.00 6.002 Agua 0.11229 gl 0.35 0.04

M2 $6.04*EMP 10130016 NATILLA, SIN ANDAMIOS:

1 Agua 0.06281 gl 0.35 44.232 Cemento gris (15 m2 / funda) 0.06667 m3 250.00 16.673 Mano de obra 1.00 m2 50.96 50.96

M2 $67.63*EMP 10130017 REPELLO maestrado TECHOS, 2 capas de 1.5 cm. c/u. (SIN ANDAMIOS):

1 Mortero 1:4 p/empañete + 30% desp., 2 capas (Rend. 33.33 m2/m3, 2 capas) 0.03900 m3 4,710.27 183.702 Regla (1 de 1"x4"x10' / 10 usos) 0.0333 pt 154.28 5.143 Mano de obra 1.00 m2 87.50 87.50

M2 $276.34*EMP 10130018 RESANE, SIN ANDAMIOS:

1 Mortero 1:4 p/empañete + 30% desp., 0.5 mm. Esp. (Rendim. 200 m2 / m3) 0.00650 m3 4,710.27 30.622 Regla (1 de 1"x4"x10' / 100 usos) 0.0333 pt 154.28 5.143 Mano de obra 1.00 m2 31.73 31.73

M2 $67.49

*ESC 10150000 ESCALONES

*ESC 10150001 ESCALON GRANITO 2 y 3 BLANCO1 Escalón .17 x .30 m. Bocel redondo + 10% desp. 1.10 m 928.00 1,020.802 Mortero de fijación + 10% desp. 0.0561 m3 3,932.52 220.61

Page 67: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 37

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

3 Colocación Huella y Contra Huella (No aplica) 1.00 m 165.634 Pulido y brillado 1.00 m 236.13 236.13

M $1,477.54*ESC 10150002 ESCALON MARMOL AGLOMERADO (PERLATTO ROYAL) 1.10 M.

1 Escalón .17x1.10 m. + .34x1.10 m., Bocel redondo + 10% desp. 1.10 u 1,044.00 1,148.402 Mortero de fijación + 10% desp. 0.0561 m3 3,932.52 220.613 Colocación Huella y Contra Huella 1.10 m 165.63 182.194 Pulido y brillado 1.10 m 236.13 259.74

U $1,810.94M 1,646.31

*ESC 10150003 ESCALON SUPER CHAPA BLANCO1 Escalón .17 x .30 m. Bocel redondo + 10% desp. 1.10 m 1,740.00 1,914.002 Mortero de fijación + 10% desp. 0.0561 m3 3,932.52 220.613 Colocación Huella y Contra Huella (No aplica) 1.00 m 165.634 Pulido y brillado 1.00 m 236.13 236.13

M $2,370.74*ESC 10150004 ZOCALO P/ESCALONES, GRANITO 2 y3 BLANCO:

1 Escalón + transporte + 10% desp. + itbis 1.10 u 186.48 205.132 Mortero 1:3 + 5% desp. 0.0063 m3 3,932.52 24.77

U $24.77

*HAANT 10170000 HORM. ARMADO ANTEPECHOS

*HAANT 10170001 ANTEPECHO .40x.15, 1:2:4, 3/8" grado 40 A .40 + 2 DE 3/8":1 Acero 3/8" x 20' grado 40 + 10% desp. 1.6338 qq 1,915.88 3,130.162 M.O. acero 1.6338 qq 213.92 349.503 Subida acero 1.6338 qq 21.39 34.954 Madera bruta amer. (4 usos) 183.06 pt 29.00 5,308.745 Clavos corrientes (5 lb. / 100 pie madera) 36.61 lb 24.79 907.566 Clavos de acero (¼ lb / metro) 8.34 lb 45.24 377.307 Alambre calibre #14 (¼ lb. / metro) 8.34 lb 25.44 212.178 Confección e instalación de madera 33.35 m 148.36 4,947.819 Desencofrado 26.68 m2 21.40 570.9510 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 3,761.45 4,137.60

M3 $19,976.74*HAANT 10170002 ANTEPECHO .40x.15, 180 kg/Cm², 3/8" grado 40 A .40, 2 DE 3/8":

1 Partidas comunes del análisis anterior (1-9) 1.00 m3 15,839.14 15,839.142 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $21,772.54*HAANT 10170003 ANTEPECHO .40x.15, 210 kg/Cm², 3/8" grado 40 A .40, 2 DE 3/8":

1 Partidas comunes del análisis anterior (1-9) 1.00 m3 15,839.14 15,839.142 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $22,027.74*HAANT 10170004 ANTEPECHO .40x.15, 240 kg/Cm², 3/8" grado 40 A .40, 2 DE 3/8":

1 Partidas comunes del análisis anterior (1-9) 1.00 m3 15,839.14 15,839.142 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $22,282.94

*HABAD 10190000 HORM. ARMADO BADENES (TIPO CUNETA) Notas:

*HABAD 10190001 BADEN SOBRE HORM CICLOPESO, ACERO GRADO 40: No toque las celdas que tengan color verde o las que aparecen en las columnas I en adelante.

Tipo acero y espac. 3/8 @ 0.20 a.d. Llene las dimensiones del baden: ancho "X", largo "Y" y por último el espesor "Z".

Dimens. badén: ancho, Y, Z 1.75 x 10.00 x 0.25 El lado corto no tiene considerado el solape del acero, ya que no es necesario.

Espesor horm. ciclópeo: 0.30 m Opciones para el hormigón: 1:3:5, 1:2:4, 140, 180, 210 y 240

Pendiente: 20.00% Esta hoja y las anteriores no están protegidas.

Desperdicio del acero: 5.00% Guarde este archivo en lugar seguro y trabaje en una copia.

Area del badén: 17.50 m2 Este documento solo se actualiza con este mismo archivo.

Vol. H.A. del Badén: 2.8438 m3 Para actualizar los precios, actualice solo la columna de p. unit. en los análisis.

1 Acero grado 40 + alambre dulce + 10% desp. (Ver análisis aceros) 0.8712 qq 1,915.88 1,669.112 M.O. acero. 0.8712 qq 213.92 186.373 Hormigón del badén + 2% desp. Tipo: 1:3:5 1.02 m3 3,572.06 3,643.504 Base del badén, horm. ciclópeo, 1:3:5 (15% del vol. total) + 10% desp. 0.30 m3 3,572.06 1,071.625 Base del badén, piedras grandes (85% del vol. total) + 10% desp. 1.73 m3 750.00 1,297.506 Base del badén (mano de obra colocar las piedras solamente). 1.73 m3 314.29 543.727 Mortero 1:2 para pulido, .005 m. de espesor. 0.0308 m3 6,371.00 196.238 M. O. pulido del piso 6.15 m2 96.05 590.71

M3 $9,198.76*HABAD 10190002 BADEN SOBRE HORM CICLOPESO, ACERO GRADO 40:

Tipo acero y espac. 3/8 @ 0.20 a.d.Dimens. badén: ancho, Y, Z 1.75 x 10.00 x 0.25Espesor horm. ciclópeo: 0.30 mPendiente: 20.00%Desperdicio del acero: 5.00%Area del badén: 17.50 m2Vol. H.A. del Badén: 2.8438 m3

1 Acero grado 40 + alambre dulce + 10% desp. (Ver análisis aceros) 0.8712 qq 1,915.88 1,669.112 M.O. acero. 0.8712 qq 213.92 186.373 Hormigón del badén + 2% desp. Tipo: 1:2:4 1.02 m3 3,963.92 4,043.204 Base del badén, horm. ciclópeo, 1:3:5 (15% del vol. total) + 10% desp. 0.30 m3 3,572.06 1,071.625 Base del badén, piedras grandes (85% del vol. total) + 10% desp. 1.73 m3 750.00 1,297.506 Base del badén (mano de obra colocar las piedras solamente). 1.73 m3 314.29 543.727 Mortero 1:2 para pulido, .005 m. de espesor. 0.0308 m3 6,371.00 196.238 M. O. pulido del piso 6.15 m2 96.05 590.71

M3 $9,598.46*HABAD 10190003 BADEN SOBRE HORM CICLOPESO, ACERO GRADO 40:

Tipo acero y espac. 3/8 @ 0.20 a.d.

Llene solo las letras en AZUL y cuyas celdas no estén sombreadas en verde.

Page 68: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 38

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

Dimens. badén: ancho, Y, Z 1.75 x 10.00 x 0.25Espesor horm. ciclópeo: 0.30 mPendiente: 20.00%Desperdicio del acero: 5.00%Area del badén: 17.50 m2Vol. H.A. del Badén: 2.8438 m3

1 Acero grado 40 + alambre dulce + 10% desp. (Ver análisis aceros) 0.8712 qq 1,915.88 1,669.112 M.O. acero. 0.8712 qq 213.92 186.373 Hormigón del badén + 2% desp. Tipo: 180 Kg/Cm2 1.02 m3 5,933.40 6,052.074 Base del badén, horm. ciclópeo, 1:3:5 (15% del vol. total) + 10% desp. 0.30 m3 3,572.06 1,071.625 Base del badén, piedras grandes (85% del vol. total) + 10% desp. 1.73 m3 750.00 1,297.506 Base del badén (mano de obra colocar las piedras solamente). 1.73 m3 314.29 543.727 Mortero 1:2 para pulido, .005 m. de espesor. 0.0308 m3 6,371.00 196.238 M. O. pulido del piso 6.15 m2 96.05 590.71

M3 $11,607.33*HABAD 10190004 BADEN SOBRE HORM CICLOPESO, ACERO GRADO 40:

Tipo acero y espac. 3/8 @ 0.20 a.d.Dimens. badén: ancho, Y, Z 1.75 x 10.00 x 0.25Espesor horm. ciclópeo: 0.30 mPendiente: 20.00%Desperdicio del acero: 5.00%Area del badén: 17.50 m2Vol. H.A. del Badén: 2.8438 m3

1 Acero grado 40 + alambre dulce + 10% desp. (Ver análisis aceros) 0.8712 qq 1,915.88 1,669.112 M.O. acero. 0.8712 qq 213.92 186.373 Hormigón del badén + 2% desp. Tipo: 210 Kg/Cm2 1.02 m3 6,188.60 6,312.374 Base del badén, horm. ciclópeo, 1:3:5 (15% del vol. total) + 10% desp. 0.30 m3 3,572.06 1,071.625 Base del badén, piedras grandes (85% del vol. total) + 10% desp. 1.73 m3 750.00 1,297.506 Base del badén (mano de obra colocar las piedras solamente). 1.73 m3 314.29 543.727 Mortero 1:2 para pulido, .005 m. de espesor. 0.0308 m3 6,371.00 196.238 M. O. pulido del piso 6.15 m2 96.05 590.71

M3 $11,867.63

*HACOL 10210000 HORM. ARMADO COLUMNAS

*HACOL 10210001 COL. 20x20, 1:2:4, 40,4 DE 3/8", ¼" A 20, LIG.:1 Acero ¼" + 10% desp. 0.804 qq 1,088.60 875.232 Acero 3/8" x 20' grado 40 + 10% desp. 1.462 qq 1,915.88 2,801.023 M.O. acero 25.00 m 71.30 1,782.504 Madera bruta amer. (4 usos) 254.77 pt 29.00 7,388.335 Clavos corrientes (5 lb. / 100 pie madera) 50.95 lb 24.79 1,263.056 Clavos de acero (¼ lb / metro) 6.25 lb 45.24 282.757 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 25.44 159.008 Confección madera 25.00 m 106.98 2,674.509 Instalación madera 25.00 m 122.68 3,067.0010 Desencofrado 20.00 m2 18.54 370.8011 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $24,593.74*HACOL 10210002 COL. 20x20, 1:2:4, 40, 4 DE 3/8", ¼" A 20 A MANO:

1 Partidas comunes de la analizada anteriormente (1-10) 1.000 m3 20,664.18 20,664.182 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $25,024.49*HACOL 10210003 COL. 20x20, 1:2:4, 40, 4 DE ½", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.778 qq 1,088.60 1,935.532 Acero ½" x 20' grado 40 + 10% desp. 2.598 qq 1,915.88 4,977.463 Partidas comunes de la analizada completa anterior (3-11) 1.000 m3 20,917.49 20,917.49

M3 $27,830.48*HACOL 10210004 COL. 20x20, 1:2:4, 40, 4 DE ½", 3/8" A 20 A MANO:

1 Partidas comunes de la analizada completa anterior (1-10) 1.000 m3 27,830.48 27,830.482 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $32,190.79*HACOL 10210005 COL. 20x30, 1:2:4, 40, 4 DE ½", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.506 qq 1,915.88 2,885.322 Acero ½" x 20' grado 40 + 10% desp. 1.732 qq 1,915.88 3,318.303 M.O. acero 13.13 m 71.30 936.174 Madera bruta amer. (4 usos) 130.36 pt 29.00 3,780.445 Clavos corrientes (5 lb. / 100 pie madera) 26.07 lb 24.79 646.286 Clavos de acero (¼ lb / metro) 3.28 lb 45.24 148.397 Alambre calibre #14 (¼ lb. / metro) 3.28 lb 25.44 83.448 Confección madera 13.13 m 106.98 1,404.659 Instalación madera 13.13 m 122.68 1,610.7910 Desencofrado 13.13 m2 18.54 243.4311 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $18,986.77*HACOL 10210006 COL. 20x30, 1:2:4, 40, 4 DE ½", 3/8" A 20 A MANO:

1 Partidas comunes de la analizada completa anterior (1-10) 1.000 m3 15,057.21 15,057.212 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $19,417.52*HACOL 10210007 COL. 30x30, 1:2:4, 40, 8 DE ½", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.144 qq 1,915.88 2,191.772 Acero ½" x 20' grado 40 + 10% desp. 2.278 qq 1,915.88 4,364.373 M.O. acero 3.422 qq 213.92 732.034 Madera bruta amer. (4 usos) 134.11 pt 29.00 3,889.195 Clavos corrientes (5 lb. / 100 pie madera) 26.82 lb 24.79 664.876 Clavos de acero (¼ lb / metro) 2.78 lb 45.24 125.777 Alambre calibre #14 (¼ lb. / metro) 2.78 lb 25.44 70.72

Page 69: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 39

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

8 Confección madera 11.11 m 106.98 1,188.559 Instalación madera 11.11 m 122.68 1,362.9710 Desencofrado 13.33 m2 18.54 247.1411 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $18,766.94*HACOL 10210008 COL. 30x30, 1:2:4, 40, 8 DE ½", 3/8" A 20 A MANO:

1 Partidas comunes de la analizada completa anterior (1-10) 1.000 m3 14,837.38 14,837.382 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $19,197.69*HACOL 10210009 COL. 30x40, 1:2:4, 40, 4 DE ¾", 3/8" A 30, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.744 qq 1,915.88 1,425.412 Acero ¾" grado 40 + 10% desp. 1.979 qq 1,915.88 3,791.533 M.O. acero 2.723 qq 213.92 582.504 Madera bruta amer. (4 usos) 76.99 pt 29.00 2,232.715 Clavos corrientes (5 lb. / 100 pie madera) 15.4 lb 24.79 381.776 Clavos de acero (¼ lb / metro) 2.08 lb 45.24 94.107 Alambre calibre #14 (¼ lb. / metro) 2.08 lb 25.44 52.928 Confección madera 8.33 m 122.68 1,021.929 Instalación madera 8.33 m 158.33 1,318.8910 Desencofrado 11.66 m2 18.54 216.1811 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $15,047.49*HACOL 10210010 COL. 30x40, 1:2:4, 40, 4 DE ¾", 3/8" A 30 A MANO:

1 Partidas comunes de la analizada completa anterior (1-10) 1.000 m3 11,117.93 11,117.932 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $15,478.24*HACOL 10210011 COL. 40x40, 1:2:4, 40, 4 DE ½" + 4 DE ¾", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 1,915.88 1,647.662 Acero ½" x 20' grado 40 + 10% desp. 0.640 qq 1,915.88 1,226.163 Acero ¾" grado 40 + 10% desp. 1.481 qq 1,915.88 2,837.424 M.O. acero 2.981 qq 213.92 637.705 Madera bruta amer. (4 usos) 87.25 pt 29.00 2,530.256 Clavos corrientes (5 lb. / 100 pie madera) 17.45 lb 24.79 432.597 Clavos de acero (¼ lb / metro) 1.56 lb 45.24 70.578 Alambre calibre #14 (¼ lb. / metro) 1.56 lb 25.44 39.699 Confección madera 6.25 m 122.68 766.7510 Instalación madera 6.25 m 158.33 989.5611 Desencofrado 10.00 m2 18.54 185.4012 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $15,293.31*HACOL 10210012 COL. 40x40, 1:2:4, 40, 4 DE ½" + 4 DE ¾", 3/8" A 20 A MANO:

1 Partidas comunes de la analizada completa anterior (1-11) 1.000 m3 9,716.09 9,716.092 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $14,076.40*HACOL 10210013 COL. 50x50, 1:2:4, 40, 4 DE ¾" + 4 DE 1", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.687 qq 1,915.88 1,316.212 Acero ¾" x 20' grado 40 + 10% desp. 0.948 qq 1,915.88 1,816.253 Acero 1" x 20' grado 40 + 10% desp. 1.733 qq 1,915.88 3,320.224 M.O. acero 3.368 qq 213.92 720.485 Madera bruta amer. (4 usos) 63.41 pt 29.00 1,838.896 Clavos corrientes (5 lb. / 100 pie madera) 12.68 lb 24.79 314.347 Clavos de acero (¼ lb / metro) 1.00 lb 45.24 45.248 Alambre calibre #14 (¼ lb. / metro) 1.00 lb 25.44 25.449 Confección madera 4.00 m 141.22 564.8810 Instalación madera 4.00 m 176.88 707.5211 Desencofrado 8.00 m2 18.54 148.3212 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $15,178.10*HACOL 10210014 COL. 50x50, 1:2:4, 40, 4 DE ¾" + 4 DE 1", 3/8" A 20 A MANO:

1 Partidas comunes de la analizada completa anterior (1-11) 1.000 m3 9,501.58 9,501.582 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $13,431.14*HACOL 10210015 COL. 60x60, 1:2:4, 40, 12 DE 1", 3/8" A 20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.718 qq 1,915.88 3,291.482 Acero 1" x 20' grado 40 + 10% desp. 3.612 qq 1,915.88 6,920.163 M.O. acero 5.330 qq 213.92 1,140.194 Madera bruta amer. (4 usos) 49.29 pt 29.00 1,429.415 Clavos corrientes (5 lb. / 100 pie madera) 9.86 lb 24.79 244.436 Clavos de acero (¼ lb / metro) 0.70 lb 45.24 31.677 Alambre calibre #14 (¼ lb. / metro) 0.70 lb 25.44 17.818 Confección madera 2.78 m 176.88 491.739 Instalación madera 2.78 m 281.02 781.2410 Desencofrado 6.67 m2 18.54 123.6611 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $18,832.09*HACOL 10210016 COL. 60x60, 1:2:4, 40, 12 DE 1", 3/8" A 20 A MANO:

1 Partidas comunes de la analizada completa anterior (1-11) 1.000 m3 14,471.78 14,471.782 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $18,401.34*HACOL 10210017 COL. 20x20, 180 kg/Cm², 40, 4 DE ½", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.778 qq 1,915.88 3,406.432 Acero ½" x 20' grado 40 + 10% desp. 2.598 qq 1,915.88 4,977.463 M.O. acero 25.00 m 71.30 1,782.504 Madera bruta amer. (4 usos) 177.79 pt 29.00 5,155.915 Clavos corrientes (5 lb. / 100 pie madera) 35.56 lb 24.79 881.536 Clavos de acero (¼ lb / metro) 6.25 lb 45.24 282.757 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 25.44 159.008 Confección madera 25.00 m 106.98 2,674.50

Page 70: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 40

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

9 Instalación madera 25.00 m 122.68 3,067.0010 Desencofrado 20.00 m2 18.54 370.8011 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 5,933.40 5,933.40

M3 $28,691.28*HACOL 10210018 COL. 20x20, 180 kg/Cm², 40, 4 DE ½" x 25', 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.778 qq 1,915.88 3,406.432 Acero ½" x 25' grado 40 + 10% desp. 2.598 qq 1,915.88 4,977.463 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 20,307.39 20,307.39

M3 $28,691.28*HACOL 10210019 COL. 20x20, 180 kg/Cm², 60, 4 DE ½" x 20', 3/8" x 20' A 20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.778 qq 2,021.08 3,593.482 Acero ½" x 20' grado 60 + 10% desp. 2.598 qq 2,021.08 5,250.773 Partidas comunes de la analizada completa anterior (3-11) 1.00 m3 20,307.39 20,307.39

M3 $29,151.64*HACOL 10210020 COL. 20x20, 180 kg/Cm², 60, 4 DE ½" x 25', 3/8" x 20' A 20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.778 qq 2,021.08 3,593.482 Acero ½" x 25' grado 60 + 10% desp. 2.598 qq 2,021.08 5,250.773 Partidas comunes de la analizada completa anterior (3-11) 1.00 m3 20,307.39 20,307.39

M3 $29,151.64*HACOL 10210021 COL. 20x30, 180 kg/Cm², 60, 4 DE ½", 3/8" A 20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.506 qq 2,021.08 3,043.752 Acero ½" x 20' grado 60 + 10% desp. 1.732 qq 2,021.08 3,500.513 M.O. acero 13.13 m 71.30 936.174 Madera bruta amer. (4 usos) 130.36 pt 29.00 3,780.445 Clavos corrientes (5 lb. / 100 pie madera) 26.07 lb 24.79 646.286 Clavos de acero (¼ lb / metro) 3.28 lb 45.24 148.397 Alambre calibre #14 (¼ lb. / metro) 3.28 lb 25.44 83.448 Confección madera 13.13 m 106.98 1,404.659 Instalación madera 13.13 m 122.68 1,610.7910 Desencofrado 13.13 m2 18.54 243.4311 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 5,933.40 5,933.40

M3 $21,331.25*HACOL 10210022 COL. 20x30, 180 kg/Cm², 60, 4 DE ½" x 25', 3/8" x 20' A 20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.506 qq 2,021.08 3,043.752 Acero ½" x 25' grado 60 + 10% desp. 1.732 qq 2,021.08 3,500.513 Partidas comunes de la analizada completa anterior (3-11) 1.00 m3 14,786.99 14,786.99

M3 $21,331.25*HACOL 10210023 COL. 30x30, 180 kg/Cm², 40, 8 DE ½", 3/8" A 30:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.144 qq 1,915.88 2,191.772 Acero ½" x 20' grado 40 + 10% desp. 2.278 qq 1,915.88 4,364.373 M.O. acero 3.422 qq 213.92 732.034 Madera bruta amer. (4 usos) 134.11 pt 29.00 3,889.195 Clavos corrientes (5 lb. / 100 pie madera) 26.82 lb 24.79 664.876 Clavos de acero (¼ lb / metro) 2.78 lb 45.24 125.777 Alambre calibre #14 (¼ lb. / metro) 2.78 lb 25.44 70.728 Confección madera 11.11 m 106.98 1,188.559 Instalación madera 11.11 m 122.68 1,362.9710 Desencofrado 13.33 m2 18.54 247.1411 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 5,933.40 5,933.40

M3 $20,770.78*HACOL 10210024 COL. 30x30, 180 kg/Cm², 40, 8 DE ½", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 6,556.14 6,556.142 M.O. acero 3.422 qq 341.37 1,168.173 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,482.61 13,482.61

M3 $21,206.92*HACOL 10210025 COL. 30x30, 180 kg/Cm², 40, 8 DE ½" x 25', 3/8" A:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.144 qq 1,915.88 2,191.772 Acero ½" x 25' grado 40 + 10% desp. 2.278 qq 1,915.88 4,364.373 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 14,214.64 14,214.64

M3 $20,770.78*HACOL 10210026 COL. 30x30, 180 kg/Cm², 40, 8 DE ½"x25', 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 6,556.14 6,556.142 M.O. acero 3.422 qq 341.37 1,168.173 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,482.61 13,482.61

M3 $21,206.92*HACOL 10210027 COL. 30x30, 180 kg/Cm², 60, 8 DE ½", 3/8" A 30:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.144 qq 2,021.08 2,312.122 Acero ½" x 20' grado 60 + 10% desp. 2.278 qq 2,021.08 4,604.023 M.O. acero 3.422 qq 323.23 1,106.094 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,482.61 13,482.61

M3 $21,504.84*HACOL 10210028 COL. 30x30, 180 kg/Cm², 60, 8 DE ½", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 6,916.14 6,916.142 M.O. acero 3.422 qq 341.37 1,168.173 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,482.61 13,482.61

M3 $21,566.92*HACOL 10210029 COL. 30x30, 180 kg/Cm², 60, 8 DE ½"x25', 3/8" x 20' A 30:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.144 qq 2,021.08 2,312.122 Acero ½" x 25' grado 60 + 10% desp. 2.278 qq 2,021.08 4,604.023 M.O. acero 3.422 qq 323.23 1,106.093 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,482.61 13,482.61

M3 $21,504.84*HACOL 10210030 COL. 30x30, 180 kg/Cm², 60, 8 DE ½"x25', 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 6,916.14 6,916.142 M.O. acero 3.422 qq 341.37 1,168.173 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,482.61 13,482.61

M3 $21,566.92*HACOL 10210031 COL. 30x40, 180 kg/Cm², 40, 4 DE ¾", 3/8" A 30:

Page 71: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 41

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.744 qq 1,915.88 1,425.412 Acero ¾" grado 40 + 10% desp. 1.979 qq 1,915.88 3,791.533 M.O. acero 2.723 qq 213.92 582.504 Madera bruta amer. (4 usos) 76.990 pt 29.00 2,232.715 Clavos corrientes (5 lb. / 100 pie madera) 15.4 lb 24.79 381.776 Clavos de acero (¼ lb / metro) 2.08 lb 45.24 94.107 Alambre calibre #14 (¼ lb. / metro) 2.08 lb 25.44 52.928 Confección madera 8.33 m 122.68 1,021.929 Instalación madera 8.33 m 158.33 1,318.8910 Desencofrado 11.66 m2 18.54 216.1811 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 5,933.40 5,933.40

M3 $17,051.33*HACOL 10210032 COL. 30x40, 180 kg/Cm², 40, 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 5,216.94 5,216.942 M.O. acero 2.723 qq 341.37 929.553 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,251.89 11,251.89

M3 $17,398.38*HACOL 10210033 COL. 30x40, 180 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.744 qq 2,021.08 1,503.682 Acero ¾" x 20' grado 60 + 10% desp. 1.979 qq 2,021.08 3,999.723 M.O. acero 2.723 qq 323.23 880.164 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,251.89 11,251.89

M3 $17,635.45*HACOL 10210034 COL. 30x40, 180 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 5,503.40 5,503.402 M.O. acero 2.723 qq 341.37 929.553 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,251.89 11,251.89

M3 $17,684.84*HACOL 10210035 COL. 40x40, 180 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 1,915.88 1,647.662 Acero ½" x 20' grado 40 + 10% desp. 0.640 qq 1,915.88 1,226.163 Acero ¾" + 10% desp. 1.481 qq 1,915.88 2,837.424 M.O. acero 2.981 qq 213.92 637.705 Madera bruta amer. (4 usos) 87.25 pt 29.00 2,530.256 Clavos corrientes (5 lb. / 100 pie madera) 17.45 lb 24.79 432.597 Clavos de acero (¼ lb / metro) 1.56 lb 45.24 70.578 Alambre calibre #14 (¼ lb. / metro) 1.56 lb 25.44 39.699 Confección madera 6.25 m 122.68 766.7510 Instalación madera 6.25 m 158.33 989.5611 Desencofrado 10.00 m2 18.54 185.4012 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 5,933.40 5,933.40

M3 $17,297.15*HACOL 10210036 COL. 40x40, 180 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,711.24 5,711.242 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,948.21 10,948.21

M3 $17,677.07*HACOL 10210037 COL. 40x40, 180 kg/Cm², 40, 4 DE ½"x25' + 4 DE ¾"x25', 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 1,915.88 1,647.662 Acero ½" x 25' grado 40 + 10% desp. 0.640 qq 1,915.88 1,226.163 Acero ¾" + 10% desp. 1.481 qq 1,915.88 2,837.424 Partidas comunes de la analizada completa anterior (4-12) 1.00 u 11,585.91 11,585.91

M3 $17,297.15*HACOL 10210038 COL. 40x40, 180 kg/Cm², 40, 4 DE ½"x25' + 4 DE ¾"x25', 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,711.24 5,711.242 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,948.21 10,948.21

M3 $17,677.07*HACOL 10210039 COL. 40x40, 180 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,021.08 1,738.132 Acero ½" x 20' grado 60 + 10% desp. 0.640 qq 2,021.08 1,293.493 Acero ¾" + 10% desp. 1.481 qq 2,021.08 2,993.224 M.O. acero 2.981 qq 323.23 963.555 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 10,948.21 10,948.21

M3 $17,936.60*HACOL 10210040 COL. 40x40, 180 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,024.84 6,024.842 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,948.21 10,948.21

M3 $17,990.67*HACOL 10210041 COL. 40x40, 180 kg/Cm², 60, 4 DE ½"x25' + 4 DE ¾"x25', 3/8" A 30:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,021.08 1,738.132 Acero ½" x 25' grado 60 + 10% desp. 0.640 qq 2,021.08 1,293.493 Acero ¾" grado 60 + 10% desp. 1.481 qq 2,021.08 2,993.224 M.O. acero 2.981 qq 323.23 963.555 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,948.21 10,948.21

M3 $17,936.60*HACOL 10210042 COL. 40x40, 180 kg/Cm², 60, 4 DE ½" x 25' + 4 DE 4/4", 3/8" x 20' A 30: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,024.84 6,024.842 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,948.21 10,948.21

M3 $17,990.67*HACOL 10210043 COL. 50x50, 180 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.687 qq 1,915.88 1,316.212 Acero ¾" + 10% desp. 0.948 qq 1,915.88 1,816.253 Acero 1" + 10% desp. 1.733 qq 1,915.88 3,320.224 M.O. acero 3.368 qq 213.92 720.485 Madera bruta amer. (4 usos) 63.41 pt 29.00 1,838.89

Page 72: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 42

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

6 Clavos corrientes (5 lb. / 100 pie madera) 12.68 lb 24.79 314.347 Clavos de acero (¼ lb / metro) 1.00 lb 45.24 45.248 Alambre calibre #14 (¼ lb. / metro) 1.00 lb 25.44 25.449 Confección madera 4.00 m 141.22 564.8810 Instalación madera 4.00 m 176.88 707.5211 Desencofrado 8.00 m2 18.54 148.3212 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 5,933.40 5,933.40

M3 $16,751.19*HACOL 10210044 COL. 50x50, 180 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,136.47 5,136.472 M.O. acero 3.368 qq 341.37 1,149.733 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,578.03 9,578.03

M3 $15,864.23*HACOL 10210045 COL. 50x50, 180 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.687 qq 2,021.08 1,388.482 Acero ¾" x 20' grado 60 + 10% desp. 0.948 qq 2,021.08 1,915.983 Acero 1" + 10% desp. 1.733 qq 2,021.08 3,502.534 M.O. acero 3.368 qq 323.23 1,088.645 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,578.03 9,578.03

M3 $17,473.66*HACOL 10210046 COL. 50x50, 180 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,806.99 6,806.992 M.O. acero 3.368 qq 341.37 1,149.733 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,578.03 9,578.03

M3 $17,534.75*HACOL 10210047 COL. 60x60, 180 kg/Cm², 40, 12 DE 1", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.718 qq 1,915.88 3,291.482 Acero 1" x 20' grado 40 + 10% desp. 3.612 qq 1,915.88 6,920.163 M.O. acero 5.330 qq 213.92 1,140.194 Madera bruta amer. (4 usos) 49.29 pt 29.00 1,429.415 Clavos corrientes (5 lb. / 100 pie madera) 9.86 lb 24.79 244.436 Clavos de acero (¼ lb / metro) 1.00 lb 45.24 45.247 Alambre calibre #14 (¼ lb. / metro) 1.00 lb 25.44 25.448 Confección madera 4.00 m 141.22 564.889 Instalación madera 4.00 m 176.88 707.5210 Desencofrado 8.00 m2 18.54 148.3211 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 5,933.40 5,933.40

M3 $20,450.47*HACOL 10210048 COL. 60x60, 180 kg/Cm², 40, 12 DE 1", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 10,211.64 10,211.642 M.O. acero 5.330 qq 341.37 1,819.503 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 9,098.64 9,098.64

M3 $21,129.78*HACOL 10210049 COL. 60x60, 180 kg/Cm², 60, 12 DE 1", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.718 qq 2,021.08 3,472.222 Acero 1" x 20' grado 60 + 10% desp. 3.612 qq 2,021.08 7,300.143 M.O. acero 5.330 qq 323.23 1,722.824 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 9,098.64 9,098.64

M3 $21,593.82*HACOL 10210050 COL. 60x60, 180 kg/Cm², 60, 12 DE 1", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 10,772.36 10,772.362 M.O. acero 5.330 qq 341.37 1,819.503 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 9,098.64 9,098.64

M3 $21,690.50*HACOL 10210051 COL. 30x30, 210 kg/Cm², 40, 4 DE ¾", 3/8" A 30:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.144 qq 1,915.88 2,191.772 Acero ¾" x 20' grado 40 + 10% desp. 2.278 qq 1,915.88 4,364.373 M.O. acero 3.422 qq 213.92 732.034 Madera bruta amer. (4 usos) 134.11 pt 29.00 3,889.195 Clavos corrientes (5 lb. / 100 pie madera) 26.82 lb 24.79 664.876 Clavos de acero (¼ lb / metro) 2.78 lb 45.24 125.777 Alambre calibre #14 (¼ lb. / metro) 2.78 lb 25.44 70.728 Confección madera 11.11 m 106.98 1,188.559 Instalación madera 11.11 m 122.68 1,362.9710 Desencofrado 13.33 m2 18.54 247.1411 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 6,188.60 6,188.60

M3 $21,025.98*HACOL 10210052 COL. 30x30, 210 kg/Cm², 40, 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 6,556.14 6,556.142 M.O. acero 3.422 qq 341.37 1,168.173 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,737.81 13,737.81

M3 $21,462.12*HACOL 10210053 COL. 30x30, 210 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.144 qq 2,021.08 2,312.122 Acero ¾" x 20' grado 60 + 10% desp. 2.278 qq 2,021.08 4,604.023 M.O. acero 3.422 qq 323.23 1,106.094 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,737.81 13,737.81

M3 $21,760.04*HACOL 10210054 COL. 30x30, 210 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 6,916.14 6,916.142 M.O. acero 3.422 qq 341.37 1,168.173 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,737.81 13,737.81

M3 $21,822.12*HACOL 10210055 COL. 30x40, 210 kg/Cm², 40, 4 DE ¾", 3/8" A 30:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.744 qq 1,915.88 1,425.412 Acero ¾" x 20' grado 40 + 10% desp. 1.979 qq 1,915.88 3,791.533 M.O. acero 2.723 qq 213.92 582.504 Madera bruta amer. (4 usos) 76.99 pt 29.00 2,232.71

Page 73: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 43

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

5 Clavos corrientes (5 lb. / 100 pie madera) 15.4 lb 24.79 381.776 Clavos de acero (¼ lb / metro) 2.08 lb 45.24 94.107 Alambre calibre #14 (¼ lb. / metro) 2.08 lb 25.44 52.928 Confección madera 8.33 m 122.68 1,021.929 Instalación madera 8.33 m 158.33 1,318.8910 Desencofrado 11.66 m2 18.54 216.1811 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 6,188.60 6,188.60

M3 $17,306.53*HACOL 10210056 COL. 30x40, 210 kg/Cm², 40, 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 5,216.94 5,216.942 M.O. acero 2.723 qq 341.37 929.553 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,507.09 11,507.09

M3 $17,653.58*HACOL 10210057 COL. 30x40, 210 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.744 qq 2,021.08 1,503.682 Acero ¾" x 20' grado 60 + 10% desp. 1.979 qq 2,021.08 3,999.723 M.O. acero 2.723 qq 323.23 880.164 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,507.09 11,507.09

M3 $17,890.65*HACOL 10210058 COL. 30x40, 210 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 5,503.40 5,503.402 M.O. acero 2.723 qq 341.37 929.553 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,507.09 11,507.09

M3 $17,940.04*HACOL 10210059 COL. 40x40, 210 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 1,915.88 1,647.662 Acero ½" x 20' grado 40 + 10% desp. 0.640 qq 1,915.88 1,226.163 Acero ¾" x 20' grado 40 + 10% desp. 1.481 qq 1,915.88 2,837.424 M.O. acero 2.981 qq 213.92 637.705 Madera bruta amer. (4 usos) 87.25 pt 29.00 2,530.256 Clavos corrientes (5 lb. / 100 pie madera) 17.45 lb 24.79 432.597 Clavos de acero (¼ lb / metro) 1.56 lb 45.24 70.578 Alambre calibre #14 (¼ lb. / metro) 1.56 lb 25.44 39.699 Confección madera 6.25 m 122.68 766.7510 Instalación madera 6.25 m 158.33 989.5611 Desencofrado 10.00 m2 18.54 185.4012 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 6,188.60 6,188.60

M3 $17,552.35*HACOL 10210060 COL. 40x40, 210 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,711.24 5,711.242 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,203.41 11,203.41

M3 $17,932.27

Page 74: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 44

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HACOL 10210061 COL. 40x40, 210 kg/Cm², 40, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 20:1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 1,915.88 1,647.662 Acero ½" x 25' grado 40 + 10% desp. 0.640 qq 1,915.88 1,226.163 Acero ¾" + 10% desp. 1.481 qq 1,915.88 2,837.424 Partidas comunes de la analizada completa anterior (4-12) 1.00 u 11,841.11 11,841.11

M3 $17,552.35*HACOL 10210062 COL. 40x40, 210 kg/Cm², 40, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,711.24 5,711.242 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,203.41 11,203.41

M3 $17,932.27*HACOL 10210063 COL. 40x40, 210 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,021.08 1,738.132 Acero ½" x 20' grado 60 + 10% desp. 0.640 qq 2,021.08 1,293.493 Acero ¾" + 10% desp. 1.481 qq 2,021.08 2,993.224 M.O. acero 2.981 qq 323.23 963.555 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,203.41 11,203.41

M3 $18,191.80*HACOL 10210064 COL. 40x40, 210 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,024.84 6,024.842 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,203.41 11,203.41

M3 $18,245.87*HACOL 10210065 COL. 40x40, 210 kg/Cm², 60, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 30 x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,021.08 1,738.132 Acero ½" x 25' grado 60 + 10% desp. 0.640 qq 2,021.08 1,293.493 Acero ¾" grado 60 + 10% desp. 1.481 qq 2,021.08 2,993.224 M.O. acero 2.981 qq 323.23 963.555 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,203.41 11,203.41

M3 $18,191.80*HACOL 10210066 COL. 40x40, 210 kg/Cm², 60, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 30 x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,024.84 6,024.842 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,203.41 11,203.41

M3 $18,245.87*HACOL 10210067 COL. 50x50, 210 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.687 qq 1,915.88 1,316.212 Acero ¾" x 20' grado 40 + 10% desp. 0.948 qq 1,915.88 1,816.253 Acero 1" x 20' grado 40 + 10% desp. 1.733 qq 1,915.88 3,320.224 M.O. acero 3.368 qq 213.92 720.485 Madera bruta amer. (4 usos) 63.41 pt 29.00 1,838.896 Clavos corrientes (5 lb. / 100 pie madera) 12.68 lb 24.79 314.347 Clavos de acero (¼ lb / metro) 1.00 lb 45.24 45.248 Alambre calibre #14 (¼ lb. / metro) 1.00 lb 25.44 25.449 Confección madera 4.00 m 141.22 564.8810 Instalación madera 4.00 m 176.88 707.5211 Desencofrado 8.00 m2 18.54 148.3212 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 6,188.60 6,188.60

M3 $17,006.39*HACOL 10210068 COL. 50x50, 210 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,136.47 5,136.472 M.O. acero 3.368 qq 341.37 1,149.733 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,833.23 9,833.23

M3 $16,119.43*HACOL 10210069 COL. 50x50, 210 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.687 qq 2,021.08 1,388.482 Acero ¾" x 20' grado 60 + 10% desp. 0.948 qq 2,021.08 1,915.983 Acero 1" + 10% desp. 1.733 qq 2,021.08 3,502.534 M.O. acero 3.368 qq 323.23 1,088.645 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,833.23 9,833.23

M3 $17,728.86*HACOL 10210070 COL. 50x50, 210 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,806.99 6,806.992 M.O. acero 3.368 qq 341.37 1,149.733 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,833.23 9,833.23

M3 $17,789.95*HACOL 10210071 COL. 60x60, 210 kg/Cm², 40, 12 DE 1", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.718 qq 1,915.88 3,291.482 Acero 1" x 20' grado 40 + 10% desp. 3.612 qq 1,915.88 6,920.163 M.O. acero 5.330 qq 213.92 1,140.194 Madera bruta amer. (4 usos) 49.29 pt 29.00 1,429.415 Clavos corrientes (5 lb. / 100 pie madera) 9.86 lb 24.79 244.436 Clavos de acero (¼ lb / metro) 0.70 lb 45.24 31.677 Alambre calibre #14 (¼ lb. / metro) 0.70 lb 25.44 17.818 Confección madera 2.78 m 176.88 491.739 Instalación madera 2.78 m 281.02 781.2410 Desencofrado 6.67 m2 18.54 123.6611 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 6,188.60 6,188.60

M3 $20,660.38*HACOL 10210072 COL. 60x60, 210 kg/Cm², 40, 12 DE 1", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 10,211.64 10,211.642 M.O. acero 5.330 qq 341.37 1,819.503 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 9,308.55 9,308.55

M3 $21,339.69*HACOL 10210073 COL. 60x60, 210 kg/Cm², 60, 12 DE 1", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.718 qq 2,021.08 3,472.222 Acero 1" x 20' grado 60 + 10% desp. 3.612 qq 2,021.08 7,300.143 M.O. acero 5.330 qq 323.23 1,722.82

Page 75: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 45

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

4 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 9,308.55 9,308.55M3 $21,803.73

*HACOL 10210074 COL. 60x60, 210 kg/Cm², 60, 12 DE 1", 3/8" A 30, x 20': PORTICO1 Partidas comunes del análisis anterior (1-2) 1.00 u 10,772.36 10,772.362 M.O. acero 5.330 qq 341.37 1,819.503 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 9,308.55 9,308.55

M3 $21,900.41*HACOL 10210075 COL. 30x30, 240 kg/Cm², 40, 4 DE ¾", 3/8" A 30:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.144 qq 1,915.88 2,191.772 Acero ¾" x 20' grado 40 + 10% desp. 2.278 qq 1,915.88 4,364.373 M.O. acero 3.422 qq 213.92 732.034 Madera bruta amer. (4 usos) 134.11 pt 29.00 3,889.195 Clavos corrientes (5 lb. / 100 pie madera) 26.82 lb 24.79 664.876 Clavos de acero (¼ lb / metro) 2.78 lb 45.24 125.777 Alambre calibre #14 (¼ lb. / metro) 2.78 lb 25.44 70.728 Confección madera 11.11 m 106.98 1,188.559 Instalación madera 11.11 m 122.68 1,362.9710 Desencofrado 13.33 m2 18.54 247.1411 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 6,443.80 6,443.80

M3 $21,281.18*HACOL 10210076 COL. 30x30, 240 kg/Cm², 40, 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 6,556.14 6,556.142 M.O. acero 3.422 qq 341.37 1,168.173 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,993.01 13,993.01

M3 $21,717.32*HACOL 10210077 COL. 30x30, 240 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.144 qq 2,021.08 2,312.122 Acero ¾" x 20' grado 60 + 10% desp. 2.278 qq 2,021.08 4,604.023 M.O. acero 3.422 qq 323.23 1,106.094 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,993.01 13,993.01

M3 $22,015.24*HACOL 10210078 COL. 30x30, 240 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 6,916.14 6,916.142 M.O. acero 3.422 qq 341.37 1,168.173 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 13,993.01 13,993.01

M3 $22,077.32*HACOL 10210079 COL. 30x40, 240 kg/Cm², 40, 4 DE ¾", 3/8" A 30:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.744 qq 1,915.88 1,425.412 Acero ¾" x 20' grado 40 + 10% desp. 1.979 qq 1,915.88 3,791.533 M.O. acero 2.723 qq 213.92 582.504 Madera bruta amer. (4 usos) 76.99 pt 29.00 2,232.715 Clavos corrientes (5 lb. / 100 pie madera) 15.4 lb 24.79 381.776 Clavos de acero (¼ lb / metro) 2.08 lb 45.24 94.107 Alambre calibre #14 (¼ lb. / metro) 2.08 lb 25.44 52.928 Confección madera 8.33 m 122.68 1,021.929 Instalación madera 8.33 m 158.33 1,318.8910 Desencofrado 11.66 m2 18.54 216.1811 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 6,443.80 6,443.80

M3 $17,561.73*HACOL 10210080 COL. 30x40, 240 kg/Cm², 40, 4 DE ¾", 3/8" A 30: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 5,216.94 5,216.942 M.O. acero 2.723 qq 341.37 929.553 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,762.29 11,762.29

M3 $17,908.78*HACOL 10210081 COL. 30x40, 240 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.744 qq 2,021.08 1,503.682 Acero ¾" x 20' grado 60 + 10% desp. 1.979 qq 2,021.08 3,999.723 M.O. acero 2.723 qq 323.23 880.164 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,762.29 11,762.29

M3 $18,145.85*HACOL 10210082 COL. 30x40, 240 kg/Cm², 60, 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 5,503.40 5,503.402 M.O. acero 2.723 qq 341.37 929.553 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,762.29 11,762.29

M3 $18,195.24*HACOL 10210083 COL. 40x40, 240 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 1,915.88 1,647.662 Acero ½" x 20' grado 40 + 10% desp. 0.640 qq 1,915.88 1,226.163 Acero ¾" x 20' grado 40 + 10% desp. 1.481 qq 1,915.88 2,837.424 M.O. acero 2.981 qq 213.92 637.705 Madera bruta amer. (4 usos) 87.25 pt 29.00 2,530.256 Clavos corrientes (5 lb. / 100 pie madera) 17.45 lb 24.79 432.597 Clavos de acero (¼ lb / metro) 1.56 lb 45.24 70.578 Alambre calibre #14 (¼ lb. / metro) 1.56 lb 25.44 39.699 Confección madera 6.25 m 122.68 766.7510 Instalación madera 6.25 m 158.33 989.5611 Desencofrado 10.00 m2 18.54 185.4012 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 6,443.80 6,443.80

M3 $17,807.55*HACOL 10210084 COL. 40x40, 240 kg/Cm², 40, 4 DE ½" + 4 DE ¾", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,711.24 5,711.242 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,458.61 11,458.61

M3 $18,187.47*HACOL 10210085 COL. 40x40, 240 kg/Cm², 40, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.860 qq 1,915.88 1,647.662 Acero ½" x 25' grado 40 + 10% desp. 0.640 qq 1,915.88 1,226.163 Acero ¾" + 10% desp. 1.481 qq 1,915.88 2,837.42

Page 76: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 46

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

4 Partidas comunes de la analizada completa anterior (4-12) 1.00 u 12,096.31 12,096.31M3 $17,807.55

*HACOL 10210086 COL. 40x40, 240 kg/Cm², 40, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 20: PORTICO1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,711.24 5,711.242 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,458.61 11,458.61

M3 $18,187.47

Page 77: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 47

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HACOL 10210087 COL. 40x40, 240 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30, x 20':1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,021.08 1,738.132 Acero ½" x 20' grado 60 + 10% desp. 0.640 qq 2,021.08 1,293.493 Acero ¾" + 10% desp. 1.481 qq 2,021.08 2,993.224 M.O. acero 2.981 qq 323.23 963.555 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 11,458.61 11,458.61

M3 $18,447.00*HACOL 10210088 COL. 40x40, 240 kg/Cm², 60, 4 DE ½" + 4 DE ¾", 3/8" A 30, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,024.84 6,024.842 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,458.61 11,458.61

M3 $18,501.07*HACOL 10210089 COL. 40x40, 240 kg/Cm², 60, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 30 x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.860 qq 2,021.08 1,738.132 Acero ½" x 25' grado 60 + 10% desp. 0.640 qq 2,021.08 1,293.493 Acero ¾" grado 60 + 10% desp. 1.481 qq 2,021.08 2,993.223 M.O. acero 2.981 qq 323.23 963.553 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,458.61 11,458.61

M3 $18,447.00*HACOL 10210090 COL. 40x40, 240 kg/Cm², 60, 4 DE ½" x 25' + 4 DE ¾", 3/8" A 30 x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,024.84 6,024.842 M.O. acero 2.981 qq 341.37 1,017.623 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,458.61 11,458.61

M3 $18,501.07*HACOL 10210091 COL. 50x50, 240 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.687 qq 1,915.88 1,316.212 Acero ¾" x 20' grado 40 + 10% desp. 0.948 qq 1,915.88 1,816.253 Acero 1" x 20' grado 40 + 10% desp. 1.733 qq 1,915.88 3,320.224 M.O. acero 3.368 qq 213.92 720.485 Madera bruta amer. (4 usos) 63.41 pt 29.00 1,838.896 Clavos corrientes (5 lb. / 100 pie madera) 12.68 lb 24.79 314.347 Clavos de acero (¼ lb / metro) 1.00 lb 45.24 45.248 Alambre calibre #14 (¼ lb. / metro) 1.00 lb 25.44 25.449 Confección madera 4.00 m 141.22 564.8810 Instalación madera 4.00 m 176.88 707.5211 Desencofrado 8.00 m2 18.54 148.3212 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 6,443.80 6,443.80

M3 $17,261.59*HACOL 10210092 COL. 50x50, 240 kg/Cm², 40, 4 DE ¾" + 4 DE 1", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 5,136.47 5,136.472 M.O. acero 3.368 qq 341.37 1,149.733 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,088.43 10,088.43

M3 $16,374.63*HACOL 10210093 COL. 50x50, 240 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.687 qq 2,021.08 1,388.482 Acero ¾" x 20' grado 60 + 10% desp. 0.948 qq 2,021.08 1,915.983 Acero 1" + 10% desp. 1.733 qq 2,021.08 3,502.534 M.O. acero 3.368 qq 323.23 1,088.645 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,088.43 10,088.43

M3 $17,984.06*HACOL 10210094 COL. 50x50, 240 kg/Cm², 60, 4 DE ¾" + 4 DE 1", 3/8" A 20, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-3) 1.00 u 6,806.99 6,806.992 M.O. acero 3.368 qq 341.37 1,149.733 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,088.43 10,088.43

M3 $18,045.15*HACOL 10210095 COL. 60x60, 240 kg/Cm², 40, 12 DE 1", 3/8" A 20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.718 qq 1,915.88 3,291.482 Acero 1" x 20' grado 40 + 10% desp. 3.612 qq 1,915.88 6,920.163 M.O. acero 5.330 qq 213.92 1,140.194 Madera bruta amer. (4 usos) 49.29 pt 29.00 1,429.415 Clavos corrientes (5 lb. / 100 pie madera) 9.86 lb 24.79 244.436 Clavos de acero (¼ lb / metro) 0.70 lb 45.24 31.677 Alambre calibre #14 (¼ lb. / metro) 0.70 lb 25.44 17.818 Confección madera 2.78 m 176.88 491.739 Instalación madera 2.78 m 281.02 781.2410 Desencofrado 6.67 m2 18.54 123.6611 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 6,443.80 6,443.80

M3 $20,915.58*HACOL 10210096 COL. 60x60, 240 kg/Cm², 40, 12 DE 1", 3/8" A 20: PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 10,211.64 10,211.642 M.O. acero 5.330 qq 341.37 1,819.503 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 9,563.75 9,563.75

M3 $21,594.89*HACOL 10210097 COL. 60x60, 240 kg/Cm², 60, 12 DE 1", 3/8" A 20, x 20':

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.718 qq 2,021.08 3,472.222 Acero 1" x 20' grado 60 + 10% desp. 3.612 qq 2,021.08 7,300.143 M.O. acero 5.330 qq 323.23 1,722.824 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 9,563.75 9,563.75

M3 $22,058.93*HACOL 10210098 COL. 60x60, 240 kg/Cm², 60, 12 DE 1", 3/8" A 20, x 20': PORTICO

1 Partidas comunes del análisis anterior (1-2) 1.00 u 10,772.36 10,772.362 M.O. acero 5.330 qq 341.37 1,819.503 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 9,563.75 9,563.75

M3 $22,155.61

*HACOLC 10230000 HORM. ARMADO COL. CIRCULARES

*HACOLC 10230001 COL. CIRCULAR, 1:2:4, 6 DE 3/8" grado 60, 3/8" A 10 LIGADORA:

Page 78: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 48

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

1 Acero 3/8" x 20' grado 60 + 10% desp.. Diámetro: 0.300 1.7027 qq 2,021.08 3,441.292 Acero ½" x 20' grado 60 + 10% desp.. Area: 0.0707 5.6896 qq 2,021.08 11,499.143 M.O. acero. Perímetro: 0.9425 14.14 m 71.30 1,008.494 Madera bruta amer. (4 usos). 73.71 pt 29.00 2,137.595 Clavos corrientes (5 lb. / 100 pie madera). 11.79 lb 24.79 292.276 Clavos de acero (¼ lb / metro). 3.54 lb 45.24 160.157 Alambre calibre #14 (¼ lb. / metro). 3.54 lb 25.44 90.068 Confección de madera. 14.14 m 299.56 4,237.069 Instalación de madera. 14.14 m 158.33 2,239.4610 Desencofrado. 13.33 m2 18.54 247.1411 Horm. 1:2:4 ligadora + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $29,282.21*HACOLC 10230002 COL. CIRCULAR, 1:2:4, 6 DE 3/8" grado 60, 3/8" A 10 A MANO:

1 Acero 3/8" x 20' grado 60 + 10% desp.. Diámetro: 0.300 1.7027 qq 2,021.08 3,441.292 Acero ½" x 20' grado 60 + 10% desp.. Area: 0.0707 5.6896 qq 2,021.08 11,499.143 M.O. acero. Perímetro: 0.9425 14.14 m 71.30 1,008.494 Madera bruta amer. (4 usos). 73.71 pt 29.00 2,137.595 Clavos corrientes (5 lb. / 100 pie madera). 11.79 lb 24.79 292.276 Clavos de acero (¼ lb / metro). 3.54 lb 45.24 160.157 Alambre calibre #14 (¼ lb. / metro). 3.54 lb 25.44 90.068 Confección de madera. 14.14 m 299.56 4,237.069 Instalación de madera. 14.14 m 158.33 2,239.4610 Desencofrado. 13.33 m2 18.54 247.1411 Horm. 1:2:4 ligadora + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $29,712.96

*HACOLA 10250000 HORM. ARMADO COL. DE AMARRE

*HACOLA 10250001 COL. AMARRE 15x20, 1:2:4, 40, 4 DE 3/8", ¼" A 20, LIG.:1 Acero ¼" + 10% desp. 0.779 qq 1,088.60 848.022 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 1,915.88 3,638.263 M.O. acero 33.33 m 71.30 2,376.434 Madera bruta amer. (4 usos) 97.97 pt 29.00 2,841.135 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 24.79 485.646 Clavos de acero (¼ lb / metro) 8.33 lb 45.24 376.857 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 25.44 211.928 Confección e instalación de madera 33.33 m 88.44 2,947.719 Desencofrado 13.33 m2 18.54 247.1410 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $17,902.66*HACOLA 10250002 COL. AMARRE 15x20, 1:2:4, 40, 4 DE 3/8", ¼" A 20 A MANO:

1 Acero ¼" + 10% desp. 0.779 qq 1,088.60 848.022 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 1,915.88 3,638.263 M.O. acero 33.33 m 71.30 2,376.434 Madera bruta amer. (4 usos) 97.97 pt 29.00 2,841.135 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 24.79 485.646 Clavos de acero (¼ lb / metro) 8.33 lb 45.24 376.857 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 25.44 211.928 Confección e instalación de madera 33.33 m 88.44 2,947.719 Desencofrado 13.33 m2 18.54 247.1410 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $18,333.41*HACOLA 10250003 COL. AMARRE 15x20, 1:2:4, 40, 4 DE 3/8", 3/8" A 20, LIG.:

1 Acero 3/8" + 10% desp. en entribos 1.723 qq 1,915.88 3,301.062 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 1,915.88 3,638.263 M.O. acero 33.33 m 71.30 2,376.434 Madera bruta amer. (4 usos) 97.97 pt 29.00 2,841.135 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 24.79 485.646 Clavos de acero (¼ lb / metro) 8.33 lb 45.24 376.857 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 25.44 211.928 Confección e instalación de madera 33.33 m 88.44 2,947.719 Desencofrado 13.33 m2 18.54 247.1410 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $20,355.70*HACOLA 10250004 COL. AMARRE 15x20, 1:2:4, 40, 4 DE 3/8", 3/8" A 20 A MANO:

1 Acero 3/8" + 10% desp. en entribos 1.723 qq 1,915.88 3,301.062 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 1,915.88 3,638.263 M.O. acero 33.33 m 71.30 2,376.434 Madera bruta amer. (4 usos) 97.97 pt 29.00 2,841.135 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 24.79 485.646 Clavos de acero (¼ lb / metro) 8.33 lb 45.24 376.857 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 25.44 211.928 Confección e instalación de madera 33.33 m 88.44 2,947.719 Desencofrado 13.33 m2 18.54 247.1410 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $20,786.45*HACOLA 10250005 COL. AMARRE 20x20, 1:2:4, 40, 4 DE 3/8", ¼" A 20, LIG.:

