Flete Rural

4
CALCULO DEL FLETE OBRA CREACION PAVIMENTACION DEL JR. ALAMEDA CUADRA N°01, PROL. ATAHUAPA CDN° 02 Y JR. LOS HORQUITOS CD 02, DISTRITO DE SAN JUAN - CAJAMARCA- CAJAMARCA 1- DATOS GENERALES NOTA: FLETE CONSIDERADO DESDE CAJAMARCA A- POR PESO MATERIALES UNIDAD AFECTO IGV PESO.UNIT. PESO.TOTAL CEMENTO BL. 9,140.00 42.50 388,450.00 FIERRO KG 6,680.00 1.00 6,680.00 MADERA P2 5,875.00 1.50 8,812.50 LADRILLO UND 1,200.00 4.50 5,400.00 ALCANTARILLA 36" ML 13.00 ALCANTARILLAS 24" ML 10.00 ALCANTARILLA 12" ML 4.50 YESO BL 44.00 25.00 1,100.00 TAPA BUZON UND 130.00 OTROS(MOD.CAP.) KG 1.00 ALAMBRE,CLAVOS, KG. 987.00 1.00 987.00 PERNOS KG 1.00 ASFALTO GALON 290.00 5.00 1,450.00 IMPRIMANTE KG 1.00 PINTURA - OTROS GALON 90.00 5.00 450.00 TEJA UND 1.50 EXPLOSIVOS KG 1.00 TRONCO MADERA ML a P2 11.60 PESO TOTAL 413,329.50 B - POR VOLUMEN EN AGREGADOS Y MADERA DESCRIPC. UNIDAD AFECTOS IGV SIN IGV ARENA M3 PIEDRA M3 HORMIGÓN M3 MADERA P2 VOLUMEN TOTAL CAPACIDAD DEL CAMION (M3) NUMERO DE VIAJES REDONDEO EN TUBERIA UNIDAD DE (2.20 M. x 3.00 M.) DE CARROCERIA, CON H= 1.50 M. CAPACIDAD DEL CAMION EN TUBOS / VIAJE ML No de tubos No VIAJES Tub.1/2" 6,000.00 U Tub. 3/4" 4,500.00 U Tub, 1" 3,360.00 U Tub,1 1/2" 1,690.00 U Tub,1 1/2" Fº Gº 1,320.00 U Tub 2:" 994.00 U Tub, 3" 470.00 U Tub 4": 259.00 U Tub 2" U-PVC 994.00 U Tub 4": U-PVC 259.00 U Tub 6:" U-PVC 110.00 U Tub 8" U-PVC 65.00 U Tub 6'; CSN 160.00 U Tub 8'; CSN 80.00 U NUMERO TOTAL DE VIAJES REDONDEO TUBERIA EN VOLUMEN

description

flete

Transcript of Flete Rural

Flete Mat

CALCULO DEL FLETE

OBRA :CREACION PAVIMENTACION DEL JR. ALAMEDA CUADRA N01, PROL. ATAHUAPA CDN 02Y JR. LOS HORQUITOS CD 02, DISTRITO DE SAN JUAN - CAJAMARCA- CAJAMARCA

1- DATOS GENERALESNOTA: FLETE CONSIDERADO DESDE CAJAMARCA

A- POR PESO

MATERIALESUNIDADAFECTO IGVPESO.UNIT.PESO.TOTALCEMENTOBL.9,140.0042.50388,450.00FIERROKG6,680.001.006,680.00MADERAP25,875.001.508,812.50LADRILLOUND1,200.004.505,400.00ALCANTARILLA 36"ML13.00ALCANTARILLAS 24"ML10.00ALCANTARILLA 12"ML4.50YESOBL44.0025.001,100.00TAPA BUZONUND130.00OTROS(MOD.CAP.)KG1.00ALAMBRE,CLAVOS,KG.987.001.00987.00PERNOSKG1.00ASFALTOGALON290.005.001,450.00IMPRIMANTEKG1.00PINTURA - OTROSGALON90.005.00450.00TEJAUND1.50EXPLOSIVOSKG1.00TRONCO MADERAML a P211.60PESO TOTAL 413,329.50

