Metrado Puente Estribo Yanamayo

37
METRADO PUENTE EL INGENIO 5m 5m A 5m 5 m L A = ancho total del puente = 4.80 m L = Longitud total del puente= 10.00 m A´= ancho total de estribos = 5.90 m. L´= longitud total de alas = 20.00 m # De estribos = 2 u. PUENTE PLANTA

Transcript of Metrado Puente Estribo Yanamayo

Page 1: Metrado Puente Estribo Yanamayo

METRADO PUENTE EL INGENIO

5m 5m

A A´

5m5 m

L

A = ancho total del puente = 4.80 mL = Longitud total del puente= 10.00 mA´= ancho total de estribos = 5.90 m.L´= longitud total de alas = 20.00 m# De estribos = 2 u.

PUENTE PLANTA

Page 2: Metrado Puente Estribo Yanamayo

a2 a1 c

h3

h4

h

h2

t

B

D b D´1

a1 = 0.50 m h = 8.60 ma2 = 0.50 m h2 = 1.60 mD = 1.20 m h3 = 0.80 mb = 1.20 m h4 = 7.00 m

D´1 = 1.80 m B = 4.20 mt = 0.80 m c = 0.20 m

CORTE ESTRIBO

Page 3: Metrado Puente Estribo Yanamayo

a´ c´

h2´

Promedio h´

h3´ t´

D´ b´ D´1 "

DIMENSIONES SECCION INICIAL (i)

a´ = 0.60 m h´ = 6.23 m promedioc´ = 0.60 m h2´ = 5.85 m

D´ = 1.20 m h3´ = 1.40 mb´ = 1.20 m B´ = 4.10 m

D´1" = 1.70 m t´ = 0.80 m

DIMENSIONES SECCION FINAL (f)

a´ = 0.60 m h´ = 6.23 mc´ = 0.60 m h2´ = 5.85 m

D´ = 1.20 m h3´ = 1.40 mb´ = 1.20 m B´ = 4.10 m

D´1" = 1.70 m t´ = 0.80 m

CORTE ALA

Page 4: Metrado Puente Estribo Yanamayo

B1 V S' V B1

g

c1 e

t1f

b1 S b1 S1

B1 = 0.00 m g = 0.90 mV = 0.60 m c1 = 0.20 mS´= 3.60 m e = 0.20 mt1 = 0.80 m f = 0.60 mb1 = 0.50 m S = 2.00 mS1 = 0.90 m

CORTE SUPERESTRUCTURA

VIGAS DIAFRAGMAS

l = LARGO DIAFRAGM 2.00 mt1´ b1´= ANCHO DIAFRAG 0.25 m

t1´= ALTO DIAFRAGM 0.50 m# DE DIFRAGMAS = 3.00

´ b1´

Page 5: Metrado Puente Estribo Yanamayo

01,01,01 TRAZO Y REPLANTEO CON TOPOGRAFOESTRIBOS Y ALAS = A´*B*#Estribos + (B´(i)+B´(f))/2)*L´= 131.56 m2PUENTE = L*A´= 56.44 m2

TOTAL = 188.00 m2

01.01.02 LIMPIEZA MANUAL DE CAUCE DE RIOAREA A INTERVENIR 60 m2

TOTAL= 60 m2

01.01.03 DEMOLICION Y ELIMINACION DE ESTRUVTURAS EXISTENTESVOLUMEN TOTAL= 90.00 m3

TOTAL= 90.00 m3

01.02.01 EXCAVACION EN TERRENO SUELTO

VOLUMEN TOTAL= 147.71 m3TOTAL= 147.71 m3

01.02.02 EXCAVACION EN SUELO GRAVOSO BAJO AGUA

VOLUMENT TOTAL= 89.11 m3TOTAL= 89.11 m3

01.02.03 EXCAVACION EN ROCA

VOLUMEN TOTAL= 89.11 m3TOTAL= 89.11 m3

01.02.04 RELLENO Y COMPACTACION CON MATERIAL PROPIO

Se tendrá en cuenta el relleno, en ambos márgenes,(adyacente a los estribos), hasta lograr el nivel de de la carretera, que coincida con el nivel del puente, menos una capa de 30 cms, la cual será rellenada , con material de préstamo.