1 Acero ¼" + 10% desp. 0.668 qq 1,088.60 727.182 Acero 3/8" x 20' grado 40 + 10% desp. 1.424 qq 1,915.88 2,728.213 M.O. acero 25.00 m 71.30 1,782.504 Madera bruta amer. (4 usos) 94.36 pt 29.00 2,736.445 Clavos corrientes (5 lb. / 100 pie madera) 18.87 lb 24.79 467.796 Clavos de acero (¼ lb / metro) 6.25 lb 45.24 282.757 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 25.44 159.008 Confección e instalación de madera 25.00 m 88.44 2,211.009 Desencofrado 10.00 m2 18.54 185.4010 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $15,209.83

Page 79: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 49

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HACOLA 10250006 COL. AMARRE 20x20, 1:2:4, 40, 4 DE 3/8", ¼" A 20 A MANO:1 Acero ¼" + 10% desp. 0.668 qq 1,088.60 727.182 Acero 3/8" x 20' grado 40 + 10% desp. 1.424 qq 1,915.88 2,728.213 M.O. acero 25.00 m 71.30 1,782.504 Madera bruta amer. (4 usos) 94.36 pt 29.00 2,736.445 Clavos corrientes (5 lb. / 100 pie madera) 18.87 lb 24.79 467.796 Clavos de acero (¼ lb / metro) 6.25 lb 45.24 282.757 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 25.44 159.008 Confección e instalación de madera 25.00 m 88.44 2,211.009 Desencofrado 10.00 m2 18.54 185.4010 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $15,640.58

*HADIN 10270000 HORM. ARMADO DINTELES

*HADIN 10270001 DINTEL 10x20, 1:2:4, 40, 2 DE ½"-2 DE 3/8", ¼" A .20, LIG.:1 Acero ¼" + 10% desp. 0.998 qq 1,088.60 1,086.422 Acero 3/8" x 20' grado 40 + 10% desp. 1.424 qq 1,915.88 2,728.213 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 1,915.88 4,969.794 M.O. acero 50.00 m 71.30 3,565.005 Madera bruta amer. (4 usos) 242.18 pt 29.00 7,023.226 Clavos corrientes (5 lb. / 100 pie madera) 48.44 lb 24.79 1,200.837 Clavos de acero (¼ lb / metro) 12.50 lb 45.24 565.508 Alambre calibre #14 (¼ lb. / metro) 12.50 lb 25.44 318.009 Confección e instalación de madera 50.00 m 176.88 8,844.0010 Desencofrado 20.00 m2 21.40 428.0011 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $34,658.53*HADIN 10270002 DINTEL 10x20, 1:2:4, 40, 2 DE ½"-2 DE 3/8", ¼" A .20 A MANO:

1 Acero ¼" + 10% desp. 0.998 qq 1,088.60 1,086.422 Acero 3/8" x 20' grado 40 + 10% desp. 1.424 qq 1,915.88 2,728.213 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 1,915.88 4,969.794 M.O. acero 50.00 m 71.30 3,565.005 Madera bruta amer. (4 usos) 242.18 pt 29.00 7,023.226 Clavos corrientes (5 lb. / 100 pie madera) 48.44 lb 24.79 1,200.837 Clavos de acero (¼ lb / metro) 12.50 lb 45.24 565.508 Alambre calibre #14 (¼ lb. / metro) 12.50 lb 25.44 318.009 Confección e instalación de madera 50.00 m 176.88 8,844.0010 Desencofrado 20.00 m2 21.40 428.0011 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $35,089.28*HADIN 10270003 DINTEL 15x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", ¼" A .20, LIG.:

1 Acero ¼" + 10% desp. 0.779 qq 1,088.60 848.022 Acero 3/8" x 20' grado 40 + 10% desp. 0.950 qq 1,915.88 1,820.093 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 1,915.88 4,969.794 M.O. acero 33.33 m 71.30 2,376.435 Madera bruta amer. (4 usos) 169.13 pt 29.00 4,904.776 Clavos corrientes (5 lb. / 100 pie madera) 33.83 lb 24.79 838.657 Clavos de acero (¼ lb / metro) 8.33 lb 45.24 376.858 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 25.44 211.929 Confección e instalación de madera 33.33 m 176.88 5,895.4110 Desencofrado 13.33 m2 21.40 285.2611 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $26,456.75*HADIN 10270004 DINTEL 15x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", ¼" A .20 A MANO:

1 Acero ¼" + 10% desp. 0.779 qq 1,088.60 848.022 Acero 3/8" x 20' grado 40 + 10% desp. 0.950 qq 1,915.88 1,820.093 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 1,915.88 4,969.794 M.O. acero 33.33 m 71.30 2,376.435 Madera bruta amer. (4 usos) 169.13 pt 29.00 4,904.776 Clavos corrientes (5 lb. / 100 pie madera) 33.83 lb 24.79 838.657 Clavos de acero (¼ lb / metro) 8.33 lb 45.24 376.858 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 25.44 211.929 Confección e instalación de madera 33.33 m 176.88 5,895.4110 Desencofrado 13.33 m2 21.40 285.2611 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $26,887.50*HADIN 10270005 DINTEL 15x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", " 3/8" A .20, LIG.:

1 Acero 3/8" + 10% desp. en estribos 1.723 qq 1,915.88 3,301.062 Acero 3/8" x 20' grado 40 + 10% desp. 0.950 qq 1,915.88 1,820.093 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 1,915.88 4,969.794 M.O. acero 33.33 m 71.30 2,376.435 Madera bruta amer. (4 usos) 169.13 pt 29.00 4,904.776 Clavos corrientes (5 lb. / 100 pie madera) 33.83 lb 24.79 838.657 Clavos de acero (¼ lb / metro) 8.33 lb 45.24 376.858 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 25.44 211.929 Confección e instalación de madera 33.33 m 176.88 5,895.4110 Desencofrado 13.33 m2 21.40 285.2611 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $28,909.79*HADIN 10270006 DINTEL 15x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", 3/8" A .20 A MANO:

1 Acero 3/8" + 10% desp. en estribos 1.723 qq 1,915.88 3,301.062 Acero 3/8" x 20' grado 40 + 10% desp. 0.950 qq 1,915.88 1,820.093 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 1,915.88 4,969.794 M.O. acero 33.33 m 71.30 2,376.435 Madera bruta amer. (4 usos) 169.13 pt 29.00 4,904.776 Clavos corrientes (5 lb. / 100 pie madera) 33.83 lb 24.79 838.657 Clavos de acero (¼ lb / metro) 8.33 lb 45.24 376.85

Page 80: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 50

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

8 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 25.44 211.929 Confección e instalación de madera 33.33 m 176.88 5,895.4110 Desencofrado 13.33 m2 21.40 285.2611 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $29,340.54*HADIN 10270007 DINTEL 20x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", 3/8" A .20, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 2.069 qq 1,915.88 3,963.962 Acero ½" x 20' grado 40 + 10% desp. 1.945 qq 1,915.88 3,726.393 M.O. acero 25.00 m 71.30 1,782.504 Madera bruta amer. (4 usos) 132.62 pt 29.00 3,845.985 Clavos corrientes (5 lb. / 100 pie madera) 26.52 lb 24.79 657.436 Clavos de acero (¼ lb / metro) 6.25 lb 45.24 282.757 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 25.44 159.008 Confección e instalación de madera 25.00 m 176.88 4,422.009 Desencofrado 10.00 m2 21.40 214.0010 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $22,983.57*HADIN 10270008 DINTEL 20x20, 1:2:4, 40, 3 DE ½"-2 DE 3/8", 3/8" A .20 A MANO:

1 Acero 3/8" x 20' grado 40 + 10% desp. 2.069 qq 1,915.88 3,963.962 Acero ½" x 20' grado 40 + 10% desp. 1.945 qq 1,915.88 3,726.393 M.O. acero 25.00 m 71.30 1,782.504 Madera bruta amer. (4 usos) 132.62 pt 29.00 3,845.985 Clavos corrientes (5 lb. / 100 pie madera) 26.52 lb 24.79 657.436 Clavos de acero (¼ lb / metro) 6.25 lb 45.24 282.757 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 25.44 159.008 Confección e instalación de madera 25.00 m 176.88 4,422.009 Desencofrado 10.00 m2 21.40 214.0010 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $23,414.32*HADIN 10270009 DINTEL 10x20, 180 kg/Cm², 40, 2 DE ½"-2 DE 3/8", ¼" A .20:

1 Acero ¼" + 10% desp. 0.998 qq 1,088.60 1,086.422 Acero 3/8" x 20' grado 40 + 10% desp. 1.424 qq 1,915.88 2,728.213 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 1,915.88 4,969.794 M.O. acero 50.00 m 71.30 3,565.005 Madera bruta amer. (4 usos) 242.18 pt 29.00 7,023.226 Clavos corrientes (5 lb. / 100 pie madera) 48.44 lb 24.79 1,200.837 Clavos de acero (¼ lb / metro) 12.50 lb 45.24 565.508 Alambre calibre #14 (¼ lb. / metro) 12.50 lb 25.44 318.009 Confección e instalación de madera 50.00 m 176.88 8,844.0010 Desencofrado 20.00 m2 21.40 428.0011 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $36,662.37*HADIN 10270010 DINTEL 15x20, 180 kg/Cm², 40, 3 DE ½"-2 DE 3/8", ¼" A .20:

1 Acero ¼" + 10% desp. 0.779 qq 1,088.60 848.022 Acero 3/8" x 20' grado 40 + 10% desp. 0.950 qq 1,915.88 1,820.093 Acero ½" x 20' grado 40 + 10% desp. 2.594 qq 1,915.88 4,969.794 M.O. acero 33.33 m 71.30 2,376.435 Madera bruta amer. (4 usos) 169.13 pt 29.00 4,904.776 Clavos corrientes (5 lb. / 100 pie madera) 33.83 lb 24.79 838.657 Clavos de acero (¼ lb / metro) 8.33 lb 45.24 376.858 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 25.44 211.929 Confección e instalación de madera 33.33 m 176.88 5,895.4110 Desencofrado 13.33 m2 21.40 285.2611 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $28,460.59*HADIN 10270011 DINTEL 20x20, 180 kg/Cm², 40, 3 DE ½"-2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 2.069 qq 1,915.88 3,963.962 Acero ½" x 20' grado 40 + 10% desp. 1.945 qq 1,915.88 3,726.393 M.O. acero 25.00 m 71.30 1,782.504 Madera bruta amer. (4 usos) 132.62 pt 29.00 3,845.985 Clavos corrientes (5 lb. / 100 pie madera) 26.52 lb 24.79 657.436 Clavos de acero (¼ lb / metro) 6.25 lb 45.24 282.757 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 25.44 159.008 Confección e instalación de madera 25.00 m 176.88 4,422.009 Desencofrado 10.00 m2 21.40 214.0010 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $24,987.41

*HALOSM 10290000 HORM. ARMADO LOSAS MONOLITICAS

*HALOSM 10290001 LOSA H=10, 1:2:4, 40, 3/8" x 20' A 25 A. D. LIG. Y WINCHE:1 Acero 3/8" x 20' grado 40 + 10% desp. 1.819 qq 1,915.88 3,484.992 M.O. acero 1.819 qq 213.92 389.123 Subida acero 1.819 qq 21.39 38.914 Madera bruta amer. (4 usos) 69.89 pt 29.00 2,026.815 Clavos corrientes (5 lb. / 100 pie madera) 13.98 lb 24.79 346.566 Clavos de acero (.08 lb / m2) 0.80 lb 45.24 36.197 Alambre calibre #14 (.15 lb. / m2) 1.50 lb 25.44 38.168 Confección madera 10.00 m2 106.98 1,069.809 Desencofrado 10.00 m2 22.82 228.2010 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 3,761.45 4,137.60

M3 $11,796.34*HALOSM 10290002 LOSA H=10, 1:2:4, 40, 3/8" >20' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.819 qq 1,915.88 3,484.992 Partidas comunes del análisis anterior (2-10) 1.00 u 8,311.35 8,311.35

M3 $11,796.34*HALOSM 10290003 LOSA H=10, 1:2:4, 60, 3/8" x 20' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.819 qq 2,021.08 3,676.34

Page 81: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 51

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

2 M.O. acero 1.819 qq 323.23 587.963 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 7,922.23 7,922.23

M3 $12,186.53*HALOSM 10290004 LOSA H=10, 1:2:4, 60, 3/8" x 25' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.819 qq 2,021.08 3,676.342 M.O. acero 1.819 qq 323.23 587.963 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 7,922.23 7,922.23

M3 $12,186.53*HALOSM 10290005 LOSA H=12, 1:2:4, 40, 3/8" x 20' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.496 qq 1,915.88 2,866.162 M.O. acero 1.496 qq 213.92 320.023 Subida acero 1.496 qq 21.39 32.004 Madera bruta amer. (4 usos) 56.95 pt 29.00 1,651.555 Clavos corrientes (5 lb. / 100 pie madera) 11.39 lb 24.79 282.366 Clavos de acero (.08 lb / m2) 0.67 lb 45.24 30.317 Alambre calibre #14 (.15 lb. / m2) 1.25 lb 25.44 31.808 Confección 8.35 m2 106.98 893.289 Desencofrado 8.35 m2 22.82 190.5510 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 3,761.45 4,137.60

M3 $10,435.63*HALOSM 10290006 LOSA H=12 1:2:4, 40, 3/8" >20' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.496 qq 1,915.88 2,866.162 Partidas comunes del análisis anterior (2-10) 1.00 u 7,569.47 7,569.47

M3 $10,435.63*HALOSM 10290007 LOSA H=12, 1:2:4, 60, 3/8" x 20' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.496 qq 2,021.08 3,023.542 M.O. acero 1.496 qq 323.23 483.553 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 7,249.45 7,249.45

M3 $10,756.54*HALOSM 10290008 LOSA H=12, 1:2:4, 60, 3/8" x 25' A 25 A. D. LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.496 qq 2,021.08 3,023.542 M.O. acero 1.496 qq 323.23 483.553 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 7,249.45 7,249.45

M3 $10,756.54*HALOSM 10290009 LOSA H=10, 180 kg/Cm², 40, 3/8" x 20' A 25 A. D.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.819 qq 1,915.88 3,484.992 M.O. acero 1.819 qq 213.92 389.123 Subida acero 1.819 qq 21.39 38.914 Madera bruta amer. (4 usos) 69.89 pt 29.00 2,026.815 Clavos corrientes (5 lb. / 100 pie madera) 13.98 lb 24.79 346.566 Clavos de acero (.08 lb / m2) 0.80 lb 45.24 36.197 Alambre calibre #14 (.15 lb. / m2) 1.50 lb 25.44 38.168 Confección madera 10.00 m2 106.98 1,069.809 Desencofrado 10.00 m2 22.82 228.2010 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $13,592.14*HALOSM 10290010 LOSA H=10, 180 kg/Cm², 40, 3/8" >20' A 25 A. D., HORM. IND.:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.819 qq 1,915.88 3,484.992 Partidas comunes del análisis anterior (2-10) 1.00 u 10,107.15 10,107.15

M3 $13,592.14*HALOSM 10290011 LOSA H=10, 180 kg/Cm², 60, 3/8" x 20' A 25 A. D., HORM. IND.:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.819 qq 2,021.08 3,676.342 M.O. acero 1.819 qq 323.23 587.963 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 9,718.03 9,718.03

M3 $13,982.33*HALOSM 10290012 LOSA H=10, 180 kg/Cm², 60, 3/8" x 25' A 25 A. D., HORM. IND.:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.819 qq 2,021.08 3,676.342 M.O. acero 1.819 qq 323.23 587.963 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 9,718.03 9,718.03

M3 $13,982.33*HALOSM 10290013 LOSA H=12, 180 kg/Cm², 40, 3/8" x 20' A 25 A. D., HORM. IND.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.496 qq 1,915.88 2,866.162 M.O. acero 1.496 qq 213.92 320.023 Subida acero 1.496 qq 21.39 32.004 Madera bruta amer. (4 usos) 56.95 pt 29.00 1,651.555 Clavos corrientes (5 lb. / 100 pie madera) 11.39 lb 24.79 282.366 Clavos de acero (.08 lb / m2) 0.67 lb 45.24 30.317 Alambre calibre #14 (.15 lb. / m2) 1.25 lb 25.44 31.808 Confección madera 8.35 m2 106.98 893.289 Desencofrado 8.35 m2 22.82 190.5510 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $12,231.43*HALOSM 10290014 LOSA H=12 180 kg/Cm², 40, 3/8" >20' A 25 A. D., HORM. IND.:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.496 qq 1,915.88 2,866.162 Partidas comunes del análisis anterior (2-10) 1.00 u 9,365.27 9,365.27

M3 $12,231.43*HALOSM 10290015 LOSA H=12, 180 Kg/Cm², 60, 3/8" x 20' A 25 A., D. HORM. IND.:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.496 qq 2,021.08 3,023.542 M.O. acero 1.496 qq 323.23 483.553 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 9,045.25 9,045.25

M3 $12,552.34*HALOSM 10290016 LOSA H=12, 180 Kg/Cm², 60, 3/8" x 25' A 25 A. D., HORM. IND.:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.496 qq 2,021.08 3,023.542 M.O. acero 1.496 qq 323.23 483.553 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 9,045.25 9,045.25

M3 $12,552.34

*HAMUR 10310000 HORM. ARMADO MUROS

Page 82: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 52

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HAMUR 10310001 MUROS 0.15, 180 Kg/Cm², 40, 3/8" x 20' A .20 A.D., 2 CARAS: Espesor = 0.151 Acero 3/8" x 20' grado 40 + 10% desp. 1.8156 qq 1,915.88 3,478.472 M.O. acero 1.8156 qq 213.92 388.393 Planchas plywood 4'x8'x¾" (8 usos) 0.56 u 1,150.00 644.004 Madera bruta amer. (4 usos) 46.33 pt 29.00 1,343.575 Clavos corrientes (10 lb. / 100 pie madera) 18.53 lb 24.79 459.366 Clavos de acero (½ lb / m²) 6.67 lb 45.24 301.757 Alambre calibre #14 (½ lb. / m²) 6.67 lb 25.44 169.688 Confección madera (dos caras) 13.333 m2 128.38 1,711.699 Instalación madera (dos caras) 13.333 m2 161.19 2,149.1510 Desencofrado 13.333 m2 18.54 247.1911 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 5,933.40 5,933.40

M3 $16,826.65*HAMUR 10310002 MUROS 0.15, 180 Kg/Cm², 40, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.8156 qq 1,915.88 3,478.472 Partidas comunes del análisis anterior (2-11) 1.00 u 13,348.18 13,348.18

M3 $16,826.65*HAMUR 10310003 MUROS 0.15, 180 Kg/Cm², 60, 3/8" x 20' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.8156 qq 2,021.08 3,669.472 M.O. acero 1.8156 qq 323.23 586.863 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 12,959.79 12,959.79

M3 $17,216.12*HAMUR 10310004 MUROS 0.15, 180 Kg/Cm², 60, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.8156 qq 2,021.08 3,669.472 M.O. acero 1.8156 qq 323.23 586.863 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 12,959.79 12,959.79

M3 $17,216.12*HAMUR 10310005 MUROS 0.15, 210 Kg/Cm², 40 3/8" x 20' A .20 A.D., 2 CARAS: Espesor = 0.15

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.8156 qq 1,915.88 3,478.472 M.O. acero 1.8156 qq 213.92 388.393 Planchas plywood 4'x8'x¾" (8 usos) 0.56 u 1,150.00 644.004 Madera bruta amer. (4 usos) 46.33 pt 29.00 1,343.575 Clavos corrientes (10 lb. / 100 pie madera) 18.53 lb 24.79 459.366 Clavos de acero (½ lb / m²) 6.67 lb 45.24 301.757 Alambre calibre #14 (½ lb. / m²) 6.67 lb 25.44 169.688 Confección madera (dos caras) 13.333 m2 128.38 1,711.699 Instalación madera (dos caras) 13.333 m2 161.19 2,149.1510 Desencofrado 13.333 m2 18.54 247.1911 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 6,188.60 6,188.60

M3 $17,081.85*HAMUR 10310006 MUROS 0.15, 210 Kg/Cm², 40 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.8156 qq 1,915.88 3,478.472 Partidas comunes del análisis anterior (2-11) 1.00 u 13,603.38 13,603.38

M3 $17,081.85*HAMUR 10310007 MUROS 0.15, 210 Kg/Cm², 60, 3/8" x 20' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.8156 qq 2,021.08 3,669.472 M.O. acero 1.8156 qq 323.23 586.863 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,214.99 13,214.99

M3 $17,471.32*HAMUR 10310008 MUROS 0.15, 210 Kg/Cm², 60, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.8156 qq 2,021.08 3,669.472 M.O. acero 1.8156 qq 323.23 586.863 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,214.99 13,214.99

M3 $17,471.32*HAMUR 10310009 MUROS 0.15, 240 Kg/Cm², 40, 3/8" x 20' A .20 A.D., 2 CARAS: Espesor = 0.15

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.8156 qq 1,915.88 3,478.472 M.O. acero 1.8156 qq 213.92 388.393 Planchas plywood 4'x8'x¾" (8 usos) 0.56 u 1,150.00 644.004 Madera bruta amer. (4 usos) 46.33 pt 29.00 1,343.575 Clavos corrientes (10 lb. / 100 pie madera) 18.53 lb 24.79 459.366 Clavos de acero (½ lb / m²) 6.67 lb 45.24 301.757 Alambre calibre #14 (½ lb. / m²) 6.67 lb 25.44 169.688 Confección madera (dos caras) 13.333 m2 128.38 1,711.699 Instalación madera (dos caras) 13.333 m2 161.19 2,149.1510 Desencofrado 13.333 m2 18.54 247.1911 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 6,443.80 6,443.80

M3 $17,337.05*HAMUR 10310010 MUROS 0.15, 240 Kg/Cm², 40, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.8156 qq 1,915.88 3,478.472 Partidas comunes del análisis anterior (2-11) 1.00 u 13,858.58 13,858.58

M3 $17,337.05*HAMUR 10310011 MUROS 0.15, 240 Kg/Cm², 60, 3/8" x 20' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.8156 qq 2,021.08 3,669.472 M.O. acero 1.8156 qq 323.23 586.863 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,470.19 13,470.19

M3 $17,726.52*HAMUR 10310012 MUROS 0.15, 240 Kg/Cm², 60, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.8156 qq 2,021.08 3,669.472 M.O. acero 1.8156 qq 323.23 586.863 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 13,470.19 13,470.19

M3 $17,726.52*HAMUR 10310013 MUROS 0.20, 180 Kg/Cm², 40, 3/8" x 20' A .20 A.D., 2 CARAS: Espesor = 0.20

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.3634 qq 1,915.88 2,612.112 M.O. acero 1.3634 qq 213.92 291.663 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,150.00 483.004 Madera bruta amer. (4 usos) 34.79 pt 29.00 1,008.915 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 24.79 345.08

Page 83: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 53

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

6 Clavos de acero (½ lb / m²) 5.00 lb 45.24 226.207 Alambre calibre #14 (½ lb. / m²) 5.00 lb 25.44 127.208 Confección madera (dos caras) 10.000 m2 128.38 1,283.809 Instalación madera (dos caras) 10.000 m2 161.19 1,611.9010 Desencofrado 10.000 m2 18.54 185.4011 Horm. 180 Kg/Cm² + 5% desp. 1.00 m3 5,933.40 5,933.40

M3 $14,108.66*HAMUR 10310014 MUROS 0.20, 180 Kg/Cm², 40, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.3634 qq 1,915.88 2,612.112 Partidas comunes del análisis anterior (2-11) 1.00 u 11,496.55 11,496.55

M3 $14,108.66*HAMUR 10310015 MUROS 0.20, 180 Kg/Cm², 60, 3/8" x 20' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.3634 qq 2,021.08 2,755.542 M.O. acero 1.3634 qq 323.23 440.693 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,204.89 11,204.89

M3 $14,401.12*HAMUR 10310016 MUROS 0.20, 180 Kg/Cm², 60, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.3634 qq 2,021.08 2,755.542 M.O. acero 1.3634 qq 323.23 440.693 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,204.89 11,204.89

M3 $14,401.12*HAMUR 10310017 MUROS 0.20, 210 Kg/Cm², 40, 3/8" x 20' A .20 A.D., 2 CARAS: Espesor = 0.20

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.3634 qq 1,915.88 2,612.112 M.O. acero 1.3634 qq 213.92 291.663 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,150.00 483.004 Madera bruta amer. (4 usos) 34.79 pt 29.00 1,008.915 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 24.79 345.086 Clavos de acero (½ lb / m²) 5.00 lb 45.24 226.207 Alambre calibre #14 (½ lb. / m²) 5.00 lb 25.44 127.208 Confección madera (dos caras) 10.000 m2 128.38 1,283.809 Instalación madera (dos caras) 10.000 m2 161.19 1,611.9010 Desencofrado 10.000 m2 18.54 185.4011 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 6,188.60 6,188.60

M3 $14,363.86*HAMUR 10310018 MUROS 0.20, 210 Kg/Cm², 40, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.3634 qq 1,915.88 2,612.112 Partidas comunes del análisis anterior (2-11) 1.00 u 11,751.75 11,751.75

M3 $14,363.86*HAMUR 10310019 MUROS 0.20, 210 Kg/Cm², 60, 3/8" x 20' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.3634 qq 2,021.08 2,755.542 M.O. acero 1.3634 qq 323.23 440.693 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,460.09 11,460.09

M3 $14,656.32*HAMUR 10310020 MUROS 0.20, 210 Kg/Cm², 60, 3/8" x 25' A .20 A.D., 2 CARAS:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.3634 qq 2,021.08 2,755.542 M.O. acero 1.3634 qq 323.23 440.693 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,460.09 11,460.09

M3 $14,656.32*HAMUR 10310021 MUROS 0.20, 210 Kg/Cm², 40, ½" x 20' A .10 A.D., 2 CARAS: Espesor = 0.20

1 Acero ½" x 20' grado 40 + 10% desp. 4.8444 qq 1,915.88 9,281.292 M.O. acero 4.8444 qq 213.92 1,036.313 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,150.00 483.004 Madera bruta amer. (4 usos) 34.79 pt 29.00 1,008.915 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 24.79 345.086 Clavos de acero (½ lb / m²) 5.00 lb 45.24 226.207 Alambre calibre #14 (½ lb. / m²) 5.00 lb 25.44 127.208 Confección madera (dos caras) 10.000 m2 128.38 1,283.809 Instalación madera (dos caras) 10.000 m2 161.19 1,611.9010 Desencofrado 10.000 m2 18.54 185.4011 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 6,188.60 6,188.60

M3 $21,777.69*HAMUR 10310022 MUROS 0.20, 210 Kg/Cm², 40, ½" x 25' A .10 A.D., 2 CARAS:

1 Acero ½" x 25' grado 40 + 10% desp. 4.8444 qq 1,915.88 9,281.292 Partidas comunes del análisis anterior (2-11) 1.00 u 12,496.40 12,496.40

M3 $21,777.69*HAMUR 10310023 MUROS 0.20, 210 Kg/Cm², 60, ½" x 20' A .10 A.D., 2 CARAS:

1 Acero ½" x 20' grado 60 + 10% desp. 4.8444 qq 2,021.08 9,790.922 M.O. acero 4.8444 qq 323.23 1,565.863 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,460.09 11,460.09

M3 $22,816.87*HAMUR 10310024 MUROS 0.20, 210 Kg/Cm², 60, ½" >20' A .10 A.D., 2 CARAS:

1 Acero ½" x 25' grado 60 + 10% desp. 4.8444 qq 2,021.08 9,790.922 M.O. acero 4.8444 qq 323.23 1,565.863 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,460.09 11,460.09

M3 $22,816.87*HAMUR 10310025 MUROS 0.20, 210 Kg/Cm², 40, ½" x 20' A .20 A.D., 2 CARAS: Espesor = 0.20

1 Acero ½" x 20' grado 40 + 10% desp. 2.4222 qq 1,915.88 4,640.642 M.O. acero 2.4222 qq 213.92 518.163 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,150.00 483.004 Madera bruta amer. (4 usos) 34.79 pt 29.00 1,008.915 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 24.79 345.086 Clavos de acero (½ lb / m²) 5.00 lb 45.24 226.207 Alambre calibre #14 (½ lb. / m²) 5.00 lb 25.44 127.208 Confección madera (dos caras) 10.000 m2 128.38 1,283.809 Instalación madera (dos caras) 10.000 m2 161.19 1,611.9010 Desencofrado 10.000 m2 18.54 185.4011 Horm. 210 Kg/Cm² + 5% desp. 1.00 m3 6,188.60 6,188.60

M3 $16,618.89

Page 84: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 54

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HAMUR 10310026 MUROS 0.20, 210 Kg/Cm², 40, ½" x 25' A .20 A.D., 2 CARAS:1 Acero ½" x 25' grado 40 + 10% desp. 2.4222 qq 1,915.88 4,640.642 Partidas comunes del análisis anterior (2-11) 1.00 u 11,978.25 11,978.25

M3 $16,618.89*HAMUR 10310027 MUROS 0.20, 210 Kg/Cm², 60, ½" x 20' A .20 A.D., 2 CARAS:

1 Acero ½" x 20' grado 60 + 10% desp. 2.4222 qq 2,021.08 4,895.462 M.O. acero 2.4222 qq 323.23 782.933 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,460.09 11,460.09

M3 $17,138.48*HAMUR 10310028 MUROS 0.20, 210 Kg/Cm², 60, ½" x 25' A .20 A.D., 2 CARAS:

1 Acero ½" x 25' grado 60 + 10% desp. 2.4222 qq 2,021.08 4,895.462 M.O. acero 2.4222 qq 323.23 782.933 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,460.09 11,460.09

M3 $17,138.48*HAMUR 10310029 MUROS 0.20, 240 Kg/Cm², 40, ½" x 20' A .10 A.D., 2 CARAS: Espesor = 0.20

1 Acero ½" x 20' grado 40 + 10% desp. 4.8444 qq 1,915.88 9,281.292 M.O. acero 4.8444 qq 213.92 1,036.313 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,150.00 483.004 Madera bruta amer. (4 usos) 34.79 pt 29.00 1,008.915 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 24.79 345.086 Clavos de acero (½ lb / m²) 5.00 lb 45.24 226.207 Alambre calibre #14 (½ lb. / m²) 5.00 lb 25.44 127.208 Confección madera (dos caras) 10.000 m2 128.38 1,283.809 Instalación madera (dos caras) 10.000 m2 161.19 1,611.9010 Desencofrado 10.000 m2 18.54 185.4011 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 6,443.80 6,443.80

M3 $22,032.89

Page 85: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 55

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HAMUR 10310030 MUROS 0.20, 240 Kg/Cm², 40, ½" x 25' A .10 A.D., 2 CARAS:1 Acero ½" x 25' grado 40 + 10% desp. 4.8444 qq 1,915.88 9,281.292 Partidas comunes del análisis anterior (2-11) 1.00 u 12,751.60 12,751.60

M3 $22,032.89*HAMUR 10310031 MUROS 0.20, 240 Kg/Cm², 60, ½" x 20' A .10 A.D., 2 CARAS:

1 Acero ½" x 20' grado 60 + 10% desp. 4.8444 qq 2,021.08 9,790.922 M.O. acero 4.8444 qq 323.23 1,565.863 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,715.29 11,715.29

M3 $23,072.07*HAMUR 10310032 MUROS 0.20, 240 Kg/Cm², 60, ½" x 25' A .10 A.D., 2 CARAS:

1 Acero ½" x 25' grado 60 + 10% desp. 4.8444 qq 2,021.08 9,790.922 M.O. acero 4.8444 qq 323.23 1,565.863 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,715.29 11,715.29

M3 $23,072.07*HAMUR 10310033 MUROS 0.20, 240 Kg/Cm², 40, ½" x 20' A .20 A.D., 2 CARAS: Espesor = 0.20

1 Acero ½" x 20' grado 40 + 10% desp. 2.4222 qq 1,915.88 4,640.642 M.O. acero 2.4222 qq 213.92 518.163 Planchas plywood 4'x8'x¾" (8 usos) 0.42 u 1,150.00 483.004 Madera bruta amer. (4 usos) 34.79 pt 29.00 1,008.915 Clavos corrientes (10 lb. / 100 pie madera) 13.92 lb 24.79 345.086 Clavos de acero (½ lb / m²) 5.00 lb 45.24 226.207 Alambre calibre #14 (½ lb. / m²) 5.00 lb 25.44 127.208 Confección madera (dos caras) 10.000 m2 128.38 1,283.809 Instalación madera (dos caras) 10.000 m2 161.19 1,611.9010 Desencofrado 10.000 m2 18.54 185.4011 Horm. 240 Kg/Cm² + 5% desp. 1.00 m3 6,443.80 6,443.80

M3 $16,874.09*HAMUR 10310034 MUROS 0.20, 240 Kg/Cm², 40, ½" x 25' A .20 A.D., 2 CARAS:

1 Acero ½" x 25' grado 40 + 10% desp. 2.4222 qq 1,915.88 4,640.642 Partidas comunes del análisis anterior (2-11) 1.00 u 12,233.45 12,233.45

M3 $16,874.09*HAMUR 10310035 MUROS 0.20, 240 Kg/Cm², 60, ½" x 20' A .20 A.D., 2 CARAS:

1 Acero ½" x 20' grado 60 + 10% desp. 2.4222 qq 2,021.08 4,895.462 M.O. acero 2.4222 qq 323.23 782.933 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,715.29 11,715.29

M3 $17,393.68*HAMUR 10310036 MUROS 0.20, 240 Kg/Cm², 60, ½" x 25' A .20 A.D., 2 CARAS:

1 Acero ½" x 25' grado 60 + 10% desp. 2.4222 qq 2,021.08 4,895.462 M.O. acero 2.4222 qq 323.23 782.933 Partidas comunes de la analizada completa anterior (3-11) 1.00 u 11,715.29 11,715.29

M3 $17,393.68

*HARAM 10330000 HORM. ARMADO RAMPAS DE ESCALERAS

*HARAM 10330001 RAMPAS H=12, 1:2:4, 40, ½" A .20, 3/8" A .20, LIG. Y WINCHE:1 Acero 3/8" x 20' grado 40 + 10% desp. 1.140 qq 1,915.88 2,184.102 Acero ½" x 20' grado 40 + 10% desp. 1.620 qq 1,915.88 3,103.733 M.O. acero (rampa) 3.00 u 2,125.00 6,375.004 Madera bruta amer. (4 usos) 42.22 pt 29.00 1,224.385 Clavos corrientes (10 lb. / 100 pie madera) 16.89 lb 24.79 418.706 Clavos de acero (.10 lb / m2) 0.92 lb 45.24 41.627 Alambre calibre #14 (.30 lb. / m2) 2.75 lb 25.44 69.968 Encofrado 9.17 m2 350.91 3,217.849 Desencofrado 9.17 m2 22.82 209.2610 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 3,761.45 4,137.60

M3 $20,982.19*HARAM 10330002 RAMPAS H=12, 1:2:4, 40, ½"X25' A .20, 3/8" A .20, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.140 qq 1,915.88 2,184.102 Acero ½" x 25' grado 40 + 10% desp. 1.620 qq 1,915.88 3,103.733 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 15,694.36 15,694.36

M3 $20,982.19*HARAM 10330003 RAMPAS H=12, 1:2:4, 60, ½" X 20' A .20, 3/8" A .20, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.140 qq 2,021.08 2,304.032 Acero ½" x 20' grado 60 + 10% desp. 1.620 qq 2,021.08 3,274.153 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 15,694.36 15,694.36

M3 $21,272.54*HARAM 10330004 RAMPAS H=12, 1:2:4, 60, ½"X25' A .20, 3/8" A .20, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.140 qq 2,021.08 2,304.032 Acero ½" x 25' grado 60 + 10% desp. 1.620 qq 2,021.08 3,274.153 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 15,694.36 15,694.36

M3 $21,272.54*HARAM 10330005 RAMPAS H=12, 1:2:4, 40, ½" A .20, 3/8" A .20, A MANO:

1 Partidas comunes de la analizada completa anterior (1-9) 1.000 u 16,844.59 16,844.592 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $21,204.90*HARAM 10330006 RAMPAS H=12, 1:2:4, 40, ½"X25' A .20, 3/8" A .20, A MANO:

1 Acero ½" x 25' grado 40 + 10% desp. 1.620 qq 1,915.88 3,103.732 Partidas comunes de la analizada completa anterior (1, 3-9) 1.00 u 13,740.86 13,740.863 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $21,204.90*HARAM 10330007 RAMPAS H=12, 1:2:4, 60, ½" X 20' A .20, 3/8" A .20, A MANO:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.140 qq 2,021.08 2,304.032 Acero ½" x 20' grado 60 + 10% desp. 1.620 qq 2,021.08 3,274.153 Partidas comunes de la analizada completa anterior (3-9) 1.000 u 11,556.76 11,556.764 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $21,495.25*HARAM 10330008 RAMPAS H=12, 1:2:4, 60, ½"X25' A .20, 3/8" A .20, A MANO:

1 Acero ½" x 25' grado 60 + 10% desp. 1.620 qq 2,021.08 3,274.15

Page 86: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 56

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

2 Partidas comunes de la analizada completa anterior (1, 3-9) 1.00 u 13,860.79 13,860.793 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $21,495.25

Page 87: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 57

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HARAM 10330009 RAMPAS H=12, 180 kg/Cm², 40, ½" A .20 Y 3/8" A .20:1 Acero 3/8" x 20' grado 40 + 10% desp. 1.140 qq 1,915.88 2,184.102 Acero ½" x 20' grado 40 + 10% desp. 1.620 qq 1,915.88 3,103.733 M.O. acero (rampa) 3.00 u 2,125.00 6,375.004 Madera bruta amer. (4 usos) 42.22 pt 29.00 1,224.385 Clavos corrientes (10 lb. / 100 pie madera) 16.89 lb 24.79 418.706 Clavos de acero (.10 lb / m2) 0.92 lb 45.24 41.627 Alambre Calibre #14 (.30 lb. / m2) 2.75 lb 25.44 69.968 Encofrado 9.17 m2 350.91 3,217.849 Desencofrado 9.17 m2 22.82 209.2610 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $22,777.99*HARAM 10330010 RAMPAS H=12, 180 kg/Cm², 40, ½"X25' A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.1400 qq 1,915.88 2,184.102 Acero ½" x 25' grado 40 + 10% desp. 1.6200 qq 1,915.88 3,103.733 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 17,490.16 17,490.16

M3 $22,777.99*HARAM 10330011 RAMPAS H=12, 180 kg/Cm², 60, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,021.08 2,304.032 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,021.08 3,274.153 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 17,490.16 17,490.16

M3 $23,068.34*HARAM 10330012 RAMPAS H=12, 180 kg/Cm², 60, ½"X25' A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,021.08 2,304.032 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,021.08 3,274.153 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 17,490.16 17,490.16

M3 $23,068.34*HARAM 10330013 RAMPAS H=12, 210 kg/Cm², 40, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.140 qq 1,915.88 2,184.102 Acero ½" x 20' grado 40 + 10% desp. 1.620 qq 1,915.88 3,103.733 M.O. acero (rampa) 3.00 u 2,125.00 6,375.004 Madera bruta amer. (4 usos) 42.22 pt 29.00 1,224.385 Clavos corrientes (10 lb. / 100 pie madera) 16.89 lb 24.79 418.706 Clavos de acero (.10 lb / m2) 0.92 lb 45.24 41.627 Alambre Calibre #14 (.30 lb. / m2) 2.75 lb 25.44 69.968 Encofrado 9.17 m2 350.91 3,217.849 Desencofrado 9.17 m2 22.82 209.2610 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $23,033.19*HARAM 10330014 RAMPAS H=12, 210 kg/Cm², 40, ½"X25' A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.1400 qq 1,915.88 2,184.102 Acero ½" x 25' grado 40 + 10% desp. 1.6200 qq 1,915.88 3,103.733 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 17,745.36 17,745.36

M3 $23,033.19*HARAM 10330015 RAMPAS H=12, 210 kg/Cm², 60, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,021.08 2,304.032 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,021.08 3,274.153 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 17,745.36 17,745.36

M3 $23,323.54*HARAM 10330016 RAMPAS H=12, 210 kg/Cm², 60, ½"X25' A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,021.08 2,304.032 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,021.08 3,274.153 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 17,745.36 17,745.36

M3 $23,323.54*HARAM 10330017 RAMPAS H=12, 240 kg/Cm², 40, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.140 qq 1,915.88 2,184.102 Acero ½" x 20' grado 40 + 10% desp. 1.620 qq 1,915.88 3,103.733 M.O. acero (rampa) 3.00 u 2,125.00 6,375.004 Madera bruta amer. (4 usos) 42.22 pt 29.00 1,224.385 Clavos corrientes (10 lb. / 100 pie madera) 16.89 lb 24.79 418.706 Clavos de acero (.10 lb / m2) 0.92 lb 45.24 41.627 Alambre Calibre #14 (.30 lb. / m2) 2.75 lb 25.44 69.968 Encofrado 9.17 m2 350.91 3,217.849 Desencofrado 9.17 m2 22.82 209.2610 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $23,288.39*HARAM 10330018 RAMPAS H=12, 240 kg/Cm², 40, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.1400 qq 1,915.88 2,184.102 Acero ½" x 25' grado 40 + 10% desp. 1.6200 qq 1,915.88 3,103.733 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 18,000.56 18,000.56

M3 $23,288.39*HARAM 10330019 RAMPAS H=12, 240 kg/Cm², 60, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,021.08 2,304.032 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,021.08 3,274.153 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 18,000.56 18,000.56

M3 $23,578.74*HARAM 10330020 RAMPAS H=12, 240 kg/Cm², 60, ½" A .20 Y 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.1400 qq 2,021.08 2,304.032 Acero ½" x 25' grado 60 + 10% desp. 1.6200 qq 2,021.08 3,274.153 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 18,000.56 18,000.56

M3 $23,578.74

*HAV 10350000 HORM. ARMADO VIGAS

*HAV 10350001 H. A. VIGA 20X40, 1:2:4, 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20, LIG. Y WINCHE:1 Acero 3/8" x 20' grado 40 + 10% desp. 1.502 qq 1,915.88 2,877.652 Acero ¾" grado 40 + 10% desp. 2.226 qq 1,915.88 4,264.753 M.O. acero 3.728 qq 213.92 797.49

Page 88: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 58

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

4 Madera bruta amer. (4 usos) 84.25 pt 29.00 2,443.255 Clavos corrientes (5 lb. / 100 pie madera) 16.85 lb 24.79 417.716 Clavos de acero (¼ lb / metro) 3.13 lb 45.24 141.607 Alambre calibre #14 (¼ lb. / metro) 3.13 lb 25.44 79.638 Encofrado tapas laterales 12.50 m 148.36 1,854.509 Encofrado fondo 12.50 m 51.36 642.0010 Desencofrado 12.50 m2 21.40 267.5011 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 3,761.45 4,137.60

M3 $17,923.68*HAV 10350002 H. A. VIGA 20X40, 1:2:4, 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,021.08 3,035.662 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,021.08 4,498.923 M.O. acero 3.728 qq 323.23 1,205.004 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 9,983.79 9,983.79

M3 $18,723.37*HAV 10350003 H. A. VIGA 25X50, 1:2:4, 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.967 qq 1,915.88 1,852.662 Acero ¾" grado 40 + 10% desp. 1.899 qq 1,915.88 3,638.263 M.O. acero 2.866 qq 213.92 613.094 Madera bruta amer. (4 usos) 61.51 pt 29.00 1,783.795 Clavos corrientes (5 lb. / 100 pie madera) 12.30 lb 24.79 304.926 Clavos de acero (¼ lb / metro) 2.00 lb 45.24 90.487 Alambre calibre #14 (¼ lb. / metro) 2.00 lb 25.44 50.888 Encofrado tapas laterales 8.00 m 185.45 1,483.609 Encofrado fondo 8.00 m 64.20 513.6010 Desencofrado 10.00 m2 21.40 214.0011 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 3,761.45 4,137.60

M3 $14,682.88*HAV 10350004 H. A. VIGA 25X50, 1:2:4, 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,021.08 1,954.382 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,021.08 3,838.033 M.O. acero 2.866 qq 323.23 926.384 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 8,578.87 8,578.87

M3 $15,297.66*HAV 10350005 H. A. VIGA 30X60, 1:2:4, 40, 4 DE 1", 2 DE 3/8", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.776 qq 1,915.88 1,486.722 Acero 1" grado 40 + 10% desp. 2.400 qq 1,915.88 4,598.113 M.O. acero 3.176 qq 213.92 679.414 Madera bruta amer. (4 usos) 48.02 pt 29.00 1,392.585 Clavos corrientes (5 lb. / 100 pie madera) 9.60 lb 24.79 237.986 Clavos de acero (¼ lb / metro) 1.39 lb 45.24 62.887 Alambre calibre #14 (¼ lb. / metro) 1.39 lb 25.44 35.368 Encofrado tapas laterales 5.56 m 222.54 1,237.329 Encofrado fondo 5.56 m 77.04 428.3410 Desencofrado 8.34 m2 21.40 178.4811 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 3,761.45 4,137.60

M3 $14,474.78*HAV 10350006 H. A. VIGA 30X60, 1:2:4, 60, 4 DE 1", 2 DE 3/8", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,021.08 1,568.362 Acero 1" grado 60 + 10% desp. 2.400 qq 2,021.08 4,850.593 M.O. acero 3.176 qq 323.23 1,026.584 Partidas comunes de la analizada completa anterior (4-11) 1.00 u 7,710.54 7,710.54

M3 $15,156.07*HAV 10350007 H. A. VIGA 40X80, 1:2:4, 40, 5 DE 1", 2 DE ½", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.752 qq 1,915.88 1,440.742 Acero ½" x 20' grado 40 + 10% desp. 0.162 qq 1,915.88 310.373 Acero 1" grado 40 + 10% desp. 1.689 qq 1,915.88 3,235.924 M.O. acero 2.441 qq 213.92 522.185 Madera bruta amer. (4 usos) 39.23 pt 29.00 1,137.676 Clavos corrientes (5 lb. / 100 pie madera) 7.85 lb 24.79 194.607 Clavos de acero (¼ lb / metro) 0.78 lb 45.24 35.298 Alambre calibre #14 (¼ lb. / metro) 0.78 lb 25.44 19.849 Encofrado tapas laterales 3.13 m 296.72 928.7310 Encofrado fondo 3.13 m 102.72 321.5111 Desencofrado 6.26 m2 21.40 133.9612 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 3,761.45 4,137.60

M3 $12,418.41*HAV 10350008 H. A. VIGA 40X80, 1:2:4, 40, 5 DE 1", 2 DE ½" X 25', 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.752 qq 1,915.88 1,440.742 Acero ½" x 25' grado 40 + 10% desp. 0.162 qq 1,915.88 310.373 Partidas comunes de la analizada completa anterior (3-12) 1.00 u 10,667.30 10,667.30

M3 $12,418.41*HAV 10350009 H. A. VIGA 40X80, 1:2:4, 60, 5 DE 1", 2 DE ½", 3/8" A .25, LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero 1" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 323.23 789.005 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 6,909.20 6,909.20

M3 $12,959.06*HAV 10350010 H. A. VIGA 20X40, 180 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.502 qq 1,915.88 2,877.652 Acero ¾" grado 40 + 10% desp. 2.226 qq 1,915.88 4,264.753 M.O. acero 3.728 qq 213.92 797.494 Madera bruta amer. (4 usos) 84.25 pt 29.00 2,443.255 Clavos corrientes (5 lb. / 100 pie madera) 16.85 lb 24.79 417.716 Clavos de acero (¼ lb / metro) 3.13 lb 45.24 141.607 Alambre calibre #14 (¼ lb. / metro) 3.13 lb 25.44 79.638 Encofrado tapas laterales 12.50 m 148.36 1,854.50

Page 89: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 59

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

9 Encofrado fondo 12.50 m 51.36 642.0010 Desencofrado 12.50 m2 21.40 267.5011 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $19,719.48*HAV 10350011 H. A. VIGA 20X40, 180 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 7,142.40 7,142.402 M.O. acero 3.728 qq 341.37 1,272.63

Page 90: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 60

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

3 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,779.59 11,779.59M3 $20,194.62

*HAV 10350012 H. A. VIGA 20X40, 180 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20:1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,021.08 3,035.662 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,021.08 4,498.923 M.O. acero 3.728 qq 323.23 1,205.004 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,779.59 11,779.59

M3 $20,519.17*HAV 10350013 H. A. VIGA 20X40, 180 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,021.08 3,035.662 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,021.08 4,498.923 M.O. acero 3.728 qq 341.37 1,272.634 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 11,779.59 11,779.59

M3 $20,586.80*HAV 10350014 H. A. VIGA 25X50, 180 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.967 qq 1,915.88 1,852.662 Acero ¾" grado 40 + 10% desp. 1.899 qq 1,915.88 3,638.263 M.O. acero 2.866 qq 213.92 613.094 Madera bruta amer. (4 usos) 61.51 pt 29.00 1,783.795 Clavos corrientes (5 lb. / 100 pie madera) 12.30 lb 24.79 304.926 Clavos de acero (¼ lb / metro) 2.00 lb 45.24 90.487 Alambre calibre #14 (¼ lb. / metro) 2.00 lb 25.44 50.888 Encofrado tapas laterales 8.00 m 185.45 1,483.609 Encofrado fondo 8.00 m 64.20 513.6010 Desencofrado 10.00 m2 21.40 214.0011 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $16,478.68*HAV 10350015 H. A. VIGA 20X50, 180 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 5,490.92 5,490.922 M.O. acero 2.866 qq 341.37 978.373 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,374.67 10,374.67

M3 $16,843.96*HAV 10350016 H. A. VIGA 20X50, 180 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,021.08 1,954.382 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,021.08 3,838.033 M.O. acero 2.866 qq 323.23 926.384 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,374.67 10,374.67

M3 $17,093.46*HAV 10350017 H. A. VIGA 20X50, 180 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,021.08 1,954.382 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,021.08 3,838.033 M.O. acero 2.866 qq 341.37 978.374 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,374.67 10,374.67

M3 $17,145.45*HAV 10350018 H. A. VIGA 30X60, 180 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.776 qq 1,915.88 1,486.722 Acero 1" grado 40 + 10% desp. 2.400 qq 1,915.88 4,598.113 M.O. acero 3.176 qq 213.92 679.414 Madera bruta amer. (4 usos) 48.02 pt 29.00 1,392.585 Clavos corrientes (5 lb. / 100 pie madera) 9.60 lb 24.79 237.986 Clavos de acero (¼ lb / metro) 1.39 lb 45.24 62.887 Alambre calibre #14 (¼ lb. / metro) 1.39 lb 25.44 35.368 Encofrado tapas laterales 5.56 m 222.54 1,237.329 Encofrado fondo 5.56 m 77.04 428.3410 Desencofrado 8.34 m2 21.40 178.4811 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $16,270.58*HAV 10350019 H. A. VIGA 30X60, 180 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 6,084.83 6,084.832 M.O. acero 3.176 qq 341.37 1,084.193 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,506.34 9,506.34

M3 $16,675.36*HAV 10350020 H. A. VIGA 30X60, 180 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,021.08 1,568.362 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,021.08 4,850.593 M.O. acero 3.176 qq 323.23 1,026.584 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,506.34 9,506.34

M3 $16,951.87*HAV 10350021 H. A. VIGA 30X60, 180 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,021.08 1,568.362 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,021.08 4,850.593 M.O. acero 3.176 qq 341.37 1,084.194 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,506.34 9,506.34

M3 $17,009.48*HAV 10350022 H. A. VIGA 40X80, 180 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.752 qq 1,915.88 1,440.742 Acero ½" x 20' grado 40 + 10% desp. 0.162 qq 1,915.88 310.373 Acero 1" grado 40 + 10% desp. 1.689 qq 1,915.88 3,235.924 M.O. acero 2.441 qq 213.92 522.185 Madera bruta amer. (4 usos) 39.23 pt 29.00 1,137.676 Clavos corrientes (5 lb. / 100 pie madera) 7.85 lb 24.79 194.607 Clavos de acero (¼ lb / metro) 0.78 lb 45.24 35.298 Alambre calibre #14 (¼ lb. / metro) 0.78 lb 25.44 19.849 Encofrado tapas laterales 3.13 m 296.72 928.7310 Encofrado fondo 3.13 m 102.72 321.5111 Desencofrado 6.26 m2 21.40 133.9612 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $14,214.21

Page 91: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 61

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL*HAV 10350023 H. A. VIGA 40X80, 180 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-3) 1.000 u 4,987.03 4,987.032 M.O. acero 2.441 qq 341.37 833.28

Page 92: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 62

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

3 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 8,705.00 8,705.00M3 $14,525.31

*HAV 10350024 H. A. VIGA 40X80, 180 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25:1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero 1" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 323.23 789.005 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 8,705.00 8,705.00

M3 $14,754.86*HAV 10350025 H. A. VIGA 40X80, 180 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero 1" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 341.37 833.285 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 8,705.00 8,705.00

M3 $14,799.14*HAV 10350026 H. A. VIGA 40X80, 180 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 323.23 789.005 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 8,705.00 8,705.00

M3 $14,754.86*HAV 10350027 H. A. VIGA 40X80, 180 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 341.37 833.285 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 8,705.00 8,705.00

M3 $14,799.14*HAV 10350028 H. A. VIGA 20X40, 210 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.502 qq 1,915.88 2,877.652 Acero ¾" grado 40 + 10% desp. 2.226 qq 1,915.88 4,264.753 M.O. acero 3.728 qq 213.92 797.494 Madera bruta amer. (4 usos) 84.25 pt 29.00 2,443.255 Clavos corrientes (5 lb. / 100 pie madera) 16.85 lb 24.79 417.716 Clavos de acero (¼ lb / metro) 3.13 lb 45.24 141.607 Alambre calibre #14 (¼ lb. / metro) 3.13 lb 25.44 79.638 Encofrado tapas laterales 12.50 m 148.36 1,854.509 Encofrado fondo 12.50 m 51.36 642.0010 Desencofrado 12.50 m2 21.40 267.5011 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $19,974.68*HAV 10350029 H. A. VIGA 20X40, 210 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 7,142.40 7,142.402 M.O. acero 3.728 qq 341.37 1,272.633 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,034.79 12,034.79

M3 $20,449.82*HAV 10350030 H. A. VIGA 20X40, 210 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,021.08 3,035.662 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,021.08 4,498.923 M.O. acero 3.728 qq 323.23 1,205.004 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,034.79 12,034.79

M3 $20,774.37*HAV 10350031 H. A. VIGA 20X40, 210 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,021.08 3,035.662 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,021.08 4,498.923 M.O. acero 3.728 qq 341.37 1,272.634 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,034.79 12,034.79

M3 $20,842.00*HAV 10350032 H. A. VIGA 25X50, 210 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.967 qq 1,915.88 1,852.662 Acero ¾" grado 40 + 10% desp. 1.899 qq 1,915.88 3,638.263 M.O. acero 2.866 qq 213.92 613.094 Madera bruta amer. (4 usos) 61.51 pt 29.00 1,783.795 Clavos corrientes (5 lb. / 100 pie madera) 12.30 lb 24.79 304.926 Clavos de acero (¼ lb / metro) 2.00 lb 45.24 90.487 Alambre calibre #14 (¼ lb. / metro) 2.00 lb 25.44 50.888 Encofrado tapas laterales 8.00 m 185.45 1,483.609 Encofrado fondo 8.00 m 64.20 513.6010 Desencofrado 10.00 m2 21.40 214.0011 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $16,733.88*HAV 10350033 H. A. VIGA 25X50, 210 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 5,490.92 5,490.922 M.O. acero 2.866 qq 341.37 978.373 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,629.87 10,629.87

M3 $17,099.16*HAV 10350034 H. A. VIGA 25X50, 210 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,021.08 1,954.382 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,021.08 3,838.033 M.O. acero 2.866 qq 323.23 926.384 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,629.87 10,629.87

M3 $17,348.66*HAV 10350035 H. A. VIGA 25X50, 210 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,021.08 1,954.382 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,021.08 3,838.033 M.O. acero 2.866 qq 341.37 978.37

Page 93: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 63

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

4 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,629.87 10,629.87M3 $17,400.65

*HAV 10350036 H. A. VIGA 30X60, 210 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25:1 Acero 3/8" x 20' grado 40 + 10% desp. 0.776 qq 1,915.88 1,486.722 Acero 1" grado 40 + 10% desp. 2.400 qq 1,915.88 4,598.113 M.O. acero 3.176 qq 213.92 679.414 Madera bruta amer. (4 usos) 48.02 pt 29.00 1,392.585 Clavos corrientes (5 lb. / 100 pie madera) 9.60 lb 24.79 237.986 Clavos de acero (¼ lb / metro) 1.39 lb 45.24 62.887 Alambre calibre #14 (¼ lb. / metro) 1.39 lb 25.44 35.368 Encofrado tapas laterales 5.56 m 222.54 1,237.329 Encofrado fondo 5.56 m 77.04 428.3410 Desencofrado 8.34 m2 21.40 178.4811 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $16,525.78*HAV 10350037 H. A. VIGA 30X60, 210 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 6,084.83 6,084.832 M.O. acero 3.176 qq 341.37 1,084.193 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,761.54 9,761.54

M3 $16,930.56*HAV 10350038 H. A. VIGA 30X60, 210 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,021.08 1,568.362 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,021.08 4,850.593 M.O. acero 3.176 qq 323.23 1,026.584 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,761.54 9,761.54

M3 $17,207.07*HAV 10350039 H. A. VIGA 30X60, 210 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,021.08 1,568.362 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,021.08 4,850.593 M.O. acero 3.176 qq 341.37 1,084.194 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,761.54 9,761.54

