51
PARTIDA: 03.01.02.- ACERO PARA ZAPATAS f´y= 4200 kg/cm2 TIPO DETALLE LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 0.25 0.58 0.99 1.55 2.24 3.97 1.00 Z-01 ### 61.00 6 0.85 311.10 61.00 6 0.85 311.10 ### Z-02 ### 8.00 9 1.35 97.20 8.00 6 0.85 40.80 LONGITUD TOTAL 0.00 0.00 138.00 622.20 0.00 0.00 0.00 0.00 136.62 964.41 0.00 0.00 PESO TOTAL (kg) 1101.03 PARTIDA: 03.02.03.- ACERO PARA SOBRECIMIENTOS REFORZADOS f´y= 4200 kg/cm2 TIPO DETALLE LONG. 1/4" 3/8" 1/2" 5/8" 3/4" 1" 0.25 0.58 0.99 1.55 2.24 3.97 ACERO VERTICAL 0.15 ### ### 16.00 22 1.30 457.60 0.15 ### ### 3.10 16.00 6 3.40 326.40 ACERO LONGITUDINAL ACERO VERTICAL 0.15 ### ### 12.00 22 1.30 343.20 0.15 ### ### 3.00 12.00 6 3.30 237.60 ACERO LONGITUDINAL LONGITUD TOTAL 800.80 564.00 0.00 0.00 0.00 0.00 200.20 327.12 0.00 0.00 0.00 0.00 PESO TOTAL (kg) 527.32 ELEMEN. IGUALES N° DE PIEZAS POR ELEMEN. PESO TOTAL POR TIPO DE F° (kg) ELEMEN. IGUALES N° DE PIEZAS POR ELEMEN. PESO TOTAL POR TIPO DE F° (kg)

description

metrado coliseo

Transcript of Metrados Coliseo

Page 1: Metrados Coliseo

PARTIDA: 03.01.02.- ACERO PARA ZAPATAS f´y= 4200 kg/cm2

TIPO DETALLE LONG.

1/4" 3/8" 1/2" 5/8" 3/4" 1"

0.25 0.58 0.99 1.55 2.24 3.97

1.00

Z-01

1.00

61.00 6 0.85 311.10

61.00 6 0.85 311.10

###

Z-02

1.00

8.00 9 1.35 97.20

8.00 6 0.85 40.80

LONGITUD TOTAL 0.00 0.00 138.00 622.20 0.00 0.00

0.00 0.00 136.62 964.41 0.00 0.00

PESO TOTAL (kg) 1101.03

PARTIDA: 03.02.03.- ACERO PARA SOBRECIMIENTOS REFORZADOS f´y= 4200 kg/cm2

TIPO DETALLE LONG.

1/4" 3/8" 1/2" 5/8" 3/4" 1"

0.25 0.58 0.99 1.55 2.24 3.97

ACERO VERTICAL

0.15

0.50

0.50

16.00 22 1.30 457.60

0.15

0.15

0.15

3.1016.00 6 3.40 326.40

ACERO LONGITUDINAL

ACERO VERTICAL

0.15

0.50

0.50

12.00 22 1.30 343.20

0.15

0.15

0.15

3.0012.00 6 3.30 237.60

ACERO LONGITUDINAL

LONGITUD TOTAL 800.80 564.00 0.00 0.00 0.00 0.00

200.20 327.12 0.00 0.00 0.00 0.00

PESO TOTAL (kg) 527.32

N° ELEMEN. IGUALES

N° DE PIEZAS

POR ELEMEN.

PESO TOTAL POR TIPO DE F° (kg)

N° ELEMEN. IGUALES

N° DE PIEZAS

POR ELEMEN.

PESO TOTAL POR TIPO DE F° (kg)

Page 2: Metrados Coliseo

PARTIDA: 03.03.03.- ACERO PARA COLUMNAS f´y= 4200 kg/cm2

TIPO DETALLE LONG.

1/4" 3/8" 1/2" 5/8" 3/4" 1"

0.25 0.58 0.99 1.55 2.24 3.97

5.20

4 Ø

1"

5.20

4 Ø

5/8"

66.00 4.00 5.45 1438.80

C-01 66.00 4.00 5.45 1438.800.25 0.25

5.20

2 Ø

3/4

" 66.00 2.00 5.45 719.40

0.25

0.40

0.25

66.00 32.00 1.50 3168.00

5.30

8 Ø

5/8

"

4.00 8.00 5.55 177.60

C-020.25

0.25

0.25

0.25

0.45

0.25

4.00 33.00 3.20 422.400.45

4.20

6 Ø

1/2

"

15.00 6.00 4.45 400.50

C-030.25

0.30

0.15

15.00 28.00 1.10 462.00

5.10

4 Ø

1/2

"

51.00 4.00 5.35 1091.40

C/A0.25

0.20

0.15

51.00 31.00 0.90 1422.90

LONGITUD TOTAL 0.00 5475.30 1491.90 1616.40 719.40 1438.80

0.00 3175.67 1476.98 2505.42 1611.46 5712.04

PESO TOTAL (kg) 14481.57

PARTIDA: 03.04.03.- ACERO PARA VIGAS f´y= 4200 kg/cm2

TIPO DETALLE LONG.

1/4" 3/8" 1/2" 5/8" 3/4" 1"

0.25 0.58 0.99 1.55 2.24 3.97

ACERO NEGATIVO

0.25

5.06

0.25 26.00 2.00 5.56 289.122 Ø5/8"

ACERO CENTRAL

0.25 5.06

0.25

26.002.00 5.56

289.122 Ø1/2"

ACERO POSITIVO

N° ELEMEN. IGUALES

N° DE PIEZAS

POR ELEMEN.

PESO TOTAL POR TIPO DE F° (kg)

N° ELEMEN. IGUALES

N° DE PIEZAS

POR ELEME.

Page 3: Metrados Coliseo

0.25 5.06

0.25

26.00 2.00 5.56 289.122 Ø5/8"

0.25

0.50

V-1 (25x50) 24.00 22.00 1.80 950.40

ESTRIBO Ø 3/8"

ACERO NEGATIVO

0.25

6.66

0.25 8.00 2.00 7.16 114.562 Ø 1/2"

ACERO POSITIVO

0.25 6.66

0.25

8.00 2.00 7.16 114.562 Ø 1/2"

V-2 (25x30)0.25

0.30

8.00 35.00 1.40 392.00

ESTRIBO Ø 1/4"

LONGITUD TOTAL 392.00 950.40 518.24 578.24 0.00 0.00

98.00 551.23 513.06 896.27 0.00 0.00

PESO TOTAL (kg) 2058.56

PESO TOTAL POR TIPO DE F° (kg)

Page 4: Metrados Coliseo

PARTIDA: 03.05.03.- ACERO PARA LOSAS MACIZAS f´y= 4200 kg/cm2

TIPO DETALLE LONG.

1/4" 3/8" 1/2" 5/8" 3/4" 1"

0.25 0.58 0.99 1.55 2.24 3.97

ESTRADO

ACERO NEGATIVO

2.00 39.00 8.10 631.800.15

7.80

0.15

2 Ø 1/2"

0.15 4.20

0.15

2.00 21.00 4.50 189.002 Ø 1/2"

LONGITUD TOTAL 0.00 0.00 820.80 0.00 0.00 0.00

0.00 0.00 812.59 0.00 0.00 0.00

PESO TOTAL (kg) 812.59

PARTIDA: 03.06.03.- ACERO PARA GRADERIA f´y= 4200 kg/cm2

TIPO DETALLE LONG.

