Inform Final PROYECTO ELECTRICO

36
Página 1 de 36 GPI - GERENCIA EN PROYECTOS DE INGENIERIA LTDA. CONTENIDO 1. ASPECTOS ADMINISTRATIVOS Y LEGALES................................................................. 4 1.1 Contrato interventoría No 285 - 10.........................4 1.2 Contrato de obra No 279 -10...............................5 1.3 Garantías y pólizas vigentes a la fecha....................6 1.4 Permisos de paso y servidumbre.............................7 1.5 Correspondencia enviada y recibida.........................8 1.6 Aspectos legales...........................................9 2. ASPECTOS FINANCIEROS............................................................................... 10 2.1 Pagos parciales...........................................10 2.2 Control de Pagos...........................................10 Tabla No 9. Control de pagos...................................10 3. ASPECTOS TÉCNICOS...................................................................................... 10 3.1 Avance de obra.............................................10 Tabla 10. Principales cantidades ejecutadas....................11 3.2 Actividades de construcción................................11 3.3. Análisis del cronograma de Obra...........................15 3.4 Entrega de materiales de DISPAC al contratista............15 3.5 Solicitudes presentadas de suspensión del servicio.........22 3.6 Bodega, almacenamiento, clasificación y transporte.........23 El contratista hizo entrega de los materiales sobrantes a almacén de Dispac...................................................... 23 4. LIQUIDACION DEL CONTRATO....................................................................... 23 5. SALUD OCUPACIONAL Y SSOMA.................................................................... 26 5.1 Afiliaciones al sistema de seguridad social................26 5.2 Pagos de seguridad social..................................27 Avenida 15 No. 106 - 32Of. 407Pbx:+ (571) 7428240 Fax.: + (571) 7428241 Fax a email + (571) 7550139 WEBwww.gpi.com.co - E-mail [email protected] Bogotá, D. C. – Colombia

description

INFORME DE PROYECTO ELECTRICO

Transcript of Inform Final PROYECTO ELECTRICO

1

GPI - GERENCIA EN PROYECTOS DE INGENIERIA LTDA.

CONTENIDO41.ASPECTOS ADMINISTRATIVOS Y LEGALES

41.1Contrato interventora No 285 - 10

51.2Contrato de obra No 279 -10

61.3Garantas y plizas vigentes a la fecha

71.4Permisos de paso y servidumbre

81.5Correspondencia enviada y recibida.

91.6Aspectos legales

102.ASPECTOS FINANCIEROS

102.1Pagos parciales

102.2 Control de Pagos.

10Tabla No 9. Control de pagos

103.ASPECTOS TCNICOS

103.1 Avance de obra

11Tabla 10. Principales cantidades ejecutadas

113.2 Actividades de construccin

153.3. Anlisis del cronograma de Obra

153.4 Entrega de materiales de DISPAC al contratista

223.5 Solicitudes presentadas de suspensin del servicio.

233.6 Bodega, almacenamiento, clasificacin y transporte

23El contratista hizo entrega de los materiales sobrantes a almacn de Dispac.

234.LIQUIDACION DEL CONTRATO.

265.SALUD OCUPACIONAL Y SSOMA

265.1 Afiliaciones al sistema de seguridad social

275.2 Pagos de seguridad social

275.3 Planes de calidad y SOMMA

275.4 Aspectos ambientales

286.Logros alcanzados y deficiencias presentados

286.1 Logros

286.2 Deficiencias

287.CONCLUSIONES.

7. ANEXOS7.1 FOTOCOPIA DE PLANILLAS DE AFILIACIN AL SISTEMA DE SEGURIDAD SOCIAL DE LOS TRABAJADORES.

.7.2 INFORME MENSUAL DEL CONTRATISTA EN MEDIO MAGNETICO CD.

.7.3 CRONOGRAMA DE ACTIVIDADES ACTUALIZADO EN MEDIO MAGNETICO CD.

7.4 COPIAS DE LAS HOJAS DE BITCORA DE LA INTERVENTORA.7.5 AUTORIZACION CONSTRUCCION DE ACCESOS

7.6 SALIDAS DE ALMACEN DISPAC MATERIAL NUEVO

7.7 SALIDAS ALMACEN DISPAC MATERIAL DESMONTADO7.8 PAZ Y SALVOS DEL CONTRATISTAINFORME FINAL:

Enero de 2011Revisin:00

ElaborRevisAprob

CargoIngeniero de proyectoCargoCoordinador calidad y SSOMACargoDirector Proyecto

FirmaFirmaFirma

Control de cambios

RevisinFechaSeccinDescripcin del cambio

0001-18-2011N.A.Versin inicial

Lista de distribucin

No.Cargo o localizacinNombreFecha

1DISPAC S.A.E.S.P. OriginalIng. Fredy Pinilla.01-18-2011

2Servidor GPIN.A.01-18-2011

3Copia Biblioteca GPIN.A.01-18-2011

En cumplimiento a lo establecido en el literal (R) de la clusula segunda del contrato No 285 de 2010, GPI LTDA en la responsabilidad que le asiste como interventor del contrato No 279 celebrado entre DISPAC y la firma GPI LTDA, se permite presentar el informe Final correspondiente al desarrollo de las actividades, del contrato en mencin. De acuerdo a conversacin sostenida con el ingeniero interventor interno de Dispac Freddy Pinilla, se suprimen los siguientes tems del informe:

Socializacin

Anticipo

Replanteo

Herramientas del contratista

Elementos de dotacin.

