PROYECTO: AMPLIACIÓN Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE DE LA LOCALIDAD DE ATASPAYA, DISTRITO DE CARUMAS - MARISCAL NIETO - MOQUEGUA FECHA: ABRIL 2011 S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. % 01 OBRAS PROVISIONALES S/. 5,875.32 5,875.32 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M S/. 1,118.52 1,118.52 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 01.02 CAMPAMENTO P/OFICINA, GUARDIANIA Y/O DEPOSITO S/. 4,756.80 4,756.80 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 02 TRABAJOS PRELIMINARES S/. 8,306.27 8,306.27 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS S/. 206.27 206.27 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 02.02 TRANSPORTE DE MATERIALES S/. 8,100.00 8,100.00 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03 LINEA DE CONDUCCION S/. 843,389.05 45,819.22 5.43% 87,137.59 10.33% 162,885.10 19.31% 175,806.88 20.85% 171,265.71 20.31% 142,257.54 16.87% 5,239.30 0.62% 2,498.75 0.30% 29,634.87 3.51% 20,844.08 2.47% 03.01 TRABAJOS PRELIMINARES S/. 10,997.22 10,997.22 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.01.01 TRAZO DE NIVELES Y REPLANTEO S/. 10,997.22 10,997.22 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.02 MOVIMIENTO DE TIERRAS S/. 596,194.65 34,822.00 5.84% 87,137.59 14.62% 91,895.82 15.41% 132,740.64 22.26% 136,387.89 22.88% 113,210.71 18.99% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.02.01 EXCAVACION DE ZANJAS HMAX <=2.00 M TERRERNO NATURAL S/. 82,722.49 31,927.98 38.60% 37,733.07 45.61% 13,061.45 15.79% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.02.02 EXCAVACION DE ZANJAS HMAX <=2.00 M TERRERNO SEMIROCOSO S/. 107,078.81 2,894.02 2.70% 37,622.28 35.14% 39,069.30 36.49% 27,493.21 25.68% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.02.03 EXCAVACION DE ZANJA, TERRENO ROCOSO, TUBERIA 2" S/. 59,290.76 0.00% 0.00% 0.00% 51,879.42 87.50% 7,411.35 12.50% 0.00% 0.00% 0.00% 0.00% 0.00% 03.02.04 PERFILADO DE FONDO DE ZANJAS S/. 6,864.51 0.00% 0.00% 0.00% 6,406.88 93.33% 457.63 6.67% 0.00% 0.00% 0.00% 0.00% 0.00% 03.02.05 CAMA DE APOYO CON MATERIAL DE PRESTAMO S/. 53,655.24 0.00% 0.00% 0.00% 0.00% 0.00% 53,655.24 ####### 0.00% 0.00% 0.00% 0.00% 03.02.06 ZARANDEADO MANUAL DE MATERIAL PROPIO PARA RELLENO S/. 129,604.69 0.00% 11,782.24 9.09% 39,765.08 30.68% 38,292.29 29.55% 35,346.73 27.27% 4,418.34 3.41% 0.00% 0.00% 0.00% 0.00% 03.02.07 RELLENO CON MATERIAL PROPIO SELECCIONADO S/. 113,720.32 0.00% 0.00% 0.00% 0.00% 58,583.20 51.52% 55,137.12 48.48% 0.00% 0.00% 0.00% 0.00% 03.02.08 ACARREO DE MATERIAL EXCEDENTE D=500 M S/. 26,006.53 0.00% 0.00% 0.00% 8,668.84 33.33% 17,337.69 66.67% 0.00% 0.00% 0.00% 0.00% 0.00% 03.02.09 ELIMINACION DE EXCESO CON MAQUINARIA S/. 17,251.30 0.00% 0.00% 0.00% 0.00% 17,251.30 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.03 SUMINISTRO E INSTALACION DE TUBERIAS S/. 120,708.63 0.00 0.00% 0.00 0.00% 70,989.28 58.81% 34,156.40 28.30% 15,562.95 12.89% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 2" C-10 S/. 96,803.57 0.00% 0.00% 70,989.28 73.33% 25,814.29 26.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.03.02 SUMINISTRO E INSTALACION DE TUBERIA D=3" FIERRO GALVANIZADO S/. 2,891.26 0.00% 0.00% 0.00% 2,891.26 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.03.03 PRUEBA HIDRAULICA EN TUBERIA PVC AGUA S/. 7,494.92 0.00% 0.00% 0.00% 5,450.85 72.73% 2,044.07 27.27% 0.00% 0.00% 0.00% 0.00% 0.00% 03.03.04 PRUEBA DESINFECCION DE TUBERIA S/. 13,518.88 0.00% 0.00% 0.00% 0.00% 13,518.88 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.04 SUMINISTRO E INSTALACION DE ACCESORIOS S/. 5,026.28 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,026.28 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.04.01 SUMINISTRO E INST. DE CODO 90º PVC SAP 2" S/. 159.39 0.00% 0.00% 0.00% 159.39 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.04.02 SUMINISTRO E INST. DE CODO 45º PVC SAP 2" S/. 950.11 0.00% 0.00% 0.00% 950.11 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.04.03 SUMINISTRO E INST. DE CODO 22.5º PVC SAP 2" S/. 2,132.90 0.00% 0.00% 0.00% 2,132.90 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.04.04 SUMINISTRO E INST. DE CODO 11.25º PVC SAP 2" S/. 1,783.88 0.00% 0.00% 0.00% 1,783.88 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.05 VALVULAS Y ACCESORIOS S/. 345.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 345.84 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.05.01 CAJA PARA VALVULA DE FºFº CON TAPA S/. 155.26 0.00% 0.00% 0.00% 155.26 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.05.02 VALVULA COMPUERTA DE 2" S/. 190.58 0.00% 0.00% 0.00% 190.58 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.06 CAMARA DE REPARTO S/. 3,587.