ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO PROYECTOS URBANOS Y CIVILES SA DE CV Concurso No. CI-CMOP-R33-039/2011 Obra: Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturale ANALISIS DE PRECIOS UNITARIOS Código Concepto Unidad P. Unitario Cantidad Importe Partida: 1 Análisis No.: Análisis: APO20011 M2 1,258.0700 $7,108.10 MATERIALES 302-CAL-0102 CALHIDRA, TONELADA TON $1,400.00 0.000328 $0.46 305-M3A-0101 PZA $25.13 0.016124 $0.41 303-ARF-0201 KG $12.60 0.007477 $0.09 301-ARE-0101 ARENA DE MINA M3 $125.00 0.000080 $0.01 GRAVA GRAVA DE MINA T.M.A. 9 MM Ø (3/8"), M3 M3 $182.00 0.000067 $0.01 358-AGU-0201 AGUA DE PIPA M3 $0.50 0.020000 $0.01 302-CEM-0102 TON $1,950.00 0.000013 $0.03 SUBTOTAL: MATERIALES $1.02 MANO DE OBRA 1T2E-U CUADRILLA No. 75 (1 TOPOGRAFO + 2 AY ESP) JOR $645.40 0.001709 $1.10 1A5P CUADRILLA No 22 (1 ALBAÑIL + 5 PEONES) JOR $1,198.98 0.000009 $0.01 SUBTOTAL: MANO DE OBRA $1.11 EQUIPO Y HERRAMIENTA EQEST ESTACION TOTAL STS5R DE 5" DE PREC ANGUL HOR $75.01 0.033329 $2.50 EQREV REVOLVEDORA P/CONCRETO DE 1 SACO 8 DE HP HOR $18.88 0.000571 $0.01 SUBTOTAL: EQUIPO Y HERRAMIENTA $2.51 TIPO 5 %MO1 HERRAMIENTA MENOR % $1.11 0.030000 $0.03 SUBTOTAL: TIPO 5 $0.03 TIPO 6 %MO5 EQUIPO DE SEGURIDAD % $1.11 0.030000 $0.03 SUBTOTAL: TIPO 6 $0.03 COSTO DIRECTO $4.70 % DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.23 % DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.24 SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $5.17 % DE COSTO DE FINANCIAMIENTO 0.0000% $0.00 SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $5.17 % DE COSTO DE UTILIDAD 9.1667% $0.47 SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $5.64 % DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 1.12 $0.01 TOTAL DEL PRECIO UNITARIO $5.65 (* CINCO PESOS 65/100 M.N. *) CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS TRAZO Y NIVELACION DE VIALIDAD CON EQUIPO TOPOGRAFICO DE PRECISION, EL PRECIO INCLUYE: MANO DE OBRA ESPECIALIZADA, EQUIPO, MATERIALES Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION PUOT (EL PRECIO SE PAGA UNA SOLA VEZ PARA TODA LA OBRA) DUELA DE PINO DE 3a DE 3/4"x4"x8' ( 0.019x0.10x2.44 m) VARILLA R-42 DEL No. 3, (3/8" Ø), KG, 0.557 KG/M CEMENTO (GRIS) PORTLAND TIPO II PUZOLANICO, TONELADA

Transcript of Tarjetas de precios Unitarios Calle

Page 1: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

Partida: 1 Análisis No.:

Análisis: APO20011 M2 1,258.0700 $7,108.10

MATERIALES

302-CAL-0102 CALHIDRA, TONELADA TON $1,400.00 0.000328 $0.46

305-M3A-0101 PZA $25.13 0.016124 $0.41

303-ARF-0201 VARILLA R-42 DEL No. 3, (3/8" Ø), KG, 0.557 KG/M KG $12.60 0.007477 $0.09

301-ARE-0101 ARENA DE MINA M3 $125.00 0.000080 $0.01

GRAVA GRAVA DE MINA T.M.A. 9 MM Ø (3/8"), M3 M3 $182.00 0.000067 $0.01

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.020000 $0.01

302-CEM-0102 TON $1,950.00 0.000013 $0.03

SUBTOTAL: MATERIALES $1.02

MANO DE OBRA

1T2E-U CUADRILLA No. 75 (1 TOPOGRAFO + 2 AY ESP) JOR $645.40 0.001709 $1.10

1A5P CUADRILLA No 22 (1 ALBAÑIL + 5 PEONES) JOR $1,198.98 0.000009 $0.01

SUBTOTAL: MANO DE OBRA $1.11

EQUIPO Y HERRAMIENTA

EQEST ESTACION TOTAL STS5R DE 5" DE PREC ANGUL HOR $75.01 0.033329 $2.50

EQREV HOR $18.88 0.000571 $0.01

SUBTOTAL: EQUIPO Y HERRAMIENTA $2.51

TIPO 5

%MO1 HERRAMIENTA MENOR % $1.11 0.030000 $0.03

SUBTOTAL: TIPO 5 $0.03

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $1.11 0.030000 $0.03

SUBTOTAL: TIPO 6 $0.03

COSTO DIRECTO $4.70

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.23

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.24

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $5.17

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $5.17

% DE COSTO DE UTILIDAD 9.1667% $0.47

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $5.64

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 1.12 $0.01

TOTAL DEL PRECIO UNITARIO $5.65

(* CINCO PESOS 65/100 M.N. *)