1. ASPECTOS ADMINISTRATIVOS y legales1.1 Contrato interventora No 285 - 10a. Contratista: GPI LTDA

b. Objeto : Interventoria a contratos de remodelacin de redes elctricas de distribucin a 13.2 Kv en las localidades de Tado Corcovado, el Dos Plan de Raspadura, Corcovado Playa de Oro, El Tabor y Playa de oro el Carmelo, Viro Viro Santa Rita. c. Fecha de inicio: 11 de junio de 2010d. Plazo de ejecucin: 200 das calendarios a partir de la fecha de suscripcin del acta de iniciacin.e. Ampliacin plazo otro si: Se amplio el plazo en 54 das con un valor de $ 73.824.873 f. Terminacin: 4 de Febrero 2011 g. Oficina: Direccin: Calle 4 N 17-38 Municipio de Tad (Choco).h. Organizacin de la interventora: Tabla 1. Recurso Humano del Proyecto

1.2 Contrato de obra No 279 -10a. Contratista: ELECTROMONTAJES LTDA.b. Objeto: Remodelacin de redes de distribucin 13.2 Kv en las localidades de Tado Corcovado y el Dos plan de Raspadura.c. Plazo: 150 das Calendario. A partir de la fecha de suscripcin del acta de inicio.d. Fecha de inicio: 21 de junio de 2010e. Ampliacin valor otro si: El da 14 de septiembre Se ampli el valor del contrato en $15.826.796, para un valor a ejecutar de 315.108.119$.f. Ampliacin de la vigencia: Segn otro si del 17 de noviembre del 2010, se ampli la vigencia del contrato en 15 das, hasta el 2 de diciembre de 2010.g. Fecha de terminacin: 02 de diciembre de 2010h. Organizacin del contratista:A la fecha de corte del presente informe el contratista cuenta con el siguiente personal. Tabla 2. Recurso Humano del Contratista1.3 Garantas y plizas vigentes a la fechaEl Contrato 279 -10 se encuentra debidamente amparado mediante las siguientes plizas expedidas por la Compaa Aseguradora de Fianzas S.A CONFIANZA S.A. las cuales se encuentran debidamente aprobadas por la oficina jurdica de Dispac. Mediante otros del 14 de septiembre de 2010, se ampli el valor del contrato por un valor de $15.826.796. Los nuevos valores asegurados se muestran en la tabla No.3.

Tabla 3. Plizas de cumplimiento del contratoMediante otros del 17 de noviembre de 2010, se ampli la vigencia del contrato como se indica en la tabla 3, columna nuevo termino de vigencia.1.4 Permisos de paso y servidumbrea. De acuerdo a lo consignado en los pliegos numeral 4.10.12. el contratista tramito los permisos de paso correspondientes. En el trayecto Tado - Corcovado el contratista gestiono los permisos de paso con los siguientes propietarios de predios particulares, como se aprecia en la tabla 4. Se anexan en el informe las autorizaciones. Tabla 4. Permisos de paso gestionados por el contratistab. Como se menciono en los informes anteriores se presentaron problemas de servidumbre y afectaciones entre Dispac y los seores Demstenes Copete, Denis Torres y Muro Elas Andrade, La propuesta por parte de Dispac de compensaciones econmicas solo fue aceptada por los seor Denis Torres y Mauro Ely Andrade, cuyos documentos de aceptacin reposan en la oficina jurdica de Dispac. Estos permisos de paso fueron gestionados directamente entre las partes. En la tabla 5. Se relacionan las cantidades y tipos de arboles, postes que fueron compensados por Dispac.

Tabla 5. Permisos de paso gestionados por Dispacc. En vista de la no aceptacin de la propuesta hecha por Dispac al seor Copete, la interventoria en mutuo acuerdo con interventor interno Dispac ingeniero Fredy Pinilla decidi hacer cambio de trayectoria en el circuito Tado - Corcovado entre los apoyos 11 y 13, correspondiente al predio del seor copete, evitando ms demoras en los tramites que podran retrasar los trabajos por parte del contratista. Se anexan todos los permisos de paso en este informe.d. En el trayecto El Dos Plan De Raspadura, los permisos de paso y las afectaciones, fueron gestionados directamente por Dispac, cuyos documentos firmados reposan en su oficina jurdica de Quibdo. En la tabla 6. se aprecian los propietarios que fueron indemnizados por Dispac de acuerdo al nmero de postes instalados en cada predio. Se anexan todos los permisos de paso en este informe.

