CRONOGRAMA CONCRETO PREMEZCLADO.xlsx

12
CRONOGRAMA DE REQUERIMIENTO CONCRETO PREMEZCLADO JULIO AGOSTO ITEM DESCRIPCION DE PARTIDA UND CANT. SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M m3 % m3 % m3 % m3 % m3 % m3 % m3 05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84 05.07 LOSAS MACIZAS 2.61 8.33 2.61 8.33 2.61 8.33 05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26 05.08 LOSAS ALIGERADAS 37.54 9.03 37.54 9.03 37.54 9.03 05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90 m3 TOTAL 62.46 62.46 62.46 124.92 124.92 SETIEMBRE OCTUBRE ITEM DESCRIPCION DE PARTIDA UND CANT. SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M m3 % m3 % m3 % m3 % m3 % m3 % m3 05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84 05.07 LOSAS MACIZAS 2.61 8.33 2.61 8.33 2.61 8.33 05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26 05.08 LOSAS ALIGERADAS 37.54 9.03 37.54 9.03 37.54 9.03 05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90 m3 TOTAL 62.46 62.46 62.46 124.92 124.92 NOVIEMBRE DICIEMBRE ITEM DESCRIPCION DE PARTIDA UND CANT. SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M m3 % m3 % m3 % m3 % m3 % m3 % m3 05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84 05.07 LOSAS MACIZAS 2.61 8.33 2.61 8.33 2.61 8.33 05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26 05.08 LOSAS ALIGERADAS 37.54 9.03 37.54 9.03 20.27 4.87 05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90 m3 TOTAL 62.46 62.46 45.20 124.92 90.40 NOTA : EL PRESENTE CRONOGRAMA ES REFERENCIAL YA QUE SE SUJETARA AL VERDADERO REQUERIMIENTO EN OBRA

Transcript of CRONOGRAMA CONCRETO PREMEZCLADO.xlsx

Page 1: CRONOGRAMA CONCRETO PREMEZCLADO.xlsx

CRONOGRAMA DE REQUERIMIENTO CONCRETO PREMEZCLADOJULIO AGOSTO

ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8

D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S

m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %

05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 22.32 8.33

05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84

05.07 LOSAS MACIZAS 2.61 8.33 2.61 8.33 2.61 8.33 2.61 8.33

05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26

05.08 LOSAS ALIGERADAS 37.54 9.03 37.54 9.03 37.54 9.03 37.54 9.03

05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90

m3 TOTAL62.46 62.46 62.46 62.46

124.92 124.92

SETIEMBRE OCTUBRE

ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8

D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S

m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %

05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 22.32 8.33

05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84

05.07 LOSAS MACIZAS 2.61 8.33 2.61 8.33 2.61 8.33 2.61 8.33

05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26

05.08 LOSAS ALIGERADAS 37.54 9.03 37.54 9.03 37.54 9.03 37.54 9.03

05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90

m3 TOTAL62.46 62.46 62.46 62.46

124.92 124.92

NOVIEMBRE DICIEMBRE

ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8

D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S

m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %

05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 22.32 8.33

05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84

05.07 LOSAS MACIZAS 2.61 8.33 2.61 8.33 2.61 8.33 2.61 8.33

05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26

05.08 LOSAS ALIGERADAS 37.54 9.03 37.54 9.03 20.27 4.87 20.27 4.87

05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90

m3 TOTAL62.46 62.46 45.20 45.20

124.92 90.40

NOTA : EL PRESENTE CRONOGRAMA ES REFERENCIAL YA QUE SE SUJETARA AL VERDADERO REQUERIMIENTO EN OBRA

Page 2: CRONOGRAMA CONCRETO PREMEZCLADO.xlsx

CRONOGRAMA DE REQUERIMIENTO CONCRETO PREMEZCLADOSETIEMBRE OCTUBRE

ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8

D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S

m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %

05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33

05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84

05.07 LOSAS MACIZAS 2.61 8.33 2.61 8.33 2.61 0.97

05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26

05.08 LOSAS ALIGERADAS 37.54 9.03 37.54 9.03 37.54 14.01

05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90

m3 TOTAL0.00 62.46 62.46 62.46

62.46 124.92

NOVIEMBRE DICIEMBRE

ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8

D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S

m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %

05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 22.32 8.33

05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84

05.07 LOSAS MACIZAS 2.61 0.97 2.61 8.33 2.61 8.33 2.61 0.97

05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26

05.08 LOSAS ALIGERADAS 37.54 14.01 37.54 9.03 37.54 9.03 37.54 14.01

05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90

m3 TOTAL62.46 62.46 62.46 62.46

124.92 124.92

ENERO FEBRERO

ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8

D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S

m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %

05.06 VIGAS 22.32 8.33 22.32 8.33 22.32 8.33 22.32 8.33

05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84

05.07 LOSAS MACIZAS 2.61 0.97 2.61 8.33 2.61 8.33 2.61 0.97

05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26

05.08 LOSAS ALIGERADAS 37.54 14.01 37.54 9.03 37.54 9.03 20.27 7.57

05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90

m3 TOTAL62.46 62.46 62.46 45.20

124.92 107.66

MARZO ABRIL

ITEM DESCRIPCION DE PARTIDA UNDCANT.SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8

