CHIEF ENGINEER RECONSTRUCTION PERRA
NWFPDated : 18-02-2010
PROVINCIAL EARTHQUAKE RECONSTRUCTION
& REHABILITATION AGENCY
-
8/3/2019 Presentation LSF
2/23
AWARDED WORKS
-
8/3/2019 Presentation LSF
3/23
Contract No. PERRA/Mansehra/87/2009Site Location Map
-
8/3/2019 Presentation LSF
4/23
Contract No. PERRA/Mansehra/87/2009(Reconstruction of 23 Schools in Tehsil Balakot)
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Achieved
Planned
Achieved 0%
Planned 50%
Achieved
Planned 60%
Achieved 0%
Planned 40%
Achieved 0%
Achieved 2%
Planned 41%
Supply of Super
Structure Material
Sub Structure
Installation of
Super Structure
OVERALL
PROGRESS
(Design, Supply
& Install)
Financial Progress
2%
Contractor Name: M/s Ascent Structural Concepts JVPercentage Completion
Design
Activities
33%
Status
-Contract Cost = Rs. 216.596
Million
- Date of Commencement = Aug
25, 2009
- Date of Completion =Aug 24,
2010
- 2 schools deleted from scope of
work being located in Red Zone of
Old Balakot City
Notices Issued:-2778/3310/JK/02/-9104 dated
Dec 29, 2009
- 2778/3310/JK/02/-11163 dated
Feb 13, 2010
Issues:
- Factory Acceptance Tests still
awaited (Ref No.
2778/3310/JK/02/-8738 dated Dec14, 2009)
- Role of SCCI in JV is not clear
Physical Progress:
- WBM laid on only 5 schools (only
academic blocks)
- Excavation of 4 schools in
progress
-
8/3/2019 Presentation LSF
5/23
Contract No. PERRA/Mansehra/88/2009Site Location Map
-
8/3/2019 Presentation LSF
6/23
Contract No. PERRA/Mansehra/88/2009(Reconstruction of 17 Schools in Tehsil Balakot)
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Achieved
Planned
Achieved 0%
Planned 50%
Achieved
Planned
Achieved 0%
Planned 40%
Achieved (Rs. 4.62 Million)
Achieved
Planned 60%
Installation of
Super Structure
OVERALL
PROGRESS
(Design, Supply
& Install)
Financial Progress
5%
3.5%
3.5%
60%Sub Structure
Contractor Name: M/s One Ten (Pvt.) Ltd.Percentage Completion
Design
Activities
32%
Status
Supply of Super
Structure Material
-Contract Cost = Rs. 130.865
Million- Date of Commencement = Aug
11, 2009
- Date of Completion =Aug 10,
2010
- 1 schools deleted from scope of
work being allocated to USAID
Notices Issued:
-2778/3310/JK/02/-9050 datedDec 24, 2009
Issues:
-Land Issues have been reported at
5 sites (GPS Tangri, GPS Guddi, GPS
Phagal, GGMS Ghanool, GPS Agla
Gran)
Physical Progress:
- Fixing of Steel for casting of slab
on grade for 4 schools (GPS
Sobrian, GGPS Kanshian, GPS
Kanoch & GPS Budwar) in process.
-
8/3/2019 Presentation LSF
7/23
Contract No. PERRA/Battagram/23/2008Site Location Map
-
8/3/2019 Presentation LSF
8/23
Contract No. PERRA/Battagram/23/2008(Reconstruction of 37 Schools in District Battagram)
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Achieved
Planned
Achieved 25%
Planned
Achieved
Planned
Achieved
Planned
Achieved (Rs. 55.83 Million certified)
Achieved 25%
Planned
Contractor Name: M/s Urfan Khan & Co. (RECO as Supplier)Percentage Completion
Design(99%)
Activities Status
Supply of Super
Structure Material
Sub Structure
Installation of
Super Structure
OVERALL
PROGRESS
(Design, Supply
& Install)
Financial Progress
51%
19%
14%
-Contract Cost = Rs. 298.17
Million
- Date of Commencement = Jan
17, 2009
- Date of Completion =Jan 16,
2010
- EOT desired up to Jun 30, 2010
under process
Notices Issued:
- 2778/3310/MD/01/-390 dated
Feb 2, 2009
- 2778/3310/MD/01/-446 dated
Jun 3, 2009
- 2778/3310/JK/03/-6846 dated
Nov 14, 2009
- 2778/3310/MD/01/-788 dated
Jan 8, 2010
Physical Progress:- Slab on grade casted at 20 sites
- Super-structure erected on 3
sites with progress on remaining
5 sites
-
8/3/2019 Presentation LSF
9/23
Contract No. PERRA/Shangla/18/2008Site Location Map
-
8/3/2019 Presentation LSF
10/23
Contract No. PERRA/Shangla/18/2008(Reconstruction of 27 Schools in District Shangla)
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Achieved 82%
Planned
Achieved 0%
Planned
Achieved
Planned
Achieved 0%
Planned
Achieved (Rs. 31.57 Million certified)
Achieved
Planned 90%
Supply of Super
Structure Material
26%
Contractor Name: M/s Competent PEB SFAN JVPercentage Completion
Design
Activities Status
Sub Structure
Installation of
Super Structure
OVERALL
PROGRESS
(Design, Supply
& Install)
Financial Progress 12%
12%
-Contract Cost = Rs. 254.149
Million
- Date of Commencement =
March 17, 2009
- Date of Completion = March 16,
2010
-EOT case submitted to NESPAK
desired upto July 31, 2010 & is
under review.