La forma de relleno en ambos márgenes es triangular(ver planos)Longitud de relleno margen izquierdo (L 8.00 mLongitud de relleno margen derecho (Lm 6.00 m

VOLUMEN DE RELLENO = Lmi*(h-.30)*A´/2 + Lmd*(h-.30)*A´/2 147.71 m3

01.02.05 ELIMINACION MATERIAL EXCEDENTEVOLUMEN A ELIMINAR= 178.25 m3

TOTAL= 178.25 m3

01.03.01 SOLADO EN ZAPATASAREA= 103.72 m3

Page 6: Metrado Puente Estribo Yanamayo

TOTAL= 103.72 m3

01.03.02 CONCRETO EN ZAPATAS f´c = 175 Kg/cm2.ZAPATA= (B . t . A') 2 = 39.63 m3ALAS= (h4 a2 + (h-t) a1 + (h-t) c/2) A'/2 22.71 m3

TOTAL 62.34 m3

01.03.03 CONCRETO EN ESTRIBOS f´c = 175 Kg/cm2.CUERPOS= (h2' a' + h2' c'/2) lt = 86.73 m3

TOTAL 86.73 m3

01.03.04 CONCRETO f´c = 140 Kg/cm2 + 30% PG ALAS.ALAS= (h4 a2 + (h-t) a1 + (h-t) c/2) A'/2 74.76 m3

TOTAL 74.76 m3

01.03.05 ACERRO fy = 4200 Kg/cm2ZAPATAS 82 fi 3/4" emplames de 1,2m 714.6 kgESTRIBO 20 fi 1" + 93 fi 3/4" empalmes 1,2m 2716.4 kg

TOTAL 6862.00 kg

01.03.06 ENCOFRADO Y DESENCOFRADO ESTRIBOSESTRIBOS = (A´ + B)*t*#Lados encofrar*#Estribos = 100.89 m2por dos unidades 100.89 m2

TOTAL 201.78 m2

01.03.07 ENCOFRADO Y DESENCOFRADO ALASESTR. = ((h4+h3)*A´+((h4+h3)^2+c^2)^(1/2)*A´+(a2+a1+b)*(h4+ 120.40 m2por dos unidades 120.40 m2

TOTAL 240.80 m2

01.03.08 CURADO DE CONCRETOAREA TOTAL ENCOFRADA 442.58 m2

TOTAL 442.58 m2

01.04.01 CONCRETO f´c = 210 Kg/cm2, LOSA, VIGAS Y VEREDAAREA= 1,74 m2LONGITUD= 10,00 m. DIAFRAGMA 2m (,50x,25) 18.25 m3

TOTAL 18.25 m3

01.04.02 ACERO fy = 4200 Kg/cm2LOSA 83 fi 3/8" + 103 fi 5/8" empalm. Ver diseño 1978.65 kgVIGAS PRINCIPALES 60 fi 1" + 23 fi 3/4" + 36 fi 3/8" 2710.17 kgVIGAS DIAFRAGMAS 7 fi 3/4"+9 fi 5/8"+ 6fi 3/ 298.98 kg

TOTAL 4688.82 kg

01.04.03 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZAAREA = (A-#VIGAS*b1)*L +L*e*2+A*e*2 = 38.60 m2

TOTAL 38.60 m2

Page 7: Metrado Puente Estribo Yanamayo

01.04.04 ENCOFRADO Y DESENCOFRADO VIGASVIGAS = (L*f*2+L*b1)*#Vigas = 34.00 m2DIAFRAGMAS = (l*t1*2 + l*b1´)*#DIAFRAGMAS = 7.50 m2

TOTAL 41.50 m2

01.04.05 ENCOFRADO Y DESENCOFRADO DE VEREDASAREA = L*2*e*2 = 8 m2

01.04.06 CURADO DE CONCRETOAREA TOTAL ENCOFRADA 88.10 m2

TOTAL 88.10 m2

01.05.01 TARRAJEO DE VEREDAS VEREDAS = 8.00 m2

TOTAL 8.00 m2

01.05.02 TARRAJEO FROTACHADO LOSAAREA LOSA 48.00 m2

TOTAL 48.00 m2

01.06.01 CONSTRUCCION DE APOYO FIJO #APOYOS FIJOS = #VIGAS = 2.00 UND

TOTAL 2.00 UND

01.07.02 CONSTRUCCION DE APOYO MOVIL #APOYOS MOVILES = #VIGAS = 2.00 UND

TOTAL 2.00 UND

01.07.03 COLOCACION DE BARANDA DE FIERRO NEGRO LONGITUD = L*#BARANDAS = 40.00 m.#BARANDAS = 2 FIERROS PARALELOS EN CADA BARANDA 14.00 m

TOTAL 54.00 m

01.07.04 JUNTA DE CONSTRUCCION DE TECKNOPORT AREA= A*h3*2 9.44 m2

TOTAL 9.44 m2

01.07.05 DRENAJE DE ESTRIBOS Y ALAS Se colocarán 3 tubos de drenaje en los estribos y en las alas se espaciarán a cada 2 m, de preferencia en 2 hileras intercaladas en la pantalla de estribos y alas.