1/4" 3/8" 1/2" 5/8" 3/4" 1"

0.25 0.58 0.99 1.55 2.24 3.97

LATERALES 0.10

0.50 14.00 138.00 0.70 1352.40

0.10

0.10

0.40

0.10

14.00 138.00 0.60 1159.206.00

1.00

69.00 21.00 1.00 1449.001 Ø 3/8"

FRONTALES 0.10

0.50 20.00 75.00 0.70 1050.00

0.10

0.10

0.40

0.10

20.00 75.00 0.60 900.006.00

1.00

38.00 30.00 1.00 1140.001 Ø 3/8"

LONGITUD TOTAL 0.00 2589.00 4461.60 0.00 0.00 0.00

0.00 1501.62 4416.98 0.00 0.00 0.00

PESO TOTAL (kg) 5918.60

N° ELEMEN. IGUALES

N° DE PIEZAS

POR ELEMEN.

PESO TOTAL POR TIPO DE F° (kg)

N° ELEMEN. IGUALES

N° DE PIEZAS

POR ELEMEN.

PESO TOTAL POR TIPO DE F° (kg)

Page 5: Metrados Coliseo

PLANILLA DE METRADOS ESTRUCTURA

ESTRUCTURAS

01.00.00 OBRAS PROVISIONALES

01.01.00 TRANSPORTE DE MATERIAL Y EQUIPO A OBRA

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE (GLB)

( A ) ( B ) (C) = (A) x (B)

MURO FRONTALTRANSPORTE DE MATERIAL 1.00 1.00 1.00 1.00

TOTAL: GLB 1.00

02.00.00 TRABAJOS PRELIMINARES

PARTIDA: 02.01.00.- DESMONTAJE DE PUERTAS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) AREA. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

AREA 480.50 480.50 480.50

TOTAL: M3 480.50

PARTIDA: 02.02.00.- DESMONTAJE DE COBERTURA

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

MODULO 01 SUM 1.00 AREA CAD 346.49 1.00 346.49

MODULO 02 SERVICIOS 1.00 AREA CAD 116.46 1.00 116.46

MODULO 03 AULAS 1.00 AREA CAD 39.48 1.00 39.48

MODULO 04 AULAS 1.00 AREA CAD 324.48 1.00 324.48

MODULO 05 SS.HH 1.00 AREA CAD 5.94 1.00 5.94

TOTAL: M2 832.85

PARTIDA: 02.03.00.- DEMOLICION DE PISOS Y VEREDAS

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

MODULO 01 SUM 1.00 AREA CAD 0.00 1.00 0.00

MODULO 02 SERVICIOS 1.00 AREA CAD 0.00 1.00 0.00

MODULO 03 AULAS 1.00 AREA CAD 39.48 1.00 39.48

MODULO 04 AULAS 1.00 AREA CAD 324.48 1.00 324.48

MODULO 05 SS.HH 1.00 AREA CAD 0.00 1.00 0.00

MODULO 06 VEREDAS 2.00 AREA CAD 101.66 1.00 101.66

TOTAL: M2 465.62

PARTIDA: 02.04.00.- DEMOLICION DE MUROS DE ADOBE

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Cad SE REPITE ( M2)

( A ) ( B ) ( c ) (C) = (A) x (B)x(C)

"INSTALACION DEL POLIDEPORTIVO EN LA I.E. Nº 80460 GRAN PAJATEN EN LA LOCALIDAD DE PIAS, DITRITO DE PIAS, PATAZ, LA LIBERTAD"

Page 6: Metrados Coliseo

MODULO 01 SUM 1.00 AREA CAD 4.50 71.35 1.00 321.08

MODULO 02 SERVICIOS 1.00 AREA CAD 2.50 48.14 1.00 120.35

MODULO 03 AULAS 1.00 AREA CAD 6.50 22.06 1.00 143.39

MODULO 04 AULAS 1.00 AREA CAD 6.50 86.00 1.00 559.00

MODULO 05 SS.HH 1.00 AREA CAD 2.50 6.58 1.00 16.45

MODULO 06 CERCO PERIMETRICO 2.00 AREA CAD 2.50 17.40 1.00 43.50

TOTAL: M2 1,203.76

PARTIDA: 02.05.00.- ELIMINACION DE MATERIAL DE DEMOLICION

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Cad SE REPITE ( M2)

( B ) ( A ) (C ) (C) = (A) x (B)x(C)

MODULO 01 SUM 1.00 0.40 4.50 71.35 1.00 128.43

MODULO 02 SERVICIOS 1.00 0.40 2.50 48.14 1.00 48.14

MODULO 03 AULAS 1.00 0.40 6.50 22.06 1.00 57.36

MODULO 04 AULAS 1.00 0.40 6.50 86.00 1.00 223.60

MODULO 05 SS.HH 1.00 0.40 2.50 6.58 1.00 6.58

MODULO 06 CERCO PERIMETRICO 2.00 0.40 2.50 17.40 1.00 17.40

TOTAL: M2 481.51

PARTIDA: 02.06.00.- LIMPIEZA DE TERRENO MANUAL UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) AREA. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

AREA 1,406.40 1,406.40 1,406.40

TOTAL: M3 1,406.40

PARTIDA: 02.07.00.- TRAZO, NIVELACION Y REPLANTEO UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) AREA. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

AREA 1,406.40 1,406.40 1,406.40

TOTAL: M3 1,406.40

03.00 .00 MOVIMIENTO DE TIERRAS

PARTIDA: 03.01.00.- EXCAVACION PARA ZAPATAS EN ROCA UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

ZAPATA Z-01 1.00 1.00 1.30 1.30 94.00 122.20

ZAPATA Z-02 1.00 1.50 1.30 1.95 5.00 9.75

TOTAL: M3 131.95

Page 7: Metrados Coliseo

PARTIDA: 03.02.00.- EXCAVACION PARA CIMIENTOS CORRIDOS EN ROCA UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

EJE 1-1

CIMIENTO 21.60 0.50 1.00 10.80 1.00 10.80

EJE 2-2

CIMIENTO 21.10 0.50 1.00 10.55 1.00 10.55

EJE A-A

CIMIENTO 13.66 0.50 1.00 6.83 1.00 6.83

EJE C-C

CIMIENTO 35.42 0.50 1.00 17.71 1.00 17.71

TOTAL: M3 45.89

PARTIDA: 03.03.00.- CORTE DE TERRENO NATURAL UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) AREA. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

AREA ……….. ………. 0.00 ………. ……….

TOTAL: M3 2,229.42

PARTIDA: 03.04.00.- CORTE DE TERRENO EN ROCA UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) AREA. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

AREA ……….. ………. 0.00 ………. ……….

TOTAL: M3 743.14

PARTIDA: 03.05.00.- RELLENO COMPACTADO CON MATERIAL PROPIO UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

ZAPATAS

ZAPATA Z-01 1.00 1.00 0.65 0.65 94.00 61.10

ZAPATA Z-02 1.00 1.50 0.65 0.98 5.00 4.88

TOTAL: M3 65.98

PARTIDA: 03.06.00.- RELLENO COMPACTADO CON MATERIAL DE PRESTAMO UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) AREA. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

MATERIAL SELECCIONADO DE PRESTAMO 1,406.40 0.50 703.20 0.30 210.96

TOTAL: M3 210.96

Page 8: Metrados Coliseo

PARTIDA: 03.07.00.- ACARREO DE MATERIAL EXCEDENTE DE LAS EXCAVACIONES Y DEMOLICIONES UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

