Excalation Presentation 01 (2)
-
Upload
senarath-bandara -
Category
Documents
-
view
213 -
download
0
Transcript of Excalation Presentation 01 (2)
-
7/27/2019 Excalation Presentation 01 (2)
1/12
Price Escalation
Construction Projects
-
7/27/2019 Excalation Presentation 01 (2)
2/12
-
7/27/2019 Excalation Presentation 01 (2)
3/12
The Formula for the major contracts, when expressed Mathematically shall be as follows:
F = 0.966 ( VV na ) Px ( I xc - I xb ) all inputs 100 I xb
FORMULA
F - Price adjustment for the period concerned
V - Current valuation of work done for the periodV na - Value of non adjustable element or value of work not
considered for price variation
Px - Input percentage of input named x
I xc - Current indices of input x
I xb - Base indices of input x
Input Percentage
It means the percentage proportionate contribution of any input in terms
of cost of the construction based on the prices prevailing on one month
prior to submission of the Bid.
-
7/27/2019 Excalation Presentation 01 (2)
4/12
The conditions of contract allows the contractor to submit monthly
statements which should also include the 80% of the cost of materials
delivered to the site for permanent works but are not incorporated in
works. This is generally done by valuing the cumulative work done
including the 80% of the cost of materials delivered to the site but has
not been incorporated in permanent works and deducting the cumulative
payments certified up to the previous bill
Hence,
VALUATION OF WORK FOR THE PERIOD
V = ( Vc + Mc ) - ( Vp + Mp)
-
7/27/2019 Excalation Presentation 01 (2)
5/12
Three categories of items will be generally considered as non-adjustable element
Items in the BOQ for which the expenditure will be fixed and will be executed at early stages of the
contract. Most of the Preliminary items fall under this category;
Provisional sum items; and
Extra works items for which the rates are agreed based on the prices prevailing at the time of
execution of works or are priced at Day-work rates. However, if the extra works rates are agreed
based on the prices prevailed at the time of bidding or based on contract rates then such extra works
items shall not be identified as non-adjustable elements.
-
7/27/2019 Excalation Presentation 01 (2)
6/12
-
7/27/2019 Excalation Presentation 01 (2)
7/12
INPUT PERCENTAGES (Px)
The percentage cost contribution of major materials, plant and labour to
the contract shall be listed in the bid document. It is suggested to exclude
the less cost significant items, in computing the input percentages, since
the combined effect of such items will be less than 10% of the total cost of
inputs. Hence the total contribution of the major inputs will be considered
as 90%. The computation of input proportions is based on the costing
major input items required for the proposed construction.
The cost will be calculated using the prices that prevailed at the time of
bidding. The cost of major inputs will be considered as 90% of the total
cost. The total costs of all the inputs will be then derived by dividing the
cost of major inputs by 0.9. input proportion of a particular input will be
computed as the ratio between the cost of the input and the cost of all
inputs.
-
7/27/2019 Excalation Presentation 01 (2)
8/12
BASE INDICES ( Ixb )
Base Indices shall be indices for the input, prevailing for the calendar
month, one month prior to the date set for submission of Bid.
For Example,
if the bids were closed on any date of the month of September,
the base indices applicable shall be the indices published for the month of
August of the same year. If the relevant indices have been published at the
time of preperation of the bid document. The consultant may include same
in the space provided in the Contract Data Sheet.
-
7/27/2019 Excalation Presentation 01 (2)
9/12
ESTIMATING THE CUMULATIVE VALUE OF WORK DONE UP TO THE TIME OF VALUATION
The Conditions of Contract requires the contractor to submit monthly statements which will
include the cost of materials delivered to site for permanent works but have not incorporated
for works. This is generally done by valuing the cumulative work done including the 80% of
the cost of materials at site and deducting the corresponding cumulative work done up to the
previous bill certified.
Hence,
V = ( Vc + Mc ) - ( Vp + Mp)
-
7/27/2019 Excalation Presentation 01 (2)
10/12
-
7/27/2019 Excalation Presentation 01 (2)
11/12
Appli cable Current I ndices:
Claim 01 Claim 02 Claim 03 Final Claim
Case A Month 01 Month 02 Month 03 Month 06
Case A Month 01 Month 03 - Month 04
Month 01Month 02 Month 03 Month 04 Month 05 Month 06
Case A Claim 1 Claim 2 - - Claim 3 Final
Case B - Claim 1 Claim 2 - Final -
-
7/27/2019 Excalation Presentation 01 (2)
12/12
THE END