Formato Informe Del Proyecto

21
N.A. EDT F. Inicio F. Finalización P.V. E.V. $ % $ % 1.1. 9/8/2014 9/19/2014 $ - 0% $ - 0% 1.2. 9/22/2014 12/1/2014 $ - 0% $ - 0% 1.3. 9/8/2014 9/19/2014 $ - 0% $ - 0% 1.4. 9/19/2014 11/5/2014 $ - 0% $ - 0% 1.5. 11/5/2014 3/27/2015 $ - 0% $ - 0% 1.6. 3/27/2015 4/17/2015 $ - 0% $ - 0% 1.7. 9/8/2014 4/15/2015 $ - 0% $ - 0% 1.8. 4/13/2015 5/12/2015 $ - 0% $ - 0% 1.9. 5/13/2015 5/13/2015 $ - 0% $ - 0% 1.10. 9/11/2014 5/14/2015 $ - 0% $ - 0% 1.11. 5/13/2015 5/19/2015 $ - 0% $ - 0% Alcance Tiempo Seg. Reservas 11/30/2014 SV SPI $ 110,000.00 #DIV/0! #DIV/0! $ - #DIV/0! Gerencial $ 3,284,759.04 BAC $ - EAC #DIV/0! Riesgos 11/30/2014 Cerrados R6, R7 VAC #DIV/0! Materializados N.A. Latentes Calidad: Nuevos N.A. Acciones Preventivas: Control cambios 11/30/2014 Acciones Correctivas: CREACION DE UN MODULO DE AUTOGESTION PARA BRINDAR P Avance Planificado Avance real Contingencia libre R1, R2, R3, R4, R5, R8, R9, R10

description

Formato para el seguimiento a un proyecto

Transcript of Formato Informe Del Proyecto

Informe 30-11-2014CREACION DE UN MODULO DE AUTOGESTION PARA BRINDAR SERVICIOS BANCARIOS A CLIENTES EMPRESARIALES DEL BBVA SOBRE SU PLATAFORMA WEBCdigo: TDG017-005Versin: V.1.INFORME DE SEGUIMIENTO No.0001Fecha: 4/25/15

N.A.11/30/14EDTF. InicioF. FinalizacinP.V.E.V.A.C.Valor PlaneadoValor GanadoCosto Actual $%$%$$%$%$1.1.9/8/149/19/140.00%0.00%0.0$ 1,790,000100%$ 1,790,000100%$ 1,727,500.001.2.9/22/1412/1/140.00%0.00%0.01.3.9/8/149/19/140.00%0.00%0.01.4.9/19/1411/5/140.00%0.00%0.01.5.11/5/143/27/150.00%0.00%0.01.6.3/27/154/17/150.00%0.00%0.01.7.9/8/144/15/150.00%0.00%0.01.8.4/13/155/12/150.00%0.00%0.01.9.5/13/155/13/150.00%0.00%0.01.10.9/11/145/14/150.00%0.00%0.01.11.5/13/155/19/150.00%0.00%0.0AlcanceTiempoCostoAlcanceTiempoCostoSeg. Reservas11/30/14Avance PlanificadoAvance realSVSPICVCPIAvance PlanificadoAvance realSVSPICVCPIContingencia libre$ 110,000.00ERROR:#DIV/0!ERROR:#DIV/0!0.0ERROR:#DIV/0!0.0ERROR:#DIV/0!0%0%0.01$ 62,5001.0361794501Gerencial$ 3,284,759.04BAC0.0EACERROR:#DIV/0!ETCERROR:#DIV/0!BAC$ 1,790,000EAC1727500ETC0.0Riesgos11/30/14CerradosR6, R7VACERROR:#DIV/0!VAC$ 62,500.00MaterializadosN.A.LatentesR1, R2, R3, R4, R5, R8, R9, R10Calidad:Calidad:NuevosN.A.Acciones Preventivas:Acciones Preventivas:Control cambios11/30/14

Acciones Correctivas:Acciones Correctivas:

Informe 30-12-2014CREACION DE UN MODULO DE AUTOGESTION PARA BRINDAR SERVICIOS BANCARIOS A CLIENTES EMPRESARIALES DEL BBVA SOBRE SU PLATAFORMA WEBCdigo: TDG017-005Versin: V.1.INFORME DE SEGUIMIENTO No.0002Fecha: 4/25/15