ZAPATAS

EXCAVACION 131.95 131.95 1.00 131.95

CIMIENTOS

EXCAVACION 45.89 45.89 1.00 45.89

CORTE DE TERRENO NATURAL

EXCAVACION 2229.42 2229.42 1.00 2229.42

CORTE DE TERRENO EN ROCA

EXCAVACION 743.14 743.14 1.00 743.14

TOTAL: M3 3150.40

Esponj. (15%) 4095.52

PARTIDA: 03.08.00.- ELIMINACION DE MATERIAL EXCEDENTE UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

ZAPATAS

EXCAVACION 131.95 131.95 1.00 131.95

CIMIENTOS

EXCAVACION 45.89 45.89 1.00 45.89

CORTE DE TERRENO NATURAL

EXCAVACION 2229.42 2229.42 1.00 2229.42

CORTE DE TERRENO EN ROCA

EXCAVACION 743.14 743.14 1.00 743.14

TOTAL: M3 3150.40

Esponj. (15%) 4095.52

04.00.00 OBRAS DE CONCRETO SIMPLE

PARTIDA: 04.01.00.- SOLADO PARA ZAPATAS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

ZAPATAS

ZAPATA Z-01 1.00 1.00 1.00 94.00 94.00

ZAPATA Z-02 1.00 1.50 1.50 5.00 7.50

TOTAL: M2 101.50

Page 9: Metrados Coliseo

PARTIDA: 04.02.00.- CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO HORMIGON 30% PIEDRA GRANDE UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

EJE 1-1

CIMIENTO 24.75 0.50 0.70 8.66 1.00 8.66

EJE 2-2

CIMIENTO 23.31 0.50 0.70 8.16 1.00 8.16

EJE A-A

CIMIENTO 11.92 0.50 0.70 4.17 1.00 4.17

EJE B-B

CIMIENTO 5.90 0.50 0.70 2.07 1.00 2.07

EJE C-C

CIMIENTO 35.42 0.50 0.70 12.40 1.00 12.40

TOTAL: M3 35.46

PARTIDA: 04.03.00.- FALSO PISO CONCRETO 1:8, e=0.10cm UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

FALSO PISO 1,406.40 1.00 1,406.40

LOSA DEPORTIVA -18.00 34.00 -612.00 1.00 -612.00

TOTAL: M2 794.40

05.00.00 OBRAS DE CONCRETO ARMADO

06.00.00 ZAPATAS

PARTIDA: 06.01.00- CONCRETO PARA ZAPATAS f´c=210kg/cm2 UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

EJE 1-1

ZAPATA Z-01 1.00 1.00 0.55 0.55 94.00 51.70

ZAPATA Z-02 1.00 1.50 0.55 0.83 5.00 4.13

TOTAL: M3 55.83

PARTIDA: 06.02.00- ACERO ESTRUCTURAL TRABAJADO PARA ZAPATAS

07.00.00 SOBRECIMIENTO ARMADO

PARTIDA: 07.01.00.- CONCRETO EN SOBRECIMIENTO ARMADO F´C=175HG/CM2 UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

EJE 1-1

SOBRECIMIENTO 24.75 0.15 0.50 1.86 1.00 1.86

EJE 2-2

SOBRECIMIENTO 23.31 0.15 0.50 1.75 1.00 1.75

EJE A-A

SOBRECIMIENTO 11.92 0.15 0.50 0.89 1.00 0.89

EJE B-B

SOBRECIMIENTO 5.90 0.15 0.50 0.44 1.00 0.44

Page 10: Metrados Coliseo

EJE C-C

SOBRECIMIENTO 35.42 0.15 0.50 2.66 1.00 2.66

TOTAL: M3 7.60

PARTIDA: 07.02.00.- ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

EJE 1-1

SOBRECIMIENTO 24.75 0.50 12.38 2.00 24.75

EJE 2-2

SOBRECIMIENTO 23.31 0.50 11.66 2.00 23.31

EJE A-A

SOBRECIMIENTO 11.92 0.50 5.96 2.00 11.92

EJE B-B

SOBRECIMIENTO 5.90 0.50 2.95 2.00 5.90

EJE C-C

SOBRECIMIENTO 39.99 0.50 20.00 2.00 39.99

TOTAL: M2 105.87

PARTIDA: 07.03.00.- ACERO EN SOBRECIMIENTO ARMADO

Page 11: Metrados Coliseo

08.00.00 COLUMNAS

PARTIDA: 08.01.00.- CONCRETO f´c=210kg/cm2 PARA COLUMNAS UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

COLUMNAS

C-1 0.45 0.50 5.20 1.17 5.00 5.85

C-2 0.40 0.50 5.20 1.04 4.00 4.16

C-3 EJE A-A 0.40 0.25 5.60 0.56 6.00 3.36

C-3 EJE C-C 0.40 0.25 1.30 0.13 14.00 1.82

C-3 EJE 1-1 0.40 0.25 6.55 0.66 8.00 5.24

C-3 EJE 2-2 0.40 0.25 2.80 0.28 8.00 2.24

C-4 0.40 0.25 5.60 0.56 1.00 0.56

C-5 AREA 0.21 5.30 1.13 1.00 1.13

C-6 AREA 0.19 7.20 1.35 2.00 2.70

C-7 (GRADERIA FRONTAL) 0.40 0.25 3.20 0.32 16.00 5.12

C-7 (GRADERIA FRONTAL) 0.40 0.25 1.70 0.17 16.00 2.72

C-7 (GRADERIA LATERAL) 0.40 0.25 4.70 0.47 24.00 11.28

C-7 (GRADERIA LATERAL) 0.40 0.25 1.70 0.17 24.00 4.08

C/A EJE A-A 0.20 0.15 2.60 0.08 13.00 1.01

C/A EJE C-C 0.20 0.15 4.60 0.14 26.00 3.59

C/A EJE 1-1 0.20 0.15 5.60 0.17 17.00 2.86

C/A EJE 2-2 0.20 0.15 5.60 0.17 16.00 2.69

TOTAL: M3 60.40

PARTIDA: 08.02.00.- ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNAS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

COLUMNAS

C-1 1.90 5.20 9.88 5.00 49.40

C-2 1.80 5.20 9.36 4.00 37.44

C-3 EJE A-A 1.30 5.60 7.28 6.00 43.68

C-3 EJE C-C 1.30 1.30 1.69 14.00 23.66

C-3 EJE 1-1 1.30 6.55 8.52 8.00 68.12

C-3 EJE 2-2 1.30 2.80 3.64 8.00 29.12

C-4 1.30 5.60 7.28 1.00 7.28

C-5 2.00 5.30 10.60 1.00 10.60

C-6 2.00 7.20 14.40 2.00 28.80

C-7 (GRADERIA FRONTAL) 1.30 3.20 4.16 16.00 66.56

C-7 (GRADERIA FRONTAL) 1.30 1.70 2.21 16.00 35.36

C-7 (GRADERIA LATERAL) 1.30 4.70 6.11 24.00 146.64

C-7 (GRADERIA LATERAL) 1.30 1.70 2.21 24.00 53.04

C/A EJE A-A 0.70 2.60 1.82 13.00 23.66

C/A EJE C-C 0.70 4.60 3.22 26.00 83.72

C/A EJE 1-1 0.70 5.60 3.92 17.00 66.64

C/A EJE 2-2 0.70 5.60 3.92 16.00 62.72

TOTAL: M2 836.44

PARTIDA: 08.03.00.- ACERO ESTRUCTURAL TRABAJADO PARA COLUMNAS

Page 12: Metrados Coliseo

09.00.00 VIGAS

PARTIDA: 09.01.00.- CONCRETO f´c=210kg/cm2 PARA VIGAS Y DINTELES UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