LONGITUD DE TUB. = (3*b + L´/2*b´)*3 = 21 m.

01.07.06 LIMPIEZA GENERALY ENTREGA DE OBRALIMPIEZA DEL PUENTE Y PLACA RECORDATORIA 1.00 GLB

TOTAL 1.00 GLB

01.06.07 SEÑALIZACION INFORMATIVA

Page 8: Metrado Puente Estribo Yanamayo

1 SEÑAL CON LA INDICACION DE LA TARA MAXIMA 1.00 UNDTOTAL 1.00 UND

Page 9: Metrado Puente Estribo Yanamayo

Se tendrá en cuenta el relleno, en ambos márgenes,(adyacente a los estribos), hasta lograr el nivel de de la carretera, que coincida con el nivel del puente, menos una capa de 30 cms, la cual será rellenada ,

Page 10: Metrado Puente Estribo Yanamayo

Se colocarán 3 tubos de drenaje en los estribos y en las alas se espaciarán a cada 2 m, de preferencia

Page 11: Metrado Puente Estribo Yanamayo

METRADO DE ACERO

DESCRIPCION ELEMENT. VECES Q´ Nº LONG. DIAM. 1/4" 3/8" 1/2" 5/8" 3/4" 1"ESTRUC. INTERV. MIEMB. m. m. m. m. m. m. m.

10.9 VIGA.65 1.20(TRASL) . PRINC. 2 3 13.40 1" 80.40

10.9 VIGA 1.20(TRASL) PRINC. 2 6 12.10 1" 145.20

VIGA.65 1.20(TRASL) PRINC. 2 15 13.40 1" 402.00

10.9VIGA

0.6 . PRINC. 2 56 2.40 3/8" 268.80

0.4VIGA

0.20 . PRINC. 2 37 1.50 1/4" 111.000.42.9 DIAFR.

.40 EXTER. 2 6 3.70 5/8" 44.40

2.9 DIAFR..20 EXTER. 2 4 3.30 1/2" 26.40

2.9 DIAFR..40 INTER. 1 8 3.70 3/4" 29.60

2.9 DIAFR..20 INTER. 1 4 3.30 5/8" 13.20

Page 12: Metrado Puente Estribo Yanamayo

DESCRIPCION ELEMENT. VECES Q´ Nº LONG. DIAM. 1/4" 3/8" 1/2" 5/8" 3/4" 1"ESTRUC. INTERV. MIEMB. m. m. m. m. m. m. m.

2.9 DIAFR..20 INTER. 1 2 3.30 1/2" 6.60

VIGA 0.4 . DIAFRAG. 3 14 1.40 3/8" 58.80

0.2 1.90 1.90 LOSA

MACIZA 1 53 3.80 5/8" 201.40

4.75 LOSA .175 MACIZA 1 53 5.09 5/8" 269.77

4.75 LOSA MACIZA 1 48 4.75 5/8" 228.00

11.00 LOSA MACIZA 1 31 11.00 3/8" 341.00

11.00 LOSA MACIZA 1 27 11.00 3/8" 297.00

1.20 1.20 LOSA .175 2.25 MACIZA 1 31 5.33 3/8" 165.23

.575 ..20 .30 VEREDA 2 56 2.375 1/2" 266.00 1.30 .

1.00 COLUMNABARANDA 24 4 1.00 3/8" 96.00

ESTR. .11 .11 BARANDA 24 4 0.32 1/4" 30.72

1f5/8" a .21

1f5/8" a .21

1f5/8" a .23

1f3/8" a .16

1f3/8" a .18

1f3/8" a .16

Page 13: Metrado Puente Estribo Yanamayo

DESCRIPCION ELEMENT. VECES Q´ Nº LONG. DIAM. 1/4" 3/8" 1/2" 5/8" 3/4" 1"ESTRUC. INTERV. MIEMB. m. m. m. m. m. m. m.