11/30/1412/30/14EDTF. InicioF. FinalizacinP.V.E.V.A.C.Valor PlaneadoValor GanadoCosto Actual $%$%$$%$%$1.1.9/8/149/19/14$ 1,790,000.00100%$ 1,790,000.00100%$ 1,727,500.001.2.9/22/1412/1/140.00%0.00%0.01.3.9/8/149/19/140.00%0.00%0.01.4.9/19/1411/5/140.00%0.00%0.01.5.11/5/143/27/150.00%0.00%0.01.6.3/27/154/17/150.00%0.00%0.01.7.9/8/144/15/150.00%0.00%0.01.8.4/13/155/12/150.00%0.00%0.01.9.5/13/155/13/150.00%0.00%0.01.10.9/11/145/14/150.00%0.00%0.01.11.5/13/155/19/150.00%0.00%0.0AlcanceTiempoCostoAlcanceTiempoCostoSeg. Reservas12/30/14Avance PlanificadoAvance realSVSPICVCPIAvance PlanificadoAvance realSVSPICVCPIContingencia libre$ 170,000.000.00%0.00%0.01$ 62,500.001.0361794501ERROR:#DIV/0!ERROR:#DIV/0!0.0ERROR:#DIV/0!0.0ERROR:#DIV/0!Gerencial$ 3,284,759.04BAC$ 3,580,000.00EAC3455000ETC$ 1,727,500.00BAC$ 3,580,000.00EACERROR:#DIV/0!ETCERROR:#DIV/0!Riesgos12/30/14CerradosR2, R6, R7, R8VAC$ 125,000.00VACERROR:#DIV/0!MaterializadosLatentesR1, R3, R4, R5, R9, R10Calidad:Calidad:NuevosAcciones Preventivas:Acciones Preventivas:Control cambios12/30/14

Acciones Correctivas:Acciones Correctivas:

Informe 30-01-2015CREACION DE UN MODULO DE AUTOGESTION PARA BRINDAR SERVICIOS BANCARIOS A CLIENTES EMPRESARIALES DEL BBVA SOBRE SU PLATAFORMA WEBCdigo: TDG017-005Versin: V.1.INFORME DE SEGUIMIENTO No.0003Fecha: 4/25/15

12/30/141/30/15EDTF. InicioF. FinalizacinP.V.E.V.A.C.Valor PlaneadoValor GanadoCosto Actual $%$%$$%$%$1.1.9/8/149/19/140.00%0.00%0.01.2.9/22/1412/1/140.00%0.00%0.01.3.9/8/149/19/140.00%0.00%0.01.4.9/19/1411/5/140.00%0.00%0.01.5.11/5/143/27/150.00%0.00%0.01.6.3/27/154/17/150.00%0.00%0.01.7.9/8/144/15/150.00%0.00%0.01.8.4/13/155/12/150.00%0.00%0.01.9.5/13/155/13/150.00%0.00%0.01.10.9/11/145/14/150.00%0.00%0.01.11.5/13/155/19/150.00%0.00%0.0AlcanceTiempoCostoAlcanceTiempoCostoSeg. Reservas1/30/15Avance PlanificadoAvance realSVSPICVCPIAvance PlanificadoAvance realSVSPICVCPIContingencia libre$ 170,000.00000.0ERROR:#DIV/0!0.0ERROR:#DIV/0!ERROR:#DIV/0!ERROR:#DIV/0!0.0ERROR:#DIV/0!0.0ERROR:#DIV/0!Gerencial$ 3,284,759.04BAC$ 3,580,000.00EACERROR:#DIV/0!ETCERROR:#DIV/0!BAC$ 3,580,000.00EACERROR:#DIV/0!ETCERROR:#DIV/0!Riesgos1/30/15CerradosVACERROR:#DIV/0!VACERROR:#DIV/0!MaterializadosLatentesR1, R3, R4, R5, R9, R10Calidad:Calidad:NuevosAcciones Preventivas:Acciones Preventivas:Control cambios1/30/15

Acciones Correctivas:Acciones Correctivas:

Informe 30-02-2015CREACION DE UN MODULO DE AUTOGESTION PARA BRINDAR SERVICIOS BANCARIOS A CLIENTES EMPRESARIALES DEL BBVA SOBRE SU PLATAFORMA WEBCdigo: TDG017-005Versin: V.1.INFORME DE SEGUIMIENTO No.0004Fecha: 4/25/15

