Cronograma de Obra

4
CRONOGRAMA VALORIZADO DE OBRA UBICACIÓN : PUCARA - HUANCAYO - JUNIN FECHA : OCTUBRE DEL 2013 Item Descripción Und Metrado P.U Parcial (S/.) Mes 1 Mes 2 01.00 OBRAS PROVISIONALES 945.87 945.87 0.00 01.01 CARTEL DE OBRA DE 8.60 X 3.50m UNA CARA UND 1.00 945.87 945.87 945.87 02.00 TRABAJOS PRELIMINARES 27,008.67 13,914.82 3,531.29 02.01 LIMPIEZA DE TERRENO MANUAL M2 17,138.10 0.46 7,883.53 7,883.53 02.02 DESVIO DE TRANSITO Y SEÑALIZACION DURANTE LA CONSTRUM2 180.00 5.16 928.80 232.20 232.20 02.03 TRAZO, NIVELES Y REPLANTEO DE VIAS M2 17,138.10 0.77 13,196.34 3,299.09 3,299.09 02.04 MOVILIZACION DE MAQUINARIAS GLB 1.00 5,000.00 5,000.00 2,500.00 03.00 MOVIMIENTO DE TIERRAS 222,741.77 222,741.77 0.00 03.01 EXCAVACION A NIVEL DE SUB RASANTE M3 5,743.96 2.42 13,900.38 13,900.38 03.02 PERFILADO Y COMPACTADO DE LA SUB RAZANTE M2 9,510.96 1.54 14,646.88 14,646.88 03.03 SUB BASE GRANULAR H=0.20 M. M2 9,510.96 5.35 50,883.64 50,883.64 03.04 BASE AFIRMADO E=0.20 M. M2 9,510.96 6.06 57,636.42 57,636.42 03.05 CARGIO Y TRANSPORTE BASE Y SUB BASE M3 3,804.38 6.60 25,108.91 25,108.91 03.06 ELIMINACION DE MATERIAL EXCEDENTE M3 4,536.74 13.35 60,565.54 60,565.54 04.00 PAVIMENTOS FLEXIBLES 374,396.29 0.00 24,300.51 04.01 IMPRIMACION ASFALTICA M2 9,510.96 5.11 48,601.01 24,300.51 04.02 CARPETA ASFALTICA EN CALIENTE E=2" M2 8,569.05 31.96 273,866.84 04.03 SELLADO ASFALTICO M2 8,569.05 6.06 51,928.44 05.00 SARDINEL 83,900.76 0.00 83,900.76 05.01 SARDINEL ENCOFRADO Y DESENCOFRADO M2 1,255.48 20.66 25,938.22 25,938.22 05.02 SARDINEL CONCRETO F'C=175 KG/CM² M3 235.40 246.23 57,962.54 57,962.54 06.00 DRENAJE PLUVIAL 34,270.68 0.00 0.00 06.01 CUNETA ENCOFRADO Y DESENCOFRADO M2 470.81 20.66 9,726.93 06.02 CUNETA CONCRETO F'C=175 KG/CM² M3 94.16 260.66 24,543.75 PROYECTO : “MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. HER CEMENTERIO Y JR. ALEJANDRO O DEUSTUA, DISTRITO DE PUCARA- HUANCAYO-JUNIN”

description

Cronograma de Obra

Transcript of Cronograma de Obra

Hoja3CRONOGRAMA VALORIZADO DE OBRAPROYECTO : MEJORAMIENTO DE VIAS URBANAS, PAVIMENTACION DEL JR. BOLOGNESI, JR. SAN LORENZO, AV. HEROES SICAINOS, AV. CEMENTERIO Y JR. ALEJANDRO O DEUSTUA, DISTRITO DE PUCARA- HUANCAYO-JUNIN