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,234.22 34.40% 2,353.59 65.60% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.06.01 TRABAJOS PRELIMINARES S/. 20.35 0.00 0.00% 0.00 0.00% 0.00 0.00% 20.35 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.06.01.01 TRAZO DE NIVELES Y REPLANTEO S/. 20.35 0.00% 0.00% 0.00% 20.35 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.06.02 MOVI MIENTO DE TIERRAS S/. 738.57 0.00 0.00% 0.00 0.00% 0.00 0.00% 428.52 58.02% 310.05 41.98% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.06.02.01 EXCAVACION PARA CIMENTACION DE CAMARA S/. 428.52 0.00% 0.00% 0.00% 428.52 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.06.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO S/. 310.05 0.00% 0.00% 0.00% 0.00% 310.05 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.06.03 CONCRETO SIMPLE S/. 72.22 0.00 0.00% 0.00 0.00% 0.00 0.00% 72.22 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.06.03.01 SOLADO E=2" MEZCLA 1:10 C:H INC. CURADO S/. 72.22 0.00% 0.00% 0.00% 72.22 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.06.04 CONCRETO ARMADO S/. 1,511.14 0.00 0.00% 0.00 0.00% 0.00 0.00% 713.13 47.19% 798.02 52.81% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.06.04.01 CONCRETO F'C= 175 KG/CM2 EN CAMARA S/. 477.01 0.00% 0.00% 0.00% 0.00% 477.01 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.06.04.02 ENCOFRADO Y DESENCOF MUROS S/. 642.01 0.00% 0.00% 0.00% 321.01 50.00% 321.01 50.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.06.04.03 ACERO DE REFUERZO FY=4200 Kg/cm2 S/. 392.12 0.00% 0.00% 0.00% 392.12 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.06.05 REVOQUES ENLUCIDOS Y MOLDURAS S/. 427.87 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 427.87 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.06.05.01 TARRAJEO MEZCLA 1:5 S/. 427.87 0.00% 0.00% 0.00% 0.00% 427.87 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.06.06 SUMINISTRO E INSTALACION DE ACCESORIOS S/. 817.65 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 817.65 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.06.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CAMARA DE REPARTO S/. 495.83 0.00% 0.00% 0.00% 0.00% 495.83 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.06.06.02 TAPA DE FºGº ESTRIADA DE 0.60 x 0.60 S/. 178.10 0.00% 0.00% 0.00% 0.00% 178.10 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.06.06.03 TAPA DE FºGº ESTRIADA DE 0.40 x 0.40 S/. 143.72 0.00% 0.00% 0.00% 0.00% 143.72 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.07 CAMARA ROMPE PRESION S/. 50,164.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,923.75 3.83% 16,961.28 33.81% 28,870.56 57.55% 2,409.25 4.80% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.07.01 TRABAJOS PRELIMINARES S/. 267.34 0.00 0.00% 0.00 0.00% 0.00 0.00% 267.34 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.07.01.01 TRAZO DE NIVELES Y REPLANTEO S/. 267.34 0.00% 0.00% 0.00% 267.34 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.07.02 MOVI MIENTO DE TIERRAS S/. 9,647.20 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,656.41 17.17% 3,975.37 41.21% 1,606.17 16.65% 2,409.25 24.97% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.07.02.01 EXCAVACION PARA CIMENTACION DE CAMARA S/. 5,631.78 0.00% 0.00% 0.00% 1,656.41 29.41% 3,975.37 70.59% 0.00% 0.00% 0.00% 0.00% 0.00% 03.07.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO S/. 4,015.42 0.00% 0.00% 0.00% 0.00% 0.00% 1,606.17 40.00% 2,409.25 60.00% 0.00% 0.00% 0.00% 03.07.03 CONCRETO ARMADO S/. 22,618.28 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 12,985.91 57.41% 9,632.37 42.59% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.07.03.01 CONCRETO F'C= 175 KG/CM2 EN CAMARA S/. 7,266.54 0.00% 0.00% 0.00% 0.00% 0.00% 7,266.54 ####### 0.00% 0.00% 0.00% 0.00% 03.07.03.02 ENCOFRADO Y DESENCOF MUROS S/. 10,646.25 0.00% 0.00% 0.00% 0.00% 8,280.42 77.78% 2,365.83 22.22% 0.00% 0.00% 0.00% 0.00% 03.07.03.03 ACERO DE REFUERZO FY=4200 Kg/cm2 S/. 4,705.49 0.00% 0.00% 0.00% 0.00% 4,705.49 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 03.07.04 REVOQUES ENLUCIDOS Y MOLDURAS S/. 6,680.22 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 6,680.22 ####### 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 03.07.04.01 TARRAJEO MEZCLA 1:5 S/. 6,680.22 0.00% 0.00% 0.00% 0.00% 0.00% 6,680.22 ####### 0.00% 0.00% 0.00% 0.00% 03.07.05 SUMINISTRO E INSTALACION DE ACCESORIOS S/. 10,951.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 10,951.80 ####### 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% DESCRIPCION ITEM UND CANTIDAD MES 01 CRONOGRAMA VALORIZADO DE OBRA MES 09 MES 10 MES 02 MES 03 MES 04 MES 08 MES 05 MES 06 MES 07

