MORTEROS DOSIFICACION CEMENTO CALHIDRA ARENA
M3 (TON) (TON) (TON)
CAL-ARENA 1-3 0.2500 1.0000
CAL-ARENA 1-4 0.2000 1.0700
CAL-ARENA 1-5 0.1700 1.1300
CAL-ARENA 1-6 0.1450 1.1800
CAL-ARENA 1-7 0.1250 1.2200
CAL-ARENA 1-8 0.1100 1.2500
CAL-ARENA 1-9 0.1000 1.2700
CAL-ARENA 1-10 0.0900 1.2800
CEMENTO-ARENA 1-2 0.6300 1.0000
CEMENTO-ARENA 1-2.5 0.5850 1.0250
CEMENTO-ARENA 1-3 0.5400 1.0500
CEMENTO-ARENA 1-4 0.4400 1.1000
CEMENTO-ARENA 1-5 0.3800 1.1500
CEMENTO-ARENA 1-6 0.3100 1.1700
CEMENTO-CAL-ARENA 1-1-4 0.3000 0.1500 1.0000
CEMENTO-CAL-ARENA 1-1-5 0.3100 0.1550 1.0200
CEMENTO-CAL-ARENA 1-1-6 0.2550 0.1250 1.0500
CEMENTO-CAL-ARENA 1-1-8 0.2150 0.1000 1.0900
CEMENTO-CAL-ARENA 1-1-10 0.1800 0.0850 1.0650
CEMENTO-CAL-ARENA 1-1-12 0.1500 0.0750 1.1850
document.xls
Página 2
AGUA
(M3)
0.2700
0.2600
0.2550
0.2500
0.2450
0.2400
0.2350
0.2300
0.2850
0.2825
0.2800
0.2780
0.2750
0.2750
0.2800
0.2170
0.2790
0.2780
0.2750
0.2730