4
PARTIDA: MURO DE LADRILLO CON ASENTADO SOGA UND: UNIDAD CANTIDAD PRECIO CEMENTO BLS 0.408 S/. 19.00 ARENA GRUESA M3 0.058 S/. 40.00 LADRILLO UND 38 S/. 0.52 TOTAL TOTAL M2 METRADO 10 ------------------------------------------------------------------------ ANCHO(M) 4.5 8.43 LARGO(M) 6.5 0.54 AREA(M2) 29.25 0.55 espesor(M) 0.15 ------------------------------------------------------------------------ PARTIDA: PISO UND: UNIDAD CANTIDAD PRECIO CEMENTO BLS 1.2645 S/. 19.00 ARENA GRUESA M3 0.081 S/. 40.00 PIEDRA CHANCADA M3 0.0825 S/. 45.00 TOTAL METRADO 29.25 HACER 28 M2 DE PISO ME CUESTA---------------------- NOTA: Cemento Arena Piedra 175KG/CM2 1:2.3:2.3 8.43 0.54 0.55 210 KG/CM2 1:1.9:1.9 9.73 0.52 0.53

description

Calculo Materiales.obra

Transcript of Calculo Materiales.obra

Page 1: Calculo Materiales.obra

PARTIDA: MURO DE LADRILLO CON ASENTADO SOGA UND: M2

UNIDAD CANTIDAD PRECIO PARCIALCEMENTO BLS 0.408 S/. 19.00 S/. 7.75

ARENA GRUESA M3 0.058 S/. 40.00 S/. 2.32LADRILLO UND 38 S/. 0.52 S/. 19.76

TOTAL S/. 29.83

TOTAL M2METRADO 10 S/. 298.32

------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------ANCHO(M) 4.5 8.43 1.2645LARGO(M) 6.5 0.54 0.081AREA(M2) 29.25 0.55 0.0825

espesor(M) 0.15--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

PARTIDA: PISO UND: M2

UNIDAD CANTIDAD PRECIO PARCIALCEMENTO BLS 1.2645 S/. 19.00 S/. 24.03

ARENA GRUESA M3 0.081 S/. 40.00 S/. 3.24PIEDRA CHANCADA M3 0.0825 S/. 45.00 S/. 3.71

TOTAL S/. 30.98

METRADO 29.25

HACER 28 M2 DE PISO ME CUESTA------------------------------- S/. 906.11

S/. 1,204.43

NOTA:Cemento Arena Piedra Agua

175KG/CM2 1:2.3:2.3 8.43 0.54 0.55 0.185210 KG/CM2 1:1.9:1.9 9.73 0.52 0.53 0.186

Page 2: Calculo Materiales.obra

TOTAL MATERIAL4.08 BLS0.58 M3380 UND

------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

4.3875

--------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------------

TOTAL MATERIAL DEFINIT.TOTAL MATERIAL 42.00 BOLSAS CEMENTO

36.986625 BLS 2.95 M3 ARENA GRUESA2.36925 M3 400.00 UNID LADRILLO

2.413125 M3 2.00 M3 PIEDRA CHANCADA