0.95 APOYOFIJO 2 3 0.95 3/8" 5.70

SUBTOTAL DE ACERO (ml.) 141.72 1232.53 299.00 756.77 29.60 627.60

PESO DEL ACERO Kg/m. 0.25 0.58 1.02 1.6 2.26 4.04

SUBTOTAL DE ACERO (Kg.) 35.43 714.87 304.98 1210.83 66.90 2535.50

TOTAL ACERO (Kg) 4868.51

Page 14: Metrado Puente Estribo Yanamayo

METRADO PUENTE VICTORIA

5m 5m

A A´

5m5 m

L

A = ancho total del puente = 4.80 mL = Longitud total del puente= 11.00 mA´= ancho total de estribos = 5.90 m.L´= longitud total de alas = 20.00 m# De estribos = 2 u.

PUENTE PLANTA

Page 15: Metrado Puente Estribo Yanamayo

a2 a1 c

h3

h4

h

h2

t

B

D b D´1

a1 = 0.30 m h = 3.20 ma2 = 0.50 m h2 = 0.80 mD = 0.50 m h3 = 0.70 mb = 1.40 m h4 = 2.00 m

D´1 = 1.20 m B = 3.10 mt = 0.50 m c = 0.60 m

CORTE ESTRIBO

Page 16: Metrado Puente Estribo Yanamayo

a´ c´

h2´

h3´ t´

D´ b´ D´1 "

DIMENSIONES SECCION INICIAL (i)

a´ = 0.40 m h´ = 3.20 mc´ = 0.60 m h2´ = 2.70 m

D´ = 0.50 m h3´ = 0.80 mb´ = 1.00 m B´ = 2.50 m

D´1" = 1.00 m t´ = 0.50 m

DIMENSIONES SECCION FINAL (f)

a´ = 0.30 m h´ = 3.00 mc´ = 0.30 m h2´ = 2.50 m

D´ = 0.50 m h3´ = 0.80 mb´ = 0.10 m B´ = 1.80 m

D´1" = 0.60 m t´ = 0.50 m

CORTE ALA

Page 17: Metrado Puente Estribo Yanamayo

B1 V S' V B1

g

c1 e

t1f

b1 S b1 S1

B1 = 0.15 m g = 0.70 mV = 0.60 m c1 = 0.30 mS´= 3.60 m e = 0.20 mt1 = 0.70 m f = 0.50 mb1 = 0.50 m S = 2.00 mS1 = 0.90 m

CORTE SUPERESTRUCTURA

VIGAS DIAFRAGMAS

l = LARGO DIAFRAGMA = 2.00 mt1´ b1´= ANCHO DIAFRAG. = 0.25 m

t1´= ALTO DIAFRAGMA = 0.50 m# DE DIFRAGMAS = 3.00

´ b1´

Page 18: Metrado Puente Estribo Yanamayo

01.01.03 TRAZO Y REPLANTEO CON TOPOGRAFO

ESTRIBOS Y ALAS = A´*B*#Estribos + (B´(i)+B´(f))/2)*L´= 79.58 m2PUENTE = L*A´= 64.90 m2

TOTAL = 144.48 m2

01.02.02 EXCAVACION EN SUELO GRAVOSO BAJO AGUA

ESTRIBOS = (h2 + t)*A´*B*#Estribos = 47.55 m3ALAS = (h3´+ t´)*(B´(i) + B´(f))/2*L´ = 55.9 m3

TOTAL = 103.45 m3

01.02.03 RELLENO CON MATERIAL PROPIO

Se tendrá en cuenta el relleno, en ambos márgenes,(adyacente a los estribos), hasta lograr el nivel de de la carretera, que coincida con el nivel del puente, menos una capa de 30 cms, la cual será rellenada , con material de préstamo.

La forma de relleno en ambos márgenes es triangular(ver planos)Longitud de relleno margen izquierdo (L 5.00 mLongitud de relleno margen derecho (Lm 8.00 m

VOLUMEN DE RELLENO = Lmi*(h-.30)*A´/2 + Lmd*(h-.30)*A´/2 = 111.22 m3

01.02.04 RELLENO Y APISONADO CON MATERIAL DE PRESTAMO

VOLUMEN DE RELLENO = .30*A´*(Lmi + Lmd) = 23.01 m3

01.03.01 SOLADO PARA ZAPATAS e = 4", f´c = 100 Kg/cm2

AREA DE SOLADO ESTRIBOS = B*A´*#Estribos = 36.58 m2AREA DE SOLADO ALAS = (B´i + B´f)/2*L´ = 43.00 m2