Transcript of cronograma valorizado FINAL.pdf

Page 1: cronograma valorizado FINAL.pdf

PROYECTO: AMPLIACIÓN Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE DE LA LOCALIDAD DE ATASPAYA, DISTRITO DE CARUMAS - MARISCAL NIETO - MOQUEGUAFECHA: ABRIL 2011

S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. %

01 OBRAS PROVISIONALES S/. 5,875.32 5,875.32 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M S/. 1,118.52 1,118.52 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

01.02 CAMPAMENTO P/OFICINA, GUARDIANIA Y/O DEPOSITO S/. 4,756.80 4,756.80 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

02 TRABAJOS PRELIMINARES S/. 8,306.27 8,306.27 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS S/. 206.27 206.27 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

02.02 TRANSPORTE DE MATERIALES S/. 8,100.00 8,100.00 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03 LINEA DE CONDUCCION S/. 843,389.05 45,819.22 5.43% 87,137.59 10.33% 162,885.10 19.31% 175,806.88 20.85% 171,265.71 20.31% 142,257.54 16.87% 5,239.30 0.62% 2,498.75 0.30% 29,634.87 3.51% 20,844.08 2.47%

03.01 TRABAJOS PRELIMINARES S/. 10,997.22 10,997.22 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.01.01 TRAZO DE NIVELES Y REPLANTEO S/. 10,997.22 10,997.22 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.02 MOVIMIENTO DE TIERRAS S/. 596,194.65 34,822.00 5.84% 87,137.59 14.62% 91,895.82 15.41% 132,740.64 22.26% 136,387.89 22.88% 113,210.71 18.99% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.02.01 EXCAVACION DE ZANJAS HMAX <=2.00 M TERRERNO NATURAL S/. 82,722.49 31,927.98 38.60% 37,733.07 45.61% 13,061.45 15.79% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.02.02 EXCAVACION DE ZANJAS HMAX <=2.00 M TERRERNO SEMIROCOSO S/. 107,078.81 2,894.02 2.70% 37,622.28 35.14% 39,069.30 36.49% 27,493.21 25.68% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.02.03 EXCAVACION DE ZANJA, TERRENO ROCOSO, TUBERIA 2" S/. 59,290.76 0.00% 0.00% 0.00% 51,879.42 87.50% 7,411.35 12.50% 0.00% 0.00% 0.00% 0.00% 0.00%

03.02.04 PERFILADO DE FONDO DE ZANJAS S/. 6,864.51 0.00% 0.00% 0.00% 6,406.88 93.33% 457.63 6.67% 0.00% 0.00% 0.00% 0.00% 0.00%

03.02.05 CAMA DE APOYO CON MATERIAL DE PRESTAMO S/. 53,655.24 0.00% 0.00% 0.00% 0.00% 0.00% 53,655.24 ####### 0.00% 0.00% 0.00% 0.00%

03.02.06 ZARANDEADO MANUAL DE MATERIAL PROPIO PARA RELLENO S/. 129,604.69 0.00% 11,782.24 9.09% 39,765.08 30.68% 38,292.29 29.55% 35,346.73 27.27% 4,418.34 3.41% 0.00% 0.00% 0.00% 0.00%

03.02.07 RELLENO CON MATERIAL PROPIO SELECCIONADO S/. 113,720.32 0.00% 0.00% 0.00% 0.00% 58,583.20 51.52% 55,137.12 48.48% 0.00% 0.00% 0.00% 0.00%