B - POR VOLUMEN

EN AGREGADOS Y MADERADESCRIPC.UNIDADAFECTOS IGVSIN IGVARENAM3PIEDRAM3HORMIGNM3MADERAP2 VOLUMEN TOTALCAPACIDAD DEL CAMION (M3)NUMERO DE VIAJESREDONDEO EN TUBERIAUNIDAD DE (2.20 M. x 3.00 M.) DE CARROCERIA, CON H= 1.50 M.CAPACIDAD DEL CAMION EN TUBOS / VIAJEMLNo de tubosNo VIAJESVolumen / tuboPeso/tuboPeso en KgTub.1/2"6,000.00 U0.001620.30Tub. 3/4"4,500.00 U0.003130.65Tub, 1"3,360.00U0.004811.00Tub,1 1/2"1,690.00U0.009681.75Tub,1 1/2" F G1,320.00U0.0116225.92Tub 2:"994.00U0.017412.68Tub, 3"470.00U0.035286.41Tub 4":259.00U0.0605010.60Tub 2" U-PVC994.00U0.010441.61Tub 4": U-PVC259.00U0.036304.00Tub 6:" U-PVC110.00U0.1445015.53Tub 8" U-PVC 65.00U0.2420026.17Tub 6'; CSN160.00U0.0044050.00Tub 8'; CSN80.00U0.09380100.00NUMERO TOTAL DE VIAJES0.00REDONDEOTUBERIA EN VOLUMEN

2- FLETE TERRESTRE

UNIDAD DE TRANSPORTE UNIDAD QUE DA COMPROBANTEUNIDAD QUE NO DA COMPROBANTECAPACIDAD DEL CAMION ( M3 ) 30,000.00CAPACIDAD DEL CAMION ( M3 ) COSTO POR VIAJE S/.1,500.00COSTO POR VIAJE S/.1,500.00CAPACIDAD DEL CAMION (KG)30,000.00CAPACIDAD DEL CAMION (KG)30,000.00FLETE POR KG0.05FLETE POR KG0.05Flete bolsa de cemento=2.13

AFECTO IGVCON IGVFLETE POR PESO =Peso Total * Flete por pesoFLETE POR PESO20,670.73FLETE POR VOLUMEN=No viajes*costo por viajeFLETE POR VOLUMEN AGREGADOSTUBERIA COSTO TOTAL FLETE TERREST.21,328.690.00

3- FLETE FLUVIAL UNIDAD DE TRANSPORTE QUE DA COMPROBANTEUNIDAD DE TRANSPORTE QUE NO DA COMPROBANTE

CAPACIDAD DEL BOTE EN PESO (KG)CAPACIDAD DEL BOTE EN VOLUMEN (M3)COSTO POR VIAJECOSTO POR PESO

AFECTO IGVSIN IGVFLETE POR PESO =Peso Total * Flete por pesoFLETE POR PESOFLETE POR VOLUMEN=No viajes*costo por viajeFLETE POR VOLUMENAGREGADOS TUBERIACOSTO TOTAL FLETE FLUVIAL

4- FLETE EN ACEMILA La tubera ser transportada por peonesCostos de transporte por viajeAcemila S/.Peon S/.

CantidadUnidades deCapacidad deNmero deFlete no CargaCargaViajesAfecto a IGVPeso total tubera de agua60Peso total tubera desague CSN60Peso total tubera desague PVC60Numero bolsas de cemento Peso resto de materiales24,879.5085292.70Agregados Total en Kilos85Madera total en kilos 185Agregados Total en Kilos185COSTO TOTAL DEL FLETE EN ACEMILA S/.

RESUMEN FLETE TOTAL

AFECTO IGVSIN IGVTOTALFLETE TERRESTRE21,328.6921,328.69FLETE FLUVIALFLETE EN ACEMILAFLETES TOTALES S/.21,328.6921,328.6921,328.69

Nota: - El flete terrestre se realiza en vehculo motorizado desde CAJAMARCA- SAN JUAN