  • REHABILITACIN DEL CANAL LOROCOCHA - LACHAQUIINICIO DE OBRAOBRAS PROVISIONALES

    TRABAJOS PRELIMINARES ALMACEN DE OBRA S/. 573.92 S/. 573.92 CARTEL DE OBRA S/. 640.00 S/. 640.00

    CAPTACIN Y DESARENADOR - 01 UNIDAD TRABAJOS PRELIMINARES

    LIMPIEZA Y DESBROCE S/. 32.64 S/. 32.64 TRAZO, NIVELACION Y REPLANTEO EN ESTRUCTURAS S/. 227.52 S/. 227.52

    MOVIMIENTO DE TIERRAS EXCAVACION EN MATERIAL SUELTO S/EQ. S/. 227.88 S/. 227.88 EXCAVACION EN ROCA FIJA CON EQUIPO MANUAL S/. 654.31 S/. 654.31 REFINE Y NIVELACION EN TERRENO NORMAL S/. 35.60 S/. 35.60 ENROCADO DE PROTECCIN EN CAPTACIN S/. 337.06 S/. 337.06 S/. 674.12 ELIMINACIN DE MATERIAL EXCEDENTE, D=30.0 M S/. 40.99 S/. 163.98 S/. 204.97

    OBRAS DE CONCRETO ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS S/. 2,534.90 S/. 2,534.90 ARMADURA DE FIERRO CORRUGADO f'y=4200 kg/cm2 P/ESTRUCTURAS S/. 3,295.51 S/. 3,295.51 CONCRETO f'c=210 kg/cm2 S/. 2,922.63 S/. 2,922.63 CONCRETO CICLOPEO f'c=175 kg/cm2+ 30% P.G. S/. 1,806.49 S/. 1,806.49 CONCRETO CICLOPEO f'c=140 kg/cm2 + 30 % PG. S/. 1,065.51 S/. 1,065.51 ALBAILERIA DE PIEDRA ASENTADO CON CONCRETO F'C=175 KG/CM2 Y EMBOQUILLADO CON MORTERO C:A=1:3, E=0.50M. S/. 117.33 S/. 117.33 TARRAJEO DE MUROS INTERIORES C:A=1:4 + IMPERM. E=1.5cm S/. 244.16 S/. 732.47 S/. 976.63

    ACCESORIOS EN CAPTACIN Y DESARENADOR ACCESORIOS EN CAPTACIN Y DESARENADOR S/. 2,020.33 S/. 2,020.33

    CANAL DE CONDUCCIN - L=5.950 KM TRABAJOS PRELIMINARES

    LIMPIEZA Y DESBROCE EN LINEA DE CONDUCCIN S/. 2,965.08 S/. 128.92 S/. 3,094.00 TRAZO, NIVELACION Y REPLANTEO EN LINEA DE CONDUCCIN S/. 2,181.91 S/. 574.19 S/. 2,756.10

    MOVIMIENTO DE TIERRAS EXCAVACION EN MATERIAL SUELTO S/EQ. S/. 1,532.08 S/. 2,655.60 S/. 2,655.60 S/. 2,757.74 S/. 2,655.60 S/. 12,256.62 EXCAVACION EN ROCA SUELTA S/EQ. S/. 2,329.18 S/. 3,187.29 S/. 5,516.47 EXCAVACION EN ROCA FIJA CON EQUIPO MANUAL S/. 1,527.48 S/. 4,582.43 S/. 6,109.91 RELLENO COMPACTADO MANUAL MATERIAL PROPIO S/. 409.36 S/. 204.68 S/. 614.04 RELLENO COMPACTADO MANUAL- CON MATERIAL DE PRESTAMO S/. 881.07 S/. 2,422.96 S/. 3,304.03 REFINE Y NIVELACION EN TERRENO NORMAL S/. 1,011.50 S/. 1,051.96 S/. 1,092.42 S/. 485.52 S/. 3,641.40 ELIMINACIN DE MATERIAL EXCEDENTE, D=30.0 M S/. 1,672.34 S/. 2,557.70 S/. 2,656.08 S/. 2,557.70 S/. 2,360.96 S/. 11,804.78

    OBRAS DE CONCRETO ENCOFRADO Y DESENCOFRADO DE CANAL (1 CARA) S/. 13,203.47 S/. 13,731.61 S/. 14,259.75 S/. 13,731.61 S/. 8,450.22 S/. 63,376.66 CONCRETO SIMPLE f'c=175 kg/cm2 S/. 32,040.89 S/. 33,322.53 S/. 34,604.16 S/. 33,322.53 S/. 20,506.17 S/. 153,796.28 JUNTA DE CONTRACCIN - CANAL S/. 2,249.54 S/. 4,874.01 S/. 2,999.39 S/. 10,122.94 JUNTA DE DILATACIN - CANAL S/. 2,800.49 S/. 2,800.49