03.02.08 ACARREO DE MATERIAL EXCEDENTE D=500 M S/. 26,006.53 0.00% 0.00% 0.00% 8,668.84 33.33% 17,337.69 66.67% 0.00% 0.00% 0.00% 0.00% 0.00%

03.02.09 ELIMINACION DE EXCESO CON MAQUINARIA S/. 17,251.30 0.00% 0.00% 0.00% 0.00% 17,251.30 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.03 SUMINISTRO E INSTALACION DE TUBERIAS S/. 120,708.63 0.00 0.00% 0.00 0.00% 70,989.28 58.81% 34,156.40 28.30% 15,562.95 12.89% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 2" C-10 S/. 96,803.57 0.00% 0.00% 70,989.28 73.33% 25,814.29 26.67% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.03.02 SUMINISTRO E INSTALACION DE TUBERIA D=3" FIERRO GALVANIZADO S/. 2,891.26 0.00% 0.00% 0.00% 2,891.26 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.03.03 PRUEBA HIDRAULICA EN TUBERIA PVC AGUA S/. 7,494.92 0.00% 0.00% 0.00% 5,450.85 72.73% 2,044.07 27.27% 0.00% 0.00% 0.00% 0.00% 0.00%

03.03.04 PRUEBA DESINFECCION DE TUBERIA S/. 13,518.88 0.00% 0.00% 0.00% 0.00% 13,518.88 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.04 SUMINISTRO E INSTALACION DE ACCESORIOS S/. 5,026.28 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,026.28 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.04.01 SUMINISTRO E INST. DE CODO 90º PVC SAP 2" S/. 159.39 0.00% 0.00% 0.00% 159.39 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.04.02 SUMINISTRO E INST. DE CODO 45º PVC SAP 2" S/. 950.11 0.00% 0.00% 0.00% 950.11 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.04.03 SUMINISTRO E INST. DE CODO 22.5º PVC SAP 2" S/. 2,132.90 0.00% 0.00% 0.00% 2,132.90 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.04.04 SUMINISTRO E INST. DE CODO 11.25º PVC SAP 2" S/. 1,783.88 0.00% 0.00% 0.00% 1,783.88 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.05 VALVULAS Y ACCESORIOS S/. 345.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 345.84 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.05.01 CAJA PARA VALVULA DE FºFº CON TAPA S/. 155.26 0.00% 0.00% 0.00% 155.26 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.05.02 VALVULA COMPUERTA DE 2" S/. 190.58 0.00% 0.00% 0.00% 190.58 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06 CAMARA DE REPARTO S/. 3,587.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,234.22 34.40% 2,353.59 65.60% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.06.01 TRABAJOS PRELIMINARES S/. 20.35 0.00 0.00% 0.00 0.00% 0.00 0.00% 20.35 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.06.01.01 TRAZO DE NIVELES Y REPLANTEO S/. 20.35 0.00% 0.00% 0.00% 20.35 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06.02 MOVIMIENTO DE TIERRAS S/. 738.57 0.00 0.00% 0.00 0.00% 0.00 0.00% 428.52 58.02% 310.05 41.98% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.06.02.01 EXCAVACION PARA CIMENTACION DE CAMARA S/. 428.52 0.00% 0.00% 0.00% 428.52 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO S/. 310.05 0.00% 0.00% 0.00% 0.00% 310.05 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06.03 CONCRETO SIMPLE S/. 72.22 0.00 0.00% 0.00 0.00% 0.00 0.00% 72.22 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.06.03.01 SOLADO E=2" MEZCLA 1:10 C:H INC. CURADO S/. 72.22 0.00% 0.00% 0.00% 72.22 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06.04 CONCRETO ARMADO S/. 1,511.14 0.00 0.00% 0.00 0.00% 0.00 0.00% 713.13 47.19% 798.02 52.81% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.06.04.01 CONCRETO F'C= 175 KG/CM2 EN CAMARA S/. 477.01 0.00% 0.00% 0.00% 0.00% 477.01 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06.04.02 ENCOFRADO Y DESENCOF MUROS S/. 642.01 0.00% 0.00% 0.00% 321.01 50.00% 321.01 50.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06.04.03 ACERO DE REFUERZO FY=4200 Kg/cm2 S/. 392.12 0.00% 0.00% 0.00% 392.12 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06.05 REVOQUES ENLUCIDOS Y MOLDURAS S/. 427.87 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 427.87 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.06.05.01 TARRAJEO MEZCLA 1:5 S/. 427.87 0.00% 0.00% 0.00% 0.00% 427.87 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06.06 SUMINISTRO E INSTALACION DE ACCESORIOS S/. 817.65 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 817.65 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.06.06.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CAMARA DE REPARTO S/. 495.83 0.00% 0.00% 0.00% 0.00% 495.83 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06.06.02 TAPA DE FºGº ESTRIADA DE 0.60 x 0.60 S/. 178.10 0.00% 0.00% 0.00% 0.00% 178.10 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.06.06.03 TAPA DE FºGº ESTRIADA DE 0.40 x 0.40 S/. 143.72 0.00% 0.00% 0.00% 0.00% 143.72 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.07 CAMARA ROMPE PRESION S/. 50,164.84 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,923.75 3.83% 16,961.28 33.81% 28,870.56 57.55% 2,409.25 4.80% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.07.01 TRABAJOS PRELIMINARES S/. 267.34 0.00 0.00% 0.00 0.00% 0.00 0.00% 267.34 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.07.01.01 TRAZO DE NIVELES Y REPLANTEO S/. 267.34 0.00% 0.00% 0.00% 267.34 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.07.02 MOVIMIENTO DE TIERRAS S/. 9,647.20 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,656.41 17.17% 3,975.37 41.21% 1,606.17 16.65% 2,409.25 24.97% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.07.02.01 EXCAVACION PARA CIMENTACION DE CAMARA S/. 5,631.78 0.00% 0.00% 0.00% 1,656.41 29.41% 3,975.37 70.59% 0.00% 0.00% 0.00% 0.00% 0.00%

