1/19 CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA SAN ANDRES-CUTERVO-CAJAMARCA FECHA: Apr-11 PARTIDA DESCRIPCION UND METRADO PRECIO (S/.) PARCIAL (S/.) Mes 01 Mes 02 Mes 03 Mes 04 Mes 05 METRADO VALORIZACION MENSUAL METRADO VALORIZACION MENSUAL METRADO METRADO VALORIZACION MENSUAL METRADO VALORIZACION MENSUAL METRADO 01.00.00 ESTRUCTURAS 01.01.00 OBRAS PROVISIONALES 01.01.01 ALMACEN,OFICINA Y CASETA DE GUARDIANIA GLB 1.00 725.00 725.00 1.00 725.00 0.00 0.00 0.00 0.00 01.01.02 CERCO PERIMETRICO DE PROTECCION C/ESTERAS M 200.00 10.02 2,004.00 200.00 2,004.00 0.00 0.00 0.00 0.00 01.01.03 CARTEL DE OBRA 2.40 X3.60 MTS. UND 1.00 811.25 811.25 1.00 811.25 0.00 0.00 0.00 0.00 01.01.04 MOVILIZACION Y DESMOVILIZACIÓN DE EQUIPOS Y HERRAMIENTAS GLB 1.00 2,500.00 2,500.00 1.00 2,500.00 0.00 0.00 0.00 0.00 01.01.05 SERVICIOS HIGIENICOS GLB 1.00 400.00 400.00 1.00 400.00 0.00 0.00 0.00 0.00 01.01.06 AGUA PARA LA CONSTRUCCION GLB 1.00 520.00 520.00 1.00 520.00 0.00 0.00 0.00 0.00 01.02.00 TRABAJOS PRELIMINARES 0.00 0.00 0.00 0.00 0.00 01.02.01 LIMPIEZA DE TERRENO MANUAL M2 7,594.21 3.17 24,073.65 7,594.21 24,073.65 0.00 0.00 0.00 0.00 01.02.02 TRAZO Y REPLANTEO REPLANTEO PRELIMINAR M2 7,594.21 1.30 9,872.47 7,594.21 9,872.47 0.00 0.00 0.00 0.00 01.03.00 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 0.00 0.00 01.03.01 CORTE MASIVO DE TERRENO A MAQUINA M3 6,595.86 7.05 46,500.81 6,595.86 46,500.81 0.00 0.00 0.00 0.00 01.03.02 CORTE EN TERRENO ONORMAL HASTA 0.20 M M3 1,164.86 30.86 35,947.58 1,164.86 35,947.58 0.00 0.00 0.00 0.00 01.03.03 EXCAVACION DE ZANJAS Y/0 ZAPATAS Rt<2Kg/cm2 h=1.5 M M3 1,135.72 35.99 40,874.56 1,135.72 40,874.56 0.00 0.00 0.00 0.00 01.03.04 EXCAVACION DE ZANJA PARA CISTERNA Rt<2kg/cm2 M3 56.40 35.99 2,029.84 56.4 2,029.84 0.00 0.00 0.00 0.00 01.03.05 EXCAVACION DE ZANJA PARA POZO PERCOLADOR M3 67.59 43.19 2,919.21 67.59 2,919.21 0.00 0.00 0.00 0.00 01.03.06 EXCAVACION PARA SARDINELES M 720.23 5.40 3,889.24 720.23 3,889.24 0.00 0.00 0.00 0.00 01.03.07 RELLENO COMPACTADO C/EQUIPO MAT/ PROPIO M3 536.30 12.70 6,811.01 536.3 6,811.01 0.00 0.00 0.00 0.00 01.03.08 RELLENO MASIVO C/MAT. DE PRESTAMO COMP. C.EQUIPO M3 2,444.26 70.91 173,322.48 2444.26 173,322.48 0.00 0.00 0.00 0.00 01.03.09 RELLENO CON MATERIAL DE PRESTAMO(ARENA E=4") M3 5.92 107.85 638.47 5.92 638.47 0.00 0.00 0.00 0.00 01.03.10 ACARREO INTERNO MATERIAL PROCEDENTE DE EXCAVACIONES M3 10,541.98 13.49 142,211.31 10541.98 142,211.31 0.00 0.00 0.00 0.00 01.03.11 ELIMINACION MATERIAL EXCEDENTE ACARREADO M3 166.55 30.70 5,113.09 166.55 5,113.09 0.00 0.00 0.00 0.00 01.03.12 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA M3 10,083.79 26.29 265,102.84 5041.895 132,551.42 0.00 5,041.90 132,551.42 0.00 0.00 01.03.13 NIVELACION INTERIOR Y APISONADO PARA FALSO PISO Y VEREDAS M2 6,259.82 3.92 24,538.49 6259.82 24,538.49 0.00 0.00 0.00 0.00 01.03.14 AFIRMADO DE 6" PARA PISOS INTERIORES Y EXTERIORES M2 6,259.82 17.56 109,922.44 6259.82 109,922.44 0.00 0.00 0.00 0.00 01.03.15 COMFORMACION DE CAMA DE ARENA E=5CM PARA ASENTADO DE ADOQUINES M2 249.15 15.04 3,747.22 0.00 0.00 0.00 249.15 3,747.22 0.00 01.03.16 RELLENO CON MATERIAL DE CHACRA M3 808.76 13.71 11,088.10 0.00 0.00 0.00 0.00 0.00 808.76 01.03.17 PREPARACION DE TERRENO PARA SEMBRADO DE GRASS M2 4,043.80 1.76 7,117.09 0.00 0.00 0.00 0.00 0.00 4043.80 01.03.18 SEMBRADO DE GRASS CON FERTILIZANTES M2 4,043.80 4.64 18,763.23 0.00 0.00 0.00 0.00 0.00 4043.80 01.04.00 OBRAS DE CONCRETO SIMPLE 0.00 0.00 0.00 0.00 0.00 0.00 01.04.01 SOLADO PARA ZAPATAS E=4" 1:12 CEM/HORM M2 435.97 33.88 14,770.66 435.97 14,770.66 0.00 0.00 0.00 0.00 01.04.02 CIMIENTOS CORRIDOS 175 KG/CM2 +30%P.G. INC. PREPARACION C/MEZCLA. M3 102.08 294.46 30,058.48 102.08 30,058.48 0.00 0.00 0.00 0.00 01.04.03 SOBRECIMIENTO 1:8+25%P.M. M3 3.55 317.15 1,125.88 3.55 1,125.88 0.00 0.00 0.00 0.00 01.04.04 SOBRECIMIENTOS ENCOFRADO Y DESENCOFRADO M3 35.65 25.50 909.08 35.65 909.08 0.00 0.00 0.00 0.00 01.04.05 PATIO CONCRETO FC'=175KG/CM2 E=4" M2 996.55 43.75 43,599.06 0.00 0.00 996.55 43,599.06 0.00 0.00 01.04.06 PATIO ENCOFRADO Y DESENCOFRADO M2 77.73 7.44 578.31 0.00 0.00 77.73 578.31 0.00 0.00 01.05.00 OBRAS DE CONCRETO ARMADO 0.00 0.00 0.00 0.00 0.00 0.00 01.05.01 ZAPATAS 0.00 0.00 0.00 0.00 0.00 0.00 01.05.01.1 CONCRETO ZAPATAS F'C=210 KG/CM2. M3 197.58 382.16 75,507.17 197.58 75,507.17 0.00 0.00 0.00 0.00 01.05.01.2 ACERO FY = 4200 KG/CM2 KG 3,457.15 5.62 19,429.18 3,457.15 19,429.18 0.00 0.00 0.00 0.00 01.05.02 VIGAS DE CIMENTACION 0.00 0.00 0.00 0.00 0.00 01.05.02.1 CONCRETO VIGAS DE CIMENTACION F'C=210 KG/CM2. M3 88.81 386.46 34,321.51 88.81 34,321.51 0.00 0.00 0.00 0.00 01.05.02.2 ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION M2 593.18 41.10 24,379.70 593.18 24,379.70 0.00 0.00 0.00 0.00 01.05.02.3 ACERO FY = 4200 KG/CM2 KG 13,902.74 5.62 78,133.40 13,902.74 78,133.40 0.00 0.00 0.00 0.00 VALORIZACION MENSUAL

description

mm

Transcript of Cronograma Valorizado San Andres

Page 1: Cronograma Valorizado San Andres

1/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO PRECIO (S/.) PARCIAL (S/.) Mes 01 Mes 02 Mes 03 Mes 04 Mes 05 MES 06