    OBRAS DE ARTE ESTRUCTURA DE PASE DE QUEBRADA - 22 UNIDADES

    EXCAVACION EN MATERIAL SUELTO S/EQ. S/. 1,450.94 S/. 1,450.94 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS S/. 954.24 S/. 2,862.72 S/. 3,816.96 ARMADURA DE FIERRO CORRUGADO f'y=4200 kg/cm2 P/ESTRUCTURAS S/. 2,644.99 S/. 5,289.99 S/. 7,934.98 CONCRETO f'c=210 kg/cm2 S/. 5,645.72 S/. 5,645.72 ALBAILERIA DE PIEDRA ASENTADO CON CONCRETO F'C=175 KG/CM2 Y EMBOQUILLADO CON MORTERO C:A=1:3, E=0.50M. S/. 1,430.80 S/. 1,430.80

    POZA DE DISIPACIN Y ALCANTARILLA - 01 UNIDAD EXCAVACION EN MATERIAL SUELTO S/EQ. S/. 85.74 S/. 85.74 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS S/. 2,612.23 S/. 2,612.23 ARMADURA DE FIERRO CORRUGADO f'y=4200 kg/cm2 P/ESTRUCTURAS S/. 6,915.31 S/. 6,915.31 CONCRETO f'c=210 kg/cm2 S/. 3,453.14 S/. 3,453.14

    ACUEDUCTO - 01 UNIDAD EXCAVACION EN ROCA SUELTA S/EQ. S/. 32.96 S/. 32.96 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS S/. 1,083.46 S/. 1,083.46 ARMADURA DE FIERRO CORRUGADO f'y=4200 kg/cm2 P/ESTRUCTURAS S/. 3,011.73 S/. 3,011.73 CONCRETO f'c=210 kg/cm2 S/. 1,384.66 S/. 1,384.66

    TOMAS LATERALES - 20 UNIDADES EXCAVACION EN MATERIAL SUELTO S/EQ. S/. 27.48 S/. 27.48 ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS S/. 636.16 S/. 636.16 ARMADURA DE FIERRO CORRUGADO f'y=4200 kg/cm2 P/ESTRUCTURAS S/. 440.83 S/. 440.83

    Totalmes 1 mes 2 mes 3 mes 4 mes 5 mes 6 mes 7

    CRONOGRAMA VALORIZADO DE OBRA el dom 03/01/10REHABILITACIN DEL CANAL LOROCOCHA - LACHAQUI

    Pgina 1

  • CONCRETO f'c=210 kg/cm2 S/. 876.06 S/. 876.06 ACCESORIOS EN TOMA LATERAL S/. 3,063.40 S/. 3,063.40

    TRANSICIN DE CANAL - 06 UNIDADES ENCOFRADO Y DESENCOFRADO DE ESTRUCTURAS S/. 166.99 S/. 166.99 S/. 333.98 ARMADURA DE FIERRO CORRUGADO f'y=4200 kg/cm2 P/ESTRUCTURAS S/. 501.84 S/. 501.84 CONCRETO f'c=210 kg/cm2 S/. 438.03 S/. 438.03

    VARIOS VARIOS

    ENSAYO DE RESISTENCIA DE CONCRETO S/. 1,400.00 S/. 1,400.00 PLACA RECORDATORIA S/. 240.00 S/. 240.00 MODULO DE CAPACITACIN EN RIEGO S/. 748.00 S/. 748.00 INDUMENTARIA DE TRABAJO S/. 1,200.00 S/. 1,200.00

    FLETE FLETES

    FLETE TERRESTRE S/. 58,885.75 S/. 33,283.25 S/. 92,169.00 FLETE RURAL S/. 47,903.73 S/. 73,264.53 S/. 5,635.73 S/. 126,803.99

    Total S/. 130,173.00 S/. 179,205.12 S/. 75,911.79 S/. 76,161.94 S/. 62,104.69 S/. 41,384.87 S/. 564,941.41

    Totalmes 1 mes 2 mes 3 mes 4 mes 5 mes 6 mes 7

    CRONOGRAMA VALORIZADO DE OBRA el dom 03/01/10REHABILITACIN DEL CANAL LOROCOCHA - LACHAQUI

    Pgina 2