03.07.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO S/. 4,015.42 0.00% 0.00% 0.00% 0.00% 0.00% 1,606.17 40.00% 2,409.25 60.00% 0.00% 0.00% 0.00%

03.07.03 CONCRETO ARMADO S/. 22,618.28 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 12,985.91 57.41% 9,632.37 42.59% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.07.03.01 CONCRETO F'C= 175 KG/CM2 EN CAMARA S/. 7,266.54 0.00% 0.00% 0.00% 0.00% 0.00% 7,266.54 ####### 0.00% 0.00% 0.00% 0.00%

03.07.03.02 ENCOFRADO Y DESENCOF MUROS S/. 10,646.25 0.00% 0.00% 0.00% 0.00% 8,280.42 77.78% 2,365.83 22.22% 0.00% 0.00% 0.00% 0.00%

03.07.03.03 ACERO DE REFUERZO FY=4200 Kg/cm2 S/. 4,705.49 0.00% 0.00% 0.00% 0.00% 4,705.49 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.07.04 REVOQUES ENLUCIDOS Y MOLDURAS S/. 6,680.22 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 6,680.22 ####### 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.07.04.01 TARRAJEO MEZCLA 1:5 S/. 6,680.22 0.00% 0.00% 0.00% 0.00% 0.00% 6,680.22 ####### 0.00% 0.00% 0.00% 0.00%

03.07.05 SUMINISTRO E INSTALACION DE ACCESORIOS S/. 10,951.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 10,951.80 ####### 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

DESCRIPCIONITEM UND CANTIDADMES 01

CRONOGRAMA VALORIZADO DE OBRA

MES 09 MES 10MES 02 MES 03 MES 04 MES 08MES 05 MES 06 MES 07

Page 2: cronograma valorizado FINAL.pdf

PROYECTO: AMPLIACIÓN Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE DE LA LOCALIDAD DE ATASPAYA, DISTRITO DE CARUMAS - MARISCAL NIETO - MOQUEGUAFECHA: ABRIL 2011

S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. %DESCRIPCIONITEM UND CANTIDAD

MES 01

CRONOGRAMA VALORIZADO DE OBRA

MES 09 MES 10MES 02 MES 03 MES 04 MES 08MES 05 MES 06 MES 07

03.07.05.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CAMARA ROMPEPRESION S/. 7,089.96 0.00% 0.00% 0.00% 0.00% 0.00% 7,089.96 ####### 0.00% 0.00% 0.00% 0.00%

03.07.05.02 TAPA DE FºGº ESTRIADA DE 0.60 x 0.60 S/. 2,137.20 0.00% 0.00% 0.00% 0.00% 0.00% 2,137.20 ####### 0.00% 0.00% 0.00% 0.00%

03.07.05.03 TAPA DE FºGº ESTRIADA DE 0.40 x 0.40 S/. 1,724.64 0.00% 0.00% 0.00% 0.00% 0.00% 1,724.64 ####### 0.00% 0.00% 0.00% 0.00%