Tabla 6. Permisos de paso Plan de Raspadura1.5 Correspondencia enviada y recibida.Se adjuntan en anexo copia de las principales comunicaciones entre las partes, (Contratista, interventora y DISPAC). a. Correspondencia enviada por interventora:

DESTINOFECHAMEDIOASUNTO

Ing. Coordinador GPI02-Diciembre -2010E-MAILInforme mes de diciembre

Ing. Coordinador GPI07-Diciembre-2010E-MAILRegistro fotogrfico

Tabla 7. Correspondencia Enviadab. Correspondencia Recibida por la Interventoria:

ORIGENFECHAMEDIOASUNTO

Ing. Coordinador GPI01-Diciembre -2010E-MAILMaterial desmontado

Ing. Coordinador GPI02-Diciembre -2010E-MAILOficio PC113-QUD-78

Ing. Coordinador GPI03-Diciembre -2010E-MAILOficio PC113-QUD-77

Ing. Residente Electromontajes04-Diciembre -2010E-MAILProgramacin semanal del 6 al 12 de diciembre

Ing. Residente Electromontajes08-Diciembre -2010E-MAILListado de usuarios y afectaciones

Ing. Coordinador GPI08-Diciembre -2010E-MAILFormatos Dispac

Ing. Residente Electromontajes10-Diciembre -2010E-MAILSeguridad social

Ing. Interventor Dispac14-Diciembre -2010E-MAILConsumos contrato 279-10

Tabla 8. Correspondencia Recibida1.6 Aspectos legalesEl da 14 de septiembre de 2010, se firmo el otros del contrato 279-10, entre los representante legal de Dispac y Electo montajes, en el cual se incrementa el valor por $15.826.796.

Segn otro si del 17 de noviembre del 2010, se ampli la vigencia del contrato en 16 das, hasta el 2 de diciembre de 2010.

Lo mismo ocurri con el contrato 285 10, el da 11 de septiembre de 2010 se firmo entre las partes el otro si, con un incremento del valor de $73.824.873 y ampliacin del plazo en 54 das.

2. ASPECTOs FINANCIEROs 2.1Pagos parcialesFinalizado el contrato se efectu el trmite del acta de entrega final, por un valor de $46.299.099 de los cuales no se genero ningn valor por concepto de amortizacin, ya que el valor que restaba se le amortizo en el acta No4.El valor de $46.299.099 corresponde al 15.2% del valor final del contrato.2.2 Control de Pagos.

A continuacin se presenta el cuadro final de control de pagos, donde se incluye el anticipo y todas las actas que se generaron durante la ejecucin del contrato. El valor del contrato segn el replanteo fue de $315,108.119 y el valor total ejecutado es de $304.598.833 de lo cual se puede concluir que el porcentaje de obra final ejecutada en valor y cantidad es del orden del 96.7%; ejecutadas la totalidad de las obras y aprobadas por la interventoria, queda un sobrante de $10.509.286, como se aprecia en la tabla de control de pagos.CONTROL DE PAGOS

ITEMRELACIN DE PAGOSAMORTIZAC. ANTICIPOPAGO NETOVALOR CONTRACTUAL INICIALVALOR CONTRACTUAL ADICIONALVALOR NO EJECUTADO

DESCRIPCINVALOR

ANTICIPO$ 89.784.397$ 0$ 89.784.397OTRO S 01

1ACTA NUMERO 1$ 57.347.214$ 17.204.164$ 40.143.050$ 15.826.796

2ACTA NUMERO 2$ 105.096.872$ 31.529.062$ 73.567.810

3ACTA NUMERO 3$ 48.814.069$ 14.644.221$ 34.169.848

4ACTA NUMERO 4$ 47.041.579$ 26.406.951$ 20.634.628

5ACTA NUMERO 5$ 46.299.099$ 46.299.099

AVANCE PRESUPUESTAL$ 304.598.833$ 89.784.397$ 304.598.833$ 299.281.323$ 315.108.119$ 10.509.286

Tabla No 9. Control de pagos 3. ASPECTOS TCNICOS3.1 Avance de obraA continuacin se presenta cuadro de las principales actividades ejecutadas al cierre del contrato, y se comparan las cantidades del replanteo versus las cantidades finales ejecutadas, como se aprecia en la tabla No 10. Tabla 10. Principales cantidades ejecutadas3.2 Actividades de construccinA continuacin se describen las actividades ms representativas realizadas durante la construccin de la obra, incluyendo cantidades totales de estructuras, materiales instalados, postes instalados, vientos etc.3.2.1 El Dos - Plan de Raspadura a. Se instalaron un total de 34 estructuras, de las cuales tenemos 26 postes nuevos, 8 existentes y dos postes que se tuvieron que cambiar por mala calidad y que se pagaron como reubicados. Adems se reubicaron tres transformadores con todas sus protecciones. A continuacin se muestra tabla con las cantidades instaladas.