Notices Issued:
- 2778/3310/JK/04/-6886 datedJune 22, 2009
- 2778/33/AT/01/-473 dated July
2, 2009
- 2778/3310/JK/04/-3198 dated
Oct 15, 2009
- 2778/3310/JK/04/-6189 dated
Oct 26, 2009
- 2778/3310/JK/04/-6505 dated
Nov 5, 2009
Issues:
- Poor law & order situation
affected progress of work
Status:
- Opening of L/C in progress
-Slab on grade casted at 7 sites
- Retaining Wall at 5 sites is inprogress
-
8/3/2019 Presentation LSF
11/23
Contract No. PERRA/Shangla/14/2007Site Location Map
-
8/3/2019 Presentation LSF
12/23
Contract No. PERRA/Shangla/14/2007(Reconstruction of 29 Schools in District Shangla)
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Achieved
Planned
Achieved
Planned
Achieved 27%
Planned
Achieved 6%
Planned
Achieved (Rs. 54.995 Million certified)
Achieved 25%
Planned
13%
Sub Structure
Installation of
Super Structure
OVERALL
PROGRESS
(Design, Supply
& Install)
Financial Progress 23%
90%
Supply of Super
Structure Material
Contractor Name: M/s A.M. & Co. and CMES JV
Percentage Completion
Design(95%)
Activities Status
-Contract Cost = Rs. 240.905
Million
- Date of Commencement =
March 17, 2009
- Date of Completion = March 16,
2010
- EOT case submitted to NESPAK
desired upto Dec 18, 2010 & is
under review.
Notices Issued:
- 2778/3310/JK/04/-6854 dated
June 20, 2009
-2778/33/AT/01/-473 dated July
2, 2009
- 2778/3310/JK/04/-857 dated
Aug 18, 2009
Issues:
- Double storey design of GPS &GHS Kuz Karora is awaited
- Poor law & order situation
affected progress of work
Physical Progress:
- Slab on grade casted at 6 sites
- Super-structure erected on 3
sites
-
8/3/2019 Presentation LSF
13/23
PHOTOLOG
-
8/3/2019 Presentation LSF
14/23
Schools in Battagram
-
8/3/2019 Presentation LSF
15/23
Schools in Shangla
-
8/3/2019 Presentation LSF
16/23
UPCOMING WORKS
-
8/3/2019 Presentation LSF
17/23
S. No. Contract No. LocationNo. of
Schools
Date of Bid
OpeningSuccessful Bidder
ContractAmount
(Rs.) Million
1 PERRA/Kohistan/18/2009 Kohistan 25 Dec 7, 2009 A.M. & Co. and CMES JV 168.395
2 PERRA/Kohistan/19/2009 Kohistan 19 Dec 7, 2009 MSA 117.089
3 PERRA/Mansehra/232/2009 Mansehra 29 Jan 12, 2010 Chugatta Metecno JV 166.951
4 PERRA/Shangla/30/2009 Shangla 33 Jan 30, 2010 Bid under Evaluation
5 PERRA/Kohistan/28/2010 Kohistan 60 Bid invited on Mar 04, 2010
166 452.435
Upcoming Works
-
8/3/2019 Presentation LSF
18/23
Contract No. PERRA/Kohistan/18/2009Site Location Map
-
8/3/2019 Presentation LSF
19/23
Contract No. PERRA/Kohistan/19/2009Site Location Map
-
8/3/2019 Presentation LSF
20/23
Contract No. PERRA/Mansehra/232/2009Site Location Map
-
8/3/2019 Presentation LSF
21/23
Contract No. PERRA/Shangla/30/2009Site Location Map
-
8/3/2019 Presentation LSF
22/23
Contract No. PERRA/Kohistan/28/2010Site Location Map
-
8/3/2019 Presentation LSF
23/23
THANK YOU