    PROYECTO:

    ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNAFECHA : JULIO 2008

    LARGO ( L) ANCHO (B) ALTO (H)

    01.00.00 OBRAS PROVISIONALES

    01.01.00 CARTEL DE IDENTIFICACION DE OBRA UND 1.001.00 1.00

    01.02.00 CARTEL DE SEALIZACION DE DESVIOS EN LA ZONA DE TRABAJO UND 4.004.00 4.00

    01.03.00 MODULO DE MATERIALES Y HERRAMIENTAS P/MANTENIMIENTO GLB 1.001.00 1.00

    02.00.00 TRABAJOS PRELIMINARES

    02.01.00 LIMPIEZA Y LIJADO DE MUROS EXTERIORES H=2.7 M. M2 1,500.23S-01

    ef. 2 1.00 area= 83.18 83.18S-04

    ef. 3 1.00 area= 11.00 11.00ef. 5 1.00 area= 37.70 37.70ef. 6 1.00 area= 28.40 28.40ef. 8 1.00 area= 91.47 91.47

    S-07

    ef. 3 1.00 area= 16.20 16.20ef. 5 1.00 area= 30.70 30.70ef. 6 1.00 area= 28.30 28.30ef. 7 1.00 area= 17.30 17.30ef. 8 1.00 area= 15.20 15.20

    S-08ef. 1 1.00 area= 29.10 29.10ef. 2 1.00 area= 73.60 73.60ef. 3 1.00 area= 19.40 19.40ef. 4 1.00 area= 11.30 11.30ef. 5 1.00 area= 12.60 12.60ef. 6

    1.00 area= 31.70 31.70ef. 7 1.00 area= 78.95 78.95S-09

    ef. 3 1.00 area= 20.20 20.20S-11

    ef. 1 1.00 area= 143.85 143.85ef. 2 1.00 area= 11.40 11.40ef. 9 1.00 area= 118.81 118.81

    S-12ef. 1 1.00 area= 75.67 75.67ef. 3 1.00 area= 8.50 8.50ef. 4 1.00 area= 16.20 16.20

    S-13ef. 4 1.00 area= 11.50 11.50ef. 6 1.00 area= 79.56 79.56

    S-15ef. 1 1.00 area= 48.10 48.10ef. 2 1.00 area= 29.70 29.70

    S-16ef. 5 1.00 area= 5.80 5.80ef. 6 1.00 area= 3.40 3.40ef. 9 1.00 area= 4.70 4.70

    ef. 14 1.00 area= 19.50 19.50

    ef. 15 1.00 area= 41.99 41.99S-17ef. 3 1.00 area= 33.80 33.80

    S-19ef. 2 1.00 area= 13.90 13.90ef. 4 1.00 area= 17.70 17.70

    S-20ef. 3 1.00 area= 7.95 7.95ef. 4 1.00 area= 14.70 14.70ef. 7 1.00 area= 43.90 43.90

    S-21ef. 4 1.00 area= 15.10 15.10ef. 5 1.00 area= 31.30 31.30

    ef. 10 1.00 area= 9.20 9.20ef. 11 1.00 area= 29.50 29.50ef. 13 1.00 area= 28.20 28.20

    ITEM DESCRIPCION

    PLANILLA DE METRADOS

    UND PARCIALMEDIDAS

    TOTALCANT

    VECES

  • 8/14/2019 Metrado Fachadas 2 de Mayo

    2/8

    PROYECTO:

    ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNAFECHA : JULIO 2008

    LARGO (L) ANCHO (B) ALTO (H)ITEM DESCRIPCION

    PLANILLA DE METRADOS

    UND PARCIALMEDIDAS

    TOTALCANT

    VECES

    02.02.00 LIMPIEZA Y LIJADO DE MUROS EXTERIORES H=5.0 M. M2 4,068.00S-02

    ef. 2 1.00 area= 26.20 26.20ef. 3 1.00 area= 37.80 37.80ef. 4 1.00 area= 31.10 31.10ef. 5 1.00 area= 159.22 159.22