VIGAS

V-1 (15x25) EJE A-A Y C-C 49.45 0.25 0.50 6.18 5.00 30.91

V-1 (15x25) EJE 1-1 Y 2-2 29.00 0.25 0.50 3.63 4.00 14.50

V-1 (15x25) GRADERIA LATERAL 34.45 0.25 0.50 4.31 2.00 8.61

V-1 (15x25) GRADERIA FRONTAL 18.90 0.25 0.50 2.36 2.00 4.73

V-2(25x35) GRADERIA LATERAL 34.45 0.25 0.30 2.58 2.00 5.17

V-2(25x35) GRADERIA FRONTAL 18.90 0.25 0.30 1.42 2.00 2.83

TOTAL: M3 66.75

PARTIDA: 09.02.00.- ENCOFRADO Y DESENCOFRADO NORMAL EN VIGAS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

V-1 (15x25) EJE A-A Y C-C 49.45 0.50 24.73 10.00 247.25

V-1 (15x25) EJE 1-1 Y 2-2 29.00 0.50 14.50 8.00 116.00

V-1 (15x25) GRADERIA LATERAL 34.45 0.50 17.23 4.00 68.90

V-1 (15x25) GRADERIA FRONTAL 18.90 0.50 9.45 4.00 37.80

V-2(25x35) GRADERIA LATERAL 34.45 0.30 10.34 4.00 41.34

V-2(25x35) GRADERIA FRONTAL 18.90 0.30 5.67 4.00 22.68

TOTAL: M2 533.97

PARTIDA: 09.03.00.- ACERO ESTRUCTURAL TRABAJADO EN VIGAS

10.00.00 LOSAS MACIZAS

PARTIDA: 10.01.00.- CONCRETO EN LOSAS MACIZAS f´c=210kg/cm2 UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

LOSA ESTRADO

7.80 4.20 0.15 4.91 1.00 4.91

TOTAL: M3 4.91

PARTIDA: 10.02.00.- ENCOFRADO Y DESENCOFRADO NORMAL EN LOSAS MACIZAS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

LOSA ESTRADO

7.80 4.20 32.76 1.00 32.76

TOTAL: M2 32.76

PARTIDA: 10.03.00.- ACERO ESTRUCTURAL TRABAJADO PARA LOSAS MACIZAS

11.00.00 GRADERIAS

PARTIDA: 11.01.00.- CONCRETO EN GRADERIAS f´c=210kg/cm2 UNIDAD : (M3)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) AREA. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M3)

( A ) ( B ) (C) = (A) x (B)

GRADERIAS

GRADERIA FRONTAL 18.90 1.71 32.32 2.00 64.64

Page 13: Metrados Coliseo

GRADERIA LATERAL 34.45 1.23 42.37 2.00 84.75

TOTAL: M3 149.39

PARTIDA: 11.02.00.- ENCOFRADO Y DESENCOFRADO NORMAL EN GRADERIAS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

GRADERIA FRONTAL 18.90 9.90 187.11 2.00 374.22

GRADERIA LATERAL 34.45 7.70 265.27 2.00 530.53

GRADERIA FRONTAL 18.90 5.00 94.50 2.00 189.00

GRADERIA LATERAL 34.45 3.50 120.58 2.00 241.15

TOTAL: M2 1334.90

PARTIDA: 11.03.00.- ACERO EN GRADERIAS

Page 14: Metrados Coliseo

PLANILLA DE METRADOS ARQUITECTURA

ARQUITECTURA

01.00 MUROS Y TABIQUES DE ALBAÑILERIA

PARTIDA: 01.01.00.- MURO DE LADRILLO K-K 18 HUECOS A PAREJO DE SOGA UNIDAD : ( M2)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( 2 ) (3) = (1) x (2)

MURO

LADRILLO KK 18 HUECOS MAQUINADO

EJE 1-1

MURO LADRILLO KK 18 HUECOS 179.30 179.30 1.00 179.30

EJE 2-2

MURO LADRILLO KK 18 HUECOS 179.30 179.30 1.00 179.30

EJE A-A

MURO LADRILLO KK 18 HUECOS 42.80 2.60 111.28 1.00 111.28

EJE C-C

MURO LADRILLO KK 18 HUECOS 39.99 4.10 163.96 1.00 163.96

SSHH HOMBRES 7.63 2.50 19.08 1.00 19.08

CAMERINOS 21.23 2.50 53.08 4.00 212.30

SSHH DAMAS 6.43 2.50 16.08 1.00 16.08

SSHH HOMBRES 7.57 2.50 18.93 1.00 18.93

T O T A L : M2 900.21

02.00 REVOQUES ENLUCIDOS Y MOLDURAS

PARTIDA: 02.01.00.- TARRAJEO FROTACHADO DE INTERIORES E= 15 CM C7 MORTERO 1:5 UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

TARRAJEOS

LADRILLO KK 18 HUECOS MAQUINADO

EJE 1-1

MURO LADRILLO KK 18 HUECOS 179.30 179.30 1.00 179.30

EJE 2-2

MURO LADRILLO KK 18 HUECOS 179.30 179.30 1.00 179.30

EJE A-A

MURO LADRILLO KK 18 HUECOS 42.80 2.60 111.28 1.00 111.28

EJE C-C

MURO LADRILLO KK 18 HUECOS 39.99 4.10 163.96 1.00 163.96

SSHH HOMBRES 7.63 2.50 19.08 1.00 19.08

CAMERINOS 21.23 2.50 53.08 4.00 212.30

SSHH DAMAS 6.43 2.50 16.08 1.00 16.08

SSHH HOMBRES 7.57 2.50 18.93 1.00 18.93

TOTAL: M2 900.21

"INSTALACION DEL POLIDEPORTIVO EN LA I.E. Nº 80460 GRAN PAJATEN EN LA LOCALIDAD DE PIAS, DITRITO DE PIAS, PATAZ, LA LIBERTAD"

Page 15: Metrados Coliseo

PARTIDA: 02.02.00.- TARRAJEO FROTACHADO DE EXTERIORES, E= 15 CM C/MORTERO 1:5 UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

TARRAJEOS

LADRILLO KK 18 HUECOS MAQUINADO

EJE 1-1

MURO LADRILLO KK 18 HUECOS 179.30 179.30 1.00 179.30

EJE 2-2

MURO LADRILLO KK 18 HUECOS 179.30 179.30 1.00 179.30

EJE A-A

MURO LADRILLO KK 18 HUECOS 42.80 2.60 111.28 1.00 111.28

EJE C-C

MURO LADRILLO KK 18 HUECOS 39.99 4.10 163.96 1.00 163.96

SSHH HOMBRES 7.63 2.50 19.08 1.00 19.08

CAMERINOS 21.23 2.50 53.08 4.00 212.30

SSHH DAMAS 6.43 2.50 16.08 1.00 16.08

SSHH HOMBRES 7.57 2.50 18.93 1.00 18.93

TOTAL: M2 900.21

PARTIDA: 02.03.00.- TARRAJEO FROTACHADO EN COLUMNAS, E= 15 CM C/MORTERO 1:5 UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2 )

( A ) ( B ) (C) = (A) x (B)

COLUMNAS

C-1 1.90 5.20 9.88 5.00 49.40

C-2 1.80 5.20 9.36 4.00 37.44

C-3 EJE A-A 0.80 5.60 4.48 6.00 26.88

C-3 EJE C-C 0.80 1.30 1.04 14.00 14.56

C-3 EJE 1-1 0.80 6.55 5.24 8.00 41.92

C-3 EJE 2-2 0.80 2.80 2.24 8.00 17.92

C-4 0.80 5.60 4.48 1.00 4.48

C-5 1.50 5.30 7.95 1.00 7.95

C-6 1.50 7.20 10.80 2.00 21.60

C-7 (GRADERIA FRONTAL) 0.80 3.20 2.56 16.00 40.96

C-7 (GRADERIA FRONTAL) 0.80 1.70 1.36 16.00 21.76

C-7 (GRADERIA LATERAL) 0.80 4.70 3.76 24.00 90.24

C-7 (GRADERIA LATERAL) 0.80 1.70 1.36 24.00 32.64

C/A EJE A-A 0.40 2.60 1.04 13.00 13.52

C/A EJE C-C 0.40 4.60 1.84 26.00 47.84

C/A EJE 1-1 0.40 5.60 2.24 17.00 38.08

C/A EJE 2-2 0.40 5.60 2.24 16.00 35.84

TOTAL: M2 543.03

PARTIDA: 02.04.00.- TARRAJEO FROTACHADO EN VIGAS, E= 15 CM C/MORTERO 1:5 UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( m2 )