TotalMETRADO METRADO METRADO METRADO METRADO METRADO

01.00.00 ESTRUCTURAS

01.01.00 OBRAS PROVISIONALES

01.01.01 ALMACEN,OFICINA Y CASETA DE GUARDIANIA GLB 1.00 725.00 725.00 1.00 725.00 0.00 0.00 0.00 0.00 0.00 725.00

01.01.02 CERCO PERIMETRICO DE PROTECCION C/ESTERAS M 200.00 10.02 2,004.00 200.00 2,004.00 0.00 0.00 0.00 0.00 0.00 2,004.00

01.01.03 CARTEL DE OBRA 2.40 X3.60 MTS. UND 1.00 811.25 811.25 1.00 811.25 0.00 0.00 0.00 0.00 0.00 811.25

01.01.04 MOVILIZACION Y DESMOVILIZACIÓN DE EQUIPOS Y HERRAMIENTAS GLB 1.00 2,500.00 2,500.00 1.00 2,500.00 0.00 0.00 0.00 0.00 0.00 2,500.00

01.01.05 SERVICIOS HIGIENICOS GLB 1.00 400.00 400.00 1.00 400.00 0.00 0.00 0.00 0.00 0.00 400.00

01.01.06 AGUA PARA LA CONSTRUCCION GLB 1.00 520.00 520.00 1.00 520.00 0.00 0.00 0.00 0.00 0.00 520.00

01.02.00 TRABAJOS PRELIMINARES 0.00 0.00 0.00 0.00 0.00 0.00

01.02.01 LIMPIEZA DE TERRENO MANUAL M2 7,594.21 3.17 24,073.65 7,594.21 24,073.65 0.00 0.00 0.00 0.00 0.00 24,073.65

01.02.02 TRAZO Y REPLANTEO REPLANTEO PRELIMINAR M2 7,594.21 1.30 9,872.47 7,594.21 9,872.47 0.00 0.00 0.00 0.00 0.00 9,872.47

01.03.00 MOVIMIENTO DE TIERRAS 0.00 0.00 0.00 0.00 0.00 0.00

01.03.01 CORTE MASIVO DE TERRENO A MAQUINA M3 6,595.86 7.05 46,500.81 6,595.86 46,500.81 0.00 0.00 0.00 0.00 0.00 46,500.81

01.03.02 CORTE EN TERRENO ONORMAL HASTA 0.20 M M3 1,164.86 30.86 35,947.58 1,164.86 35,947.58 0.00 0.00 0.00 0.00 0.00 35,947.58

01.03.03 EXCAVACION DE ZANJAS Y/0 ZAPATAS Rt<2Kg/cm2 h=1.5 M M3 1,135.72 35.99 40,874.56 1,135.72 40,874.56 0.00 0.00 0.00 0.00 0.00 40,874.56

01.03.04 EXCAVACION DE ZANJA PARA CISTERNA Rt<2kg/cm2 M3 56.40 35.99 2,029.84 56.4 2,029.84 0.00 0.00 0.00 0.00 0.00 2,029.84

01.03.05 EXCAVACION DE ZANJA PARA POZO PERCOLADOR M3 67.59 43.19 2,919.21 67.59 2,919.21 0.00 0.00 0.00 0.00 0.00 2,919.21

01.03.06 EXCAVACION PARA SARDINELES M 720.23 5.40 3,889.24 720.23 3,889.24 0.00 0.00 0.00 0.00 0.00 3,889.24

01.03.07 RELLENO COMPACTADO C/EQUIPO MAT/ PROPIO M3 536.30 12.70 6,811.01 536.3 6,811.01 0.00 0.00 0.00 0.00 0.00 6,811.01

01.03.08 RELLENO MASIVO C/MAT. DE PRESTAMO COMP. C.EQUIPO M3 2,444.26 70.91 173,322.48 2444.26 173,322.48 0.00 0.00 0.00 0.00 0.00 173,322.48

01.03.09 RELLENO CON MATERIAL DE PRESTAMO(ARENA E=4") M3 5.92 107.85 638.47 5.92 638.47 0.00 0.00 0.00 0.00 0.00 638.47

01.03.10 ACARREO INTERNO MATERIAL PROCEDENTE DE EXCAVACIONES M3 10,541.98 13.49 142,211.31 10541.98 142,211.31 0.00 0.00 0.00 0.00 0.00 142,211.31

01.03.11 ELIMINACION MATERIAL EXCEDENTE ACARREADO M3 166.55 30.70 5,113.09 166.55 5,113.09 0.00 0.00 0.00 0.00 0.00 5,113.09

01.03.12 ELIMINACION DE MATERIAL EXCEDENTE CON MAQUINA M3 10,083.79 26.29 265,102.84 5041.895 132,551.42 0.00 5,041.90 132,551.42 0.00 0.00 0.00 265,102.84

01.03.13 NIVELACION INTERIOR Y APISONADO PARA FALSO PISO Y VEREDAS M2 6,259.82 3.92 24,538.49 6259.82 24,538.49 0.00 0.00 0.00 0.00 0.00 24,538.49

01.03.14 AFIRMADO DE 6" PARA PISOS INTERIORES Y EXTERIORES M2 6,259.82 17.56 109,922.44 6259.82 109,922.44 0.00 0.00 0.00 0.00 0.00 109,922.44

01.03.15 COMFORMACION DE CAMA DE ARENA E=5CM PARA ASENTADO DE ADOQUINES M2 249.15 15.04 3,747.22 0.00 0.00 0.00 249.15 3,747.22 0.00 0.00 3,747.22

01.03.16 RELLENO CON MATERIAL DE CHACRA M3 808.76 13.71 11,088.10 0.00 0.00 0.00 0.00 0.00 808.76 11,088.10 11,088.10

01.03.17 PREPARACION DE TERRENO PARA SEMBRADO DE GRASS M2 4,043.80 1.76 7,117.09 0.00 0.00 0.00 0.00 0.00 4043.80 7,117.09 7,117.09

01.03.18 SEMBRADO DE GRASS CON FERTILIZANTES M2 4,043.80 4.64 18,763.23 0.00 0.00 0.00 0.00 0.00 4043.80 18,763.23 18,763.23

01.04.00 OBRAS DE CONCRETO SIMPLE 0.00 0.00 0.00 0.00 0.00 0.00 0.00

01.04.01 SOLADO PARA ZAPATAS E=4" 1:12 CEM/HORM M2 435.97 33.88 14,770.66 435.97 14,770.66 0.00 0.00 0.00 0.00 0.00 14,770.66

01.04.02 CIMIENTOS CORRIDOS 175 KG/CM2 +30%P.G. INC. PREPARACION C/MEZCLA. M3 102.08 294.46 30,058.48 102.08 30,058.48 0.00 0.00 0.00 0.00 0.00 30,058.48

01.04.03 SOBRECIMIENTO 1:8+25%P.M. M3 3.55 317.15 1,125.88 3.55 1,125.88 0.00 0.00 0.00 0.00 0.00 1,125.88

01.04.04 SOBRECIMIENTOS ENCOFRADO Y DESENCOFRADO M3 35.65 25.50 909.07 35.65 909.07 0.00 0.00 0.00 0.00 0.00 909.07

01.04.05 PATIO CONCRETO FC'=175KG/CM2 E=4" M2 996.55 43.75 43,599.06 0.00 0.00 996.55 43,599.06 0.00 0.00 0.00 43,599.06

01.04.06 PATIO ENCOFRADO Y DESENCOFRADO M2 77.73 7.44 578.31 0.00 0.00 77.73 578.31 0.00 0.00 0.00 578.31

01.05.00 OBRAS DE CONCRETO ARMADO 0.00 0.00 0.00 0.00 0.00 0.00 0.00

01.05.01 ZAPATAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00

01.05.01.1 CONCRETO ZAPATAS F'C=210 KG/CM2. M3 197.58 382.16 75,507.17 197.58 75,507.17 0.00 0.00 0.00 0.00 0.00 75,507.17

01.05.01.2 ACERO FY = 4200 KG/CM2 KG 3,457.15 5.62 19,429.18 3,457.15 19,429.18 0.00 0.00 0.00 0.00 0.00 19,429.18

01.05.02 VIGAS DE CIMENTACION 0.00 0.00 0.00 0.00 0.00 0.00

01.05.02.1 CONCRETO VIGAS DE CIMENTACION F'C=210 KG/CM2. M3 88.81 386.46 34,321.51 88.81 34,321.51 0.00 0.00 0.00 0.00 0.00 34,321.51

01.05.02.2 ENCOFRADO Y DESENCOFRADO DE VIGAS DE CIMENTACION M2 593.18 41.10 24,379.70 593.18 24,379.70 0.00 0.00 0.00 0.00 0.00 24,379.70

01.05.02.3 ACERO FY = 4200 KG/CM2 KG 13,902.74 5.62 78,133.40 13,902.74 78,133.40 0.00 0.00 0.00 0.00 0.00 78,133.40

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

A8
No borrar fila, contiene datos ocultos.
Page 2: Cronograma Valorizado San Andres