    S-04ef. 2 1.00 area= 44.50 44.50ef. 4

    1.00 area= 32.90 32.90ef. 7 1.00 area= 13.80 13.80S-07

    ef. 1 1.00 area= 109.92 109.92ef. 2 1.00 area= 36.16 36.16ef. 4 1.00 area= 12.50 12.50ef. 9 1.00 area= 30.00 30.00

    ef. 10 1.00 area= 29.00 29.00ef. 11 1.00 area= 203.90 203.90

    S-09ef. 1 1.00 area= 192.10 192.10ef. 2 1.00 area= 43.90 43.90ef. 4 1.00 area= 165.90 165.90ef. 5 1.00 area= 64.03 64.03

    S-10ef. 3 1.00 area= 230.62 230.62

    S-11ef. 3 1.00 area= 14.80 14.80ef. 4 1.00 area= 12.50 12.50ef. 7 1.00 area= 15.10 15.10ef. 8 1.00 area= 9.60 9.60

    S-12ef. 5 1.00 area= 20.00 20.00

    ef. 6 1.00 area= 15.10 15.10ef. 7 1.00 area= 17.25 17.25ef. 8 1.00 area= 71.64 71.64

    S-13ef. 1 1.00 area= 314.99 314.99ef. 2 1.00 area= 37.40 37.40ef. 3 1.00 area= 11.50 11.50ef. 5 1.00 area= 21.20 21.20

    S-14ef. 1 1.00 area= 147.16 147.16ef. 2 1.00 area= 144.30 144.30ef. 3 1.00 area= 85.70 85.70

    S-16ef. 2 1.00 area= 36.20 36.20ef. 3 1.00 area= 27.30 27.30ef. 4 1.00 area= 33.00 33.00ef. 8 1.00 area= 25.70 25.70

    ef. 11 1.00 area= 19.10 19.10ef. 13 1.00 area= 12.20 12.20

    S-17ef. 1 1.00 area= 44.80 44.80ef. 2 1.00 area= 32.14 32.14

    S-19

    ef. 1 1.00 area= 38.14 38.14ef. 3 1.00 area= 30.00 30.00ef. 6 1.00 area= 53.70 53.70ef. 7 1.00 area= 74.20 74.20ef. 8 1.00 area= 377.66 377.66

    S-20ef. 1 1.00 area= 199.20 199.20ef. 2 1.00 area= 32.30 32.30ef. 5 1.00 area= 31.40 31.40ef. 6 1.00 area= 66.20 66.20ef. 9 1.00 area= 198.92 198.92

    S-21ef. 1 1.00 area= 116.65 116.65ef. 2 1.00 area= 63.10 63.10ef. 3 1.00 area= 56.00 56.00ef. 6 1.00 area= 41.20 41.20ef. 7 1.00 area= 14.80 14.80ef. 8 1.00 area= 10.90 10.90

    ef. 12 1.00 area= 31.40 31.40

  • 8/14/2019 Metrado Fachadas 2 de Mayo

    3/8

    PROYECTO:

    ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNAFECHA : JULIO 2008

    LARGO (L) ANCHO (B) ALTO (H)ITEM DESCRIPCION

    PLANILLA DE METRADOS

    UND PARCIALMEDIDAS

    TOTALCANT

    VECES

    02.03.00 LIMPIEZA Y LIJADO DE PUERTAS DE MADERA M2 798.05S-01

    ef. 2 1.00 area= 8.10 8.10S-02

    ef. 2 1.00 area= 2.20 2.20ef. 4 1.00 area= 9.80 9.80ef. 5 1.00 area= 6.18 6.18

    S-04ef. 2

    1.00 area= 12.90 12.90ef. 3 1.00 area= 7.30 7.30ef. 4 1.00 area= 14.70 14.70ef. 5 1.00 area= 11.70 11.70ef. 6 1.00 area= 9.40 9.40ef. 7 1.00 area= 1.90 1.90ef. 8 1.00 area= 17.84 17.84

