PROYECTO: Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02 01 OBRAS PROVISIONALES 01.01 INSTALACION DE CARTEL DE IDENTIFICACION DE OBRA DE 3.60X2.40M und 2.00 1,494.72 2,989.44 S/. 2,989.44 01.02 CASETA DE GUARDIANIA GLB 1.00 1,000.00 1,000.00 S/. 1,000.00 01.03 CAMPAMENTO Y ALMACEN PROVISIONAL m2 100.00 48.97 4,897.00 S/. 4,897.00 01.04 VESTUARIO DE PERSONAL OBRERO m2 20.00 89.46 1,789.20 S/. 1,000.00 S/. 789.20 01.05 SERVICIOS HIGIENICOS PORTATILES MES 2.00 720.00 1,440.00 S/. 1,440.00 02 TRABAJOS PRELIMINARES 02.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE MAQUINARIA, EQUIPOS Y HERRAMIENTAS GLB 1.00 6,000.00 6,000.00 S/. 4,000.00 S/. 2,000.00 02.02 TRAZO Y REPLANTEO KM 16.04 466.08 7,475.92 S/. 3,000.00 S/. 4,475.92 03 MOVIMIENTO DE TIERRAS 03.01 CORTE HASTA NIVEL DE SUB-RASANTE E=0.20M m3 19,248.31 2.18 41,961.32 S/. 20,000.00 S/. 21,961.32 03.02 PERFILADO Y COMPACTADO DE SUBRASANTE m2 96,241.56 0.65 62,557.01 S/. 30,000.00 S/. 32,557.01 03.03 ELIMINACION DE MATERIAL EXCEDENTE A BOTADERO m3 23,097.97 4.66 107,636.54 S/. 55,000.00 S/. 52,636.54 04 PAVIMENTOS 04.01 ZARANDEO MECANICO DE MATERIAL m3 19,248.31 0.95 18,285.89 S/. 10,000.00 S/. 8,285.89 04.02 CARGUIO DE MATERIAL GRANULAR m3 19,248.31 0.87 16,746.03 S/. 8,000.00 S/. 8,746.03 04.03 TRANSPORTE DE MATERIAL GRANULAR m3 19,248.31 17.30 332,995.76 S/. 100,000.00 S/. 232,995.76 04.04 HORMIGON e=0.20 m PARA BASE C/EQUIPO m2 96,241.56 8.73 840,188.82 S/. 300,000.00 S/. 540,188.82 05 BADENES 05.01 TRABAJOS PRELIMINARES 05.01.01 TRAZO Y REPLANTEO DE OBRAS DE ARTE m2 540.00 1.91 1,031.40 S/. 500.00 S/. 531.40 05.02 MOVIMIENTO DE TIERRAS 05.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS MANUAL m3 54.00 28.44 1,535.76 S/. 800.00 S/. 735.76 05.02.02 ELIMINACION DE MATERIAL EXCEDENTE A BOTADERO m3 64.80 4.66 301.97 S/. 101.97 S/. 200.00 05.03 CONCRETO SIMPLE 05.03.01 ENCOFRADO Y DESENCOFRADO-BADEN m2 25.20 29.36 739.87 S/. 739.87 05.03.02 EMBOQUILLADO DE PIEDRA + CONCRETO F'C=140KG/CM2, E=0.20M PARA BADEN m3 108.00 144.39 15,594.12 S/. 15,594.12 06 MITIGACION AL IMPACTO AMBIENTAL 06.01 PREPARACION Y RESTAURACION DE CANTERA 06.01.01 REMOCION DE TERRENO VEGETAL m2 1,500.00 0.58 870.00 S/. 400.00 S/. 470.00 06.01.02 MANEJO DE RESIDUOS m2 100.00 9.69 969.00 S/. 400.00 S/. 569.00 06.01.03 SIEMBRA DE PLANTONES und 100.00 0.33 33.00 S/. 33.00 07 PROGRAMA DE ABANDONO 07.01 PROGRAMA DE SEÑALIZACIÓN AMBIENTAL GLB 1.00 10,500.00 10,500.00 S/. 5,000.00 S/. 5,500.00 07.02 PROGRAMA DE REVEGETACION GLB 1.00 1,600.00 1,600.00 S/. 500.00 S/. 1,100.00 07.03 PROGRAMA DE EDUCACIÓN AMBIENTAL GLB 1.00 1,600.00 1,600.00 S/. 650.00 S/. 950.00 08 SEGURIDAD Y SALUD 08.01 EQUIPOS DE PROTECCION INDIVIDUAL und 1.00 116.00 116.00 S/. 116.00 08.02 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 930.00 930.00 S/. 600.00 S/. 330.00 08.03 CAPACITACION EN SEGURIDAD Y SALUD GLB 1.00 366.30 366.30 S/. 236.00 S/. 130.30 COSTO DIRECTO 1,482,150.35 550,630.41 931,519.94 37.15% 62.85% 37.15% 100.00% AVANCE ACTUAL PROGRAMADO AVANCE ACUMULADO PROGRAMADO CRONOGRAMA VALORIZADO MEJORAMIENTO DEL CAMINO VECINAL LA VICTORIA, TIERRA RAJADA, LA FLORIDA, GUAYAQUIL Y REDONDO, DISTRITO DE OLMOS, LAMBAYEQUE, LAMBAYEQUE.

