CALCULO DEL FLETE TERRESTRE Y RURAL SISTEMA DE AGUA POTABL PROYECTO : DESTINO DE TRANSPORTE : OBRA CENTRO ABASTECIMIENTO : SIHUAS FECHA : FEBRERO - 2015 1- DATOS GENERALES A-POR PESO MATERIALES UNIDAD CANTIDAD PESO.UNIT. PESO.TOTAL ALAMBRE NEGRO RECOCIDO # 16 kg 618.06 1.00 618.06 ALAMBRE NEGRO RECOCIDO # 8 kg 135.82 1.00 135.82 CLAVOS PARA MADERA C/C 3" kg 163.04 1.00 163.04 CLAVOS PARA MADERA C/C 2" kg 2.60 1.00 2.60 CAJA DE CONCRETO DE 10"X10" u 7.00 25.00 175.00 BUZON DE CONCRETO 0.80x0.80x0.90 INC. TAPA u 1.00 85.00 85.00 BUZON DE CONCRETO 0.35x0.35m u 22.00 4.00 88.00 CAJA DE DESAGUE DE 12"X24" u 4.00 25.00 100.00 TAPA METALICA DE 0.60X0.60X1/8" u 2.00 4.00 8.00 IMPERMEABILIZANTE Kg 22.30 1.00 22.30 ACERO FY=4200 KG/CM2 kg 10,795.01 1.00 10,795.01 CEMENTO PORTLAND TIPO I (42.5 kg) bls 3,754.18 42.50 159,552.65 MADERA TORNILLO p2 123.83 2.50 309.58 MADERA TORNILLO INC.CORTE P/ENCOFRADO p2 5,517.22 2.50 13,793.06 REGLA DE MADERA p2 126.86 2.50 317.15 MADERA ANDAMIAJE p2 727.73 2.50 1,819.33 MADERA 1" X 2" p2 43.50 2.50 108.75 MADERA 1" X 3" p2 7.40 2.50 18.50 YESO EN BOLSAS DE 25 KG. Bls 89.14 25.00 2,228.50 PESO TOTAL 190,340.33 MATERIALES UNIDAD CANTIDAD VOL./UND.(m3) VOL. PARCIAL TUBERIA PVC SAP PRESION C-10 EC 2"X5m u 17.00 0.0125 0.21 TUBERIA PVC SAP PRESION C-10 C/R. 3/4" X 5m. u 19.00 0.0072 0.14 TUBERIA PVC SAP PRESION C-10 EC DE 1"X5m u 4.00 0.0008 0.00 TUBERIA PVC SAP 4" u 7.00 0.060 0.42 PESO TOTAL 0.77 B-POR VOLUMEN EN AGREGADOS Y OTROS DESCRIPC. UNIDAD AFECTOS IGV SIN IGV ARENA FINA m3 0.00 HORMIGON m3 0.00 AFIRMADO m3 0.00 PIEDRA CHANCADA 1/2"-3/4" m3 0.00 MATERIAL DE PRESTAMO m3 0.00 ARENA GRUESA m3 0.00 VOLUMEN TOTAL 0.00 CAPACIDAD DEL CAMION (M3) 15.00 NUMERO DE VIAJES 0.00 "MEJORAMIENTO DE LA PLAZA DE ARMAS DE HUAYLLABA HUAYLLABAMBA -SIHUAS-ANCASH"

description

Calculo-flete Terrestre Ok

Transcript of Calculo-flete Terrestre Ok

Page 1: Calculo-flete Terrestre Ok

CALCULO DEL FLETE TERRESTRE Y RURAL SISTEMA DE AGUA POTABLE

PROYECTO :