    S-07ef. 1 1.00 area= 60.53 60.53ef. 2 1.00 area= 5.20 5.20ef. 3 1.00 area= 4.80 4.80ef. 4 1.00 area= 6.30 6.30ef. 5 1.00 area= 8.40 8.40ef. 6 1.00 area= 15.40 15.40ef. 7 1.00 area= 3.00 3.00ef. 8 1.00 area= 4.30 4.30ef. 9 1.00 area= 9.20 9.20

    ef. 10 1.00 area= 7.00 7.00ef. 11 1.00 area= 19.90 19.90

    S-08ef. 1 1.00 area= 4.64 4.64ef. 2 1.00 area= 10.20 10.20ef. 3 1.00 area= 5.50 5.50

    ef. 6 1.00 area= 12.90 12.90ef. 7 1.00 area= 10.02 10.02

    S-09ef. 1 1.00 area= 6.76 6.76ef. 4 1.00 area= 16.00 16.00

    S-10ef. 3 1.00 area= 45.84 45.84

    S-11ef. 1 1.00 area= 27.74 27.74ef. 2 1.00 area= 3.30 3.30ef. 3 1.00 area= 3.00 3.00ef. 4 1.00 area= 7.20 7.20ef. 9 1.00 area= 20.77 20.77

    S-12ef. 3 1.00 area= 3.90 3.90ef. 7 1.00 area= 2.20 2.20

    S-13ef. 1 1.00 area= 90.62 90.62ef. 2 1.00 area= 5.60 5.60ef. 4 1.00 area= 5.70 5.70ef. 5 1.00 area= 2.70 2.70ef. 6 1.00 area= 11.99 11.99

    S-14

    ef. 1 1.00 area= 24.85 24.85ef. 2 1.00 area= 28.20 28.20ef. 3 1.00 area= 18.60 18.60

    S-15ef. 1 1.00 area= 32.50 32.50ef. 2 1.00 area= 5.50 5.50

    S-16ef. 2 1.00 area= 2.40 2.40ef. 3 1.00 area= 5.30 5.30ef. 4 1.00 area= 6.00 6.00ef. 7 1.00 area= 6.00 6.00

    ef. 9 1.00 area= 4.40 4.40ef. 11 1.00 area= 8.10 8.10ef. 14 1.00 area= 12.60 12.60ef. 15 1.00 area= 10.07 10.07

    S-17ef. 2 1.00 area= 1.70 1.70ef. 3 1.00 area= 7.50 7.50

    S-19

  • 8/14/2019 Metrado Fachadas 2 de Mayo

    4/8

    PROYECTO:

    ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNAFECHA : JULIO 2008

    LARGO (L) ANCHO (B) ALTO (H)ITEM DESCRIPCION

    PLANILLA DE METRADOS

    UND PARCIALMEDIDAS

    TOTALCANT

    VECES

    ef. 6 1.00 area= 2.30 2.30ef. 7 1.00 area= 6.30 6.30ef. 8 1.00 area= 57.14 57.14

    S-20ef. 5 1.00 area= 6.70 6.70ef. 9 1.00 area= 3.26 3.26

    S-21ef. 5 1.00 area= 6.00 6.00

    02.04.00 LIMPIEZA Y LIJADO DE VENTANAS, MARCOS Y BARANDAS DE MADERAM2 276.12S-04

    ef. 2 1.00 area= 2.60 2.60ef. 4 1.00 area= 11.30 11.30ef. 5 1.00 area= 1.10 1.10

    S-07ef. 1 1.00 area= 5.20 5.20ef. 2 1.00 area= 1.50 1.50ef. 3 1.00 area= 1.30 1.30ef. 9 1.00 area= 1.20 1.20

    ef. 11 1.00 area= 4.20 4.20

    S-08ef. 1 1.00 area= 1.30 1.30ef. 3 1.00 area= 6.60 6.60

    S-09ef. 2 1.00 area= 2.30 2.30ef. 3 1.00 area= 3.30 3.30

    S-10ef. 3 1.00 area= 25.46 25.46

    S-11ef. 1 1.00 area= 7.19 7.19

    ef. 2 1.00 area= 1.10 1.10ef. 3 1.00 area= 5.30 5.30ef. 4 1.00 area= 0.80 0.80ef. 7 1.00 area= 2.10 2.10ef. 9 1.00 area= 4.96 4.96

    S-12ef. 3 1.00 area= 0.60 0.60ef. 7 1.00 area= 1.80 1.80ef. 8 1.00 area= 4.95 4.95