Tabla 11 Cantidades de obra instaladas Plan de Raspadurab. En este tramo ya se ejecutaron la totalidad de las obras, incluyendo la etapa de pendientes, pintura de posteria segn pliego de condiciones. Ver foto 1

Foto1. Pintada posteria segn norma Nanac. Adems ya se realizo la etapa de georrefenciacion e inventario de materiales instalados. d. Se instalaron 4 postes de concreto 12mts 1050 Kgf en parte urbana, en sitios donde no se pueden colocar vientos y poder retirar la lnea de las fachadas y techos de las viviendas en cruceta volada, como se muestra en la foto No.2 y 3.

Foto 2. Antes Foto 3. Despuse. Instalacin de abridero con pararrayos en el apoyo No 4. f. Se instalaron 21 estructuras en cruceta volada de las 34 proyectadas para cumplir con el Retie.

g. Se realizaron podas de arboles para limpiar la lnea. Ver foto 4

Foto 4. Poda de arboles

3.2.2. Tado Corcovadoh. En este se ejecutaron la totalidad de los trabajos incluyendo la etapa de pendientes y pintura de posteria segn pliego de condiciones.i. Se instalaron un total de 143 estructuras, de las cuales 123 son nuevos, 11reubicados y 9 existentes, como se aprecia en la tabla 11.

Tabla 12 Cantidades de obra instaladas Tado - Corcovado

j. Se realizo la etapa de georreferenciacion e inventario de materiales en la obra.k. Entre los apoyos 11 al 13 se realizo cambio de trayectoria en el circuito por problemas de servidumbre, instalando poste de 16 mts para realzar la lnea y evitar problemas de altura por se cruce de va. Ver foto 5.

Foto 5. Instalacin poste de 16 mts

l. Se realizaron podas de arboles para limpieza de la lnea. En la tabla 13 se muestra los usuarios a los que se talo, podo y desramo arboles y que deben ser compensados econmicamente por Dispac.

Tabla 13. Listado de usuarios que se le talo arboles 3.3. Anlisis del cronograma de Obra a. A la fecha la obra presenta un porcentaje de ejecucin del 99%. 3.4 Entrega de materiales de DISPAC al contratistaa. Se realizo la etapa de reintegro de materiales nuevos sobrantes en la obra y desmontados por parte del contratista hacia Dispac. Ver foto 6.

b. El contratista hizo entrega de la totalidad del cable ACSR desmontado en la obra, en la siguiente tabla se relacionan la cantidad de material reintegrado por el contratista en dos etapas. Ver tabla 14. Se anexan salidas de almacn.c. El total de cable ACSR desmontado segn tabla 14. Es de 38.436mts, que deben ser liquidados en el desmonte total de cable en las cantidades de obra finales, adems se hizo reintegro de cable nuevo desmontado ver tabla 14A Tabla 14. Cable desmontado entregado a Dispac por el contratista

Tabla 14A. Reintegro de cable nuevo.d. Adems se hizo entrega del resto del material desmontado como, aisladores y herrajes, la totalidad de estos se relaciona en la tabla 15. En la casilla de diferencia se muestra el material que debe ser reintegrado por el contratista.

Tabla 15. Material desmontado entregado a Dispac por el contratista

e. A continuacin se describe el Material despachado por Dispac, el instalado por el contratista, el reintegrado y el faltante. ver tabla 16.CONTROL DE MATERIAL SUMISTRADO DISPAC

Fecha despItemDescripcin temUMP Cant desp Dispac Cantidad Instalada Reintegro FaltanteComentarios

