PROGRAMACION DE OBRA OBRA : “MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS EN LA INSTITUCION EDUCATIVA N° 1545 MARIA MONTESSORI DE ANTICONA, DISTRITO CHIMBOTE, PROVINCIA SANTA ANCASH " FECHA DE TERMINO : 14/03/2016 PARTIDAS METRADO DIAS DICIEMBRE ENERO FEBRERO MARZO M J V S L M M J V S L M M J V S L M M V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L 9 10 11 12 14 15 16 17 18 19 21 22 23 24 25 26 28 29 30 31 2 4 5 6 7 8 9 11 12 13 14 15 16 18 19 20 21 22 23 25 26 27 28 29 30 1 2 3 4 5 6 8 9 10 11 12 13 15 16 17 18 19 20 22 23 24 25 26 27 29 1 2 3 4 5 7 8 9 10 11 12 14 INSTITUCION EDUCATIVA ° 1545 MARIA MONTESSORI DE ANTICONA 01 OBRAS PROVISIONALES 01.01 CARTEL DE OBRA 1.00 1 01.02 CASETA, OFICINA, CASETA, SS.HH 1.00 1 01.03 LIMPIEZA DE TERRENO 308.09 1 01.04 TRAZOS, NIVELES Y REPLANTEO 308.09 1 01.05 NIVELACION DE TERRENO 308.09 1 01.06 EXCAVACION DE ZAPATA 80.79 11 01.09 EXCAVACION DE ZANJAS 64.56 8 02 RELLENO 21.90 3 02.01 ELIMINACION MATERIAL EXCEDENTE 218.18 1 02.02 SOLADOS CONCRETO f``c=100 kg/cm2 E=4" 48.77 1 02.03 FALSA ZAPATA 1:8 + 30% PM C-H 53.86 2 02.04 CIMIENTO 16.22 1 02.05 CONCRETO VEREDAS Y LOSAS F'C=140KG/CM2 E=4" ACABADO 1:2 GRUÑADO INC. CURADO 522.59 5 02.06 ENCOFRADO Y DESENCOFRADO P/ VEREDAS 36.40 3 03 CONCRETO f`'c=210 kg/cm2 EN ZAPATAS 32.32 1 03.01 ACERO CORRUGADO fy=4200 kg/cm2 EN ZAPATAS 696.24 3 03.02 CONCRETO EN VIGAS DE CIMENTACION f'`c=210 kg/cm2 23.19 1 03.03 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE CIMENTACION 183.07 18 03.04 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 2,622.35 10 03.05 CONCRETO f'c=210 KG/CM2 EN SOBRECIMIENTOS REFORZADOS 12.11 1 03.06 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS REFORZADOS 132.52 9 03.07 CONCRETO f'c=210 kg/cm2 PARA COLUMNAS 14.61 1 03.08 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 141.31 14 03.09 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 3,621.37 14 03.10 CONCRETO EN VIGAS PERALTADAS F'C=210 kg/cm2 20.41 1 04 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS PERALTADAS 90.85 9 04.01 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 2,899.20 12 04.02 CONCRETO EN LOSAS ALIGERADAS f'c=210 kg/cm2 18.40 1 04.03 ENCOFRADO Y DESENCOFRADO PARA LOSAS ALIGERADAS 255.45 11 05 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 1,475.31 6 05.01 LADRILLO HUECO DE ARCILLA h=0.15 cm PARA TECHO ALIGERADO 2,091.60 1 05.02 CONCRETO f´c=175 kg/cm2 PARA COLUMNETAS 2.76 1 06 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS 34.13 3 ENTIDAD EJECUTORA : SUB REGION PACIFICO SUPERVISOR DE OBRA : ING. JUAN CARLOS RODRIGUEZ MIRANDA RESIDENTE DE OBRA : ING.HAMILTON BONIFACIO AMES MONTO DE OBRA : S/. 454 530.90 MODALIDAD : ADMINISTRACION DIRECTA TIEMPO DE EJECUCIÓN : 270 DIAS CALENDARIOS FECHA DE INICIO : 09/12/2015

description

Diagrama Gant Costos y presupuestos

Transcript of Diagrama Gant Costos y presupuestos

Page 1: Diagrama Gant Costos y presupuestos

PROGRAMACION DE OBRA

OBRA : “MEJORAMIENTO DE LOS SERVICIOS EDUCATIVOS EN LA INSTITUCION EDUCATIVA N° 1545 MARIA MONTESSORI DE ANTICONA, DISTRITO CHIMBOTE, PROVINCIA SANTA ANCASH "