    S-13ef. 1 1.00 area= 38.40 38.40ef. 2 1.00 area= 1.70 1.70ef. 6 1.00 area= 6.03 6.03

    S-14ef. 1 1.00 area= 2.84 2.84ef. 2 1.00 area= 10.80 10.80ef. 3 1.00 area= 1.80 1.80

    S-16ef. 3 1.00 area= 5.10 5.10ef. 4 1.00 area= 4.00 4.00

    ef. 11 1.00 area= 1.60 1.60S-17

    ef. 1 1.00 area= 7.80 7.80ef. 3 1.00 area= 2.20 2.20

    S-19ef. 7 1.00 area= 7.40 7.40ef. 8 1.00 area= 89.39 89.39

    S-21ef. 5 1.00 area= 0.90 0.90

    02.05.00 LIMPIEZA Y LIJADO DE CARPINTERIA METALICA M2 977.80S-01

    ef. 2 1.00 area= 4.74 4.74S-02

    ef. 21.00 area= 7.10 7.10ef. 3 1.00 area= 6.40 6.40

    ef. 5 1.00 area= 6.04 6.04S-04

    ef. 5 1.00 area= 11.70 11.70ef. 7 1.00 area= 4.50 4.50ef. 8 1.00 area= 7.06 7.06

  • 8/14/2019 Metrado Fachadas 2 de Mayo

    5/8

  • 8/14/2019 Metrado Fachadas 2 de Mayo

    6/8

    PROYECTO:

    ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNAFECHA : JULIO 2008

    LARGO (L) ANCHO (B) ALTO (H)ITEM DESCRIPCION

    PLANILLA DE METRADOS

    UND PARCIALMEDIDAS

    TOTALCANT

    VECES

    02.06.00 LIMPIEZA Y LIJADO DE REJAS METALICAS EXISTENTES M2 707.68S-01

    ef. 2 1.00 area= 16.80 16.80S-02

    ef. 2 1.00 area= 6.20 6.20ef. 3 1.00 area= 5.30 5.30ef. 4 1.00 area= 1.00 1.00

    S-04ef. 4

    1.00 area= 5.20 5.20ef. 5 1.00 area= 1.10 1.10ef. 7 1.00 area= 4.40 4.40

    S-07ef. 1 1.00 area= 3.10 3.10ef. 2 1.00 area= 5.00 5.00ef. 3 1.00 area= 4.80 4.80ef. 4 1.00 area= 3.00 3.00ef. 6 1.00 area= 10.20 10.20ef. 8 1.00 area= 2.30 2.30ef. 9 1.00 area= 5.30 5.30

    ef. 10 1.00 area= 3.60 3.60ef. 11 1.00 area= 0.90 0.90

    S-08ef. 1 1.00 area= 0.17 0.17ef. 4 1.00 area= 5.00 5.00ef. 7 1.00 area= 12.60 12.60

    S-09ef. 1 1.00 area= 16.01 16.01ef. 2 1.00 area= 1.90 1.90ef. 4 1.00 area= 6.20 6.20ef. 5 1.00 area= 18.04 18.04

    S-10

    ef. 3 1.00 area= 11.93 11.93S-11

    ef. 1 1.00 area= 3.62 3.62ef. 3 1.00 area= 1.92 1.92ef. 4 1.00 area= 4.80 4.80ef. 7 1.00 area= 8.80 8.80ef. 8 1.00 area= 7.60 7.60ef. 9 1.00 area= 3.40 3.40

    S-12ef. 1 1.00 area= 22.00 22.00ef. 3 1.00 area= 9.00 9.00ef. 6 1.00 area= 7.20 7.20ef. 8 1.00 area= 4.95 4.95

    S-13ef. 1 1.00 area= 50.33 50.33ef. 5 1.00 area= 8.10 8.10ef. 6 1.00 area= 29.15 29.15