M3 $17,264.68*HAV 10350040 H. A. VIGA 40X80, 210 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.752 qq 1,915.88 1,440.742 Acero ½" x 20' grado 40 + 10% desp. 0.162 qq 1,915.88 310.373 Acero 1" grado 40 + 10% desp. 1.689 qq 1,915.88 3,235.924 M.O. acero 2.441 qq 213.92 522.185 Madera bruta amer. (4 usos) 39.23 pt 29.00 1,137.676 Clavos corrientes (5 lb. / 100 pie madera) 7.85 lb 24.79 194.607 Clavos de acero (¼ lb / metro) 0.78 lb 45.24 35.298 Alambre calibre #14 (¼ lb. / metro) 0.78 lb 25.44 19.849 Encofrado tapas laterales 3.13 m 296.72 928.7310 Encofrado fondo 3.13 m 102.72 321.5111 Desencofrado 6.26 m2 21.40 133.9612 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $14,469.41*HAV 10350041 H. A. VIGA 40X80, 210 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-3) 1.000 u 4,987.03 4,987.032 M.O. acero 2.441 qq 341.37 833.283 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 8,960.20 8,960.20

M3 $14,780.51*HAV 10350042 H. A. VIGA 40X80, 210 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero 1" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 323.23 789.005 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 8,960.20 8,960.20

M3 $15,010.06*HAV 10350043 H. A. VIGA 40X80, 210 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero 1" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 341.37 833.285 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 8,960.20 8,960.20

M3 $15,054.34*HAV 10350044 H. A. VIGA 40X80, 210 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 323.23 789.005 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 8,960.20 8,960.20

M3 $15,010.06*HAV 10350045 H. A. VIGA 40X80, 210 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 341.37 833.285 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 8,960.20 8,960.20

M3 $15,054.34*HAV 10350046 H. A. VIGA 20X40, 240 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.502 qq 1,915.88 2,877.652 Acero ¾" grado 40 + 10% desp. 2.226 qq 1,915.88 4,264.753 M.O. acero 3.728 qq 213.92 797.494 Madera bruta amer. (4 usos) 84.25 pt 29.00 2,443.255 Clavos corrientes (5 lb. / 100 pie madera) 16.85 lb 24.79 417.716 Clavos de acero (¼ lb / metro) 3.13 lb 45.24 141.607 Alambre calibre #14 (¼ lb. / metro) 3.13 lb 25.44 79.638 Encofrado tapas laterales 12.50 m 148.36 1,854.50

Page 94: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 64

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

9 Encofrado fondo 12.50 m 51.36 642.0010 Desencofrado 12.50 m2 21.40 267.5011 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $20,229.88*HAV 10350047 H. A. VIGA 20X40, 240 kg/Cm², 40, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 7,142.40 7,142.402 M.O. acero 3.728 qq 341.37 1,272.63

Page 95: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 65

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

3 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,289.99 12,289.99M3 $20,705.02

*HAV 10350048 H. A. VIGA 20X40, 240 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20:1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,021.08 3,035.662 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,021.08 4,498.923 M.O. acero 3.728 qq 323.23 1,205.004 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,289.99 12,289.99

M3 $21,029.57*HAV 10350049 H. A. VIGA 20X40, 240 kg/Cm², 60, 3 DE ¾", 2 DE 3/8", 3/8" A .20: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.502 qq 2,021.08 3,035.662 Acero ¾" grado 60 + 10% desp. 2.226 qq 2,021.08 4,498.923 M.O. acero 3.728 qq 341.37 1,272.634 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 12,289.99 12,289.99

M3 $21,097.20*HAV 10350050 H. A. VIGA 25X50, 240 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.967 qq 1,915.88 1,852.662 Acero ¾" grado 40 + 10% desp. 1.899 qq 1,915.88 3,638.263 M.O. acero 2.866 qq 213.92 613.094 Madera bruta amer. (4 usos) 61.51 pt 29.00 1,783.795 Clavos corrientes (5 lb. / 100 pie madera) 12.30 lb 24.79 304.926 Clavos de acero (¼ lb / metro) 2.00 lb 45.24 90.487 Alambre calibre #14 (¼ lb. / metro) 2.00 lb 25.44 50.888 Encofrado tapas laterales 8.00 m 185.45 1,483.609 Encofrado fondo 8.00 m 64.20 513.6010 Desencofrado 10.00 m2 21.40 214.0011 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $16,989.08*HAV 10350051 H. A. VIGA 25X50, 240 kg/Cm², 40, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 5,490.92 5,490.922 M.O. acero 2.866 qq 341.37 978.373 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,885.07 10,885.07

M3 $17,354.36*HAV 10350052 H. A. VIGA 25X50, 240 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,021.08 1,954.382 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,021.08 3,838.033 M.O. acero 2.866 qq 323.23 926.384 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,885.07 10,885.07

M3 $17,603.86*HAV 10350053 H. A. VIGA 25X50, 240 kg/Cm², 60, 4 DE ¾", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.967 qq 2,021.08 1,954.382 Acero ¾" grado 60 + 10% desp. 1.899 qq 2,021.08 3,838.033 M.O. acero 2.866 qq 341.37 1,519.854 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,885.07 10,885.07

M3 $18,197.33*HAV 10350054 H. A. VIGA 30X60, 240 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.776 qq 1,915.88 1,486.722 Acero 1" grado 40 + 10% desp. 2.400 qq 1,915.88 4,598.113 M.O. acero 3.176 qq 213.92 679.414 Madera bruta amer. (4 usos) 48.02 pt 29.00 1,392.585 Clavos corrientes (5 lb. / 100 pie madera) 9.60 lb 24.79 237.986 Clavos de acero (¼ lb / metro) 1.39 lb 45.24 62.887 Alambre calibre #14 (¼ lb. / metro) 1.39 lb 25.44 35.368 Encofrado tapas laterales 5.56 m 222.54 1,237.329 Encofrado fondo 5.56 m 77.04 428.3410 Desencofrado 8.34 m2 21.40 178.4811 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $16,780.98*HAV 10350055 H. A. VIGA 30X60, 240 kg/Cm², 40, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-2) 1.000 u 6,084.83 6,084.832 M.O. acero 3.176 qq 341.37 1,084.193 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,016.74 10,016.74

M3 $17,185.76*HAV 10350056 H. A. VIGA 30X60, 240 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,021.08 1,568.362 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,021.08 4,850.593 M.O. acero 3.176 qq 323.23 1,026.584 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,016.74 10,016.74

M3 $17,462.27*HAV 10350057 H. A. VIGA 30X60, 240 kg/Cm², 60, 4 DE 1", 2 DE 3/8", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.776 qq 2,021.08 1,568.362 Acero ¾" grado 60 + 10% desp. 2.400 qq 2,021.08 4,850.593 M.O. acero 3.176 qq 341.37 1,084.194 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 10,016.74 10,016.74

M3 $17,519.88*HAV 10350058 H. A. VIGA 40X80, 240 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25:

1 Acero 3/8" x 20' grado 40 + 10% desp. 0.752 qq 1,915.88 1,440.742 Acero ½" x 20' grado 40 + 10% desp. 0.162 qq 1,915.88 310.373 Acero 1" grado 40 + 10% desp. 1.689 qq 1,915.88 3,235.924 M.O. acero 2.441 qq 213.92 522.185 Madera bruta amer. (4 usos) 39.23 pt 29.00 1,137.676 Clavos corrientes (5 lb. / 100 pie madera) 7.85 lb 24.79 194.607 Clavos de acero (¼ lb / metro) 0.78 lb 45.24 35.298 Alambre calibre #14 (¼ lb. / metro) 0.78 lb 25.44 19.849 Encofrado tapas laterales 3.13 m 296.72 928.7310 Encofrado fondo 3.13 m 102.72 321.5111 Desencofrado 6.26 m2 21.40 133.9612 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $14,724.61

Page 96: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 66

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL*HAV 10350059 H. A. VIGA 40X80, 240 kg/Cm², 40, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Partidas comunes de la analizada completa anterior (1-3) 1.000 u 4,987.03 4,987.032 M.O. acero 2.441 qq 341.37 833.28

Page 97: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 67

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

3 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,215.40 9,215.40M3 $15,035.71

*HAV 10350060 H. A. VIGA 40X80, 240 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25:1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero 1" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 323.23 789.005 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,215.40 9,215.40

M3 $15,265.26*HAV 10350061 H. A. VIGA 40X80, 240 kg/Cm², 60, 5 DE 1", 2 DE ½", 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 20' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero 1" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 341.37 833.285 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,215.40 9,215.40

M3 $15,309.54*HAV 10350062 H. A. VIGA 40X80, 240 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25:

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 323.23 789.005 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,215.40 9,215.40

M3 $15,265.26*HAV 10350063 H. A. VIGA 40X80, 240 kg/Cm², 60, 5 DE 1", 2 DE ½" x 25', 3/8" A .25: PORTICO

1 Acero 3/8" x 20' grado 60 + 10% desp. 0.752 qq 2,021.08 1,519.852 Acero ½" x 25' grado 60 + 10% desp. 0.162 qq 2,021.08 327.413 Acero ¾" grado 60 + 10% desp. 1.689 qq 2,021.08 3,413.604 M.O. acero 2.441 qq 341.37 833.285 Partidas comunes de la analizada completa anterior (5-12) 1.00 u 9,215.40 9,215.40

M3 $15,309.54

*HAVA 10370000 HORM. ARMADO VIGAS AMARRE

*HAVA 10370001 VIGA AMARRE 15x20, 1:2:4, 4 DE 3/8" grado 40, ¼" A 20, LIG.:1 Acero ¼" + 10% desp. 0.779 qq 1,088.60 848.022 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 1,915.88 3,638.263 M.O. acero 33.33 m 71.30 2,376.434 Madera bruta amer. (4 usos) 97.97 pt 29.00 2,841.135 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 24.79 485.646 Clavos de acero (¼ lb / metro) 8.33 lb 45.24 376.857 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 25.44 211.928 Confección e instalación de madera 33.33 m 106.98 3,565.649 Desencofrado 13.33 m2 21.40 285.2610 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $18,558.71*HAVA 10370002 VIGA AMARRE 15x20, 1:2:4, 4 DE 3/8" grado 40, ¼" A 20 A MANO:

1 Acero ¼" + 10% desp. 0.779 qq 1,088.60 848.022 Acero 3/8" x 20' grado 40 + 10% desp. 1.899 qq 1,915.88 3,638.263 M.O. acero 33.33 m 71.30 2,376.434 Madera bruta amer. (4 usos) 97.97 pt 29.00 2,841.135 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 24.79 485.646 Clavos de acero (¼ lb / metro) 8.33 lb 45.24 376.857 Alambre calibre #14 (¼ lb. / metro) 8.33 lb 25.44 211.928 Confección e instalación de madera 33.33 m 106.98 3,565.649 Desencofrado 13.33 m2 21.40 285.2610 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $18,989.46*HAVA 10370003 VIGA AMARRE 20x20, 1:2:4, 4 DE 3/8", 3/8" A .20 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 10% desp. 2.781 qq 1,915.88 5,328.062 M.O. acero 25.00 m 71.30 1,782.503 Madera bruta amer. (4 usos) 97.97 pt 29.00 2,841.134 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 24.79 485.645 Clavos de acero (¼ lb / metro) 6.25 lb 45.24 282.756 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 25.44 159.007 Confección e instalación de madera 25.00 m 106.98 2,674.508 Desencofrado 10.00 m2 21.40 214.009 Horm. 1:2:4, lig. + 10% desp. 1.10 m3 3,572.33 3,929.56

M3 $17,697.14*HAVA 10370004 VIGA AMARRE 20x20, 1:2:4, 4 DE 3/8", 3/8" A .20 grado 40 A MANO:

1 Acero 3/8" x 20' grado 40 + 10% desp. 2.781 qq 1,915.88 5,328.062 M.O. acero 25.00 m 71.30 1,782.503 Madera bruta amer. (4 usos) 97.97 pt 29.00 2,841.134 Clavos corrientes (5 lb. / 100 pie madera) 19.59 lb 24.79 485.645 Clavos de acero (¼ lb / metro) 6.25 lb 45.24 282.756 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 25.44 159.007 Confección e instalación de madera 25.00 m 106.98 2,674.508 Desencofrado 10.00 m2 21.40 214.009 Horm. 1:2:4 a mano + 10% desp. 1.10 m3 3,963.92 4,360.31

M3 $18,127.89

*HAVUE 10390000 HORM. ARMADO VUELOS (NO CONTINUA DEL FALSO PISO)

*HAVUE 10390001 VUELOS .40x.10, 1:2:4, 40, 3/8" A .20 + 2 DE 3/8", LIG. Y WINCHE:1 Acero 3/8" x 20' grado 40 + 10% desp. 1.857 qq 1,915.88 3,557.792 M.O. acero 1.857 qq 213.92 397.253 Subida acero 1.857 qq 21.39 39.724 Madera bruta amer. (4 usos) 106.34 pt 29.00 3,083.865 Clavos corrientes (5 lb. / 100 pie madera) 21.27 lb 24.79 527.28

Page 98: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 68

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

6 Clavos de acero (¼ lb / metro) 6.25 lb 45.24 282.757 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 25.44 159.008 Confección e instalación de madera 25.00 m 148.36 3,709.009 Desencofrado 10.00 m2 22.82 228.2010 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 3,761.45 4,137.60

M3 $16,122.45*HAVUE 10390002 VUELOS .40x.10, 1:2:4, 40, 3/8" x 25' A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.857 qq 1,915.88 3,557.792 Partidas comunes de la analizada completa anterior (2-10) 1.00 u 12,564.66 12,564.66

M3 $16,122.45*HAVUE 10390003 VUELOS .40x.10, 1:2:4, 60, 3/8" A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.857 qq 2,021.08 3,753.152 M.O. acero 1.857 qq 323.23 600.243 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 12,167.41 12,167.41

M3 $16,520.80*HAVUE 10390004 VUELOS .40x.10, 1:2:4, 60, 3/8" x 25' A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.857 qq 2,021.08 3,753.152 M.O. acero 1.857 qq 323.23 600.243 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 12,167.41 12,167.41

M3 $16,520.80*HAVUE 10390005 VUELOS .40x.12, 1:2:4, 40, 3/8" A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.548 qq 1,915.88 2,965.782 M.O. acero 1.548 qq 213.92 331.153 Subida acero 1.548 qq 21.39 33.114 Madera bruta amer. (4 usos) 90.62 pt 29.00 2,627.985 Clavos corrientes (5 lb. / 100 pie madera) 18.12 lb 24.79 449.196 Clavos de acero (¼ lb / metro) 5.21 lb 45.24 235.707 Alambre calibre #14 (¼ lb. / metro) 5.21 lb 25.44 132.548 Confección e instalación de madera 20.83 m 148.36 3,090.349 Desencofrado 8.33 m2 22.82 190.1410 Horm. 1:2:4 lig. y winche + 10% desp. 1.10 m3 3,761.45 4,137.60

M3 $14,193.53*HAVUE 10390006 VUELOS .40x.12, 1:2:4, 40, 3/8" x 25' A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.548 qq 1,915.88 2,965.782 Partidas comunes de la analizada completa anterior (2-10) 1.00 u 11,227.75 11,227.75

M3 $14,193.53*HAVUE 10390007 VUELOS .40x.12, 1:2:4, 60, 3/8" A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.548 qq 2,021.08 3,128.632 M.O. acero 1.548 qq 323.23 500.363 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 10,896.60 10,896.60

M3 $14,525.59*HAVUE 10390008 VUELOS .40x.12, 1:2:4, 60, 3/8" x 25' A .20 + 2 DE 3/8", LIG. Y WINCHE:

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.548 qq 2,021.08 3,128.632 M.O. acero 1.548 qq 323.23 500.363 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 10,896.60 10,896.60

M3 $14,525.59*HAVUE 10390009 VUELOS .40x.10, 180 kg/Cm², 40, 3/8" A .20 + 2 DE 3/8" :

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.857 qq 1,915.88 3,557.792 M.O. acero 1.857 qq 213.92 397.253 Subida acero 1.857 qq 21.39 39.724 Madera bruta amer. (4 usos) 106.34 pt 29.00 3,083.865 Clavos corrientes (5 lb. / 100 pie madera) 21.27 lb 24.79 527.286 Clavos de acero (¼ lb / metro) 6.25 lb 45.24 282.757 Alambre calibre #14 (¼ lb. / metro) 6.25 lb 25.44 159.008 Confección e instalación de madera 25.00 m 148.36 3,709.009 Desencofrado 10.00 m2 22.82 228.2010 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $17,918.25*HAVUE 10390010 VUELOS .40x.10, 180 kg/Cm², 40, 3/8" x 25' A .20 + 2 DE 3/8":

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.857 qq 1,915.88 3,557.792 Partidas comunes de la analizada completa anterior (2-10) 1.00 u 14,360.46 14,360.46

M3 $17,918.25*HAVUE 10390011 VUELOS .40x.10, 180 kg/Cm², 60, 3/8" A .20 + 2 DE 3/8":

1 Acero 3/8" x 20' grado 60 + 10% desp. 1.857 qq 2,021.08 3,753.152 M.O. acero 1.857 qq 323.23 600.243 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 13,963.21 13,963.21

M3 $18,316.60*HAVUE 10390012 VUELOS .40x.10, 180 kg/Cm², 60, 3/8" x 25' A .20 + 2 DE 3/8":

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.857 qq 2,021.08 3,753.152 M.O. acero 1.857 qq 323.23 600.243 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 13,963.21 13,963.21

M3 $18,316.60*HAVUE 10390013 VUELOS .40x.12, 180 kg/Cm², 40, 3/8" A .20 + 2 DE 3/8":

1 Acero 3/8" x 20' grado 40 + 10% desp. 1.548 qq 1,915.88 2,965.782 M.O. acero 1.548 qq 213.92 331.153 Subida acero 1.548 qq 21.39 33.114 Madera bruta amer. (4 usos) 90.62 pt 29.00 2,627.985 Clavos corrientes (5 lb. / 100 pie madera) 18.12 lb 24.79 449.196 Clavos de acero (¼ lb / metro) 5.21 lb 45.24 235.707 Alambre calibre #14 (¼ lb. / metro) 5.21 lb 25.44 132.548 Confección e instalación de madera 20.83 m 148.36 3,090.349 Desencofrado 8.33 m2 22.82 190.1410 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $15,989.33*HAVUE 10390014 VUELOS .40x.12, 180 kg/Cm², 40, 3/8" x 25' A .20 + 2 DE 3/8", :

1 Acero 3/8" x 25' grado 40 + 10% desp. 1.548 qq 1,915.88 2,965.782 Partidas comunes de la analizada completa anterior (2-10) 1.00 u 13,023.55 13,023.55

M3 $15,989.33

Page 99: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 69

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HAVUE 10390015 VUELOS .40x.12, 180 kg/Cm², 60, 3/8" A .20 + 2 DE 3/8", :1 Acero 3/8" x 20' grado 60 + 10% desp. 1.548 qq 2,021.08 3,128.632 M.O. acero 1.548 qq 323.23 500.363 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 12,692.40 12,692.40

M3 $16,321.39*HAVUE 10390016 VUELOS .40x.12, 180 kg/Cm², 60, 3/8" x 25' A .20 + 2 DE 3/8":

1 Acero 3/8" x 25' grado 60 + 10% desp. 1.548 qq 2,021.08 3,128.632 M.O. acero 1.548 qq 323.23 500.363 Partidas comunes de la analizada completa anterior (3-10) 1.00 u 12,692.40 12,692.40

M3 $16,321.39

*HAZAPC1 10410000 HORM. ARMADO ZAP. COLUMNAS (1 CAMADA ACERO)

*HAZAPC1 10410001 ZAP. COL., 1.2x1.2, 1:3:5, 40, 8 DE ½" A.D., LIG.:ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"

1 Acero ½" x 20' grado 40 + 5% desp. 1.299 qq 1,915.88 2,488.732 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 1,915.88 839.163 M.O. acero 1.737 qq 213.92 371.584 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $6,934.67*HAZAPC1 10410002 ZAP. COL., 1.2x1.2, 1:3:5, 40, 8 DE ½" x 25' A.D., LIG.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 1.299 qq 1,915.88 2,488.732 Acero ¾" grado 40 + 5% desp. 0.438 qq 1,915.88 839.163 M.O. acero 1.737 qq 213.92 371.584 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $6,934.67*HAZAPC1 10410003 ZAP. COL., 1.2x1.2, 1:3:5, 60, 8 DE ½" A.D., LIG.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 + 5% desp. 1.299 qq 2,021.08 2,625.382 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,021.08 885.233 M.O. acero 1.737 qq 323.23 561.454 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $7,307.26*HAZAPC1 10410004 ZAP. COL., 1.2x1.2, 1:3:5, 60, 8 DE ½" x 25' A.D., LIG.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 + 5% desp. 1.299 qq 2,021.08 2,625.382 Acero ¾" grado 60 + 5% desp. 0.438 qq 2,021.08 885.233 M.O. acero 1.737 qq 323.23 561.454 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $7,307.26*HAZAPC1 10410005 ZAP. COL., 1.2x1.2, 1:3:5, 40, 8 DE ½" A.D., LIG.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 0.974 qq 1,915.88 1,866.072 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 1,915.88 722.293 M.O. acero 1.351 qq 213.92 289.014 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $6,112.57*HAZAPC1 10410006 ZAP. COL., 1.2x1.2, 1:3:5, 40, 8 DE ½" x 25' A.D., LIG.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 0.974 qq 1,915.88 1,866.072 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 1,915.88 722.293 M.O. acero 1.351 qq 213.92 289.014 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $6,112.57*HAZAPC1 10410007 ZAP. COL., 1.2x1.2, 1:3:5, 60, 8 DE ½" A.D., LIG.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 + 5% desp. 0.974 qq 2,021.08 1,968.532 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,021.08 761.953 M.O. acero 1.351 qq 323.23 436.684 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $6,402.36*HAZAPC1 10410008 ZAP. COL., 1.2x1.2, 1:3:5, 60, 8 DE ½" x 25' A.D., LIG.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 + 5% desp. 0.974 qq 2,021.08 1,968.532 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,021.08 761.953 M.O. acero 1.351 qq 323.23 436.684 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $6,402.36*HAZAPC1 10410009 ZAP. COL., 1.2x1.2, 140, 40, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" y ¾" grado 40 + 5% desp. 1.299 qq 1,915.88 2,488.732 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 1,915.88 839.163 M.O. acero 1.737 qq 213.92 371.584 Horm. 140 Kg/Cm² 1.00 m3 5,614.40 5,614.40

M3 $9,313.87*HAZAPC1 10410010 ZAP. COL., 1.2x1.2, 140, 40, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 1.299 qq 1,915.88 2,488.732 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 1,915.88 839.163 M.O. acero 1.737 qq 213.92 371.584 Horm. 140 Kg/Cm² 1.00 m3 5,614.40 5,614.40

M3 $9,313.87*HAZAPC1 10410011 ZAP. COL., 1.2x1.2, 140, 60, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" y ¾" grado 60 + 5% desp. 1.299 qq 2,021.08 2,625.382 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,021.08 885.233 M.O. acero 1.737 qq 323.23 561.45

Page 100: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 70

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

4 Horm. 140 Kg/Cm² 1.00 m3 5,742.00 5,742.00M3 $9,814.06

*HAZAPC1 10410012 ZAP. COL., 1.2x1.2, 140, 60, 8 DE ½" x 25' A.D.:ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"

1 Acero ½" x 25' grado 60 + 5% desp. 1.299 qq 2,021.08 2,625.382 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,021.08 885.233 M.O. acero 1.737 qq 323.23 561.454 Horm. 140 Kg/Cm² 1.00 m3 5,742.00 5,742.00

M3 $9,814.06*HAZAPC1 10410013 ZAP. COL., 1.2x1.2, 140, 40, 8 DE ½" A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 0.974 qq 1,915.88 1,866.072 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 1,915.88 722.293 M.O. acero 1.351 qq 213.92 289.014 Horm. 140 Kg/Cm² 1.00 m3 5,614.40 5,614.40

M3 $8,491.77*HAZAPC1 10410014 ZAP. COL., 1.2x1.2, 140, 40, 8 DE ½" x 25' A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 0.974 qq 1,915.88 1,866.072 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 1,915.88 722.293 M.O. acero 1.351 qq 213.92 289.014 Horm. 140 Kg/Cm² 1.00 m3 5,614.40 5,614.40

M3 $8,491.77*HAZAPC1 10410015 ZAP. COL., 1.2x1.2, 140, 60, 8 DE ½" A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 0.974 qq 2,021.08 1,968.532 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,021.08 761.953 M.O. acero 1.351 qq 323.23 436.684 Horm. 140 Kg/Cm² 1.00 m3 5,742.00 5,742.00

M3 $8,909.16*HAZAPC1 10410016 ZAP. COL., 1.2x1.2, 140, 60, 8 DE ½" x 25' A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 0.974 qq 2,021.08 1,968.532 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,021.08 761.953 M.O. acero 1.351 qq 323.23 436.684 Horm. 140 Kg/Cm² 1.00 m3 5,742.00 5,742.00

M3 $8,909.16*HAZAPC1 10410017 ZAP. COL., 1.2x1.2, 180, 40, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 1.299 qq 1,915.88 2,488.732 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 1,915.88 839.163 M.O. acero 1.737 qq 213.92 371.584 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $9,632.87*HAZAPC1 10410018 ZAP. COL., 1.2x1.2, 180, 40, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 1.299 qq 1,915.88 2,488.732 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 1,915.88 839.163 M.O. acero 1.737 qq 213.92 371.584 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $9,632.87*HAZAPC1 10410019 ZAP. COL., 1.2x1.2, 180, 60, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 1.299 qq 2,021.08 2,625.382 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,021.08 885.233 M.O. acero 1.737 qq 323.23 561.454 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $10,005.46*HAZAPC1 10410020 ZAP. COL., 1.2x1.2, 180, 60, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 1.299 qq 2,021.08 2,625.382 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,021.08 885.233 M.O. acero 1.737 qq 323.23 561.454 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $10,005.46*HAZAPC1 10410021 ZAP. COL., 1.2x1.2, 180, 40, 8 DE ½" A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 0.974 qq 1,915.88 1,866.072 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 1,915.88 722.293 M.O. acero 1.351 qq 213.92 289.014 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $8,810.77*HAZAPC1 10410022 ZAP. COL., 1.2x1.2, 180, 40, 8 DE ½" x 25' A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 0.974 qq 1,915.88 1,866.072 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 1,915.88 722.293 M.O. acero 1.351 qq 213.92 289.014 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $8,810.77*HAZAPC1 10410023 ZAP. COL., 1.2x1.2, 180, 60, 8 DE ½" A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 0.974 qq 2,021.08 1,968.532 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,021.08 761.953 M.O. acero 1.351 qq 323.23 436.684 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $9,100.56*HAZAPC1 10410024 ZAP. COL., 1.2x1.2, 180, 60, 8 DE ½" x 25' A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"

Page 101: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 71

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 0.974 qq 2,021.08 1,968.532 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,021.08 761.953 M.O. acero 1.351 qq 323.23 436.684 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $9,100.56*HAZAPC1 10410025 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 40, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 1.299 qq 1,915.88 2,488.732 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 1,915.88 839.163 M.O. acero 1.737 qq 213.92 371.584 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $9,888.07*HAZAPC1 10410026 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 40, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 1.299 qq 1,915.88 2,488.732 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 1,915.88 839.163 M.O. acero 1.737 qq 213.92 371.584 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $9,888.07*HAZAPC1 10410027 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 60, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 1.299 qq 2,021.08 2,625.382 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,021.08 885.233 M.O. acero 1.737 qq 323.23 561.454 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $10,260.66*HAZAPC1 10410028 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 60, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 1.299 qq 2,021.08 2,625.382 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,021.08 885.233 M.O. acero 1.737 qq 323.23 561.454 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $10,260.66*HAZAPC1 10410029 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 40, 8 DE ½" A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 0.974 qq 1,915.88 1,866.072 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 1,915.88 722.293 M.O. acero 1.351 qq 213.92 289.014 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $9,065.97*HAZAPC1 10410030 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 40, 8 DE ½" x 25' A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 0.974 qq 1,915.88 1,866.072 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 1,915.88 722.293 M.O. acero 1.351 qq 213.92 289.014 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $9,065.97*HAZAPC1 10410031 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 60, 8 DE ½" A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 0.974 qq 2,021.08 1,968.532 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,021.08 761.953 M.O. acero 1.351 qq 323.23 436.684 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $9,355.76*HAZAPC1 10410032 ZAP. COL., 1.2x1.2, 210 Kg/Cm², 60, 8 DE ½" x 25' A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 0.974 qq 2,021.08 1,968.532 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,021.08 761.953 M.O. acero 1.351 qq 323.23 436.684 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $9,355.76*HAZAPC1 10410033 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 40, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 1.299 qq 1,915.88 2,488.732 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 1,915.88 839.163 M.O. acero 1.737 qq 213.92 371.584 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $10,143.27*HAZAPC1 10410034 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 40, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 1.299 qq 1,915.88 2,488.732 Acero ¾" x 20' grado 40 + 5% desp. 0.438 qq 1,915.88 839.163 M.O. acero 1.737 qq 213.92 371.584 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $10,143.27*HAZAPC1 10410035 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 60, 8 DE ½" A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 1.299 qq 2,021.08 2,625.382 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,021.08 885.233 M.O. acero 1.737 qq 323.23 561.454 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $10,515.86*HAZAPC1 10410036 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 60, 8 DE ½" x 25' A.D.:

ESPESOR = .30 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 1.299 qq 2,021.08 2,625.382 Acero ¾" x 20' grado 60 + 5% desp. 0.438 qq 2,021.08 885.233 M.O. acero 1.737 qq 323.23 561.454 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

Page 102: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 72

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

M3 $10,515.86*HAZAPC1 10410037 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 40, 8 DE ½" A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 40 y ¾" + 5% desp. 0.974 qq 1,915.88 1,866.072 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 1,915.88 722.293 M.O. acero 1.351 qq 213.92 289.014 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $9,321.17*HAZAPC1 10410038 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 40, 8 DE ½" x 25' A.D.:

ESPESOR = .40 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 40 y ¾" + 5% desp. 0.974 qq 1,915.88 1,866.072 Acero ¾" x 20' grado 40 + 5% desp. 0.377 qq 1,915.88 722.293 M.O. acero 1.351 qq 213.92 289.014 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $9,321.17*HAZAPC1 10410039 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 60, 8 DE ½" A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 20' grado 60 y ¾" + 5% desp. 0.974 qq 2,021.08 1,968.532 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,021.08 761.953 M.O. acero 1.351 qq 323.23 436.684 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $9,610.96*HAZAPC1 10410040 ZAP. COL., 1.2x1.2, 240 Kg/Cm², 60, 8 DE ½" x 25' A.D.:

ESPESOR = .60 MT. ACERO COL.: 6 DE ¾"1 Acero ½" x 25' grado 60 y ¾" + 5% desp. 0.974 qq 2,021.08 1,968.532 Acero ¾" x 20' grado 60 + 5% desp. 0.377 qq 2,021.08 761.953 M.O. acero 1.351 qq 323.23 436.684 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $9,610.96

*HAZAPC2 10430000 HORM. ARMADO ZAP. COLUMNAS (2 CAMADAS ACERO)

*HAZAPC2 10430001 ZAP. COL., 2.15x2.80, 180, 40, 20 DE ½", 17 DE ½" X 20', 2 CAM.:ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"

1 Acero ½" x 20' grado 40 + 5% desp. 2.737 qq 1,915.88 5,243.762 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 1,915.88 716.543 M.O. acero 3.111 qq 213.92 665.514 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $12,559.21*HAZAPC2 10430002 ZAP. COL., 2.15x2.80, 180, 40, 20 DE ½", 17 DE ½" x 25', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 2.737 qq 1,915.88 5,243.762 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 1,915.88 716.543 M.O. acero 3.111 qq 213.92 665.514 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $12,559.21*HAZAPC2 10430003 ZAP. COL., 2.15x2.80, 180, 60, 20 DE ½", 17 DE ½" X 20', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 20' grado 60 + 5% desp. 2.737 qq 2,021.08 5,531.702 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,021.08 755.883 M.O. acero 3.111 qq 323.23 1,005.574 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $13,226.55*HAZAPC2 10430004 ZAP. COL., 2.15x2.80, 180, 60, 20 DE ½", 17 DE ½" x 25', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 25' grado 60 + 5% desp. 2.737 qq 2,021.08 5,531.702 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,021.08 755.883 M.O. acero 3.111 qq 323.23 1,005.574 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $13,226.55*HAZAPC2 10430005 ZAP. COL., 2.15x2.80, 210 Kg/Cm², 40, 20 DE ½", 17 DE ½" X 20', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 20' grado 40 + 5% desp. 2.737 qq 1,915.88 5,243.762 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 1,915.88 716.543 M.O. acero 3.111 qq 213.92 665.514 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $12,814.41*HAZAPC2 10430006 ZAP. COL., 2.15x2.80, 210 Kg/Cm², 40, 20 DE ½", 17 DE ½" x 25', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 2.737 qq 1,915.88 5,243.762 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 1,915.88 716.543 M.O. acero 3.111 qq 213.92 665.514 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $12,814.41*HAZAPC2 10430007 ZAP. COL., 2.15x2.80, 210 Kg/Cm², 60, 20 DE ½", 17 DE ½" X 20', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 20' grado 60 + 5% desp. 2.737 qq 2,021.08 5,531.702 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,021.08 755.883 M.O. acero 3.111 qq 323.23 1,005.574 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $13,481.75*HAZAPC2 10430008 ZAP. COL., 2.15x2.80, 210 Kg/Cm², 60, 20 DE ½", 17 DE ½" x 25', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 25' grado 60 + 5% desp. 2.737 qq 2,021.08 5,531.702 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,021.08 755.883 M.O. acero 3.111 qq 323.23 1,005.574 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $13,481.75

Page 103: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 73

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HAZAPC2 10430009 ZAP. COL., 2.15x2.80, 240 Kg/Cm², 40, 20 DE ½", 17 DE ½" X 20', 2 CAM.:ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"

1 Acero ½" x 20' grado 40 + 5% desp. 2.737 qq 1,915.88 5,243.762 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 1,915.88 716.543 M.O. acero 3.111 qq 213.92 665.514 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $13,069.61*HAZAPC2 10430010 ZAP. COL., 2.15x2.80, 240 Kg/Cm², 40, 20 DE ½", 17 DE ½" x 25', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 25' grado 40 + 5% desp. 2.737 qq 1,915.88 5,243.762 Acero ¾" x 20' grado 40 + 5% desp. 0.374 qq 1,915.88 716.543 M.O. acero 3.111 qq 213.92 665.514 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $13,069.61*HAZAPC2 10430011 ZAP. COL., 2.15x2.80, 240 Kg/Cm², 60, 20 DE ½", 17 DE ½" X 20', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 20' grado 60 + 5% desp. 2.737 qq 2,021.08 5,531.702 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,021.08 755.883 M.O. acero 3.111 qq 323.23 1,005.574 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $13,736.95*HAZAPC2 10430012 ZAP. COL., 2.15x2.80, 240 Kg/Cm², 60, 20 DE ½", 17 DE ½" x 25', 2 CAM.:

ESPESOR = .35 MT. ACERO COL.: 18 DE ¾"1 Acero ½" x 25' grado 60 + 5% desp. 2.737 qq 2,021.08 5,531.702 Acero ¾" x 20' grado 60 + 5% desp. 0.374 qq 2,021.08 755.883 M.O. acero 3.111 qq 323.23 1,005.574 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $13,736.95

*HAZAPM1 10450000 HORMIGON ARMADO ZAPATAS DE MUROS (1 CAMADA ACERO)

*HAZAPM1 10450001 ZAP. MURO, 30x20, 1:3:5, 2 DE 3/8", 3/8" A .25 grado 40, LIG.:1 Acero ¼" (bastones) + 5% desp. 0.0479 qq 1,088.60 52.142 Acero 3/8" x 20' grado 40 + 5% desp. 0.8082 qq 1,915.88 1,548.413 M.O. acero 16.6670 m 71.30 1,188.364 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $6,024.11*HAZAPM1 10450002 ZAP. MURO, 45x20, 1:3:5, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.8747 qq 1,915.88 1,675.822 M.O. acero 11.1110 m 71.30 792.213 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $5,703.23*HAZAPM1 10450003 ZAP. MURO, 45x25, 1:3:5, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.7130 qq 1,915.88 1,366.022 M.O. acero 8.8890 m 71.30 633.793 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $5,235.01*HAZAPM1 10450004 ZAP. MURO, 60x25, 1:3:5, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.5912 qq 1,915.88 1,132.672 M.O. acero 6.6670 m 71.30 475.363 Horm. 1:3:5, lig. + 2% desp. 1.02 m3 3,171.76 3,235.20

M3 $4,843.23*HAZAPM1 10450005 ZAP. MURO, 20x15, 1:2:4, 2 DE 3/8", 3/8" A .30 grado 40, LIG., para Bordillos:

1 Acero ¼" (bastones) + 5% desp. 0.0766 qq 1,088.60 83.392 Acero 3/8" x 20' grado 40 + 5% desp. 1.3632 qq 1,915.88 2,611.733 M.O. acero 33.3330 m 71.30 2,376.644 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 3,572.33 3,643.78

M3 $8,632.15*HAZAPM1 10450006 ZAP. MURO, 30x15, 1:2:4, 2 DE 3/8", 3/8" A .30 grado 40, LIG., para Bordillos:

1 Acero 3/8" (bastones) + 5% desp. 0.1338 qq 1,915.88 256.342 Acero 3/8" x 20' grado 40 + 5% desp. 1.0070 qq 1,915.88 1,929.293 M.O. acero 22.2220 m 71.30 1,584.434 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 3,572.33 3,643.78

M3 $7,157.50*HAZAPM1 10450007 ZAP. MURO, 40x15, 1:2:4, 2 DE 3/8", 3/8" A .30 grado 40, LIG., para Bordillos:

1 Acero 3/8" (bastones) + 5% desp. 0.1012 qq 1,915.88 193.892 Acero 3/8" x 20' grado 40 + 5% desp. 0.8297 qq 1,915.88 1,589.613 M.O. acero 16.6670 m 71.30 1,188.364 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 3,572.33 3,643.78

M3 $6,421.75*HAZAPM1 10450008 ZAP. MURO, 30x20, 1:2:4, 2 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero ¼" (bastones) + 5% desp. 0.0479 qq 1,088.60 52.142 Acero 3/8" x 20' grado 40 + 5% desp. 0.8082 qq 1,915.88 1,548.413 M.O. acero 16.6670 m 71.30 1,188.364 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 3,572.33 3,643.78

M3 $6,432.69*HAZAPM1 10450009 ZAP. MURO, 45x20, 1:2:4, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.8747 qq 1,915.88 1,675.822 M.O. acero 11.1110 m 71.30 792.213 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 3,572.33 3,643.78

M3 $6,111.81*HAZAPM1 10450010 ZAP. MURO, 45x25, 1:2:4, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.7130 qq 1,915.88 1,366.022 M.O. acero 8.8890 m 71.30 633.793 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 3,572.33 3,643.78

M3 $5,643.59*HAZAPM1 10450011 ZAP. MURO, 60x25, 1:2:4, 3 DE 3/8", 3/8" A .25 grado 40, LIG.:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.5912 qq 1,915.88 1,132.67

Page 104: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 74

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

2 M.O. acero 6.6670 m 71.30 475.363 Horm. 1:2:4, lig. + 2% desp. 1.02 m3 3,572.33 3,643.78

M3 $5,251.81*HAZAPM1 10450012 ZAP. MURO, 30x20, 140, 2 DE 3/8", 3/8" A .25 grado 40:

1 Acero ¼" (bastones) + 5% desp. 0.0479 qq 1,088.60 52.142 Acero 3/8" x 20' grado 40 + 5% desp. 0.8082 qq 1,915.88 1,548.413 M.O. acero 16.6670 m 71.30 1,188.364 Horm. 140 Kg/Cm² 1.00 m3 5,614.40 5,614.40

M3 $8,351.17*HAZAPM1 10450013 ZAP. MURO, 45x20, 140, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.8747 qq 1,915.88 1,675.822 M.O. acero 11.1110 m 71.30 792.213 Horm. 140 Kg/Cm² 1.00 m3 5,614.40 5,614.40

M3 $8,082.43*HAZAPM1 10450014 ZAP. MURO, 45x25, 140, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.7130 qq 1,915.88 1,366.022 M.O. acero 8.8890 m 71.30 633.793 Horm. 140 Kg/Cm² 1.00 m3 5,614.40 5,614.40

M3 $7,614.21*HAZAPM1 10450015 ZAP. MURO, 60x25, 140, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.5912 qq 1,915.88 1,132.672 M.O. acero 6.6670 m 71.30 475.363 Horm. 140 Kg/Cm² 1.00 m3 5,614.40 5,614.40

M3 $7,222.43*HAZAPM1 10450016 ZAP. MURO, 30x20, 180, 2 DE 3/8", 3/8" A .25 grado 40:

1 Acero ¼" (bastones) + 5% desp. 0.0479 qq 1,088.60 52.142 Acero 3/8" x 20' grado 40 + 5% desp. 0.8082 qq 1,915.88 1,548.413 M.O. acero 16.6670 m 71.30 1,188.364 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $8,722.31*HAZAPM1 10450017 ZAP. MURO, 45x20, 180, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.8747 qq 1,915.88 1,675.822 M.O. acero 11.1110 m 71.30 792.213 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $8,401.43*HAZAPM1 10450018 ZAP. MURO, 45x25, 180, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.7130 qq 1,915.88 1,366.022 M.O. acero 8.8890 m 71.30 633.793 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $7,933.21*HAZAPM1 10450019 ZAP. MURO, 60x25, 180, 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.5912 qq 1,915.88 1,132.672 M.O. acero 6.6670 m 71.30 475.363 Horm. 180 Kg/Cm² 1.00 m3 5,933.40 5,933.40

M3 $7,541.43*HAZAPM1 10450020 ZAP. MURO, 45x25, 210 Kg/Cm², 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.7170 qq 1,915.88 1,373.692 M.O. acero 8.8890 m 71.30 633.793 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $8,196.08*HAZAPM1 10450021 ZAP. MURO, 60x25, 210 Kg/Cm², 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 40 + 5% desp. 0.5912 qq 1,915.88 1,132.672 M.O. acero 6.6670 m 71.30 475.363 Horm. 210 Kg/Cm² 1.00 m3 6,188.60 6,188.60

M3 $7,796.63*HAZAPM1 10450022 ZAP. MURO, 45x25, 240 Kg/Cm², 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 60 + 5% desp. 0.7130 qq 2,021.08 1,441.032 M.O. acero 8.8890 m 71.30 633.793 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $8,518.62*HAZAPM1 10450023 ZAP. MURO, 60x25, 240 Kg/Cm², 3 DE 3/8", 3/8" A .25 grado 40:

1 Acero 3/8" x 20' grado 60 + 5% desp. 0.5912 qq 2,021.08 1,194.862 M.O. acero 6.6670 m 71.30 475.363 Horm. 240 Kg/Cm² 1.00 m3 6,443.80 6,443.80

M3 $8,114.02

*HORIND 10470000 HORMIGONES INDUSTRIALES

*HORIND 10470001 HORM. 140 Kg/Cm²:1 Horm. industrial + 10% desp. 1.10 m3 4,582.00 5,040.202 Bomba + personal + 10% desp. 1.10 m3 522.00 574.203 Aditivo 0.1289 gl 304.50

M3 $5,614.40*HORIND 10470002 HORM. 160 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 4,698.00 5,167.802 Bomba + personal + 10% desp. 1.10 m3 522.00 574.203 Aditivo 0.1558 gl 304.50

M3 $5,742.00*HORIND 10470003 HORM. 180 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 4,872.00 5,359.202 Bomba + personal + 10% desp. 1.10 m3 522.00 574.203 Aditivo 0.1805 gl 304.50

M3 $5,933.40*HORIND 10470004 HORM. 210 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 5,104.00 5,614.402 Bomba + personal + 10% desp. 1.10 m3 522.00 574.203 Aditivo 0.2063 gl 304.50

M3 $6,188.60

Page 105: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 75

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HORIND 10470005 HORM. 240 Kg/Cm²:1 Horm. industrial + 10% desp. 1.10 m3 5,336.00 5,869.602 Bomba + personal + 10% desp. 1.10 m3 522.00 574.203 Aditivo 0.2063 gl 304.50

M3 $6,443.80*HORIND 10470006 HORM. 250 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 5,452.00 5,997.202 Bomba + personal + 10% desp. 1.10 m3 522.00 574.203 Aditivo 0.2063 gl 304.50

M3 $6,571.40*HORIND 10470007 HORM. 260 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 5,626.00 6,188.602 Bomba + personal + 10% desp. 1.10 m3 522.00 574.203 Aditivo 0.2063 gl 304.50

M3 $6,762.80*HORIND 10470008 HORM. 280 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 5,800.00 6,380.002 Bomba + personal + 10% desp. 1.10 m3 522.00 574.203 Aditivo 0.2063 gl 304.50

M3 $6,954.20*HORIND 10470009 HORM. 300 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 5,974.00 6,571.402 Bomba + personal + 10% desp. 1.10 m3 522.00 574.203 Aditivo 0.2063 gl 304.50

M3 $7,145.60*HORIND 10470010 HORM. 350 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 6,438.00 7,081.802 Bomba + personal + 10% desp. 1.10 m3 522.00 574.203 Aditivo 0.2063 gl 304.50

M3 $7,656.00*HORIND 10470011 HORM. 400 Kg/Cm²:

1 Horm. industrial + 10% desp. 1.10 m3 6,960.00 7,656.002 Bomba + personal + 10% desp. 1.10 m3 522.00 574.203 Aditivo 0.2063 gl 304.50

M3 $8,230.20

*HORSIM 10490000 HORMIGONES SIMPLES

*HORSIM 10490001 LIGADO Y VACIADO A MANO:1400 m3 horm. 1:3:5 vaciados en 8 horas, a 1.75 m3 por hora.

1 Madera para puentes (4 de 2"x10"x 12', 6 usos) 14.00 pt 29.00 406.002 Carretilla (7 meses de uso) 5.00 u 253.13 1,265.633 Palas (7 meses de uso) 6.00 u 25.05 150.304 Tanques de agua (7 meses de uso) 4.00 u 52.56 210.245 Cubetas para medir el agua (7 meses de uso) 2.00 u 25.02 50.046 Maestro 1.00 u 1,125.00 1,125.007 Llenador de agregados (TC) 1.00 u 425.00 425.008 Maleteros o acarreadores de agregados (TC) 2.00 u 425.00 850.009 Ligadores (TC) 4.00 u 425.00 1,700.0010 Cementero (acarreador de cemento) (TC) 1.00 u 425.00 425.0011 Vaciador y tenedor (TC) 1.00 u 425.00 425.0012 Aguatero (TC) 1.00 u 425.00 425.00

Total 7,457.21M3 $532.66

*HORSIM 10490002 LIGADORA 2 FUNDAS:1 Rendimiento del equipo: 18.00 m3 horm. 1:3:5 en 5 horas 18.00 m32 Potencia del equipo 20 hp3 Vida útil: 5 años. Veloc. depreciación: 20% / año4 Costo del equipo 113,899.99 $5 Deprec. 40% 1er. año (Doble veloc. deprec.) 45,560.00 $6 Tiempo de trabajo: 1,200 horas / año 1,200 horas7 Deprec. horaria: Deprec. 1er. año ÷ Tiempo trabajo 37.97 $8 Costo inversión: 36% del costo equipo 41,004.00 $9 Costo inv. horario (Costo inversión ÷ Tiempo trabajo) 34.17 $10 Combustible / hora (.05 gls. / HP potencia) 1.00 gl11 Lubricante (15% consumo combustible) 23.75 $

*HORSIM 10490003 WINCHE (ELEVADOR):Capacidad: 2000 kilosAltura elevación: 12 m. Velocidad elevación: 0.50 m./seg.Tiempo elevación: 24 seg. Cant. m3 elevado: 4 m3 / horaVaciado: 18.00 m3 en 5 horas

1 Costo del equipo 265,152.16 $2 Depreciación 40% 1er. año (Doble velocidad deprec.) 106,060.86 $3 Tiempo de trabajo: 1,200 horas / año 1,200 horas4 Deprec. horaria: Deprec. 1er. año ÷ Tiempo trabajo 88.38 $5 Costo inversión: 36% del costo del equipo 95,454.78 $6 Costo inv. horario (Costo inversión ÷ Tiempo trabajo) 79.55 $

*HORSIM 10490004 COSTO USO, LIG. P/HORA:1 Depreciación horaria 1.00 u 37.97 37.972 Costo inversión horaria 1.00 u 34.17 34.173 Mant. y reparaciones (75% Deprec. horaria) 1.00 u 28.47 28.474 Combustible 1.00 gl 158.30 158.305 Lubricante (15% valor combustible consumido) 15% 23.75

Hora $282.66

Page 106: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 76

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HORSIM 10490005 COSTO USO WINCHE (ELEVADOR) P/HORA:1 Depreciación horaria 1.00 u 88.38 88.382 Costo inversión horaria 1.00 u 79.55 79.553 Mant. y reparaciones (75% Deprec. horaria) 1.00 u 66.29 66.294 Combustible 0.90 gl 158.30 142.475 Lubricante (15% valor combustible consumido) 15% 21.37

Hora $398.06*HORSIM 10490006 LIGADO Y VACIADO,, LIG. 2 FUNDAS: 18.00 m3

1 Uso ligadora 5.00 horas 282.66 1,413.302 Maestro 5.00 horas 140.63 703.153 Cargadores agregados y cemento (3 hombres) 15.00 horas 53.13 796.954 Operador 5.00 horas 53.13 265.655 Transp. horm. (3 hombres) 15.00 horas 53.13 796.956 Tendedor 5.00 horas 78.13 390.65

Total $4,366.65M3 $242.59

*HORSIM 10490007 LIGADO Y VACIADO, LIG. 2 FDA. Y WINCHE: 18.00 m31 Uso ligadora 5.00 horas 282.66 1,413.302 Uso Winche 5.00 horas 398.06 1,990.303 Maestro 5.00 horas 140.63 703.154 Cargadores agregados y cemento (3 hombres) 15.00 horas 53.13 796.955 Operador 5.00 horas 53.13 265.656 Operador Winche (cargador) 5.00 horas 53.13 265.657 Transp. horm. (3 hombres) 15.00 horas 53.13 796.958 Vaciador en Winche (cargador) 5.00 horas 53.13 265.659 Tendedor 5.00 horas 78.13 390.65

Total $6,888.25M3 $382.68

*HORSIM 10490008 HORMIGON (1:3:5) A MANO:1 Arena gruesa lavada 0.5229 m3 1,100.00 575.192 Grava combinada 0.8544 m3 750.00 640.803 agua 60.00 gl 0.35 21.004 Cemento gris 6.40 fda 250.00 1,600.005 Vaciado a mano 1.38 m3 532.66 735.07

M3 $3,572.06

Page 107: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 77

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*HORSIM 10490009 HORMIGON (1:3:5), LIG.:1 Arena gruesa lavada 0.5229 m3 1,100.00 575.192 Grava combinada 0.8544 m3 750.00 640.803 agua 60.00 gl 0.35 21.004 Cemento gris 6.40 fda 250.00 1,600.005 Vaciado con ligadora 1.38 m3 242.59 334.77

M3 $3,171.76*HORSIM 10490010 HORMIGON (1:3:5) LIG. Y WINCHE:

1 Arena gruesa lavada 0.5229 m3 1,100.00 575.192 Grava combinada 0.8544 m3 750.00 640.803 agua 60.00 gl 0.35 21.004 Cemento gris 6.40 fda 250.00 1,600.005 Vaciado con ligadora y winche 1.38 m3 382.68 528.10

M3 $3,365.09*HORSIM 10490011 HORMIGON (1:2:4) A MANO:

1 Arena gruesa lavada 0.4483 m3 1,100.00 493.132 Grava combinada 0.8976 m3 750.00 673.203 agua 60.00 gl 0.35 21.004 Cemento gris 8.23 fda 250.00 2,057.505 Vaciado a mano 1.35 m3 532.66 719.09

M3 $3,963.92*HORSIM 10490012 HORMIGON (1:2:4), LIG.:

1 Arena gruesa lavada 0.4483 m3 1,100.00 493.132 Grava combinada 0.8976 m3 750.00 673.203 agua 60.00 gl 0.35 21.004 Cemento gris 8.23 fda 250.00 2,057.505 Vaciado con ligadora 1.35 m3 242.59 327.50

M3 $3,572.33*HORSIM 10490013 HORMIGON (1:2:4) LIG. Y WINCHE:

1 Arena gruesa lavada 0.4483 m3 1,100.00 493.132 Grava combinada 0.8976 m3 750.00 673.203 agua 60.00 gl 0.35 21.004 Cemento gris 8.23 fda 250.00 2,057.505 Vaciado con ligadora y winche 1.35 m3 382.68 516.62

M3 $3,761.45

*IMP 10510000 IMPERMEABILIZANTES

*IMP 10510001 SX-PEL + SUPRACURE PLUS (IMPERM. ESTRUCTURAL):1 Limpieza superficie 1.00 m2 30.11 30.112 "SX-PEL" para .2125 m3 horm. 180 0.26 gl 304.50 79.173 Sellador "SUPRACURE PLUS" sobre área expuesta 0.042 gl 894.00 37.554 Mano de obra 1.00 m2 76.56 76.56

M2 $223.39*IMP 10510002 SILICOOL:

1 Limpieza superficie 1.00 m2 30.11 30.112 Sellador ALM + 10% desp. 0.090 gl 606.88 54.623 Silicool + 10% desp. 0.090 gl 820.00 73.804 Mano de obra 1.00 m2 37.32 37.32

M2 $195.85

*IEACO 10530000 INSTALACION ELECTRICA: ACOMETIDAS

*IEACO 10530001 ACOM. PRIM. 3 PH., DESDE POSTE HASTA TRANSF., SOTERRADA: 26.00 m1 Adaptador hembra 3", PVC 1 u 32.89 32.892 Alambre URD #2, 33% neutro, concéntrico, 1 cond. por fase 282.00 p 116.79 32,934.783 Bote material excavado en zanja 9.40 m3 300.00 2,820.004 Cemento PVC Cano, ¼ gl. 0.0503 u 238.00 11.975 Cinta de peligro (rollo) 1 u 319.00 319.006 Codo 3"x90, PVC 2 u 126.00 252.007 Condulet 3", hg 2 u 1,736.00 3,472.008 Cono de alivio 3 u 2,128.70 6,386.109 Cut Out 200 a., 15 kv 3 u 4,259.64 12,778.9210 Elbow Conector 3 u 1,465.58 4,396.7411 Excavación zanja para tuberías, roca Long. Zanja (m.): 9.00 6.48 m3 1,962.36 12,716.0912 Fusible tipo cartucho, 8 amp. 3 u 74.47 223.4113 Pararrayo 9 kva (Arrester) 3 u 1,743.71 5,231.1314 Piezas p/soporte Estructura SS-1 1 u 2,203.88 2,203.8815 Relleno granular 6.48 m3 1,028.45 6,664.3616 Tubería 3", BX 10.00 p 439.72 3,456.6717 Tubo 3"x19', PVC SDR-26 + 10% desp. 3 u 676.26 2,028.7818 Tubo IMC 3"x20', hg 1 u 4,628.67 4,628.67

Subtotal 100,557.3919 Miscelaneos 2.00% 2,011.1520 Mano de obra especializada y beneficios sub-contratista 25.00% 25,139.35

Acometida 127,707.89m $4,911.84

*IEACO 10530002 ACOM. AL-01 DESDE TRANSF. HASTA MOD. MEDICION 8.00 m1 Alambre #3/0 THW, 9 cond., 3 por fase 260.00 p 108.55 28,223.002 Alambre #3/0 THW, 2 cond., neutro 58.00 p 108.55 6,295.903 Alambre #3/0 THW, 1 cond. pelado, tierra 29.00 p 108.55 3,147.954 Cemento PVC Cano, ¼ gl. 0.1241 u 238.00 29.545 Codo 2"x90, PVC 2 u 31.32 62.646 Codo 3"x90, PVC 6 u 126.00 756.007 Tubos 2"x19', PVC SDR-26 + 10% desp. 2 u 256.04 512.088 Tubos 3"x19', PVC SDR-26 + 10% desp., 4 alambres p/tubo 5 u 676.26 3,381.30

Subtotal 42,408.419 Miscelaneos 2.00% 848.17

Page 108: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 78

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

10 Mano de obra especializada y beneficios sub-contratista 25.00% 10,602.10Acometida 53,858.68

m $6,732.34

Page 109: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 79

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*IEACO 10530003 ACOM. AL-02 DESDE MOD. MEDICION HASTA PANEL AREA COMUN 38.00 m1 Alambre No. 2 THW, 3 cond. 412.00 p 45.32 18,671.842 Alambre No. 4 THW, 1 cond., neutro 138.00 p 29.30 4,043.403 Alambre No. 4 THW, 1 cond., tierra 138.00 p 29.30 4,043.404 Bote material excavado en zanja 3.99 m3 300.00 1,197.005 Cemento PVC Cano, ¼ gl. 0.0769 u 238.00 18.306 Codo 3"x90, PVC 2 u 126.00 252.007 Excavación zanja para tuberías, roca Long. Zanja (m.): 30.50 2.75 m3 1,962.36 5,396.498 Relleno granular 2.75 m3 1,028.45 2,828.249 Tubo 3"x19', PVC SDR-26 + 10% desp. 8 u 676.26 5,410.08