( A ) ( B ) (C) = (A) x (B)

V-1 (15x25) EJE A-A Y C-C 49.45 0.50 24.73 10.00 247.25

V-1 (15x25) EJE 1-1 Y 2-2 29.00 0.50 14.50 8.00 116.00

V-1 (15x25) GRADERIA LATERAL 34.45 0.50 17.23 4.00 68.90

V-1 (15x25) GRADERIA FRONTAL 18.90 0.50 9.45 4.00 37.80

V-2(25x35) GRADERIA LATERAL 34.45 0.30 10.34 4.00 41.34

V-2(25x35) GRADERIA FRONTAL 18.90 0.30 5.67 4.00 22.68

Page 16: Metrados Coliseo

TOTAL: M2 533.97

Page 17: Metrados Coliseo

PARTIDA: 02.05.00.- TARRAJEO DE CIELO RASO CON MEZCLA CEMENTO - ARENA UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( m2 )

( A ) ( B ) (C) = (A) x (B)

LOSA ESTRADO

7.80 4.20 32.76 1.00 32.76

TOTAL: M2 32.76

PARTIDA: 02.06.00.- REVESTIMIENTO DE GRADERIAS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( m2 )

( A ) ( B ) (C) = (A) x (B)

GRADERIA FRONTAL 18.90 9.90 187.11 2.00 374.22

GRADERIA LATERAL 34.45 7.70 265.27 2.00 530.53

GRADERIA FRONTAL 18.90 5.00 94.50 2.00 189.00

GRADERIA LATERAL 34.45 3.50 120.58 2.00 241.15

TOTAL: M2 1334.90

03.00 PISOS Y PAVIMENTOS

PARTIDA: 03.01.00.- CONTRAPISO DE 48 MM. UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

SS HH VARONES 16.84 1.00 16.84

CAMERINOS VARONES Y DAMAS 126.60 1.00 126.60

SS HH MUJERES 14.92 1.00 14.92

SS HH VARONES 21.32 1.00 21.32

TOTAL: M2 179.68

PARTIDA: 03.02.00.- PISO DE CEMENTO PULIDO e=2" UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

PASADIZO INTERNO SSHH 237.52 1.00 237.52

PASADIZO EXTERNO GRADERIAS FRONTALES

PASADIZO EXTERNO GRADERIAS LATERALES

TOTAL: M2 237.52

PARTIDA: 03.03.00.- PISO DE CERAMICO 0.30x0.30 ALTO TRANSITO UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

SS HH VARONES 16.84 1.00 16.84

CAMERINOS VARONES Y DAMAS 126.60 1.00 126.60

SS HH MUJERES 14.92 1.00 14.92

SS HH VARONES 21.32 1.00 21.32

TOTAL: M2 179.68

Page 18: Metrados Coliseo

04.00. PISO PARQUETON SHIHUAHUACU - LOSA DEPORTIVA

PARTIDA: 04.01.00.- PARQUETON SHUHUAHUACU 10 CM X 60 CM X 15 MM. UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

SS HH VARONES 16.86 1.80 30.35 1.00 30.35

CAMERINOS VARONES Y DAMAS 96.68 1.80 174.02 1.00 174.02

SS HH MUJERES 15.85 1.80 28.53 1.00 28.53

SS HH VARONES 19.00 1.80 34.20 1.00 34.20

TOTAL: M2 267.10

05.00.ZOCALOS

PARTIDA: 05.01.00.- ZACALO DE CERAMICA EN BAÑO DE 20 X 30

06.00. CARPINTERIA DE MADERA

07.00. PUERTAS DE MADERA

PARTIDA: 07.01.00.- PUERTAS DE MADERA MACIZA (2.80x3.00) UNIDAD : (UND)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE (UND)

( A ) ( B ) (C) = (A) x (B)

PUERTA PRINCIPAL

(2.80x3.00) 2.00 2.00 1.00 2.00

TOTAL: UND 2.00

PARTIDA: 07.02.00.- PUERTAS CONTRAPLACADAS (0.90x2.10) UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE (UND)

( A ) ( B ) (C) = (A) x (B)

SSHHH

SS HH DAMAS 1.00 1.00 1.00

SS HH VARONES 1.00 2.00 2.00

CAMERINOS

CAMERINOS DAMAS 1.00 2.00 2.00

CAMERINOS VARONES 1.00 2.00 2.00

TOTAL: UND 7.00

PARTIDA: 07.03.00.- PUERTAS CONTRAPLACADAS (0.70x1.80) UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

SSHHH

SS HH DAMAS 4.00 1.00 4.00

SS HH VARONES 5.00 1.00 5.00

CAMERINOS

SS HH DAMAS 2.00 2.00 4.00

SS HH VARONES 2.00 2.00 4.00

TOTAL: M2 17.00

08.00. CARPINTERIA METALICA

PARTIDA: 08.01.00.- PUERTA METALICA DE 3.80X3.00 UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( ML)

( A ) ( B ) (C) = (A) x (B)

PUERTA METALICA

Page 19: Metrados Coliseo

87.18 87.18 1.00 87.18

TOTAL: ML 87.18

PARTIDA: 08.02.00.- PUERTA METALICA DE 3.50X3.00 UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( UND)

( A ) ( B ) (C) = (A) x (B)

PUERTA METALICA

2.00 2.00 1.00 2.00

TOTAL: UND 2.00

PARTIDA: 08.03.00.- PUERTA METALICA DE 4.00X3.00

PARTIDA: 08.04.00.- BARANDAS DE TUBO NEGRO PASAMANO D=3" TRANSVERSAL Y PARANTES D=1 1/2 EN GRADERIAS

PARTIDA: 08.05.00.- ARCOS DEPORTIVOS

PARTIDA: 08.06.00.- SOPORTES Y ACCESORIOS PARA MALLA DE VOLEY UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( UND)

( A ) ( B ) (C) = (A) x (B)

PARANTE METALICO Y NET DE VOLEY

1.00 1.00 1.00 1.00

TOTAL: UND 1.00

PARTIDA: 08.07.00.- VENTANA METALICA h= 0.40mt.