2/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO PRECIO (S/.) PARCIAL (S/.) Mes 01 Mes 02 Mes 03 Mes 04 Mes 05 MES 06

TotalMETRADO METRADO METRADO METRADO METRADO METRADO

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

01.05.03 SOBRECIMIENTOS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.03.1 CONCRETO SOBRECIMIENTOS F'C=210 KG/CM2. M3 87.58 453.84 39,747.31 0.00 87.58 39,747.31 0.00 0.00 0.00 0.00 39,747.31

01.05.03.2 ENCOFRADO Y DESENCOFRADO PARA SOBRECIMIENTOS M2 1,040.57 25.62 26,659.40 0.00 1040.57 26,659.40 0.00 0.00 0.00 0.00 26,659.40

01.05.03.3 ACERO FY = 4200 KG/CM2 KG 4,421.41 5.62 24,848.32 0.00 4421.41 24,848.32 0.00 0.00 0.00 0.00 24,848.32

01.05.04 COLUMNAS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.04.1 CONCRETO COLUMNAS F'C=210 KG/CM2 M3 205.92 482.02 99,257.56 0.00 205.92 99,257.56 0.00 0.00 0.00 0.00 99,257.56

01.05.04.2 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS M2 2,319.24 41.83 97,013.81 0.00 2319.24 97,013.81 0.00 0.00 0.00 0.00 97,013.81

01.05.04.3 ACERO FY = 4200 KG/CM2 KG 33,172.62 5.62 186,430.12 0.00 33172.62 186,430.12 0.00 0.00 0.00 0.00 186,430.12

01.05.05 VIGAS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.05.1 CONCRETO VIGAS, F'C=210 KG/CM2 M3 159.80 400.55 64,007.89 0.00 159.80 64,007.89 0.00 0.00 0.00 0.00 64,007.89

01.05.05.2 ENCOFRADO Y DESENCOFRADO DE VIGAS M2 1,198.42 47.99 57,512.18 0.00 1,198.42 57,512.18 0.00 0.00 0.00 0.00 57,512.18

01.05.05.3 ACERO FY = 4200 KG/CM2 KG 19,225.16 5.62 108,045.40 0.00 19,225.16 108,045.40 0.00 0.00 0.00 0.00 108,045.40

01.05.06 LOSAS ALIGERADAS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.06.1 CONCRETO DE LOSA ALIGERADA, F'C=210 KG/CM2 M3 101.19 397.49 40,222.01 0.00 101.19 40,222.01 0.00 0.00 0.00 0.00 40,222.01

01.05.06.2 ENCOFRADO Y DESENCOFRADO DE LOSA ALIGERADA M2 1,156.47 29.41 34,011.78 0.00 1156.47 34,011.78 0.00 0.00 0.00 0.00 34,011.78

01.05.06.3 ACERO FY = 4200 KG/CM2 KG 6,399.00 5.62 35,962.38 0.00 6399 35,962.38 0.00 0.00 0.00 0.00 35,962.38

01.05.06.4 LADRILLOS PARA TECHO, 15x30x30 CM. UND 9,661.70 3.36 32,463.31 0.00 9661.7 32,463.31 0.00 0.00 0.00 0.00 32,463.31

01.05.07 GARGOLAS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.07.1 CONCRETO EN GARGOLAS DE F'C= 175 KG/CM2 M3 0.89 381.26 339.32 0.00 0.89 339.32 0.00 0.00 0.00 0.00 339.32

01.05.07.2 ENCOFRADO Y DESENCOFRADO GRAGOLAS M2 15.46 46.94 725.69 0.00 15.46 725.69 0.00 0.00 0.00 0.00 725.69

01.05.07.3 ACERO FY = 4200 KG/CM2 KG 8.06 5.62 45.30 0.00 8.06 45.30 0.00 0.00 0.00 0.00 45.30

01.05.08 ESCALERAS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.08.1 CONCRETO EN ESCALERAS DE F'C= 175 KG/CM2 M3 9.82 479.71 4,710.75 0.00 9.82 4,710.75 0.00 0.00 0.00 0.00 4,710.75

01.05.08.2 ENCOFRADO Y DESENCOFRADO ESCALERAS M2 45.96 63.54 2,920.30 0.00 45.96 2,920.30 0.00 0.00 0.00 0.00 2,920.30

01.05.08.3 ACERO FY = 4200 KG/CM2 KG 585.54 5.62 3,290.73 0.00 585.54 3,290.73 0.00 0.00 0.00 0.00 3,290.73

01.05.09 ESCALINATAS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.09.1 CONCRETO EN ESCALINATAS DE F'C= 175 KG/CM2 M3 58.06 393.77 22,862.29 0.00 58.06 22,862.29 0.00 0.00 0.00 0.00 22,862.29

01.05.09.2 ENCOFRADO Y DESENCOFRADO ESCALINATAS M2 93.26 28.94 2,698.94 0.00 93.26 2,698.94 0.00 0.00 0.00 0.00 2,698.94

01.05.09.3 ACERO FY = 4200 KG/CM2 KG 1,467.27 5.62 8,246.06 0.00 1467.27 8,246.06 0.00 0.00 0.00 0.00 8,246.06

01.05.10 CANALETAS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.10.1 CANALETA PARA AGUAS PLUVIALES FC'=175 KG/CM2 M 420.50 63.40 26,659.70 0.00 0.00 420.50 26,659.70 0.00 0.00 0.00 26,659.70

01.05.11 CISTERNA 0.00 0.00 0.00 0.00 0.00 0.00

01.05.11.1 CONCRETO EN CISTERNA F'C= 175 KG/CM2 M3 18.10 472.62 8,554.42 0.00 0.00 18.10 8,554.42 0.00 0.00 0.00 8,554.42

01.05.11.2 ENCOFRADO Y DESENCOFRADO CISTERNA M2 70.80 44.52 3,152.02 0.00 0.00 70.80 3,152.02 0.00 0.00 0.00 3,152.02

01.05.11.3 ACERO FY = 4200 KG/CM2 KG 1,090.00 5.62 6,125.80 0.00 0.00 1090.00 6,125.80 0.00 0.00 0.00 6,125.80

01.05.12 TANQUE ELEVADO 0.00 0.00 0.00 0.00 0.00 0.00

01.05.12.1 CONCRETO EN TANQUE ELEVADO F'C= 175 KG/CM2 M3 6.00 484.41 2,906.46 0.00 0.00 6.00 2,906.46 0.00 0.00 0.00 2,906.46

01.05.12.2 ENCOFRADO Y DESENCOFRADO TANQUE ELEVADO M2 44.40 46.20 2,051.28 0.00 0.00 44.40 2,051.28 0.00 0.00 0.00 2,051.28

01.05.12.3 ACERO FY = 4200 KG/CM2 KG 366.00 5.62 2,056.92 0.00 0.00 366.00 2,056.92 0.00 0.00 0.00 2,056.92

01.05.13 TANQUE SEPTICO 0.00 0.00 0.00 0.00 0.00 0.00

01.05.13.1 CONCRETO EN TANQUE SEPTICO F'C= 175 KG/CM2 M3 5.81 385.01 2,236.91 0.00 0.00 0.00 5.81 2,236.91 0.00 0.00 2,236.91

01.05.13.2 ENCOFRADO Y DESENCOFRADO TANQUE SEPTICO M2 60.99 43.51 2,653.67 0.00 0.00 0.00 60.99 2,653.67 0.00 0.00 2,653.67

01.05.13.3 ACERO FY = 4200 KG/CM2 KG 170.35 5.62 957.37 0.00 0.00 0.00 170.35 957.37 0.00 0.00 957.37

01.05.14 BANCAS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.14.1 CONCRETO EN BANCAS F'C= 175 KG/CM2 M3 12.75 362.28 4,619.07 0.00 0.00 0.00 12.75 4,619.07 0.00 0.00 4,619.07

A8
No borrar fila, contiene datos ocultos.
Page 3: Cronograma Valorizado San Andres

3/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO PRECIO (S/.) PARCIAL (S/.) Mes 01 Mes 02 Mes 03 Mes 04 Mes 05 MES 06

TotalMETRADO METRADO METRADO METRADO METRADO METRADO

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

01.05.14.2 ENCOFRADO Y DESENCOFRADO BANCAS M2 128.09 47.99 6,147.04 0.00 0.00 0.00 128.09 6,147.04 0.00 0.00 6,147.04

01.05.14.3 ACERO FY = 4200 KG/CM2 KG 612.39 5.62 3,441.63 0.00 0.00 0.00 612.39 3,441.63 0.00 0.00 3,441.63

01.05.15 MURO DE CONTENCION 0.00 0.00 0.00 0.00 0.00 0.00

01.05.15.1 CONCRETO EN MURO DE CONTENCION F'C= 210 KG/CM2 M3 54.20 465.23 25,215.47 0.00 0.00 0.00 54.2 25,215.47 0.00 0.00 25,215.47