Subtotal 41,860.7510 Miscelaneos 2.00% 837.2211 Mano de obra especializada 25.00% 10,465.19

Acometida 53,163.16m $1,399.03

*IEACO 10530004 ACOM. AL-02 DESDE PLANTA EMERG. HASTA MODULO MEDICION 8.00 m1 Alambre No. 12 THW, 2 cond. 58.00 p 45.32 2,628.561 Alambre No. 2 THW, 3 cond. 87.00 p 45.32 3,942.842 Alambre No. 4 THW, 1 cond., neutro 29.00 p 29.30 849.703 Alambre No. 4 THW, 1 cond., tierra 29.00 p 29.30 849.704 Cemento PVC Cano, ¼ gl. 0.0683 u 238.00 16.264 Codo ½"x90, PVC 2 u 126.00 252.005 Codo 3"x90, PVC 2 u 126.00 252.005 Tubo ½"x19', PVC SDR-26 + 10% desp. 2 u 676.26 1,352.526 Tubo 3"x19', PVC SDR-26 + 10% desp. 2 u 676.26 1,352.52

Subtotal 11,496.107 Miscelaneos 2.00% 229.928 Mano de obra especializada 25.00% 2,874.03

Acometida 14,600.05m $1,825.01

*IEACO 10530005 ACOM. AL-03 DESDE MODULO MEDICION HASTA PA, PB y PC 56.00 m1 Alambre No. 2 THW, 2 cond. (1 en c/fase) 405.00 p 45.32 18,354.602 Alambre No. 4 THW, 1 cond., neutro 203.00 p 29.30 5,947.903 Alambre No. 10 THW, 1 cond., tierra 203.00 p 7.34 1,490.024 Bote material excavado en zanja 1.65 m3 300.00 495.005 Cemento PVC Cano, ¼ gl. 0.0369 u 238.00 8.786 Codo 1½"x90, PVC 2 u 27.84 55.687 Excavación zanja para tuberías, roca Long. Zanja (m.): 28.50 1.14 m3 1,962.36 2,237.098 Relleno granular 1.14 m3 1,028.45 1,172.439 Tubo 1½"x19', PVC SDR-26 + 10% desp. 11 u 214.01 2,354.11

Subtotal 32,115.6110 Miscelaneos 2.00% 642.3111 Mano de obra especializada 25.00% 8,028.90

Acometida 40,786.82m $728.34

*IEACO 10530006 58.00 m1 Alambre dulce #18 como mensajero 3.00 lb 25.44 76.322 Bote material excavado en zanja 2.67 m3 300.00 801.003 Cemento PVC Cano, ¼ gl. 0.0879 u 238.00 20.924 Codo 2"x90, PVC 6 u 31.32 187.925 Excavación zanja para tuberías, roca Long. Zanja (m.): 46.00 1.84 m3 1,962.36 3,610.746 Registro 24"x24", usa, hg 4 u 2,693.26 10,773.047 Relleno granular 1.84 m3 1,028.45 1,892.358 Tubo 2"x19', PVC SDR-26 + 10% desp. 12 u 256.04 3,072.48

Subtotal 20,434.779 Miscelaneos 2.00% 408.7010 Mano de obra especializada 25.00% 5,108.69

Acometida 25,952.16m $447.45

Registro $6,488.04*IEACO 10530007 2.80 m

1 Alambre dulce #18 como mensajero 1.00 lb 25.44 25.442 Cemento PVC Cano, ¼ gl. 0.0261 u 238.00 6.213 Codo 2"x90, PVC 2 u 31.32 62.644 Registro 24"x24", usa, hg 3 u 2,693.26 8,079.785 Tubo 2"x19', PVC SDR-26 + 10% desp. 1 u 256.04 256.04

Subtotal 8,430.116 Miscelaneos 2.00% 168.607 Mano de obra especializada 25.00% 2,107.53

Acometida 10,706.24m $3,823.66

Registro $3,568.75*IEACO 10530008 8.30 m

1 Alambre dulce #18 como mensajero 1.00 lb 25.44 25.442 Cemento PVC Cano, ¼ gl. 0.0109 u 238.00 2.593 Codo ¾"x90, PVC 2 u 5.75 11.504 Registro 6"x6", criollo, hg 1 u 99.76 99.765 Tubo ¾"x19', PVC SDR-26 + 10% desp. 2 u 71.00 142.00

Subtotal 281.296 Miscelaneos 2.00% 5.637 Mano de obra especializada 25.00% 70.32

Acometida 638.53m $76.93

Registro $638.53*IEACO 10530009 8.30 m

1 Alambre dulce #18 como mensajero 1.00 lb 25.44 25.442 Cemento PVC Cano, ¼ gl. 0.0005 u 238.00 0.123 Codo ½"x90, PVC 0 u 4.58 0.00

ACOM. CABLE Y TELEF. 1ER. N., CASETA HASTA REG. ESCALERA

ACOM. CABLE Y TELEF. , CADA NIVEL EN ESCALERA

ACOM. CABLE, CADA NIVEL DESDE ESCALERA HACIA ADENTRO

ACOM. TELEF., CADA NIVEL DESDE ESCALERA HACIA ADENTRO

Page 110: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 80

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

4 Registro 4"x4", USA, hg 1 u 52.00 52.005 Tubo ½"x19', PVC SDR-26 + 10% desp. 2 u 50.87 101.74

Subtotal 179.306 Miscelaneos 2.00% 3.597 Mano de obra especializada 25.00% 44.83

Acometida 407.02m $49.04

Registro $407.02*IEACO 10530010 ACOM. TRIF. DESDE PANEL "PAC" HASTA ASCENSOR 30.50 m

1 Alambre No. 6 THW, 3 cond. (1 en c/fase) 331.00 p 45.32 15,000.922 Alambre No. 6 THW, 1 cond., neutro 111.00 p 29.30 3,252.303 Alambre No. 6 THW, 1 cond., tierra 111.00 p 7.34 814.744 Bote material excavado en zanja 0.23 m3 300.00 69.005 Cemento PVC Cano, ¼ gl. 0.0315 u 238.00 7.506 Codo 1½"x90, PVC 2 u 27.84 55.687 Excavación zanja para tuberías, roca Long. Zanja (m.): 4.00 0.16 m3 1,962.36 313.988 Relleno granular 0.16 m3 1,028.45 164.559 Tubo 1½"x19', PVC SDR-26 + 10% desp. 6 u 214.01 1,284.06

Subtotal 20,962.7310 Miscelaneos 2.00% 419.2511 Mano de obra especializada 25.00% 5,240.68

Acometida 26,622.66m $872.87

*IEACO 10530011 ACOM. TRIF. DESDE PANEL "PAC" HASTA BOMBAS DE AGUA 31.50 m1 Alambre No. 2 THW, 3 alambres 341.00 p 45.32 15,454.122 Alambre No. 4 THW, 1 alambre, neutro 114.00 p 29.30 3,340.203 Alambre No. 10 THW, 1 alambre, tierra 114.00 p 7.34 836.764 Bote material excavado en zanja 1.68 m3 300.00 504.005 Cemento PVC Cano, ¼ gl. 0.0315 u 238.00 7.506 Codo 1½"x90, PVC 2 u 27.84 55.687 Excavación zanja para tuberías, roca Long. Zanja (m.): 29.00 1.16 m3 1,962.36 2,276.348 Relleno granular 1.16 m3 1,028.45 1,193.009 Tubo 1½"x19', PVC SDR-26 + 10% desp. 6 u 214.01 1,284.06

Subtotal 24,951.6610 Miscelaneos 2.00% 499.0311 Mano de obra especializada 25.00% 6,237.92

Acometida 31,688.61m $1,005.99

*IESAL 10550000 INSTALACION ELECTRICA: SALIDAS Y PANELES

*IESAL 10550001 LUZ CENITAL:1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 50.87 50.872 Caja octagonal 1.00 u 32.48 32.483 Alambre #12 TW 40.00 p 4.65 186.004 Roseta de porcelana 1.00 u 34.68 34.685 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.896 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.987 Mano de obra 1.00 u 387.57 387.578 Gastos indirectos contratistas eléctricos 20.00% 140.49

Unid. $842.96*IESAL 10550002 INTERRUPTOR SENCILLO:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 50.87 50.872 Caja rectangular de ½" 1.00 u 40.50 40.503 Alambre #12 TW 40.00 p 4.65 186.004 Accesorio 1.00 u 33.78 33.785 Codos plásticos ½" 1.00 u 4.58 4.586 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.897 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.988 Mano de obra 1.00 u 387.57 387.579 Beneficios contratistas eléctricos 20.00% 142.83

Unid. $857.00*IESAL 10550003 INTERRUPTOR DOBLE:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 50.87 50.872 Caja rectangular ½" 1.00 u 40.50 40.503 Alambre #12 TW 60.00 p 4.65 279.004 Accesorio 1.00 u 121.29 121.295 Codos plásticos ½" 1.00 u 4.58 4.586 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.897 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.988 Mano de obra 1.00 u 469.62 469.629 Beneficios contratistas eléctricos 20.00% 195.35

Unid. $1,172.08*IESAL 10550004 INTERRUPTOR TRIPLE:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 50.87 50.872 Caja rectangular ½" 1.00 u 40.50 40.503 Alambre #12 TW 80.00 p 4.65 372.004 Accesorio 1.00 u 144.33 144.335 Codos plásticos ½" 1.00 u 4.58 4.586 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.897 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.988 Mano de obra 1.00 u 523.37 523.379 Beneficios contratistas eléctricos 20.00% 229.30

Unid. $1,375.82*IESAL 10550005 INTERRUPTOR TRES VIAS:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 50.87 50.872 Caja rectangular ½" 1.00 u 40.50 40.503 Alambre #12 TW 60.00 p 4.65 279.00

Page 111: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 81

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

4 Accesorio 1.00 u 70.12 70.125 Codos plásticos ½" 1.00 u 4.58 4.586 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.897 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.988 Mano de obra 1.00 u 469.62 469.629 Beneficios contratistas eléctricos 20.00% 185.11

Unid. $1,110.67

Page 112: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 82

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*IESAL 10550006 INTERRUPTOR CUATRO VIAS:1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 50.87 50.872 Caja rectangular ½" 1.00 u 40.50 40.503 Alambre #12 TW 80.00 p 4.65 372.004 Accesorio 1.00 u 343.50 343.505 Codos plásticos ½" 1.00 u 4.58 4.586 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.897 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.988 Mano de obra 1.00 u 575.71 575.719 Beneficios contratistas eléctricos 20.00% 279.61

Unid. $1,677.64*IESAL 10550007 INTERRUPTOR PILOTO:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 50.87 50.872 Caja rectangular ½" 1.00 u 40.50 40.503 Alambre #12 TW 60.00 p 4.65 279.004 Accesorio 1.00 u 158.72 158.725 Codos plásticos ½" 1.00 u 4.58 4.586 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.897 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.988 Mano de obra 1.00 u 469.62 469.629 Beneficios contratistas eléctricos 20.00% 202.83

Unid. $1,216.99*IESAL 10550008 TOMACORRIENTE DOBLE 110 V.:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.00 u 50.87 50.872 Caja rectangular ½" 1.00 u 40.50 40.503 Alambre #12 TW+ 5% desp. 60.00 p 4.65 279.004 Accesorio 1.00 u 24.59 24.595 Codos plásticos ½" 2.00 u 4.58 9.166 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.897 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.988 Mano de obra 1.00 u 387.57 387.579 Beneficios contratistas eléctricos 20.00% 160.51

Unid. $963.07*IESAL 10550009 TOMACORRIENTE SENCILLO 220 V.:

1 Tubo ¾"x10' PVC SDR-26 + 15% desp. 2.00 u 71.00 142.002 Caja rectangular ¾". 1.00 u 31.32 31.323 Alambre #10 TW + 5% desp. 80.00 p 7.34 587.204 Alambre #12 TW+ 5% desp. 40.00 p 4.65 186.005 Accesorio 1.00 u 70.83 70.836 Codos plásticos ¾". 2.00 u 5.75 11.507 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.898 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.989 Mano de obra 1.00 u 441.17 441.1710 Beneficios contratistas eléctricos 20.00% 296.18

Unid. $1,777.07*IESAL 10550010 SALIDA CALENTADOR:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 2.00 u 50.87 101.742 Caja rectangular ½" 1.00 u 40.50 40.503 Alambre #12 TW+ 5% desp. 40.00 p 4.65 186.004 Accesorio 1.00 u 70.83 70.835 Codos plásticos ½" 2.00 u 4.58 9.166 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.897 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.988 Mano de obra 1.00 u 441.17 441.179 Beneficios contratistas eléctricos 20.00% 172.05

Unid. $1,032.32*IESAL 10550011 SALIDA TELEFONO:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 2.00 u 50.87 101.742 Caja rectangular ½" 1.00 u 40.50 40.503 Alambre dulce #18+ 5% desp. 0.33 lb 25.44 8.404 Accesorio (tapa ciega pvc). 1.00 u 14.24 14.245 Codos plásticos ½" 2.00 u 4.58 9.166 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.987 Mano de obra 1.00 u 387.57 387.578 Beneficios contratistas eléctricos 20.00% 112.92

Unid. $677.51*IESAL 10550012 TIMBRE CORRIENTE:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.50 u 50.87 76.312 Caja rectangular ½" 1.00 u 40.50 40.503 Alambre #14 TW+ 5% desp. 100.00 p 3.12 312.004 Accesorio 1.00 u 414.12 414.125 Codos plásticos ½" 1.00 u 4.58 4.586 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.897 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.988 Mano de obra 1.00 u 387.57 387.579 Beneficios contratistas eléctricos 20.00% 249.19

Unid. $1,495.14*IESAL 10550013 BOTON DE TIMBRE:

1 Tubo ½"x20' PVC SDR-26 + 15% desp. 1.50 u 50.87 76.312 Caja rectangular ½" 1.00 u 40.50 40.503 Alambre #14 TW + 5% desp. 50.00 p 3.12 156.004 Accesorio 1.00 u 136.17 136.175 Codos plásticos ½" 2.00 u 4.58 9.166 Cinta adhesiva "3M" (rollo) 0.05 u 157.76 7.897 Cemento PVC + 30% desp. (¼ gl.) 0.0125 u 238.00 2.988 Mano de obra 1.00 u 387.57 387.579 Beneficios contratistas eléctricos 20.00% 163.32

Unid. $979.90

Page 113: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 83

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*IESAL 10550014 PANEL DISTRIBUCION 2 ESPACIOS, 1 PH:1 "Breakers" 15 A. 2.00 u 133.40 266.802 Panel distribución. 1.00 u 411.80 411.803 Hacer hueco y colocar panel 1.00 u 543.17 543.174 Coloc. "Breakers" 2.00 u 87.70 175.405 Beneficios contratistas eléctricos 20.00% 279.43

Unid. $1,676.60*IESAL 10550015 PANEL DISTRIBUCION 4 ESPACIOS, 1 PH:

1 "Breakers" 15 A. 4.00 u 133.40 533.602 Panel distribución. 1.00 u 527.80 527.803 Hacer hueco y colocar panel 1.00 u 543.17 543.174 Coloc. "Breakers" 4.00 u 87.70 350.805 Beneficios contratistas eléctricos 20.00% 391.07

Unid. $2,346.44*IESAL 10550016 PANEL DISTRIBUCION 6 ESPACIOS, 1 PH:

1 "Breakers" 15 y 20 A. 6.00 u 133.40 800.402 Panel distribución. 1.00 u 1,121.00 1,121.003 Hacer hueco y colocar panel 1.00 u 543.17 543.174 Coloc. "Breakers" 6.00 u 87.70 526.205 Beneficios contratistas eléctricos 20.00% 598.15

Unid. $3,588.92*IESAL 10550017 PANEL DISTRIBUCION 8 ESPACIOS, 1 PH:

1 "Breakers" 15 y 20 A. 8.00 u 133.40 1,067.202 Panel distribución. 1.00 u 1,238.00 1,238.003 Hacer hueco y colocar panel 1.00 u 543.17 543.174 Coloc. "Breakers" 8.00 u 87.70 701.605 Beneficios contratistas eléctricos 20.00% 709.99

Unid. $4,259.96*IESAL 10550018 PANEL DISTRIBUCION 12 ESPACIOS, 1 PH:

1 "Breakers" 15 y 20 A. 12.00 u 133.40 1,600.802 Panel distribución. 1.00 u 1,780.60 1,780.603 Hacer hueco y colocar panel 1.00 u 543.17 543.174 Coloc. "Breakers" 12.00 u 87.70 1,052.405 Beneficios contratistas eléctricos 20.00% 995.39

Unid. $5,972.36*IESAL 10550019 PANEL DISTRIBUCION 16 ESPACIOS, 1 PH:

1 "Breakers" 15 y 20 A. 16.00 u 133.40 2,134.402 Panel distribución. 1.00 u 1,238.00 1,238.003 Hacer hueco y colocar panel 1.00 u 543.17 543.174 Coloc. "Breakers" 16.00 u 87.70 1,403.205 Beneficios contratistas eléctricos 20.00% 1,063.75

Unid. $6,382.52*IESAL 10550020 PANEL DISTRIBUCION 24 ESPACIOS, 1 PH:

1 "Breakers" 15 y 20 A. 24.00 u 133.40 3,201.602 Panel distribución. 1.00 u 1,780.60 1,780.603 Hacer hueco y colocar panel 1.00 u 543.17 543.174 Coloc. "Breakers" 24.00 u 87.70 2,104.805 Beneficios contratistas eléctricos 20.00% 1,526.03

Unid. $9,156.20*IESAL 10550021 PANEL DISTRIB., 30 ESPACIOS, 3 PH.:

1 "Breakers" 20 A., 1 ph 9.00 u 133.40 1,200.602 "Breakers" 30 A., 2 ph 1.00 u 330.60 330.603 "Breakers" 60 A., 3 ph 2.00 u 1,609.20 3,218.404 Cemento PVC Cano, ¼ gl. 0.0505 u 238.00 12.025 Codos plásticos ½". 6.00 u 4.58 27.486 Codos plásticos ¾". 6.00 u 5.75 34.507 Coloc. "Breakers". 12.00 u 87.70 1,052.408 Hacer hueco y colocar panel. 1.00 u 543.17 543.179 Mortero 1:3 p/remendar para empotrar panel y tuberías 0.06 m3 3,932.52 235.9510 Panel distribución. 1.00 u 5,963.00 5,963.0011 Tubo ½"x20' PVC SDR-26 + 15% desp. 12.00 u 50.87 610.4412 Tubo ¾"x20' PVC SDR-26 + 15% desp. 1.00 u 71.00 71.0013 Beneficios contratistas eléctricos. 15.00% 1,984.28

Unid. $15,283.84*IESAL 10550022 TRANSFORMADOR PADMOUNTED, 225 KVA: (EN TORRES)

1 Base horm. 210 kg/cm2, 3/8" a 0.20 m. a. d., 1.50X1.20X0.20 M. 0.36 m3 1,787.81 643.612 Tranformador 225 KVA, Pad-Mounted, 3ph, 7200, 120/208/240 v. 1 u 336,400.00 336,400.00

Subtotal 337,043.613 Miscelaneos 1.00% 3,370.444 Mano de obra especializada y beneficios sub-contratista 25.00% 84,260.905 Uso de grúa 1 hr. 4,285.33 4,285.33

Unid. $428,960.28

*ISASHG 10570000 INST. SANITARIA: APARATOS SANIT., TUB. HG Y M. DE OBRA

*ISASHG 10550023 BAJANTE O VENT. SANIT. 3" PVC SDR-411 Cemento pvc "Tangit", 460 gramos + 25% desp.. 0.0357 u 554.48 19.792 Codo 3"x90, pvc dren. 1.00 u 35.31 35.313 Mano de obra Bajante o Vent. p/piso 1.00 u 593.43 593.434 Tubo 3", pvc SDR-41 + 10% desp. 0.67 tubo 428.04 286.79

Unid. $915.53*ISASHG 10550024 BAJANTE O VENT. SANIT. 4" PVC SDR-41

1 Cemento pvc "Tangit", 460 gramos + 25% desp.. 0.0500 u 554.48 27.722 Codo 4"x90, pvc dren. 1.00 u 60.32 60.323 Mano de obra Bajante o Vent. p/piso 1.00 u 668.06 668.064 Tubo 4", pvc SDR-41 + 10% desp. 0.67 tubo 264.04 176.91

Unid. $905.29*ISASHG 10550025 BAÑERA LIVIANA, BLANCA O A COLOR:

Page 114: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 84

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 209.65 35.642 Sifón 2", pvc drenaje 1.00 u 78.40 78.403 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.004 Codo 2"x45, pvc dren. 1.00 u 8.35 8.355 Codo 2"x90, pvc dren. 1.00 u 13.06 13.066 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.327 Tee ½" h.g. (fría y cal.) 2.00 u 17.86 35.728 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.90 tubo 522.00 469.809 Codo ½" h.g. (fría y cal.) 3.00 u 15.10 45.3010 Unión univ. ½", h.g. 2.00 u 32.64 65.2811 Niple ½"x4", h.g. 2.00 u 42.00 84.0012 Pintura OXIDO ROJO en tub. h.g. 0.09 gl 448.00 40.3213 BAÑERA liviana blanca o a color 1.00 u 5,974.00 5,974.0014 Mezcl. p/bañera, 3 puños, "SAYCO" 1.00 u 3,611.00 3,611.0015 Desagüe autom. p/bañera, pvc 1.00 u 2,302.99 2,302.9916 Sifón 2", pvc 1.00 u 78.40 78.4017 Cemento bco. 0.03 fda 600.00 18.0018 Teflón + 25% desp. 1.50 rollo 9.25 13.8819 Horm. frotado en base p/bañera 1.20 m2 664.76 797.7120 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0021 Mano de obra desagüe de 2. 1.00 u 518.80 518.8022 Mano de obra salidas ½" 3.00 u 518.80 1,556.4023 Mano de obra albañilería, base p/bañera 1.00 u 220.83 220.8324 Mano de obra coloc. mezcl. 1.00 u 518.80 518.8025 Mano de obra coloc. bañera liviana. 1.00 u 1,186.85 1,186.85

Unid. $17,787.85*ISASHG 10550026 BAÑERA HIERRO FUNDIDO, BLANCA:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 209.65 35.642 Sifón 2", pvc dren. 1.00 u 78.40 78.403 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.004 Codo 2"x45, pvc dren. 1.00 u 8.35 8.355 Codo 2"x90, pvc dren. 1.00 u 13.06 13.066 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.327 Tee ½" h.g. (fría y cal.) 2.00 u 17.86 35.728 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.90 tubo 522.00 469.809 Codo ½" h.g. (fría y cal.) 3.00 u 15.10 45.3010 Unión univ. ½", h.g. 2.00 u 32.64 65.2811 Niple ½"x4", h.g. 2.00 u 42.00 84.0012 Pintura OXIDO ROJO en tub. h.g. 0.09 gl 448.00 40.3213 BAÑERA hierro fundido bca. 1.00 u 13,304.78 13,304.7814 Mezcl. p/bañera, 3 puños, "SAYCO" 1.00 u 3,611.00 3,611.0015 Desagüe autom. p/bañera, pvc 1.00 u 2,302.99 2,302.9916 Sifón 2", pvc 1.00 u 78.40 78.4017 Cemento bco. 0.03 fda 600.00 18.0018 Teflón + 25% desp. 1.50 rollo 9.25 13.8819 Horm. frotado en base p/bañera 1.20 m2 664.76 797.7120 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0021 Mano de obra desagüe 2" 1.00 u 518.80 518.8022 Mano de obra salidas ½" 3.00 u 518.80 1,556.4023 Mano de obra albañilería, base p/bañera 1.00 u 220.83 220.8324 Mano de obra coloc. mezcl. 1.00 u 518.80 518.8025 Mano de obra coloc. bañera hierro fundido 1.00 u 1,250.00 1,250.00

Unid. $25,181.78*ISASHG 10550027 BAÑERA HIERRO FUNDIDO, A COLOR:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 209.65 35.642 Sifón 2", pvc dren. 1.00 u 78.40 78.403 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.004 Codo 2"x45, pvc dren. 1.00 u 8.35 8.355 Codo 2"x90, pvc dren. 1.00 u 13.06 13.066 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.327 Tee ½" h.g. (fría y cal.) 2.00 u 17.86 35.728 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.90 tubo 522.00 469.809 Codo ½" h.g. (fría y cal.) 3.00 u 15.10 45.3010 Unión univ. ½", h.g. 2.00 u 32.64 65.2811 Niple ½"x4", h.g. 2.00 u 42.00 84.0012 Pintura OXIDO ROJO en tub. h.g. 0.09 gl 448.00 40.3213 BAÑERA hierro fundido a color 1.00 u 12,180.00 12,180.0014 Mezcl. p/bañera, 3 puños, "SAYCO" 1.00 u 3,611.00 3,611.0015 Desagüe autom. p/bañera, pvc 1.00 u 2,302.99 2,302.9916 Sifón 2", pvc 1.00 u 78.40 78.4017 Cemento bco. 0.03 fda 600.00 18.0018 Teflón + 25% desp. 1.50 rollo 9.25 13.8819 Horm. frotado en base p/bañera 1.20 m2 664.76 797.7120 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0021 Mano de obra desagüe 2" 1.00 u 518.80 518.8022 Mano de obra salidas ½" 3.00 u 518.80 1,556.4023 Mano de obra albañilería, base p/bañera 1.00 u 220.83 220.8324 Mano de obra coloc. mezcl. 1.00 u 518.80 518.8025 Mano de obra coloc. bañera hierro fundido 1.00 u 1,250.00 1,250.00

Unid. $24,057.00*ISASHG 10550028 BIDET BLANCO:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 209.65 35.642 Sifón 2", pvc dren. 1.00 u 78.40 78.403 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.004 Codo 2"x45, pvc dren. 1.00 u 8.35 8.355 Codo 2"x90, pvc dren. 1.00 u 13.06 13.066 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.327 Tee ½" h.g. (fría y cal.) 2.00 u 17.86 35.72

Page 115: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 85

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

8 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.20 tubo 522.00 104.409 Codo ½" h.g. (fría y cal.) 4.00 u 15.10 60.4010 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 8.31 16.6211 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 448.00 8.9612 BIDET bco. 1.00 u 2,989.32 2,989.3213 Mezcl. p/bidet, completa, con boquilla 1.00 u 578.00 578.0014 Tornillos fijación 1.00 juego 13.70 13.7015 Cemento bco. 0.03 fda 600.00 18.0016 Llave angular 3/8" 2.00 u 165.00 330.0017 Niple 3/8"x2 ½", cromo 2.00 u 28.65 57.3018 Tubo flexible con tuerca 2.00 u 125.23 250.4619 Cubrefalta 3/8", cromo 2.00 u 6.88 13.7620 Teflón + 25% desp. 1.40 rollo 9.25 12.9521 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0022 Mano de obra desagüe 2" 1.00 u 518.80 518.8023 Mano de obra salidas ½" 2.00 u 518.80 1,037.6024 Mano de obra coloc. bidet 1.00 u 889.54 889.54

Unid. $7,185.30*ISASHG 10550029 BIDET A COLOR:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 209.65 35.642 Sifón 2", pvc dren. 1.00 u 78.40 78.403 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.004 Codo 2"x45, pvc dren. 1.00 u 8.35 8.355 Codo 2"x90, pvc dren. 1.00 u 13.06 13.066 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.327 Tee ½" h.g. (fría y cal.) 2.00 u 17.86 35.728 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.20 tubo 522.00 104.409 Codo ½" h.g. (fría y cal.) 4.00 u 15.10 60.4010 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 8.31 16.6211 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 448.00 8.9612 BIDET a color 1.00 u 2,734.33 2,734.3313 Mezcl. p/bidet, completa, con boquilla 1.00 u 578.00 578.0014 Tornillos fijación 1.00 juego 13.70 13.7015 Cemento bco. 0.03 fda 600.00 18.0016 Llave angular 3/8" 2.00 u 165.00 330.0017 Niple 3/8"x2 ½", cromo 2.00 u 28.65 57.3018 Tubo flexible con tuerca 2.00 u 125.23 250.4619 Cubrefalta 3/8", cromo 2.00 u 6.88 13.7620 Teflón + 25% desp. 1.40 rollo 9.25 12.9521 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0022 Mano de obra desagüe 2" 1.00 u 518.80 518.8023 Mano de obra salidas ½" 2.00 u 518.80 1,037.6024 Mano de obra coloc. bidet 1.00 u 889.54 889.54

Unid. $6,930.31*ISASHG 10550030 DESAGÜE DE PISO 2", INSTALADO (TUB. MATRIZ 4"):

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 209.65 35.642 Sifón 2", pvc dren. 1.00 u 78.40 78.403 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.004 Codo 2"x45, pvc dren. 1.00 u 8.35 8.355 Codo 2"x90, pvc dren. 1.00 u 13.06 13.066 Rejilla de piso 2", cromo 1.00 u 68.32 68.327 Cemento pvc criollo, PINTA + 25% desp. 0.16 pinta 43.00 6.888 Mano de obra desagüe 2" con parrilla 1.00 u 593.43 593.43

Unid. $863.08*ISASHG 10550031 DESAGÜE DE PISO 3", INSTALADO (TUB. MATRIZ 4"):

1 Tubo 3", pvc SDR-41 + 10% desp. 0.17 tubo 428.04 72.772 Sifón 3", pvc dren. 1.00 u 175.00 175.003 Yee red. 4"x3", pvc dren. 1.00 u 70.04 70.044 Codo 3"x45, pvc dren. 1.00 u 26.13 26.135 Codo 3"x90, pvc dren. 1.00 u 35.31 35.316 Rejilla de piso 3" x 1 ½", cromo 1.00 u 68.32 68.327 Cemento pvc criollo, PINTA + 25% desp. 0.23 pinta 43.00 9.898 Mano de obra desagüe 3" con parrilla 1.00 u 668.06 668.06

Unid. $1,125.52*ISASHG 10550032 DESAGÜE DE PISO 4", INSTALADO (TUB. MATRIZ 4"):

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 264.04 44.892 Sifón 4", pvc dren. 1.00 u 1,762.21 1,762.213 Yee de 4"x4", pvc dren. 1.00 u 59.14 59.144 Codo 4"x45, pvc dren. 1.00 u 40.62 40.625 Codo 4"x90, pvc dren. 1.00 u 60.32 60.326 Rejilla de piso 4", aluminio 1.00 u 28.65 28.657 Cemento pvc criollo, PINTA + 25% desp. 0.30 pinta 43.00 12.908 Mano de obra desagüe 4" con parrilla 1.00 u 668.06 668.06

Unid. $2,676.79*ISASHG 10550033 DESAGÜE DE PISO 4", INSTALADO (TUB. MATRIZ 6"):

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 264.04 44.892 Sifón 4", pvc dren. 1.00 u 1,762.21 1,762.213 Yee de 6"x4", pvc dren. 1.00 u 822.00 822.004 Codo 4"x45, pvc dren. 1.00 u 40.62 40.625 Codo 4"x90, pvc dren. 1.00 u 60.32 60.326 Rejilla de piso 4", aluminio 1.00 u 28.65 28.657 Cemento pvc criollo, PINTA + 25% desp. 0.30 pinta 43.00 12.908 Mano de obra desagüe 4" 1.00 u 668.06 668.06

Unid. $3,439.65*ISASHG 10550034 DUCHA: (Agua fría solamente)

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 209.65 35.642 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.35

Page 116: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 86

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

4 Codo 2"x90, pvc dren. 1.00 u 13.06 13.065 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ½" h.g. (fría y cal.) 1.00 u 17.86 17.867 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.51 tubo 522.00 266.228 Codo ½" h.g. (fría y cal.) 2.00 u 15.10 30.209 Unión univ. ½", h.g. 2.00 u 32.64 65.2810 Niple ½"x4", h.g. 2.00 u 42.00 84.0011 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 448.00 22.4012 Ducha cte. plástica, ½", cromo 1.00 u 81.55 81.5513 Llave de empotrar ½", cromo, NIBCO 1.00 u 482.40 482.4014 Sifón 2", pvc + rejilla de piso 2" 1.00 u 146.72 146.7215 Cemento bco. 0.03 fda 600.00 18.0016 Teflón + 25% desp. 1.00 rollo 9.25 9.2517 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0018 Mano de obra desagüe de 2 con parrilla 1.00 u 593.43 593.4319 Mano de obra salidas ½" 1.00 u 518.80 518.8020 Mano de obra coloc. llave de empotrar 1.00 u 296.11 296.1121 Mano de obra coloc. ducha 1.00 u 296.11 296.11

Unid. $3,099.70*ISASHG 10550035 FREG. A. INOX. DOBLE, H.G., MANGUERA:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ½" h.g. (fría y cal.) 3.00 u 17.86 53.587 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 522.00 245.348 Codo ½" h.g. (fría y cal.) 5.00 u 15.10 75.509 Red. bushing ½" a 3/8", h.g. (fría y cal.) 3.00 u 8.31 24.9310 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 448.00 22.4011 FREG. DOBLE a. inox.. 1.00 u 1,316.89 1,316.8912 Mezcl. "SAYCO" con manguera 1.00 u 2,047.01 2,047.0113 Boquilla para freg., cromo 2.00 u 137.75 275.5014 Sifón 1 ½", pvc 1.00 u 134.68 134.6815 Desagüe doble para freg., pvc 1.00 u 139.00 139.0016 "Silicone" para sellar (tubo) 1.00 u 176.11 176.1117 Cemento bco. 0.03 fda 600.00 18.0018 Llave angular 3/8" 2.00 u 165.00 330.0019 Niple 3/8"x2 ½", cromo 2.00 u 28.65 57.3020 Cubrefalta 3/8", cromo 2.00 u 6.88 13.7621 Tubo flexible con tuerca 2.00 u 125.23 250.4622 Teflón + 25% desp. 2.00 rollo 9.25 18.5023 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7524 Mano de obra desagüe 2" 1.00 u 518.80 518.8025 Mano de obra salidas ½" 2.00 u 518.80 1,037.6026 Mano de obra coloc. fregadero doble 1.00 u 950.93 950.93

Unid. $7,973.01*ISASHG 10550036 FREG. A. INOX. SENCILLO, H.G., MANGUERA:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ½" h.g. (fría y cal.) 3.00 u 17.86 53.587 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 522.00 245.348 Codo ½" h.g. (fría y cal.) 5.00 u 15.10 75.509 Red. bushing ½" a 3/8", h.g. (fría y cal.) 3.00 u 8.31 24.9310 Pintura OXIDO ROJO en tub.s h.g. 0.05 gl 448.00 22.4011 FREG. SENCILLO a. inox. 1.00 u 1,614.43 1,614.4312 Mezcl. "SAYCO" con manguera 1.00 u 2,047.01 2,047.0113 Boquilla para freg., cromo 2.00 u 137.75 275.5014 Sifón 1 ½", pvc 1.00 u 134.68 134.6815 Desagüe doble para fregadero, pvc 1.00 u 139.00 139.0016 "Silicone" para sellar (tubo) 1.00 u 176.11 176.1117 Cemento bco. 0.03 fda 600.00 18.0018 Llave angular 3/8" 2.00 u 165.00 330.0019 Niple 3/8"x2 ½", cromo 2.00 u 28.65 57.3020 Cubrefalta 3/8", cromo 2.00 u 6.88 13.7621 Tubo flexible con tuerca 2.00 u 125.23 250.4622 Teflón + 25% desp. 2.00 rollo 9.25 18.5023 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7524 Mano de obra desagüe 2" 1.00 u 518.80 518.8025 Mano de obra salidas ½" 2.00 u 668.06 1,336.1226 Mano de obra coloc. fregadero sencillo 1.00 u 742.69 742.69

Unid. $8,360.83*ISASHG 10550037 INODORO BCO., TAPA: BAÑO SERVICIO

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 264.04 44.892 Yee de 4"x4", pvc dren. 1.00 u 59.14 59.143 Codo 4"x45, pvc dren. 1.00 u 40.62 40.624 Codo 4"x90, pvc dren. 1.00 u 60.32 60.325 Cemento pvc criollo, PINTA + 25% desp. 0.35 pinta 43.00 15.056 Tee ½" h.g. (fría y cal.) 1.00 u 17.86 17.867 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.17 tubo 522.00 88.748 Codo ½" h.g. (fría y cal.) 2.00 u 15.10 30.209 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 8.31 8.3110 Pintura OXIDO ROJO en tub.s h.g. 0.02 gl 448.00 8.9611 INODORO corriente, bco., CON tapa 1.00 u 2,943.00 2,943.0012 Arandela pvc 4", para fijar inodoro 1.00 u 27.26 27.26

Page 117: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 87

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

13 Tornillos fijación 1.00 juego 13.70 13.7014 Junta de cera. 1.00 u 37.00 37.0015 Cemento bco. 0.04 fda 600.00 24.0016 Llave angular 3/8" 1.00 u 165.00 165.0017 Niple 3/8"x2 ½", cromo 1.00 u 28.65 28.6518 Cubrefalta 3/8", cromo 1.00 u 6.88 6.8819 Tubo flexible con tuerca 1.00 u 136.65 136.6520 Teflón + 25% desp. 0.70 rollo 9.25 6.4821 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0022 Mano de obra desagüe 4" 1.00 u 668.06 668.0623 Mano de obra salidas ½" 1.00 u 668.06 668.0624 Mano de obra coloc. Inodoro 1.00 u 593.43 593.43

Unid. $5,737.26*ISASHG 10550038 INODORO, BCO., TAPA: BAÑO SERV.

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 264.04 44.892 Yee de 4"x4", pvc dren. 1.00 u 59.14 59.143 Codo 4"x45, pvc dren. 1.00 u 40.62 40.624 Codo 4"x90, pvc dren. 1.00 u 60.32 60.325 Cemento pvc criollo, PINTA + 25% desp. 0.35 pinta 43.00 15.056 Tee ½" h.g. (fría y cal.) 1.00 u 17.86 17.867 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.17 tubo 522.00 88.748 Codo ½" h.g. (fría y cal.) 2.00 u 15.10 30.209 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 8.31 8.3110 Pintura OXIDO ROJO en tub.s h.g. 0.02 gl 448.00 8.9611 INODORO corriente, bco., tapa 1.00 u 2,920.00 2,920.0012 Arandela pvc 4", para fijar inodoro 1.00 u 27.26 27.2613 Tornillos fijación 1.00 juego 13.70 13.7014 Junta de cera. 1.00 u 37.00 37.0015 Cemento bco. 0.04 fda 600.00 24.0016 Llave angular 3/8" 1.00 u 165.00 165.0017 Niple 3/8"x2 ½", cromo 1.00 u 28.65 28.6518 Cubrefalta 3/8", cromo 1.00 u 6.88 6.8819 Tubo flexible con tuerca 1.00 u 136.65 136.6520 Teflón + 25% desp. 0.70 rollo 9.25 6.4821 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0022 Mano de obra desagüe 4" 1.00 u 668.06 668.0623 Mano de obra salidas ½" 1.00 u 668.06 668.0624 Mano de obra coloc. Inodoro 1.00 u 593.43 593.43

Unid. $5,714.26*ISASHG 10550039 INODORO ALARGADO BCO.:

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 264.04 44.892 Yee de 4"x4", pvc dren. 1.00 u 59.14 59.143 Codo 4"x45, pvc dren. 1.00 u 40.62 40.624 Codo 4"x90, pvc dren. 1.00 u 60.32 60.325 Cemento pvc criollo, PINTA + 25% desp. 0.35 pinta 43.00 15.056 Tee ½" h.g. (fría y cal.) 1.00 u 17.86 17.867 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.17 tubo 522.00 88.748 Codo ½" h.g. (fría y cal.) 2.00 u 15.10 30.209 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 8.31 8.3110 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 448.00 8.9611 INODORO alargado, bco., tapa 1.00 u 4,796.48 4,796.4812 Arandela pvc 4", para fijar inodoro 1.00 u 27.26 27.2613 Tornillos fijación 1.00 juego 13.70 13.7014 Junta de cera. 1.00 u 37.00 37.0015 Cemento bco. 0.04 fda 600.00 24.0016 Llave angular 3/8" 1.00 u 165.00 165.0017 Niple 3/8"x2 ½", cromo 1.00 u 28.65 28.6518 Cubrefalta 3/8", cromo 1.00 u 6.88 6.8819 Tubo flexible con tuerca 1.00 u 136.65 136.6520 Teflón + 25% desp. 0.70 rollo 9.25 6.4821 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0022 Mano de obra desagüe 4" 1.00 u 668.06 668.0623 Mano de obra salidas ½" 1.00 u 668.06 668.0624 Mano de obra coloc. Inodoro 1.00 u 593.43 593.43

Unid. $7,590.74*ISASHG 10550040 INODORO ALARGADO A COLOR:

1 Tubo 4", pvc SDR-41 + 10% desp. 0.17 tubo 264.04 44.892 Yee de 4"x4", pvc dren. 1.00 u 59.14 59.143 Codo 4"x45, pvc dren. 1.00 u 40.62 40.624 Codo 4"x90, pvc dren. 1.00 u 60.32 60.325 Cemento pvc criollo, PINTA + 25% desp. 0.35 pinta 43.00 15.056 Tee ½" h.g. (fría y cal.) 1.00 u 17.86 17.867 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.17 tubo 522.00 88.748 Codo ½" h.g. (fría y cal.) 2.00 u 15.10 30.209 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 8.31 8.3110 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 448.00 8.9611 INODORO alargado, color, tapa 1.00 u 6,431.01 6,431.0112 Arandela pvc de 4", para fijar inodoro 1.00 u 27.26 27.2613 Tornillos fijación 1.00 juego 13.70 13.7014 Junta de cera. 1.00 u 37.00 37.0015 Cemento bco. 0.04 fda 600.00 24.0016 Llave angular 3/8" 1.00 u 165.00 165.0017 Niple 3/8"x2 ½", cromo 1.00 u 28.65 28.6518 Cubrefalta 3/8", cromo 1.00 u 6.88 6.8819 Tubo flexible con tuerca 1.00 u 136.65 136.6520 Teflón + 25% desp. 0.70 rollo 9.25 6.4821 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0022 Mano de obra desagüe 4" 1.00 u 668.06 668.06

Page 118: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 88

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

23 Mano de obra salidas ½" 1.00 u 668.06 668.0624 Mano de obra coloc. Inodoro 1.00 u 593.43 593.43

Unid. $9,225.27*ISASHG 10550041 LAVADERO GRANITO BCO., DOBLE:

1 Tubo 2", pvc SDR-41 + 10% desp. (enterrado). 0.17 tubo 209.65 35.642 Tubo 1 ½", pvc dren. + 10% desp. (visible). 0.22 tubo 136.78 30.093 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.004 Codo 2"x45, pvc dren. 1.00 u 8.35 8.355 Codo 2"x90, pvc dren. 1.00 u 13.06 13.066 Sifón 2", pvc 1.00 u 78.40 78.407 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.328 Tee ½" h.g. (fría y cal.) 2.00 u 17.86 35.729 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.46 tubo 522.00 240.1210 Codo ½" h.g. (fría y cal.) 4.00 u 15.10 60.4011 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 448.00 22.4012 Lavadero GRANITO, doble 1.00 u 3,617.37 3,617.3713 Transporte lavadero Sto. Dgo., (variable) 1.00 u 116.00 116.0014 Boquilla para lavadero, cromo, con tapón 2.00 u 88.16 176.3215 Parrilla de piso 4", aluminio 1.00 u 28.65 28.6516 Cemento bco. 0.03 fda 600.00 18.0017 Llave de chorro ½" 2.00 u 338.99 677.9818 Teflón + 25% desp. 1.10 rollo 9.25 10.1819 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0020 Mano de obra desagüe 2" 1.00 u 518.80 518.8021 Mano de obra salida ½" 2.00 u 518.80 1,037.6022 Mano de obra coloc. lavadero doble 1.00 u 668.06 668.06

Unid. $7,507.46*ISASHG 10550042 LAVADERO GRANITO BCO., SENCILLO:

1 Tubo 2", pvc SDR-41 + 10% desp. (enterrado). 0.17 tubo 209.65 35.642 Tubo 1 ½", pvc dren. + 10% desp. (visible). 0.11 tubo 136.78 15.053 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.004 Codo 2"x45, pvc dren. 1.00 u 8.35 8.355 Codo 2"x90, pvc dren. 1.00 u 13.06 13.066 Sifón 2", pvc 1.00 u 78.40 78.407 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.328 Tee ½" h.g. (fría y cal.) 1.00 u 17.86 17.869 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.37 tubo 522.00 193.1410 Codo ½" h.g. (fría y cal.) 2.00 u 15.10 30.2011 Pintura OXIDO ROJO en tub. h.g. 0.04 gl 448.00 17.9212 Lavadero GRANITO, sencillo 1.00 u 2,305.86 2,305.8613 Transporte lavadero Sto. Dgo., (variable) 1.00 u 58.00 58.0014 Boquilla para lavadero, cromo, con tapón 1.00 u 88.16 88.1615 Parrilla de piso 4", aluminio 1.00 u 28.65 28.6516 Cemento bco. 0.03 fda 600.00 18.0017 Llave de chorro ½" 1.00 u 338.99 338.9918 Teflón + 25% desp. 0.50 rollo 9.25 4.6319 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0020 Mano de obra desagüe 2" 1.00 u 518.80 518.8021 Mano de obra salida ½" 1.00 u 518.80 518.8022 Mano de obra tub. ½" en piso 0.60 m 10.83 6.5023 Mano de obra coloc. lavadero sencillo 1.00 u 518.80 518.80

Unid. $4,929.13*ISASHG 10550043 LAVAMANOS 19"x17", BCO.:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ½" h.g. (fría y cal.) 2.00 u 17.86 35.727 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 522.00 245.348 Codo ½" h.g. (fría y cal.) 4.00 u 15.10 60.409 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 8.31 16.6210 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 448.00 22.4011 Lavamanos 19"x17", BCO. 1.00 u 1,187.96 1,187.9612 Mezcl. "SAYCO" con boquilla cromo 1.00 u 1,760.00 1,760.0013 Sifón 1 ¼", cromo, NIBCO 1.00 u 475.60 475.6014 Cola ext. 1 ¼"x8", cromo 1.00 u 148.00 148.0015 Cemento bco. 0.03 fda 600.00 18.0016 Llave angular 3/8" 2.00 u 165.00 330.0017 Niple 3/8"x2 ½", cromo 2.00 u 28.65 57.3018 Cubrefalta 3/8", cromo 2.00 u 6.88 13.7619 Tubo flexible con tuerca 2.00 u 125.23 250.4620 Teflón + 25% desp. 1.40 rollo 9.25 12.9521 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7522 Mano de obra desagüe 2" 1.00 u 518.80 518.8023 Mano de obra salidas ½" 2.00 u 518.80 1,037.6024 Mano de obra coloc. lavamanos 1.00 u 593.43 593.43

Unid. $7,051.06*ISASHG 10550044 LAVAMANOS 19"x17", COLOR:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ½" h.g. (fría y cal.) 2.00 u 17.86 35.727 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 522.00 245.348 Codo ½" h.g. (fría y cal.) 4.00 u 15.10 60.409 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 8.31 16.62

Page 119: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 89

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

10 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 448.00 22.4011 Lavamanos 19"x17", color 1.00 u 1,601.99 1,601.9912 Mezcl. "SAYCO" con boquilla cromo 1.00 u 1,760.00 1,760.0013 Sifón 1 ¼", cromo, NIBCO 1.00 u 475.60 475.6014 Cola ext. 1 ¼"x8", cromo 1.00 u 148.00 148.0015 Cemento bco. 0.03 fda 600.00 18.0016 Llave angular 3/8" 2.00 u 165.00 330.0017 Niple 3/8"x2 ½", cromo 2.00 u 28.65 57.3018 Cubrefalta 3/8", cromo 2.00 u 6.88 13.7619 Tubo flexible con tuerca 2.00 u 125.23 250.4620 Teflón + 25% desp. 1.40 rollo 9.25 12.9521 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7522 Mano de obra desagüe 2" 1.00 u 518.80 518.8023 Mano de obra salidas ½" 2.00 u 518.80 1,037.6024 Mano de obra coloc. lavamanos 1.00 u 593.43 593.43

Unid. $7,465.09*ISASHG 10550045 LAVAMANOS OVALADO BCO., empotrar:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ½" h.g. (fría y cal.) 2.00 u 17.86 35.727 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 522.00 245.348 Codo ½" h.g. (fría y cal.) 4.00 u 15.10 60.409 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 8.31 16.6210 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 448.00 22.4011 Lav. ovalado, BCO., empotrar, "SAONA" 1.00 u 2,188.00 2,188.0012 Mezcl. "SAYCO" con boquilla cromo 1.00 u 1,760.00 1,760.0013 Sifón 1 ¼", cromo, NIBCO 1.00 u 475.60 475.6014 Cola ext. 1 ¼"x8", cromo 1.00 u 148.00 148.0015 Cemento bco. 0.03 fda 600.00 18.0016 Llave angular 3/8" 2.00 u 165.00 330.0017 Niple 3/8"x2 ½", cromo 2.00 u 28.65 57.3018 Cubrefalta 3/8", cromo 2.00 u 6.88 13.7619 Tubo flexible con tuerca 2.00 u 125.23 250.4620 Teflón + 25% desp. 1.40 rollo 9.25 12.9521 "Silicone" para sellar (tubo) 0.25 u 176.11 44.0322 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7523 Mano de obra desagüe 2" 1.00 u 518.80 518.8024 Mano de obra salidas ½" 2.00 u 518.80 1,037.6025 Mano de obra coloc. lavamanos 1.00 u 593.43 593.43

Unid. $8,095.13*ISASHG 10550046 LAVAMANOS OVALADO COLOR, empotrar:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ½" h.g. (fría y cal.) 2.00 u 17.86 35.727 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.47 tubo 522.00 245.348 Codo ½" h.g. (fría y cal.) 4.00 u 15.10 60.409 Red. bushing ½" a 3/8", h.g. (fría y cal.) 2.00 u 8.31 16.6210 Pintura OXIDO ROJO en tub. h.g. 0.05 gl 448.00 22.4011 Lavamanos ovalado, COLOR, "SAONA" 1.00 u 2,302.60 2,302.6012 Mezcl. "SAYCO" con boquilla cromo 1.00 u 1,760.00 1,760.0013 Sifón 1 ¼", cromo, NIBCO 1.00 u 475.60 475.6014 Cola ext. 1 ¼"x8", cromo 1.00 u 148.00 148.0015 Cemento bco. 0.03 fda 600.00 18.0016 Llave angular 3/8" 2.00 u 165.00 330.0017 Niple 3/8"x2 ½", cromo 2.00 u 28.65 57.3018 Cubrefalta 3/8", cromo 2.00 u 6.88 13.7619 Tubo flexible con tuerca 2.00 u 125.23 250.4620 Teflón + 25% desp. 1.40 rollo 9.25 12.9521 "Silicone" para sellar (tubo) 0.25 u 176.11 44.0322 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7523 Mano de obra desagüe 2" 1.00 u 518.80 518.8024 Mano de obra salidas ½" 2.00 u 518.80 1,037.6025 Mano de obra coloc. lavamanos 1.00 u 593.43 593.43

Unid. $8,209.73*ISASHG 10550047 LAVAMANOS PEQUEÑO, BCO.: BAÑO SERV.

