Page 1: CRONOGRAMA VALORIZADO

PUENTE SAMUELITO L=10m.OBRAS PROVISIONALES, TRABAJOS PRELIMINARES

OBRAS PRELIMINARESALMACEN, OFICINA, CASETA DE GUARDIANIA Y SS. HH. S/. 3,000.00 S/. 3,000.00DESBROCE Y LIMPIEZA S/. 562.13 S/. 562.13MOVILIZACION Y DESMOVILIZACION DE EQUIPO S/. 5,000.00 S/. 5,000.00TRANQUERAS DE MADERA 1.20X1.10M P/DESVIO TRANSITO VEHICULAR S/. 452.56 S/. 452.56

TRABAJOS PRELIMINARESLIMPIEZA DE TERRENO MANUAL S/. 55.63 S/. 55.63TRANSPORTE DE MATERIALES, EQUIPOS Y HERRAMIENTAS S/. 5,000.00 S/. 5,000.00ELIMINACION DE MATERIAL DE DESBROCE D= 5Km. S/. 876.07 S/. 876.07CARTEL DE OBRA (3.60 x 2.40) BANNER INC. MATERIALES S/. 748.39 S/. 748.39MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL PERMANENTE S/. 4,000.00 S/. 4,000.00

PLAN DE SEGURIDAD Y SALUD DE OBRAIMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO S/. 2,000.00 S/. 2,000.00EQUIPOS DE PROTECCIÓN INDIVIDUAL S/. 3,000.00 S/. 3,000.00EQUIPOS DE PROTECCIÓN COLECTIVA S/. 2,000.00 S/. 2,000.00SEÑALIZACIÓN TEMPORAL DE SEGURIDAD S/. 2,500.00 S/. 2,500.00CAPACITACIÓN EN SEGURIDAD Y SALUD S/. 1,500.00 S/. 1,500.00RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SALUD DURANTE EL TRABAJO S/. 1,810.17 S/. 589.83 S/. 2,400.00

SUB ESTRUCTURAESTRIBOS

MOVIMIENTO DE TIERRAS EN ESTRIBOTRAZO NIVELACION Y REPLANTEO 3 ETAPAS (EXCAVACIÓN, RELLENO, AFIRMADO) S/. 750.00 S/. 750.00CORTE DE TERRENO C/EQUIPO PESADO (Zona Selva Baja) S/. 10,917.01 S/. 10,917.01EXCAVACION PARA ESTRUCTURAS EN LECHO DE RIO S/. 1,444.95 S/. 1,444.95RELLENO COMPAC. C/EQUIPO LIVIANO DE ZANJA C/MATERIAL PROPIO @ 0.30m. S/. 1,773.82 S/. 1,773.82RELLENO COMPAC. C/EQUIPO LIVIANO DE ZANJA C/MATERIAL PRESTAMO COMPACTADO @ 0.30m. S/. 10,882.84 S/. 10,882.84ELIMINACION DE MATERIAL EXCEDENTE D= 5Km. S/. 2,638.04 S/. 2,638.04

CONCRETO ARMADOSOLADO DE CONCRETO F'C=100 KG/CM2. E=0.10 M. S/. 3,280.80 S/. 3,280.80CONCRETO EN ESTRIBOS BAJO AGUA F'c= 210 Kg/Cm2 . S/. 15,098.15 S/. 15,098.15CONCRETO EN ESTRIBOS EN CONDICIONES SECAS F'c= 210 Kg/Cm2 . S/. 32,278.51 S/. 32,278.51ENCOFRADO Y DESENCOFRADO ESTRIBOS. S/. 22,214.79 S/. 22,214.79ACERO GRADO 60 Fy=4200 Kg/cm2 S/. 41,950.75 S/. 41,950.75CURADO DE CONCRETO C/ADITIVO S/. 2,470.36 S/. 2,470.36

MOVIMIENTO DE TIERRAS EN ACCESOSCORTE DE TERRENO C/EQUIPO PESADO S/. 280.76 S/. 280.76ELIMINACION DE MATERIAL EXCEDENTE D= 5Km. S/. 2,600.64 S/. 2,600.64CONFORMACION DE TALUD Y/O RELLENO COMP. C/MATERIAL DE PRESTAMO (CBR>10%) C/ EQUIPO PESADO PARA SUB RASANTE S/. 15,523.58 S/. 15,523.58CONFORMACION DE TALUD Y/O RELLENO COMP. C/MATERIAL PROPIO (CBR>10%) C/ EQUIPO PESADO PARA SUB RASANTE S/. 15,126.90 S/. 15,126.90AFIRMADO DE 0.20 M. HORMIGON : TIERRA 80%:20% C/EQUIPO PESADO S/. 5,336.76 S/. 5,336.76