03.08 CRUCES DE CANAL S/. 379.77 0.00 0.00% 0.00 0.00% 0.00 0.00% 379.77 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.08.01 OBRAS PRELIMINARES S/. 3.48 0.00 0.00% 0.00 0.00% 0.00 0.00% 3.48 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.08.01.01 TRAZO Y REPLANTEO S/. 3.48 0.00% 0.00% 0.00% 3.48 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.08.02 MOVIMIENTO DE TIERRAS S/. 19.45 0.00 0.00% 0.00 0.00% 0.00 0.00% 19.45 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.08.02.01 EXCAVACION PARA OBRAS DE ARTES S/. 19.45 0.00% 0.00% 0.00% 19.45 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.08.03 CONCRETO SIMPLE S/. 259.90 0.00 0.00% 0.00 0.00% 0.00 0.00% 259.90 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.08.03.01 DADO DE CONCRETO 1:10 +30% PM S/. 102.09 0.00% 0.00% 0.00% 102.09 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.08.03.02 ENCOFRADO DE MUROS PARA DADOS DE CONCRETOÇ S/. 157.81 0.00% 0.00% 0.00% 157.81 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.08.04 ACCESORIOS Y OTROS S/. 96.94 0.00 0.00% 0.00 0.00% 0.00 0.00% 96.94 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.08.04.01 INSTALACION DE TUBERIA EMPOTRADA EN DADO DE ONCRETO DE FªGª 2" S/. 96.94 0.00% 0.00% 0.00% 96.94 100.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00%

03.09 PASE AEREO S/. 55,984.02 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 176.27 0.31% 2,830.05 5.06% 2,498.75 4.46% 29,634.87 52.93% 20,844.08 37.23%

03.09.01 OBRAS PRELIMINARES S/. 795.88 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 176.27 22.15% 619.61 77.85% 0.00 0.00% 0.00 0.00% 0.00 0.00%

03.09.01.01 LIMPIEZA DE TERRENO MANUAL S/. 352.54 0.00% 0.00% 0.00% 0.00% 0.00% 176.27 50.00% 176.27 50.00% 0.00% 0.00% 0.00%

03.09.01.02 TRAZO Y REPLANTEO EN PASE AEREO S/. 443.34 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 443.34 100.00% 0.00% 0.00% 0.00%

03.09.02 MOVIMIENTO DE TIERRAS S/. 6,517.92 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,210.44 33.91% 2,498.75 38.34% 192.21 2.95% 1,616.52 24.80%

03.09.02.01 EXCAVACION PARA OBRAS DE ARTES S/. 4,901.40 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2,210.44 45.10% 2,498.75 50.98% 192.21 3.92% 0.00%

03.09.02.02 RELLENO COMPACATDO CON MATERIAL PROPIO S/. 1,616.52 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,616.52 100.00%

03.09.03 CONCRETO SIMPLE S/. 11,573.89 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 11,573.89 100.00% 0.00 0.00%

03.09.03.01 SOLADO E=2" MEZCLA 1:10 C:H INC. CURADO S/. 634.73 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 634.73 100.00% 0.00%

03.09.03.02 DADO DE CONCRETO 1:10 +30% PM S/. 6,962.40 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6,962.40 100.00% 0.00%

03.09.03.03 ENCOFRADO DE MUROS PARA DADOS DE CONCRETOÇ S/. 3,976.76 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3,976.76 100.00% 0.00%

03.09.04 CONCRETO ARMADO S/. 15,860.32 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 15,860.32 100.00% 0.00 0.00%

03.09.04.01 CONCRETO F'C=210 KG/CM2. PARA COLUMNAS S/. 7,839.99 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 7,839.99 100.00% 0.00%

03.09.04.02 ENCOFRADO Y DESENCOFRADO EN COLUMNAS S/. 1,279.83 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,279.83 100.00% 0.00%

03.09.04.03 ACERO DE REFUERZO FY=4200 Kg/cm2 S/. 6,740.50 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6,740.50 100.00% 0.00%

03.09.05 REVESTIMIENTOS S/. 5,021.13 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,008.45 40.00% 3,012.68 60.00%

03.09.05.01 TARRAJEO MEZCLA 1:5 S/. 5,021.13 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2,008.45 40.00% 3,012.68 60.00%

03.09.06 SISTEMA DE ANCLAJE S/. 16,214.88 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 16,214.88 100.00%

03.09.06.01 ANCLAJE EN DADOS DE CONCRETO S/. 2,308.50 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2,308.50 100.00%

03.09.06.02 INSTALACION DE TUBERIA EMPOTRADA DE PVC C-10 SAP 2" S/. 323.47 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 323.47 100.00%

03.09.06.03 ANCLAJE DE CABLE DE ACERO TIPO BOA D=1/2" CON TENSORES S/. 1,114.12 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,114.12 100.00%

03.09.06.04 ANCLAJE DE CABLE DE ACERO TIPO BOA D=3/8" CON TENSORES S/. 1,641.18 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,641.18 100.00%

03.09.06.05 TENDIDO DE CABLE DE ACERO TIPO BOA D=1/2" S/. 1,807.98 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,807.98 100.00%

03.09.06.06 TENDIDO DE CABLE DE ACERO TIPO BOA D=3/8" S/. 3,236.47 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 3,236.47 100.00%