UBICACIN : PUCARA - HUANCAYO - JUNINFECHA : OCTUBRE DEL 2013

ItemDescripcinUndMetradoP.UParcial (S/.)Mes 1Mes 2Mes 3Mes 401.00 OBRAS PROVISIONALES 945.87945.870.000.000.0001.01 CARTEL DE OBRA DE 8.60 X 3.50m UNA CARAUND 1.00945.87945.87945.8702.00 TRABAJOS PRELIMINARES 27,008.6713,914.823,531.293,531.296,031.2902.01 LIMPIEZA DE TERRENO MANUALM2 17,138.100.467,883.537,883.5302.02 DESVIO DE TRANSITO Y SEALIZACION DURANTE LA CONSTRUCCIONM2 180.005.16928.80232.20232.20232.20232.2002.03 TRAZO, NIVELES Y REPLANTEO DE VIASM2 17,138.100.7713,196.343,299.093,299.093,299.093,299.0902.04 MOVILIZACION DE MAQUINARIASGLB 1.005,000.005,000.002,500.002,500.0003.00 MOVIMIENTO DE TIERRAS 222,741.77222,741.770.000.000.0003.01 EXCAVACION A NIVEL DE SUB RASANTEM3 5,743.962.4213,900.3813,900.3803.02 PERFILADO Y COMPACTADO DE LA SUB RAZANTEM2 9,510.961.5414,646.8814,646.8803.03 SUB BASE GRANULAR H=0.20 M.M2 9,510.965.3550,883.6450,883.6403.04 BASE AFIRMADO E=0.20 M.M2 9,510.966.0657,636.4257,636.4203.05 CARGIO Y TRANSPORTE BASE Y SUB BASEM3 3,804.386.6025,108.9125,108.9103.06 ELIMINACION DE MATERIAL EXCEDENTEM3 4,536.7413.3560,565.5460,565.5404.00 PAVIMENTOS FLEXIBLES 374,396.290.0024,300.5124,300.51325,795.2804.01 IMPRIMACION ASFALTICAM2 9,510.965.1148,601.0124,300.5124300.5104.02 CARPETA ASFALTICA EN CALIENTE E=2"M2 8,569.0531.96273,866.84273,866.8404.03 SELLADO ASFALTICOM2 8,569.056.0651,928.4451,928.4405.00 SARDINEL 83,900.760.0083,900.760.000.0005.01 SARDINEL ENCOFRADO Y DESENCOFRADOM2 1,255.4820.6625,938.2225,938.2205.02 SARDINEL CONCRETO F'C=175 KG/CMM3 235.40246.2357,962.5457,962.5406.00 DRENAJE PLUVIAL 34,270.680.000.0034,270.680.0006.01 CUNETA ENCOFRADO Y DESENCOFRADOM2 470.8120.669,726.939,726.9306.02 CUNETA CONCRETO F'C=175 KG/CMM3 94.16260.6624,543.7524,543.7507.00 SEALIZACION HORIZONTAL 4,039.500.000.000.004,039.5007.01 PINTURA ZONAL CRUCE PEATONALM2 90.0021.321,918.801,918.8007.02 PINTURA INTERM. DISCONT.-CENTRO DE VIAML 525.002.741,438.501,438.5007.03 PINTURA DE SIMBOLOS - FLECHASM2 45.0015.16682.20682.20COSTO DIRECTO747,303.54237,602.46111,732.5562,102.47335,866.07GASTOS GENERALES7.00%52,311.2516,632.177,821.284,347.1723,510.62UTILIDAD3.00%22,419.117,128.073,351.981,863.0710,075.98SUBTOTAL822,033.90261,362.70122,905.8168,312.71369,452.67IGV (18%)18.00%147,966.1047,045.2922,123.0512,296.2966,501.49TOTAL PRESUPUESTO970,000.00308,407.99145,028.8680,609.00435,954.16

PORCENTAJE MENSUAL%31.79%14.95%8.31%44.94%PORCENTAJE ACUMULADO%31.79%46.75%55.06%100.00%