SUPER ESTRUCTURAVIGAS PRINCIPALES Y VIGAS DIAFRAGMA

CONCRETO ARMADO EN VIGASCONCRETO EN VIGAS F'C= 210 KG/CM2 . S/. 3,336.97 S/. 3,336.97ENCOFRADO Y DESENCOFRADO EN VIGAS ( VIGA PRINCIP. Y DIAFRAGMA) S/. 3,688.31 S/. 3,688.31ACERO GRADO 60 Fy=4200 Kg/cm2 S/. 8,238.78 S/. 8,238.78CURADO DE CONCRETO C/ADITIVO S/. 319.50 S/. 319.50

CONCRETO EN LOSA Y VEREDACONCRETO EN LOSA F'C= 210 KG/CM2 . S/. 4,145.15 S/. 4,145.15ENCOFRADO Y DESENCOFRADO EN LOSA DE PUENTE Y VEREDAS S/. 3,543.11 S/. 3,543.11ACERO GRADO 60 Fy=4200 Kg/cm2 S/. 6,083.25 S/. 6,083.25CURADO DE CONCRETO C/ADITIVO S/. 333.20 S/. 333.20

FALSO PUENTEEXCAVACION PARA ESTRUCTURAS BAJO AGUA S/. 44.26 S/. 44.26CONCRETO CICLOPEO EN FALSO PUENTE FC=140KG/CM2 + 30 % PM. S/. 5,614.45 S/. 5,614.45

Totalmes 1 mes 2 mes 3

"ESTUDIO DE FACTIBILIDAD PARA RECONSTRUCCION DEL PUENTE SAMUELITO INGRESO AL LOTE 31C PLANTA DE GAS - CURIMANA, DISTRITO DE CURIMANA, PROVINCIA DE PADRE ABAD -REGION UCAYALI"

Página 1

Page 2: CRONOGRAMA VALORIZADO

TRONCOS DE MADERA, L=3.40m a L= 4.70m, DIAM. >= 0.65 m S/. 8,660.00 S/. 8,660.00ENTABLADO DE MADERA 3"x10"x14' S/. 1,900.41 S/. 220.69 S/. 2,121.10

OBRAS COMPLEMENTARIAS DE PUENTEAPOYO DE NEOPRENO S/. 4,471.96 S/. 4,471.96JUNTA DE DILATACION METALICA S/. 4,389.22 S/. 4,389.22ACABADO DE VEREDA S/. 308.40 S/. 308.40DRENAJE TUBO PVC DE D=3" S/. 174.00 S/. 174.00BARANDA METALICA S/. 4,313.80 S/. 4,313.80

SEÑALIZACIÓNSEÑALIZACION VERTICAL S/. 1,339.82 S/. 1,339.82

PLAN DE MANEJO AMBIENTALPROGRAMA DE PREVENCION O MITIGACION

PROGRAMA DE RIESGO PERMANENTE EN OBRAPLAN DE CONTINGENCIAS S/. 1,000.00 S/. 1,000.00SEÑALIZACION DE SEGURIDAD S/. 400.00 S/. 400.00

PROGRAMA DE MONITOREOMITIGACION DE RUIDOS S/. 2,000.00 S/. 2,000.00CALIDAD DEL AGUA S/. 1,500.00 S/. 1,500.00CALIDAD DE AIRE (GASES, MATERIAL PARTICULADO) S/. 1,500.00 S/. 1,500.00

PROGRAMA DE MANEJO DE RESIDUOS SOLIDOSIMPLEMENTACION DE UN PROGRAMA DE MANEJO DE RR.SS (ESCOMBROS, MATERIALES REUTIZABLES, MATERIAL RECICLABLE, ETC) S/. 2,000.00 S/. 2,000.00TACHOS DE BASURA S/. 320.00 S/. 320.00

PROGRAMA DE ABANDONORECUPERACION DE AREAS UTILIZADAS S/. 1,200.00 S/. 1,200.00

VARIOSLIMPIEZA DE TERRENO C/EQUIPO PESADO S/. 1,218.00 S/. 1,218.00FIN DE OBRA

Total S/. 187,849.39 S/. 102,077.33 S/. 289,926.72

Totalmes 1 mes 2 mes 3

"ESTUDIO DE FACTIBILIDAD PARA RECONSTRUCCION DEL PUENTE SAMUELITO INGRESO AL LOTE 31C PLANTA DE GAS - CURIMANA, DISTRITO DE CURIMANA, PROVINCIA DE PADRE ABAD -REGION UCAYALI"