19/07/20102207027AISLADOR PIN 8214 15KV GAMMAUND249

06/09/20102207029AISLADOR PIN 8214 15KV MINQUINUND284

53355200Reutilizaron

19/07/20105303805ESPIGA GALV MET 3/4X6"X2"UND259

06/09/20105303805ESPIGA GALV MET 3/4X6"X2"UND283

54255200Reutilizados

19/07/20102205070AISLADOR POLIMERICO DE CADENAUND142

06/09/20102205070AISLADOR POLIMERICO DE CADENAUND158

29/10/20102205070AISLADOR POLIMERICO DE CADENAUND100

400379210

19/07/20102222063AISLADOR TENSOR 4+1/4"GAMMAUND104

06/09/20102222063AISLADOR TENSOR 4+1/4"GAMMAUND128

23224580Reutilizaron

19/07/20102414743ALAMBRE CU DESNUDO No.6 CEDSAML39

06/09/20102414749ALAMBRE CUDESNUDO No.6 FACELECUND11

505600

19/07/20102414755ALAMBRE CUDESNUDO No.4 FACELECML298

06/09/20102414701ALAMBRECU DESNUDONo.4 CENTELSAML92

39039300

19/07/20105147518BAYONETA DOBLE 1.50MX3X3"X1/4"UND56

06/09/20105147518BAYONETA DOBLE 1.50MX3X3"X1/4"UND66

12212020

19/07/20105147520BAYONETA SENC. 1.50MX3X3"X1/4"UND32

06/09/20105147520BAYONETA SENC. 1.50MX3X3"X1/4"UND9

4130110

19/07/20102413900CABLE SGX 1/4 TIANJINML11.200

06/09/20102413900CABLE SGX 1/4 TIANJINML11.184

22.38421.8285600

19/07/20102414216CABLE ACSR 4/0 AWG PROCABLEML27.000

06/09/20102414216CABLE ACSR 4/0 AWG PROCABLEML25.902

MATERIAL NO RETIRADO CABLE ACSR 4/0 - 1307 Mts51.59548.2043.4930

19/07/20108202027CORTACIRCUITO15KV100A10KAMELECUND37

06/09/20108202027CORTACIRCUITO15KV100A10KAMELECUND16

373160

19/07/20105212020CRUCETA GALV 2.4Mx3" x1/4"UND160

06/09/20105212020CRUCETA GALV 2.4Mx3" x1/4"UND149

30932170Reutilizaron

19/07/20105212050CRUCETA GALV 4.5Mx3" x1/4"UND9

06/09/20105212050CRUCETA GALV 4.5Mx3" x1/4"UND6

151230

19/07/20105302030DIAGONAL GALV V 48"x18"UND136

06/09/20105302030DIAGONAL GALV V 48"x18"UND89

22522320

19/07/20100407073GRAPA RET Recta ACSR 1/0 -4/0UND142

06/09/20100407073GRAPA RET Recta ACSR 1/0 -4/0UND158

29/10/20100407073GRAPA RET Recta ACSR 1/0 -4/0UND100

400370300

19/07/20100407107GRAPA RET.TIPO PISTOLA SGX 1/4UND10011800Reutilizado

19/07/20100407103GRAPA SUSP SGX 1/4 CELEC LTDAUND59

06/09/20100407080GRAPA SUSPENSION SGX 1/4 EPMUND

26/09/20100407080GRAPA SUSPENSION SGX 1/4 EPMUND41

1009550

19/07/20108202000PARARRAYOS POL 10KV 10KA CELSAUND31

06/09/20108212027PARARRAYOS POL 10KV10KA JOSLINUND11

312470

19/07/20105576202PIEAMIGO ANG 2.40MX1+1/2X31/6UND24

06/09/20105576202PIEAMIGO ANG 2.40MX1+1/2X31/6UND17

06/09/20105576202PIEAMIGO ANG 2.40MX1+1/2X31/6UND43

848700Reutilizados

06/09/20105576272POSTE CTO12MTSX1050KF PRETECORUND4

26/11/20105576272POSTE CTO12MTSX1050KF PRETECORUND1

5500

14/07/20105576280POSTECTO 12 MTSX510KF PRETECORUND40

06/09/20105576280POSTECTO 12 MTSX510KF PRETECORUND15

545400

14/07/20105576274POSTE CTO 12 MTSX750KF PRETECORUND30

06/09/20105576274POSTE CTO 12 MTSX750KF PRETECORUND26

525200

26/11/20105576270POSTE CTO16MTSX1050KF PRETECORUND2200

14/07/20105576273POSTE CTO 14 MTSX750KF PRETECORUND9

06/09/20105576273POSTE CTO 14 MTSX750KF PRETECORUND1

06/09/20105576278POSTE CTO14 MTSX1050KF PRETECORUND10

202000

19/07/20105302041RIOSTA PARA CABLE DE GUARDAUND9

06/09/20105302041RIOSTA PARA CABLE DE GUARDAUND6

151050

03/08/20105576252TORRECILLA 12 MTS500K FHERRAJEUND 3

18/08/20105576252TORRECILLA 12 MTS500K FHERRAJEUND 4

03/08/20105576253TORRECILLA 12 MTS500K MHERRAJEUND 1

18/08/20105576253TORRECILLA 12 MTS500K MHERRAJEUND 4

8 8 00

06/09/20105302000VARILL COP 5/8X2.40 ELECTROTECUND 16

19/07/20105302001VARILLA COPER 5/8X2.40 EMSAUND 25

41 32 9

19/07/20105302039VARILLA ANCLAJE 5/8X1.8 DISICOUND 164

06/09/20105302039VARILLA ANCLAJE 5/8X1.8 DISICOUND 218

382 346 360

Tabla 16 Material despachado, instalado, entregado a Dispac

COMENTARIOS:

Se deben reintegrar 21 aisladores polimricos.

Se deben reintegrar 53 cortacircuitos, el contratista hizo dos retiros en el primero retiro 37 y en el segundo retiro 16 para un total de 53, ellos sostienen que hicieron el segundo pedido de 16 ms no el retiro, segn tabla 16. Tomando como referencia el primer pedido de 37, deben reintegrar 6 ,pero en el almacn no se los recibieron como nuevos sino como usados. ver tabla No 16.

El contratista aduce que 6 de esas cajas de cortacircuitos fueron instalados como nuevas en aisladeros provisionales en Manungara y El Dos Plan de raspadura, y que los funcionarios de Dispac haciendo maniobras deterioraron las cajas primarias, quedando con apariencia de usadas.