01.05.15.2 ENCOFRADO Y DESENCOFRADO MURO DE CONTENCION M2 284.04 40.39 11,472.38 0.00 0.00 0.00 284.04 11,472.38 0.00 0.00 11,472.38

01.05.15.3 ACERO FY = 4200 KG/CM2 KG 1,705.13 5.62 9,582.83 0.00 0.00 0.00 1705.13 9,582.83 0.00 0.00 9,582.83

01.05.16 GRADERIAS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.16.1 CONCRETO EN GRADERIAS F'C= 210 KG/CM2 M3 163.79 401.74 65,800.99 0.00 81.895 32,900.50 81.895 32,900.50 0.00 0.00 0.00 65,800.99

01.05.16.2 ENCOFRADO Y DESENCOFRADO GRADERIAS M2 801.75 25.20 20,204.10 0.00 400.875 10,102.05 400.875 10,102.05 0.00 0.00 0.00 20,204.10

01.05.16.3 ACERO FY = 4200 KG/CM2 KG 8,988.43 5.62 50,514.98 0.00 4494.215 25,257.49 4494.215 25,257.49 0.00 0.00 0.00 50,514.98

01.05.17 BASUREROS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.17.1 CONCRETO EN BASUREROS F'C= 175 KG/CM2 M3 0.24 381.58 91.58 0.00 0.00 0.24 91.58 0.00 0.00 0.00 91.58

01.05.17.2 ENCOFRADO Y DESENCOFRADO BASUREROS M2 2.80 48.99 137.17 0.00 0.00 2.80 137.17 0.00 0.00 0.00 137.17

01.05.17.3 ACERO FY = 4200 KG/CM2 KG 12.32 5.62 69.24 0.00 0.00 12.32 69.24 0.00 0.00 0.00 69.24

01.05.18 JARDINERAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00

01.05.18.1 CONCRETO EN JARDINERAS F'C= 175 KG/CM2 M3 55.42 364.79 20,216.66 0.00 0.00 55.42 20,216.66 0.00 0.00 0.00 20,216.66

01.05.18.2 ENCOFRADO Y DESENCOFRADO JARDINERAS M2 277.08 40.61 11,252.22 0.00 0.00 277.08 11,252.22 0.00 0.00 0.00 11,252.22

01.05.18.3 ACERO FY = 4200 KG/CM2 KG 1,445.81 5.62 8,125.45 0.00 0.00 1445.81 8,125.45 0.00 0.00 0.00 8,125.45

01.05.19 RAMPAS 0.00 0.00 0.00 0.00 0.00 0.00

01.05.19.1 CONCRETO EN RAMPAS F'C= 175 KG/CM2 M3 22.23 364.79 8,109.28 0.00 0.00 0.00 22.23 8,109.28 0.00 0.00 8,109.28

01.05.19.2 ENCOFRADO Y DESENCOFRADO RAMPAS M2 12.62 40.61 512.50 0.00 0.00 0.00 12.62 512.50 0.00 0.00 512.50

01.05.19.3 ACERO FY = 4200 KG/CM2 KG 1,255.95 5.62 7,058.44 0.00 0.00 0.00 1255.95 7,058.44 0.00 0.00 7,058.44

01.05.20 SARDINEL 0.00 0.00 0.00 0.00 0.00 0.00

01.05.20.1 CONCRETO EN SARDINEL F'C= 175 KG/CM2 M3 64.82 362.28 23,482.99 0.00 64.82 23,482.99 0.00 0.00 0.00 0.00 23,482.99

01.05.20.2 ENCOFRADO Y DESENCOFRADO SARDINEL M2 446.75 25.50 11,392.13 0.00 446.75 11,392.13 0.00 0.00 0.00 0.00 11,392.13

01.05.20.3 ACERO FY = 4200 KG/CM2 KG 1,831.42 5.62 10,292.58 0.00 1831.42 10,292.58 0.00 0.00 0.00 0.00 10,292.58

01.06.00 POZO PERCOLADOR 0.00 0.00 0.00 0.00 0.00 0.00

01.06.01 CIMIENTOS CORRIDOS 1:10+30% PG M3 3.10 244.15 756.87 0.00 0.00 0.00 3.10 756.87 0.00 0.00 756.87

01.06.02 CONCRETO EN TAPA FC'=210 KG/CM2 M3 1.28 483.84 619.32 0.00 0.00 0.00 1.28 619.32 0.00 0.00 619.32

01.06.03 ENCOFRADO Y DESENCOFRADO M2 15.39 45.54 700.86 0.00 0.00 0.00 15.39 700.86 0.00 0.00 700.86

01.06.04 ACERO FY = 4200 KG/CM2 KG 83.98 5.62 471.97 0.00 0.00 0.00 83.98 471.97 0.00 0.00 471.97

01.06.05 MURO DE LADRILLO EN APAREJO DE CABEZA M2 26.39 101.35 2,674.63 0.00 0.00 0.00 26.39 2,674.63 0.00 0.00 2,674.63

01.06.06 FILTRO DE PIEDRA 6" M3 1.85 110.63 204.67 0.00 0.00 0.00 1.85 204.67 0.00 0.00 204.67

01.06.07 FILTRO LATERAL DE CONFITILLO D 1/2" M3 11.13 205.94 2,292.11 0.00 0.00 0.00 11.13 2,292.11 0.00 0.00 2,292.11

01.07.00 ESTRUCTURAS METALICAS Y COBERTURAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00

01.07.01 CORREAS DE MADERA TORNILLO P2 1,032.34 9.14 9,435.59 0.00 0.00 0.00 1,032.34 9,435.59 0.00 0.00 9,435.59

01.07.02 COBERTURA C/CALAMINA TERMOACUSTICA TIPO TEJA C/ALMA ACERO M2 749.61 61.05 45,763.69 0.00 0.00 0.00 749.61 45,763.69 0.00 0.00 45,763.69

01.07.03 CUMBRERA TERMOACUSTICA C/ALMA ROJO M2 54.75 63.47 3,474.98 0.00 0.00 0.00 54.75 3,474.98 0.00 0.00 3,474.98

01.07.04 TAJA ARTESANAL DE ARCILLA M 380.00 23.99 9,116.20 0.00 0.00 0.00 380.00 9,116.20 0.00 0.00 9,116.20

01.07.05 CUBIERT. LADRILLO PASTELERO ASENTADO CON BARRO E=2" C/FRAGUA M2 22.86 59.22 1,353.77 0.00 0.00 0.00 22.86 1,353.77 0.00 0.00 1,353.77

01.07.06 ARMADURA 1 UND 12.00 11,320.60 135,847.20 0.00 0.00 0.00 12.00 135,847.20 0.00 0.00 135,847.20

01.07.07 VIGETAS V-1 GLB 1.00 38,594.43 38,594.43 0.00 0.00 0.00 1.00 38,594.43 0.00 0.00 38,594.43

01.07.08 ARRIOSTRE DE ARMADURA 1 GLB 1.00 5,169.40 5,169.40 0.00 0.00 0.00 1.00 5,169.40 0.00 0.00 5,169.40

01.07.09 ARRIOSTRE DE VIGETAS V-1 GLB 1.00 4,896.45 4,896.45 0.00 0.00 0.00 1.00 4,896.45 0.00 0.00 4,896.45

01.07.10 TEMPLADORES DE ARMADURA 1 GLB 1.00 8,449.85 8,449.85 0.00 0.00 0.00 1.00 8,449.85 0.00 0.00 8,449.85

A8
No borrar fila, contiene datos ocultos.
Page 4: Cronograma Valorizado San Andres

4/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO PRECIO (S/.) PARCIAL (S/.) Mes 01 Mes 02 Mes 03 Mes 04 Mes 05 MES 06

TotalMETRADO METRADO METRADO METRADO METRADO METRADO

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

01.07.11 COBERTURA DE POLICARBONATO M2 1,417.14 103.25 146,319.71 0.00 0.00 0.00 1,417.14 146,319.71 0.00 0.00 146,319.71

01.08.00 MUROS Y TABIQUES DE ALBAÑILERIA 0.00 0.00 0.00 0.00 0.00 0.00

01.08.01 MUROS Y TABIQUES DE ALBAÑILERIA 0.00 0.00 0.00 0.00 0.00 0.00

01.08.01.1 MURO DE LADRILLO KK TIPO IV CABEZA M:1:1:4 E=1.5 CM M2 652.49 105.04 68,537.55 0.00 326.25 34,268.77 326.25 34,268.77 0.00 0.00 0.00 68,537.55