FECHA DE TERMINO : 14/03/2016

N° PARTIDAS METRADO DIAS

DICIEMBRE ENERO FEBRERO MARZO

M J V S L M M J V S L M M J V S L M M V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L M M J V S L

9 10 11 12 14 15 16 17 18 19 21 22 23 24 25 26 28 29 30 31 2 4 5 6 7 8 9 11 12 13 14 15 16 18 19 20 21 22 23 25 26 27 28 29 30 1 2 3 4 5 6 8 9 10 11 12 13 15 16 17 18 19 20 22 23 24 25 26 27 29 1 2 3 4 5 7 8 9 10 11 12 14

INSTITUCION EDUCATIVA ° 1545 MARIA MONTESSORI DE ANTICONA

01 OBRAS PROVISIONALES

01.01 CARTEL DE OBRA 1.00 1

01.02 CASETA, OFICINA, CASETA, SS.HH 1.00 1

01.03 LIMPIEZA DE TERRENO 308.09 1

01.04 TRAZOS, NIVELES Y REPLANTEO 308.09 1

01.05 NIVELACION DE TERRENO 308.09 1

01.06 EXCAVACION DE ZAPATA 80.79 11

01.09 EXCAVACION DE ZANJAS 64.56 8

02 RELLENO 21.90 3

02.01 ELIMINACION MATERIAL EXCEDENTE 218.18 1

02.02 SOLADOS CONCRETO f``c=100 kg/cm2 E=4" 48.77 1

02.03 FALSA ZAPATA 1:8 + 30% PM C-H 53.86 2

02.04 CIMIENTO 16.22 1

02.05 CONCRETO VEREDAS Y LOSAS F'C=140KG/CM2 E=4" ACABADO 1:2 GRUÑADO INC. CURADO 522.59 5

02.06 ENCOFRADO Y DESENCOFRADO P/ VEREDAS 36.40 3

03 CONCRETO f`'c=210 kg/cm2 EN ZAPATAS 32.32 1

03.01 ACERO CORRUGADO fy=4200 kg/cm2 EN ZAPATAS 696.24 3

03.02 CONCRETO EN VIGAS DE CIMENTACION f'`c=210 kg/cm2 23.19 1

03.03 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS DE CIMENTACION 183.07 18

03.04 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 2,622.35 10

03.05 CONCRETO f'c=210 KG/CM2 EN SOBRECIMIENTOS REFORZADOS 12.11 1

03.06 ENCOFRADO Y DESENCOFRADO NORMAL EN SOBRECIMIENTOS REFORZADOS 132.52 9

03.07 CONCRETO f'c=210 kg/cm2 PARA COLUMNAS 14.61 1

03.08 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS 141.31 14

03.09 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 3,621.37 14

03.10 CONCRETO EN VIGAS PERALTADAS F'C=210 kg/cm2 20.41 1

04 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS PERALTADAS 90.85 9

04.01 ACERO CORRUGADO fy=4200 KG/CM2 GRADO 60 2,899.20 12

04.02 CONCRETO EN LOSAS ALIGERADAS f'c=210 kg/cm2 18.40 1

04.03 ENCOFRADO Y DESENCOFRADO PARA LOSAS ALIGERADAS 255.45 11

05 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 1,475.31 6

05.01 LADRILLO HUECO DE ARCILLA h=0.15 cm PARA TECHO ALIGERADO 2,091.60 1

05.02 CONCRETO f´c=175 kg/cm2 PARA COLUMNETAS 2.76 1

06 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETAS 34.13 3

ENTIDAD EJECUTORA : SUB REGION PACIFICO

SUPERVISOR DE OBRA : ING. JUAN CARLOS RODRIGUEZ MIRANDA

RESIDENTE DE OBRA : ING.HAMILTON BONIFACIO AMES

MONTO DE OBRA : S/. 454 530.90

MODALIDAD : ADMINISTRACION DIRECTA

TIEMPO DE EJECUCIÓN : 270 DIAS CALENDARIOS

FECHA DE INICIO : 09/12/2015