Se deben reintegrar 30 grapas tipo recta. Lo mismo ocurre con los pararrayos se hicieron dos pedidos uno de 31 y otro de 11, pero solo se reclamo el de primero, para un total de 42, tomando como base el primer pedido de 31, se deben reintegrar 7 unidades. ver tabla No 16.

Brazo viento farol se deben reintegrar 12 y solo se reintegraron 10.

Foto 6. Reintegro de MaterialesM ATERIAL SUMINISTRADO POR EL CONTRATISTTA

CONTRATO 279 - 10

NoDESCRIPCIONUNID. RaspaduraTado - CorcTotal Instalado Despachado Contrat

1Arandela 4x4Un62284346346

2Bloques concretoUn62284346346

3Camisa para vientoUn15355050

4Collarines 200 mmUn000

5Collarines 150 mmUn282957109

6Collarines180 mmUn01717

7Conectores DBH 40/40Un137348485539

8Conectores DBH 10/10Un296796120

9Conectores BimetalicoUn000

10Eslabones en UUn101468569700

11Espaciadores de 5/8 X 10''Un173614787809

12Espaciadores de 5/8 X 12''Un20164184370

13Espaciadores de 5/8 X 8''Un00044

14Grapas de operar en calienteUn8253330

15Guardacabos de 1/2Un78358436400

16Tornillos de 5/8 X 10''Un000

17Tornillos de 5/8 X 11/2''Un144517661700

18Tornillos de 5/8 X 12''Un00050

19Tuercas de ojoUn41317

20Ojal de suspensinUn19597869

21Amortiguadores lnea 4/0Un0121215

Tabla 17 Material suministrado por el Contratista3.5 Solicitudes presentadas de suspensin del servicio.Estas son las solicitudes de suspensin del servicio solicitadas por el contratista a la interventoria en el mes de diciembre y que fueron aprobadas por el Operador de Red.

Tabla 18. Aperturas de servicio realizadas por el contratista mes de diciembre3.6 Bodega, almacenamiento, clasificacin y transporteEl contratista hizo entrega de los materiales sobrantes a almacn de Dispac.4. liquidacion del CONTRATO.De acuerdo al otro si en cuanto a la prorroga del contrato, el contratista finalizo construccin incluyendo los pendientes el da 2 de diciembre del 2010.

La visita para revisin y entrega de Obra a Dispac, se realizo el da 01 de Diciembre del 2010, donde asistieron por parte de la Interventoria el Coordinador Ing. Nelson Vergara, el Ing. residente Carlos Mario Giraldo, por parte de Dispac el Ing. Freddy Pinilla y por parte del Contratista el Ing. Juan Felipe Catao.Para efectos y de acuerdo a los trminos de referencia, tanto la interventoria como el contratista, iniciaron la liquidacin del contrato, de los cuales a continuacin se presenta el cuadro consolidado que muestra cantidades de materiales colocadas en obra y que ha sido un resumen de acuerdo a conciliacin entre Interventoria y Contratista. CANTIDADES CONTRACTUALES INICIALESCANTIDADES CONTRACTUALES ADICIONALESCANTIDAD EJECUTADA

TEMDESCRIPCINUNCANT.VALOR UNITARIOVALOR TOTALCANT.VALOR UNITARIOVALOR TOTALCANT.VALOR TOTAL

1DESMONTAJE DE RED EXISTENTE

1.1Desmonte de poste de concreto de 12mUn95156.29214.847.740120156.29218.755.04011417.817.288

1.2Reubicacin de poste de concreto de 12 m Un39268.80310.483.31711268.8032.956.833133.494.439

1.3Desmontaje de poste de madera de 12 mUn1104.088104.0881104.088104.0881104.088

1.4Desmontaje estructura de media tensin Un19435.4546.878.07619435.4546.878.0761414.999.014

1.5Reubicacin estructura de baja tensin Un1816.952305.1364016.952678.08056949.312

1.6Desmontaje de templete de media tensin Un11825.0002.950.00013025.0003.250.0001323.300.000

1.7Desmontaje de conductor de media tensin M50.21533616.872.24050.21533616.872.24038.43612.914.496

1.8Reubicacin de transformador con proteccionesUn11418.1464.599.60611418.1464.599.606145.854.044

2MONTAJE DE RED NUEVA

2.1Replanteo y digitalizacin de planosUn12.000.0002.000.00012.000.0002.000.00012.000.000

2.2Limpieza de trocha corredor de lnea Km17500.0008.500.00017500.0008.500.000178.500.000

2.3Transporte e instalacin de Poste de concreto 12 m x 510 kgfUn80208.66316.693.04055208.66311.476.4655411.267.802

2.4Transporte e instalacin de Poste de concreto 12 m x 750 kgfUn60238.18614.291.16060238.18614.291.1605713.576.602

2.5Transporte e instalacin de Poste de concreto 14 mts 750 kgUn2568.1331.136.26620568.13311.362.6602212.498.926