01.08.01.2 MURO DE LADRILLO KK TIPO KK SOGA M:1:1:4 E=1.5 CM M2 3,722.60 62.34 232,066.88 0.00 1,861.30 116,033.44 1,861.30 116,033.44 0.00 0.00 0.00 232,066.88

01.08.01.3 MURO DE LADRILLO KK TIPO IV CANTO M:1:1:4 E=1.5 CM M2 60.09 52.56 3,158.33 0.00 30.05 1,579.17 30.05 1,579.17 0.00 0.00 0.00 3,158.33

01.08.01.4 ALAMBRE #08 REFUERZO HORIZONTAL EN MUROS KG 4,264.06 4.76 20,296.93 0.00 2,132.03 10,148.46 2,132.03 10,148.46 0.00 0.00 0.00 20,296.93

COSTO DIRECTO S/. 3,251,571.33 1,046,811.38 1,167,478.44 498,417.59 501,895.48 - 36,968.42 3,251,571.33

GASTOS GENERALES 6.5% S/. 211,352.14 68,042.74 75,886.10 32,397.14 32,623.21 - 2,402.95 211,352.14

UTILIDAD 10% S/. 325,157.13 104,681.14 116,747.84 49,841.76 50,189.55 - 3,696.84 325,157.13

SUB PRESUPUESTO 3,788,080.60 1,219,535.26 1,360,112.38 580,656.50 584,708.23 - 43,068.21 3,788,080.60

IGV 18% S/. 681,854.51 219,516.35 244,820.23 104,518.17 105,247.48 - 7,752.28 681,854.51

SUBPRESUPUESTO 1 S/. 4,469,935.11 1,439,051.61 1,604,932.61 685,174.67 689,955.71 - 50,820.49 4,469,935.11

SUPERVICION Y LIQUIDACION 4.5% S/. 201,147.08 64,757.32 72,221.97 30,832.86 31,048.01 - 2,286.92 201,147.08

TOTAL PRESUPUESTO S/. 4,671,082.19 1,503,808.93 1,677,154.58 716,007.53 721,003.72 - 53,107.41 4,671,082.19

% DE AVANCE DE OBRA PROGRAMADO 32.19% 35.91% 47.61% 15.44% 0.00% 1.14%

A8
No borrar fila, contiene datos ocultos.
Page 5: Cronograma Valorizado San Andres

5/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO PRECIO (S/.) PARCIAL (S/.) Mes 01 Mes 02 Mes 03 Mes 04 Mes 05 Mes 06

Total

METRADO METRADO METRADO METRADO METRADO METRADO

02.00.00 ARQUITECTURA

02.01.00 REVOQUES ENLUCIDOS Y MOLDURAS

02.01.01 TARRAJEO EN MURO INTERIOR Y EXTERIOR M2 8259.41 18.34 151,477.58 0.00 0.00 0.00 4129.705 75738.79 4129.705 75738.79 0.00 151,477.58

02.01.02 TARRAJEO EN MUROS EXTERIORES APARTIR DEL 2do PISO M2 120.27 26.80 3,223.24 0.00 0.00 0.00 0.00 120.27 3223.24 0.00 3,223.24

02.01.03 TARRAJEO EN MUROS E CONCRETO (1:5) M2 978.23 21.34 20,875.43 0.00 0.00 0.00 0.00 978.23 20875.43 0.00 20,875.43

02.01.04 TARRAJEO DE COLUMNAS M2 1,718.18 27.71 47,610.77 0.00 0.00 0.00 859.09 23805.38 859.09 23805.38 0.00 47,610.77

02.01.05 TARRAJEO DE VIGAS M2 1,114.73 37.82 42,159.09 0.00 0.00 0.00 557.37 21079.54 557.37 21079.54 0.00 42,159.09

02.01.06 TARRAJEO PRIMARIO MORTERO C:A 1:5 M2 617.26 17.46 10,777.36 0.00 0.00 0.00 617.26 10777.36 0.00 0.00 10,777.36

02.01.07 TARRAJEO CON IMPERMEABILIZANTE M2 72.40 26.55 1,922.22 0.00 0.00 0.00 0.00 72.40 1922.22 0.00 1,922.22

02.01.08 VESTIDURA DE DERRAMES (1:5) EN PUERTAS, VENTANAS Y VANOS. M 526.43 10.42 5,485.40 0.00 0.00 0.00 0.00 263.22 2742.70 263.215 2,742.70 5,485.40

02.01.09 VESTIDURA DE DERRAMES CON BORDES BOLEADOS M 1:2 M 2,832.70 15.27 43,255.33 0.00 0.00 0.00 0.00 1,416.35 21627.66 1416.35 21,627.66 43,255.33

02.01.10 BRUÑAS SEGUN DETALLE (1 X1 CM) M 4,395.03 5.35 23,513.41 0.00 0.00 0.00 0.00 2,197.52 11756.71 2197.515 11,756.71 23,513.41

02.01.11 TARRAJEO PULIDO EN SARDINEL DE CONCRETO M2 540.17 19.46 10,511.71 0.00 0.00 0.00 0.00 0.00 540.17 10,511.71 10,511.71

02.02.00 CIELORRASOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.02.01 CIELO RASO CON MEZCLA C:A 1:5 M2 1,166.57 29.84 34,810.45 0.00 0.00 0.00 0.00 1,166.57 34810.45 0.00 34,810.45

02.02.02 VESTIDURA EN FONDO DE ESCALERA M2 29.31 30.54 895.13 0.00 0.00 0.00 0.00 29.31 895.13 0.00 895.13

02.03.00 PISOS Y PAVIMENTOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.03.01 FALSO PISO MEZCLA C:H 1:8 E=4" M2 606.74 34.75 21,084.22 0.00 0.00 0.00 0.00 606.74 21084.22 0.00 21,084.22

02.03.02 CONTRAPISO DE 40 MM. M2 1017.51 24.17 24,593.22 0.00 0.00 0.00 0.00 1,017.51 24593.22 0.00 24,593.22

02.03.03 VEREDA CONCRETO F'C=175 KG/CM2 E=4" FROT. Y BRUÑADO M2 2281.18 51.67 117,868.57 0.00 0.00 0.00 0.00 1,140.59 58934.29 1140.59 58,934.29 117,868.57

02.03.04 SARDINEL EN URINARIO REVEST. CON CERAMICA (H=0.30M) M 2.35 81.69 191.97 0.00 0.00 0.00 0.00 0.00 2.35 191.97 191.97

02.03.05 PISO CERAMICO 30X30 SERIE COLOR NACIONAL M2 1034.7 46.54 48,154.94 0.00 0.00 0.00 0.00 34.70 1614.94 1000.00 46,540.00 48,154.94

02.03.06 VEREDA CON ADOQUINES 10x20 e=6 CM M2 2175.96 67.4 146,659.70 0.00 0.00 0.00 0.00 175.96 11859.70 2000.00 134,800.00 146,659.70

02.03.07 PISO DE CEMENTO PULIDO Y BRUÑADO E=2" S/COLOREAR M2 25.42 28.83 732.86 0.00 0.00 0.00 0.00 0.00 25.42 732.86 732.86

02.04.00 CONTRAZOCALOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.04.01 CONTRAZOCALO CERAMICO 10x30 M 584.50 9.23 5,394.94 0.00 0.00 0.00 0.00 0.00 584.50 5,394.94 5,394.94

02.04.02 CONTR. S/COLOREAR H =20 CM MZ 1:2 E=1.5 CM M 156.19 9.36 1,461.94 0.00 0.00 0.00 0.00 0.00 156.19 1,461.94 1,461.94

02.04.03 CONTR. S/COLOREAR H =30 CM MZ 1:2 E=1.5 CM M 595.45 11.44 6,811.95 0.00 0.00 0.00 0.00 0.00 595.45 6,811.95 6,811.95

02.04.04 CONTR. S/COLOREAR H =55 CM MZ 1:2 E=1.5 CM M 388.50 14.48 5,625.48 0.00 0.00 0.00 0.00 0.00 388.50 5,625.48 5,625.48

02.04.05 CONTRAZOCALO RECTO DE ESCALERA M 35.52 13.36 474.55 0.00 0.00 0.00 0.00 35.52 474.55 0.00 474.55

02.05.00 ZOCALOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.05.01 ZOCALO DE CERAMICO 20x30 M2 613.22 50.31 30,851.10 0.00 0.00 0.00 0.00 13.22 665.10 600.00 30,186.00 30,851.10

02.06.00 REVESTIMIENTO EN ESCALINATAS Y ESCALERAS 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.06.01 REVEST. C/CEMENTO PULIDO PASO Y CONTRAPASO M 2,093.05 27.15 56,826.31 0.00 0.00 0.00 0.00 1,046.53 28413.15 1046.525 28,413.15 56,826.31

