CALCULO DEL FLETE
CONSTRUCCION TROCHA CARROZABLE RETIRO DEL CARMEN-PALTAYBAMBA
1- DATOS GENERALES
A-POR PESO
MATERIALES UND CANTIDAD PESO.UNIT. PESO.TOTALCEMENTO BL. 1,575.50 42.50 66,958.75DINAMITA KG 0.00 1.00 0.00MADERA P2 1,333.00 1.50 1,999.50ASFALTO RC-250 GLN 315.00 4.50 1,417.50ALAMBRE NEGRO # 8 KG 94.00 1.00 94.00CALAMINA UN 56.00 3.50 196.00YESO BL 34.00 25.00 850.00CLAVOS DE 3" KG 59.00 1.00 59.00CLAVOS DE 4" KG 0.00 1.00 0.00CLAVOS PARA CALAMINA KG 24.00 1.00 24.00TUBERIA PVC SAP DE 6" M 0.00 1.30 0.00TUBERIA PVC SAP DE 6" CRIBADA M 0.00 1.30 0.00ACERO CORRUGADO KG 0.00 1.00 0.00PINTURA GLN 16.00 3.00 48.00KEROSENE GLN 26.00 3.00 78.00ALAMBRE NEGRO # 16 KG 0.00 1.00 0.00PESO TOTAL 71,724.75
2.00 POR VOLUMEN
AGREGADOS, MADERA Y OTROSDESCRIPCION UNIDAD AFECTOS IGV SIN IGV
ARENA, hormigon M3 0.00 0.00PIEDRA M3 0.00 0.00TIERRA SELECIONADA M3 0.00 0.00HORMIGON M3 0.00 0.00TUBERIA PVC, L=4 M, e=2" UND 0.00
VOLUMEN TOTALCAPACIDAD DEL CAMION (M3) 10.00 10.00NUMERO DE VIAJESREDONDEO 0.00
POR ALQUILER HORA MAQUINAIDA
DESDE A TIPO DE VIA LONG. VD (KM/H) TIEMPO KM. Veloc.
(Km/h TIEMPOCUSCO CALCA ASFALTADA 42 30 1.40CALCA QIEBRADA AFIRMADA 124 18 6.89
QUEBRADA PALTAYBAMBA TIERRA 8 10 0.80TOTAL 174 9.09
REGRESODESDE A TIPO DE VIA LONG. VD (KM/H) TIEMPO
KM. Veloc.(Km/h TIEMPOCUSCO CALCA ASFALTADA 42 37 1.14CALCA QIEBRADA AFIRMADA 124 23 5.39
QUEBRADA PALTAYBAMBA TIERRA 8 11 0.73TOTAL 174 7.25
PESO TOTAL 71724.75 KGTIEMPO TOTAL 16.34 HORASCOSTO HORARIO DE VEHICULO CARGA 115.00 SOLESCAPACIDAD VEHICULO (HASTA 14 TON) 14000.00 KGNUMERO DE VIAJES 5.12 COSTO TOTAL FLETE 9628.53 SOLES