09.00. CERRAJERIA

PARTIDA: 09.01.00.- BISAGRA CAPUCHINA DE 3 1/2" X 3 1/2"ALUMINIZADAS UNIDAD : (UND)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( B ) (C) = (A) x (B)

SSHH

PUERTA SS HH DAMAS 1.00 4.00 4.00

PUERTAS DE INODOROS 4.00 2.00 8.00

PUERTA SS HH VARONES 2.00 4.00 8.00

PUERTAS DE INODOROS 5.00 2.00 10.00

CAMERINOS

CAMERINOS DAMAS 4.00 4.00 16.00

CAMERINOS VARONES 4.00 4.00 16.00

PUERTA PRINCIPAL

PUERTA PRINCIPAL 2.00 8.00 16.00

TOTAL: Und 78.00

Page 20: Metrados Coliseo

PARTIDA: 09.02.00.- CERRADURA PARA PUERTA PRINCIPAL PESADA UNIDAD : (UND)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( B ) (C) = (A) x (B)

PUERTA PRINCIPAL

PUERTA PRINCIPAL 2.00 1.00 2.00

PUERTA PRINCIPAL SSHH

PUERTA SSHH 3.00 1.00 3.00

PUERTA PRINCIPAL CAMERINOS

PUERTA CAMERINOS 2.00 2.00 4.00

TOTAL: Und 9.00

PARTIDA: 09.03.00.- CERROJO ALUMINIZADO 3" UNIDAD : (UND)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( B ) (C) = (A) x (B)

CERROJOS ALUMINIZADOS

PUERTA SSHHH INODOROS 17.00 1.00 17.00

TOTAL: Und 17.00

10.00. PINTURA

PARTIDA: 10.01.00.- PINTURA LATEX EN MUROS INTERIORES 2 MANOS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

SSHH HOMBRES 7.63 2.50 19.08 1.00 19.08

CAMERINOS 21.23 2.50 53.08 4.00 212.30

SSHH DAMAS 6.43 2.50 16.08 1.00 16.08

SSHH HOMBRES 7.57 2.50 18.93 1.00 18.93

TOTAL: M2 266.38

PARTIDA: 10.02.00.- PINTURA LATEX EN MUROS EXTERIORES 2 MANOS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

EJE 1-1

MURO LADRILLO KK 18 HUECOS 179.30 179.30 1.00 179.30

EJE 2-2

MURO LADRILLO KK 18 HUECOS 179.30 179.30 1.00 179.30

EJE A-A

MURO LADRILLO KK 18 HUECOS 42.80 2.60 111.28 1.00 111.28

EJE C-C

MURO LADRILLO KK 18 HUECOS 39.99 4.10 163.96 1.00 163.96

SSHH HOMBRES 7.63 2.50 19.08 1.00 19.08

CAMERINOS 21.23 2.50 53.08 4.00 212.30

SSHH DAMAS 6.43 2.50 16.08 1.00 16.08

SSHH HOMBRES 7.57 2.50 18.93 1.00 18.93

TOTAL: M2 900.21

Page 21: Metrados Coliseo

PARTIDA: 10.03.00.- PINTURA LATEX EN COLUMNAS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2 )

( A ) ( B ) (C) = (A) x (B)

COLUMNAS

C-1 1.90 5.20 9.88 5.00 49.40

C-2 1.80 5.20 9.36 4.00 37.44

C-3 EJE A-A 0.80 5.60 4.48 6.00 26.88

C-3 EJE C-C 0.80 1.30 1.04 14.00 14.56

C-3 EJE 1-1 0.80 6.55 5.24 8.00 41.92

C-3 EJE 2-2 0.80 2.80 2.24 8.00 17.92

C-4 0.80 5.60 4.48 1.00 4.48

C-5 1.50 5.30 7.95 1.00 7.95

C-6 1.50 7.20 10.80 2.00 21.60

C-7 (GRADERIA FRONTAL) 0.80 3.20 2.56 16.00 40.96

C-7 (GRADERIA FRONTAL) 0.80 1.70 1.36 16.00 21.76

C-7 (GRADERIA LATERAL) 0.80 4.70 3.76 24.00 90.24

C-7 (GRADERIA LATERAL) 0.80 1.70 1.36 24.00 32.64

C/A EJE A-A 0.40 2.60 1.04 13.00 13.52

C/A EJE C-C 0.40 4.60 1.84 26.00 47.84

C/A EJE 1-1 0.40 5.60 2.24 17.00 38.08

C/A EJE 2-2 0.40 5.60 2.24 16.00 35.84

TOTAL: M2 543.03

PARTIDA: 10.04.00.- PINTURA LATEX EN VIGAS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( m2 )

( A ) ( B ) (C) = (A) x (B)

V-1 (15x25) EJE A-A Y C-C 49.45 0.50 24.73 10.00 247.25

V-1 (15x25) EJE 1-1 Y 2-2 29.00 0.50 14.50 8.00 116.00

V-1 (15x25) GRADERIA LATERAL 34.45 0.50 17.23 4.00 68.90

V-1 (15x25) GRADERIA FRONTAL 18.90 0.50 9.45 4.00 37.80

V-2(25x35) GRADERIA LATERAL 34.45 0.30 10.34 4.00 41.34

V-2(25x35) GRADERIA FRONTAL 18.90 0.30 5.67 4.00 22.68

TOTAL: M2 533.97

PARTIDA: 10.05.00.- PINTURA LATEX EN CIELORASOS UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( m2 )

( A ) ( B ) (C) = (A) x (B)

LOSA ESTRADO

7.80 4.20 32.76 1.00 32.76

TOTAL: M2 32.76

11.00 COBERTURAS Y CERRAMIENTO

PARTIDA: 11.01.00.- COBERTURA AUTOSOPORTANTE CURVA DE ACERO UNIDAD : (M2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

COBERTURA COLISEO

COLISEO 30x50 FLECHA 6M. 50.00 30.00 1500.00 1.00 1500.00

TOTAL: M2 1500.00

Page 22: Metrados Coliseo

PARTIDA: 11.02.00.- CERRAMIENTO DE TIMPANO FRONTAL DE ACERO UNIDAD : (UND)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( M2)

( A ) ( B ) (C) = (A) x (B)

COBERTURA COLISEO

TIMPANOS FRONTALES 261.91 1.00 261.91

TOTAL: UND 261.91

12.00 VIDRIOS, CRISTALES Y SIMILARES

PARTIDA: 12.01.00.- VIDRIOS DOBLES NACIONALES UNIDAD : (Pie2)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Pie2)

( A ) ( B ) (C) = (A) x (B)

EJE 1-1

24.75 0.40 9.90 1.00 9.90

EJE 2-2

23.31 0.40 9.32 1.00 9.32

EJE A-A

34.09 0.40 13.64 1.00 13.64

EJE B-B

5.90 0.40 2.36 1.00 2.36

EJE C-C

39.99 0.40 16.00 1.00 16.00

TOTAL: M2 51.22

Pie2 551.08

13.00 OTROS

PARTIDA: 13.01.00.- MESADA DE CONCRETO UNIDAD : (ML)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( ML)

( A ) ( B ) (C) = (A) x (B)

SSHH

SS HH VARONES 1.75 1.75 1.00 1.75

SS HH DAMAS 2.15 2.15 1.00 2.15

SS HH VARONES 3.10 3.10 1.00 3.10

SS HH CAMERINOS VARONES 2.72 2.72 2.00 5.44

SS HH CAMERINOS DAMAS 2.72 2.72 2.00 5.44

TOTAL: ML 17.88

Page 23: Metrados Coliseo

PLANILLA DE METRADOS SANITARIAS

INSTALACIONES SANITARIAS

01.00 CAJA DE REGISTRO

PARTIDA: 01.01.00.- SALIDA DE DESAGÜE PVC 4"

PARTIDA: 01.02.00.- SALIDA DE DESAGÜE PVC 2"

PARTIDA: 01.03.00.- CAJAS DE REGISTRO DE DESAGUE 12" x 24" UNIDAD : ( UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( UND)

( A ) ( 2 ) (3) = (1) x (2)

1° NIVEL

CAJAS DE REGISTRO 3.00 3.00 1.00 3.00

T O T A L : UND 3.00

PARTIDA: 01.04.00.- CAJAS DE REGISTRO CIEGA DE 0.40 x 0.40 UNIDAD : ( UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( UND)

( A ) ( 2 ) (3) = (1) x (2)

1° NIVEL

CRP 2.00 2.00 1.00 2.00

T O T A L : UND 2.00

02.00 TUBERIAS DE DESAGÜE

PARTIDA: 02.01.00.- TUBERIA DE PVC 6" UNIDAD : ( ML)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( ML)