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ½" h.g. (fría y cal.) 1.00 u 17.86 17.867 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.24 tubo 522.00 125.288 Codo ½" h.g. (fría y cal.) 2.00 u 15.10 30.209 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 8.31 8.3110 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 448.00 8.9611 Lavamanos BCO. pequeño, "SIMPLEX" 1.00 u 719.99 719.9912 Llave sencilla, cromo 1.00 u 586.03 586.0313 Boquilla para lavamanos, pvc 1.00 u 70.30 70.3014 Sifón 1 ¼", pvc 1.00 u 78.00 78.0015 Cemento bco. 0.03 fda 600.00 18.0016 Llave angular 3/8" 1.00 u 165.00 165.0017 Niple 3/8"x2 ½", cromo 1.00 u 28.65 28.65

Page 120: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 90

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

18 Cubrefalta 3/8", cromo 1.00 u 6.88 6.8819 Tubo flexible pvc 1.00 u 253.46 253.4620 Teflón + 25% desp. 0.70 rollo 9.25 6.4821 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7522 Mano de obra desagüe 2" 1.00 u 518.80 518.8023 Mano de obra salidas ½" 1.00 u 518.80 518.8024 Mano de obra coloc. lavamanos 1.00 u 593.43 593.43

Unid. $4,021.15*ISASHG 10550048 ORINAL ½ FALDA, BCO.:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ½" h.g. (fría y cal.) 1.00 u 17.86 17.867 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.24 tubo 522.00 125.288 Codo ½" h.g. (fría y cal.) 2.00 u 15.10 30.209 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 8.31 8.3110 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 448.00 8.9611 Orinal ½ falda "Yaque" 1.00 u 9,784.00 9,784.0012 Llave cromada p/orinal 1.00 u 555.59 555.5913 Niple 3/8"x2 ½", cromo 1.00 u 28.65 28.6514 Cubrefalta 3/8", cromo 1.00 u 6.88 6.8815 Tubo flexible con tuerca 1.00 u 125.23 125.2316 Teflón + 25% desp. 0.70 rollo 9.25 6.4817 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7518 Mano de obra desagüe 2" 1.00 u 518.80 518.8019 Mano de obra salidas ½" 1.00 u 518.80 518.8020 Mano de obra coloc. Orinal ½ falda 1.00 u 668.06 668.06

Unid. $12,669.82*ISASHG 10550049 ORINAL ½ FALDA, BCO., FLUXOMETRO:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ¾" h.g. 1.00 u 22.01 22.017 Tubo ¾" h.g. + 10% desp. 0.24 tubo 693.68 166.488 Codo ¾" h.g. 2.00 u 14.50 29.009 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 448.00 8.9610 Orinal ½ falda "Yaque" 1.00 u 9,784.00 9,784.0011 Válvula fluxómetro ¾" 1.00 u 3,849.00 3,849.0012 Teflón + 25% desp. 0.50 rollo 9.25 4.6313 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7514 Mano de obra desagüe 2" 1.00 u 518.80 518.8015 Mano de obra salidas ½" 1.00 u 668.06 668.0616 Mano de obra coloc. Orinal ½ falda 1.00 u 668.06 668.06

Unid. $15,985.72*ISASHG 10550050 ORINAL FALDA COMPLETA, BCO.:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ½" h.g. (fría y cal.) 1.00 u 17.86 17.867 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.24 tubo 522.00 125.288 Codo ½" h.g. (fría y cal.) 2.00 u 15.10 30.209 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 8.31 8.3110 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 448.00 8.9611 Orinal falda completa "Yaque" 1.00 u 9,092.20 9,092.2012 Llave cromada p/orinal 1.00 u 555.59 555.5913 Niple 3/8"x2 ½", cromo 1.00 u 28.65 28.6514 Cubrefalta 3/8", cromo 1.00 u 6.88 6.8815 Tubo flexible con tuerca 1.00 u 125.23 125.2316 Teflón + 25% desp. 0.70 rollo 9.25 6.4817 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7518 Mano de obra desagüe 2" 1.00 u 518.80 518.8019 Mano de obra salidas ½" 1.00 u 668.06 668.0620 Mano de obra coloc. Orinal falda completa 1.00 u 1,038.80 1,038.80

Unid. $12,498.02*ISASHG 10550051 ORINAL FALDA COMPLETA, BCO., FLUXOMETRO:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ¾" h.g. 1.00 u 22.01 22.017 Tubo ¾" h.g. + 10% desp. 0.24 tubo 693.68 166.488 Codo ¾" h.g. 2.00 u 14.50 29.009 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 448.00 8.9610 Orinal falda completa "Yaque" 1.00 u 9,092.20 9,092.2011 Válvula fluxómetro ¾" 1.00 u 3,849.00 3,849.0012 Teflón + 25% desp. 0.50 rollo 9.25 4.6313 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7514 Mano de obra desagüe 2" 1.00 u 518.80 518.8015 Mano de obra salidas ¾". 1.00 u 668.06 668.0616 Mano de obra coloc. Orinal falda completa 1.00 u 1,038.80 1,038.80

Unid. $15,664.66

Page 121: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 91

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*ISASHG 10550052 ORINAL PEQUEÑO, BCO.:1 Tubo 2", pvc SDR-41 + 10% desp. 0.33 tubo 209.65 69.182 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 2.00 u 13.06 26.125 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.326 Tee ½" h.g. (fría y cal.) 1.00 u 17.86 17.867 Tubo ½" h.g. + 10% desp. (fría y cal.) 0.24 tubo 522.00 125.288 Codo ½" h.g. (fría y cal.) 2.00 u 15.10 30.209 Red. bushing ½" a 3/8", h.g. (fría y cal.) 1.00 u 8.31 8.3110 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 448.00 8.9611 1.00 u 2,420.60 2,420.6012 Llave cromada p/orinal pequeño 1.00 u 555.59 555.5913 Niple 3/8"x2 ½", cromo 1.00 u 28.65 28.6514 Cubrefalta 3/8", cromo 1.00 u 6.88 6.8815 Tubo flexible con tuerca 1.00 u 125.23 125.2316 Teflón + 25% desp. 0.70 rollo 9.25 6.4817 Excavar y tapar zanja (tierra) 0.25 día 375.00 93.7518 Mano de obra desagüe 2" 1.00 u 518.80 518.8019 Mano de obra salidas ½" 1.00 u 518.80 518.8020 Mano de obra coloc. Orinal pequeño 1.00 u 742.69 742.69

Unid. $5,381.05*ISASHG 10550053 VERTEDERO O TINA DE GRANITO, GRIS:

1 Tubo 2", pvc SDR-41 + 10% desp. 0.17 tubo 209.65 35.642 Yee red. 4"x2", pvc dren. 1.00 u 59.00 59.003 Codo 2"x45, pvc dren. 1.00 u 8.35 8.354 Codo 2"x90, pvc dren. 1.00 u 13.06 13.065 Sifón 2", pvc 1.00 u 78.40 78.406 Cemento pvc criollo, PINTA + 25% desp. 0.24 pinta 43.00 10.327 Tee ½" galv. 1.00 u 17.86 17.868 Tubo ½" galv. + 10% desp. 0.24 tubo 522.00 125.289 Codo ½" galv. 2.00 u 15.10 30.2010 Pintura OXIDO ROJO en tub. h.g. 0.02 gl 448.00 8.9611 Vertedero de GRANITO de una boca 1.00 u 1,794.50 1,794.5012 Transporte vertedero en Sto. Dgo. (variable) 1.00 u 58.00 58.0013 Parrilla de piso 4", aluminio 1.00 u 28.65 28.6514 Cemento bco. 0.03 fda 600.00 18.0015 Llave de chorro ½" 1.00 u 338.99 338.9916 Teflón + 25% desp. 0.50 rollo 9.25 4.6317 Excavar y tapar zanja (tierra) 0.12 día 375.00 45.0018 Mano de obra desagüe 2" 1.00 u 593.43 593.4319 Mano de obra salida ½" 1.00 u 518.80 518.8020 Mano de obra tub. ½" en piso 0.30 m 10.83 3.2521 Mano de obra coloc. vertedero sencillo 1.00 u 149.26 149.26

Unid. $3,939.58

*ISCIS 10590000 INST. SANITARIA: CAMARAS INSP., CISTERNAS, SEPTICOS Y TRAMPAS DE GRASA

*ISCIS 10590001 CAMARA INSP., CALICHE, .60X.60X.60 M. INT.:1 Excavación caliche (.8x.8x.8 m.). 0.512 m3 382.65 195.922 Bote material excavado 0.690 m3 300.00 207.003 Horm. 1:3:5 en losas 0.049 m3 3,572.06 175.034 Acero ¼" incrustado losa 0.003 qq 1,088.60 3.275 Acero 3/8" x 20' grado 40 en tapa 0.180 qq 1,915.88 344.866 Bloques 4" sin mano de obra albañilería 1.646 m2 500.68 824.127 Horm. 1:3:5 en int. 0.029 m3 3,572.06 103.598 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0069 m3 6,371.00 43.969 Mano de obra 1.00 u 766.67 766.67

Unid. $2,664.42*ISCIS 10590002 CAMARA INSP., ROCA, .60X.60X.60 M. INT.:

1 Excavación roca (.8x.8x.8 m.). 0.512 m3 1,635.30 837.272 Bote material excavado 0.820 m3 300.00 246.003 Horm. 1:3:5 en losas 0.049 m3 3,572.06 175.034 Acero ¼" incrustado losa 0.003 qq 1,088.60 3.275 Acero 3/8" x 20' grado 40 en tapa 0.180 qq 1,915.88 344.866 Bloques 4" sin mano de obra albañilería 1.646 m2 500.68 824.127 Horm. 1:3:5 en int. 0.029 m3 3,572.06 103.598 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0069 m3 6,371.00 43.969 Mano de obra 1.00 u 766.67 766.67

Unid. $3,344.77*ISCIS 10590003 CAMARA INSP., TIERRA, .60X.60X.60 M. INT.:

1 Excavación en tierra (.8x.8x.8 m.). 0.512 m3 235.85 120.762 Bote material excavado 0.670 m3 300.00 201.003 Horm. 1:3:5 en losas 0.049 m3 3,572.06 175.034 Acero ¼" incrustado losa 0.003 qq 1,088.60 3.275 Acero 3/8" x 20' grado 40 en tapa 0.180 qq 1,915.88 344.866 Bloques 4" sin mano de obra albañilería 1.800 m2 500.68 901.227 Horm. 1:3:5 en int. 0.029 m3 3,572.06 103.598 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0069 m3 6,371.00 43.969 Mano de obra 1.00 u 766.67 766.67

Unid. $2,660.36*ISCIS 10590004 CAMARA SEPTICA, CALICHE, 1.70X3.40X1.60 M. INT.:

1 Excav. caliche (2.00x3.70x2.00 mt.). 14.80 m3 382.65 5,663.222 Bote material excavado 19.98 m3 300.00 5,994.003 Horm. 1:2:4 en losas 1.156 m3 3,963.92 4,582.294 Acero 3/8" x 20' grado 40 en losas 1.550 qq 1,915.88 2,969.615 Bloques 6" 18.20 m2 802.34 14,602.596 Horm. 1:3:5 llenado todos los hoyos 0.568 m3 3,572.06 2,028.93

Orinal pequeño, bco. "Simplex"

Page 122: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 92

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

7 Madera bruta amer. (4 usos) 40.40 pt 29.00 1,171.608 Clavos corrientes (5 lb. / 100 pie madera) 8.08 lb 24.79 200.309 Clavos de acero (.08 lb / m2) 0.46 lb 45.24 20.8110 Alambre calibre #14 (.15 lb. / m2) 0.87 lb 25.44 22.1311 Confección madera 5.78 m2 106.98 618.3412 Desencofrado 5.78 m2 22.82 131.9013 Empañete pulido int. 22.10 m2 233.49 5,160.13

Unid. $43,165.85*ISCIS 10590005 CAMARA SEPTICA, ROCA, 1.70X3.40X1.60 M. INT.:

1 Excav. roca a mano (2.00x3.70x2.00 mt.). 14.80 m3 781.25 11,562.502 Bote material excavado 23.68 m3 300.00 7,104.003 Horm. 1:2:4 en losas 1.156 m3 3,963.92 4,582.294 Acero 3/8" x 20' grado 40 en losas 1.550 qq 1,915.88 2,969.615 Bloques 6" 18.20 m2 802.34 14,602.596 Horm. 1:3:5 llenado todos los hoyos 0.568 m3 3,572.06 2,028.937 Madera bruta amer. (4 usos) 40.40 pt 29.00 1,171.608 Clavos corrientes (5 lb. / 100 pie madera) 8.08 lb 24.79 200.309 Clavos de acero (.08 lb / m2) 0.46 lb 45.24 20.8110 Alambre calibre #14 (.15 lb. / m2) 0.87 lb 25.44 22.1311 Confección madera 5.78 m2 106.98 618.3412 Desencofrado 5.78 m2 22.82 131.9013 Empañete pulido int. 22.10 m2 233.49 5,160.13

Unid. $50,175.13*ISCIS 10590006 CAMARA SEPTICA, TIERRA, 1.70X3.40X1.60 M. INT.:

1 Excav. tierra (2.00x3.70x2.00 mt.). 14.80 m3 235.85 3,490.582 Bote material excavado 19.24 m3 300.00 5,772.003 Horm. 1:2:4 en losas 1.156 m3 3,963.92 4,582.294 Acero 3/8" x 20' grado 40 en losas 1.550 qq 1,915.88 2,969.615 Bloques 6" 18.20 m2 802.34 14,602.596 Horm. 1:3:5 llenado todos los hoyos 0.568 m3 3,572.06 2,028.937 Madera bruta amer. (4 usos) 40.40 pt 29.00 1,171.608 Clavos corrientes (5 lb. / 100 pie madera) 8.08 lb 24.79 200.309 Clavos de acero (.08 lb / m2) 0.46 lb 45.24 20.8110 Alambre calibre #14 (.15 lb. / m2) 0.87 lb 25.44 22.1311 Confección madera 5.78 m2 106.98 618.3412 Desencofrado 5.78 m2 22.82 131.9013 Empañete pulido int. 22.10 m2 233.49 5,160.13

Unid. $40,771.21*ISCIS 10590007 CISTERNA 4,000 GLS., CALICHE, 2.50X3.50X2.00 M. INT.:

1 Excav. en caliche (3.00x4.00x2.50 m.). 30.00 m3 382.65 11,479.502 Bote material excavado 40.50 m3 300.00 12,150.003 Horm. 1:2:4 en losas (losa piso y losa superior h=0.12 m.). 2.49 m3 3,963.92 9,870.164 Acero 3/8" x 20' grado 40 en losa piso 1.56 qq 1,915.88 2,988.775 Acero 3/8" x 20' grado 40 en losa superior 3.12 qq 1,915.88 5,977.556 Bloques 8" todos los hoyos llenos 25.60 m2 1,263.19 32,337.667 Madera bruta amer. (4 usos) 61.15 pt 29.00 1,773.358 Clavos corrientes (5 lb. / 100 pie madera) 12.23 lb 24.79 303.189 Clavos de acero (.08 lb / m2) 0.70 lb 45.24 31.6710 Alambre calibre #14 (.15 lb. / m2) 1.31 lb 25.44 33.3311 Confección madera 8.75 m2 106.98 936.0812 Desencofrado 8.75 m2 22.82 199.6813 Empañete pulido int. 32.75 m2 233.49 7,646.8014 Zabaletas en esq. paredes int. y en piso 20.00 m 68.51 1,370.2015 Bloques 6" en tapa 2.04 m2 802.34 1,636.7716 Empañete liso en tapa 4.59 m2 347.95 1,597.0917 Cantos en tapa 9.20 m 72.49 666.9118 Tapa de hierro 1.00 u 2,662.20 2,662.20

Unid. $93,660.90*ISCIS 10590008 CISTERNA 4,000 GLS., ROCA, 2.50X3.50X2.00 M. INT.:

1 Excav. roca a mano (3.00x4.00x2.50 m.). 30.00 m3 781.25 23,437.502 Bote material excavado 48.00 m3 300.00 14,400.003 Horm. 1:2:4 en losas (losa piso y losa superior h=0.12 m.). 2.49 m3 3,963.92 9,870.164 Acero 3/8" x 20' grado 40 en losa piso 1.56 qq 1,915.88 2,988.775 Acero 3/8" x 20' grado 40 en losa superior 3.12 qq 1,915.88 5,977.556 Bloques 8" todos los hoyos llenos 25.60 m2 1,263.19 32,337.667 Madera bruta amer. (4 usos) 61.15 pt 29.00 1,773.358 Clavos corrientes (5 lb. / 100 pie madera) 12.23 lb 24.79 303.189 Clavos de acero (.08 lb / m2) 0.70 lb 45.24 31.6710 Alambre calibre #14 (.15 lb. / m2) 1.31 lb 25.44 33.3311 Confección madera 8.75 m2 106.98 936.0812 Desencofrado 8.75 m2 22.82 199.6813 Empañete pulido int. 32.75 m2 233.49 7,646.8014 Zabaletas en esq. paredes int. y en piso 20.00 m 68.51 1,370.2015 Bloques 6" en tapa 2.04 m2 802.34 1,636.7716 Empañete liso en tapa 4.59 m2 347.95 1,597.0917 Cantos en tapa 9.20 m 72.49 666.9118 Tapa de hierro 1.00 u 2,662.20 2,662.20

Unid. $107,868.90*ISCIS 10590009 CISTERNA 4,000 GLS., TIERRA, 2.50X3.50X2.00 M. INT.:

1 Excav. en tierra (3.00x4.00x2.50 m.). 30.00 m3 235.85 7,075.502 Bote material excavado 39.00 m3 300.00 11,700.003 Horm. 1:2:4 en losas (losa piso y losa superior h=0.12 m.). 2.49 m3 3,963.92 9,870.164 Acero 3/8" x 20' grado 40 en losa piso 1.56 qq 1,915.88 2,988.775 Acero 3/8" x 20' grado 40 en losa superior 3.12 qq 1,915.88 5,977.556 Bloques 8" todos los hoyos llenos 25.60 m2 1,263.19 32,337.667 Madera bruta amer. (4 usos) 61.15 pt 29.00 1,773.358 Clavos corrientes (5 lb. / 100 pie madera) 12.23 lb 24.79 303.189 Clavos de acero (.08 lb / m2) 0.70 lb 45.24 31.67

Page 123: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 93

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

10 Alambre calibre #14 (.15 lb. / m2) 1.31 lb 25.44 33.3311 Confección madera 8.75 m2 106.98 936.0812 Desencofrado 8.75 m2 22.82 199.6813 Empañete pulido int. (paredes y piso). 32.75 m2 233.49 7,646.8014 Zabaletas en esq. paredes int. y en piso 20.00 m 68.51 1,370.2015 Bloques 6" en tapa 2.04 m2 802.34 1,636.7716 Empañete liso en tapa 4.59 m2 347.95 1,597.0917 Cantos en tapa 9.20 m 72.49 666.9118 Tapa de hierro 1.00 u 2,662.20 2,662.20

Unid. $88,806.90*ISCIS 10590010 TRAMPA GRASA, CALICHE, 1.00X1.00X1.00 M. INT.:

1 Excav. caliche (1.20x1.20x1.20 mt.). 1.73 m3 382.65 661.982 Bote material excavado 2.34 m3 300.00 702.003 Horm. 1:3:5 en losas 0.288 m3 3,572.06 1,028.754 Acero 3/8" x 20' grado 40 en tapa 0.361 qq 1,915.88 691.635 Bloques 4" sin mano de obra albañilería 4.00 m2 500.68 2,002.726 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0192 m3 6,371.00 122.327 Mano de obra albañilería 1.00 u 1,525.00 1,525.00

Unid. $6,734.40*ISCIS 10590011 TRAMPA GRASA, ROCA, 1.00X1.00X1.00 M. INT.:

1 Excav. roca a mano (1.20x1.20x1.20 mt.). 1.73 m3 781.25 1,351.562 Bote material excavado 2.77 m3 300.00 831.003 Horm. 1:3:5 en losas 0.288 m3 3,572.06 1,028.754 Acero 3/8" x 20' grado 40 en tapa 0.361 qq 1,915.88 691.635 Bloques 4" sin mano de obra albañilería 4.00 m2 500.68 2,002.726 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0192 m3 6,371.00 122.327 Mano de obra albañilería 1.00 u 1,525.00 1,525.00

Unid. $7,552.98*ISCIS 10590012 TRAMPA GRASA, TIERRA, 1.00X1.00X1.00 M. INT.:

1 Excav. tierra (1.20x1.20x1.20 m.). 1.73 m3 235.85 408.022 Bote material excavado 2.25 m3 300.00 675.003 Horm. 1:3:5 en losas 0.288 m3 3,572.06 1,028.754 Acero 3/8" x 20' grado 40 en tapa 0.361 qq 1,915.88 691.635 Bloques 4" sin mano de obra albañilería 4.00 m2 500.68 2,002.726 Mortero 1:2 imperm. (4 mm. + 20% desp.) 0.0192 m3 6,371.00 122.327 Mano de obra albañilería 1.00 u 1,525.00 1,525.00

Unid. $6,453.44

Page 124: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 94

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*ISCISSD 10610000 INST. SANITARIA: CISTERNAS Y SEPTICOS SEGÚN DISEÑO:

*ISCISSD 10610001 CISTERNA S/DISEÑO, EN CALICHE: (En prueba) Cambie solo los valores en AZUL.

Tipo de Bloque Ancho int. X Largoo int. Y Alto int. Z Cám. aire Hueco Long. Exc. X0.20 2.20 1.60 2.50 0.20 8.10 Int. Tapa 2.70

H Losa Piso H Losa Techo Alto Tierra Cant. Cist. En X Long. Exc. Y0.15 0.20 0.30 8 64.80 0.80 14.70

Espac. Acero Piso Espac. Acero Techo Gl. / Cist. En Y Alto Exc.Direc. X Direc. Y Direc. X Direc. Y 2,140 0.80 3.15

0.20 0.20 0.20 0.20 Tot. GL Agua Abult. Volumen Exc.Diámetro ( " ) --> 3/8 3/8 1/2 1/2 17,118 25.00% 125.02

1 Acero en losa de piso de 3*8" 3.51 qq 1,915.88 6,716.122 Acero en losa superior de 1/2" 4.56 qq 1,915.88 8,735.613 Alambre calibre #14 (.15 lb. / m2). 4.22 lb 25.44 107.364 Bloques 6" en tapa. 6.72 m2 802.34 5,391.725 Bloques 8" todos los hoyos llenos. 90.72 m2 1,338.73 121,449.596 Bote material excavado 156.50 m3 300.00 46,950.007 Cantos en tapa. 67.20 m 72.49 4,871.338 Clavos corrientes (5 lb. / 100 pie madera). 64.3 lb 24.79 1,594.009 Clavos de acero (.08 lb / m2). 2.25 lb 45.24 101.7910 Confección madera. 28.16 m2 106.98 3,012.5611 Desencofrado. 28.16 m2 22.82 642.6112 Empañete liso en tapa. 8.64 m2 220.88 1,908.4013 Empañete paredes int 75.00 m2 233.49 17,511.7514 Empañete pulido piso 28.16 m2 233.49 6,575.0815 Excavación + 0.10 m. a cada lado 125.02 m3 382.65 47,838.9016 Horm. 1:2:4 en losa piso 10.00 m3 3,963.92 39,639.2017 Horm. 1:2:4 en losa superior 12.42 m3 3,963.92 49,216.0318 Madera bruta amer. (4 usos). 321.52 pt 29.00 9,324.0819 Mano de obra Varillero losa de piso y superior 8.07 pt 213.92 1,725.2819 Zabaletas en esq. paredes int. y en piso. 87.60 m 68.51 6,001.48

Unid. $379,312.89*ISCISSD 10610002 CISTERNA S/DISEÑO, EN ROCA: (En prueba) Cambie solo los valores en AZUL.

Tipo de Bloque Ancho int. X Largoo int. Y Alto int. Z Cám. aire Hueco Long. Exc. X0.20 2.20 1.60 2.50 0.20 8.10 Int. Tapa 2.70

H Losa Piso H Losa Techo Alto Tierra Cant. Cist. En X Long. Exc. Y0.15 0.20 0.30 8 64.80 0.80 14.70

Espac. Acero Piso Espac. Acero Techo Gl. / Cist. En Y Alto Exc.Direc. X Direc. Y Direc. X Direc. Y 2,140 0.80 3.15

0.20 0.20 0.20 0.20 Tot. GL Agua Abult. Volumen Exc.Diámetro ( " ) --> 3/8 3/8 1/2 1/2 17,118 60.00% 125.02

1 Acero en losa de piso de 3*8" 3.51 qq 1,915.88 6,716.122 Acero en losa superior de 1/2" 4.56 qq 1,915.88 8,735.613 Alambre calibre #14 (.15 lb. / m2). 4.22 lb 25.44 107.364 Bloques 6" en tapa. 6.72 m2 802.34 5,391.725 Bloques 8" todos los hoyos llenos. 90.72 m2 1,338.73 121,449.596 Bote material excavado 200.50 m3 300.00 60,150.007 Cantos en tapa. 67.20 m 72.49 4,871.338 Clavos corrientes (5 lb. / 100 pie madera). 64.3 lb 24.79 1,594.009 Clavos de acero (.08 lb / m2). 2.25 lb 45.24 101.7910 Confección madera. 28.16 m2 106.98 3,012.5611 Desencofrado. 28.16 m2 22.82 642.6112 Empañete liso en tapa. 8.64 m2 220.88 1,908.4013 Empañete paredes int 75.00 m2 233.49 17,511.7514 Empañete pulido piso 28.16 m2 233.49 6,575.0815 Excavación + 0.10 m. a cada lado 125.02 m3 781.25 97,671.8816 Horm. 1:2:4 en losa piso 10.00 m3 3,963.92 39,639.2017 Horm. 1:2:4 en losa superior 12.42 m3 3,963.92 49,216.0318 Madera bruta amer. (4 usos). 321.52 pt 29.00 9,324.0819 Mano de obra Varillero losa de piso y superior 8.07 pt 213.92 1,725.2819 Zabaletas en esq. paredes int. y en piso. 87.60 m 68.51 6,001.48

Unid. $442,345.87*ISCISSD 10610003 CISTERNA S/DISEÑO, EN TIERRA: (En prueba) Cambie solo los valores en AZUL.

Tipo de Bloque Ancho int. X Largoo int. Y Alto int. Z Cám. aire Hueco Long. Exc. X0.20 2.20 1.60 2.50 0.20 8.10 Int. Tapa 2.70

H Losa Piso H Losa Techo Alto Tierra Cant. Cist. En X Long. Exc. Y0.15 0.20 0.30 8 64.80 0.80 14.70

Espac. Acero Piso Espac. Acero Techo Gl. / Cist. En Y Alto Exc.Direc. X Direc. Y Direc. X Direc. Y 2,140 0.80 3.15

0.20 0.20 0.20 0.20 Tot. GL Agua Abult. Volumen Exc.Diámetro ( " ) --> 3/8 3/8 1/2 1/2 17,118 20.00% 125.02

1 Acero en losa de piso de 3*8" 3.51 qq 1,915.88 6,716.122 Acero en losa superior de 1/2" 4.56 qq 1,915.88 8,735.613 Alambre calibre #14 (.15 lb. / m2). 4.22 lb 25.44 107.364 Bloques 6" en tapa. 6.72 m2 802.34 5,391.725 Bloques 8" todos los hoyos llenos. 90.72 m2 1,338.73 121,449.596 Bote material excavado 150.50 m3 300.00 45,150.007 Cantos en tapa. 67.20 m 72.49 4,871.338 Clavos corrientes (5 lb. / 100 pie madera). 64.3 lb 24.79 1,594.009 Clavos de acero (.08 lb / m2). 2.25 lb 45.24 101.7910 Confección madera. 28.16 m2 106.98 3,012.56

M3 Agua

CISTERNAS EN HILERA

Tot. M3 Agua

M3 Agua

CISTERNAS EN HILERA

Tot. M3 Agua

M3 Agua

CISTERNAS EN HILERA

Tot. M3 Agua

Page 125: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 95

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

11 Desencofrado. 28.16 m2 22.82 642.6112 Empañete liso en tapa. 8.64 m2 220.88 1,908.4013 Empañete paredes int 75.00 m2 233.49 17,511.7514 Empañete pulido piso 28.16 m2 233.49 6,575.0815 Excavación + 0.10 m. a cada lado 125.02 m3 235.85 29,485.9716 Horm. 1:2:4 en losa piso 10.00 m3 3,963.92 39,639.2017 Horm. 1:2:4 en losa superior 12.42 m3 3,963.92 49,216.0318 Madera bruta amer. (4 usos). 321.52 pt 29.00 9,324.0819 Mano de obra Varillero losa de piso y superior 8.07 pt 213.92 1,725.2819 Zabaletas en esq. paredes int. y en piso. 87.60 m 68.51 6,001.48

Unid. $359,159.96

*ISCAMO 10630000 INST. SANITARIA: COLOC. APARATOS SIN ITBIS (SOLO M. O.)

*ISCAMO 10630001 M.O. PLOM. COLOC. BAÑERA LIVIANA CON MEZCLADORA:1 M.O. Alb., base p/bañera. 1.00 u 220.83 220.832 M.O. Plom. coloc. bañera liv. 1.00 u 1,186.85 1,186.853 M.O. Plom. coloc. mezcl.. 1.00 u 518.80 518.804 M.O. Plom. desagüe de 2. 1.00 u 518.80 518.805 M.O. Plom. salidas ½". 2.00 u 518.80 1,037.60

Unid. $3,482.88*ISCAMO 10630002 M.O. PLOM. COLOC. BAÑERA PESADA CON MEZCLADORA:

1 M.O. Alb., base p/bañera. 1.00 u 220.83 220.832 M.O. Plom. coloc. bañera hierro fund. 1.00 u 1,250.00 1,250.003 M.O. Plom. coloc. mezcl.. 1.00 u 518.80 518.804 M.O. Plom. desagüe de 2. 1.00 u 518.80 518.805 M.O. Plom. salidas ½". 2.00 u 518.80 1,037.60

Unid. $3,546.03*ISCAMO 10630003 M.O. PLOM. COLOC. BIDET:

1 M.O. Plom. coloc. bidet. 1.00 u 889.54 889.542 M.O. Plom. desagüe 2". 1.00 u 518.80 518.803 M.O. Plom. salidas ½". 2.00 u 518.80 1,037.60

Unid. $2,445.94*ISCAMO 10630004 M.O. PLOM. COLOC. DUCHA: Agua caliente y fría, arriba y abajo, mezcladora

1 M.O. Plom. coloc. mezcl.. 1.00 u 518.80 518.802 M.O. Plom. desagüe de 2. 1.00 u 518.80 518.803 M.O. Plom. salidas ½". 2.00 u 518.80 1,037.60

Unid. $2,075.20*ISCAMO 10630005 M.O. PLOM. COLOC. DUCHA: Agua fría solamente

1 M.O. Plom. coloc.llave de empotrar ½" 1.00 u 296.11 296.112 M.O. Plom. desagüe de 2. 1.00 u 518.80 518.803 M.O. Plom. salidas ½". 1.00 u 518.80 518.80

Unid. $1,333.71*ISCAMO 10630006 M.O. PLOM. COLOC. FREG. A. INOX. DOBLE, MANGUERA:

1 M.O. Plom. coloc. Fregadero 1.00 u 950.93 950.932 M.O. Plom. desagüe 2". 1.00 u 518.80 518.803 M.O. Plom. salidas ½". 2.00 u 518.80 1,037.60

Unid. $2,507.33*ISCAMO 10630007 M.O. PLOM. COLOC. FREG. A. INOX. SENCILLO, MANGUERA:

1 M.O. Plom. coloc. Fregadero 1.00 u 742.69 742.692 M.O. Plom. desagüe 2". 1.00 u 518.80 518.803 M.O. Plom. salidas ½". 1.00 u 518.80 518.80

Unid. $1,780.29*ISCAMO 10630008 M.O. PLOM. COLOC. INODORO:

1 M.O. Plom. coloc. inodoro. 1.00 u 593.43 593.432 M.O. Plom. desagüe 4". 1.00 u 668.06 668.063 M.O. Plom. salidas ½". 1.00 u 668.06 668.06

Unid. $1,929.55*ISCAMO 10630009 M.O. PLOM. COLOC. LAVADERO GRANITO, DOBLE:

1 M.O. Plom. coloc. lavadero 2 cámara2 1.00 u 668.06 668.062 M.O. Plom. desagüe 2". 3.00 u 518.80 1,556.403 M.O. Plom. salida ½". 2.00 u 518.80 1,037.60

Unid. $3,262.06*ISCAMO 10630010 M.O. PLOM. COLOC. LAVADERO GRANITO, SENCILLO:

1 M.O. Plom. coloc. lavadero 1 cámara 1.00 u 518.80 518.802 M.O. Plom. desagüe 2". 2.00 u 518.80 1,037.603 M.O. Plom. salida ½". 1.00 u 518.80 518.80

Unid. $2,075.20*ISCAMO 10630011 M.O. PLOM. COLOC. LAVAMANOS CON PATAS:

1 M.O. Plom. coloc. lavamanos con patas 1.00 u 722.22 722.222 M.O. Plom. desagüe 2" 1.00 u 518.80 518.803 M.O. Plom. salidas ½" 2.00 u 518.80 1,037.60

Unid. $2,278.62*ISCAMO 10630012 M.O. PLOM. COLOC. LAVAMANOS EMPOTRADO:

1 M.O. Plom. coloc. lavamanos empotrado 1.00 u 1,038.80 1,038.802 M.O. Plom. desagüe 2" 1.00 u 518.80 518.803 M.O. Plom. salidas ½" 2.00 u 518.80 1,037.60

Unid. $2,595.20*ISCAMO 10630013 M.O. PLOM. COLOC. LAVAMANOS PEDESTAL:

1 M.O. Plom. coloc. lavamanos pedestal 1.00 u 812.50 812.502 M.O. Plom. desagüe 2" 1.00 u 518.80 518.803 M.O. Plom. salidas ½" 2.00 u 518.80 1,037.60

Unid. $2,368.90*ISCAMO 10630014 M.O. PLOM. COLOC. LAVAMANOS SALON DE BELLEZA:

1 M.O. Plom. coloc. lavamanos salón de belleza 1.00 u 1,038.80 1,038.802 M.O. Plom. desagüe 2" 1.00 u 518.80 518.803 M.O. Plom. salidas ½" 2.00 u 518.80 1,037.60

Unid. $2,595.20

Page 126: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 96

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*ISCAMO 10630015 M.O. PLOM. COLOC. LAVAMANOS SIN PATAS:1 M.O. Plom. coloc. lavamanos sin patas 1.00 u 593.43 593.432 M.O. Plom. desagüe 2" 1.00 u 518.80 518.803 M.O. Plom. salidas ½" 2.00 u 518.80 1,037.60

Unid. $2,149.83*ISCAMO 10630016 M.O. PLOM. COLOC. ORINAL ½ FALDA:

1 M.O. Plom. coloc. Orinal ½ falda 1.00 u 668.06 668.062 M.O. Plom. desagüe 2". 1.00 u 518.80 518.803 M.O. Plom. salidas ½". 1.00 u 668.06 668.06

Unid. $1,854.92*ISCAMO 10630017 M.O. PLOM. COLOC. ORINAL FALDA COMPLETA, FLUX.:

1 M.O. Plom. coloc. Orinal falda completa 1.00 u 1,038.80 1,038.802 M.O. Plom. desagüe 2". 1.00 u 518.80 518.803 M.O. Plom. salidas ½". 1.00 u 668.06 668.06

Unid. $2,225.66*ISCAMO 10630018 M.O. PLOM. COLOC. ORINAL PEQUEÑO:

1 M.O. Plom. coloc. Orinal pequeño 1.00 u 742.69 742.692 M.O. Plom. desagüe 2". 1.00 u 518.80 518.803 M.O. Plom. salidas ½". 1.00 u 668.06 668.06

Unid. $1,929.55*ISCAMO 10630019 M.O. PLOM. COLOC. VERTEDERO O TINA GRANITO:

1 M.O. Plom. coloc. vertedero sencillo. 1.00 u 149.26 149.262 M.O. Plom. desagüe 2". 1.00 u 518.80 518.803 M.O. Plom. salida ½". 1.00 u 518.80 518.804 M.O. Plom. tub. ½" en piso. 0.30 m 10.83 3.25

Unid. $1,190.11

*MALCIC 10650000 MALLAS CICLONICAS

*MALCIC 10650001 MALLA CICLONICA DE 6 PIES DE ALTO, LIGERA:1 Abrazadera de 1 ½" 0.780 u 13.22 10.312 Alambre de puas cal. 16 x 90 m. (rollo) 0.040 u 474.41 18.983 Alambre galvanizado #14 0.050 lb 25.44 1.274 Barra tensora de 6' 0.080 u 99.18 7.935 Bote material excavado 0.160 m3 300.00 48.006 Carpintería columnas de amarre 0.264 m 177.30 46.817 Colocar mallas 1.000 m 252.94 252.948 Copa Final 1 ½" 0.060 u 30.86 1.859 Corte y soldadura de abrazaderas 0.260 u 15.84 4.1210 Empañete liso (en 3 líneas de bloques) 1.200 m2 220.88 265.0611 Excación de zapata (tierra) 0.18 día 235.85 42.4512 Hoja de segueta 0.050 u 35.26 1.7613 Horm. 1:2:4 en columnas de amarre (.15 x .20 x .80 m.) 0.008 m3 3,572.33 28.5814 Horm. armado zapata (1:3:5, .45 x .20, 3 de 3/8" y 3/8" a .25 m.) 0.090 m3 4,843.23 435.8915 Malla ciclónica 6 pies, cal. 9 + 5% desp. 3.50 pie 80.94 283.2916 Muro de bloques de 6" x 8" x 16" (4 líneas) 0.800 m2 802.34 641.8717 Reata de amarre (zabaleta doble sin mano de obra) 2.000 m 82.58 165.1618 Relleno de reposición 0.060 m3 198.77 11.9319 Palometa 1 ½" doble, en aluminio fundido 0.280 u 123.42 34.5620 Terminal de 1 ¼" + abrazadera de 1 ½" 0.200 u 40.77 8.1521 Tubo HG de agua, de 1" x 20" para unir tubos de 1 ¼" 0.120 u 980.00 117.6022 Tubo HG ligero de 1 ½" x 15' 0.180 u 457.33 82.3223 Tubo HG ligero de 1 ¼" x 20' 0.160 u 511.56 81.85

M $2,592.68

*MOR 10670000 M O R T E R O S

*MOR 10670001 MEZCLA DE EMPAÑETE:1 Arena fina + 2% desp. 1.02 m3 820.00 836.402 Cal hidratada + 2% desp. (50 lbs.) 3.06 fda 285.00 872.103 Mano de obra mezclado (un peón) 0.50 día 425.00 212.50

M3 $1,921.00*MOR 10670002 MEZCLA CAL Y ARENA, P/MORTERO COLOC. PISO:

1 Arena gruesa lavada + 2% desp. 1.02 m3 820.00 836.402 Cal hidratada + 2% desp. (50 lbs.) 3.06 fda 285.00 872.103 Mano de obra mezclado (un peón) 0.50 día 425.00 212.50

M3 $1,921.00*MOR 10670003 MORTERO 1: 1 (Nuevo)

1 Agua 71.96 gl 0.35 25.192 Arena gruesa lavada + 2% desp. 0.694 m3 820.00 569.083 Cemento gris 24.01 fda 250.00 6,002.504 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 425.00 212.50

M3 $6,809.27*MOR 10670004 MORTERO 1: 2 (Nuevo)

2 Agua 70.10 gl 0.35 24.541 Arena gruesa lavada + 2% desp. 0.900 m3 820.00 738.003 Cemento gris 15.57 fda 250.00 3,892.504 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 425.00 212.50

M3 $4,867.54*MOR 10670005 MORTERO 1: 2 PARA PULIDO (ENLUCIDO IMPERMEABLE):

2 Agua 100.00 gl 0.35 35.001 Arena fina + 2% desp. 1.02 m3 820.00 836.403 Cal hidratada + 2% desp. (50 lbs.) 3.06 fda 285.00 872.104 Cemento gris 17.66 fda 250.00 4,415.005 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 425.00 212.50

M3 $6,371.00*MOR 10670006 MORTERO 1: 3, P/COLOCAR BLOQUES:

2 Agua 69.04 gl 0.35 24.16

Page 127: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 97

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

1 Arena gruesa lavada + 2% desp. 0.998 m3 820.00 818.363 Cemento gris 11.51 fda 250.00 2,877.504 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 425.00 212.50

M3 $3,932.52*MOR 10670007 MORTERO 1: 4 PARA EMPAÑETE:

3 Agua 45.24 gl 0.35 15.832 Cemento gris 9.46 fda 250.00 2,365.004 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 425.00 212.501 Mezcla de empañete + 3% desp. 1.102 m3 1,921.00 2,116.94

M3 $4,710.27*MOR 10670008 MORTERO 1: 5: (Nuevo)

2 Agua 67.99 gl 0.35 23.801 Arena gruesa lavada + 2% desp. 1.091 m3 820.00 894.623 Cemento gris 7.56 fda 250.00 1,890.004 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 425.00 212.50

M3 $3,020.92*MOR 10670009 MORTERO 1: 6: (Nuevo)

2 Agua 67.72 gl 0.35 23.701 Arena gruesa lavada + 2% desp. 1.120 m3 820.00 918.403 Cemento gris 6.46 fda 250.00 1,615.004 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 425.00 212.50

M3 $2,769.60*MOR 10670010 MORTERO 1:10, COLOCAR PISOS:

3 Agua 70.00 gl 0.35 24.502 Cemento gris 5.24 fda 250.00 1,310.004 Mano de obra mezclado (un peón = 2 m3 / 8 horas) 0.50 día 425.00 212.501 Mezcla cal y arena para pisos + 20% desp. 1.20 m3 1,921.00 2,305.20

M3 $3,852.20

*MOVTIE 10690000 MOVIMIENTO DE TIERRAS

*MOVTIE 10690001 RELLENO ARENA O CASCAJO (A MANO):1 Arena o cascajo de mina + 15% abult. + 3% 1.185 m3 750.00 888.752 Agua 15.22 gl 0.41 6.243 Traslado material (1 TC = 5.00 m3 / día) 0.237 día 425.00 100.734 Regar, mojar y apis. (1 TC = 15.45 m3 / día) 0.077 día 425.00 32.73

M3 $1,028.45*MOVTIE 10690002 RELLENO ARENA O CASCAJO (CON EQUIPO):

1 Alquiler compactador mecánico + transporte 0.375 hr 79.18 29.692 Arena o cascajo de mina + 15% abult. + 3% 1.185 m3 750.00 888.753 Agua 15.22 gl 0.41 6.244 Traslado material (1 TC = 5.00 m3 / día) 0.237 día 425.00 100.735 Regar, mojar y apis. (1 TC = 23.18 m3 / día) 0.051 día 425.00 21.68

M3 $1,047.09*MOVTIE 10690003 RELLENO CALICHE (A MANO):

1 Caliche fino + 30 % abult. + 3% desp. 1.339 m3 280.00 374.922 Agua 15.22 gl 0.41 6.243 Traslado material (1 TC = 3.33 m3 / día) 0.402 día 425.00 170.854 Regar, mojar y apis. (1 TC = 9.80 m3 / día) 0.137 día 425.00 58.23

M3 $610.24*MOVTIE 10690004 RELLENO CALICHE (CON EQUIPO):

1 Alquiler compactador mecánico + transporte 0.375 hr 79.18 29.692 Caliche fino + 30 % abult. + 3% desp. 1.339 m3 280.00 374.923 Agua 15.22 gl 0.41 6.244 Traslado material (1 TC = 3.33 m3 / día) 0.402 día 425.00 170.855 Regar, mojar y apis. (1 TC = 1470 m3 / día) 0.091 día 425.00 38.68

M3 $620.38*MOVTIE 10690005 RELLENO CALICHE Y ARENA O CASCAJO (A MANO):

1 Caliche fino + 30 % abult. + 3% desp. 0.670 m3 280.00 187.602 Arena itabo o cascajo fino + 15% abult. + 3% 0.592 m3 750.00 444.003 Agua 15.22 gl 0.41 6.244 Traslado del material (1 TC = 4.00 m3 / día) 0.316 día 425.00 134.305 Regar, mojar y apis. (1 TC = 13.17 m3 / día) 0.096 día 425.00 40.80

M3 $812.94*MOVTIE 10690006 RELLENO CALICHE Y ARENA O CASCAJO (CON EQUIPO):

1 Alquiler compactador mecánico + transporte 0.375 hr 79.18 29.692 Caliche fino + 30 % abult. + 3% desp. 0.670 m3 280.00 187.603 Arena itabo o cascajo fino + 15% abult. + 3% 0.592 m3 750.00 444.004 Agua 15.22 gl 0.41 6.245 Traslado del material (1 TC = 4.00 m3 / día) 0.316 día 425.00 134.306 Regar, mojar y apis. (1 TC = 19.76 m3 / día) 0.051 día 425.00 21.68

M3 $823.51*MOVTIE 10690007 RELLENO DE REPOSICION CALICHE SUELTO (A MANO):

1 Agua 15.22 gl 0.41 6.242 Traslado del material (1 TC = 4.00 m3 / día) 0.316 día 425.00 134.303 Regar, mojar y apisonar (1 TC = 9.80 m3 compactado / día) 0.137 día 425.00 58.23

M3 $198.77*MOVTIE 10690008 RELLENO DE REPOSICION SUELTO (Caliche) (CON EQUIPO):

1 Alquiler compactador mecánico + transporte 0.375 hr 79.18 29.692 Agua 15.22 gl 0.41 6.243 Traslado del material (1 TC = 4.00 m3 / día) 0.316 día 425.00 134.304 Regar, mojar (1 TC = 1470 m3 compactado / día) 0.091 día 425.00 38.68

M3 $208.91*MOVTIE 10690009 REMOCION CAPA VEGETAL (A MANO):

1 Excavación a mano 1.00 m3 235.85 235.852 Traslado del material (1 TC = 3.33 m3 / día) 0.300 día 425.00 127.50

M3 $363.35

Page 128: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 98

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*PIN 10710000 PINTURAS

*PIN 10710001 PINTURA ACRILICA EXTERIOR:1 Pintura colores preparados 0.08 gl 719.00 57.522 Piedra sobre paredes 1.00 m2 6.25 6.253 Aplicación dos manos 1.00 m2 30.09 30.094 Desperdicios y retoques 20.00% 18.77

M2 $112.63*PIN 10710002 PINTURA ACRILICA INTERIOR:

1 Pintura 0.08 gl 458.00 36.642 Piedra sobre paredes 1.00 m2 6.25 6.253 Aplicación dos manos 1.00 m2 30.09 30.094 Desperdicios y retoques 20.00% 14.60

M2 $87.58*PIN 10710003 PINTURA ACRILICA EXTERIOR CON ANDAMIOS:

1 Pintura colores preparados 0.08 gl 719.00 57.522 Piedra sobre paredes 1.00 m2 6.25 6.253 Aplicación dos manos 1.00 m2 30.09 30.094 Andamios y Gindolas 1.00 m2 68.95 68.955 Desperdicios y retoques 20.00% 18.77

M2 $181.58*PIN 10710004 PINTURA EPOXICA:

1 Pintura 0.08 gl 1,292.00 103.362 Thinner 0.13 gl 423.40 55.043 Piedra sobre paredes 1.00 m2 6.25 6.254 Aplicación dos manos 1.00 m2 37.32 37.325 Desperdicios y retoques 20.00% 40.39

M2 $242.36*PIN 10710005 PINTURA LACA PARA PUERTAS:

1 Pintura 0.10 gl 477.53 47.752 Piedra sobre paredes 1.00 m2 6.25 6.253 Aplicación dos manos 1.00 m2 30.09 30.094 Desperdicios y retoques 20.00% 16.82

M2 $100.91*PIN 10710006 PINTURA LATEX "ECONOMICA" O "PINTEX":

1 Pintura 0.10 gl 191.01 19.102 Piedra sobre paredes 1.00 m2 6.25 6.253 Aplicación dos manos 1.00 m2 30.09 30.094 Desperdicios y retoques 20.00% 11.09

M2 $66.53*PIN 10710007 PINTURA MANTENIMIENTO:

1 Pintura 0.08 gl 651.00 52.082 Thinner 0.13 gl 423.40 55.043 Piedra sobre paredes 1.00 m2 6.25 6.254 Aplicación dos manos 1.00 m2 37.32 37.325 Desperdicios y retoques 20.00% 30.14

M2 $180.83*PIN 10710008 PINTURA MANTENIMIENTO CON ANDAMIOS:

1 Pintura 0.08 gl 651.00 52.082 Thinner 0.13 gl 423.40 55.043 Piedra sobre paredes 1.00 m2 6.25 6.254 Aplicación dos manos 1.00 m2 37.32 37.325 Andamios y Gindolas 1.00 m2 68.95 68.956 Desperdicios y retoques 20.00% 30.14

M2 $249.78

*PIS 10730000 PISOS

*PIS 10730001 ACERA FROTADA Y VIOLINADA:1 Preparación terreno 1.00 m2 30.11 30.112 Horm. 1:3:5 + 5% desp. 0.105 m3 3,572.06 375.073 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.634 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 154.28 13.585 Elaboración, vaciado y frotado 1.00 m2 107.32 107.326 Cantos laterales 0.80 m 72.49 57.99

M2 $687.70*PIS 10730002 ADOQUIN 500-80 AGUAYO 8X10X20 CM., GRIS:

1 Preparación terreno 1.00 m2 45.17 45.172 Arena lavada 0.08 m3 1,100.00 88.003 Baldosas + transporte + 5% desp. 1.00 m2 1,573.91 1,573.914 Corte de chazos 0.15 u 30.16 4.525 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 154.28 27.156 Cantos laterales 0.80 m 72.49 57.997 Colocación 1.00 m2 60.23 60.23

M2 $1,856.97*PIS 10730003 ADOQUIN 500-80 AGUAYO 8X10X20 CM., ROJO:

1 Preparación terreno 1.00 m2 45.17 45.172 Arena lavada 0.08 m3 1,100.00 88.003 Baldosas + transporte + 5% desp. 1.00 m2 2,038.92 2,038.924 Corte de chazos 0.15 u 30.16 4.525 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 154.28 27.156 Cantos laterales 0.80 m 72.49 57.997 Colocación 1.00 m2 60.23 60.23

M2 $2,321.98*PIS 10730004 ADOQUIN 511 AGUAYO TIPO PALETA, GRIS:

1 Preparación terreno 1.00 m2 45.17 45.172 Arena lavada 0.08 m3 1,100.00 88.003 Baldosas + transporte + 5% desp. 1.00 m2 1,400.72 1,400.72

Page 129: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 99

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

4 Corte de chazos 0.15 u 30.16 4.525 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 154.28 27.156 Cantos laterales 0.80 m 72.49 57.997 Colocación 1.00 m2 60.23 60.23

M2 $1,683.78*PIS 10730005 ADOQUIN 511 AGUAYO TIPO PALETA, ROJO:

1 Preparación terreno 1.00 m2 45.17 45.172 Arena lavada 0.08 m3 1,100.00 88.003 Baldosas + transporte + 5% desp. 1.00 m2 1,645.72 1,645.724 Corte de chazos 0.15 u 30.16 4.525 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 154.28 27.156 Cantos laterales 0.80 m 72.49 57.997 Colocación 1.00 m2 60.23 60.23

M2 $1,928.78*PIS 10730006 ADOQUIN 604 AGUAYO 6X10.2X20.2 CM., GRIS:

1 Preparación terreno 1.00 m2 45.17 45.172 Arena lavada 0.08 m3 1,100.00 88.003 Baldosas + transporte + 5% desp. 1.00 m2 1,165.89 1,165.894 Corte de chazos 0.15 u 30.16 4.525 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 154.28 27.156 Cantos laterales 0.80 m 72.49 57.997 Colocación 1.00 m2 60.23 60.23

M2 $1,448.95*PIS 10730007 ADOQUIN 604 AGUAYO 6X10.2X20.2 CM., ROJO:

1 Preparación terreno 1.00 m2 45.17 45.172 Arena lavada 0.08 m3 1,100.00 88.003 Baldosas + transporte + 5% desp. 1.00 m2 1,389.41 1,389.414 Corte de chazos 0.15 u 30.16 4.525 Regla (2 de 1"x4"x2.62' / 10 usos) 0.176 pt 154.28 27.156 Cantos laterales 0.80 m 72.49 57.997 Colocación 1.00 m2 60.23 60.23

M2 $1,672.47*PIS 10730008 CERAMICA CRIOLLA TIPO 01:

1 Preparación terreno 1.00 m2 30.11 30.112 Horm. 1:3:5 + 5% desp. h=.10 m. 0.105 m3 3,572.06 375.073 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.774 Baldosas + transporte + 10% desp. 1.10 m2 409.51 450.465 Corte de chazos 5.00 u 7.05 35.256 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.807 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.198 Colocación 1.00 m2 265.00 265.00

M2 $1,212.65*PIS 10730009 CERAMICA IMPORTADA TIPO 09:

1 Preparación terreno 1.00 m2 30.11 30.112 Horm. 1:3:5 + 5% desp. h=.10 m. 0.105 m3 3,572.06 375.073 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.774 Baldosas + transporte + 10% desp. 1.10 m2 1,160.31 1,276.345 Corte de chazos 5.00 u 7.05 35.256 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.807 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.198 Colocación 1.00 m2 278.95 278.95

M2 $2,052.48*PIS 10730010 GRANITO 40x40, AGLOMERADO PERLATTO ROYAL:

1 Preparación terreno 1.00 m2 30.11 30.112 Mortero 1:10 + 5% desp. 0.0315 m3 3,852.20 121.343 Baldosas + transporte + 10% desp. 1.10 m2 646.13 710.744 Corte de chazos 2.50 u 12.76 31.905 Derretido color + 10% desp. 0.0344 fda 806.20 27.736 Colocación 1.00 m2 165.91 165.917 Pulido y cristalizado 1.00 m2 262.17 262.17

M2 $1,349.90*PIS 10730011 GRANITO 30x30, 1-2-3, FONDO BLANCO:

1 Preparación terreno 1.00 m2 30.11 30.112 Mortero 1:10 + 5% desp. 0.0315 m3 3,852.20 121.343 Baldosas + transporte + 10% desp. 1.10 m2 381.15 419.274 Corte de chazos 3.33 u 9.28 30.905 Derreterido blanco + 10% desp. 0.0344 fda 806.20 27.736 Colocación 1.00 m2 140.38 140.387 Pulido y cristalizado 1.00 m2 262.17 262.17

M2 $1,031.90*PIS 10730012 GRANITO 30x30, 1-2-3, FONDO GRIS:

1 Preparación terreno 1.00 m2 30.11 30.112 Mortero 1:10 + 5% desp. 0.0315 m3 3,852.20 121.343 Baldosas + transporte + 10% desp. 1.10 m2 325.49 358.044 Corte de chazos 3.33 u 9.28 30.905 Derreterido gris + 10% desp. 0.0344 fda 382.80 13.176 Colocación 1.00 m2 140.38 140.387 Pulido y cristalizado 1.00 m2 262.17 262.17

M2 $956.11*PIS 10730013 GRANITO 40x40, 1-2-3, FONDO BLANCO:

1 Preparación terreno 1.00 m2 30.11 30.112 Mortero 1:10 + 5% desp. 0.0315 m3 3,852.20 121.343 Baldosas + transporte + 10% desp. 1.10 m2 545.94 600.534 Corte de chazos 2.5 u 12.76 31.905 Derreterido blanco + 10% desp. 0.0344 fda 806.20 27.736 Colocación 1.00 m2 165.91 165.917 Pulido y cristalizado 1.00 m2 262.17 262.17

M2 $1,239.69

Page 130: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 100

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*PIS 10730014 HORMIGON ARMADO 3/8" A 20, 1:2:4, PISO .10 M. ESP.:1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 1:2:4 + 5% desp. 0.105 m3 3,572.06 375.075 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 154.28 13.587 Elaboración, vaciado y frotado 1.00 m2 84.38 84.38

10,608.67 M3 M2 $910.97*PIS 10730015 HORMIGON ARMADO 3/8" A 20, 1:2:4, PISO .12 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 1:2:4 + 5% desp. 0.130 m3 3,572.06 464.375 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.110 pt 154.28 16.977 Elaboración, vaciado y frotado 1.00 m2 84.38 84.38

8,568.54 M3 M2 $1,003.66*PIS 10730016 HORMIGON ARMADO 3/8" A 20, 1:2:4, PISO .15 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 1:2:4 + 5% desp. 0.160 m3 3,572.06 571.535 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.130 pt 154.28 20.067 Elaboración, vaciado y frotado 1.00 m2 84.38 84.38

6,961.94 M3 M2 $1,113.91*PIS 10730017 HORMIGON ARMADO 3/8" A 20, 1:2:4, PISO .20 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 1:2:4 + 5% desp. 0.210 m3 3,572.06 750.135 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.180 pt 154.28 27.777 Elaboración, vaciado y frotado 1.00 m2 84.38 84.38

5,304.33 M3 M2 $1,300.22*PIS 10730018 HORMIGON ARMADO 3/8" A 20, 140 Kg/Cm², PISO .10 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 140 Kg/Cm² 0.100 m3 5,614.40 561.445 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 154.28 13.587 frotado 1.00 m2 84.38 84.38

11,139.10 M3 M2 $1,097.34*PIS 10730019 HORMIGON ARMADO 3/8" A 20, 140 Kg/Cm², PISO .12 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 140 Kg/Cm² 0.120 m3 5,614.40 673.735 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.110 pt 154.28 16.977 frotado 1.00 m2 84.38 84.38

9,282.58 M3 M2 $1,213.02*PIS 10730020 HORMIGON ARMADO 3/8" A 20, 140 Kg/Cm², PISO .15 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 140 Kg/Cm² 0.150 m3 5,614.40 842.165 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.130 pt 154.28 20.067 frotado 1.00 m2 84.38 84.38

7,426.07 M3 M2 $1,384.54*PIS 10730021 HORMIGON ARMADO 3/8" A 20, 140 Kg/Cm², PISO .20 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 140 Kg/Cm² 0.200 m3 5,614.40 1,122.885 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.180 pt 154.28 27.777 frotado 1.00 m2 84.38 84.38

5,569.55 M3 M2 $1,672.97*PIS 10730022 HORMIGON ARMADO 3/8" A 20, 180 Kg/Cm², PISO .10 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 180 Kg/Cm² 0.100 m3 5,933.40 593.345 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 154.28 13.587 frotado 1.00 m2 84.38 84.38

11,139.10 M3 M2 $1,129.24*PIS 10730023 HORMIGON ARMADO 3/8" A 20, 180 Kg/Cm², PISO .12 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 180 Kg/Cm² 0.120 m3 5,933.40 712.015 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.110 pt 154.28 16.97

Page 131: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 101

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

7 frotado 1.00 m2 84.38 84.389,282.58 M3 M2 $1,251.30

*PIS 10730024 HORMIGON ARMADO 3/8" A 20, 180 Kg/Cm², PISO .15 M. ESP.:1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 180 Kg/Cm² 0.150 m3 5,933.40 890.015 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.130 pt 154.28 20.067 frotado 1.00 m2 84.38 84.38

7,426.07 M3 M2 $1,432.39*PIS 10730025 HORMIGON ARMADO 3/8" A 20, 180 Kg/Cm², PISO .20 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 180 Kg/Cm² 0.200 m3 5,933.40 1,186.685 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.180 pt 154.28 27.777 frotado 1.00 m2 84.38 84.38

5,569.55 M3 M2 $1,736.77*PIS 10730026 HORMIGON ARMADO 3/8" A 20, 210 Kg/Cm², PISO .10 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 210 Kg/Cm² 0.100 m3 6,188.60 618.865 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 154.28 13.58

Page 132: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 102

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

7 frotado 1.00 m2 84.38 84.3811,139.10 M3 M2 $1,154.76

*PIS 10730027 HORMIGON ARMADO 3/8" A 20, 210 Kg/Cm², PISO .12 M. ESP.:1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 210 Kg/Cm² 0.120 m3 6,188.60 742.635 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.110 pt 154.28 16.977 frotado 1.00 m2 84.38 84.38

9,282.58 M3 M2 $1,281.92*PIS 10730028 HORMIGON ARMADO 3/8" A 20, 210 Kg/Cm², PISO .15 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 210 Kg/Cm² 0.150 m3 6,188.60 928.295 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.130 pt 154.28 20.067 frotado 1.00 m2 84.38 84.38

7,426.07 M3 M2 $1,470.67*PIS 10730029 HORMIGON ARMADO 3/8" A 20, 210 Kg/Cm², PISO .20 M. ESP.:

1 Preparación terreno 1.00 m2 30.11 30.112 Acero de 3/8" + 10% desp. 0.136 qq 1,915.88 260.563 Mano de obra acero 0.136 qq 320.86 43.644 Horm. 210 Kg/Cm² 0.200 m3 6,188.60 1,237.725 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.636 Regla (1 de 1"x4"x2.62' / 10 usos) 0.180 pt 154.28 27.777 frotado 1.00 m2 84.38 84.38

5,569.55 M3 M2 $1,787.81*PIS 10730030 HORMIGON FROTADO, PISO 10 CM.:

1 Preparación terreno 1.00 m2 30.11 30.112 Horm. 1:3:5 + 5% desp. 0.105 m3 3,572.06 375.073 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.634 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 154.28 13.585 Elaboración, vaciado y frotado 1.00 m2 84.38 84.386 Cantos laterales 0.80 m 72.49 57.99

10,608.67 M3 M2 $664.76*PIS 10730031 HORMIGON FROTADO Y VIOLINADO, PISO 10 CM.:

1 Preparación terreno 1.00 m2 30.11 30.112 Horm. 1:3:5 + 5% desp. 0.105 m3 3,572.06 375.073 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.634 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 154.28 13.585 Elaboración, vaciado, frotado y pulido 1.00 m2 112.50 112.506 Cantos laterales 0.80 m 72.49 57.99

10,608.67 M3 M2 $692.88*PIS 10730032 HORMIGON PULIDO, PISO 10 CM.:

1 Preparación terreno 1.00 m2 30.11 30.112 Horm. 1:3:5 + 5% desp. 0.105 m3 3,572.06 375.073 Mortero 1:4 + 5% desp. 0.022 m3 4,710.27 103.634 Regla (1 de 1"x4"x2.62' / 10 usos) 0.088 pt 154.28 13.585 Elaboración, vaciado, frotado y pulido 1.00 m2 119.12 119.126 Cantos laterales 0.80 m 72.49 57.997 Cemento gris para pulido. 0.04 fda 250.00 10.00

10,608.67 M3 M2 $709.50*PIS 10730033 LADRILLO EXAGONAL PEQUEÑA, PISO:

1 Preparación terreno 1.00 m2 30.11 30.112 Mortero 1:10 + 5% desp. 0.0315 m3 3,852.20 121.343 Baldosas + transporte + 10% desp. 55.00 u 6.16 338.804 Corte de chazos 6.00 u 8.12 48.725 Derretido gris + 10% desp. 0.0344 fda 382.80 13.176 Colocación 1.00 m2 150.57 150.57

M2 $702.71*PIS 10730034 LADRILLO TIPO FERIA PEQUEÑA, PISO:

1 Preparación terreno 1.00 m2 30.11 30.112 Mortero 1:10 + 5% desp. 0.0315 m3 3,852.20 121.343 Baldosas + transporte + 10% desp. 71.50 u 5.39 385.394 Corte de chazos 3.00 u 8.12 24.365 Derretido gris + 10% desp. 0.0344 fda 382.80 13.176 Colocación 1.00 m2 194.85 194.85

M2 $769.22*PIS 10730035 MOSAICOS 25x25, ROJO:

1 Preparación terreno 1.00 m2 30.11 30.112 Mortero 1:10 + 5% desp. 0.0315 m3 3,852.20 121.343 Baldosas + transporte + 10% desp. 1.10 m2 819.97 901.974 Corte de chazos 4.00 u 8.12 32.485 Derretido gris + 10% desp. 0.0344 fda 382.80 13.176 Colocación 1.00 m2 121.67 121.67

M2 $1,220.74*PIS 10730036 QUICIO GRANITO 30x07, BLANCO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 3,932.52 8.262 Baldosas + transporte + 10% desp. 1.10 m 71.61 78.773 Corte de chazos 1.00 u 9.28 9.284 Lechada cemento blanco + 10% desp. 0.001 fda 806.20 0.815 Colocación 1.00 m 100.00 100.00

M $197.12*PIS 10730037 QUICIO GRANITO 40x07, BLANCO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 3,932.52 8.262 Baldosas + transporte + 10% desp. 1.10 m 79.97 87.97

Page 133: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 103

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

3 Corte de chazos 1.00 u 12.76 12.764 Lechada cemento blanco + 10% desp. 0.001 fda 806.20 0.815 Colocación 1.00 m 100.00 100.00

M $209.80*PIS 10730038 QUICIO MOSAICOS 25x07, ROJO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 3,932.52 8.262 Baldosas + transporte + 10% desp. 1.10 m 124.63 137.093 Corte de chazos 1.00 u 12.76 12.764 Lechada cemento gris + 10% desp. 0.001 fda 382.80 0.385 Colocación 1.00 m 100.00 100.00

M $258.49*PIS 10730039 QUICIO LADRILLO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 3,932.52 8.262 Baldosas + transporte + 10% desp. 4.40 u 9.31 40.963 Corte de chazos 1.00 u 5.80 5.804 Lechada cemento gris + 10% desp. 0.001 fda 382.80 0.385 Colocación 1.00 m 100.00 100.00

M $155.40*PIS 10730040 ZABALETA DE PISO:

1 Mortero 1:3. 0.0105 m3 3,932.52 41.292 Mano de obra 1.00 m 27.22 27.22

M $68.51*PIS 10730041 ZOCALO GRANITO PERLATTO ROYAL 40x07:

1 Mortero 1:3 + 5% desp. 0.0021 m3 3,932.52 8.262 Baldosas + transporte + 10% desp. 1.10 m 103.16 113.483 Corte de chazos 1.00 u 5.80 5.804 Lechada cemento con color + 10% desp. 0.001 fda 806.20 0.815 Colocación 1.00 m 60.23 60.23

M $188.58*PIS 10730042 ZOCALO P/ESCALONES, SUPER CHAPA CREMA MARFIL:

1 Mortero 1:3 + 5% desp. 0.0063 m3 3,932.52 24.772 Baldosas + transporte + 10% desp. 1.25 p 222.72 278.403 Colocación 1.00 u 101.92 101.92

U $405.09*PIS 10730043 ZOCALO GRANITO 30x07, BLANCO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 3,932.52 8.262 Baldosas + transporte + 10% desp. 1.10 m 71.61 78.773 Corte de chazos 1.00 u 5.80 5.804 Lechada cemento blanco + 10% desp. 0.001 fda 806.20 0.815 Colocación 1.00 m 60.23 60.23

M $153.87*PIS 10730044 ZOCALO GRANITO 30x07, GRIS:

1 Mortero 1:3 + 5% desp. 0.0021 m3 3,932.52 8.262 Baldosas + transporte + 10% desp. 1.10 m 45.26 49.793 Corte de chazos 1.00 u 5.80 5.804 Lechada cemento gris + 10% desp. 0.001 fda 382.80 0.385 Colocación 1.00 m 60.23 60.23

M $124.46*PIS 10730045 ZOCALO GRANITO 40x07, BLANCO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 3,932.52 8.262 Baldosas + transporte + 10% desp. 1.10 m 79.97 87.973 Corte de chazos 1.00 u 5.80 5.804 Lechada cemento blanco + 10% desp. 0.001 fda 806.20 0.815 Colocación 1.00 m 60.23 60.23

M $163.07*PIS 10730046 ZOCALO LADRILLOS 28x7:

1 Mortero 1:3 + 5% desp. 0.0021 m3 3,932.52 8.262 Baldosas + transporte + 10% desp. 3.93 u 9.31 36.593 Corte de chazos 1.00 u 5.80 5.804 Lechada cemento gris + 10% desp. 0.001 fda 382.80 0.385 Colocación 1.00 m 60.23 60.23

M $111.26*PIS 10730047 ZOCALO MOSAICOS 25x07, ROJO:

1 Mortero 1:3 + 5% desp. 0.0021 m3 3,932.52 8.262 Baldosas + transporte + 10% desp. 1.10 m 124.63 137.093 Corte de chazos 1.00 u 5.80 5.804 Lechada cemento gris + 10% desp. 0.001 fda 382.80 0.385 Colocación 1.00 m 44.17 44.17

M $195.70

*PORMAD 10750000 PORTAJE DE MADERA

*PORMAD 10750001 PUERTA DE PLYWOOD 3'x7':1 Marco de pino 16.73 p 44.00 736.122 Puerta plywood 3'x7' 21.00 pt 85.00 1,785.003 Bisagras "STANLEY" 3 ½"x3 ½" 1.50 par 69.60 104.404 Tornillos 3"x14 7.00 u 3.20 22.405 Tarugos 3/8" plásticos 7.00 u 1.50 10.506 Llavín corriente 1.00 u 484.88 484.887 Montura todo costo 1.00 u 1,025.00 1,025.00

M2 $2,135.76 Unid. $4,168.30*PORMAD 10750002 PUERTA DE PINO panel 3'x7':

1 Marco de pino 16.73 p 44.00 736.122 Puerta pino 3'x7' 21.00 pt 154.00 3,234.003 Bisagras "STANLEY" 3 ½"x3 ½" 1.50 par 69.60 104.404 Tornillos 3"x14 7.00 u 3.20 22.405 Tarugos 3/8" plásticos 7.00 u 1.50 10.506 Llavín corriente 1.00 u 484.88 484.88

Page 134: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 104

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

7 Montura todo costo 1.00 u 1,025.00 1,025.00M2 $2,878.20 Unid. $5,617.30

*PORMAD 10750003 PUERTA DE CAOBA panel 3'x7':1 Marco de caoba. 16.73 p 136.00 2,275.282 Puerta caoba 3'x7' 21.00 pt 528.00 11,088.003 Bisagras "STANLEY" 3 ½"x3 ½" 1.50 par 69.60 104.404 Tornillos 3"x14 7.00 u 3.20 22.405 Tarugos 3/8" plásticos 7.00 u 1.50 10.506 Llavín de calidad. 1.00 u 1,388.52 1,388.527 Montura todo costo 1.00 u 1,025.00 1,025.00

M2 $8,154.08 Unid. $15,914.10*PORMAD 10750004 PUERTA DE CAOBA panel ESP. 3'x7':

1 Marco de caoba. 16.73 p 136.00 2,275.282 Puerta caoba 3'x7' 21.00 pt 543.00 11,403.003 Bisagras "STANLEY" 3 ½"x3 ½" 1.50 par 69.60 104.404 Tornillos 3"x14 7.00 u 3.20 22.405 Tarugos 3/8" plásticos 7.00 u 1.50 10.506 Llavín especial 1.00 u 4,165.56 4,165.567 Montura todo costo 1.00 u 1,025.00 1,025.00

M2 $9,738.38 Unid. $19,006.14*PORMAD 10750005 PUERTA DE CAOBA, VAIVEN 3'x7':

1 Marco de caoba. 16.73 p 136.00 2,275.282 Puerta caoba 3'x7' 21.00 pt 528.00 11,088.003 Bisagra vaiven de piso 1.00 u 523.45 523.454 Tornillos 3"x14 7.00 u 3.20 22.405 Tarugos 3/8" plásticos 7.00 u 1.50 10.506 Montura todo costo 1.00 u 1,025.00 1,025.00

M2 $7,657.34 Unid. $14,944.63*PORMAD 10750006 PUERTA DE CAOBA, FRANCESA: (Ancho = 2.8 m.)