description

CRON_VALORIZ

Transcript of cronograma valorizado

Page 1: cronograma valorizado

PROYECTO:

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) MES 01 MES 02

01 OBRAS PROVISIONALES

01.01 INSTALACION DE CARTEL DE IDENTIFICACION DE OBRA DE 3.60X2.40M und 2.00 1,494.72 2,989.44 S/. 2,989.44

01.02 CASETA DE GUARDIANIA GLB 1.00 1,000.00 1,000.00 S/. 1,000.00

01.03 CAMPAMENTO Y ALMACEN PROVISIONAL m2 100.00 48.97 4,897.00 S/. 4,897.00

01.04 VESTUARIO DE PERSONAL OBRERO m2 20.00 89.46 1,789.20 S/. 1,000.00 S/. 789.20

01.05 SERVICIOS HIGIENICOS PORTATILES MES 2.00 720.00 1,440.00 S/. 1,440.00

02 TRABAJOS PRELIMINARES

02.01 MOVILIZACIÓN Y DESMOVILIZACIÓN DE MAQUINARIA, EQUIPOS Y HERRAMIENTAS GLB 1.00 6,000.00 6,000.00 S/. 4,000.00 S/. 2,000.00

02.02 TRAZO Y REPLANTEO KM 16.04 466.08 7,475.92 S/. 3,000.00 S/. 4,475.92

03 MOVIMIENTO DE TIERRAS

03.01 CORTE HASTA NIVEL DE SUB-RASANTE E=0.20M m3 19,248.31 2.18 41,961.32 S/. 20,000.00 S/. 21,961.32

03.02 PERFILADO Y COMPACTADO DE SUBRASANTE m2 96,241.56 0.65 62,557.01 S/. 30,000.00 S/. 32,557.01

03.03 ELIMINACION DE MATERIAL EXCEDENTE A BOTADERO m3 23,097.97 4.66 107,636.54 S/. 55,000.00 S/. 52,636.54

04 PAVIMENTOS

04.01 ZARANDEO MECANICO DE MATERIAL m3 19,248.31 0.95 18,285.89 S/. 10,000.00 S/. 8,285.89

04.02 CARGUIO DE MATERIAL GRANULAR m3 19,248.31 0.87 16,746.03 S/. 8,000.00 S/. 8,746.03

04.03 TRANSPORTE DE MATERIAL GRANULAR m3 19,248.31 17.30 332,995.76 S/. 100,000.00 S/. 232,995.76

04.04 HORMIGON e=0.20 m PARA BASE C/EQUIPO m2 96,241.56 8.73 840,188.82 S/. 300,000.00 S/. 540,188.82

05 BADENES

05.01 TRABAJOS PRELIMINARES

05.01.01 TRAZO Y REPLANTEO DE OBRAS DE ARTE m2 540.00 1.91 1,031.40 S/. 500.00 S/. 531.40

05.02 MOVIMIENTO DE TIERRAS

05.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS MANUAL m3 54.00 28.44 1,535.76 S/. 800.00 S/. 735.76

05.02.02 ELIMINACION DE MATERIAL EXCEDENTE A BOTADERO m3 64.80 4.66 301.97 S/. 101.97 S/. 200.00

05.03 CONCRETO SIMPLE

05.03.01 ENCOFRADO Y DESENCOFRADO-BADEN m2 25.20 29.36 739.87 S/. 739.87

05.03.02 EMBOQUILLADO DE PIEDRA + CONCRETO F'C=140KG/CM2, E=0.20M PARA BADEN m3 108.00 144.39 15,594.12 S/. 15,594.12

06 MITIGACION AL IMPACTO AMBIENTAL

06.01 PREPARACION Y RESTAURACION DE CANTERA

06.01.01 REMOCION DE TERRENO VEGETAL m2 1,500.00 0.58 870.00 S/. 400.00 S/. 470.00

06.01.02 MANEJO DE RESIDUOS m2 100.00 9.69 969.00 S/. 400.00 S/. 569.00

06.01.03 SIEMBRA DE PLANTONES und 100.00 0.33 33.00 S/. 33.00

07 PROGRAMA DE ABANDONO

07.01 PROGRAMA DE SEÑALIZACIÓN AMBIENTAL GLB 1.00 10,500.00 10,500.00 S/. 5,000.00 S/. 5,500.00

07.02 PROGRAMA DE REVEGETACION GLB 1.00 1,600.00 1,600.00 S/. 500.00 S/. 1,100.00

07.03 PROGRAMA DE EDUCACIÓN AMBIENTAL GLB 1.00 1,600.00 1,600.00 S/. 650.00 S/. 950.00

08 SEGURIDAD Y SALUD

08.01 EQUIPOS DE PROTECCION INDIVIDUAL und 1.00 116.00 116.00 S/. 116.00

08.02 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 930.00 930.00 S/. 600.00 S/. 330.00

08.03 CAPACITACION EN SEGURIDAD Y SALUD GLB 1.00 366.30 366.30 S/. 236.00 S/. 130.30

COSTO DIRECTO 1,482,150.35 550,630.41 931,519.94

37.15% 62.85%

37.15% 100.00%

AVANCE ACTUAL PROGRAMADO