02.06.02 ACABAO DE DESCANSO CEMENTO PULIDO Y RUÑADO M2 17.51 26.13 457.54 0.00 0.00 0.00 0.00 17.51 457.54 0.00 457.54

02.07.00 CARPINTERIA DE MADERA 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.07.01 PUERTA CN C/TABLEROS DE MADERA CEDRO M2 80.19 354.27 28,408.91 0.00 0.00 0.00 0.00 0.00 80.19 28,408.91 28,408.91

02.07.02 PTA.CN C/TRIP.6mm (1.4x0.6),CAB.SSHH.780 M2 25.08 223.79 5,612.65 0.00 0.00 0.00 0.00 0.00 25.08 5,612.65 5,612.65

02.07.03 PUERTA CEDRO C/TABLERO C/SOBRE LUZ EN SS HH M2 3.78 332.97 1,258.63 0.00 0.00 0.00 0.00 0.00 3.78 1,258.63 1,258.63

02.07.04 VENTANA CEDRO M2 254.23 193.73 49,251.98 0.00 0.00 0.00 0.00 0.00 254.23 49,251.98 49,251.98

02.07.05 TICERO DE MADERA CEDRO (L=5 M) BARNIZADO UND 9.00 213.49 1,921.41 0.00 0.00 0.00 0.00 0.00 9.00 1,921.41 1,921.41

02.07.06 ESTANTRIA PARA LIBROS (2.00 x 0.35 M) UND 30.00 427.08 12,812.40 0.00 0.00 0.00 0.00 0.00 30.00 12,812.40 12,812.40

02.08.00 CARPINTERIA METALICA Y HERRERIA 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.08.01 PUERTA CASETA DE ELECTROBOMBA(CISTERNA Y TAQ. ELEVADO) UND 1.00 220.67 220.67 0.00 0.00 0.00 0.00 0.00 1.00 220.67 220.67

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

VALORIZACION MENSUAL

A8
No borrar fila, contiene datos ocultos.
Page 6: Cronograma Valorizado San Andres

6/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO PRECIO (S/.) PARCIAL (S/.) Mes 01 Mes 02 Mes 03 Mes 04 Mes 05 Mes 06

Total

METRADO METRADO METRADO METRADO METRADO METRADOVALORIZACION

MENSUALVALORIZACION

MENSUALVALORIZACION

MENSUALVALORIZACION

MENSUALVALORIZACION

MENSUALVALORIZACION

MENSUAL

02.08.02 VENTANA DE FIERRO TIPO REJA UND 1.00 75.00 75.00 0.00 0.00 0.00 0.00 0.00 1.00 75.00 75.00

02.08.03 ESCALERA DE GATO DE TUBO DE FIERRO GALVANIZADO D 1 1/2" Y 1" M 10.00 135.25 1,352.50 0.00 0.00 0.00 0.00 0.00 10.00 1,352.50 1,352.50

02.08.04 ESCALERA GATO EMPOTRADA DE ALUMINIO P/CISTERNA UND 1.00 319.77 319.77 0.00 0.00 0.00 0.00 0.00 1.00 319.77 319.77

02.08.05 PASAMANOS DE TUBO DE FºGº DE 2" EN ESCALERAS M 565.92 68.85 38,963.59 0.00 0.00 0.00 0.00 0.00 565.92 38,963.59 38,963.59

02.08.06 CANTONERA DE FIERRO EN ESCALERA M 90.40 34.83 3,148.63 0.00 0.00 0.00 0.00 0.00 90.40 3,148.63 3,148.63

02.08.07 PORTON DE INGRESO METALICO M2 61.46 215.13 13,221.89 0.00 0.00 0.00 0.00 0.00 61.46 13,221.89 13,221.89

02.08.08 VENTANA METALICA C/MALLA COCADA 3/8" M2 21.86 55.00 1,202.30 0.00 0.00 0.00 0.00 0.00 21.86 1,202.30 1,202.30

02.08.09 CERCO DE MALLA TEJIDA 2"x2" C/PERF. COLUM. FºGº ESTÁNDAR 3" M2 224.00 181.62 40,682.88 0.00 0.00 0.00 0.00 0.00 224.00 40,682.88 40,682.88

02.08.10 MARCO Y TAPA DE FIERRO 0.80x0.80 P/TANQ. CISTERNA APOYADO UND 1.00 168.26 168.26 0.00 0.00 0.00 0.00 0.00 1.00 168.26 168.26

02.09.00 CERRAJERIA 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.09.01 BISAGRA DE ACERO ALUMINIZADA DE 4" PESADA EN PUERTA PZA 200.00 4.15 830.00 0.00 0.00 0.00 0.00 0.00 200.00 830.00 830.00

02.09.02 BISAGRA DE ACERO ALUMINIZADA DE 2.5" PESADA EN VENTANAS/PUERTA PZA 584.00 13.15 7,679.60 0.00 0.00 0.00 0.00 0.00 584.00 7,679.60 7,679.60

02.09.03 CERRADURA DOS GOLPES CON TIRADOR PZA 2.00 81.60 163.20 0.00 0.00 0.00 0.00 0.00 2.00 163.20 163.20

02.09.04 CERRADURA DOS GOLPES EN PUERTAS PZA 41.00 66.37 2,721.17 0.00 0.00 0.00 0.00 0.00 41.00 2,721.17 2,721.17

02.09.05 CERRADURA SAPITO SEGURIDAD BAT. VENTANAS UND 226.00 14.87 3,360.62 0.00 0.00 0.00 0.00 0.00 226.00 3,360.62 3,360.62

02.09.06 MANIJA DE BRONCE 4" PARA PUERTAS PZA 41.00 10.02 410.82 0.00 0.00 0.00 0.00 0.00 41.00 410.82 410.82

02.09.07 CANDADO TIPO FORTE 60 MM UND 2.00 28.00 56.00 0.00 0.00 0.00 0.00 0.00 2.00 56.00 56.00

02.10.00 VIDRIOS, CRISTALES Y SIMILARES 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.10.01 VIDRIOS SEMIDOBLES IMPORTADOS P2 2,736.50 2.36 6,458.14 0.00 0.00 0.00 0.00 2,000.00 4720.00 736.50 1,738.14 6,458.14

02.11.00 PINTURA 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.11.01 SELLADO DE CONCRETO EXPUESTO M2 1,353.72 7.04 9,530.19 0.00 0.00 0.00 0.00 676.86 4765.09 676.86 4,765.09 9,530.19

02.11.02 PINTURA LATEX 2 MANOS EN MUROS Y COLUMNA M2 4,982.80 7.16 35,676.85 0.00 0.00 0.00 0.00 2,491.40 17838.42 2,491.40 17,838.42 35,676.85

02.11.03 PINTURA LATEX 2 MANOS EN CIELO RASO Y VIGAS M2 2,301.98 7.94 18,277.72 0.00 0.00 0.00 0.00 1,150.99 9138.86 1,150.99 9,138.86 18,277.72

02.11.04 PINTURA EN PUERTAS C/BARNIZ 2 MANOS M2 91.95 15.75 1,448.21 0.00 0.00 0.00 0.00 45.98 724.11 45.98 724.11 1,448.21

02.11.05 PINTURA ANTICORROSIVA Y ESM. EN BARANDAS M 565.92 5.80 3,282.34 0.00 0.00 0.00 0.00 282.96 1641.17 282.96 1,641.17 3,282.34

02.11.06 PINTURA ESMALTE 2 MANOS EN CONTRAZOCALOS M2 466.26 12.60 5,874.88 0.00 0.00 0.00 0.00 233.13 2937.44 233.13 2,937.44 5,874.88

02.11.07 PINTURA ESMALTE DOS MANOS EN CARPINTERIA METALICA M2 311.22 10.81 3,364.29 0.00 0.00 0.00 0.00 155.61 1682.14 155.61 1,682.14 3,364.29

02.11.08 PINTURA DEMARCACION DE LOSA DEPORTIVA M 261.98 2.88 754.50 0.00 0.00 0.00 0.00 130.99 377.25 130.99 377.25 754.50

02.12.00 VARIOS 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.12.01 JUNTA DE DILATACIÒN CON ESPUMA PLASTICA+JEBE MICROPOROSO M 729.61 10.43 7,609.83 0.00 0.00 0.00 0.00 600.00 6258.00 129.61 1,351.83 7,609.83

02.12.02 JUNTA DE DILATACION RELLENO CON MORTERO ASFALTICO E=1" M 2,016.36 7.99 16,110.72 0.00 0.00 0.00 0.00 0.00 2,016.36 16,110.72 16,110.72

02.12.03 TAPA JUNTA METALICA ENTRE ESCALERA Y MUDOLOS M 39.92 69.13 2,759.67 0.00 0.00 0.00 0.00 0.00 39.92 2,759.67 2,759.67