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

TRAZO Y NIVELACION DE VIALIDAD CON EQUIPO TOPOGRAFICO DE PRECISION, EL PRECIO INCLUYE: MANO DE OBRA ESPECIALIZADA, EQUIPO, MATERIALES Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION PUOT (EL PRECIO SE PAGA UNA SOLA VEZ PARA TODA LA OBRA)

DUELA DE PINO DE 3a DE 3/4"x4"x8' ( 0.019x0.10x2.44 m)

CEMENTO (GRIS) PORTLAND TIPO II PUZOLANICO, TONELADA

REVOLVEDORA P/CONCRETO DE 1 SACO 8 DE HP

Page 2: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 1 Análisis No.:

Análisis: AP010001 PZA 1.0000 $1,994.54

MATERIALES

317-ALA-0104 PZA $510.10 2.000000 $1020.20

317-AAC-0108 KG $19.78 12.000000 $237.36

313-SOL-0101 KG $43.15 0.450000 $19.42

SUBTOTAL: MATERIALES $1276.98

MANO DE OBRA

1S2E CUADRILLA No 18 (1 SOLDADOR+2 AY.ESP.) JOR $600.18 0.600000 $360.11

SUBTOTAL: MANO DE OBRA $360.11

TIPO 5

%MO1 HERRAMIENTA MENOR % $360.11 0.030000 $10.80

SUBTOTAL: TIPO 5 $10.80

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $360.11 0.030000 $10.80

SUBTOTAL: TIPO 6 $10.80

COSTO DIRECTO $1,658.69

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $81.02

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $83.46

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $1,823.17

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $1,823.17

% DE COSTO DE UTILIDAD 9.1667% $167.12

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $1,990.29

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 360.11 $4.25

TOTAL DEL PRECIO UNITARIO $1,994.54

(* UN MIL NOVECIENTOS NOVENTA Y CUATRO PESOS 54/100 M.N. *)

SUMINISTRO Y COLOCACIÓN DE PROPAGANDA (LETRERO ESPECTACULAR) DE LA OBRA A BASE DE LÁMINA NEGRA CAL 16 DE 0.90 X 1.50 MTS., CON SOPORTES DE ÁNGULO DE FIERRO DE 1 1/2 " Y LEYENDA SEGÚN DISEÑO INCLUYE: HERRAMIENTA Y MANO DE OBRA

LAMINA NEGRA CAL.16 HOJA DE 1.22x2.44M (36.29 KG )

ANGULO DE ACERO DE 3/16" x 1 1/2" DE 2.68 KG/M

SOLDADURA ELECTRODO 7018 DE 5/32" (4 MM) DE DIAMETRO

Page 3: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: EXCA023-2 M3 1,003.2300 $10,965.30

EXCAVACION EN CAJA POR MEDIOS MECANICOS EN TERRENO TIPO I Y II CUALQUIER ZONA (CON MOTONIVELADORA)

EQUIPO Y HERRAMIENTA

EQMOTO MOTONIVELADORA CAT. 120 H DE 140 HP HOR $260.32 0.034957 $9.10

SUBTOTAL: EQUIPO Y HERRAMIENTA $9.10

COSTO DIRECTO $9.10

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.44

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.46

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $10.00

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $10.00

% DE COSTO DE UTILIDAD 9.1667% $0.92

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $10.92

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 1.05 $0.01

TOTAL DEL PRECIO UNITARIO $10.93

(* DIEZ PESOS 93/100 M.N. *)

Page 4: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: PAASO11 M2 1,258.0700 $27,815.93

COMPACTACION DE TERRENO NATURAL EN CAPAS DE 20 CMS DE ESPESOR POR MEDIOS MECANICOS

MATERIALES

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.180000 $0.09

SUBTOTAL: MATERIALES $0.09

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.039110 $7.51

SUBTOTAL: MANO DE OBRA $7.51

EQUIPO Y HERRAMIENTA

EQPIPA CAMION PIPA DE 9 M3 HOR $164.09 0.035000 $5.74

EQ815F COMPACTADOR DE TAMBOR DE PISONES 815F HOR $251.49 0.018000 $4.53

SUBTOTAL: EQUIPO Y HERRAMIENTA $10.27

TIPO 5

%MO1 HERRAMIENTA MENOR % $7.51 0.030000 $0.23

SUBTOTAL: TIPO 5 $0.23

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $7.51 0.030000 $0.23

SUBTOTAL: TIPO 6 $0.23

COSTO DIRECTO $18.33

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.90

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.92

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $20.15

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $20.15

% DE COSTO DE UTILIDAD 9.1667% $1.85

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $22.00

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 9.1 $0.11

TOTAL DEL PRECIO UNITARIO $22.11

(* VEINTIDOS PESOS 11/100 M.N. *)