1 Marco caoba (4 de 7' + 9.18') 37.18 p 136.00 5,056.482 Puerta caoba 9.18'x7' 63.27 pt 528.00 33,406.563 Bisagras "STANLEY" 3 ½"x3 ½" 3.00 par 69.60 208.804 Tornillos 3"x14 10.00 u 3.20 32.005 Tarugos 3/8" plásticos 10.00 u 1.50 15.006 Fallebas 6" 1.00 u 119.00 119.007 Fallebas 10" 1.00 u 127.99 127.998 Clavos 2" 0.50 lb 24.79 12.409 Llavín de calidad 1.00 u 1,388.52 1,388.5210 Montura todo costo 4.00 u 1,025.00 4,100.00

M2 $7,562.23 Unid. $44,466.75

*REP 10710000 REPLANTEO SEGUN DISEÑO

*REP 10710001 CHARRANCHA, CALCULO DEL COSTO Cambie solo los valores en AZUL.Perímetro 73.88 m.

Rectángulo EDIFICADO 265.92 m2Lado X de edificación 14.16 m.Lado Y de edificación 18.78 m. 57.75

Cant. Ejes de Col. y Muros en X-X 10 u. 1Cant. Ejes de Col. y Muros en Y-Y 12 u. 3

Separación madera de ZAP. 1.000 m. 1,5Cant. estacas./enlates. 3 u. 1.5

Cant. Usos madera 3 usos 1.5Desperdicio clavos 25%

Desperdicio madera 10%Dim. enlate (pulg. x pulg. x pies) 1 4 10 pies 27.00 uDim. etaca (pulg. x pulg. x pies) 1 4 2.500 pies 81.00 u

Cant. clavos por estaca (fijación) 4 u.

1 Clavos corrientes Rend./lb. 67 u. 9.33 lb 24.79 231.292 Cal 50 lbs. Rend./m. 0.040 funda 3.00 fda 285.00 855.003 Madera, pino bruto americano 57.75 pt 29.00 1,674.754 Hilo de nylon Rend./m. 0.005 rollo 1.00 u 139.58 139.585 Técnico Calificado (TC) Rend./m. 0.034 día 3.00 u 425.00 1,275.006 Carpintero de segunda (OP2) Rend./m. 0.015 día 1.50 u 725.00 1,087.507 Maestro de área (MA) Rend./m. 0.015 día 1.50 u 1,125.00 1,687.508 Brigada topográfica Rend./m. 0.015 día 1.50 u 4,600.00 6,900.00

Unid. $13,850.62M $187.47

M2 $52.09

*REV 10730000 REVESTIMIENTO EN PAREDES

*REV 10730001 CERAMICA CRIOLLA TIPO 01:1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 409.51 450.463 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 252.38 252.38

M2 $794.85*REV 10730002 CERAMICA CRIOLLA TIPO 02:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 443.64 488.003 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 252.38 252.38

Page 135: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 105

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

M2 $832.39*REV 10730003 CERAMICA CRIOLLA TIPO 03:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 477.78 525.563 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 252.38 252.38

M2 $869.95*REV 10730004 CERAMICA CRIOLLA TIPO 04:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 546.04 600.643 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 252.38 252.38

M2 $945.03*REV 10730005 CERAMICA CRIOLLA TIPO 05:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 682.54 750.793 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 252.38 252.38

M2 $1,095.18*REV 10730006 CERAMICA CRIOLLA TIPO 06:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 750.79 825.873 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 252.38 252.38

M2 $1,170.26*REV 10730007 CERAMICA CRIOLLA TIPO 07:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 887.31 976.043 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 252.38 252.38

M2 $1,320.43*REV 10730008 CERAMICA CRIOLLA TIPO 08:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 1,023.80 1,126.183 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 252.38 252.38

M2 $1,470.57*REV 10730009 CERAMICA IMPORT. TIPO 09:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 1,160.31 1,276.343 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 278.95 278.95

M2 $1,647.30*REV 10730010 CERAMICA IMPORT. TIPO 10:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 1,262.69 1,388.963 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 278.95 278.95

M2 $1,759.92*REV 10730011 CERAMICA IMPORT. TIPO 11:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 1,365.08 1,501.593 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 278.95 278.95

M2 $1,872.55*REV 10730012 CERAMICA IMPORT. TIPO 12:

1 Mortero 1:2 imp. + 5% desp. 0.0053 m3 6,371.00 33.772 Baldosas + 10% desp. 1.10 m2 1,501.59 1,651.753 Corte de chazos 5.00 u 7.05 35.254 Lechada cemento bco. + 10% desp. 0.0330 fda 600.00 19.805 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.196 Colocación 1.00 m2 278.95 278.95

M2 $2,022.71*REV 10730013 LADRILLO BISCOCHO 2"x2"x8":

1 Mortero 1:2 imp. + 20% desp. 0.0120 m3 6,371.00 76.452 Ladrillos + transporte + 5% desp. 58.00 u 9.39 544.623 Corte de chazos 5.80 u 30.16 174.934 Colocación 58.00 u 6.31 365.98

M2 $1,161.98*REV 10730014 LADRILLO 2"x4"x8":

Page 136: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 106

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

1 Mortero 1:2 imp. + 20% desp. 0.0120 m3 6,371.00 76.452 Ladrillos + transporte + 5% desp. 58.00 u 13.39 776.623 Corte de chazos 5.80 u 30.16 174.934 Estopa (1 lb. / 20 m2) 0.05 lb 63.80 3.195 Colocación 58.00 u 6.31 365.98

M2 $1,397.17

*TEC 10750000 TECHOS DE MADERA CON FORRO DE MADERA

*TEC 10750001 TECHO TEJA ASF., FORRADO EN CAOBA (SOBRE DINTEL CORRIDO):Durmientes: 2" x 4" Vigas (Limatesa): 2" x 6"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 6"Tablas (borde perimetral): 1" x 6"

1 Durmientes en caoba sobre dintel + 25% desp. 1.39 pt 135.00 187.652 Vigas (limatesa) en caoba + 25% desp. 1.63 pt 135.00 220.053 Bajantes o cargaderas en caoba + 25% desp. 7.75 pt 135.00 1,046.254 Separadores de Bajantes en caoba + 25% desp. 3.66 pt 135.00 494.105 Tablas en caoba en borde perimetral + 25% desp. 1.17 pt 135.00 157.956 Tablas (forro) en caoba + 25% desp. 16.50 pt 135.00 2,227.507 Teja asfáltica 3' x 1', Felpa, instadada + 10% desp. 1.16 m2 324.10 375.968 Transporte teja asfáltica 34.84 u 0.22 7.669 Caballete de teja asfáltica + 10% desp. 0.40 m 114.81 45.9210 Línea doble teja asfáltica inst. todo costo, en bordes 0.60 m 114.81 68.8911 Clavos corrientes (5 lb. / 100 p2) 0.78 lb 24.79 19.3412 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 39.20 32.3413 Clavos galv. ¾" para cartón (125 unid. / m2) 0.43 lb 47.56 20.4514 Andamios 1.11 m2 68.95 76.5315 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 1,682.00 185.0216 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,200.60 2,161.0817 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 9.89 124.7118 Mano de obra madera sin forro 15.60 pt 43.50 678.6019 Mano de obra madera del forro + laqueado 11.93 pt 91.35 1,089.81

M2 $9,219.81*TEC 10750002 TECHO TEJA ASF., FORRADO EN CEDRO (SOBRE DINTEL CORRIDO):

Durmientes: 2" x 4" Vigas (Limatesa): 2" x 6"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 6"Tablas (borde perimetral): 1" x 6"

1 Durmientes en cedro sobre dintel + 25% desp. 1.39 pt 143.00 198.772 Vigas (limatesa) en cedro + 25% desp. 1.63 pt 143.00 233.093 Bajantes o cargaderas en cedro + 25% desp. 7.75 pt 143.00 1,108.254 Separadores de Bajantes en cedro + 25% desp. 3.66 pt 143.00 523.385 Tablas en cedro en borde perimetral + 25% desp. 1.17 pt 143.00 167.316 Tablas (forro) en cedro + 25% desp. 16.50 pt 143.00 2,359.507 Teja asfáltica 3' x 1', Felpa, instadada + 10% desp. 1.16 m2 324.10 375.968 Transporte 34.84 u 0.22 7.669 Caballete de teja asfáltica + 10% desp. 0.40 m 114.81 45.9210 Línea doble teja asfáltica inst. todo costo, en bordes 0.60 m 114.81 68.8911 Clavos corrientes (5 lb. / 100 p2) 0.78 lb 24.79 19.3412 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 39.20 32.3413 Clavos galv. ¾" para cartón (125 unid. / m2) 0.43 lb 47.56 20.4514 Andamios 1.11 m2 68.95 76.5315 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 1,682.00 185.0216 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,200.60 2,161.0817 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 9.89 124.7118 Mano de obra madera sin forro 15.60 pt 43.50 678.6019 Mano de obra madera del forro + laqueado 11.93 pt 91.35 1,089.81

M2 $9,476.61*TEC 10750003 TECHO TEJA ASF., FORRADO EN PINO TRAT. (SOBRE DINTEL CORRIDO):

Durmientes: 2" x 4" Vigas (Limatesa): 2" x 6"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 6"Tablas (borde perimetral): 1" x 6"

1 Durmientes en pino trat. sobre dintel + 25% desp. 1.39 pt 42.00 58.382 Vigas (limatesa) en pino trat. + 25% desp. 1.63 pt 42.00 68.463 Bajantes o cargaderas en pino trat. + 25% desp. 7.75 pt 42.00 325.504 Separadores de Bajantes en pino trat. + 25% desp. 3.66 pt 42.00 153.725 Tablas en pino trat. en borde perimetral + 25% desp. 1.17 pt 42.00 49.146 Tablas (forro) en pino trat. + 25% desp. 16.50 pt 42.00 693.007 Teja asfáltica 3' x 1', Felpa, instadada + 10% desp. 1.16 m2 324.10 375.968 Transporte teja asfáltica 34.84 u 0.22 7.669 Caballete de teja asfáltica + 10% desp. 0.40 m 114.81 45.9210 Línea doble teja asfáltica inst. todo costo, en bordes 0.60 m 114.81 68.8911 Clavos corrientes (5 lb. / 100 p2) 0.78 lb 24.79 19.3412 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 39.20 32.3413 Clavos galv. ¾" para cartón (125 unid. / m2) 0.43 lb 47.56 20.4514 Andamios 1.11 m2 68.95 76.5315 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 1,682.00 185.0216 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,200.60 2,161.0817 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 9.89 124.7118 Mano de obra madera sin forro 15.60 pt 43.50 678.6019 Mano de obra madera del forro + laqueado 11.93 pt 91.35 1,089.81

M2 $6,234.51*TEC 10750004 TECHO TEJA ASF., FORRADO EN ROBLE BRASILEÑO (SOBRE DINTEL CORRIDO):

Durmientes: 2" x 4" Vigas (Limatesa): 2" x 6"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 6"Tablas (borde perimetral): 1" x 6"

1 Durmientes en roble sobre dintel + 25% desp. 1.39 pt 130.00 180.702 Vigas (limatesa) en roble + 25% desp. 1.63 pt 130.00 211.903 Bajantes o cargaderas en roble + 25% desp. 7.75 pt 130.00 1,007.50

Page 137: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 107

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

4 Separadores de Bajantes en roble + 25% desp. 3.66 pt 130.00 475.805 Tablas en roble en borde perimetral + 25% desp. 1.17 pt 130.00 152.106 Tablas (forro) en roble + 25% desp. 16.50 pt 130.00 2,145.007 Teja asfáltica 3' x 1', Felpa, instadada + 10% desp. 1.16 m2 324.10 375.968 Transporte teja asfáltica 34.84 u 0.22 7.669 Caballete de teja asfáltica + 10% desp. 0.40 m 114.81 45.9210 Línea doble teja asfáltica inst. todo costo, en bordes 0.60 m 114.81 68.8911 Clavos corrientes (5 lb. / 100 p2) 0.78 lb 24.79 19.3412 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 39.20 32.3413 Clavos galv. ¾" para cartón (125 unid. / m2) 0.43 lb 47.56 20.4514 Andamios 1.11 m2 68.95 76.5315 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 1,682.00 185.0216 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,200.60 2,161.0817 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 9.89 124.7118 Mano de obra madera sin forro 15.60 pt 43.50 678.6019 Mano de obra madera del forro + laqueado 11.93 pt 91.35 1,089.81

M2 $9,059.31*TEC 10750005 TECHO TEJA CURVA BARRO, FORRADO EN CAOBA (SOBRE DINTEL CORRIDO):

Durmientes: 3" x 6" Vigas (Limatesa): 2" x 10"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 10"Tablas (borde perimetral): 1" x 10"

1 Durmientes en caoba sobre dintel + 25% desp. 3.13 pt 135.00 422.552 Vigas (limatesa) en caoba + 25% desp. 2.71 pt 135.00 365.853 Bajantes o cargaderas en caoba + 25% desp. 12.92 pt 135.00 1,744.204 Separadores de Bajantes en caoba + 25% desp. 6.09 pt 135.00 822.155 Tablas en caoba en borde perimetral + 25% desp. 1.94 pt 135.00 261.906 Tablas (forro) en caoba + 25% desp. 16.50 pt 135.00 2,227.507 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 15.05 524.368 Mortero 1:2 imp. + 10% desp. 0.055 m3 6,371.00 350.419 Estopa (1 lb. / 20 m2) 0.06 lb 63.80 3.8310 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 0.54 18.8111 Caballete de teja 0.20 u 82.86 16.8412 Clavos corrientes (5 lb. / 100 p2) 1.34 lb 24.79 33.2213 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 39.20 32.3414 Andamios 1.11 m2 68.95 76.5315 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 1,682.00 185.0216 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,200.60 2,161.0817 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 9.89 124.7118 Mano de obra madera sin forro 26.79 pt 43.50 1,165.3719 Mano de obra madera del forro + laqueado 11.93 pt 91.35 1,089.8120 Bitupol 4 mm., reforz. poliester, 10 años gar. 1.11 m2 505.24 560.8221 Coloc. de tejas 1.00 m2 228.13 228.1322 Coloc. Caballete 0.20 u 37.09 7.54

M2 $12,422.97*TEC 10750006 TECHO TEJA CURVA BARRO, FORRADO EN CEDRO (SOBRE DINTEL CORRIDO):

Durmientes: 3" x 6" Vigas (Limatesa): 2" x 10"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 10"Tablas (borde perimetral): 1" x 10"

1 Durmientes en cedro sobre dintel + 25% desp. 3.13 pt 143.00 447.592 Vigas (limatesa) en cedro + 25% desp. 2.71 pt 143.00 387.533 Bajantes o cargaderas en cedro + 25% desp. 12.92 pt 143.00 1,847.564 Separadores de Bajantes en cedro + 25% desp. 6.09 pt 143.00 870.875 Tablas en cedro en borde perimetral + 25% desp. 1.94 pt 143.00 277.426 Tablas (forro) en cedro + 25% desp. 16.50 pt 143.00 2,359.507 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 15.05 524.368 Mortero 1:2 imp. + 10% desp. 0.055 m3 6,371.00 350.419 Estopa (1 lb. / 20 m2) 0.06 lb 63.80 3.8310 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 0.54 18.8111 Caballete de teja. 0.20 u 71.43 14.5112 Clavos corrientes (5 lb. / 100 p2) 1.34 lb 24.79 33.2213 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 39.20 32.3414 Andamios 1.11 m2 68.95 76.5315 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 1,682.00 185.0216 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,200.60 2,161.0817 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 9.89 124.7118 Mano de obra madera sin forro 26.79 pt 43.50 1,165.3719 Mano de obra madera del forro + laqueado 11.93 pt 91.35 1,089.8120 Bitupol 4 mm., reforz. poliester, 10 años gar. 1.11 m2 505.24 560.8221 Coloc. de tejas 1.00 m2 228.13 228.1322 Coloc. Caballete 0.20 u 37.09 7.54

M2 $12,766.96*TEC 10750007 TECHO TEJA CURVA BARRO, FORRADO EN PINO TRAT. (SOBRE DINTEL CORRIDO):

Durmientes: 3" x 6" Vigas (Limatesa): 2" x 10"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 10"Tablas (borde perimetral): 1" x 10"

1 Durmientes en pino sobre dintel + 25% desp. 3.13 pt 42.00 131.462 Vigas (limatesa) en pino + 25% desp. 2.71 pt 42.00 113.823 Bajantes o cargaderas en pino + 25% desp. 12.92 pt 42.00 542.644 Separadores de Bajantes en pino + 25% desp. 6.09 pt 42.00 255.785 Tablas en pino en borde perimetral + 25% desp. 1.94 pt 42.00 81.486 Tablas (forro) en pino + 25% desp. 16.50 pt 42.00 693.007 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 15.05 524.368 Mortero 1:2 imp. + 10% desp. 0.055 m3 6,371.00 350.419 Estopa (1 lb. / 20 m2) 0.06 lb 63.80 3.8310 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 0.54 18.8111 Caballete de teja. 0.20 u 71.43 14.5112 Clavos corrientes (5 lb. / 100 p2) 1.34 lb 24.79 33.2213 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 39.20 32.34

Page 138: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 108

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

14 Andamios 1.11 m2 68.95 76.5315 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 1,682.00 185.0216 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,200.60 2,161.0817 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 9.89 124.7118 Mano de obra madera sin forro 26.79 pt 43.50 1,165.3719 Mano de obra madera del forro + laqueado 11.93 pt 91.35 1,089.8120 Bitupol 4 mm., reforz. poliester, 10 años gar. 1.11 m2 505.24 560.8221 Coloc. de tejas 1.00 m2 228.13 228.1322 Coloc. Caballete 0.20 u 37.09 7.54

M2 $8,394.67*TEC 10750008 TECHO TEJA CURVA BARRO, FORRADO EN ROBLE BRASILEÑO (SOBRE DINTEL CORRIDO):

Durmientes: 3" x 6" Vigas (Limatesa): 2" x 10"Bajantes cada .5 m. y separadores cada 1 m: 1 ½" x 10"Tablas (borde perimetral): 1" x 10"

1 Durmientes en roble sobre dintel + 25% desp. 3.13 pt 130.00 406.902 Vigas (limatesa) en roble + 25% desp. 2.71 pt 130.00 352.303 Bajantes o cargaderas en roble + 25% desp. 12.92 pt 130.00 1,679.604 Separadores de Bajantes en roble + 25% desp. 6.09 pt 130.00 791.705 Tablas en roble en borde perimetral + 25% desp. 1.94 pt 130.00 252.206 Tablas (forro) en roble + 25% desp. 16.50 pt 130.00 2,145.007 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 15.05 524.368 Mortero 1:2 imp. + 10% desp. 0.055 m3 6,371.00 350.419 Estopa (1 lb. / 20 m2) 0.06 lb 63.80 3.8310 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 0.54 18.8111 Caballete de teja. 0.20 u 71.43 14.5112 Clavos corrientes (5 lb. / 100 p2) 1.34 lb 24.79 33.2213 Clavos galvanizados en forro (5 lb. / 100 p2) 0.83 lb 39.20 32.3414 Andamios 1.11 m2 68.95 76.5315 Placas unir vigas (¼") inst. + 10% desp. 0.11 u 1,682.00 185.0216 Placas unir bajantes-vigas (¼") inst.+ 10% desp. 1.80 u 1,200.60 2,161.0817 Tornillos 3/8" x 3", galv., arandela + tuerca + 10% 12.61 u 9.89 124.7118 Mano de obra madera sin forro 26.79 pt 43.50 1,165.3719 Mano de obra madera del forro + laqueado 11.93 pt 91.35 1,089.8120 Bitupol 4 mm., reforz. poliester, 10 años gar. 1.11 m2 505.24 560.8221 Coloc. de tejas 1.00 m2 228.13 228.1322 Coloc. Caballete 0.20 u 37.09 7.54

M2 $12,204.19*TEC 10750009 TECHO TEJA CURVA BARRO SOBRE FINO DE HORM. IMPERMEABILIZADO:

1 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 15.05 524.362 Mortero 1:2 imp. + 10% desp. 0.055 m3 6,371.00 350.413 Estopa (1 lb. / 20 m2) 0.06 lb 63.80 3.834 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 0.54 18.815 Caballete de teja. 0.20 u 71.43 14.516 Bitupol 4 mm., reforz. poliester, 10 años gar. 1.11 m2 505.24 560.827 Coloc. de tejas 1.00 m2 228.13 228.138 Coloc. Caballete 0.20 u 37.09 7.54

M2 $1,708.41*TEC 10750010 TECHO TEJA CURVA BARRO Y TIJERILLA EN PINO:

1 Madera tijerilla + 25% desp. 2.91 pt 29.00 84.272 Correas, .948 piezas 2"x4"x10' + 25% desp., pino am. bruto. 7.90 pt 29.00 229.103 Tejas 16" (.18 y .13x.40 m.) + 25% desp. 34.84 u 15.05 524.364 Transporte tejas de barro (camión con 5,000 unid.) 34.84 u 0.54 18.815 Caballete de teja. 0.20 u 71.43 14.516 Alambre #18 (0.5 lb. / m2) 0.50 lb 25.44 12.727 Clavos corrientes (5 lb. / 100 p2) 0.54 lb 24.79 13.468 Mano de obra madera 10.86 pt 43.50 472.549 Coloc. de tejas 1.00 m2 228.13 228.1310 Coloc. Caballete 0.20 u 37.09 7.54

M2 $1,605.44*TEC 10750011 TECHO ZINC CAL. 26 Y TIJERILLA EN PINO:

1 Madera tijerilla + 25% desp. 2.9058 pt 29.00 84.272 Correas, .677 piezas 2"x4"x10' + 25% desp., pino am. Bruto 5.6417 pt 29.00 163.613 Planchas de ZINC ACANALADO cal. 26, de 3'x6' + 25% desp. 1.05 u 498.80 523.744 Caballete de zinc de 3', cal. 29 0.1354 m 134.56 18.225 Clavos corrientes (5 lb. / 100 p2) 0.43 lb 24.79 10.666 Clavos de zinc + 5% desp. 0.14 lb 33.76 4.737 Mano de obra madera 8.55 pt 43.50 371.828 Coloc. láminas de zinc 1.33 u 28.53 37.949 Coloc. caballete de zinc 0.14 u 37.27 5.05

M2 $1,220.04

*TERTEC 10770000 TECHOS (TERMINACION)

*TERTEC 10770001 FINO TECHO BERMUDA:1 Fino inclinado para preparar superficie 1.00 m2 286.08 286.082 Mortero 1:3 + 5% desp., 4.5 cm. espesor 0.0473 m3 3,932.52 186.013 Reglas (1 de 1"x4"x10' / 10 usos) 0.3333 pt 154.28 51.424 Subida materiales 0.0473 m3 532.66 25.195 Mano de obra Bermuda, sin los cantos 1.00 m2 188.46 188.466 Cantos cada 0.40 m. 3.00 m 38.33 114.99

M2 $852.15*TERTEC 10770002 FINO TECHO INCLINADO:

1 Mortero 1:3 + 5% desp., 4 cm. espesor 0.0420 m3 3,932.52 165.172 Reglas (1 de 1"x4"x10' / 10 usos) 0.3333 pt 154.28 51.423 Subida materiales 0.0420 m3 532.66 22.374 Mano de obra 1.00 m2 47.12 47.12

M2 $286.08*TERTEC 10770003 FINO TECHO PLANO:

Page 139: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 109

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

1 Mortero 1:3 + 5% desp. (6 cm. espesor promedio). 0.0630 m3 3,932.52 247.752 Reglas (1 de 1"x4"x10' / 10 usos) 0.3333 pt 154.28 51.423 Subida materiales 0.0630 m3 532.66 33.564 Mano de obra 1.00 m2 76.56 76.56

M2 $409.29*TERTEC 10770004 ZABALETA DE TECHO:

1 Mortero 1:3. 0.0105 m3 3,932.52 41.292 Subida materiales 0.0105 m3 532.66 5.593 Mano de obra 1.00 m 40.83 40.83

M $87.71

*VEN 10790000 VENTANAS

*VEN 10790001 VENTANA SALOM. ALUM. NAT. Y VIDRIO CLARO, MANIG. AA:1 Ventana 1.00 m2 3,642.85 3,642.852 Operador de manigueta 2.0833 u 102.59 213.733 Transporte + Instalación (12.00%) 12.00% 462.79

P2 $401.43 M2 $4,319.37

*VEN 10790002 VENTANA SALOM. ALUMINIO BCO., MANIG. AA:1 Ventana 1.00 m2 3,226.55 3,226.552 Operador de manigueta 2.0833 u 102.59 213.733 Transporte + Instalación (12.00%) 12.00% 412.83

P2 $358.10 M2 $3,853.11

*VEN 10790003 VENTANA SALOM. ALUMINIO BRONCE, MANIG. AA:1 Ventana 1.00 m2 3,414.53 3,414.532 Operador de manigueta 2.0833 u 102.59 213.733 Transporte + Instalación (12.00%) 12.00% 435.39

P2 $377.66 M2 $4,063.65

*VEN 10790004 VENTANA SALOM. ALUM. Y VIDRIO, TODO BRONCE,MANIG. AA:1 Ventana 1.00 m2 3,345.00 3,345.002 Operador de manigueta 2.0833 u 102.59 213.733 Transporte + Instalación (12.00%) 12.00% 427.05

P2 $370.43 M2 $3,985.78

*VEN 10790005 VENTANA SALOM. ALUM. NAT. Y VIDRIO CLARO, PALANCA:1 Ventana 1.00 m2 2,770.76 2,770.762 Operador de palanca 2.0833 u 28.21 58.773 Transporte + Instalación (12.00%) 12.00% 339.54

P2 $294.52 M2 $3,169.07

*VEN 10790006 VENTANA SALOM. ALUMINIO BCO., PALANCA:1 Ventana 1.00 m2 3,232.99 3,232.992 Operador de palanca 2.0833 u 28.21 58.773 Transporte + Instalación (12.00%) 12.00% 395.01

P2 $342.64 M2 $3,686.77

*VEN 10790007 VENTANA SALOM. ALUM. NAT., VIDRIO BRONCE, PALANCA:1 Ventana 1.00 m2 2,372.92 2,372.922 Operador de palanca 2.0833 u 28.21 58.773 Transporte + Instalación (12.00%) 12.00% 291.80

P2 $253.11 M2 $2,723.49

*VERBLO 10810000 VERJAS DE BLOQUES DE HORMIGON

*VERBLO 10810001 VERJA DE BLOQUES 5", RETALLE, COL. AMARRE CADA 3.00 m., CALICHE, Sin empañete:Largo: 32.00 H bloques: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,021.52

1 Excación de zapata 0.45 x 0.45 m., CALICHE a mano 6.48 m3 382.65 2,479.572 Regar material producto de excavación 8.100 m3 198.77 1,610.043 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 1,915.88 4,828.024 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 1,915.88 5,939.235 M. O. acero zapata del muro 33.00 m 71.30 2,352.906 M. O. acero col. amarre del muro 30.33 m 71.30 2,162.537 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,171.76 9,134.678 Horm. 1:2:4 en columnas de amarre de .175 x .20 m. Col. Cada: 3.00 0.92 m3 3,572.33 3,286.549 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 29.00 3,845.6910 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 24.79 657.4311 Clavos de acero (¼ lb / metro). 6.42 lb 45.24 290.4412 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 25.44 163.3213 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 141.22 3,625.1214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 18.54 190.4115 Muro de bloques de 5" x 8" x 16" 65.27 m2 792.97 51,754.51

2,885.01 M U $92,320.42M2 Verja $1,311.37

*VERBLO 10810002 VERJA DE BLOQUES 6", RETALLE, COL. AMARRE CADA 3.00 m., CALICHE, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,035.79

1 Excación de zapata 0.45 x 0.45 m., CALICHE a mano 6.48 m3 382.65 2,479.572 Regar material producto de excavación 8.100 m3 198.77 1,610.043 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 1,915.88 4,828.024 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 1,915.88 5,939.235 M. O. acero zapata del muro 33.00 m 71.30 2,352.906 M. O. acero col. amarre del muro 30.33 m 71.30 2,162.537 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,171.76 9,134.678 Horm. 1:2:4 en columnas de amarre de .20 x .20 m. Col. Cada: 3.00 1.03 m3 3,572.33 3,679.509 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 29.00 3,845.6910 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 24.79 657.43

Page 140: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 110

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

11 Clavos de acero (¼ lb / metro). 6.42 lb 45.24 290.4412 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 25.44 163.3213 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 141.22 3,625.1214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 18.54 190.4115 Muro de bloques de 6" x 8" x 16" 65.27 m2 802.34 52,366.06

2,916.40 M U $93,324.93M2 Verja $1,325.64

*VERBLO 10810003 VERJA DE BLOQUES 8", RETALLE, COL. AMARRE CADA 3.00 m., CALICHE, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,212.31

1 Excación de zapata 0.6 x 0.45 m., CALICHE a mano 8.64 m3 382.65 3,306.102 Regar material producto de excavación 10.800 m3 198.77 2,146.723 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.840 qq 1,915.88 5,441.104 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 1,915.88 5,939.235 M. O. acero zapata del muro 33.00 m 71.30 2,352.906 M. O. acero col. amarre del muro 30.33 m 71.30 2,162.537 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,171.76 9,134.678 Horm. 1:2:4 en columnas de amarre de .25 x .20 m. Col. Cada: 3.00 1.28 m3 3,572.33 4,572.589 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 29.00 3,845.6910 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 24.79 657.4311 Clavos de acero (¼ lb / metro). 6.42 lb 45.24 290.4412 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 25.44 163.3213 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 141.22 3,625.1214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 18.54 190.4115 Muro de bloques de 8" x 8" x 16" 65.27 m2 979.06 63,899.98

3,366.51 M U $107,728.22M2 Verja $1,530.23

*VERBLO 10810004 VERJA DE BLOQUES 5", RETALLE, COL. AMARRE CADA 3.00 m., ROCA, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,021.52

1 Excación de zapata 0.45 x 0.45 m., ROCA a mano 6.48 m3 1,635.30 10,596.742 Regar material producto de excavación 10.370 m3 198.77 2,061.243 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 1,915.88 4,828.024 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 1,915.88 5,939.235 M. O. acero zapata del muro 33.00 m 71.30 2,352.906 M. O. acero col. amarre del muro 30.33 m 71.30 2,162.537 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,171.76 9,134.678 Horm. 1:2:4 en columnas de amarre de .175 x .20 m. Col. Cada: 3.00 0.92 m3 3,572.33 3,286.549 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 29.00 3,845.6910 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 24.79 657.4311 Clavos de acero (¼ lb / metro). 6.42 lb 45.24 290.4412 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 25.44 163.3213 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 141.22 3,625.1214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 18.54 190.4115 Muro de bloques de 5" x 8" x 16" 65.27 m2 792.97 51,754.51

3,152.77 M U $100,888.79M2 Verja $1,433.08

*VERBLO 10810005 VERJA DE BLOQUES 6", RETALLE, COL. AMARRE CADA 3.00 m., ROCA, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,035.79

1 Excación de zapata 0.45 x 0.45 m., ROCA a mano 6.48 m3 1,635.30 10,596.742 Regar material producto de excavación 10.370 m3 198.77 2,061.243 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 1,915.88 4,828.024 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 1,915.88 5,939.235 M. O. acero zapata del muro 33.00 m 71.30 2,352.906 M. O. acero col. amarre del muro 30.33 m 71.30 2,162.537 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,171.76 9,134.678 Horm. 1:2:4 en columnas de amarre de .20 x .20 m. Col. Cada: 3.00 1.03 m3 3,572.33 3,679.509 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 29.00 3,845.6910 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 24.79 657.4311 Clavos de acero (¼ lb / metro). 6.42 lb 45.24 290.4412 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 25.44 163.3213 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 141.22 3,625.1214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 18.54 190.4115 Muro de bloques de 6" x 8" x 16" 65.27 m2 802.34 52,366.06

3,184.17 M U $101,893.30M2 Verja $1,447.35

*VERBLO 10810006 VERJA DE BLOQUES 8", RETALLE, COL. AMARRE CADA 3.00 m., ROCA, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,048.48

1 Excación de zapata 0.45 x 0.45 m., ROCA a mano 8.64 m3 1,635.30 14,128.992 Regar material producto de excavación 13.820 m3 198.77 2,747.003 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.840 qq 1,915.88 5,441.104 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 1,915.88 5,939.235 M. O. acero zapata del muro 33.00 m 71.30 2,352.906 M. O. acero col. amarre del muro 30.33 m 71.30 2,162.537 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,171.76 9,134.678 Horm. 1:2:4 en columnas de amarre de .25 x .20 m. Col. Cada: 3.00 1.28 m3 3,572.33 4,572.589 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 29.00 3,845.6910 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 24.79 657.4311 Clavos de acero (¼ lb / metro). 6.42 lb 45.24 290.4412 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 25.44 163.3213 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 141.22 3,625.1214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 18.54 190.4115 Muro de bloques de 8" x 8" x 16" 65.27 m2 802.34 52,366.06

3,363.05 M U $107,617.47M2 Verja $1,528.66

*VERBLO 10810007 VERJA DE BLOQUES 5", RETALLE, COL. AMARRE CADA 3.00 m., TIERRA, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,021.52

1 Excación de zapata 0.45 x 0.45 m., TIERRA a mano 6.48 m3 235.85 1,528.312 Regar material producto de excavación 7.780 m3 198.77 1,546.433 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 1,915.88 4,828.02

Page 141: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 111

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

4 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 1,915.88 5,939.235 M. O. acero zapata del muro 33.00 m 71.30 2,352.906 M. O. acero col. amarre del muro 30.33 m 71.30 2,162.537 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,171.76 9,134.678 Horm. 1:2:4 en columnas de amarre de .175 x .20 m. Col. Cada: 3.00 0.92 m3 3,572.33 3,286.549 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 29.00 3,845.6910 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 24.79 657.4311 Clavos de acero (¼ lb / metro). 6.42 lb 45.24 290.4412 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 25.44 163.3213 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 141.22 3,625.1214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 18.54 190.4115 Muro de bloques de 5" x 8" x 16" 65.27 m2 792.97 51,754.51

2,853.30 M U $91,305.55M2 Verja $1,296.95

*VERBLO 10810008 VERJA DE BLOQUES 6", RETALLE, COL. AMARRE CADA 3.00 m., TIERRA, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,035.79

1 Excación de zapata 0.45 x 0.45 m., TIERRA a mano 6.48 m3 235.85 1,528.312 Regar material producto de excavación 7.780 m3 198.77 1,546.433 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.520 qq 1,915.88 4,828.024 Acero col. amarre: 3/8" en 4 varillas long. y estribos a 0.20 m. + 10% desp. 3.100 qq 1,915.88 5,939.235 M. O. acero zapata del muro 33.00 m 71.30 2,352.906 M. O. acero col. amarre del muro 30.33 m 71.30 2,162.537 Horm. 1:3:5 en zapata de .45 x .20 m. 2.88 m3 3,171.76 9,134.678 Horm. 1:2:4 en columnas de amarre de .20 x .20 m. Col. Cada: 3.00 1.03 m3 3,572.33 3,679.509 Madera de pino americano, bruto, 4 usos + 10% desp. 132.61 pt 29.00 3,845.6910 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 24.79 657.4311 Clavos de acero (¼ lb / metro). 6.42 lb 45.24 290.4412 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 25.44 163.3213 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 141.22 3,625.1214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 18.54 190.4115 Muro de bloques de 5" x 8" x 16" 65.27 m2 802.34 52,366.06

2,884.69 M U $92,310.06M2 Verja $1,311.22

Page 142: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 112

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.REFERENCIA D E S C R I P C I O N CANT. U. P. UNIT SUBTOTAL

*VERBLO 10810009 VERJA DE BLOQUES 8", RETALLE, COL. AMARRE CADA 3.00 m., TIERRA, Sin empañete:Largo: 32.00 Alto: 2.20 Area: 70.40 m2 Costo m2 VERJA sin zapata 1,048.48

1 Excación de zapata 0.60 x 0.40 x 32.20 m., tierra a mano 8.64 m3 235.85 2,037.742 Regar material producto de excavación 10.370 m3 198.77 2,061.243 Acero zapata: 3/8" en 3 varillas long. y cangrejos a 0.25 m. + 5% desp. 2.840 qq 1,915.88 5,441.104 Acero col. amarre: 3/8" en 4 varillas long. y cangrejos a 0.20 m. + 10% desp. 3.100 qq 1,915.88 5,939.235 M. O. acero zapata del muro 33.00 m 71.30 2,352.906 M. O. acero col. amarre del muro 30.33 m 71.30 2,162.537 Horm. 1:3:5 en zapata de .60 x .25 x 32.20 m. 2.88 m3 3,171.76 9,134.678 Horm. 1:2:4 en columnas de amarre de .25 x .20 m. Col. Cada: 3.00 1.28 m3 3,572.33 4,572.589 Madera de pino americano, bruto, 4 usos + 25% desp. 132.61 pt 29.00 3,845.6910 Clavos corrientes (5 lb. / 100 pie madera). 26.52 lb 24.79 657.4311 Clavos de acero (¼ lb / metro). 6.42 lb 45.24 290.4412 Alambre calibre #14 (¼ lb. / metro). 6.42 lb 25.44 163.3213 M. O. Carpintería colocar madera columnas amarre, retalle .025 m. 25.67 m 141.22 3,625.1214 M. O. Carpintería desencobrar madera columnas amarre, retalle .025 m. 10.27 m2 18.54 190.4115 Muro de bloques de 8" x 8" x 16", 11 líneas 65.27 m2 802.34 52,366.06

2,963.76 M U $94,840.46M2 Verja $1,347.17

Page 143: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 113

ANALISIS DE COSTOSINDICE ABR 2010

88.36% 1,160.00100.00% 63.6088.97% 1,223.60

112.41% 1,659.09100.00% 50.88112.04% 1,709.97

112.41% 1,659.09100.00% 50.88112.04% 1,709.97

112.41% 1,659.09100.00% 50.88112.04% 1,709.97

112.41% 1,659.09100.00% 50.88112.04% 1,709.97

112.41% 1,659.09100.00% 50.88112.04% 1,709.97

112.41% 1,659.09100.00% 50.88112.04% 1,709.97

106.50% 1,849.99100.00% 50.88106.32% 1,900.87

106.50% 1,849.99100.00% 50.88106.32% 1,900.87

106.50% 1,849.99100.00% 50.88106.32% 1,900.87

106.50% 1,849.99100.00% 50.88106.32% 1,900.87

106.50% 1,849.99100.00% 50.88106.32% 1,900.87

106.50% 1,849.99100.00% 50.88106.32% 1,900.87

100.00% 376.98100.00% 78.65100.00% 32.8688.98% 13.70

100.00% 0.07100.00% 20.70100.00% 6.37100.00% 12.74100.00% 171.6099.79% 713.67

100.00% 389.08100.00% 102.25100.00% 71.44112.03% 42.24100.00% 0.07100.00% 20.70100.00% 6.37100.00% 12.74100.00% 143.00100.64% 787.89

100.00% 363.72100.00% 122.69100.00% 171.46112.04% 84.30100.00% 0.07100.00% 20.70

Page 144: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 114

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 12.74100.00% 25.61100.00% 143.00101.07% 944.29

100.00% 363.72100.00% 122.69100.00% 85.73112.03% 42.24100.00% 0.07100.00% 20.70100.00% 6.37100.00% 12.74100.00% 143.00100.64% 797.26

100.00% 363.72100.00% 122.69100.00% 85.73112.03% 42.24100.00% 0.07100.00% 20.70100.00% 6.37100.00% 12.74100.00% 180.96100.61% 835.22

100.00% 470.32100.00% 153.37100.00% 327.20112.04% 126.54106.32% 128.88100.00% 0.07100.00% 5.27100.00% 20.70100.00% 24.41100.00% 25.61100.00% 158.86101.62% 1,441.23

100.00% 470.32100.00% 153.37100.00% 327.20112.04% 126.54100.00% 0.07100.00% 20.70100.00% 18.98100.00% 47.45100.00% 158.86101.15% 1,323.49

100.00% 470.32100.00% 153.37100.00% 218.61112.04% 84.30100.00% 0.07100.00% 20.70100.00% 12.74100.00% 25.61100.00% 158.86100.89% 1,144.58

100.00% 470.32100.00% 153.37100.00% 109.31112.03% 42.24100.00% 0.07100.00% 20.70100.00% 6.37100.00% 12.74100.00% 158.86100.52% 973.98

100.00% 470.32100.00% 153.37100.00% 327.20112.04% 84.30100.00% 0.07100.00% 20.70100.00% 12.74100.00% 25.48100.00% 158.86100.81% 1,253.04

100.00% 1,350.72100.00% 233.20100.00% 63.58112.03% 42.24

Page 145: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 115

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 0.07100.00% 20.70100.00% 6.37100.00% 12.74100.00% 292.50100.25% 2,022.12

100.00% 84.78100.00% 1,683.62100.00% 1,124.28100.00% 2,892.68

100.00% 54.64100.00% 961.08100.00% 632.36100.00% 1,648.08

100.00% 40.51100.00% 976.74100.00% 316.30100.00% 1,333.55

100.00% 25.94100.00% 7.95100.00% 27.00103.37% 250.5199.79% 285.47

100.00% 154.62100.00% 79.74100.00% 78.84100.86% 910.07

100.00% 40.09100.00% 12.65100.00% 42.00103.00% 347.46100.64% 318.90100.00% 176.70100.00% 79.74100.00% 90.10101.12% 1,107.64

100.00% 51.89100.00% 15.90100.00% 54.00102.75% 374.99100.52% 389.59100.00% 176.70100.00% 79.74100.00% 90.10101.00% 1,232.91

100.00% 1,836.57100.00% 2,495.50100.00% 195.50100.00% 1,745.80100.00% 251.21100.00% 62.79100.00% 139.20100.00% 28.65100.00% 24.24100.00% 495.90100.00% 1,685.92100.00% 1,714.00100.00% 963.07100.00% 525.00100.00% 2,900.00100.00% 2,000.00100.00% 17,063.35100.00% 955.39

Page 146: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 116

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 7,557.98100.00% 3,254.50100.00% 379.50100.00% 2,869.09100.00% 1,033.73100.00% 121.20100.00% 556.80100.00% 200.55100.00% 48.48100.00% 991.80100.00% 2,528.88100.00% 2,571.00100.00% 963.07100.00% 975.00100.00% 5,800.00100.00% 4,000.00100.00% 33,851.58100.00% 1,005.39

100.00% 350.90100.00% 136.35100.00% 3,643.50100.00% 868.25100.00% 637.10100.00% 25.14100.00% 1,116.80100.00% 6,778.04100.00% 677.80

100.00% 338.13100.00% 35.31100.00% 9.52100.00% 75.00100.00% 518.80100.00% 976.76

100.00% 533.60100.00% 35.31100.00% 9.52100.00% 75.00100.00% 593.43100.00% 1,246.86

100.00% 17.29100.00% 16.87100.00% 38.33100.00% 72.49

100.00% 9.19100.00% 20.91100.00% 30.10

100.00% 102.26100.00% 5.14100.00% 5.28100.00% 20.70100.00% 163.33100.00% 296.71

100.00% 122.47100.00% 5.14100.00% 41.77100.00% 63.27100.00% 3.94100.00% 111.36

Page 147: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 117

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 347.95

100.00% 102.26100.00% 5.14100.00% 5.28100.00% 20.70100.00% 87.50100.00% 220.88

100.00% 102.26100.00% 5.14100.00% 28.75100.00% 63.27100.00% 3.94100.00% 125.86100.00% 329.22

100.00% 93.07100.00% 5.14100.00% 5.28100.00% 20.70100.00% 13.25100.00% 96.05100.00% 233.49

100.00% 102.26100.00% 10.29100.00% 41.77100.00% 63.27100.00% 3.94100.00% 111.36100.00% 332.89

100.00% 102.26100.00% 222.19100.00% 63.27100.00% 3.94100.00% 66.25100.00% 457.91

100.00% 40.89100.00% 41.66100.00% 71.88100.00% 154.43

100.00% 35.33100.00% 5.14100.00% 13.41100.00% 53.88

100.00% 44.94100.00% 33.63100.00% 88.46100.00% 167.03

100.00% 22.47100.00% 16.82100.00% 76.67100.00% 115.96

100.00% 14.40100.00% 0.04100.00% 14.44

100.00% 6.00100.00% 0.04100.00% 6.04

100.00% 44.23100.00% 16.67100.00% 50.96100.00% 67.63

100.00% 183.70100.00% 5.14100.00% 87.50100.00% 276.34

100.00% 30.62100.00% 5.14100.00% 31.73100.00% 67.49

100.00% 1,020.80100.00% 220.61

Page 148: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 118

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 236.13100.00% 1,477.54

100.00% 1,148.40100.00% 220.61100.00% 182.19100.00% 259.74100.00% 1,810.94100.00% 1,646.31

100.00% 1,914.00100.00% 220.61

100.00% 236.13100.00% 2,370.74

100.00% 24.77

112.04% 2,793.75100.00% 349.50100.00% 34.95100.00% 5,308.74100.00% 907.56100.00% 377.30100.00% 212.17100.00% 4,947.81100.00% 570.95100.05% 4,135.44101.72% 19,638.17

102.17% 15,502.73100.00% 5,933.40101.57% 21,436.13

102.17% 15,502.73100.00% 6,188.60101.55% 21,691.33

102.17% 15,502.73100.00% 6,443.80101.53% 21,946.53

No toque las celdas que tengan color verde o las que aparecen en las columnas I en adelante.Llene las dimensiones del baden: ancho "X", largo "Y" y por último el espesor "Z".El lado corto no tiene considerado el solape del acero, ya que no es necesario.

Para actualizar los precios, actualice solo la columna de p. unit. en los análisis.