AREA TOTAL DE SOLADO 79.58 m2

01.03.02 CONCRETO CICLOPEO f´c = 140 Kg/cm2 + 30 % P.G.

ESTRIBOS = B*A´*t*#Estribos = 18.29 m3ALAS = (B´i + B´f)/2*t´*L´ = 21.5 m3

TOTAL 39.79 m3

01.03.03 ENCOFRADO Y DESENCOFRADO DE ZAPATAS

ESTRIBOS = (A´ + B)*t*#Lados encofrar*#Estribos = 36.00 m2ALAS = L´ * t´*#Lados encofrar = 20.00 m2

TOTAL 56.00 m2

01.04.01 CONCRETO f´c = 140 Kg/cm2, ESTRIBOS Y ALAS

Page 19: Metrado Puente Estribo Yanamayo

ESTRIBOS = (h4*a2*A´+ (h4+h3)*a1*A´ + c*(h4+h3)/2*A´)*#Estribos 30.92 m3ALAS = (h2´i*a´i + h2´f*a´f)/2*L´+(h2´i*c´i + h2´f*c´f)/4*L´ = 30.15 m3

TOTAL 61.07 m3

01.04.02 CONCRETO f´c = 210 Kg/cm2, VIGAS Y DIAFRAGMAS

VIGAS = L*b1*t1*#Vigas = 7.70 m3DIAFRAGMAS = l*b1´*t1´*#Diafragmas = 0.75 m3

TOTAL 8.45 m3

01.04.03 CONCRETO f´c = 210 Kg/cm2, LOSA MACIZA

VOLUMEN LOSA = L*A*e - L*b1*e = 9.46 m3

01.04.04 CONCRETO f´c = 175 Kg/cm2, VEREDAS Y BARANDAS

# DE BARANDAS = 24 U.VEREDAS = L*V*c1*2 = 3.96 m3BARANDAS = g*B1*B1*#Barandas = 0.38 m3

TOTAL 4.34 m3

01.04.06 ENCOFRADO Y DESENCOFRADO DE ESTRIBOS Y ALAS

ESTR. = ((h4+h3)*A´+((h4+h3)^2+c^2)^(1/2)*A´+(a2+a1+b)*(h4+h3))* 76.38 m2ALAS = (h2´i+h2´f)/2*L´*#LADOS ALAS = 104.00 m2

TOTAL 180.38 m2

01.04.07 ENCOFRADO Y DESENCOFRADO DE VIGAS Y DIAFRAGMAS

VIGAS = (L*f*2+L*b1)*#Vigas = 33.00 m2DIAFRAGMAS = (l*t1*2 + l*b1´)*#DIAFRAGMAS = 7.50 m2

TOTAL 40.50 m2

01.04.09 ENCOFRADO Y DESENCOFRADO DE LOSA MACIZA

AREA = (A-#VIGAS*b1)*L +L*e*2+A*e*2 = 59.12 m2

01.04.10 ENCOFRADO Y DESENCOFRADO DE VEREDAS Y BARANDAS

VEREDAS = (L*c1*2)*#VEREDAS = 13.20 m2BARANDAS = (B1*#LADOS*g*#BARANDAS) = 10.08 m2

TOTAL 23.28 m2

01.04.12 ACERO fy = 4200 Kg/cm2

TOTAL DE ACERO (VER CUADROS DE CALCULO DE ACERO) 4868.51 Kg

01.05.01 FALSO PUENTE

Page 20: Metrado Puente Estribo Yanamayo

VOLUMEN = (L-2*a2)*A*H = 96.00 m3H = ALTURA DEL FONDO DE RIO A LA PARTE BAJA DEL PUENTE 2.00 m

01.06.01 TARRAJEO DE VEREDAS Y MUROS DE BARANDA

VEREDAS = L*(2*c1 + V)*#VEREDAS= 26.40 m2BARANDAS= (B1*#LADOS*g*#BARANDAS)= 10.08 m2

TOTAL 36.48 m2

01.06.02 TARRAJEO FROTACHADO 1:5 EN LOSA

AREA = L*S´= 39.60 m2

01.07.01 CONSTRUCCION DE APOYO FIJO

#APOYOS FIJOS = #VIGAS = 2.00 UNIDADES

01.07.02 CONSTRUCCION DE APOYO MOVIL

#APOYOS MOVILES = #VIGAS = 2.00 UNIDADES

01.07.03 COLOCACION DE BARANDA DE FIERRO NEGRO

LONGITUD = L*#BARANDAS = 44.00 m.#BARANDAS = 2 FIERROS PARALELOS EN CADA BARANDAL= 4.00

01.07.07 DRENAJE DE ESTRIBOS Y ALAS

Se colocarán 3 tubos de drenaje en los estribos y en las alas se espaciarán a cada 2 m, de preferencia en 3 hileras intercaladas en la pantalla de estribos y alas.