2.6Suministro, transporte e instalacin de Estructura RA2-021 (Vestida)Un1571.6701.075.050471.670286.680141.003.380

2.7Suministro, transporte e instalacin de Estructura RA2-022 (Vestida)Un192.48892.4884592.4884.161.960343.144.592

2.8Suministro, transporte e instalacin de Estructura RA2-023 (Vestida)Un15113.4291.701.4355113.429567.1452226.858

2.9Suministro, transporte e instalacin de Estructura RA2-024 (Vestida)Un1160.367160.3678160.3671.282.9365801.835

2.10Suministro, transporte e instalacin de Estructura RA2-026 (Vestida)Un2281.555563.1100281.555000

2.11Suministro, transporte e instalacin de Estructura RA2-026 (2F) (Vestida)Un27242.8346.556.51811242.8342.671.174143.399.676

2.12Suministro, transporte e instalacin de Estructura RA2-007 (Vestida)Un496.971387.884696.971581.8267678.797

2.13Suministro, transporte e instalacin de Estructura RA2-051 (Vestida)Un49118.2725.795.32815118.2721.774.080222.601.984

2.14Suministro, transporte e instalacin de Estructura RA2-052 (Vestida)Un53127.3326.748.59636127.3324.583.952324.074.624

2.15Suministro, transporte e instalacin de Estructura RA2-053 (Vestida)Un24146.5883.518.1122146.588293.176192.785.172

2.16Suministro, transporte e instalacin de Estructura RA2-054 (Vestida)Un18212.6083.826.94435212.6087.441.2805110.843.008

2.17Suministro, transporte e instalacin de Estructura RA2-074 (Vestida)Un9447.2644.025.3766447.2642.683.58452.236.320

2.18Suministro, transporte e instalacin de Estructura RA2-640 (Vestida)Un1584.378584.3780584.378000

2.19Suministro, transporte e instalacin de Templete directo a tierra en MT Un16988.13714.895.15324088.13721.152.88023620.800.332

2.20Suministro, transporte e instalacin de Templete en farol en MTUn4095.7863.831.4401595.7861.436.7908766.288

2.21Suministro, transporte e instalacin de Templete para cable de guardaUn11984.09410.007.18618084.09415.136.9201018.493.494

CANTIDADES CONTRACTUALES INICIALESCANTIDADES CONTRACTUALES ADICIONALESCANTIDAD EJECUTADA

TEMDESCRIPCINUNCANT.VALOR UNITARIOVALOR TOTALCANT.VALOR UNITARIOVALOR TOTALCANT.VALOR TOTAL

2.22Suministro, transporte e instalacin de AmortiguadoresUn1828.798518.3643028.798863.94016460.768

2.23Suministro, transporte e instalacin de Puesta a tierra en MTUn2136.557767.6972136.557767.69717621.469

2.24Transporte e instalacin de Red 3# 4/0 ACSR mMts17.6343.18256.111.38817.6343.18256.111.38815.60049.639.200

2.25Transporte e instalacin de Cable de guarda SGX 1/4 "Mts17.6341.00017.634.00017.6341.00017.634.00015.60015.600.000

2.26Suministro, transporte e instalacin de Cimentacin Tipo 2Un5099.9184.995.9008099.9187.993.44010510.491.390

2.27Suministro, transporte e instalacin de Cimentacin Tipo 3Un1594.2781.414.1701594.2781.414.17000

2.28Suministro, transporte e instalacin de Cimentacin AnclajesUn9392.6668.617.93812092.66611.119.92018917.513.874

2.29Suministro, transporte e instalacin de Concreto de 3.000 PSI (1:2:3)Un5315.8451.579.2255315.8451.579.22551.579.225

2.30Suministro, transporte e instalacin de Concreto de 2.500 PSI (1:2:3.5)Un5303.3561.516.7805303.3561.516.7803910.068

3ACTIVIDADES NO PREVISTAS

3.1Suministro, transporte e instalacin de Estructura RA2 - 040 (Vestida)Un

293.306186.6123279.918

3.2Suministro, transporte e instalacin de Templete con poste auxiliar en MT Un490.833363.332190.833

3.3Transporte e instalacin de estructura tipo torrecilla de 12mUn8238.1861.905.48881.905.488

3.4Instalacion de camisa para vientoUn5058.3962.919.800502.919.800

TOTAL COSTOS DIRECTOS256.585.496270.154.423261.144.404

ADMINISTRACIN8%20.526.84021.612.35420.891.552

IMPREVISTOS4%10.263.42010.806.17710.445.776

UTILIDADES4%10.263.42010.806.17710.445.776

IVA (16% SOBRE UTILIDAD)16%1.642.1471.728.9881.671.324

COSTO TOTAL299.281.323315.108.119304.598.833

CUADRO RESUMEN DE OBRA

Los cuadros que a continuacin relaciono van en un DVD, anexo al informe.

Materiales desmontados por el contratista, y entregados a almacn Dispac.