112.04% 1,489.73100.00% 186.37100.00% 3,643.50100.00% 1,071.62100.00% 1,297.50100.00% 543.72100.00% 196.23100.00% 590.71101.99% 9,019.38

112.04% 1,489.73100.00% 186.37100.00% 4,043.20100.00% 1,071.62100.00% 1,297.50100.00% 543.72100.00% 196.23100.00% 590.71101.90% 9,419.08

Page 149: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 119

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 1,489.73100.00% 186.37100.00% 6,052.07100.00% 1,071.62100.00% 1,297.50100.00% 543.72100.00% 196.23100.00% 590.71101.57% 11,427.95

112.04% 1,489.73100.00% 186.37100.00% 6,312.37100.00% 1,071.62100.00% 1,297.50100.00% 543.72100.00% 196.23100.00% 590.71101.53% 11,688.25

88.97% 983.77112.04% 2,499.98100.00% 1,782.50100.00% 7,388.33100.00% 1,263.05100.00% 282.75100.00% 159.00100.00% 2,674.50100.00% 3,067.00100.00% 370.80100.03% 3,928.43100.79% 24,400.11

100.94% 20,471.68100.00% 4,360.31100.78% 24,831.99

88.97% 2,175.56112.04% 4,442.50100.01% 20,916.36101.08% 27,534.42

101.08% 27,534.42100.00% 4,360.31100.93% 31,894.73

112.04% 2,575.21112.04% 2,961.67100.00% 936.17100.00% 3,780.44100.00% 646.28100.00% 148.39100.00% 83.44100.00% 1,404.65100.00% 1,610.79100.00% 243.43100.03% 3,928.43103.65% 18,318.90

104.63% 14,390.47100.00% 4,360.31103.56% 18,750.78

112.04% 1,956.21112.04% 3,895.31100.00% 732.03100.00% 3,889.19100.00% 664.87100.00% 125.77100.00% 70.72

Page 150: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 120

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 1,188.55100.00% 1,362.97100.00% 247.14100.03% 3,928.43103.91% 18,061.19

104.99% 14,132.76100.00% 4,360.31103.81% 18,493.07

112.04% 1,272.22112.04% 3,384.03100.00% 582.50100.00% 2,232.71100.00% 381.77100.00% 94.10100.00% 52.92100.00% 1,021.92100.00% 1,318.89100.00% 216.18100.03% 3,928.43103.88% 14,485.67

105.31% 10,557.24100.00% 4,360.31103.76% 14,917.55

112.04% 1,470.57112.04% 1,094.38112.04% 2,532.47100.00% 637.70100.00% 2,530.25100.00% 432.59100.00% 70.57100.00% 39.69100.00% 766.75100.00% 989.56100.00% 185.40100.03% 3,928.43104.19% 14,678.36

104.71% 9,279.36100.00% 4,360.31103.20% 13,639.67

112.04% 1,174.75112.04% 1,621.05112.04% 2,963.38100.00% 720.48100.00% 1,838.89100.00% 314.34100.00% 45.24100.00% 25.44100.00% 564.88100.00% 707.52100.00% 148.32100.00% 4,360.31104.79% 14,484.60

106.17% 8,949.54100.03% 3,928.43104.30% 12,877.97

112.04% 2,937.73112.04% 6,176.41100.00% 1,140.19100.00% 1,429.41100.00% 244.43100.00% 31.67100.00% 17.81100.00% 491.73100.00% 781.24100.00% 123.66100.00% 4,360.31106.19% 17,734.59

108.21% 13,374.28100.03% 3,928.43106.35% 17,302.71

112.04% 3,040.33112.04% 4,442.50100.00% 1,782.50100.00% 5,155.91100.00% 881.53100.00% 282.75100.00% 159.00100.00% 2,674.50

Page 151: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 121

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 3,067.00100.00% 370.80100.00% 5,933.40103.24% 27,790.22

112.04% 3,040.33112.04% 4,442.50100.00% 20,307.39103.24% 27,790.22

106.32% 3,379.75106.32% 4,938.46100.00% 20,307.39101.84% 28,625.60

106.32% 3,379.75106.32% 4,938.46100.00% 20,307.39101.84% 28,625.60

106.32% 2,862.71106.32% 3,292.31100.00% 936.17100.00% 3,780.44100.00% 646.28100.00% 148.39100.00% 83.44100.00% 1,404.65100.00% 1,610.79100.00% 243.43100.00% 5,933.40101.86% 20,942.01

106.32% 2,862.71106.32% 3,292.31100.00% 14,786.99101.86% 20,942.01

112.04% 1,956.21112.04% 3,895.31100.00% 732.03100.00% 3,889.19100.00% 664.87100.00% 125.77100.00% 70.72100.00% 1,188.55100.00% 1,362.97100.00% 247.14100.00% 5,933.40103.51% 20,066.16

112.04% 5,851.52100.00% 1,168.17100.00% 13,482.61103.44% 20,502.30

112.04% 1,956.21112.04% 3,895.31100.00% 14,214.64103.51% 20,066.16

112.04% 5,851.52100.00% 1,168.17100.00% 13,482.61103.44% 20,502.30

106.32% 2,174.60106.32% 4,330.18100.00% 1,106.09100.00% 13,482.61101.95% 21,093.48

106.32% 6,504.78100.00% 1,168.17100.00% 13,482.61101.94% 21,155.56

106.32% 2,174.60106.32% 4,330.18100.00% 1,106.09100.00% 13,482.61101.95% 21,093.48

106.32% 6,504.78100.00% 1,168.17100.00% 13,482.61101.94% 21,155.56

Page 152: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 122

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 1,272.22112.04% 3,384.03100.00% 582.50100.00% 2,232.71100.00% 381.77100.00% 94.10100.00% 52.92100.00% 1,021.92100.00% 1,318.89100.00% 216.18100.00% 5,933.40103.40% 16,490.64

112.04% 4,656.25100.00% 929.55100.00% 11,251.89103.33% 16,837.69

106.32% 1,414.25106.32% 3,761.82100.00% 880.16100.00% 11,251.89101.89% 17,308.12

106.32% 5,176.07100.00% 929.55100.00% 11,251.89101.89% 17,357.51

112.04% 1,470.57112.04% 1,094.38112.04% 2,532.47100.00% 637.70100.00% 2,530.25100.00% 432.59100.00% 70.57100.00% 39.69100.00% 766.75100.00% 989.56100.00% 185.40100.00% 5,933.40103.68% 16,683.33

112.04% 5,097.42100.00% 1,017.62100.00% 10,948.21103.60% 17,063.25

112.04% 1,470.57112.04% 1,094.38112.04% 2,532.47100.00% 11,585.91103.68% 16,683.33

112.04% 5,097.42100.00% 1,017.62100.00% 10,948.21103.60% 17,063.25

106.32% 1,634.75106.32% 1,216.56106.32% 2,815.19100.00% 963.55100.00% 10,948.21102.04% 17,578.26

106.32% 5,666.50100.00% 1,017.62100.00% 10,948.21102.03% 17,632.33

106.32% 1,634.75106.32% 1,216.56106.32% 2,815.19100.00% 963.55100.00% 10,948.21102.04% 17,578.26

106.32% 5,666.50100.00% 1,017.62100.00% 10,948.21102.03% 17,632.33

112.04% 1,174.75112.04% 1,621.05112.04% 2,963.38100.00% 720.48100.00% 1,838.89

Page 153: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 123

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 314.34100.00% 45.24100.00% 25.44100.00% 564.88100.00% 707.52100.00% 148.32100.00% 5,933.40104.32% 16,057.69

112.04% 4,584.43100.00% 1,149.73100.00% 9,578.03103.61% 15,312.19

106.32% 1,305.90106.32% 1,802.02106.32% 3,294.21100.00% 1,088.64100.00% 9,578.03102.37% 17,068.80

106.32% 6,402.13100.00% 1,149.73100.00% 9,578.03102.36% 17,129.89

112.04% 2,937.73112.04% 6,176.41100.00% 1,140.19100.00% 1,429.41100.00% 244.43100.00% 45.24100.00% 25.44100.00% 564.88100.00% 707.52100.00% 148.32100.00% 5,933.40105.67% 19,352.97

112.04% 9,114.14100.00% 1,819.50100.00% 9,098.64105.48% 20,032.28

106.32% 3,265.69106.32% 6,865.94100.00% 1,722.82100.00% 9,098.64103.06% 20,953.09

106.32% 10,131.63100.00% 1,819.50100.00% 9,098.64103.04% 21,049.77

112.04% 1,956.21112.04% 3,895.31100.00% 732.03100.00% 3,889.19100.00% 664.87100.00% 125.77100.00% 70.72100.00% 1,188.55100.00% 1,362.97100.00% 247.14100.00% 6,188.60103.47% 20,321.36

112.04% 5,851.52100.00% 1,168.17100.00% 13,737.81103.39% 20,757.50

106.32% 2,174.60106.32% 4,330.18100.00% 1,106.09100.00% 13,737.81101.93% 21,348.68

106.32% 6,504.78100.00% 1,168.17100.00% 13,737.81101.92% 21,410.76

112.04% 1,272.22112.04% 3,384.03100.00% 582.50100.00% 2,232.71

Page 154: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 124

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 381.77100.00% 94.10100.00% 52.92100.00% 1,021.92100.00% 1,318.89100.00% 216.18100.00% 6,188.60103.35% 16,745.84

112.04% 4,656.25100.00% 929.55100.00% 11,507.09103.28% 17,092.89

106.32% 1,414.25106.32% 3,761.82100.00% 880.16100.00% 11,507.09101.86% 17,563.32

106.32% 5,176.07100.00% 929.55100.00% 11,507.09101.86% 17,612.71

112.04% 1,470.57112.04% 1,094.38112.04% 2,532.47100.00% 637.70100.00% 2,530.25100.00% 432.59100.00% 70.57100.00% 39.69100.00% 766.75100.00% 989.56100.00% 185.40100.00% 6,188.60103.62% 16,938.53

112.04% 5,097.42100.00% 1,017.62100.00% 11,203.41103.54% 17,318.45

Page 155: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 125

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 1,470.57112.04% 1,094.38112.04% 2,532.47100.00% 11,841.11103.62% 16,938.53

112.04% 5,097.42100.00% 1,017.62100.00% 11,203.41103.54% 17,318.45

106.32% 1,634.75106.32% 1,216.56106.32% 2,815.19100.00% 963.55100.00% 11,203.41102.01% 17,833.46

106.32% 5,666.50100.00% 1,017.62100.00% 11,203.41102.00% 17,887.53

106.32% 1,634.75106.32% 1,216.56106.32% 2,815.19100.00% 963.55100.00% 11,203.41102.01% 17,833.46

106.32% 5,666.50100.00% 1,017.62100.00% 11,203.41102.00% 17,887.53

112.04% 1,174.75112.04% 1,621.05112.04% 2,963.38100.00% 720.48100.00% 1,838.89100.00% 314.34100.00% 45.24100.00% 25.44100.00% 564.88100.00% 707.52100.00% 148.32100.00% 6,188.60104.25% 16,312.89

112.04% 4,584.43100.00% 1,149.73100.00% 9,833.23103.55% 15,567.39

106.32% 1,305.90106.32% 1,802.02106.32% 3,294.21100.00% 1,088.64100.00% 9,833.23102.34% 17,324.00

106.32% 6,402.13100.00% 1,149.73100.00% 9,833.23102.33% 17,385.09

112.04% 2,937.73112.04% 6,176.41100.00% 1,140.19100.00% 1,429.41100.00% 244.43100.00% 31.67100.00% 17.81100.00% 491.73100.00% 781.24100.00% 123.66100.00% 6,188.60105.61% 19,562.88

112.04% 9,114.14100.00% 1,819.50100.00% 9,308.55105.42% 20,242.19

106.32% 3,265.69106.32% 6,865.94100.00% 1,722.82

Page 156: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 126

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 9,308.55103.03% 21,163.00

106.32% 10,131.63100.00% 1,819.50100.00% 9,308.55103.01% 21,259.68

112.04% 1,956.21112.04% 3,895.31100.00% 732.03100.00% 3,889.19100.00% 664.87100.00% 125.77100.00% 70.72100.00% 1,188.55100.00% 1,362.97100.00% 247.14100.00% 6,443.80103.42% 20,576.56

112.04% 5,851.52100.00% 1,168.17100.00% 13,993.01103.35% 21,012.70

106.32% 2,174.60106.32% 4,330.18100.00% 1,106.09100.00% 13,993.01101.90% 21,603.88

106.32% 6,504.78100.00% 1,168.17100.00% 13,993.01101.90% 21,665.96

112.04% 1,272.22112.04% 3,384.03100.00% 582.50100.00% 2,232.71100.00% 381.77100.00% 94.10100.00% 52.92100.00% 1,021.92100.00% 1,318.89100.00% 216.18100.00% 6,443.80103.30% 17,001.04

112.04% 4,656.25100.00% 929.55100.00% 11,762.29103.23% 17,348.09

106.32% 1,414.25106.32% 3,761.82100.00% 880.16100.00% 11,762.29101.84% 17,818.52

106.32% 5,176.07100.00% 929.55100.00% 11,762.29101.83% 17,867.91

112.04% 1,470.57112.04% 1,094.38112.04% 2,532.47100.00% 637.70100.00% 2,530.25100.00% 432.59100.00% 70.57100.00% 39.69100.00% 766.75100.00% 989.56100.00% 185.40100.00% 6,443.80103.57% 17,193.73

112.04% 5,097.42100.00% 1,017.62100.00% 11,458.61103.49% 17,573.65

112.04% 1,470.57112.04% 1,094.38112.04% 2,532.47

Page 157: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 127

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 12,096.31103.57% 17,193.73

112.04% 5,097.42100.00% 1,017.62100.00% 11,458.61103.49% 17,573.65

Page 158: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 128

ANALISIS DE COSTOSINDICE ABR 2010

106.32% 1,634.75106.32% 1,216.56106.32% 2,815.19100.00% 963.55100.00% 11,458.61101.98% 18,088.66

106.32% 5,666.50100.00% 1,017.62100.00% 11,458.61101.98% 18,142.73

106.32% 1,634.75106.32% 1,216.56106.32% 2,815.19100.00% 963.55100.00% 11,458.61101.98% 18,088.66

106.32% 5,666.50100.00% 1,017.62100.00% 11,458.61101.98% 18,142.73

112.04% 1,174.75112.04% 1,621.05112.04% 2,963.38100.00% 720.48100.00% 1,838.89100.00% 314.34100.00% 45.24100.00% 25.44100.00% 564.88100.00% 707.52100.00% 148.32100.00% 6,443.80104.19% 16,568.09

112.04% 4,584.43100.00% 1,149.73100.00% 10,088.43103.49% 15,822.59

106.32% 1,305.90106.32% 1,802.02106.32% 3,294.21100.00% 1,088.64100.00% 10,088.43102.30% 17,579.20

106.32% 6,402.13100.00% 1,149.73100.00% 10,088.43102.30% 17,640.29

112.04% 2,937.73112.04% 6,176.41100.00% 1,140.19100.00% 1,429.41100.00% 244.43100.00% 31.67100.00% 17.81100.00% 491.73100.00% 781.24100.00% 123.66100.00% 6,443.80105.54% 19,818.08

112.04% 9,114.14100.00% 1,819.50100.00% 9,563.75105.35% 20,497.39

106.32% 3,265.69106.32% 6,865.94100.00% 1,722.82100.00% 9,563.75102.99% 21,418.20

106.32% 10,131.63100.00% 1,819.50100.00% 9,563.75102.98% 21,514.88

Page 159: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 129

ANALISIS DE COSTOSINDICE ABR 2010

106.32% 3,236.61106.32% 10,815.19100.00% 1,008.49100.00% 2,137.59100.00% 292.27100.00% 160.15100.00% 90.06100.00% 4,237.06100.00% 2,239.46100.00% 247.14100.03% 3,928.43103.13% 28,392.45

106.32% 3,236.61106.32% 10,815.19100.00% 1,008.49100.00% 2,137.59100.00% 292.27100.00% 160.15100.00% 90.06100.00% 4,237.06100.00% 2,239.46100.00% 247.14100.00% 4,360.31103.08% 28,824.33

88.97% 953.18112.04% 3,247.23100.00% 2,376.43100.00% 2,841.13100.00% 485.64100.00% 376.85100.00% 211.92100.00% 2,947.71100.00% 247.14100.03% 3,928.43101.63% 17,615.66

88.97% 953.18112.04% 3,247.23100.00% 2,376.43100.00% 2,841.13100.00% 485.64100.00% 376.85100.00% 211.92100.00% 2,947.71100.00% 247.14100.00% 4,360.31101.58% 18,047.54

112.04% 2,946.28112.04% 3,247.23100.00% 2,376.43100.00% 2,841.13100.00% 485.64100.00% 376.85100.00% 211.92100.00% 2,947.71100.00% 247.14100.03% 3,928.43103.81% 19,608.76

112.04% 2,946.28112.04% 3,247.23100.00% 2,376.43100.00% 2,841.13100.00% 485.64100.00% 376.85100.00% 211.92100.00% 2,947.71100.00% 247.14100.00% 4,360.31103.72% 20,040.64

88.97% 817.36112.04% 2,435.00100.00% 1,782.50100.00% 2,736.44100.00% 467.79100.00% 282.75100.00% 159.00100.00% 2,211.00100.00% 185.40100.03% 3,928.43101.36% 15,005.67

Page 160: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 130

ANALISIS DE COSTOSINDICE ABR 2010

88.97% 817.36112.04% 2,435.00100.00% 1,782.50100.00% 2,736.44100.00% 467.79100.00% 282.75100.00% 159.00100.00% 2,211.00100.00% 185.40100.00% 4,360.31101.32% 15,437.55

88.97% 1,221.15112.04% 2,435.00112.04% 4,435.66100.00% 3,565.00100.00% 7,023.22100.00% 1,200.83100.00% 565.50100.00% 318.00100.00% 8,844.00100.00% 428.00100.03% 3,928.43102.04% 33,964.79

88.97% 1,221.15112.04% 2,435.00112.04% 4,435.66100.00% 3,565.00100.00% 7,023.22100.00% 1,200.83100.00% 565.50100.00% 318.00100.00% 8,844.00100.00% 428.00100.00% 4,360.31102.01% 34,396.67

88.97% 953.18112.04% 1,624.47112.04% 4,435.66100.00% 2,376.43100.00% 4,904.77100.00% 838.65100.00% 376.85100.00% 211.92100.00% 5,895.41100.00% 285.26100.03% 3,928.43102.42% 25,831.03

88.97% 953.18112.04% 1,624.47112.04% 4,435.66100.00% 2,376.43100.00% 4,904.77100.00% 838.65100.00% 376.85100.00% 211.92100.00% 5,895.41100.00% 285.26100.00% 4,360.31102.38% 26,262.91

112.04% 2,946.28112.04% 1,624.47112.04% 4,435.66100.00% 2,376.43100.00% 4,904.77100.00% 838.65100.00% 376.85100.00% 211.92100.00% 5,895.41100.00% 285.26100.03% 3,928.43103.90% 27,824.13

112.04% 2,946.28112.04% 1,624.47112.04% 4,435.66100.00% 2,376.43100.00% 4,904.77100.00% 838.65100.00% 376.85

Page 161: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 131

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 211.92100.00% 5,895.41100.00% 285.26100.00% 4,360.31103.84% 28,256.01

112.04% 3,537.93112.04% 3,325.89100.00% 1,782.50100.00% 3,845.98100.00% 657.43100.00% 282.75100.00% 159.00100.00% 4,422.00100.00% 214.00100.03% 3,928.43103.74% 22,155.91

112.04% 3,537.93112.04% 3,325.89100.00% 1,782.50100.00% 3,845.98100.00% 657.43100.00% 282.75100.00% 159.00100.00% 4,422.00100.00% 214.00100.00% 4,360.31103.66% 22,587.79

88.97% 1,221.15112.04% 2,435.00112.04% 4,435.66100.00% 3,565.00100.00% 7,023.22100.00% 1,200.83100.00% 565.50100.00% 318.00100.00% 8,844.00100.00% 428.00100.00% 5,933.40101.93% 35,969.76

88.97% 953.18112.04% 1,624.47112.04% 4,435.66100.00% 2,376.43100.00% 4,904.77100.00% 838.65100.00% 376.85100.00% 211.92100.00% 5,895.41100.00% 285.26100.00% 5,933.40102.24% 27,836.00

112.04% 3,537.93112.04% 3,325.89100.00% 1,782.50100.00% 3,845.98100.00% 657.43100.00% 282.75100.00% 159.00100.00% 4,422.00100.00% 214.00100.00% 5,933.40103.42% 24,160.88

112.04% 3,110.44100.00% 389.12100.00% 38.91100.00% 2,026.81100.00% 346.56100.00% 36.19100.00% 38.16100.00% 1,069.80100.00% 228.20100.05% 4,135.44103.30% 11,419.63

112.04% 3,110.44100.03% 8,309.19103.30% 11,419.63

106.32% 3,457.68

Page 162: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 132

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 587.96100.03% 7,920.07101.85% 11,965.71

106.32% 3,457.68100.00% 587.96100.03% 7,920.07101.85% 11,965.71

112.04% 2,558.12100.00% 320.02100.00% 32.00100.00% 1,651.55100.00% 282.36100.00% 30.31100.00% 31.80100.00% 893.28100.00% 190.55100.05% 4,135.44103.06% 10,125.43

112.04% 2,558.12100.03% 7,567.31103.06% 10,125.43

106.32% 2,843.70100.00% 483.55100.03% 7,247.29101.72% 10,574.54

106.32% 2,843.70100.00% 483.55100.03% 7,247.29101.72% 10,574.54

112.04% 3,110.44100.00% 389.12100.00% 38.91100.00% 2,026.81100.00% 346.56100.00% 36.19100.00% 38.16100.00% 1,069.80100.00% 228.20100.00% 5,933.40102.83% 13,217.59

112.04% 3,110.44100.00% 10,107.15102.83% 13,217.59

106.32% 3,457.68100.00% 587.96100.00% 9,718.03101.59% 13,763.67

106.32% 3,457.68100.00% 587.96100.00% 9,718.03101.59% 13,763.67

112.04% 2,558.12100.00% 320.02100.00% 32.00100.00% 1,651.55100.00% 282.36100.00% 30.31100.00% 31.80100.00% 893.28100.00% 190.55100.00% 5,933.40102.58% 11,923.39

112.04% 2,558.12100.00% 9,365.27102.58% 11,923.39

106.32% 2,843.70100.00% 483.55100.00% 9,045.25101.45% 12,372.50

106.32% 2,843.70100.00% 483.55100.00% 9,045.25101.45% 12,372.50

Page 163: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 133

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 3,104.62100.00% 388.39100.00% 644.00100.00% 1,343.57100.00% 459.36100.00% 301.75100.00% 169.68100.00% 1,711.69100.00% 2,149.15100.00% 247.19100.00% 5,933.40102.27% 16,452.80

112.04% 3,104.62100.00% 13,348.18102.27% 16,452.80

106.32% 3,451.22100.00% 586.86100.00% 12,959.79101.28% 16,997.87

106.32% 3,451.22100.00% 586.86100.00% 12,959.79101.28% 16,997.87

112.04% 3,104.62100.00% 388.39100.00% 644.00100.00% 1,343.57100.00% 459.36100.00% 301.75100.00% 169.68100.00% 1,711.69100.00% 2,149.15100.00% 247.19100.00% 6,188.60102.24% 16,708.00

112.04% 3,104.62100.00% 13,603.38102.24% 16,708.00

106.32% 3,451.22100.00% 586.86100.00% 13,214.99101.26% 17,253.07

106.32% 3,451.22100.00% 586.86100.00% 13,214.99101.26% 17,253.07

112.04% 3,104.62100.00% 388.39100.00% 644.00100.00% 1,343.57100.00% 459.36100.00% 301.75100.00% 169.68100.00% 1,711.69100.00% 2,149.15100.00% 247.19100.00% 6,443.80102.20% 16,963.20

112.04% 3,104.62100.00% 13,858.58102.20% 16,963.20

106.32% 3,451.22100.00% 586.86100.00% 13,470.19101.25% 17,508.27

106.32% 3,451.22100.00% 586.86100.00% 13,470.19101.25% 17,508.27

112.04% 2,331.37100.00% 291.66100.00% 483.00100.00% 1,008.91100.00% 345.08

Page 164: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 134

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 226.20100.00% 127.20100.00% 1,283.80100.00% 1,611.90100.00% 185.40100.00% 5,933.40102.03% 13,827.92

112.04% 2,331.37100.00% 11,496.55102.03% 13,827.92

106.32% 2,591.65100.00% 440.69100.00% 11,204.89101.15% 14,237.23

106.32% 2,591.65100.00% 440.69100.00% 11,204.89101.15% 14,237.23

112.04% 2,331.37100.00% 291.66100.00% 483.00100.00% 1,008.91100.00% 345.08100.00% 226.20100.00% 127.20100.00% 1,283.80100.00% 1,611.90100.00% 185.40100.00% 6,188.60101.99% 14,083.12

112.04% 2,331.37100.00% 11,751.75101.99% 14,083.12

106.32% 2,591.65100.00% 440.69100.00% 11,460.09101.13% 14,492.43

106.32% 2,591.65100.00% 440.69100.00% 11,460.09101.13% 14,492.43

112.04% 8,283.78100.00% 1,036.31100.00% 483.00100.00% 1,008.91100.00% 345.08100.00% 226.20100.00% 127.20100.00% 1,283.80100.00% 1,611.90100.00% 185.40100.00% 6,188.60104.80% 20,780.18

112.04% 8,283.78100.00% 12,496.40104.80% 20,780.18

106.32% 9,208.57100.00% 1,565.86100.00% 11,460.09102.62% 22,234.52

106.32% 9,208.57100.00% 1,565.86100.00% 11,460.09102.62% 22,234.52

112.04% 4,141.89100.00% 518.16100.00% 483.00100.00% 1,008.91100.00% 345.08100.00% 226.20100.00% 127.20100.00% 1,283.80100.00% 1,611.90100.00% 185.40100.00% 6,188.60103.09% 16,120.14

Page 165: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 135

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 4,141.89100.00% 11,978.25103.09% 16,120.14

106.32% 4,604.29100.00% 782.93100.00% 11,460.09101.73% 16,847.31

106.32% 4,604.29100.00% 782.93100.00% 11,460.09101.73% 16,847.31

112.04% 8,283.78100.00% 1,036.31100.00% 483.00100.00% 1,008.91100.00% 345.08100.00% 226.20100.00% 127.20100.00% 1,283.80100.00% 1,611.90100.00% 185.40100.00% 6,443.80104.74% 21,035.38

Page 166: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 136

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 8,283.78100.00% 12,751.60104.74% 21,035.38

106.32% 9,208.57100.00% 1,565.86100.00% 11,715.29102.59% 22,489.72

106.32% 9,208.57100.00% 1,565.86100.00% 11,715.29102.59% 22,489.72

112.04% 4,141.89100.00% 518.16100.00% 483.00100.00% 1,008.91100.00% 345.08100.00% 226.20100.00% 127.20100.00% 1,283.80100.00% 1,611.90100.00% 185.40100.00% 6,443.80103.05% 16,375.34

112.04% 4,141.89100.00% 12,233.45103.05% 16,375.34

106.32% 4,604.29100.00% 782.93100.00% 11,715.29101.70% 17,102.51

106.32% 4,604.29100.00% 782.93100.00% 11,715.29101.70% 17,102.51

112.04% 1,949.37112.04% 2,770.15100.00% 6,375.00100.00% 1,224.38100.00% 418.70100.00% 41.62100.00% 69.96100.00% 3,217.84100.00% 209.26100.05% 4,135.44102.79% 20,411.72

112.04% 1,949.37112.04% 2,770.15100.01% 15,692.20102.79% 20,411.72

106.32% 2,166.99106.32% 3,079.41100.01% 15,692.20101.59% 20,938.60

106.32% 2,166.99106.32% 3,079.41100.01% 15,692.20101.59% 20,938.60

103.49% 16,276.28100.00% 4,360.31102.75% 20,636.59

112.04% 2,770.15101.74% 13,506.13100.00% 4,360.31102.75% 20,636.59

106.32% 2,166.99106.32% 3,079.41100.00% 11,556.76100.00% 4,360.31101.57% 21,163.47

106.32% 3,079.41

Page 167: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 137

ANALISIS DE COSTOSINDICE ABR 2010

101.00% 13,723.75100.00% 4,360.31101.57% 21,163.47

Page 168: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 138

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 1,949.37112.04% 2,770.15100.00% 6,375.00100.00% 1,224.38100.00% 418.70100.00% 41.62100.00% 69.96100.00% 3,217.84100.00% 209.26100.00% 5,933.40102.56% 22,209.68

112.04% 1,949.37112.04% 2,770.15100.00% 17,490.16102.56% 22,209.68

106.32% 2,166.99106.32% 3,079.41100.00% 17,490.16101.46% 22,736.56

106.32% 2,166.99106.32% 3,079.41100.00% 17,490.16101.46% 22,736.56

112.04% 1,949.37112.04% 2,770.15100.00% 6,375.00100.00% 1,224.38100.00% 418.70100.00% 41.62100.00% 69.96100.00% 3,217.84100.00% 209.26100.00% 6,188.60102.53% 22,464.88

112.04% 1,949.37112.04% 2,770.15100.00% 17,745.36102.53% 22,464.88

106.32% 2,166.99106.32% 3,079.41100.00% 17,745.36101.44% 22,991.76

106.32% 2,166.99106.32% 3,079.41100.00% 17,745.36101.44% 22,991.76

112.04% 1,949.37112.04% 2,770.15100.00% 6,375.00100.00% 1,224.38100.00% 418.70100.00% 41.62100.00% 69.96100.00% 3,217.84100.00% 209.26100.00% 6,443.80102.50% 22,720.08

112.04% 1,949.37112.04% 2,770.15100.00% 18,000.56102.50% 22,720.08

106.32% 2,166.99106.32% 3,079.41100.00% 18,000.56101.43% 23,246.96

106.32% 2,166.99106.32% 3,079.41100.00% 18,000.56101.43% 23,246.96

112.04% 2,568.37112.04% 3,806.39100.00% 797.49

Page 169: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 139

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 2,443.25100.00% 417.71100.00% 141.60100.00% 79.63100.00% 1,854.50100.00% 642.00100.00% 267.50100.05% 4,135.44104.49% 17,153.88

106.32% 2,855.11106.32% 4,231.34100.00% 1,205.00100.02% 9,981.63102.46% 18,273.08

112.04% 1,653.54112.04% 3,247.23100.00% 613.09100.00% 1,783.79100.00% 304.92100.00% 90.48100.00% 50.88100.00% 1,483.60100.00% 513.60100.00% 214.00100.05% 4,135.44104.20% 14,090.57

106.32% 1,838.14106.32% 3,609.75100.00% 926.38100.03% 8,576.71102.32% 14,950.98

112.04% 1,326.94112.04% 4,103.93100.00% 679.41100.00% 1,392.58100.00% 237.98100.00% 62.88100.00% 35.36100.00% 1,237.32100.00% 428.34100.00% 178.48100.05% 4,135.44104.75% 13,818.66

106.32% 1,475.08106.32% 4,562.09100.00% 1,026.58100.03% 7,708.38102.60% 14,772.13

112.04% 1,285.90112.04% 277.02112.04% 2,888.14100.00% 522.18100.00% 1,137.67100.00% 194.60100.00% 35.29100.00% 19.84100.00% 928.73100.00% 321.51100.00% 133.96100.05% 4,135.44104.53% 11,880.28

112.04% 1,285.90112.04% 277.02103.39% 10,317.36104.53% 11,880.28

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 789.00100.03% 6,907.04102.49% 12,644.00

112.04% 2,568.37112.04% 3,806.39100.00% 797.49100.00% 2,443.25100.00% 417.71100.00% 141.60100.00% 79.63100.00% 1,854.50

Page 170: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 140

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 642.00100.00% 267.50100.00% 5,933.40104.05% 18,951.84

112.04% 6,374.76100.00% 1,272.63

Page 171: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 141

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 11,779.59103.95% 19,426.98

106.32% 2,855.11106.32% 4,231.34100.00% 1,205.00100.00% 11,779.59102.23% 20,071.04

106.32% 2,855.11106.32% 4,231.34100.00% 1,272.63100.00% 11,779.59102.23% 20,138.67

112.04% 1,653.54112.04% 3,247.23100.00% 613.09100.00% 1,783.79100.00% 304.92100.00% 90.48100.00% 50.88100.00% 1,483.60100.00% 513.60100.00% 214.00100.00% 5,933.40103.71% 15,888.53

112.04% 4,900.77100.00% 978.37100.00% 10,374.67103.63% 16,253.81

106.32% 1,838.14106.32% 3,609.75100.00% 926.38100.00% 10,374.67102.06% 16,748.94

106.32% 1,838.14106.32% 3,609.75100.00% 978.37100.00% 10,374.67102.05% 16,800.93

112.04% 1,326.94112.04% 4,103.93100.00% 679.41100.00% 1,392.58100.00% 237.98100.00% 62.88100.00% 35.36100.00% 1,237.32100.00% 428.34100.00% 178.48100.00% 5,933.40104.19% 15,616.62

112.04% 5,430.87100.00% 1,084.19100.00% 9,506.34104.08% 16,021.40

106.32% 1,475.08106.32% 4,562.09100.00% 1,026.58100.00% 9,506.34102.30% 16,570.09

106.32% 1,475.08106.32% 4,562.09100.00% 1,084.19100.00% 9,506.34102.30% 16,627.70

112.04% 1,285.90112.04% 277.02112.04% 2,888.14100.00% 522.18100.00% 1,137.67100.00% 194.60100.00% 35.29100.00% 19.84100.00% 928.73100.00% 321.51100.00% 133.96100.00% 5,933.40103.92% 13,678.24

Page 172: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 142

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 4,451.06100.00% 833.28

Page 173: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 143

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 8,705.00103.83% 13,989.34

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 789.00100.00% 8,705.00102.17% 14,441.96

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 833.28100.00% 8,705.00102.16% 14,486.24

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 789.00100.00% 8,705.00102.17% 14,441.96

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 833.28100.00% 8,705.00102.16% 14,486.24

112.04% 2,568.37112.04% 3,806.39100.00% 797.49100.00% 2,443.25100.00% 417.71100.00% 141.60100.00% 79.63100.00% 1,854.50100.00% 642.00100.00% 267.50100.00% 6,188.60104.00% 19,207.04

112.04% 6,374.76100.00% 1,272.63100.00% 12,034.79103.90% 19,682.18

106.32% 2,855.11106.32% 4,231.34100.00% 1,205.00100.00% 12,034.79102.20% 20,326.24

106.32% 2,855.11106.32% 4,231.34100.00% 1,272.63100.00% 12,034.79102.20% 20,393.87

112.04% 1,653.54112.04% 3,247.23100.00% 613.09100.00% 1,783.79100.00% 304.92100.00% 90.48100.00% 50.88100.00% 1,483.60100.00% 513.60100.00% 214.00100.00% 6,188.60103.66% 16,143.73

112.04% 4,900.77100.00% 978.37100.00% 10,629.87103.57% 16,509.01

106.32% 1,838.14106.32% 3,609.75100.00% 926.38100.00% 10,629.87102.03% 17,004.14

106.32% 1,838.14106.32% 3,609.75100.00% 978.37

Page 174: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 144

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 10,629.87102.02% 17,056.13

112.04% 1,326.94112.04% 4,103.93100.00% 679.41100.00% 1,392.58100.00% 237.98100.00% 62.88100.00% 35.36100.00% 1,237.32100.00% 428.34100.00% 178.48100.00% 6,188.60104.12% 15,871.82

112.04% 5,430.87100.00% 1,084.19100.00% 9,761.54104.02% 16,276.60

106.32% 1,475.08106.32% 4,562.09100.00% 1,026.58100.00% 9,761.54102.27% 16,825.29

106.32% 1,475.08106.32% 4,562.09100.00% 1,084.19100.00% 9,761.54102.26% 16,882.90

112.04% 1,285.90112.04% 277.02112.04% 2,888.14100.00% 522.18100.00% 1,137.67100.00% 194.60100.00% 35.29100.00% 19.84100.00% 928.73100.00% 321.51100.00% 133.96100.00% 6,188.60103.85% 13,933.44

112.04% 4,451.06100.00% 833.28100.00% 8,960.20103.76% 14,244.54

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 789.00100.00% 8,960.20102.13% 14,697.16

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 833.28100.00% 8,960.20102.12% 14,741.44

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 789.00100.00% 8,960.20102.13% 14,697.16

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 833.28100.00% 8,960.20102.12% 14,741.44

112.04% 2,568.37112.04% 3,806.39100.00% 797.49100.00% 2,443.25100.00% 417.71100.00% 141.60100.00% 79.63100.00% 1,854.50

Page 175: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 145

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 642.00100.00% 267.50100.00% 6,443.80103.94% 19,462.24

112.04% 6,374.76100.00% 1,272.63

Page 176: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 146

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 12,289.99103.85% 19,937.38

106.32% 2,855.11106.32% 4,231.34100.00% 1,205.00100.00% 12,289.99102.18% 20,581.44

106.32% 2,855.11106.32% 4,231.34100.00% 1,272.63100.00% 12,289.99102.17% 20,649.07

112.04% 1,653.54112.04% 3,247.23100.00% 613.09100.00% 1,783.79100.00% 304.92100.00% 90.48100.00% 50.88100.00% 1,483.60100.00% 513.60100.00% 214.00100.00% 6,443.80103.60% 16,398.93

112.04% 4,900.77100.00% 978.37100.00% 10,885.07103.52% 16,764.21

106.32% 1,838.14106.32% 3,609.75100.00% 926.38100.00% 10,885.07102.00% 17,259.34

106.32% 1,838.14106.32% 3,609.75106.32% 1,429.45100.00% 10,885.07102.45% 17,762.41

112.04% 1,326.94112.04% 4,103.93100.00% 679.41100.00% 1,392.58100.00% 237.98100.00% 62.88100.00% 35.36100.00% 1,237.32100.00% 428.34100.00% 178.48100.00% 6,443.80104.06% 16,127.02

112.04% 5,430.87100.00% 1,084.19100.00% 10,016.74103.96% 16,531.80

106.32% 1,475.08106.32% 4,562.09100.00% 1,026.58100.00% 10,016.74102.24% 17,080.49

106.32% 1,475.08106.32% 4,562.09100.00% 1,084.19100.00% 10,016.74102.23% 17,138.10

112.04% 1,285.90112.04% 277.02112.04% 2,888.14100.00% 522.18100.00% 1,137.67100.00% 194.60100.00% 35.29100.00% 19.84100.00% 928.73100.00% 321.51100.00% 133.96100.00% 6,443.80103.78% 14,188.64

Page 177: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 147

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 4,451.06100.00% 833.28

Page 178: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 148

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 9,215.40103.70% 14,499.74

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 789.00100.00% 9,215.40102.09% 14,952.36

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 833.28100.00% 9,215.40102.09% 14,996.64

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 789.00100.00% 9,215.40102.09% 14,952.36

106.32% 1,429.45106.32% 307.94106.32% 3,210.57100.00% 833.28100.00% 9,215.40102.09% 14,996.64

88.97% 953.18112.04% 3,247.23100.00% 2,376.43100.00% 2,841.13100.00% 485.64100.00% 376.85100.00% 211.92100.00% 3,565.64100.00% 285.26100.03% 3,928.43101.57% 18,271.71

88.97% 953.18112.04% 3,247.23100.00% 2,376.43100.00% 2,841.13100.00% 485.64100.00% 376.85100.00% 211.92100.00% 3,565.64100.00% 285.26100.00% 4,360.31101.53% 18,703.59

112.04% 4,755.43100.00% 1,782.50100.00% 2,841.13100.00% 485.64100.00% 282.75100.00% 159.00100.00% 2,674.50100.00% 214.00100.03% 3,928.43103.35% 17,123.38

112.04% 4,755.43100.00% 1,782.50100.00% 2,841.13100.00% 485.64100.00% 282.75100.00% 159.00100.00% 2,674.50100.00% 214.00100.00% 4,360.31103.26% 17,555.26

112.04% 3,175.41100.00% 397.25100.00% 39.72100.00% 3,083.86100.00% 527.28

Page 179: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 149

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 282.75100.00% 159.00100.00% 3,709.00100.00% 228.20100.05% 4,135.44102.44% 15,737.91

112.04% 3,175.41100.02% 12,562.50102.44% 15,737.91

106.32% 3,529.92100.00% 600.24100.02% 12,165.25101.38% 16,295.41

106.32% 3,529.92100.00% 600.24100.02% 12,165.25101.38% 16,295.41

112.04% 2,647.03100.00% 331.15100.00% 33.11100.00% 2,627.98100.00% 449.19100.00% 235.70100.00% 132.54100.00% 3,090.34100.00% 190.14100.05% 4,135.44102.31% 13,872.62

112.04% 2,647.03100.02% 11,225.59102.31% 13,872.62

106.32% 2,942.55100.00% 500.36100.02% 10,894.44101.31% 14,337.35

106.32% 2,942.55100.00% 500.36100.02% 10,894.44101.31% 14,337.35

112.04% 3,175.41100.00% 397.25100.00% 39.72100.00% 3,083.86100.00% 527.28100.00% 282.75100.00% 159.00100.00% 3,709.00100.00% 228.20100.00% 5,933.40102.18% 17,535.87

112.04% 3,175.41100.00% 14,360.46102.18% 17,535.87

106.32% 3,529.92100.00% 600.24100.00% 13,963.21101.23% 18,093.37

106.32% 3,529.92100.00% 600.24100.00% 13,963.21101.23% 18,093.37

112.04% 2,647.03100.00% 331.15100.00% 33.11100.00% 2,627.98100.00% 449.19100.00% 235.70100.00% 132.54100.00% 3,090.34100.00% 190.14100.00% 5,933.40102.03% 15,670.58

112.04% 2,647.03100.00% 13,023.55102.03% 15,670.58

Page 180: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 150

ANALISIS DE COSTOSINDICE ABR 2010

106.32% 2,942.55100.00% 500.36100.00% 12,692.40101.15% 16,135.31

106.32% 2,942.55100.00% 500.36100.00% 12,692.40101.15% 16,135.31

112.04% 2,221.25112.04% 748.97100.00% 371.58100.03% 3,234.13105.46% 6,575.93

112.04% 2,221.25112.04% 748.97100.00% 371.58100.03% 3,234.13105.46% 6,575.93

106.32% 2,469.23106.32% 832.58100.00% 561.45100.03% 3,234.13102.96% 7,097.39

106.32% 2,469.23106.32% 832.58100.00% 561.45100.03% 3,234.13102.96% 7,097.39

112.04% 1,665.51112.04% 644.66100.00% 289.01100.03% 3,234.13104.79% 5,833.31

112.04% 1,665.51112.04% 644.66100.00% 289.01100.03% 3,234.13104.79% 5,833.31

106.32% 1,851.45106.32% 716.63100.00% 436.68100.03% 3,234.13102.62% 6,238.89

106.32% 1,851.45106.32% 716.63100.00% 436.68100.03% 3,234.13102.62% 6,238.89

112.04% 2,221.25112.04% 748.97100.00% 371.58100.00% 5,614.40103.99% 8,956.20

112.04% 2,221.25112.04% 748.97100.00% 371.58100.00% 5,614.40103.99% 8,956.20

106.32% 2,469.23106.32% 832.58100.00% 561.45

Page 181: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 151

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 5,742.00102.17% 9,605.26

106.32% 2,469.23106.32% 832.58100.00% 561.45100.00% 5,742.00102.17% 9,605.26

112.04% 1,665.51112.04% 644.66100.00% 289.01100.00% 5,614.40103.39% 8,213.58

112.04% 1,665.51112.04% 644.66100.00% 289.01100.00% 5,614.40103.39% 8,213.58

106.32% 1,851.45106.32% 716.63100.00% 436.68100.00% 5,742.00101.86% 8,746.76

106.32% 1,851.45106.32% 716.63100.00% 436.68100.00% 5,742.00101.86% 8,746.76

112.04% 2,221.25112.04% 748.97100.00% 371.58100.00% 5,933.40103.86% 9,275.20

112.04% 2,221.25112.04% 748.97100.00% 371.58100.00% 5,933.40103.86% 9,275.20

106.32% 2,469.23106.32% 832.58100.00% 561.45100.00% 5,933.40102.13% 9,796.66

106.32% 2,469.23106.32% 832.58100.00% 561.45100.00% 5,933.40102.13% 9,796.66

112.04% 1,665.51112.04% 644.66100.00% 289.01100.00% 5,933.40103.26% 8,532.58

112.04% 1,665.51112.04% 644.66100.00% 289.01100.00% 5,933.40103.26% 8,532.58

106.32% 1,851.45106.32% 716.63100.00% 436.68100.00% 5,933.40101.82% 8,938.16

Page 182: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 152

ANALISIS DE COSTOSINDICE ABR 2010

106.32% 1,851.45106.32% 716.63100.00% 436.68100.00% 5,933.40101.82% 8,938.16

112.04% 2,221.25112.04% 748.97100.00% 371.58100.00% 6,188.60103.75% 9,530.40

112.04% 2,221.25112.04% 748.97100.00% 371.58100.00% 6,188.60103.75% 9,530.40

106.32% 2,469.23106.32% 832.58100.00% 561.45100.00% 6,188.60102.08% 10,051.86

106.32% 2,469.23106.32% 832.58100.00% 561.45100.00% 6,188.60102.08% 10,051.86

112.04% 1,665.51112.04% 644.66100.00% 289.01100.00% 6,188.60103.17% 8,787.78

112.04% 1,665.51112.04% 644.66100.00% 289.01100.00% 6,188.60103.17% 8,787.78

106.32% 1,851.45106.32% 716.63100.00% 436.68100.00% 6,188.60101.77% 9,193.36

106.32% 1,851.45106.32% 716.63100.00% 436.68100.00% 6,188.60101.77% 9,193.36

112.04% 2,221.25112.04% 748.97100.00% 371.58100.00% 6,443.80103.66% 9,785.60

112.04% 2,221.25112.04% 748.97100.00% 371.58100.00% 6,443.80103.66% 9,785.60

106.32% 2,469.23106.32% 832.58100.00% 561.45100.00% 6,443.80102.03% 10,307.06

106.32% 2,469.23106.32% 832.58100.00% 561.45100.00% 6,443.80

Page 183: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 153

ANALISIS DE COSTOSINDICE ABR 2010

102.03% 10,307.06

112.04% 1,665.51112.04% 644.66100.00% 289.01100.00% 6,443.80103.08% 9,042.98

112.04% 1,665.51112.04% 644.66100.00% 289.01100.00% 6,443.80103.08% 9,042.98

106.32% 1,851.45106.32% 716.63100.00% 436.68100.00% 6,443.80101.72% 9,448.56

106.32% 1,851.45106.32% 716.63100.00% 436.68100.00% 6,443.80101.72% 9,448.56

112.04% 4,680.19112.04% 639.53100.00% 665.51100.00% 5,933.40105.37% 11,918.63

112.04% 4,680.19112.04% 639.53100.00% 665.51100.00% 5,933.40105.37% 11,918.63

106.32% 5,202.68106.32% 710.93100.00% 1,005.57100.00% 5,933.40102.91% 12,852.58

106.32% 5,202.68106.32% 710.93100.00% 1,005.57100.00% 5,933.40102.91% 12,852.58

112.04% 4,680.19112.04% 639.53100.00% 665.51100.00% 6,188.60105.26% 12,173.83

112.04% 4,680.19112.04% 639.53100.00% 665.51100.00% 6,188.60105.26% 12,173.83

106.32% 5,202.68106.32% 710.93100.00% 1,005.57100.00% 6,188.60102.85% 13,107.78

106.32% 5,202.68106.32% 710.93100.00% 1,005.57100.00% 6,188.60102.85% 13,107.78

Page 184: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 154

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 4,680.19112.04% 639.53100.00% 665.51100.00% 6,443.80105.15% 12,429.03

112.04% 4,680.19112.04% 639.53100.00% 665.51100.00% 6,443.80105.15% 12,429.03

106.32% 5,202.68106.32% 710.93100.00% 1,005.57100.00% 6,443.80102.80% 13,362.98

106.32% 5,202.68106.32% 710.93100.00% 1,005.57100.00% 6,443.80102.80% 13,362.98

88.96% 58.61112.04% 1,382.00100.00% 1,188.36100.03% 3,234.13102.75% 5,863.10

112.04% 1,495.71100.00% 792.21100.03% 3,234.13103.28% 5,522.05

112.04% 1,219.21100.00% 633.79100.03% 3,234.13102.91% 5,087.13

112.04% 1,010.93100.00% 475.36100.03% 3,234.13102.60% 4,720.42

88.97% 93.73112.04% 2,331.03100.00% 2,376.64100.03% 3,642.73103.37% 8,350.40

112.04% 228.79112.04% 1,721.94100.00% 1,584.43100.03% 3,642.73103.00% 6,949.10

112.04% 173.05112.04% 1,418.76100.00% 1,188.36100.03% 3,642.73102.75% 6,249.85

88.96% 58.61112.04% 1,382.00100.00% 1,188.36100.03% 3,642.73102.57% 6,271.70

112.04% 1,495.71100.00% 792.21100.03% 3,642.73103.05% 5,930.65

112.04% 1,219.21100.00% 633.79100.03% 3,642.73102.69% 5,495.73

112.04% 1,010.93

Page 185: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 155

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 475.36100.03% 3,642.73102.39% 5,129.02

88.96% 58.61112.04% 1,382.00100.00% 1,188.36100.00% 5,614.40102.03% 8,184.76

112.04% 1,495.71100.00% 792.21100.00% 5,614.40102.28% 7,902.32

112.04% 1,219.21100.00% 633.79100.00% 5,614.40101.97% 7,467.40

112.04% 1,010.93100.00% 475.36100.00% 5,614.40101.71% 7,100.69

88.96% 58.61112.04% 1,382.00100.00% 1,188.36100.00% 5,933.40101.87% 8,562.37

112.04% 1,495.71100.00% 792.21100.00% 5,933.40102.19% 8,221.32

112.04% 1,219.21100.00% 633.79100.00% 5,933.40101.89% 7,786.40

112.04% 1,010.93100.00% 475.36100.00% 5,933.40101.64% 7,419.69

112.04% 1,226.05100.00% 633.79100.00% 6,188.60101.83% 8,048.44

112.04% 1,010.93100.00% 475.36100.00% 6,188.60101.59% 7,674.89

106.32% 1,355.32100.00% 633.79100.00% 6,443.80101.02% 8,432.91

106.32% 1,123.79100.00% 475.36100.00% 6,443.80100.88% 8,042.95

100.00% 5,040.20100.00% 574.20

100.00% 5,614.40

100.00% 5,167.80100.00% 574.20

100.00% 5,742.00

100.00% 5,359.20100.00% 574.20

100.00% 5,933.40

100.00% 5,614.40100.00% 574.20

100.00% 6,188.60

Page 186: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 156

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 5,869.60100.00% 574.20

100.00% 6,443.80

100.00% 5,997.20100.00% 574.20

100.00% 6,571.40

100.00% 6,188.60100.00% 574.20

100.00% 6,762.80

100.00% 6,380.00100.00% 574.20

100.00% 6,954.20

100.00% 6,571.40100.00% 574.20

100.00% 7,145.60

100.00% 7,081.80100.00% 574.20

100.00% 7,656.00

100.00% 7,656.00100.00% 574.20

100.00% 8,230.20

100.00% 406.00100.00% 1,265.63100.00% 150.30100.00% 210.24100.00% 50.04100.00% 1,125.00100.00% 425.00100.00% 850.00100.00% 1,700.00100.00% 425.00100.00% 425.00100.00% 425.00100.00% 7,457.21100.00% 532.66

100.00% 37.97100.00% 34.17100.00% 28.47101.54% 155.90101.54% 23.39100.99% 279.90

Page 187: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 157

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 88.38100.00% 79.55100.00% 66.29101.54% 140.31101.52% 21.05100.63% 395.58

100.99% 1,399.50100.00% 703.15100.00% 796.95100.00% 265.65100.00% 796.95100.00% 390.65100.32% 4,352.85100.31% 241.83

100.99% 1,399.50100.63% 1,977.90100.00% 703.15100.00% 796.95100.00% 265.65100.00% 265.65100.00% 796.95100.00% 265.65100.00% 390.65100.38% 6,862.05100.38% 381.23

100.00% 575.19100.00% 640.80100.00% 21.00100.00% 1,600.00100.00% 735.07100.00% 3,572.06

Page 188: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 158

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 575.19100.00% 640.80100.00% 21.00100.00% 1,600.00100.31% 333.73100.03% 3,170.72

100.00% 575.19100.00% 640.80100.00% 21.00100.00% 1,600.00100.38% 526.10100.06% 3,363.09

100.00% 493.13100.00% 673.20100.00% 21.00100.00% 2,057.50100.00% 719.09100.00% 3,963.92

100.00% 493.13100.00% 673.20100.00% 21.00100.00% 2,057.50100.32% 326.47100.03% 3,571.30

100.00% 493.13100.00% 673.20100.00% 21.00100.00% 2,057.50100.38% 514.66100.05% 3,759.49

100.00% 30.11100.00% 79.17100.00% 37.55100.00% 76.56100.00% 223.39

100.00% 30.11100.00% 54.62100.00% 73.80100.00% 37.32100.00% 195.85

100.00% 32.89100.00% 32,934.78100.00% 2,820.00100.00% 11.97100.00% 319.00100.00% 252.00100.00% 3,472.00100.00% 6,386.10100.00% 12,778.92100.00% 4,396.74100.27% 12,681.55100.00% 223.41100.00% 5,231.13100.00% 2,203.88100.00% 6,664.36100.00% 3,456.67100.00% 2,028.78100.00% 4,628.67100.03% 100,522.85100.03% 2,010.46100.03% 25,130.71100.03% 127,664.02100.03% 4,910.15

100.00% 28,223.00100.00% 6,295.90100.00% 3,147.95100.00% 29.54100.00% 62.64100.00% 756.00100.00% 512.08100.00% 3,381.30100.00% 42,408.41100.00% 848.17

Page 189: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 159

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 10,602.10100.00% 53,858.68100.00% 6,732.34

Page 190: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 160

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 18,671.84100.00% 4,043.40100.00% 4,043.40100.00% 1,197.00100.00% 18.30100.00% 252.00100.27% 5,381.83100.00% 2,828.24100.00% 5,410.08100.04% 41,846.09100.04% 836.92100.04% 10,461.52100.04% 53,144.53100.04% 1,398.54

100.00% 2,628.56100.00% 3,942.84100.00% 849.70100.00% 849.70100.00% 16.26100.00% 252.00100.00% 252.00100.00% 1,352.52100.00% 1,352.52100.00% 11,496.10100.00% 229.92100.00% 2,874.03100.00% 14,600.05100.00% 1,825.01

100.00% 18,354.60100.00% 5,947.90100.00% 1,490.02100.00% 495.00100.00% 8.78100.00% 55.68100.27% 2,231.01100.00% 1,172.43100.00% 2,354.11100.02% 32,109.53100.02% 642.19100.02% 8,027.38100.02% 40,779.10100.02% 728.20

100.00% 76.32100.00% 801.00100.00% 20.92100.00% 187.92100.27% 3,600.94100.00% 10,773.04100.00% 1,892.35100.00% 3,072.48100.05% 20,424.97100.05% 408.50100.05% 5,106.24100.05% 25,939.71100.05% 447.24100.05% 6,484.93

100.00% 25.44100.00% 6.21100.00% 62.64100.00% 8,079.78100.00% 256.04100.00% 8,430.11100.00% 168.60100.00% 2,107.53100.00% 10,706.24100.00% 3,823.66100.00% 3,568.75

100.00% 25.44100.00% 2.59100.00% 11.50100.00% 99.76100.00% 142.00100.00% 281.29100.00% 5.63100.00% 70.32100.00% 638.53100.00% 76.93100.00% 638.53

100.00% 25.44100.00% 0.12

0.00

Page 191: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 161

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 52.00100.00% 101.74100.00% 179.30100.00% 3.59100.00% 44.83100.00% 407.02100.00% 49.04100.00% 407.02

100.00% 15,000.92100.00% 3,252.30100.00% 814.74100.00% 69.00100.00% 7.50100.00% 55.68100.27% 313.12100.00% 164.55100.00% 1,284.06100.00% 20,961.87100.00% 419.24100.00% 5,240.47100.00% 26,621.58100.00% 872.84

100.00% 15,454.12100.00% 3,340.20100.00% 836.76100.00% 504.00100.00% 7.50100.00% 55.68100.27% 2,270.15100.00% 1,193.00100.00% 1,284.06100.02% 24,945.47100.02% 498.91100.02% 6,236.37100.02% 31,680.75100.02% 1,005.74

100.00% 50.87100.00% 32.48100.00% 186.00100.00% 34.68100.00% 7.89100.00% 2.98100.00% 387.57100.00% 140.49100.00% 842.96

100.00% 50.87100.00% 40.50100.00% 186.00100.00% 33.78100.00% 4.58100.00% 7.89100.00% 2.98100.00% 387.57100.00% 142.83100.00% 857.00

100.00% 50.87100.00% 40.50100.00% 279.00100.00% 121.29100.00% 4.58100.00% 7.89100.00% 2.98100.00% 469.62100.00% 195.35100.00% 1,172.08

100.00% 50.87100.00% 40.50100.00% 372.00100.00% 144.33100.00% 4.58100.00% 7.89100.00% 2.98100.00% 523.37100.00% 229.30100.00% 1,375.82

100.00% 50.87100.00% 40.50100.00% 279.00

Page 192: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 162

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 70.12100.00% 4.58100.00% 7.89100.00% 2.98100.00% 469.62100.00% 185.11100.00% 1,110.67

Page 193: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 163

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 50.87100.00% 40.50100.00% 372.00100.00% 343.50100.00% 4.58100.00% 7.89100.00% 2.98100.00% 575.71100.00% 279.61100.00% 1,677.64

100.00% 50.87100.00% 40.50100.00% 279.00100.00% 158.72100.00% 4.58100.00% 7.89100.00% 2.98100.00% 469.62100.00% 202.83100.00% 1,216.99

100.00% 50.87100.00% 40.50100.00% 279.00100.00% 24.59100.00% 9.16100.00% 7.89100.00% 2.98100.00% 387.57100.00% 160.51100.00% 963.07

100.00% 142.00100.00% 31.32100.00% 587.20100.00% 186.00100.00% 70.83100.00% 11.50100.00% 7.89100.00% 2.98100.00% 441.17100.00% 296.18100.00% 1,777.07

100.00% 101.74100.00% 40.50100.00% 186.00100.00% 70.83100.00% 9.16100.00% 7.89100.00% 2.98100.00% 441.17100.00% 172.05100.00% 1,032.32

100.00% 101.74100.00% 40.50100.00% 8.40100.00% 14.24100.00% 9.16100.00% 2.98100.00% 387.57100.00% 112.92100.00% 677.51

100.00% 76.31100.00% 40.50100.00% 312.00100.00% 414.12100.00% 4.58100.00% 7.89100.00% 2.98100.00% 387.57100.00% 249.19100.00% 1,495.14

100.00% 76.31100.00% 40.50100.00% 156.00100.00% 136.17100.00% 9.16100.00% 7.89100.00% 2.98100.00% 387.57100.00% 163.32100.00% 979.90

Page 194: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 164

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 266.80100.00% 411.80100.00% 543.17100.00% 175.40100.00% 279.43100.00% 1,676.60

100.00% 533.60100.00% 527.80100.00% 543.17100.00% 350.80100.00% 391.07100.00% 2,346.44

100.00% 800.40100.00% 1,121.00100.00% 543.17100.00% 526.20100.00% 598.15100.00% 3,588.92

100.00% 1,067.20100.00% 1,238.00100.00% 543.17100.00% 701.60100.00% 709.99100.00% 4,259.96

100.00% 1,600.80100.00% 1,780.60100.00% 543.17100.00% 1,052.40100.00% 995.39100.00% 5,972.36

100.00% 2,134.40100.00% 1,238.00100.00% 543.17100.00% 1,403.20100.00% 1,063.75100.00% 6,382.52

100.00% 3,201.60100.00% 1,780.60100.00% 543.17100.00% 2,104.80100.00% 1,526.03100.00% 9,156.20

100.00% 1,200.60100.00% 330.60100.00% 3,218.40100.00% 12.02100.00% 27.48100.00% 34.50100.00% 1,052.40100.00% 543.17100.00% 235.95100.00% 5,963.00100.00% 610.44100.00% 71.00100.00% 1,984.28100.00% 15,283.84

101.59% 633.53100.00% 336,400.00100.00% 337,033.53100.00% 3,370.34100.00% 84,258.38100.00% 4,285.33100.00% 428,947.58

100.00% 593.43

100.00% 915.53

100.00% 668.06

100.00% 905.29

Page 195: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 165

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 35.64100.00% 78.40100.00% 59.00100.00% 8.35100.00% 13.06100.00% 10.32100.00% 35.72100.00% 469.80100.00% 45.30100.00% 65.28100.00% 84.00100.00% 40.32100.00% 5,974.00100.00% 3,611.00100.00% 2,302.99100.00% 78.40100.00% 18.00100.00% 13.88100.00% 797.71100.00% 45.00100.00% 518.80100.00% 1,556.40100.00% 220.83100.00% 518.80100.00% 1,186.85100.00% 17,787.85

100.00% 35.64100.00% 78.40100.00% 59.00100.00% 8.35100.00% 13.06100.00% 10.32100.00% 35.72100.00% 469.80100.00% 45.30100.00% 65.28100.00% 84.00100.00% 40.32100.00% 13,304.78100.00% 3,611.00100.00% 2,302.99100.00% 78.40100.00% 18.00100.00% 13.88100.00% 797.71100.00% 45.00100.00% 518.80100.00% 1,556.40100.00% 220.83100.00% 518.80100.00% 1,250.00100.00% 25,181.78