03.09.06.07 INSTALACION DE PENDOLAS DE ACERO LISO T-BOA D=1/4 S/. 1,262.95 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,262.95 100.00%

03.09.06.08 ABRAZADERAS P/UNION CABLE CON PENDOLA (INC. ACCESORIOS) S/. 851.01 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 851.01 100.00%

03.09.06.09 ABRAZADERAS P/UNION CABLE CON TUBERIA (INC. ACCESORIOS) S/. 1,362.30 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,362.30 100.00%

03.09.06.10 CARRO DE DILATACION EN SUJECION (INC. ACCESORIOS) S/. 2,306.90 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2,306.90 100.00%

04 RESERVORIO DE ALMACENAMIENTO S/. 2,299.67 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,299.67 100.00%

04.01 SUMINISTRO Y COLOCACION DE HIPOCLORADOR S/. 90.88 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 90.88 100.00%

04.02 PICADO DE TARRAJEOS EN PARED EXTERIOR DE RESERVORIO S/. 534.07 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 534.07 100.00%

04.03 TAPA DE INSPECCION DE VALVULA 0.80X0.80 S/. 79.38 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 79.38 100.00%

04.04 TARRAJEO EXTERIOR C/MORTERO 1:5 S/. 1,252.16 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,252.16 100.00%

04.05 DESINFECCION DE RESERVORIOS DE CºAº S/. 175.68 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 175.68 100.00%

04.06 PINTADO INTERIOR DE RESERVORIOS S/. 90.49 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 90.49 100.00%

04.07 MANTENIMIENTO DE VALVULAS S/. 77.01 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 77.01 100.00%

05 LINEA DE ADUCCION Y/O RED DE DISTRIBUCION S/. 395,609.76 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 28,821.28 7.29% 39,202.88 9.91% 37,750.92 9.54% 45,845.35 11.59% ######### 34.54% 107,333.13 27.13%

05.01 TRABAJOS PRELIMINARES S/. 4,137.99 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,137.99 100.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00%

05.01.01 TRAZO DE NIVELES Y REPLANTEO S/. 4,137.99 0.00% 0.00% 0.00% 0.00% 4,137.99 100.00% 0.00% 0.00% 0.00% 0.00% 0.00%

05.02 MOVIMIENTO DE TIERRAS S/. 300,827.40 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 24,683.29 8.21% 39,202.88 13.03% 37,750.92 12.55% 40,529.55 13.47% 91,589.02 30.45% 67,071.73 22.30%

05.02.01 EXCAVACION DE ZANJAS HMAX <=2.00 M TERRERNO SEMIROCOSO S/. 105,992.97 0.00% 0.00% 0.00% 0.00% 24,683.29 23.29% 39,202.88 36.99% 37,750.92 35.62% 4,355.88 4.11% 0.00% 0.00%

05.02.02 PERFILADO DE FONDO DE ZANJAS S/. 1,713.18 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,713.18 100.00% 0.00% 0.00%

05.02.03 ZARANDEADO MANUAL DE MATERIAL PROPIO PARA RELLENO S/. 16,511.93 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 16,511.93 100.00% 0.00% 0.00%

05.02.04 CAMA DE APOYO CON MATERIAL PROPIO S/. 44,858.93 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 6,901.37 15.38% 37,957.56 84.62% 0.00%

05.02.05 RELLENO CON MATERIAL DE PRESTAMO S/. 52,084.14 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 32,051.78 61.54% 20,032.36 38.46%

05.02.06 RELLENO CON MATERIAL PROPIO SELECCIONADO S/. 26,138.22 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 9,091.55 34.78% 17,046.67 65.22%

05.02.07 ACARREO DE MATERIAL EXCEDENTE D=500 M S/. 32,180.96 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 11,047.20 34.33% 12,488.13 38.81% 8,645.63 26.87%

05.02.08 ELIMINACION DE EXCESO CON MAQUINARIA S/. 21,347.07 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 21,347.07 100.00%

05.03 SUMINISTRO E INSTALACION DE TUBERIAS S/. 44,331.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 36,424.82 82.16% 7,906.98 17.84%

05.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC 2" C-10 S/. 36,424.82 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 36,424.82 100.00% 0.00%

05.03.02 PRUEBA HIDRAULICA EN TUBERIA PVC AGUA S/. 2,820.16 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2,820.16 100.00%

Page 3: cronograma valorizado FINAL.pdf

PROYECTO: AMPLIACIÓN Y MEJORAMIENTO DEL SISTEMA DE AGUA POTABLE DE LA LOCALIDAD DE ATASPAYA, DISTRITO DE CARUMAS - MARISCAL NIETO - MOQUEGUAFECHA: ABRIL 2011

S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. % S/. %DESCRIPCIONITEM UND CANTIDAD