02.12.04 TAPA JUNTA METALICA EN PISOS M 22.00 87.11 1,916.42 0.00 0.00 0.00 0.00 0.00 22.00 1,916.42 1,916.42

02.12.05 PIZARRA CEMENTO 5.0X1.20 SIN TICERO PZA 9.00 188.91 1,700.19 0.00 0.00 0.00 0.00 5.00 944.55 4.00 755.64 1,700.19

02.12.06 ARCOS TABLERO FULBITO Y BASQUET (MADERA Y METAL) UND 2.00 1,820.63 3,641.26 0.00 0.00 0.00 0.00 0.00 2.00 3,641.26 3,641.26

02.12.07 TUBOS C. VOLEY,INCL. RED Y DADOS DE CONCRETO JGO 1.00 329.66 329.66 0.00 0.00 0.00 0.00 0.00 1.00 329.66 329.66

02.12.08 MESA C.A REVESTIDO CON CERAMICA M2 5.10 651.71 3,323.72 0.00 0.00 0.00 0.00 5.10 3323.72 0.00 3,323.72

02.12.09 GRUTA GLB 1.00 6,000.00 6,000.00 0.00 0.00 0.00 0.00 1.00 6000.00 0.00 6,000.00

02.12.10 BASUREROS METALICOS UND 10.00 75.00 750.00 0.00 0.00 0.00 0.00 10.00 750.00 0.00 750.00

02.12.11 ASTA DE BANDERA TIPICA PZA 1.00 1,100.19 1,100.19 0.00 0.00 0.00 0.00 1.00 1100.19 0.00 1,100.19

02.12.12 SEMBRADO DE PLANTONES UND 216.00 31.68 6,842.88 0.00 0.00 0.00 0.00 0.00 216.00 6,842.88 6,842.88

02.13.00 EQUIPAMIENTO 0.00 0.00 0.00 0.00 0.00 0.00 0.00

02.13.01 MOBILIARIO ESCOILAR 1º Y 2º (1 AULA)(1 MESA+2 SILLAS) MOD 60.00 208.05 12,483.00 0.00 0.00 0.00 0.00 0.00 60.00 12,483.00 12,483.00

02.13.02 MOBILIARIO ESCOILAR 3º A 6º (1 AULA)(1 MESA+1 SILLAS) MOD 120.00 132.03 15,843.60 0.00 0.00 0.00 0.00 0.00 120.00 15,843.60 15,843.60

A8
No borrar fila, contiene datos ocultos.
Page 7: Cronograma Valorizado San Andres

7/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO PRECIO (S/.) PARCIAL (S/.) Mes 01 Mes 02 Mes 03 Mes 04 Mes 05 Mes 06

Total

METRADO METRADO METRADO METRADO METRADO METRADOVALORIZACION

MENSUALVALORIZACION

MENSUALVALORIZACION

MENSUALVALORIZACION

MENSUALVALORIZACION

MENSUALVALORIZACION

MENSUAL

02.13.03 MOBILIARIO ESCOILAR PROFESORES (1 MESA+1 SILLAS) MOD 6.00 248.22 1,489.32 0.00 0.00 0.00 0.00 0.00 6.00 1,489.32 1,489.32

02.13.04 MOBILIARIO PARA CRAEP MOD 6.00 388.45 2,330.70 0.00 0.00 0.00 0.00 0.00 6.00 2,330.70 2,330.70

02.13.05 MOBILIARIO DE AREAS ADMINISTRATIVAS MOD 9.00 347.45 3,127.05 0.00 0.00 0.00 0.00 0.00 9.00 3,127.05 3,127.05

02.13.06 MOBILIARIO PARA SALA DE COMPUTO MOD 30.00 347.45 10,423.50 0.00 0.00 0.00 0.00 0.00 30.00 10,423.50 10,423.50

02.13.07 COMPUTADORAS INCL. ACCESORIOS UND 30.00 1,500.00 45,000.00 0.00 0.00 0.00 0.00 0.00 30.00 45,000.00 45,000.00

COSTO DIRECTO S/. 1,304,998.12 - - - 131,401.08 428,774.89 744,822.11 1,304,998.12

GASTOS GENERALES 6.5% S/. 84,824.88 - - - 8,541.07 27,870.37 48,413.44 84,824.88

UTILIDAD 10% S/. 130,499.81 - - - 13,140.11 42,877.49 74,482.21 130,499.81

SUB PRESUPUESTO S/. 1,520,322.81 - - - 153,082.26 499,522.75 867,717.75 1,520,322.81

IGV 18% S/. 273,658.11 - - - 27,554.81 89,914.09 156,189.20 273,658.11

SUB PRESUPUESTO 1 S/. 1,793,980.92 - - - 180,637.06 589,436.84 1,023,906.95 1,793,980.92

SUPERVICION Y LIQUIDACION 4.5% S/. 80,729.14 - - - 8,128.67 26,524.66 46,075.81 80,729.14

TOTAL PRESUPUESTO S/. 1,874,710.06 - - - 188,765.73 615,961.50 1,069,982.76 1,874,710.06

% DE AVANCE DE OBRA PROGRAMADO 0.00% 0.00% 0.00% 10.07% 32.86% 57.07%

A8
No borrar fila, contiene datos ocultos.
Page 8: Cronograma Valorizado San Andres

8/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO

03.00.00 INSTALACIONES SANITARIAS

03.01.00 APARATOS SANITARIOS

03.01.02 INODORO TANQUE BAJO DE LOSA 1ERA CALIDAD (NAC. BLANCO) PZA 34.00

03.01.04 URINARIO PICO DE LORO DE LOSA VITRIFICADA PZA 14.00

03.01.07 LAVATORIO DE LOSA BLANCA DE PRIMERA 545x460 mm PZA 38.00

03.02.00 ACCESORIOS SANITARIOS

03.02.01 ACCESORIOS DE W.C TANQUE ALTO+TUB. BAJADA UND 34.00

03.02.02 GRIFERIA PARA URINARIO UND 14.00

03.02.04 GRIFERIA PARA LAVATORIO UND 38.00

03.02.06 PAPELERA DE PARED UND 9.00

03.02.07 COLOCACION DE APARATOS SANITARIOS PZA 86.00

03.03.00 INSTALACIONES DE DESAGUE

03.03.01 EMPALME A RED EXISTENTE DESAGUE UND 1.00

03.03.02 SALIDAS DE PVC SAL PARA DESAGUE DE 2" PTO 35.00

03.03.03 SALIDAS DE PVC SAL PARA DESAGUE DE 4" PTO 34.00

03.03.04 SALIDAS DE PVC SAL PARA DESAGUE DE 6" PTO 25.00

03.03.05 SALIDA PARA VENTILACION PTO 10.00

03.03.06 SOMBRERO VENTILACION PVC DE 2" PZA 10.00

03.03.07 EXCAVACION DE ZANJAS PARA REDES EXT. SANIT. M3 45.51

03.03.08 RELLENO MANUAL CON MATERIAL PROPIO (REDES EXT. SANT.) M3 27.35

03.03.09 TUBERIA DE PVC SAL 2" M 134.11

03.03.10 TUBERIA PVC SAL 4" M 65.73

03.03.11 TUBERIA PVC SAL 6" M 111.88

03.03.12 TUBERIA DE BAJADA PVC SAL 3" P/LLUVIAS M 127.46

03.03.13 SUMIDERO DE BRONCE Ø 2" UND 5.00

03.03.14 SUMIDERO DE BRONCE Ø 3" UND 9.00

SUMIDERO PLUVIAL Ø 3" UND 28.00

03.03.15 REGISTRO ROSCA DE BRONCE 3" UND 27.00

03.03.16 CAJA SUMIDERO CON REJILLA DE FIERRO UND 14.00

03.03.17 UND 41.00

03.03.18 UND 25.00

03.03.19 UND 6.00

03.03.20 UND 4.00

03.03.21 UND 24.00

03.03.22 YEE 4 ° UND 25.00

03.03.23 YEE 6° UND 13.00

03.03.24 UND 25.00

03.03.25 TEE 4° UND 29.00

03.03.26 UND 5.00

03.03.27 REDUCCION 4° Y 6° UND 5.00

03.03.28 REDUCCION 2° Y 4° UND 7.00

03.03.29 REDUCCION 2° Y 3° UND 9.00

03.03.30 CAJA DE REGISTRO DE DESAGUE 10" X 20" UND 3.00

03.03.31 CAJA DE REGISTRO DE DESAGUE 12" X 24" UND 6.00

03.04.00 INSTALACIONES DE AGUA

03.04.01 EMPALME A RED EXISTENTE AGUA UND 1.00

CODO 90° 2"

CODO 90° 4"

CODO DE 45° 2''

CODO DE 45° 4''