LONGITUD DE TUB. = (3*b + L´/2*b´)*3 = 42.6 m.

Page 21: Metrado Puente Estribo Yanamayo

Se tendrá en cuenta el relleno, en ambos márgenes,(adyacente a los estribos), hasta lograr el nivel de de la carretera, que coincida con el nivel del puente, menos una capa de 30 cms, la cual será rellenada ,

Page 22: Metrado Puente Estribo Yanamayo

Se colocarán 3 tubos de drenaje en los estribos y en las alas se espaciarán a cada 2 m, de preferencia

Page 23: Metrado Puente Estribo Yanamayo

METRADO DE ACERO PUENTE CARROZABLE VICTORIA

DESCRIPCION ELEMENT. VECES Q´ Nº LONG. DIAM. 1/4" 3/8" 1/2" 5/8" 3/4" 1"ESTRUC. INTERV. MIEMB. m. m. m. m. m. m. m.

10.9 VIGA.65 1.20(TRASL) . PRINC. 2 3 13.40 1" 80.40

10.9 VIGA 1.20(TRASL) PRINC. 2 6 12.10 1" 145.20

VIGA.65 1.20(TRASL) PRINC. 2 15 13.40 1" 402.00

10.9VIGA

0.6 . PRINC. 2 56 2.40 3/8" 268.80

0.4VIGA

0.20 . PRINC. 2 37 1.50 1/4" 111.000.42.9 DIAFR.

.40 EXTER. 2 6 3.70 5/8" 44.40

2.9 DIAFR..20 EXTER. 2 4 3.30 1/2" 26.40

2.9 DIAFR..40 INTER. 1 8 3.70 3/4" 29.60

2.9 DIAFR..20 INTER. 1 4 3.30 5/8" 13.20

Page 24: Metrado Puente Estribo Yanamayo

DESCRIPCION ELEMENT. VECES Q´ Nº LONG. DIAM. 1/4" 3/8" 1/2" 5/8" 3/4" 1"ESTRUC. INTERV. MIEMB. m. m. m. m. m. m. m.

2.9 DIAFR..20 INTER. 1 2 3.30 1/2" 6.60

VIGA 0.4 . DIAFRAG. 3 14 1.40 3/8" 58.80

0.2 1.90 1.90 LOSA

MACIZA 1 53 3.80 5/8" 201.40

4.75 LOSA .175 MACIZA 1 53 5.09 5/8" 269.77

4.75 LOSA MACIZA 1 48 4.75 5/8" 228.00

11.00 LOSA MACIZA 1 31 11.00 3/8" 341.00

11.00 LOSA MACIZA 1 27 11.00 3/8" 297.00

1.20 1.20 LOSA .175 2.25 MACIZA 1 31 5.33 3/8" 165.23

.575 ..20 .30 VEREDA 2 56 2.375 1/2" 266.00 1.30 .

1.00 COLUMNABARANDA 24 4 1.00 3/8" 96.00

ESTR. .11 .11 BARANDA 24 4 0.32 1/4" 30.72

1f5/8" a .21

1f5/8" a .21

1f5/8" a .23

1f3/8" a .16

1f3/8" a .18

1f3/8" a .16

Page 25: Metrado Puente Estribo Yanamayo

DESCRIPCION ELEMENT. VECES Q´ Nº LONG. DIAM. 1/4" 3/8" 1/2" 5/8" 3/4" 1"ESTRUC. INTERV. MIEMB. m. m. m. m. m. m. m.

0.95 APOYOFIJO 2 3 0.95 3/8" 5.70

SUBTOTAL DE ACERO (ml.) 141.72 1232.53 299.00 756.77 29.60 627.60

PESO DEL ACERO Kg/m. 0.25 0.58 1.02 1.6 2.26 4.04

SUBTOTAL DE ACERO (Kg.) 35.43 714.87 304.98 1210.83 66.90 2535.50

TOTAL ACERO (Kg) 4868.51