MES 01

CRONOGRAMA VALORIZADO DE OBRA

MES 09 MES 10MES 02 MES 03 MES 04 MES 08MES 05 MES 06 MES 07

05.03.03 PRUEBA DESINFECCION DE TUBERIA S/. 5,086.82 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 5,086.82 100.00%

05.04 SUMINISTRO E INSTALACION DE ACCESORIOS S/. 2,369.75 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,454.82 61.39% 914.93 38.61%

05.04.01 SUMINISTRO E INST. DE TEE PVC SAP 2" S/. 349.41 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 349.41 100.00% 0.00%

05.04.02 SUMINISTRO E INST. DE CODO 90º PVC SAP 2" S/. 523.71 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 523.71 100.00% 0.00%

05.04.03 SUMINISTRO E INST. DE CODO 45º PVC SAP 2" S/. 407.19 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 407.19 100.00% 0.00%

05.04.04 SUMINISTRO E INST. DE CODO 22.5º PVC SAP 2" S/. 349.02 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 174.51 50.00% 174.51 50.00%

05.04.05 SUMINISTRO E INST. DE CODO 11.25º PVC SAP 2" S/. 349.02 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 349.02 100.00%

05.04.06 SUMINISTRO E INST. DE TAPON PVC 2" S/. 391.40 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 391.40 100.00%

05.05 VALVULAS Y ACCESORIOS S/. 31,439.49 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 31,439.49 100.00%

05.05.01 CAJA PARA VALVULA DE FºFº CON TAPA S/. 310.52 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 310.52 100.00%

05.05.02 VALVULA COMPUERTA DE 2" S/. 381.16 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 381.16 100.00%

05.05.03 CONEXION DOMICILIARIAS DE AGUA S/. 30,747.81 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 30,747.81 100.00%

05.06 CAMARA ROMPE PRESION S/. 12,503.33 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 5,315.80 42.52% 7,187.53 57.48% 0.00 0.00%

05.06.01 TRABAJOS PRELIMINARES S/. 66.83 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 66.83 100.00% 0.00 0.00% 0.00 0.00%

05.06.01.01 TRAZO DE NIVELES Y REPLANTEO S/. 66.83 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 66.83 100.00% 0.00% 0.00%

05.06.02 MOVIMIENTO DE TIERRAS S/. 2,411.90 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,408.09 58.38% 1,003.81 41.62% 0.00 0.00%

05.06.02.01 EXCAVACION PARA CIMENTACION DE CAMARA S/. 1,408.09 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,408.09 100.00% 0.00% 0.00%

05.06.02.02 RELLENO CON MATERIAL PROPIO SELECCIONADO S/. 1,003.81 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,003.81 100.00% 0.00%

05.06.03 CONCRETO ARMADO S/. 5,659.74 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 3,840.88 67.86% 1,818.86 32.14% 0.00 0.00%

05.06.03.01 CONCRETO F'C= 175 KG/CM2 EN CAMARA S/. 1,818.86 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,818.86 100.00% 0.00%

05.06.03.02 ENCOFRADO Y DESENCOF MUROS S/. 2,661.56 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2,661.56 100.00% 0.00% 0.00%

05.06.03.03 ACERO DE REFUERZO FY=4200 Kg/cm2 S/. 1,179.32 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,179.32 100.00% 0.00% 0.00%

05.06.04 REVOQUES ENLUCIDOS Y MOLDURAS S/. 1,670.05 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 1,670.05 100.00% 0.00 0.00%

05.06.04.01 TARRAJEO MEZCLA 1:5 S/. 1,670.05 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,670.05 100.00% 0.00%

05.06.05 SUMINISTRO E INSTALACION DE ACCESORIOS S/. 2,694.81 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,694.81 100.00% 0.00 0.00%

05.06.05.01 SUMINISTRO E INSTALACION DE ACCESORIOS EN CAMARA ROMPEPRESION S/. 1,772.49 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 1,772.49 100.00% 0.00%

05.06.05.02 TAPA DE INSPECCION 0.60 x 0.60 M METALICO S/. 491.16 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 491.16 100.00% 0.00%

05.06.05.03 TAPA DE INSPECCION 0.40 x 0.40 M METALICO S/. 431.16 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 431.16 100.00% 0.00%

06 MITIGACION AMBIENTAL S/. 2,954.00 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 2,954.00 100.00%

06.01 REACONDICIONAMIENTO MDE CAMPAMENTO S/. 19.40 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 19.40 100.00%

06.02 REACONDICIONAMIENTO DE CANTERAS S/. 37.00 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 37.00 100.00%

06.03 REFORESTACION S/. 2,897.60 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 2,897.60 100.00%

07 CAPACITACION S/. 4,264.80 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 0.00 0.00% 4,264.80 100.00%

07.01 CAPACITACION DEL MANTENIMIENTO S/. 4,264.80 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 4,264.80 100.00%