( A ) ( 2 ) (3) = (1) x (2)

MATRIZ DE 6" 50.30 50.30 2.00 100.60

T O T A L : ML 100.60

PARTIDA: 02.02.00.- TUBERIA DE PVC 4" UNIDAD : ( ML)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( ML)

( A ) ( 2 ) (3) = (1) x (2)

TUBERIA DE PVC 4" 50.30 50.30 2.00 100.60

T O T A L : ML 100.60

PARTIDA: 02.03.00.- TUBERIA DE PVC 2" UNIDAD : ( ML)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( ML)

( A ) ( 2 ) (3) = (1) x (2)

TUBERIA PVC 2" 50.30 50.30 2.00 100.60

T O T A L : ML 100.60

"INSTALACION DEL POLIDEPORTIVO EN LA I.E. Nº 80460 GRAN PAJATEN EN LA LOCALIDAD DE PIAS, DITRITO DE PIAS, PATAZ, LA LIBERTAD"

Page 24: Metrados Coliseo

03.00 ACCESORIOS PARA TUBERIA DE DESAGÜE

PARTIDA: 03.01.00.- TEE RECTA DE 4" UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SS HH VARONES

INODORO 8.00 8.00 1.00 8.00

T O T A L : Und 8.00

PARTIDA: 03.02.00.- TEE PVC - SAL 4"x2" UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SS HH VARONES

SALIDA PARA VENTILACION 2.00 2.00 1.00 2.00

SS HH DE MUJERES

SALIDA PARA VENTILACION 1.00 1.00 1.00 1.00

CAMERINOS VARONES

SALIDA PARA VENTILACION 2.00 2.00 1.00 2.00

CAMERINOS MUJERES

SALIDA PARA VENTILACION 2.00 2.00 1.00 2.00

T O T A L : Und 7.00

PARTIDA: 03.03.00.- CODO PVC - SAL 4"x90° UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

6.00 6.00 2.00 12.00

T O T A L : Und 12.00

PARTIDA: 03.04.00.- CODO PVC - SAL 4"x90° CON VENTILACION UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SS HH VARONES 1.00 1.00 2.00 2.00

SS HH MUJERES 1.00 1.00 2.00 2.00

T O T A L : Und 4.00

PARTIDA: 03.05.00.- YEE SANITARIA SIMPLE DE 4" UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SS HH VARONES 1.00 1.00 2.00 2.00

SS HH MUJERES 4.00 4.00 2.00 8.00

T O T A L : Und 10.00

PARTIDA: 03.06.00.- YEE DE PVC - SAL DE 4" CON REDUCCION A 2" UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SS HH VARONES 5.00 5.00 1.00 5.00

SS HH MUJERES 4.00 4.00 1.00 4.00

SS HH VARONES 2.00 2.00 2.00 4.00

SS HH MUJERES 2.00 2.00 2.00 4.00

T O T A L : Und 17.00

PARTIDA: 03.07.00.- CODO DE PVC - SAL DE 4"x45° UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SS HH VARONES 1.00 1.00 2.00 2.00

SS HH MUJERES 2.00 2.00 2.00 4.00

T O T A L : Und 6.00

Page 25: Metrados Coliseo

PARTIDA: 03.08.00.- TEE RECTA DE 2" UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SS HH VARONES 8.00 8.00 2.00 16.00

SS HH MUJERES 8.00 8.00 2.00 16.00

T O T A L : Und 32.00

PARTIDA: 03.09.00.- CODO PVC - SAL 2"x 90° UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SS HH VARONES 10.00 10.00 2.00 20.00

SS HH MUJERES 8.00 8.00 2.00 16.00

T O T A L : Und 36.00

PARTIDA: 03.10.00.- TRAMPA "P" DE PVC - SAL PARA DESAGÜE DE 2" UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SS HH VARONES

OVALINES 21.00 21.00 1.00 21.00

DUCHAS 12.00 12.00 1.00 12.00

URINARIOS 2.00 2.00 1.00 2.00

T O T A L : Und 35.00

PARTIDA: 03.11.00.- TRAMPA "S" DE PVC - SAL PARA DESAGÜE DE 2" UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SS HH VARONES

SUMIDEROS 2.00 2.00 1.00 2.00

SS HH MUJERES

SUMIDEROS 1.00 1.00 1.00 1.00

CAMERINOS VARONES

SUMIDEROS 2.00 2.00 1.00 2.00

CAMERINOS MUJERES

SUMIDEROS 1.00 1.00 1.00 1.00

T O T A L : Und 6.00

PARTIDA: 03.12.00.- REGISTROS DE BRONCE DE 4" UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SS HH VARONES

REGISTROS 2.00 2.00 1.00 2.00

SS HH MUJERES

REGISTROS 1.00 1.00 1.00 1.00

CAMERINOS VARONES

SUMIDEROS 2.00 2.00 1.00 2.00

CAMERINOS MUJERES

SUMIDEROS 2.00 2.00 1.00 2.00

T O T A L : Und 7.00

04.00 TUBERIA DE AGUA FRIA

PARTIDA: 04.01.00.- TUBERIA PVC 3/4" PARA DISTRIBUCION UNIDAD : ( ML)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( ML)

( A ) ( 2 ) (3) = (1) x (2)SSHH VARONES 2.30 2.30 2.00 4.60

SSHH DAMAS 3.14 3.14 2.00 6.28

CAMERINOS FRONTAL 35.00 35.00 1.00 35.00

RED DE ALIMENTACION CISTERNA 65.00 65.00 1.00 65.00

T O T A L : ML 110.88

Page 26: Metrados Coliseo

PARTIDA: 04.02.00.- TUBERIA PVC 1/2" PARA DISTRIBUCION UNIDAD : (ML)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SSHH VARONES 15.45 15.45 2.00 30.90

SSHH DAMAS 12.75 12.75 2.00 25.50

T O T A L : ML 56.40

05.00 ACCESORIOS PARA TUBERIA DE AGUA FRIA

PARTIDA: 05.01.00.- CODO DE FIERRO GALVANIZADO UNION ROSCADA DE 1/2" /(INC. ADAPT.) UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SSHH VARONES 14.00 14.00 2.00 28.00

SSHH DAMAS 14.00 14.00 2.00 28.00

T O T A L : Und 56.00

PARTIDA: 05.02.00.- VALVULA COMPUERTA DE BRONCE DE UNION ROSCADA DE 1/2" (INC. ADAPT.) UNIDAD : ( Und)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( 2 ) (3) = (1) x (2)

SSHH VARONES 1.00 1.00 2.00 2.00

SSHH DAMAS 2.00 2.00 2.00 4.00

T O T A L : Und 6.00

06.00. APARATOS SANITARIOS

PARTIDA: 06.01.00.- INODORO TANQUE BAJO UNIDAD : (Und)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( Und)

( A ) ( B ) (C) = (A) x (B)

INODOROS

SS HH DAMAS 4.00 1.00 4.00

SS HH VARONES 5.00 1.00 5.00

CAMERINOS DAMAS 2.00 2.00 4.00

CAMERINOS VARONES 2.00 2.00 4.00

TOTAL: Und 17.00

PARTIDA: 06.02.00.- URINARIO CORRIDO DE CEMENTO ENCHAPADO CON CERAMICA UNIDAD : (ML)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( ML)

( A ) ( B ) (C) = (A) x (B)

SS HH VARONES 3.74 3.74 1.00 3.74

SS HH VARONES 4.34 4.34 1.00 4.34

TOTAL: ML 8.08

CAMERINOS DAMAS 3.00 2.00 6.00

CAMERINOS VARONES 3.00 2.00 6.00

TOTAL: Und 12.00

PARTIDA: 06.03.00.- LAVATORIO DE PARED - OVALIN

PARTIDA: 06.04.00.- DUCHAS CROMADAS DE CABEZA GIRATORIA Y LLAVE MEZCLADORA UNIDAD : (UND)