D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S D L M M J V S

m3 % m3 % m3 % m3 % m3 % m3 % m3 % m3 %

05.06 VIGAS 22.32 8.33

05.06.01 CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84

05.07 LOSAS MACIZAS 2.61 8.33

05.07.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZAS m3 31.26

05.08 LOSAS ALIGERADAS 20.27 4.87

05.08.01 CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90

m3 TOTAL45.20

Page 3: CRONOGRAMA CONCRETO PREMEZCLADO.xlsx

m3 TOTAL45.20

NOTA : EL PRESENTE CRONOGRAMA ES REFERENCIAL YA QUE SE SUJETARA AL VERDADERO REQUERIMIENTO EN OBRA

Page 4: CRONOGRAMA CONCRETO PREMEZCLADO.xlsx

CRONOGRAMA DE REQUERIMIENTO CONCRETO PREMEZCLADO

OBRA : MEJORAMIENTO DE LA CAPACIDAD OPERATIVA DEL ARCHIVO REGIONAL PUNO

PROPIETARIO : GOBIERNO REGIONAL DE PUNO

DESCRIPCION DE PARTIDA UNDCANT.

SETIEMBRE OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO

1ra entrega 2da. entrega 3ra. Entrega 4ta. Entrega 5ta. Entrega 6ta. Entrega 7ma. Entrega 8va. Entrega 9na. Entrega 10 ma. Entrega 11 va. Entrega 12 va. Entrega

lunes 16 lunes 01 Jueves 17 Lunes 04 Martes 19 Miercoles 04 Jueves 19 Viernes 03 Jueves 16 Sabado 01 Sabado 15 Lunes 02

VIGAS

CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32

LOSAS MACIZAS

CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZASm3 31.26 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605

LOSAS ALIGERADAS

CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90 34.66 34.66 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658

Page 5: CRONOGRAMA CONCRETO PREMEZCLADO.xlsx

CRONOGRAMA REPROGRAMADO DE REQUERIMIENTO CONCRETO PREMEZCLADO

OBRA : MEJORAMIENTO DE LA CAPACIDAD OPERATIVA DEL ARCHIVO REGIONAL PUNO

PROPIETARIO : GOBIERNO REGIONAL DE PUNO

DESCRIPCION DE PARTIDA UNDCANT.

OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO

1ra entrega 2da. entrega 3ra. Entrega 4ta. Entrega 5ta. Entrega 6ta. Entrega 7ma. Entrega 8va. Entrega 9na. Entrega 10 ma. Entrega 11 va. Entrega 12 va. Entrega

Viernes 04 Lunes 21 Martes 05 Miercoles 20 Jueves 05 Viernes 20 Sabado 04 Lunes 20 Lunes 03 Martes 18 Miercoles 05 Jueves 20

VIGAS

CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32

LOSAS MACIZAS

CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZASm3 31.26 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605

LOSAS ALIGERADAS

CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90 34.66 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.66

Page 6: CRONOGRAMA CONCRETO PREMEZCLADO.xlsx

12 va. Entrega

Page 7: CRONOGRAMA CONCRETO PREMEZCLADO.xlsx

CRONOGRAMA REPROGRAMADO DE REQUERIMIENTO CONCRETO PREMEZCLADO

OBRA : MEJORAMIENTO DE LA CAPACIDAD OPERATIVA DEL ARCHIVO REGIONAL PUNO

PROPIETARIO : GOBIERNO REGIONAL DE PUNO

DESCRIPCION DE PARTIDA UNDCANT.

OCTUBRE NOVIEMBRE DICIEMBRE ENERO FEBRERO MARZO

1ra entrega 2da. entrega 3ra. Entrega 4ta. Entrega 5ta. Entrega 6ta. Entrega 7ma. Entrega 8va. Entrega 9na. Entrega 10 ma. Entrega 11 va. Entrega 12 va. Entrega

VIGAS

CONCRETO F'C= 210 KG/CM2. PARA VIGAS m3 267.84 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32 22.32

LOSAS MACIZAS

CONCRETO F'C= 210 KG/CM2. PARA LOSAS MACIZASm3 31.26 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605 2.605

LOSAS ALIGERADAS

CONCRETO F'C= 210 KG/CM2. PARA LOSAS ALIGERADAS m3 415.90 34.66 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.658 34.66

TOTAL m3 715.00 59.58 59.58 59.58 59.58 59.58 59.58 59.58 59.58 59.58 59.58 59.58 59.58

Page 8: CRONOGRAMA CONCRETO PREMEZCLADO.xlsx

12 va. Entrega