    S-14ef. 2 1.00 area= 12.12 12.12ef. 3 1.00 area= 6.12 6.12

    S-15ef. 2 1.00 area= 7.36 7.36

    S-16

    ef. 2 1.00 area= 3.40 3.40ef. 3 1.00 area= 7.40 7.40ef. 4 1.00 area= 2.00 2.00ef. 7 1.00 area= 5.70 5.70ef. 8 1.00 area= 2.10 2.10ef. 9 1.00 area= 5.20 5.20

    ef. 15 1.00 area= 5.21 5.21S-17

    ef. 1 1.00 area= 9.10 9.10ef. 3 1.00 area= 4.40 4.40

    S-19

    ef. 1 1.00 area= 2.28 2.28ef. 4 1.00 area= 5.30 5.30ef. 6 1.00 area= 7.60 7.60ef. 7 1.00 area= 21.00 21.00

  • 8/14/2019 Metrado Fachadas 2 de Mayo

    7/8

    PROYECTO:

    ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNAFECHA : JULIO 2008

    LARGO (L) ANCHO (B) ALTO (H)ITEM DESCRIPCION

    PLANILLA DE METRADOS

    UND PARCIALMEDIDAS

    TOTALCANT

    VECES

    S-20ef. 1 1.00 area= 18.15 18.15ef. 2 1.00 area= 87.90 87.90ef. 3 1.00 area= 11.68 11.68ef. 4 1.00 area= 12.94 12.94ef. 5 1.00 area= 6.94 6.94ef. 6 1.00 area= 10.70 10.70ef. 7 1.00 area= 16.90 16.90ef. 9

    1.00 area= 38.48 38.48S-21ef. 1 1.00 area= 4.57 4.57ef. 2 1.00 area= 30.24 30.24ef. 4 1.00 area= 16.63 16.63ef. 5 1.00 area= 3.98 3.98ef. 6 1.00 area= 2.80 2.80ef. 7 1.00 area= 0.25 0.25

    ef. 10 1.00 area= 11.17 11.17ef. 12 1.00 area= 17.14 17.14

    02.07.00 LIMPIEZA Y LIJADO DE MUROS CON PIEDRA DE CANTERA M2 125.86S-07

    ef. 1 1.00 area= 10.78 10.78S-08

    ef. 2 1.00 area= 34.40 34.40S-12

    ef. 1 1.00 area= 22.58 22.58S-13

    ef. 3 1.00 area= 4.50 4.50S-19

    ef. 8 1.00 area= 53.60 53.60

    02.08.00 LIMPIEZA DE MUROS ENCHAPADOS C/PIEDDRA LAJA, CERAMICO O SIMIM2 237.78S-09

    ef. 5 1.00 area= 18.30 18.30S-11

    ef. 4 1.00 area= 6.90 6.90ef. 7 1.00 area= 2.40 2.40

    S-12ef. 1 1.00 area= 33.48 33.48ef. 2 1.00 area= 19.80 19.80ef. 7 1.00 area= 7.50

    S-13ef. 1 1.00 area= 19.30 19.30ef. 5 1.00 area= 11.00 11.00

    S-16ef. 7 1.00 area= 6.90 6.90

    ef. 10 1.00 area= 15.30 15.30S-19

    ef. 1 1.00 area= 14.90 14.90ef. 8 1.00 area= 37.40 37.40

    S-20ef. 1 1.00 area= 15.70 15.70

    S-21ef. 7 1.00 area= 7.20 7.20ef. 8 1.00 area= 4.80 4.80

    ef. 11 1.00 area= 24.40 24.40

    02.09.00 PICADO DE MUROS A RESANAR M2 22.711.00 area= 22.71 22.71

    03.00.00 RESANES Y DEMAS REPARACIONES

    03.01.00 RESANE EN MUROS DE ADOBE (TIPO DIABLO FUERTE) M2 8.41S-4, ef 2 1.00 area= 0.06 0.06S-4, ef 8 1.00 area= 0.14 0.14S-7, ef 1 1.00 area= 1.51 1.51S-7, ef 3

    1.00 area= 0.10 0.10S-8, ef 1 1.00 area= 0.12 0.12S-8, ef 2 1.00 area= 2.20 2.20S-8, ef 3 1.00 area= 1.60 1.60S-11, ef 1 1.00 area= 0.46 0.46S-11, ef 9 1.00 area= 0.01 0.01S-21, ef 5 1.00 area= 2.21 2.21