Materiales suministrados por el contratista.

Materiales suministrados por Dispac al contratista.

Punto a punto georeferenciado.

Balance de materiales en Obra.

Planos elctricos definitivos.

Registro fotogrfico del antes y despus.

Informe final del contratista.

En cuanto a la liquidacin en si del contrato 279-10, la interventoria esta elaborando las actas de RECEPCION FINAL , y de LIQUIDACION FINAL , de los cuales se encuentran en Bogot para revisin , y ser enviadas firmadas en Original por la representante Legal de GPI LTDA BOGOTA.

5. salud ocupaciOnal Y SSOMAa. Durante el mes de diciembre no se presentaron accidentes de trabajo.b. Cumpliendo con lo establecido en el pliego de condiciones, el da 6 de noviembre el contratista realizo capacitacin a todo el personal sobre elementos bsicos de salud ocupacional y trabajos en altura.5.1 Afiliaciones al sistema de seguridad socialEn el siguiente cuadro se reflejan las Empresas a las cuales han sido afiliados los trabajadores del Contratista Electromontajes. Es de anotar que la informacin aqu presentada ha sido debidamente revisada en medio fsico por la Interventora, y corresponde nica y exclusivamente a la enviada por el Contratista. De igual manera, se verific en campo que este sea el personal que se encuentra laborando.Como parte del cumplimiento de lo establecido en el Plan de Salud Ocupacional del mes de Octubre de 2010 se presenta el siguiente cuadro:

Tabla 19. Listado chequeo seguridad social del contratista5.2 Pagos de seguridad socialSe presentan en anexo, los pagos que aplican del mes de diciembre de 2010.La interventora reviso las planillas de pago presentadas en forma digital por el contratista. Los pagos fueron realizados por el contratista cumplidamente y corresponden a todo el personal en obra, el cual est relacionado en el cuadro anterior.5.3 Planes de calidad y SOMMAEl contratista presento el Plan de Calidad, El plan de Salud Ocupacional y el panorama de riesgos el da 28 de junio del 2010 mediante correo electrnico, y fue revisado en las oficinas principales de GPI LTDA, de los cuales fue devuelto con observaciones al contratista el da 5 de julio del 2010, para una aprobacin definitiva el da 9 de julio del 2010 por parte de la seccin de Calidad de GPI LTDA.5.4 Aspectos ambientales

El da 29 de octubre el contratista Electromontajes entrego a Codechoco el oficio donde se relaciona el plan de aprovechamiento forestal nico, elaborado por el Ingeniero Agroindustrial Roberto Roa para su aprobacin. Dicha aprobacin es fundamental para llegar a un acuerdo entre Asocasan y Dispac. A la fecha no se conoce respuesta alguna por parte de Codechoco.6. Logros alcanzados y deficiencias presentados6.1 Logrosc. La concertacin entre Dispac y propietarios de predios particulares tanto en el trayecto Tado Corcovado como en el Dos Plan de Raspadura, que permitieron la culminacin de las obras. d. Entrega de la totalidad de los materiales desmontados y sobrantes nuevos del proyecto por parte del contratista.e. Terminacin de los trabajos por parte del contratista a satisfaccin de la interventoria.f. No se presentaron accidentes de trabajo en el mes de diciembre por parte del contratista.

6.2 Deficienciasa. Demora en las concertaciones que debi realizar Dispac con propietarios de predios particulares, para definir las servidumbres que demoraron la ejecucin de los trabajos.b. Mala calidad en postes suministrados por Dispac, marca Pretensados de Risaralda de los cuales la interventoria envi oficio a Dispac PC- 113 QUD-68 de noviembre 19 de 2010, haciendo claridad de dicha calidad. Paraello fueron cambiados por marca Pretecor para garantizar estabilidad en la obra. c. La inestabilidad del personal laborando en el proyecto.d. Demora por parte de Codechoco de la aprobacin del PMA

7. CONCLUSIONES.a. El dia 29 de octubre el contratista entrego a Codechoco el oficio donde se relaciona el Plan de aprovechamiento forestal nico para su aprobacin y seguimiento. Dicha aprobacin es fundamental para llegar a acuerdo entre Asocasan y Dispac, a la fecha no se conoce respuesta de su aprobacin por parte de Codechoco.b. La demora por parte de Dispac en las negociaciones de servidumbres y compensaciones con propietarios de predios particulares, que retrasaron la ejecucin de las obras y que no permitieron que el contrato se ejecutara en el tiempo previsto, 17 de noviembre de 2010.

c. Terminacin de los trabajos a satisfaccin de la interventoria.

d. A pesar de las intensas lluvias que azotan al pas entero se terminaron la totalidad de los trabajos.Elaboro,

Ing. Carlos M. Giraldo G.Residente GPI LTDA.

Debe presentar cuadro con la actualizacin de plizas segn el otro s de vigencia en noviembre.

PENDIENTE REVISAR

PENDIENTE REVISAR

Pendiente Revisar

PENDIENTE REVISAR