1/30/1530/02/2015EDTF. InicioF. FinalizacinP.V.E.V.A.C.Valor PlaneadoValor GanadoCosto Actual $%$%$$%$%$1.1.9/8/149/19/140.00%0.00%0.01.2.9/22/1412/1/140.00%0.00%0.01.3.9/8/149/19/140.00%0.00%0.01.4.9/19/1411/5/140.00%0.00%0.01.5.11/5/143/27/150.00%0.00%0.01.6.3/27/154/17/150.00%0.00%0.01.7.9/8/144/15/150.00%0.00%0.01.8.4/13/155/12/150.00%0.00%0.01.9.5/13/155/13/150.00%0.00%0.01.10.9/11/145/14/150.00%0.00%0.01.11.5/13/155/19/150.00%0.00%0.0AlcanceTiempoCostoAlcanceTiempoCostoSeg. Reservas30/02/2015Avance PlanificadoAvance realSVSPICVCPIAvance PlanificadoAvance realSVSPICVCPIContingencia libre$ 170,000.00000.0ERROR:#DIV/0!0.0ERROR:#DIV/0!ERROR:#DIV/0!ERROR:#DIV/0!0.0ERROR:#DIV/0!0.0ERROR:#DIV/0!Gerencial$ 3,284,759.04BAC$ 3,580,000.00EACERROR:#DIV/0!ETCERROR:#DIV/0!BAC$ 3,580,000.00EACERROR:#DIV/0!ETCERROR:#DIV/0!Riesgos30/02/2015CerradosVACERROR:#DIV/0!VACERROR:#DIV/0!MaterializadosLatentesR1, R3, R4, R5, R8, R9, R10Calidad:Calidad:NuevosAcciones Preventivas:Acciones Preventivas:Control cambios30/02/2015

Acciones Correctivas:Acciones Correctivas:

Informe 30-03-2015CREACION DE UN MODULO DE AUTOGESTION PARA BRINDAR SERVICIOS BANCARIOS A CLIENTES EMPRESARIALES DEL BBVA SOBRE SU PLATAFORMA WEBCdigo: TDG017-005Versin: V.1.INFORME DE SEGUIMIENTO No.0005Fecha: 4/25/15

30/02/20153/30/15EDTF. InicioF. FinalizacinP.V.E.V.A.C.Valor PlaneadoValor GanadoCosto Actual $%$%$$%$%$1.1.9/8/149/19/140.00%0.00%0.01.2.9/22/1412/1/140.00%0.00%0.01.3.9/8/149/19/140.00%0.00%0.01.4.9/19/1411/5/140.00%0.00%0.01.5.11/5/143/27/150.00%0.00%0.01.6.3/27/154/17/150.00%0.00%0.01.7.9/8/144/15/150.00%0.00%0.01.8.4/13/155/12/150.00%0.00%0.01.9.5/13/155/13/150.00%0.00%0.01.10.9/11/145/14/150.00%0.00%0.01.11.5/13/155/19/150.00%0.00%0.0AlcanceTiempoCostoAlcanceTiempoCostoSeg. Reservas3/30/15Avance PlanificadoAvance realSVSPICVCPIAvance PlanificadoAvance realSVSPICVCPIContingencia libre$ 2,031,845.00000.0ERROR:#DIV/0!0.0ERROR:#DIV/0!ERROR:#DIV/0!ERROR:#DIV/0!0.0ERROR:#DIV/0!0.0ERROR:#DIV/0!Gerencial$ 3,284,759.04BAC$ 3,580,000.00EACERROR:#DIV/0!ETCERROR:#DIV/0!BAC$ 3,580,000.00EACERROR:#DIV/0!ETCERROR:#DIV/0!Riesgos3/30/15CerradosR1VACERROR:#DIV/0!VACERROR:#DIV/0!MaterializadosLatentesR3, R4, R5, R8, R9, R10Calidad:Calidad:NuevosR11, R12, R13, R14Acciones Preventivas:Acciones Preventivas:Control cambios3/30/15

Acciones Correctivas:Acciones Correctivas:

Informe 30-04-2015CREACION DE UN MODULO DE AUTOGESTION PARA BRINDAR SERVICIOS BANCARIOS A CLIENTES EMPRESARIALES DEL BBVA SOBRE SU PLATAFORMA WEBCdigo: TDG017-005Versin: V.1.INFORME DE SEGUIMIENTO No.0006Fecha: 4/25/15

3/30/154/30/15EDTF. InicioF. FinalizacinP.V.E.V.A.C.Valor PlaneadoValor GanadoCosto Actual $%$%$$%$%$1.1.9/8/149/19/140.00%0.00%0.01.2.9/22/1412/1/140.00%0.00%0.01.3.9/8/149/19/140.00%0.00%0.01.4.9/19/1411/5/140.00%0.00%0.01.5.11/5/143/27/150.00%0.00%0.01.6.3/27/154/17/150.00%0.00%0.01.7.9/8/144/15/150.00%0.00%0.01.8.4/13/155/12/150.00%0.00%0.01.9.5/13/155/13/150.00%0.00%0.01.10.9/11/145/14/150.00%0.00%0.01.11.5/13/155/19/150.00%0.00%0.0AlcanceTiempoCostoAlcanceTiempoCostoSeg. Reservas4/30/15Avance PlanificadoAvance realSVSPICVCPIAvance PlanificadoAvance realSVSPICVCPIContingencia libre$ 2,031,845.00000.0ERROR:#DIV/0!0.0ERROR:#DIV/0!ERROR:#DIV/0!ERROR:#DIV/0!0.0ERROR:#DIV/0!0.0ERROR:#DIV/0!Gerencial$ 3,284,759.04BAC$ 3,580,000.00EACERROR:#DIV/0!ETCERROR:#DIV/0!BAC$ 3,580,000.00EACERROR:#DIV/0!ETCERROR:#DIV/0!Riesgos4/30/15CerradosR1VACERROR:#DIV/0!VACERROR:#DIV/0!MaterializadosLatentesR3, R4, R5, R8, R9, R10Calidad:Calidad:NuevosR11, R12, R13, R14Acciones Preventivas:Acciones Preventivas:Control cambios4/30/15

Acciones Correctivas:Acciones Correctivas:

Informe 30-05-2015CREACION DE UN MODULO DE AUTOGESTION PARA BRINDAR SERVICIOS BANCARIOS A CLIENTES EMPRESARIALES DEL BBVA SOBRE SU PLATAFORMA WEBCdigo: TDG017-005Versin: V.1.INFORME DE SEGUIMIENTO No.0007Fecha: 4/25/15

4/30/155/30/15EDTF. InicioF. FinalizacinP.V.E.V.A.C.Valor PlaneadoValor GanadoCosto Actual $%$%$$%$%$1.1.9/8/149/19/140.00%0.00%0.01.2.9/22/1412/1/140.00%0.00%0.01.3.9/8/149/19/140.00%0.00%0.01.4.9/19/1411/5/140.00%0.00%0.01.5.11/5/143/27/150.00%0.00%0.01.6.3/27/154/17/150.00%0.00%0.01.7.9/8/144/15/150.00%0.00%0.01.8.4/13/155/12/150.00%0.00%0.01.9.5/13/155/13/150.00%0.00%0.01.10.9/11/145/14/150.00%0.00%0.01.11.5/13/155/19/150.00%0.00%0.0AlcanceTiempoCostoAlcanceTiempoCostoSeg. Reservas5/30/15Avance PlanificadoAvance realSVSPICVCPIAvance PlanificadoAvance realSVSPICVCPIContingencia libre$ 110,000.00000.0ERROR:#DIV/0!0.0ERROR:#DIV/0!ERROR:#DIV/0!ERROR:#DIV/0!0.0ERROR:#DIV/0!0.0ERROR:#DIV/0!Gerencial$ 3,284,759.04BAC$ 3,580,000.00EACERROR:#DIV/0!ETCERROR:#DIV/0!BAC$ 3,580,000.00EACERROR:#DIV/0!ETCERROR:#DIV/0!Riesgos5/30/15CerradosR6, R7VACERROR:#DIV/0!VACERROR:#DIV/0!MaterializadosLatentesR1, R2, R3, R4, R5, R8, R9, R10Calidad:Calidad:NuevosAcciones Preventivas:Acciones Preventivas:Control cambios5/30/15

Acciones Correctivas:Acciones Correctivas:

Curva S proyecto