  • 8/14/2019 Metrado Fachadas 2 de Mayo

    8/8

    PROYECTO:

    ENTIDAD : MUNICIPALIDAD PROVINCIAL DE TACNAFECHA : JULIO 2008

    LARGO (L) ANCHO (B) ALTO (H)ITEM DESCRIPCION

    PLANILLA DE METRADOS

    UND PARCIALMEDIDAS

    TOTALCANT

    VECES

    03.02.00 RESANE EN MUROS DE ALBAILERIA M2 14.30S -1, ef 1 1.00 area= 0.50 0.50S -2, ef 2 1.00 area= 0.26 0.26S -2, ef 4 1.00 area= 0.05 0.05S -2, ef 5 1.00 area= 0.03 0.03S -4, ef 5 1.00 area= 0.37 0.37S -4, ef 6 1.00 area= 0.02 0.02S-7, ef 2 1.00 area= 0.37 0.37S-7, ef 5

    1.00 area= 0.31 0.31S-7, ef 6 1.00 area= 0.28 0.28S-7, ef 8 1.00 area= 0.15 0.15S-7, ef 10 1.00 area= 0.15 0.15S-7, ef 11 1.00 area= 0.03 0.03S-8, ef 4 1.00 area= 0.40 0.40S-9, ef 2 1.00 area= 0.44 0.44S-10, ef 3 1.00 area= 0.63 0.63S-12, ef 3 1.00 area= 0.05 0.05S-12, ef 6 1.00 area= 0.20 0.20S-13, ef 4 1.00 area= 0.34 0.34S-14, ef 1 1.00 area= 0.49 0.49S-14, ef 2 1.00 area= 0.20 0.20S-14, ef 3 1.00 area= 0.85 0.85S-15, ef 1 1.00 area= 0.24 0.24S-16, ef 2 1.00 area= 0.36 0.36S-16, ef 5 1.00 area= 0.48 0.48S-16, ef 8 1.00 area= 0.80 0.80S-16, ef 11 1.00 area= 0.10 0.10S-16, ef 14 1.00 area= 0.40 0.40S-19, ef 2 1.00 area= 0.10 0.10S-19, ef 5 1.00 area= 0.50 0.50S-19, ef 7 1.00 area= 0.74 0.74

    S-20, ef 3 1.00 area= 0.48 0.48S-20, ef 4 1.00 area= 0.14 0.14S-20, ef 5 1.00 area= 0.05 0.05S-20, ef 7 1.00 area= 0.43 0.43S-21, ef 2 1.00 area= 0.63 0.63S-21, ef 3 1.00 area= 0.55 0.55S-21, ef 5 1.00 area= 1.85 1.85S-21, ef 6 1.00 area= 0.21 0.21S-21, ef 8 1.00 area= 0.05 0.05S-21, ef 10 1.00 area= 0.07 0.07

    03.03.00 RESANE EN CARPINTERIA DE MADERA GLB 1.001.00 1.00

    03.04.00 TAPADO DE VENTANAS CON TRIPLAY M2 5.20S-8, ef 3 5.20 5.20

    04.00.00 PINTURA

    04.01.00 PINTURA OLEO MATE EN MUROS EXTERIORES H=2.70M. M2 1,500.231.00 area= 1,500.23 1,500.23

    04.02.00 PINTURA OLEO MATE EN MUROS EXTERIORES H=5.0M. M2 4,068.001.00 area= 4,068.00 4,068.00

    04.03.00 PINTURA BARNIZ EN PUERTAS DE MADERA M2 798.051.00 area= 798.05 798.05

    04.04.00 PINTURA BARNIZ EN VENTANAS, MARCOS Y BARANDAS DE MADERA M2 276.121.00 area= 276.12 276.12

    04.05.00 PINTURA ESMALTE EN CARPINTERIA METALICA M2 977.801.00 area= 977.80 977.80

    04.06.00 PINTURA ESMALTE EN REJAS METALICAS EXISTENTES M2 707.68

    1.00 area= 707.68 707.68

    05.00.00 VARIOS

    05.01.00 LIMPIEZA FINAL DE OBRA M2 8,327.881.00 area= 8,327.88 8,327.88