100.00% 35.64100.00% 78.40100.00% 59.00100.00% 8.35100.00% 13.06100.00% 10.32100.00% 35.72100.00% 469.80100.00% 45.30100.00% 65.28100.00% 84.00100.00% 40.32100.00% 12,180.00100.00% 3,611.00100.00% 2,302.99100.00% 78.40100.00% 18.00100.00% 13.88100.00% 797.71100.00% 45.00100.00% 518.80100.00% 1,556.40100.00% 220.83100.00% 518.80100.00% 1,250.00100.00% 24,057.00

100.00% 35.64100.00% 78.40100.00% 59.00100.00% 8.35100.00% 13.06100.00% 10.32100.00% 35.72

Page 196: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 166

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 104.40100.00% 60.40100.00% 16.62100.00% 8.96100.00% 2,989.32100.00% 578.00100.00% 13.70100.00% 18.00100.00% 330.00100.00% 57.30100.00% 250.46100.00% 13.76100.00% 12.95100.00% 45.00100.00% 518.80100.00% 1,037.60100.00% 889.54100.00% 7,185.30

100.00% 35.64100.00% 78.40100.00% 59.00100.00% 8.35100.00% 13.06100.00% 10.32100.00% 35.72100.00% 104.40100.00% 60.40100.00% 16.62100.00% 8.96100.00% 2,734.33100.00% 578.00100.00% 13.70100.00% 18.00100.00% 330.00100.00% 57.30100.00% 250.46100.00% 13.76100.00% 12.95100.00% 45.00100.00% 518.80100.00% 1,037.60100.00% 889.54100.00% 6,930.31

100.00% 35.64100.00% 78.40100.00% 59.00100.00% 8.35100.00% 13.06100.00% 68.32100.00% 6.88100.00% 593.43100.00% 863.08

100.00% 72.77100.00% 175.00100.00% 70.04100.00% 26.13100.00% 35.31100.00% 68.32100.00% 9.89100.00% 668.06100.00% 1,125.52

100.00% 44.89100.00% 1,762.21100.00% 59.14100.00% 40.62100.00% 60.32100.00% 28.65100.00% 12.90100.00% 668.06100.00% 2,676.79

100.00% 44.89100.00% 1,762.21100.00% 822.00100.00% 40.62100.00% 60.32100.00% 28.65100.00% 12.90100.00% 668.06100.00% 3,439.65

100.00% 35.64100.00% 59.00100.00% 8.35

Page 197: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 167

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 13.06100.00% 10.32100.00% 17.86100.00% 266.22100.00% 30.20100.00% 65.28100.00% 84.00100.00% 22.40100.00% 81.55100.00% 482.40100.00% 146.72100.00% 18.00100.00% 9.25100.00% 45.00100.00% 593.43100.00% 518.80100.00% 296.11100.00% 296.11100.00% 3,099.70

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 53.58100.00% 245.34100.00% 75.50100.00% 24.93100.00% 22.40100.00% 1,316.89100.00% 2,047.01100.00% 275.50100.00% 134.68100.00% 139.00100.27% 175.64100.00% 18.00100.00% 330.00100.00% 57.30100.00% 13.76100.00% 250.46100.00% 18.50100.00% 93.75100.00% 518.80100.00% 1,037.60100.00% 950.93100.01% 7,972.54

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 53.58100.00% 245.34100.00% 75.50100.00% 24.93100.00% 22.40100.00% 1,614.43100.00% 2,047.01100.00% 275.50100.00% 134.68100.00% 139.00100.27% 175.64100.00% 18.00100.00% 330.00100.00% 57.30100.00% 13.76100.00% 250.46100.00% 18.50100.00% 93.75100.00% 518.80100.00% 1,336.12100.00% 742.69100.01% 8,360.36

100.00% 44.89100.00% 59.14100.00% 40.62100.00% 60.32100.00% 15.05100.00% 17.86100.00% 88.74100.00% 30.20100.00% 8.31100.00% 8.96100.00% 2,943.00100.00% 27.26

Page 198: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 168

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 13.70100.00% 37.00100.00% 24.00100.00% 165.00100.00% 28.65100.00% 6.88100.00% 136.65100.00% 6.48100.00% 45.00100.00% 668.06100.00% 668.06100.00% 593.43100.00% 5,737.26

100.00% 44.89100.00% 59.14100.00% 40.62100.00% 60.32100.00% 15.05100.00% 17.86100.00% 88.74100.00% 30.20100.00% 8.31100.00% 8.96100.00% 2,920.00100.00% 27.26100.00% 13.70100.00% 37.00100.00% 24.00100.00% 165.00100.00% 28.65100.00% 6.88100.00% 136.65100.00% 6.48100.00% 45.00100.00% 668.06100.00% 668.06100.00% 593.43100.00% 5,714.26

100.00% 44.89100.00% 59.14100.00% 40.62100.00% 60.32100.00% 15.05100.00% 17.86100.00% 88.74100.00% 30.20100.00% 8.31100.00% 8.96100.00% 4,796.48100.00% 27.26100.00% 13.70100.00% 37.00100.00% 24.00100.00% 165.00100.00% 28.65100.00% 6.88100.00% 136.65100.00% 6.48100.00% 45.00100.00% 668.06100.00% 668.06100.00% 593.43100.00% 7,590.74

100.00% 44.89100.00% 59.14100.00% 40.62100.00% 60.32100.00% 15.05100.00% 17.86100.00% 88.74100.00% 30.20100.00% 8.31100.00% 8.96100.00% 6,431.01100.00% 27.26100.00% 13.70100.00% 37.00100.00% 24.00100.00% 165.00100.00% 28.65100.00% 6.88100.00% 136.65100.00% 6.48100.00% 45.00100.00% 668.06

Page 199: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 169

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 668.06100.00% 593.43100.00% 9,225.27

100.00% 35.64100.00% 30.09100.00% 59.00100.00% 8.35100.00% 13.06100.00% 78.40100.00% 10.32100.00% 35.72100.00% 240.12100.00% 60.40100.00% 22.40100.00% 3,617.37100.00% 116.00100.00% 176.32100.00% 28.65100.00% 18.00100.00% 677.98100.00% 10.18100.00% 45.00100.00% 518.80100.00% 1,037.60100.00% 668.06100.00% 7,507.46

100.00% 35.64100.00% 15.05100.00% 59.00100.00% 8.35100.00% 13.06100.00% 78.40100.00% 10.32100.00% 17.86100.00% 193.14100.00% 30.20100.00% 17.92100.00% 2,305.86100.00% 58.00100.00% 88.16100.00% 28.65100.00% 18.00100.00% 338.99100.00% 4.63100.00% 45.00100.00% 518.80100.00% 518.80100.00% 6.50100.00% 518.80100.00% 4,929.13

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 35.72100.00% 245.34100.00% 60.40100.00% 16.62100.00% 22.40100.00% 1,187.96100.00% 1,760.00100.00% 475.60100.00% 148.00100.00% 18.00100.00% 330.00100.00% 57.30100.00% 13.76100.00% 250.46100.00% 12.95100.00% 93.75100.00% 518.80100.00% 1,037.60100.00% 593.43100.00% 7,051.06

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 35.72100.00% 245.34100.00% 60.40100.00% 16.62

Page 200: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 170

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 22.40100.00% 1,601.99100.00% 1,760.00100.00% 475.60100.00% 148.00100.00% 18.00100.00% 330.00100.00% 57.30100.00% 13.76100.00% 250.46100.00% 12.95100.00% 93.75100.00% 518.80100.00% 1,037.60100.00% 593.43100.00% 7,465.09

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 35.72100.00% 245.34100.00% 60.40100.00% 16.62100.00% 22.40100.00% 2,188.00100.00% 1,760.00100.00% 475.60100.00% 148.00100.00% 18.00100.00% 330.00100.00% 57.30100.00% 13.76100.00% 250.46100.00% 12.95100.27% 43.91100.00% 93.75100.00% 518.80100.00% 1,037.60100.00% 593.43100.00% 8,095.01

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 35.72100.00% 245.34100.00% 60.40100.00% 16.62100.00% 22.40100.00% 2,302.60100.00% 1,760.00100.00% 475.60100.00% 148.00100.00% 18.00100.00% 330.00100.00% 57.30100.00% 13.76100.00% 250.46100.00% 12.95100.27% 43.91100.00% 93.75100.00% 518.80100.00% 1,037.60100.00% 593.43100.00% 8,209.61

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 17.86100.00% 125.28100.00% 30.20100.00% 8.31100.00% 8.96100.00% 719.99100.00% 586.03100.00% 70.30100.00% 78.00100.00% 18.00100.00% 165.00100.00% 28.65

Page 201: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 171

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 6.88100.00% 253.46100.00% 6.48100.00% 93.75100.00% 518.80100.00% 518.80100.00% 593.43100.00% 4,021.15

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 17.86100.00% 125.28100.00% 30.20100.00% 8.31100.00% 8.96100.00% 9,784.00100.00% 555.59100.00% 28.65100.00% 6.88100.00% 125.23100.00% 6.48100.00% 93.75100.00% 518.80100.00% 518.80100.00% 668.06100.00% 12,669.82

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 22.01100.00% 166.48100.00% 29.00100.00% 8.96100.00% 9,784.00100.00% 3,849.00100.00% 4.63100.00% 93.75100.00% 518.80100.00% 668.06100.00% 668.06100.00% 15,985.72

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 17.86100.00% 125.28100.00% 30.20100.00% 8.31100.00% 8.96100.00% 9,092.20100.00% 555.59100.00% 28.65100.00% 6.88100.00% 125.23100.00% 6.48100.00% 93.75100.00% 518.80100.00% 668.06100.00% 1,038.80100.00% 12,498.02

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 22.01100.00% 166.48100.00% 29.00100.00% 8.96100.00% 9,092.20100.00% 3,849.00100.00% 4.63100.00% 93.75100.00% 518.80100.00% 668.06100.00% 1,038.80100.00% 15,664.66

Page 202: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 172

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 69.18100.00% 59.00100.00% 8.35100.00% 26.12100.00% 10.32100.00% 17.86100.00% 125.28100.00% 30.20100.00% 8.31100.00% 8.96100.00% 2,420.60100.00% 555.59100.00% 28.65100.00% 6.88100.00% 125.23100.00% 6.48100.00% 93.75100.00% 518.80100.00% 518.80100.00% 742.69100.00% 5,381.05

100.00% 35.64100.00% 59.00100.00% 8.35100.00% 13.06100.00% 78.40100.00% 10.32100.00% 17.86100.00% 125.28100.00% 30.20100.00% 8.96100.00% 1,794.50100.00% 58.00100.00% 28.65100.00% 18.00100.00% 338.99100.00% 4.63100.00% 45.00100.00% 593.43100.00% 518.80100.00% 3.25100.00% 149.26100.00% 3,939.58

100.00% 195.92100.00% 207.00100.00% 175.0389.10% 3.67

112.04% 307.7999.70% 826.60

100.00% 103.59100.00% 43.96100.00% 766.67101.30% 2,630.23

100.27% 835.00100.00% 246.00100.00% 175.0388.97% 3.67

112.04% 307.7999.70% 826.60

100.00% 103.59100.00% 43.96100.00% 766.67101.10% 3,308.31

100.00% 120.76100.00% 201.00100.00% 175.0389.10% 3.67

112.04% 307.7999.70% 903.94

100.00% 103.59100.00% 43.96100.00% 766.67101.29% 2,626.41

100.00% 5,663.22100.00% 5,994.00100.00% 4,582.29112.04% 2,650.45100.64% 14,510.13100.00% 2,028.93

Page 203: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 173

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 1,171.60100.00% 200.30100.00% 20.81100.00% 22.13100.00% 618.34100.00% 131.90100.00% 5,160.13100.96% 42,754.23

100.00% 11,562.50100.00% 7,104.00100.00% 4,582.29112.04% 2,650.45100.64% 14,510.13100.00% 2,028.93100.00% 1,171.60100.00% 200.30100.00% 20.81100.00% 22.13100.00% 618.34100.00% 131.90100.00% 5,160.13100.83% 49,763.51

100.00% 3,490.58100.00% 5,772.00100.00% 4,582.29112.04% 2,650.45100.64% 14,510.13100.00% 2,028.93100.00% 1,171.60100.00% 200.30100.00% 20.81100.00% 22.13100.00% 618.34100.00% 131.90100.00% 5,160.13101.02% 40,359.59

100.00% 11,479.50100.00% 12,150.00100.00% 9,870.16112.04% 2,667.55112.04% 5,335.11100.81% 32,077.82100.00% 1,773.35100.00% 303.18100.00% 31.67100.00% 33.33100.00% 936.08100.00% 199.68100.00% 7,646.80100.00% 1,370.20100.64% 1,626.41100.00% 1,597.09100.00% 666.91100.00% 2,662.20101.33% 92,427.04

100.00% 23,437.50100.00% 14,400.00100.00% 9,870.16112.04% 2,667.55112.04% 5,335.11100.81% 32,077.82100.00% 1,773.35100.00% 303.18100.00% 31.67100.00% 33.33100.00% 936.08100.00% 199.68100.00% 7,646.80100.00% 1,370.20100.64% 1,626.41100.00% 1,597.09100.00% 666.91100.00% 2,662.20101.16% 106,635.04

100.00% 7,075.50100.00% 11,700.00100.00% 9,870.16112.04% 2,667.55112.04% 5,335.11100.81% 32,077.82100.00% 1,773.35100.00% 303.18100.00% 31.67

Page 204: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 174

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 33.33100.00% 936.08100.00% 199.68100.00% 7,646.80100.00% 1,370.20100.64% 1,626.41100.00% 1,597.09100.00% 666.91100.00% 2,662.20101.41% 87,573.04

100.00% 661.98100.00% 702.00100.00% 1,028.75112.04% 617.3099.70% 2,008.76

100.00% 122.32100.00% 1,525.00101.02% 6,666.11

100.00% 1,351.56100.00% 831.00100.00% 1,028.75112.04% 617.3099.70% 2,008.76

100.00% 122.32100.00% 1,525.00100.91% 7,484.69

100.00% 408.02100.00% 675.00100.00% 1,028.75112.04% 617.3099.70% 2,008.76

100.00% 122.32100.00% 1,525.00101.07% 6,385.15

Page 205: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 175

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 5,994.30112.04% 7,796.75100.00% 107.36100.64% 5,357.59101.15% 120,067.01100.00% 46,950.00100.00% 4,871.33100.00% 1,594.00100.00% 101.79100.00% 3,012.56100.00% 642.61100.00% 1,908.40100.00% 17,511.75100.00% 6,575.08100.00% 47,838.90100.00% 39,639.20100.00% 49,216.03100.00% 9,324.08100.00% 1,725.28100.00% 6,001.48100.82% 376,235.50

112.04% 5,994.30112.04% 7,796.75100.00% 107.36100.64% 5,357.59101.15% 120,067.01100.00% 60,150.00100.00% 4,871.33100.00% 1,594.00100.00% 101.79100.00% 3,012.56100.00% 642.61100.00% 1,908.40100.00% 17,511.75100.00% 6,575.08100.00% 97,671.88100.00% 39,639.20100.00% 49,216.03100.00% 9,324.08100.00% 1,725.28100.00% 6,001.48100.70% 439,268.48

112.04% 5,994.30112.04% 7,796.75100.00% 107.36100.64% 5,357.59101.15% 120,067.01100.00% 45,150.00100.00% 4,871.33100.00% 1,594.00100.00% 101.79100.00% 3,012.56

Page 206: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 176

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 642.61100.00% 1,908.40100.00% 17,511.75100.00% 6,575.08100.00% 29,485.97100.00% 39,639.20100.00% 49,216.03100.00% 9,324.08100.00% 1,725.28100.00% 6,001.48100.86% 356,082.57

100.00% 220.83100.00% 1,186.85100.00% 518.80100.00% 518.80100.00% 1,037.60100.00% 3,482.88

100.00% 220.83100.00% 1,250.00100.00% 518.80100.00% 518.80100.00% 1,037.60100.00% 3,546.03

100.00% 889.54100.00% 518.80100.00% 1,037.60100.00% 2,445.94

100.00% 518.80100.00% 518.80100.00% 1,037.60100.00% 2,075.20

100.00% 296.11100.00% 518.80100.00% 518.80100.00% 1,333.71

100.00% 950.93100.00% 518.80100.00% 1,037.60100.00% 2,507.33

100.00% 742.69100.00% 518.80100.00% 518.80100.00% 1,780.29

100.00% 593.43100.00% 668.06100.00% 668.06100.00% 1,929.55

100.00% 668.06100.00% 1,556.40100.00% 1,037.60100.00% 3,262.06

100.00% 518.80100.00% 1,037.60100.00% 518.80100.00% 2,075.20

100.00% 722.22100.00% 518.80100.00% 1,037.60100.00% 2,278.62

100.00% 1,038.80100.00% 518.80100.00% 1,037.60100.00% 2,595.20

100.00% 812.50100.00% 518.80100.00% 1,037.60100.00% 2,368.90

100.00% 1,038.80100.00% 518.80100.00% 1,037.60100.00% 2,595.20

Page 207: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 177

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 593.43100.00% 518.80100.00% 1,037.60100.00% 2,149.83

100.00% 668.06100.00% 518.80100.00% 668.06100.00% 1,854.92

100.00% 1,038.80100.00% 518.80100.00% 668.06100.00% 2,225.66

100.00% 742.69100.00% 518.80100.00% 668.06100.00% 1,929.55

100.00% 149.26100.00% 518.80100.00% 518.80100.00% 3.25100.00% 1,190.11

100.00% 10.31100.00% 18.98100.00% 1.27100.00% 7.93100.00% 48.00100.00% 46.81100.00% 252.94100.00% 1.85100.00% 4.12100.00% 265.06100.00% 42.45100.00% 1.76100.04% 28.57102.60% 424.84100.00% 283.29100.64% 637.81100.00% 165.16100.00% 11.93100.00% 34.56100.00% 8.15100.00% 117.60100.00% 82.32100.00% 81.85100.59% 2,577.56

100.00% 836.40100.00% 872.10100.00% 212.50100.00% 1,921.00

100.00% 836.40100.00% 872.10100.00% 212.50100.00% 1,921.00

100.00% 25.19100.00% 569.08100.00% 6,002.50100.00% 212.50100.00% 6,809.27

100.00% 24.54100.00% 738.00100.00% 3,892.50100.00% 212.50100.00% 4,867.54

100.00% 35.00100.00% 836.40100.00% 872.10100.00% 4,415.00100.00% 212.50100.00% 6,371.00

100.00% 24.16

Page 208: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 178

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 818.36100.00% 2,877.50100.00% 212.50100.00% 3,932.52

100.00% 15.83100.00% 2,365.00100.00% 212.50100.00% 2,116.94100.00% 4,710.27

100.00% 23.80100.00% 894.62100.00% 1,890.00100.00% 212.50100.00% 3,020.92

100.00% 23.70100.00% 918.40100.00% 1,615.00100.00% 212.50100.00% 2,769.60

100.00% 24.50100.00% 1,310.00100.00% 212.50100.00% 2,305.20100.00% 3,852.20

100.00% 888.75100.00% 6.24100.00% 100.73100.00% 32.73100.00% 1,028.45

100.00% 29.69100.00% 888.75100.00% 6.24100.00% 100.73100.00% 21.68100.00% 1,047.09

100.00% 374.92100.00% 6.24100.00% 170.85100.00% 58.23100.00% 610.24

100.00% 29.69100.00% 374.92100.00% 6.24100.00% 170.85100.00% 38.68100.00% 620.38

100.00% 187.60100.00% 444.00100.00% 6.24100.00% 134.30100.00% 40.80100.00% 812.94

100.00% 29.69100.00% 187.60100.00% 444.00100.00% 6.24100.00% 134.30100.00% 21.68100.00% 823.51

100.00% 6.24100.00% 134.30100.00% 58.23100.00% 198.77

100.00% 29.69100.00% 6.24100.00% 134.30100.00% 38.68100.00% 208.91

100.00% 235.85100.00% 127.50100.00% 363.35

Page 209: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 179

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 57.52100.00% 6.25100.00% 30.09100.00% 18.77100.00% 112.63

100.00% 36.64100.00% 6.25100.00% 30.09100.00% 14.60100.00% 87.58

100.00% 57.52100.00% 6.25100.00% 30.09100.00% 68.95100.00% 18.77100.00% 181.58

100.00% 103.36100.00% 55.04100.00% 6.25100.00% 37.32100.00% 40.39100.00% 242.36

100.00% 47.75100.00% 6.25100.00% 30.09100.00% 16.82100.00% 100.91

100.00% 19.10100.00% 6.25100.00% 30.09100.00% 11.09100.00% 66.53

100.00% 52.08100.00% 55.04100.00% 6.25100.00% 37.32100.00% 30.14100.00% 180.83

100.00% 52.08100.00% 55.04100.00% 6.25100.00% 37.32100.00% 68.95100.00% 30.14100.00% 249.78

100.00% 30.11100.00% 375.07100.00% 103.63100.00% 13.58100.00% 107.32100.00% 57.99100.00% 687.70

100.00% 45.17100.00% 88.00100.00% 1,573.91100.00% 4.52100.00% 27.15100.00% 57.99100.00% 60.23100.00% 1,856.97

100.00% 45.17100.00% 88.00100.00% 2,038.92100.00% 4.52100.00% 27.15100.00% 57.99100.00% 60.23100.00% 2,321.98

100.00% 45.17100.00% 88.00100.00% 1,400.72

Page 210: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 180

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 4.52100.00% 27.15100.00% 57.99100.00% 60.23100.00% 1,683.78

100.00% 45.17100.00% 88.00100.00% 1,645.72100.00% 4.52100.00% 27.15100.00% 57.99100.00% 60.23100.00% 1,928.78

100.00% 45.17100.00% 88.00100.00% 1,165.89100.00% 4.52100.00% 27.15100.00% 57.99100.00% 60.23100.00% 1,448.95

100.00% 45.17100.00% 88.00100.00% 1,389.41100.00% 4.52100.00% 27.15100.00% 57.99100.00% 60.23100.00% 1,672.47

100.00% 30.11100.00% 375.07100.00% 33.77100.00% 450.46100.00% 35.25100.00% 19.80100.00% 3.19100.00% 265.00100.00% 1,212.65

100.00% 30.11100.00% 375.07100.00% 33.77100.00% 1,276.34100.00% 35.25100.00% 19.80100.00% 3.19100.00% 278.95100.00% 2,052.48

100.00% 30.11100.00% 121.34100.00% 710.74100.00% 31.90100.00% 27.73100.00% 165.91100.00% 262.17100.00% 1,349.90

100.00% 30.11100.00% 121.34100.00% 419.27100.00% 30.90100.00% 27.73100.00% 140.38100.00% 262.17100.00% 1,031.90

100.00% 30.11100.00% 121.34100.00% 358.04100.00% 30.90100.00% 13.17100.00% 140.38100.00% 262.17100.00% 956.11

100.00% 30.11100.00% 121.34100.00% 600.53100.00% 31.90100.00% 27.73100.00% 165.91100.00% 262.17100.00% 1,239.69

Page 211: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 181

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 375.07100.00% 103.63100.00% 13.58100.00% 84.38103.17% 882.97

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 464.37100.00% 103.63100.00% 16.97100.00% 84.38102.87% 975.66

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 571.53100.00% 103.63100.00% 20.06100.00% 84.38102.58% 1,085.91

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 750.13100.00% 103.63100.00% 27.77100.00% 84.38102.20% 1,272.22

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 561.44100.00% 103.63100.00% 13.58100.00% 84.38102.62% 1,069.34

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 673.73100.00% 103.63100.00% 16.97100.00% 84.38102.36% 1,185.02

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 842.16100.00% 103.63100.00% 20.06100.00% 84.38102.06% 1,356.54

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 1,122.88100.00% 103.63100.00% 27.77100.00% 84.38101.70% 1,644.97

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 593.34100.00% 103.63100.00% 13.58100.00% 84.38102.54% 1,101.24

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 712.01100.00% 103.63100.00% 16.97

Page 212: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 182

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 84.38102.29% 1,223.30

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 890.01100.00% 103.63100.00% 20.06100.00% 84.38101.99% 1,404.39

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 1,186.68100.00% 103.63100.00% 27.77100.00% 84.38101.64% 1,708.77

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 618.86100.00% 103.63100.00% 13.58

Page 213: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 183

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 84.38102.49% 1,126.76

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 742.63100.00% 103.63100.00% 16.97100.00% 84.38102.23% 1,253.92

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 928.29100.00% 103.63100.00% 20.06100.00% 84.38101.94% 1,442.67

100.00% 30.11112.04% 232.56100.00% 43.64100.00% 1,237.72100.00% 103.63100.00% 27.77100.00% 84.38101.59% 1,759.81

100.00% 30.11100.00% 375.07100.00% 103.63100.00% 13.58100.00% 84.38100.00% 57.99100.00% 664.76

100.00% 30.11100.00% 375.07100.00% 103.63100.00% 13.58100.00% 112.50100.00% 57.99100.00% 692.88

100.00% 30.11100.00% 375.07100.00% 103.63100.00% 13.58100.00% 119.12100.00% 57.99100.00% 10.00100.00% 709.50

100.00% 30.11100.00% 121.34100.00% 338.80100.00% 48.72100.00% 13.17100.00% 150.57100.00% 702.71

100.00% 30.11100.00% 121.34100.00% 385.39100.00% 24.36100.00% 13.17100.00% 194.85100.00% 769.22

100.00% 30.11100.00% 121.34100.00% 901.97100.00% 32.48100.00% 13.17100.00% 121.67100.00% 1,220.74

100.00% 8.26100.00% 78.77100.00% 9.28100.00% 0.81100.00% 100.00100.00% 197.12

100.00% 8.26100.00% 87.97

Page 214: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 184

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 12.76100.00% 0.81100.00% 100.00100.00% 209.80

100.00% 8.26100.00% 137.09100.00% 12.76100.00% 0.38100.00% 100.00100.00% 258.49

100.00% 8.26100.00% 40.96100.00% 5.80100.00% 0.38100.00% 100.00100.00% 155.40

100.00% 41.29100.00% 27.22100.00% 68.51

100.00% 8.26100.00% 113.48100.00% 5.80100.00% 0.81100.00% 60.23100.00% 188.58

100.00% 24.77100.00% 278.40100.00% 101.92100.00% 405.09

100.00% 8.26100.00% 78.77100.00% 5.80100.00% 0.81100.00% 60.23100.00% 153.87

100.00% 8.26100.00% 49.79100.00% 5.80100.00% 0.38100.00% 60.23100.00% 124.46

100.00% 8.26100.00% 87.97100.00% 5.80100.00% 0.81100.00% 60.23100.00% 163.07

100.00% 8.26100.00% 36.59100.00% 5.80100.00% 0.38100.00% 60.23100.00% 111.26

100.00% 8.26100.00% 137.09100.00% 5.80100.00% 0.38100.00% 44.17100.00% 195.70

100.00% 736.12100.00% 1,785.00100.00% 104.40100.00% 22.40100.00% 10.50100.00% 484.88100.00% 1,025.00100.00% 4,168.30

100.00% 736.12100.00% 3,234.00100.00% 104.40100.00% 22.40100.00% 10.50100.00% 484.88

Page 215: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 185

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 1,025.00100.00% 5,617.30

100.00% 2,275.28100.00% 11,088.00100.00% 104.40100.00% 22.40100.00% 10.50100.00% 1,388.52100.00% 1,025.00100.00% 15,914.10

100.00% 2,275.28100.00% 11,403.00100.00% 104.40100.00% 22.40100.00% 10.50100.00% 4,165.56100.00% 1,025.00100.00% 19,006.14

100.00% 2,275.28100.00% 11,088.00100.00% 523.45100.00% 22.40100.00% 10.50100.00% 1,025.00100.00% 14,944.63

100.00% 5,056.48100.00% 33,406.56100.00% 208.80100.00% 32.00100.00% 15.00100.00% 119.00100.00% 127.99100.00% 12.40100.00% 1,388.52100.00% 4,100.00100.00% 44,466.75

130.30% 177.50100.00% 855.00168.00% 996.88100.00% 139.58120.00% 1,062.50100.00% 1,087.50100.00% 1,687.50100.00% 6,900.00107.32% 12,906.4698.77% 189.8080.72% 64.53

100.00% 33.77100.00% 450.46100.00% 35.25100.00% 19.80100.00% 3.19100.00% 252.38100.00% 794.85

100.00% 33.77100.00% 488.00100.00% 35.25100.00% 19.80100.00% 3.19100.00% 252.38

Page 216: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 186

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 832.39

100.00% 33.77100.00% 525.56100.00% 35.25100.00% 19.80100.00% 3.19100.00% 252.38100.00% 869.95

100.00% 33.77100.00% 600.64100.00% 35.25100.00% 19.80100.00% 3.19100.00% 252.38100.00% 945.03

100.00% 33.77100.00% 750.79100.00% 35.25100.00% 19.80100.00% 3.19100.00% 252.38100.00% 1,095.18

100.00% 33.77100.00% 825.87100.00% 35.25100.00% 19.80100.00% 3.19100.00% 252.38100.00% 1,170.26

100.00% 33.77100.00% 976.04100.00% 35.25100.00% 19.80100.00% 3.19100.00% 252.38100.00% 1,320.43

100.00% 33.77100.00% 1,126.18100.00% 35.25100.00% 19.80100.00% 3.19100.00% 252.38100.00% 1,470.57

100.00% 33.77100.00% 1,276.34100.00% 35.25100.00% 19.80100.00% 3.19100.00% 278.95100.00% 1,647.30

100.00% 33.77100.00% 1,388.96100.00% 35.25100.00% 19.80100.00% 3.19100.00% 278.95100.00% 1,759.92

100.00% 33.77100.00% 1,501.59100.00% 35.25100.00% 19.80100.00% 3.19100.00% 278.95100.00% 1,872.55

100.00% 33.77100.00% 1,651.75100.00% 35.25100.00% 19.80100.00% 3.19100.00% 278.95100.00% 2,022.71

100.00% 76.45100.00% 544.62100.00% 174.93100.00% 365.98100.00% 1,161.98

Page 217: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 187

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 76.45100.00% 776.62100.00% 174.93100.00% 3.19100.00% 365.98100.00% 1,397.17

100.00% 187.65100.00% 220.05100.00% 1,046.25100.00% 494.10100.00% 157.95100.00% 2,227.50100.00% 375.96100.00% 7.66100.00% 45.92100.00% 68.89100.00% 19.34100.00% 32.34100.00% 20.45100.00% 76.53100.00% 185.02100.00% 2,161.08100.00% 124.71100.00% 678.60100.00% 1,089.81100.00% 9,219.81

100.00% 198.77100.00% 233.09100.00% 1,108.25100.00% 523.38100.00% 167.31100.00% 2,359.50100.00% 375.96100.00% 7.66100.00% 45.92100.00% 68.89100.00% 19.34100.00% 32.34100.00% 20.45100.00% 76.53100.00% 185.02100.00% 2,161.08100.00% 124.71100.00% 678.60100.00% 1,089.81100.00% 9,476.61

100.00% 58.38100.00% 68.46100.00% 325.50100.00% 153.72100.00% 49.14100.00% 693.00100.00% 375.96100.00% 7.66100.00% 45.92100.00% 68.89100.00% 19.34100.00% 32.34100.00% 20.45100.00% 76.53100.00% 185.02100.00% 2,161.08100.00% 124.71100.00% 678.60100.00% 1,089.81100.00% 6,234.51

100.00% 180.70100.00% 211.90100.00% 1,007.50

Page 218: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 188

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 475.80100.00% 152.10100.00% 2,145.00100.00% 375.96100.00% 7.66100.00% 45.92100.00% 68.89100.00% 19.34100.00% 32.34100.00% 20.45100.00% 76.53100.00% 185.02100.00% 2,161.08100.00% 124.71100.00% 678.60100.00% 1,089.81100.00% 9,059.31

100.00% 422.55100.00% 365.85100.00% 1,744.20100.00% 822.15100.00% 261.90100.00% 2,227.50100.00% 524.36100.00% 350.41100.00% 3.83100.00% 18.81100.00% 16.84100.00% 33.22100.00% 32.34100.00% 76.53100.00% 185.02100.00% 2,161.08100.00% 124.71100.00% 1,165.37100.00% 1,089.81100.00% 560.82100.00% 228.13100.00% 7.54100.00% 12,422.97

100.00% 447.59100.00% 387.53100.00% 1,847.56100.00% 870.87100.00% 277.42100.00% 2,359.50100.00% 524.36100.00% 350.41100.00% 3.83100.00% 18.81100.00% 14.51100.00% 33.22100.00% 32.34100.00% 76.53100.00% 185.02100.00% 2,161.08100.00% 124.71100.00% 1,165.37100.00% 1,089.81100.00% 560.82100.00% 228.13100.00% 7.54100.00% 12,766.96

100.00% 131.46100.00% 113.82100.00% 542.64100.00% 255.78100.00% 81.48100.00% 693.00100.00% 524.36100.00% 350.41100.00% 3.83100.00% 18.81100.00% 14.51100.00% 33.22100.00% 32.34

Page 219: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 189

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 76.53100.00% 185.02100.00% 2,161.08100.00% 124.71100.00% 1,165.37100.00% 1,089.81100.00% 560.82100.00% 228.13100.00% 7.54100.00% 8,394.67

100.00% 406.90100.00% 352.30100.00% 1,679.60100.00% 791.70100.00% 252.20100.00% 2,145.00100.00% 524.36100.00% 350.41100.00% 3.83100.00% 18.81100.00% 14.51100.00% 33.22100.00% 32.34100.00% 76.53100.00% 185.02100.00% 2,161.08100.00% 124.71100.00% 1,165.37100.00% 1,089.81100.00% 560.82100.00% 228.13100.00% 7.54100.00% 12,204.19

100.00% 524.36100.00% 350.41100.00% 3.83100.00% 18.81100.00% 14.51100.00% 560.82100.00% 228.13100.00% 7.54100.00% 1,708.41

100.00% 84.27100.00% 229.10100.00% 524.36100.00% 18.81100.00% 14.51100.00% 12.72100.00% 13.46100.00% 472.54100.00% 228.13100.00% 7.54100.00% 1,605.44

100.00% 84.27100.00% 163.61100.00% 523.74100.00% 18.22100.00% 10.66100.00% 4.73100.00% 371.82100.00% 37.94100.00% 5.05100.00% 1,220.04

100.00% 286.08100.00% 186.01100.00% 51.42100.00% 25.19100.00% 188.46100.00% 114.99100.00% 852.15

100.00% 165.17100.00% 51.42100.00% 22.37100.00% 47.12100.00% 286.08

Page 220: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 190

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 247.75100.00% 51.42100.00% 33.56100.00% 76.56100.00% 409.29

100.00% 41.29100.00% 5.59100.00% 40.83100.00% 87.71

100.27% 3,632.97100.28% 213.14100.27% 461.53100.27% 4,307.64

100.27% 3,217.79100.28% 213.14100.27% 411.71100.27% 3,842.64

100.27% 3,405.26100.28% 213.14100.27% 434.21100.27% 4,052.61

100.27% 3,335.93100.28% 213.14100.27% 425.89100.27% 3,974.96

100.27% 2,763.25100.26% 58.62100.27% 338.62100.27% 3,160.49

100.27% 3,224.22100.26% 58.62100.27% 393.94100.27% 3,676.78

100.27% 2,366.48100.26% 58.62100.27% 291.01100.27% 2,716.11

101.64% 90,827.70101.64% 1,290.17

101.35% 1,022.00100.00% 2,479.57100.00% 1,610.04112.04% 4,309.12112.04% 5,300.91100.00% 2,352.90100.00% 2,162.53100.03% 9,131.67100.03% 3,678.44100.00% 3,845.69100.00% 657.43

Page 221: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 191

ANALISIS DE COSTOSINDICE ABR 2010

100.00% 290.44100.00% 163.32100.00% 3,625.12100.00% 190.41100.64% 52,034.50101.63% 91,832.09101.63% 1,304.43

101.15% 1,198.52100.00% 3,306.10100.00% 2,146.72112.04% 4,856.31112.04% 5,300.91100.00% 2,352.90100.00% 2,162.53100.03% 9,131.67100.03% 4,571.26100.00% 3,845.69100.00% 657.43100.00% 290.44100.00% 163.32100.00% 3,625.12100.00% 190.41100.52% 63,568.43101.47% 106,169.24101.47% 1,508.09

101.37% 1,007.73100.27% 10,567.97100.00% 2,061.24112.04% 4,309.12112.04% 5,300.91100.00% 2,352.90100.00% 2,162.53100.03% 9,131.67100.03% 3,285.60100.00% 3,845.69100.00% 657.43100.00% 290.44100.00% 163.32100.00% 3,625.12100.00% 190.41100.64% 51,422.95101.53% 99,367.30101.53% 1,411.47

101.35% 1,022.00100.27% 10,567.97100.00% 2,061.24112.04% 4,309.12112.04% 5,300.91100.00% 2,352.90100.00% 2,162.53100.03% 9,131.67100.03% 3,678.44100.00% 3,845.69100.00% 657.43100.00% 290.44100.00% 163.32100.00% 3,625.12100.00% 190.41100.64% 52,034.50101.52% 100,371.69101.52% 1,425.73

101.33% 1,034.68100.27% 14,090.63100.00% 2,747.00112.04% 4,856.31112.04% 5,300.91100.00% 2,352.90100.00% 2,162.53100.03% 9,131.67100.03% 4,571.26100.00% 3,845.69100.00% 657.43100.00% 290.44100.00% 163.32100.00% 3,625.12100.00% 190.41100.64% 52,034.50101.51% 106,020.12101.51% 1,505.97

101.37% 1,007.73100.00% 1,528.31100.00% 1,546.43112.04% 4,309.12

Page 222: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 192

ANALISIS DE COSTOSINDICE ABR 2010

112.04% 5,300.91100.00% 2,352.90100.00% 2,162.53100.03% 9,131.67100.03% 3,285.60100.00% 3,845.69100.00% 657.43100.00% 290.44100.00% 163.32100.00% 3,625.12100.00% 190.41100.64% 51,422.95101.66% 89,812.83101.66% 1,275.75

101.35% 1,022.00100.00% 1,528.31100.00% 1,546.43112.04% 4,309.12112.04% 5,300.91100.00% 2,352.90100.00% 2,162.53100.03% 9,131.67100.03% 3,678.44100.00% 3,845.69100.00% 657.43100.00% 290.44100.00% 163.32100.00% 3,625.12100.00% 190.41100.64% 52,034.50101.64% 90,817.22101.64% 1,290.02

Page 223: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 193

ANALISIS DE COSTOSINDICE ABR 2010

101.33% 1,034.68100.00% 2,037.74100.00% 2,061.24112.04% 4,856.31112.04% 5,300.91100.00% 2,352.90100.00% 2,162.53100.03% 9,131.67100.03% 4,571.26100.00% 3,845.69100.00% 657.43100.00% 290.44100.00% 163.32100.00% 3,625.12100.00% 190.41100.64% 52,034.50101.67% 93,281.47101.67% 1,325.02

Page 224: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 99

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.

PARTIDA No. I N D I C E PAG.HIPERVINCULO

INSUMOS (TODOS los precios con ITBIS incluido)INACE 50000 ACEROS Y ALAMBRE GALVANIZADO: 1INACE 70000 AGREGADOS, BOTES, ETC.: (Domingo López, Cel. 750-8895) 1INASC 90000 ASCENSORES: 1INBOV 110000 BOVEDILLAS DE "FOAM" 1INBAL 130000 BALAUSTRES Y PASAMANOS: Precios estimados 1INBAÑ 150000 BAÑOS, FREGADEROS , CALENTADORES ELECT. Y ACCESORIOS: 1INBAR 170000 BARRO, PRODUCTOS: 3INBLC 190000 BLOQUES DE CEMENTO: (INDUSTRIAS AGUAYO 533-3161) 3INBLV 210000 BLOQUES DE VIDRIO: 4

INBOM 230000 BOMBAS DE AGUA Y TANQUES DE PRESION : 4INCEM 250000 CEMENTOS, CAL, ADITIVOS, CURADORES, ENDURECEDORES, SELLADORES: 4INCER 270000 CERAMICAS: 4INCEJ 290000 CERRAJERIA: 4

INCOM 310000 COMBUSTIBLES Y LUBRICANTES: 5INDIV 330000 DIVISAS: 5INEBA 350000 EBANISTERIA: 5INELL 370000 ELECTRICIDAD (LAMPARAS Y GLOBOS): 5INELR 390000 ELECTRICIDAD RESIDENCIAL (MATERIALES): 5INELA 410000 ELECTRICIDAD ALTA TENSION (MATERIALES): 6INEQU 430000 EQUIPOS DE CONSTRUCCION: 6INESC 450000 ESCALONES Y MESETAS GRANITO: (Precios sin ITBIS) 7INEST 470000 ESTRUCTURA METALICA Y PUERTA ENROLLABLE: 7INHER 490000 HERRERIA: 7INHOR 510000 HORMIGONES INDUSTRIALES Y VACIADOS: (SINERCON) 8INIMP 530000 IMPERMEABILIZANTES: 8INLAB 550000 LABORATORIO MECANICA DE SUELOS> 8INLAV 570000 LAVADEROS Y VERTEDEROS DE GRANITO: 8INLLA 590000 LLAVES DE PASO, VALVULAS, CHEQUES Y TAPAS CISTERNA: 8

INMAD 610000 MADERAS, CLAVOS, ZINC Y OTROS: 8INMAL 630000 MALLAS CICLONICAS Y ACCESORIOS: 9INMAT 650000 MATERIALES INSTALADOS: 9

INPIE 670000 PIEDRAS EN LAJAS PARA PISOS: 9INPIN 690000 PINTURAS: 9INPIS 710000 PISOS Y ADOQUINES: 9

INPLA 730000 PLANTAS ELECTRICAS: 10INPOZ 750000 POZOS FILTRANTE: 10INPUE 770000 PUERTAS DE ALUMINIO: 10INTIN 790000 TINACOS: 11INTCP 810000 TUBERIAS Y PIEZAS CPVC: 11INTHG 830000 TUBERIAS Y PIEZAS H.G. (HIERRO GALVANIZADO): 11INTDR 850000 TUBERIAS Y PIEZAS PVC DRENAJE: 12INTPR 870000 TUBERIAS Y PIEZAS PVC PRESION: 13INVEN 890000 VENTANAS DE ALUMINIO: 13

RENDI 5000000 RENDIMIENTO DE MATERIALESRENDI 5020000 ACEROS Y ALAMBRES GALVANIZADOS: 15RENDI 5040000 BLOQUES: 16RENDI 5060000 CAL, CEMENTOS, ADITIVOS, CURADORES, ENDURECEDORES, SELLADORES: 16RENDI 5080000 CEMENTO PVC (NUMERO DE JUNTAS POR GL.): 16RENDI 5100000 CEMENTO PVC (NUMERO DE JUNTAS POR KILO): 16RENDI 5120000 CEMENTO PVC (NUMERO DE JUNTAS POR PINTA): 16RENDI 5140000 CLAVOS (CANTIDAD x LIBRA): 16RENDI 5160000 IMPERMEABILIZANTES: 16RENDI 5180000 MATERIALES INSTALADOS: 16RENDI 5200000 PINTURAS: 17RENDI 5220000 PISOS, ADOQUINES Y TABLETAS: 17RENDI 5240000 TEFLON: 17RENDI 5260000 TRANSPORTE BLOQUES / VIAJE 19RENDI 5280000 TRANSPORTE PIEZAS DE GRANITO / VIAJE 19

MANO DE OBRA (Agregar ITBIS en Subcontratos, si no lo incluye)MOAL 6000000 MANO DE OBRA ALBAÑILERIA 20MOAL 6000100 M.O. ALB., ACCESORIOS DE BAÑOS, INST.: 20MOAL 6000200 M.O. ALB., ACERA Y CONTENES: 20MOAL 6000300 M.O. ALB., ADICIONAL P/PLANTA, COLOC.: 20MOAL 6000400 M.O. ALB., BADENES Y COLECTORES: 20MOAL 6000500 M.O. ALB., BLOQUES, COLOCACION 20

Page 225: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 100

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.

PARTIDA No. I N D I C E PAG.HIPERVINCULO

MOAL 6000600 M.O. ALB., DESAGÜES: 20MOAL 6000700 M.O. ALB., EMPAÑETES, TERM. PAREDES Y TECHOS: 20MOAL 6000800 M.O. ALB., ESCALONES: 21MOAL 6000900 M.O. ALB., INST. VENTANAS: (ITBIS incluido por subcontrato) 21MOAL 6001000 M.O. ALB., LABORES VARIAS: 21MOAL 6001100 M.O. ALB., LADRILLOS: 21MOAL 6001200 M.O. ALB., LAVADEROS Y VERT.: 21MOAL 6001300 M.O. ALB., MALLA CICLONICA (ZAB., TUBOS, MALLA, PALOMETAS, ALAMBRE PUAS): 21MOAL 6001400 M.O. ALB., MARMOL: 21MOAL 6001500 M.O. ALB., PIEDRA: 21MOAL 6001600 M.O. ALB., PISOS Y ZOCALOS: 21MOAL 6001700 M.O. ALB., PULIMENTO Y BRILLADO PISOS: (ITBIS incluido por subcontrto) 22MOAL 6001800 M.O. ALB., REGISTROS Y TRAMPA GRASA: 22MOAL 6001900 M.O. ALB., REVESTIMIENTO PAREDES: 22MOAL 6002000 M.O. ALB., SUBIR MATERIALES / PLANTA: 22MOAL 6002100 M.O. ALB., TECHOS, TERMINACION: 23MOAL 6002200 M.O. ALB., VACIADOS: 23MOAL 6002300 M.O. ALB., YESO A TODO COSTO: 23MOCA 6100000 MANO DE OBRA CARPINTERIA: 23MOCA 6100100 M.O. CARPINT., COL. CONICAS Y RED., CONF.: 23MOCA 6100200 M.O. CARPINT., COL. CONICAS Y RED., INST.: 23MOCA 6100300 M.O. CARPINT., COL. CUADRADAS O RECTANG., CONF.: 23MOCA 6100400 M.O. CARPINT., COL. CUADRADAS O RECTANG., INST.: 24MOCA 6100500 M.O. CARPINT., COL., TAPAS, CONF. E INST.: 24MOCA 6100600 M.O. CARPINT., DESENCOFRADOS (AREA CONTACTO FORRO-CONCRETO): 24MOCA 6100700 M.O. CARPINT., ESTRUCT. VARIAS, INST. (HASTA 4 M. ALTURA): 24MOCA 6100800 M.O. CARPINT., FALSO PISO, HECHURA: 24MOCA 6100900 M.O. CARPINT., MUROS, CONF. E INST. MOLDE: 24MOCA 6101000 M.O. CARPINT., OTROS, CONF. E INST. MOLDE: 24MOCA 6101100 M.O. CARPINT., TODO COSTO: (ITBIS incluido por subcontrto) 24MOCA 6101200 M.O. CARPINT., TRABAJOS DE TERMINACION: 25MOCA 6101300 M.O. CARPINT., VIGAS Y DINTELES, CONF. E INST. MOLDE: 25MODE 6200000 MANO DE OBRA DEMOLICIONES: 25MOEB 6300000 MANO DE OBRA EBANISTERIA: 25MOEL 6400000 MANO DE OBRA ELECTRICIDAD: 25MOEL 6400100 M.O. ELECTRICIDAD, CONEXIÓN APARATOS: 25MOEL 6400200 M.O. ELECTRICIDAD, INTERRUPTOR DE SEGURIDAD: 25MOEL 6400300 M.O. ELECTRICIDAD, SALIDAS DE TIMBRES, TELEF. Y CABLE: 26MOEL 6400400 M.O. ELECTRICIDAD, RESIDENCIAS ECONOMICAS EN SERIE : 26MOEL 6400500 M.O. ELECTRICIDAD, SALIDAS EN TUB. EXTERIOR VISIBLE: 26MOEL 6400600 M.O. ELECTRICIDAD, SALIDAS EN TUB. OCULTA: 26MOEL 6400700 M.O. ELECTRICIDAD, SALIDAS TIPO ECONOMICO EN TUB.: 26MOEL 6400800 M.O. ELECTRICIDAD, SALIDAS WATERPROOF Y EXPLOTIONPROOF: 26MOEX 6500000 MANO DE OBRA EXCAVACIONES Y CORTES CON EQUIPO: 26MOJO 6600000 MANO DE OBRA JORNALES DIARIOS: 26MOPI 6700000 MANO DE OBRA PINTURA: 26

MOPL 6800000 MANO DE OBRA PLOMERIA: 26MOPL 6800100 M.O. PLOMERIA, ARRASTRE DOMIC. Y PLUVIAL: 27MOPL 6800200 M.O. PLOMERIA, AUMENTO POR PLANTA EN EDIFICIOS: 27MOPL 6800300 M.O. PLOMERIA, BAJANTE O VENTILACION / PLANTA: 27MOPL 6800400 M.O. PLOMERIA, BOMBA DE AGUA, INST. CIRCUITO COMPLETO: 27MOPL 6800500 M.O. PLOMERIA, BOMBA DE AGUA, SIN EL CIRCUITO: 27MOPL 6800600 M.O. PLOMERIA, CALENTADOR DE AGUA EXCLUSIV.: 27MOPL 6800700 M.O. PLOMERIA, COL. ABASTECER AGUA, COBRE, POR PLANTA: 27MOPL 6800800 M.O. PLOMERIA, COL. ABASTECER AGUA, H.G., POR PLANTA: 27MOPL 6800900 M.O. PLOMERIA, COL. DESAGÜE PLUVIAL, POR PLANTA: 27MOPL 6801000 M.O. PLOMERIA, CONEXION AL SEPTICO Y FILTRANTE: 27MOPL 6801100 M.O. PLOMERIA, DESAGÜE APARATOS, POR SALIDA: 27MOPL 6801200 M.O. PLOMERIA, DESMONTAR APARATOS: 28MOPL 6801300 M.O. PLOMERIA, EMPALME A TUB. AGUA EXIST.: 28MOPL 6801400 M.O. PLOMERIA, EMPALME A TUB. ARRASTRE EXIST.: 28MOPL 6801500 M.O. PLOMERIA, INST. CAJA DE VALVULA: 28MOPL 6801600 M.O. PLOMERIA, INST. HIDRANTE: 28MOPL 6801700 M.O. PLOMERIA, INST. LAVADORA: 28MOPL 6801800 M.O. PLOMERIA, INST. LLAVE PASO Y CHORRO: 28MOPL 6801900 M.O. PLOMERIA, INST. MANGA O NIPLE: 28MOPL 6802000 M.O. PLOMERIA, INST. MEDIDOR DE AGUA: 28MOPL 6802100 M.O. PLOMERIA, INST. NEVERA, BEBEDERO Y FILTRO: 28

Page 226: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 101

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.

PARTIDA No. I N D I C E PAG.HIPERVINCULO

MOPL 6802200 M.O. PLOMERIA, INST. PIEZA ESP., CAMPANA, POR DIAM., C/BOCA: 28MOPL 6802300 M.O. PLOMERIA, INST. PIEZA ESP., GIBAULT, POR DIAM., C/BOCA: 28MOPL 6802400 M.O. PLOMERIA, INST. PIEZA ESP., PVC, POR DIAM., C/BOCA: 28MOPL 6802500 M.O. PLOMERIA, INST. PIEZA ESP., ROSCA, POR DIAM., C/BOCA: 29MOPL 6802600 M.O. PLOMERIA, INST. TINACO DE AGUA: 29MOPL 6802700 M.O. PLOMERIA, INST. TRAMPA GRASA Y CAMARA INSP.: 29MOPL 6802800 M.O. PLOMERIA, INST. VALVULA DE AIRE: 29MOPL 6802900 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, CAMPANA: 29MOPL 6803000 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, PLATILLO: 29MOPL 6803100 M.O. PLOMERIA, INST. VALVULA DE COMPUERTA, ROSCA: 29MOPL 6803200 M.O. PLOMERIA, MONTAR BAÑERA Y DUCHA: 29MOPL 6803300 M.O. PLOMERIA, MONTAR FREGADERO Y LAVAPLATO: 29MOPL 6803400 M.O. PLOMERIA, MONTAR INODORO: 29MOPL 6803500 M.O. PLOMERIA, MONTAR LAVAMANOS Y BIDET: 29MOPL 6803600 M.O. PLOMERIA, MONTAR ORINAL: 30MOPL 6803700 M.O. PLOMERIA, SALIDAS DE AGUA, APARATO SANIT., COBRE: 30MOPL 6803800 M.O. PLOMERIA, SALIDAS DE AGUA, APARATO SANIT., H. G. o PVC: 30MOPL 6803900 M.O. PLOMERIA, TERM. LAVADERO Y VERTEDERO: 30MOPL 6804000 M.O. PLOMERIA, TUB. ALCANTARILLADO SANIT. Y PLUVIAL PROF. HASTA 3.00 M.: 30MOPL 6804100 M.O. PLOMERIA, TUB. ALCANTARILLADO SANIT. Y PLUVIAL PROF. MAYOR DE 3.00 M.: 30MOPL 6804200 M.O. PLOMERIA, TUB. ASBESTO CEMENTO: 30MOPL 6804300 M.O. PLOMERIA, TUB. HIERRO FUNDIDO O ACERO: 30MOPL 6804400 M.O. PLOMERIA, TUB. HIERRO GALV.: 30MOPL 6804500 M.O. PLOMERIA, TUB. PVC: 31

MOVA 6900000 MANO DE OBRA VARILLEROS: 31MOVO 7000000 MANO DE OBRA VARIOS: 31

* 10000000 ANALISIS DE COSTOS (Con ITBIS incluido)*ACE 10010000 A C E R O S 32*BLO 10030000 BLOQUES, MUROS DE 32*BOR 10050000 BORDILLOS DE BLOQUES DE HORM. 34*CAS 10070000 CASETAS DE MATERIALES 34*CON 10090000 CONTEN (TELFORD) 35*DES 10110000 DESAGÜES PLUVIALES 35*EMP 10130000 EMPAÑETES 35*ESC 10150000 ESCALONES 36

*HAANT 10170000 HORM. ARMADO ANTEPECHOS 37*HABAD 10190000 HORM. ARMADO BADENES (TIPO CUNETA) 37*HACOL 10210000 HORM. ARMADO COLUMNAS 38

*HACOLC 10230000 HORM. ARMADO COL. CIRCULARES 45*HACOLA 10250000 HORM. ARMADO COL. DE AMARRE 46

*HADIN 10270000 HORM. ARMADO DINTELES 47*HALOSM 10290000 HORM. ARMADO LOSAS MONOLITICAS 48*HAMUR 10310000 HORM. ARMADO MUROS 49*HARAM 10330000 HORM. ARMADO RAMPAS DE ESCALERAS 52

*HAV 10350000 HORM. ARMADO VIGAS 53*HAVA 10370000 HORM. ARMADO VIGAS AMARRE 59

*HAVUE 10390000 HORM. ARMADO VUELOS (NO CONTINUA DEL FALSO PISO) 59*HAZAPC1 10410000 HORM. ARMADO ZAP. COLUMNAS (1 CAMADA ACERO) 61*HAZAPC2 10430000 HORM. ARMADO ZAP. COLUMNAS (2 CAMADAS ACERO) 64*HAZAPM1 10450000 HORMIGON ARMADO ZAPATAS DE MUROS (1 CAMADA ACERO) 65

*HORIND 10470000 HORMIGONES INDUSTRIALES 66*HORSIM 10490000 HORMIGONES SIMPLES 67

*IMP 10510000 IMPERMEABILIZANTES 68*IEACO 10530000 INSTALACION ELECTRICA: ACOMETIDAS 68*IESAL 10550000 INSTALACION ELECTRICA: SALIDAS Y PANELES 70

*ISASHG 10570000 INST. SANITARIA: APARATOS SANIT., TUB. HG Y M. DE OBRA 72*ISCIS 10590000 INST. SANITARIA: CAMARAS INSP., CISTERNAS, SEPTICOS Y TRAMPAS DE GRASA 80

*ISCISSD 10610000 INST. SANITARIA: CISTERNAS Y SEPTICOS SEGÚN DISEÑO: 82*ISCAMO 10630000 INST. SANITARIA: COLOC. APARATOS SIN ITBIS (SOLO M. O.) 83*MALCIC 10650000 MALLAS CICLONICAS 84

*MOR 10670000 M O R T E R O S 84*MOVTIE 10690000 MOVIMIENTO DE TIERRAS 85

*PIN 10710000 PINTURAS 85*PIS 10730000 PISOS 86

*PORMAD 10750000 PORTAJE DE MADERA 90*REP 10710000 REPLANTEO SEGUN DISEÑO 91*REV 10730000 REVESTIMIENTO EN PAREDES 91

Page 227: Base Datos Precios Unitarios a MayoSIMO 2010 Txt-1

PROPUESTA DEL ARQ. JOSE ALEJ. GARCIA SIMO-M., E-MAIL: [email protected] Pág. 102

5 MAYO 2010 GUIA DE ANALISIS DE COSTOS EDIFICACIONES EN SANTO DOMINGO, REP. DOM.

PARTIDA No. I N D I C E PAG.HIPERVINCULO

*TEC 10750000 TECHOS DE MADERA CON FORRO DE MADERA 92*TERTEC 10770000 TECHOS (TERMINACION) 95

*VEN 10790000 VENTANAS 95*VERBLO 10810000 VERJAS DE BLOQUES DE HORMIGON 96