YEE 2 °

TEE 2°

REDUCCION 2° Y 6°

A8
No borrar fila, contiene datos ocultos.
Page 9: Cronograma Valorizado San Andres

9/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO

03.04.02 SALIDA DE AGUA FRIA CON TUBERIA DE PVC-SAP 1/2" PTO 101.00

03.04.03 TUBERIA PVC CLASE 10- 1/2" ROSCADA M 170.77

03.04.04 TUBERIA PVC CLASE 10- 3/4" ROSCADA M 50.09

TUBERIA PVC CLASE 10- 1" ROSCADA M 6.60

03.04.05 TUBERIA PVC CLASE 10- 1 1/4" ROSCADA M 36.39

03.04.06 TUBERIA PVC CLASE 10- 1 1/2" ROSCADA M 42.26

03.04.07 TUBERIA PVC CLASE 10- 2" ROSCADA M 50.95

TUBERIA PVC CLASE 10 - 2 1/2" ROSCADA M 37.50

UND 81.00

UND 14.00

UND 3.00

UND 2.00

UND 7.00

UND 3.00

UND 3.00

TEE 1/2'' UND 10.00

TEE 3/4'' UND 17.00

TEE 1'' UND 4.00

TEE 1 1/4'' UND 2.00

TEE 1 1/2'' UND 18.00

TEE 2'' UND 8.00

TEE 2 1/2'' UND 22.00

RE3/4"X1/2" UND 34.00

RE3/4"X1" UND 6.00

RE1"X1/2" UND 3.00

RE1"X3/4" UND 6.00

REC 1 1/4"X3/4" UND 3.00

RE11/2"X1" UND 4.00

RE11/2"X3/4" UND 3.00

RE 1 1/2'' X 1/2" UND 34.00

RE 1 1/2'' X 1 1/4" UND 1.00

RE2"X1 1/2" UND 7.00

RE2 1/2"X1 1/2" UND 21.00

RE2 1/2"X2" UND 2.00

03.04.08 VALVULA DE COMPUERTA DE 1/2" UND 5.00

03.04.09 VALVULA DE COMPUERTA 3/4" UND 10.00

VALVULA DE COMPUERTA 1" UND 5.00

VALVULA DE COMPUERTA 1 1/4" UND 0.00

VALVULA DE COMPUERTA 1 1/2" UND 5.00

VALVULA DE COMPUERTA 2" UND 2.00

UNION UNIVERSAL DE 1/2" UND 10.00

UNION UNIVERSAL DE 3/4" UND 20.00

UNION UNIVERSAL DE 1" UND 8.00

UNION UNIVERSAL DE 1 1/4" UND 0.00

UNION UNIVERSAL DE 1 1/2" UND 10.00

UNION UNIVERSAL DE 2" UND 4.00

CODO 90° 1/2"

CODO 90° 3/4"

CODO 90° 1"

CODO 90° 1 1/4"

CODO 90° 1 1/2"

CODO 90° 2"

CODO 90° 2 1/2"

A8
No borrar fila, contiene datos ocultos.
Page 10: Cronograma Valorizado San Andres

10/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO

LLAVE DE RIEGO C/GRIFO 1/2" EN CAJA DE CONCRETO FC=175KG/CM2 UND 13.00

03.04.12 CAJA PARA VALVULA (NICHO DE MAYOLICA) UND 17.00

03.04.13 ROMPE AGUA UND 1.00

03.04.14 TUBERIA Y ACCESORIOS REBOSE Y LIMPIEZA TANQUE ELEVADO GLB 1.00

03.04.15 ACCESORIO Y TUBO DE AGUA EN TANQUE ELEVADO Y CISTERNA GLB 1.00

03.04.16 EQUIPO DE BOMBEO 2 ELECTROBOMBAS 4 HP GLB 1.00

A8
No borrar fila, contiene datos ocultos.
Page 11: Cronograma Valorizado San Andres

11/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO

04.00.00 INSTALACIONES ELECTRICAS

04.01.00 INSTALACIONES ELECTRICAS

04.01.01 CONEXION A RED EXISTENTE UND 1.00

04.01.02 SALIDA DE TECHO (CENTRO DE LUZ) PTO 167.00

04.01.03 SALIDA PARA BRAQUET(PARED) PTO 13.00

04.01.04 CABLE DE LUZ DE 2.5 mm M 2657.64

04.01.05 CABLE DE LUZ DE 4 mm M 1736.288

04.01.06 CABLE DE LUZ DE 6 mm M 458.95

04.01.07 INTERRUPTOR DE 01 GOLPE PTO 44.00

04.01.08 INTERRUPTOR DE 02 GOLPES PTO 28.00

04.01.09 INTERRUPTOR DE 03 GOLPES PTO 2.00

04.01.10 INTERRUPTOR DE DOBLE COMUTADOR PTO 8.00

04.01.11 SALIDA TOMACORRIENTE DOBLE CON LINEA DE TIERRA PTO 203.91

04.01.12 POZO PUESTA TIERRA UND 6.00

04.02.00 SALIDA PARA COMUNICACIONES Y SENALES

04.02.01 SALIDA PARA TIMBRE PTO 1.00

04.03.00 CANALIZACION Y/O TUBERIAS

04.03.01 EXCAVACION DE ZANJAS PARA REDES EXT. ELECT. M3 93.29

04.03.02 RELLENO MANUAL CON MATERIAL PROPIO (REDES EXT. ELECT.) M3 93.29

04.03.03 TUBERIA PVC SEL 20 mm PARA INST. UND 1,820.52

04.03.04 TUBERIA PVC SEL 25 mm PARA INST. UND 105.00

04.04.00 CAJAS

04.04.01 CAJA PASE FºGº 4x4x2.5" UND 398.00

04.05.00 TABLEROS Y CUCHILLAS(LLAVES)

04.05.01 TABLERO AUT. 5-2X15A;2-2x20A(TD-1) UND 1.00

04.05.02 TABLERO AUT. 5-2X15A;5-2x20A(TD-2) UND 1.00

04.05.03 TABLERO AUT. 5-2X15A;5-2x20A(TD-3) UND 1.00

04.05.04 TABLERO AUT. 5-2X15A;5-2x20A(TD-4) UND 1.00

04.05.05 TABLERO AUT. 5-2X15A;5-2x20A(TD-5) UND 1.00

04.05.06 TABLERO AUT. 5-2X15A;5-2x20A(TD-6) UND 1.00

TABLERO AUT. 5-2X15A;5-2x20A(TD-7) UND 1.00

TABLERO AUT. 5-2X15A;5-2x20A(TD-8) UND 1.00

TABLERO AUT. 5-2X15A;5-2x20A(TD-9) UND 1.00

TABLERO AUT. 5-2X15A;5-2x20A(TD-10) UND 1.00

04.05.07 TABLERO AUT. 5-2X15A;5-2x20A(TD-11) UND 1.00

04.05.08 TABLERO AUT. 5-2X15A;5-2x20A(TG) UND 1.00

04.06.00 CONEXIONES A RED EXTERNA Y MEDIDORES

04.06.01 ALIMENTADOR CABLE 6 mm2 M 458.95

ALIMENTADOR CABLE 10 mm2 M 0.00

04.06.02 ALIMENTADOR CABLE 16 mm2 M 0.00

04.06.03 ALIMENTADOR CABLE 50 mm2 M 20.00

04.07.00 ARTEFACTOS

04.07.01 ARTEFACTO FLUORESCENTE 3/36 W (SIM. BE JOSFEL) C/SOPORTE UND 128.00

04.07.02 ARTEFACTO FLUORESCENTE 2/36 W (SIM. BE JOSFEL) C/SOPORTE UND 34.00

04.07.03 ARTEFACTO FLUORESCENTE CIRCULAR DE 20W UND 9.00

04.07.06 BRAQUETE REFLECTOR C/LAMP. 2x18W AHORRAD.SIM JOSFEL RSP-2 UND 18.00

A8
No borrar fila, contiene datos ocultos.
Page 12: Cronograma Valorizado San Andres

12/12

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA

OBRA: MEJORAMIENTO DE LA INFRAESTRUCTURA EN LA I.E. 10340 SAN ANDRES DISTRITO DE SAN ANDRES DE CUTERVO-CUTERVO-CAJAMARCA

LUGAR: SAN ANDRES-CUTERVO-CAJAMARCA

FECHA: Apr-11

PARTIDA DESCRIPCION UND METRADO

04.07.07 CAMPANILLA DE TIMBRE DE 4" CON TRANSFORMADOR 220/12V UND 1.00

04.07.08 SALIDA PARA POSTES DE LUZ(FAROLA DE 2 SALIDAS) UND 6.00

04.07.09 FAROLA DECO SPC 70+EQ SON I 70W E27 UND 10.00

04.07.11 ARM. T MONT. DE POSTE METALICO H=8.00 M D=6" UND 6.00