DESTINO DE TRANSPORTE : OBRA

CENTRO ABASTECIMIENTO : SIHUAS

FECHA : FEBRERO - 2015

1- DATOS GENERALES

A-POR PESO

MATERIALES UNIDAD CANTIDAD PESO.UNIT. PESO.TOTAL

ALAMBRE NEGRO RECOCIDO # 16 kg 618.06 1.00 618.06

ALAMBRE NEGRO RECOCIDO # 8 kg 135.82 1.00 135.82

CLAVOS PARA MADERA C/C 3" kg 163.04 1.00 163.04

CLAVOS PARA MADERA C/C 2" kg 2.60 1.00 2.60

CAJA DE CONCRETO DE 10"X10" u 7.00 25.00 175.00

BUZON DE CONCRETO 0.80x0.80x0.90 INC. TAPA u 1.00 85.00 85.00

BUZON DE CONCRETO 0.35x0.35m u 22.00 4.00 88.00

CAJA DE DESAGUE DE 12"X24" u 4.00 25.00 100.00

TAPA METALICA DE 0.60X0.60X1/8" u 2.00 4.00 8.00

IMPERMEABILIZANTE Kg 22.30 1.00 22.30

ACERO FY=4200 KG/CM2 kg 10,795.01 1.00 10,795.01

CEMENTO PORTLAND TIPO I (42.5 kg) bls 3,754.18 42.50 159,552.65

MADERA TORNILLO p2 123.83 2.50 309.58

MADERA TORNILLO INC.CORTE P/ENCOFRADO p2 5,517.22 2.50 13,793.06

REGLA DE MADERA p2 126.86 2.50 317.15

MADERA ANDAMIAJE p2 727.73 2.50 1,819.33

MADERA 1" X 2" p2 43.50 2.50 108.75

MADERA 1" X 3" p2 7.40 2.50 18.50

YESO EN BOLSAS DE 25 KG. Bls 89.14 25.00 2,228.50

PESO TOTAL 190,340.33

MATERIALES UNIDAD CANTIDAD VOL./UND.(m3) VOL. PARCIAL

TUBERIA PVC SAP PRESION C-10 EC 2"X5m u 17.00 0.0125 0.21

TUBERIA PVC SAP PRESION C-10 C/R. 3/4" X 5m. u 19.00 0.0072 0.14

TUBERIA PVC SAP PRESION C-10 EC DE 1"X5m u 4.00 0.0008 0.00

TUBERIA PVC SAP 4" u 7.00 0.060 0.42

PESO TOTAL 0.77

B-POR VOLUMEN

EN AGREGADOS Y OTROS

DESCRIPC. UNIDAD AFECTOS IGV SIN IGV

ARENA FINA m3 0.00

HORMIGON m3 0.00

AFIRMADO m3 0.00

PIEDRA CHANCADA 1/2"-3/4" m3 0.00

MATERIAL DE PRESTAMO m3 0.00

ARENA GRUESA m3 0.00

VOLUMEN TOTAL 0.00

CAPACIDAD DEL CAMION (M3) 15.00

NUMERO DE VIAJES 0.00

"MEJORAMIENTO DE LA PLAZA DE ARMAS DE HUAYLLABAMBA, DISTRITO DE HUAYLLABAMBA -SIHUAS-ANCASH"

Page 2: Calculo-flete Terrestre Ok

REDONDEO 0 ……….(C)

Page 3: Calculo-flete Terrestre Ok

EN TUBERIAS

VOLUMEN TOTAL m3 0.77

CAPACIDAD DEL CAMION (M3) (2.2x5x1.5) m3 15.00

NUMERO DE VIAJES 0.05

REDONDEO 1 ……….(D)

2- FLETE TERRESTRE

UNIDAD DE TRANSPORTE

UNIDAD QUE DA COMPROBANTE UNIDAD QUE NO DA COMPROBANTE

CAPACIDAD DEL CAMION ( M3 ) 15.00 CAPACIDAD DEL CAMION /M3

1,000.00 COSTO POR VIAJE S/.

800.00 COSTO POR VIAJE S/.

10,000.00 CAPACIDAD DEL CAMION / KG

0.10 CAPACIDAD DEL CAMION / KG

DESCRIPCION AFECTO IGV SIN IGV TOTAL

19,034.03

800.00

COSTO TOTAL FLETE TERRESTRE 19,834.03 19,834.03

3- FLETE RURAL

UNIDAD DE TRANSPORTE

UNIDAD QUE DA COMPROBANTE UNIDAD QUE NO DA COMPROBANTE

CAPACIDAD DEL CAMION ( M3 ) CAPACIDAD DEL CAMION /M3

COSTO POR VIAJE S/. 25.00 COSTO POR VIAJE S/.

CAPACIDAD (KG) 45.00 CAPACIDAD DEL CAMION / KG

FLETE POR KG 0.00

DESCRIPCION AFECTO IGV SIN IGV TOTAL

FLETE POR PESO 0.00

FLETE POR VOLUMEN

COSTO TOTAL FLETE RURAL 0.00 0.00

COSTO DEL FLETE TOTAL S/. 19,834.03

COSTO POR VIAJE: DE FERRETERIA A OBRA (S/.)………...(E)

COSTO POR VIAJE: DE CANTERA A OBRA (S/.)…………….(F)

CAPACIDAD DEL CAMION (KG)………………………………….(G)

FLETE POR KG: DE FERRETERIA A OBRA……....…(E)/(G)=(H)

FLETE POR PESO……………………..(A)*(H)

FLETE POR VOLUMEN……………….(C+D)*(F)

Page 4: Calculo-flete Terrestre Ok

CALCULO DEL FLETE TERRESTRE Y RURAL SISTEMA DE AGUA POTABLE

OBRA

SIHUAS

FEBRERO - 2015

……….(A)

……….(B)

"MEJORAMIENTO DE LA PLAZA DE ARMAS DE HUAYLLABAMBA, DISTRITO DE

Page 5: Calculo-flete Terrestre Ok
Page 6: Calculo-flete Terrestre Ok

UNIDAD DE TRANSPORTE

15.00

800.00

500.00

10,000.00

0.08

UNIDAD DE TRANSPORTE