DIMENSIONES VECES QUE ÁREA

D E S C R I P C I O N LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ML)

( A ) ( B ) (C) = (A) x (B)

SSHH

CAMERINOS VARONES 3.00 3.00 2.00 6.00

CAMERINOS DAMAS 3.00 3.00 2.00 6.00

Page 27: Metrados Coliseo

TOTAL: UND 12.00

Page 28: Metrados Coliseo

PLANILLA DE METRADOS ELÉCTRICAS

INSTALACIONES ELECTRICAS

01.00 TABLEROS Y SUBTABLEROS

PARTIDA: 01.01.00.- TABLERO GENERAL DE DISTRIBUCION C/BARRAS DE cu 8 POLOS + P/TIERRAS UNIDAD : ( UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE UND

( A ) ( 2 ) (3) = (1) x (2)

COLISEO 1.00 1.00 1.00 1.00

T O T A L : UND 1.00

02.00 LLAVES TERMOMAGNETICAS

PARTIDA: 02.01.00.- LLAVE TERMOMAGNETICA 3x30 A TICINO O SIMILAR UNIDAD : ( UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE UND

( A ) ( 2 ) (3) = (1) x (2)

TABLERO GENERAL 1.00 1.00 1.00 1.00

T O T A L : UND 1.00

PARTIDA: 02.02.00.- LLAVE TERMOMAGNETICA 2x20 A TICINO O SIMILAR UNIDAD : ( UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE UND

( A ) ( 2 ) (3) = (1) x (2)

TABLERO GENERAL 6.00 6.00 1.00 6.00

T O T A L : UND 6.00

PARTIDA: 02.03.00.- LLAVE DIFERENCIAL DE 3x30 A, 30ma TICINO O SIMILAR UNIDAD : ( UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE UND

( A ) ( 2 ) (3) = (1) x (2)

TABLERO GENERAL 1.00 1.00 1.00 1.00

T O T A L : UND 1.00

PARTIDA: 02.04.00.- LLAVE DIFERENCIAL 2x20 A, 30ma TICINO O SIMILAR UNIDAD : ( UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE UND

( A ) ( 2 ) (3) = (1) x (2)

TABLERO GENERAL 6.00 6.00 1.00 6.00

T O T A L : UND 6.00

03.00 TUBERIAS

PARTIDA: 03.01.00.- TUBERIA PVC 20 MM ALIMENTADOR PRINCIPAL UNIDAD : (ML)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( ML)

( A ) ( 2 ) (3) = (1) x (2)

COLISEO 305.23 305.23 1.00 305.23

SSHH Y CAMERINOS 172.00 172.00 1.00 172.00

T O T A L : ML 477.23

04.00 ARTEFACTOS LUMINICOS Y ELECTRICOS

PARTIDA: 04.01.00.-ARTEFACTO FLUORESCENTE 2x40 TIPO RAS UNIDAD : (UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE UND

( A ) ( 2 ) (3) = (1) x (2)

SSHH DAMAS 2.00 2.00 2.00 4.00

SSHH VARONES 2.00 2.00 2.00 4.00

CAMERINOS VARONES 2.00 2.00 2.00 4.00

CAMERINOS DAMAS 2.00 2.00 2.00 4.00

"INSTALACION DEL POLIDEPORTIVO EN LA I.E. Nº 80460 GRAN PAJATEN EN LA LOCALIDAD DE PIAS, DITRITO DE PIAS, PATAZ, LA LIBERTAD"

Page 29: Metrados Coliseo

T O T A L : UND 16.00

PARTIDA: 04.02.00.- ARTEFACTOS DE ILUMINACION DEPORTIVA C/TEMPO RPV 350 L 400W UNIDAD : (UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE UND

( A ) ( 2 ) (3) = (1) x (2)

1° NIVEL

COLISEO 20.00 20.00 1.00 20.00

T O T A L : UND 20.00

05.00 SALIDA DE CIRCUITOS

PARTIDA: 05.01.00.-SALIDAS DE CIRCUITOS UNIDAD : (UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE UND

( A ) ( 2 ) (3) = (1) x (2)

EQUIPOS LUMINICOS 37.00 37.00 1.00 37.00

INTERRUPTORES 8.00 8.00 1.00 8.00

TOMACORRIENTES 20.00 20.00 1.00 20.00

TABLEROS 1.00 1.00 1.00 1.00

T O T A L : UND 66.00

06.00 INTERRUPTORES

PARTIDA: 06.01.00.-INTERRUPTOR SIMPLE EN CAJA FºGº 100 X 55 mm UNIDAD : (UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE UND

( A ) ( 2 ) (3) = (1) x (2)

SSHH VARONES 2.00 2.00 1.00 2.00

SSHH DAMAS} 1.00 1.00 1.00 1.00

CAMERINOS VARONES 2.00 2.00 1.00 2.00

CAMERINOS DAMAS 2.00 2.00 1.00 2.00

T O T A L : UND 7.00

07.00 TOMACORRIENTES

PARTIDA: 07.01.00.-TOMACORRIENTES CON LT EN CAJA FºGº 100 X 55mm UNIDAD : (UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( ML)

( A ) ( 2 ) (3) = (1) x (2)

SSHH VARONES 2.00 2.00 1.00 2.00

SSHH DAMAS} 1.00 1.00 1.00 1.00

CAMERINOS DAMAS 4.00 4.00 1.00 4.00

CAMERINOS VARONES 4.00 4.00 1.00 4.00

COLISEO 10.00 10.00 1.00 10.00

T O T A L : UND 21.00

08.00 CABLEAD0

PARTIDA: 08.01.00.-CABLE 3x1X25 mm2 + 1x6 mm2 NYY 4X4 mm2 1 KV (INCLUYE EXCAVACION Y RELLENO) UNIDAD : (ML)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ML

( A ) ( 2 ) (3) = (1) x (2)

ALIMENTADOR PRINCIPAL 105.00 105.00 1.00 105.00

T O T A L : ML 105.00

PARTIDA: 08.02.00.-CABLE 2x8mm2 THW+ 1x4mm2 THW UNIDAD : (ML)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( ML)

( A ) ( 2 ) (3) = (1) x (2)

ILUMINACION COLISEO 268.07 268.07 1.00 268.07

T O T A L : ML 268.07

PARTIDA: 08.03.00.-CABLE 2x4mm2 THW+ 1x2.5mm2 THW UNIDAD : (ML)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( ML)

( A ) ( 2 ) (3) = (1) x (2)

ALIMENTACION CIRCUITOS SSHH Y CAMERINOS FRONTALES 88.00 88.00 1.00 88.00

ILUMINACION SSHH Y CAMERINOS 84.80 84.80 1.00 84.80

TOMACORRIENTES COLISEO 197.16 197.16 1.00 197.16

TOMACORRIENTES SSHH Y CAMERINOS 92.80 92.80 1.00 92.80

Page 30: Metrados Coliseo

T O T A L : ML 462.76

09.00 SISTEMA DE PUESTA A TIERRA

PARTIDA: 09.01.00.-POZO A TIERRA CON VARILLA DE COBRE DE 5/8" X 24m UNIDAD : (UND)

DIMENSIONES VECES QUE UNIDAD

DESCRIPCIÓN LONG. (m.) ANCHO. (m.) ALTO. (m.) Área/Volumen SE REPITE ( UND)

( A ) ( 2 ) (3) = (1) x (2)

POZO A TIERRA 1.00 1.00 1.00 1.00

T O T A L : UND 1.00