Page 5: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: ACA090 M3 1,304.2000 $23,462.56

ACARREO EN CAMION DE MATERIAL MIXTO. PRIMER KILOMETRO, CARGA MECANICA

EQUIPO Y HERRAMIENTA

EQCAMION CAMION DE VOLTEO DE 7 M3 HOR $205.02 0.030000 $6.15

EQTRAXC CARGADOR SOBRE LLANTAS CAT 920 HOR $441.66 0.020000 $8.83

SUBTOTAL: EQUIPO Y HERRAMIENTA $14.98

COSTO DIRECTO $14.98

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.73

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.75

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $16.46

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $16.46

% DE COSTO DE UTILIDAD 9.1667% $1.51

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $17.97

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 1.5 $0.02

TOTAL DEL PRECIO UNITARIO $17.99

(* DIECISIETE PESOS 99/100 M.N. *)

Page 6: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: ACA091 M3/KM 18,258.8000 $69,383.44

ACARREO EN CAMION DE MATERIAL MIXTO. KILOMETRO SUBSECUENTE, ZONA URBANA

EQUIPO Y HERRAMIENTA

EQCAMION CAMION DE VOLTEO DE 7 M3 HOR $205.02 0.015404 $3.16

SUBTOTAL: EQUIPO Y HERRAMIENTA $3.16

COSTO DIRECTO $3.16

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.15

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.16

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $3.47

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $3.47

% DE COSTO DE UTILIDAD 9.1667% $0.32

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $3.79

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 0.46 $0.01

TOTAL DEL PRECIO UNITARIO $3.80

(* TRES PESOS 80/100 M.N. *)

Page 7: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: AP020131 M3 563.3800 $113,064.73

MATERIALES

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.180000 $0.09

TEPETATE TEPETATE PUESTO EN OBRA, M3 M3 $115.98 1.250000 $144.98

SUBTOTAL: MATERIALES $145.07

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.050000 $9.60

SUBTOTAL: MANO DE OBRA $9.60

EQUIPO Y HERRAMIENTA

EQPIPA CAMION PIPA DE 9 M3 HOR $164.09 0.010000 $1.64

EQ815F COMPACTADOR DE TAMBOR DE PISONES 815F HOR $251.49 0.018000 $4.53

EQMOTO MOTONIVELADORA CAT. 120 H DE 140 HP HOR $260.32 0.021997 $5.73

SUBTOTAL: EQUIPO Y HERRAMIENTA $11.90

TIPO 5

%MO1 HERRAMIENTA MENOR % $9.60 0.030000 $0.29

SUBTOTAL: TIPO 5 $0.29

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $9.60 0.030000 $0.29

SUBTOTAL: TIPO 6 $0.29

COSTO DIRECTO $167.15

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $8.16

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $8.41

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $183.72

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $183.72

% DE COSTO DE UTILIDAD 9.1667% $16.84

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $200.56

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 11.1 $0.13

TOTAL DEL PRECIO UNITARIO $200.69

(* DOSCIENTOS PESOS 69/100 M.N. *)

CONFORMACION Y COMPACTACION DE SUBRASANTE AL 95% PROCTOR CON MATERIAL DE BANCO, EMPLEANDO MAQUINARIA, INCLUYE: SUMINISTRO DE MATERIAL E INCORPORACION DE AGUA

Page 8: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: AP020027 M3 402.4200 $107,570.89

MATERIALES

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.180000 $0.09

365-AGR-0111 MATERIAL PARA BASE PUESTO EN OBRA M3 $185.98 1.090000 $202.72

SUBTOTAL: MATERIALES $202.81

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.039110 $7.51

SUBTOTAL: MANO DE OBRA $7.51

EQUIPO Y HERRAMIENTA

EQPIPA CAMION PIPA DE 9 M3 HOR $164.09 0.010000 $1.64

EQ815F COMPACTADOR DE TAMBOR DE PISONES 815F HOR $251.49 0.018000 $4.53

EQMOTO MOTONIVELADORA CAT. 120 H DE 140 HP HOR $260.32 0.021997 $5.73

SUBTOTAL: EQUIPO Y HERRAMIENTA $11.90

TIPO 5

%MO1 HERRAMIENTA MENOR % $7.51 0.030000 $0.23

SUBTOTAL: TIPO 5 $0.23

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $7.51 0.030000 $0.23

SUBTOTAL: TIPO 6 $0.23

COSTO DIRECTO $222.68

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $10.88

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $11.20

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $244.76

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $244.76

% DE COSTO DE UTILIDAD 9.1667% $22.44

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $267.20

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 9.01 $0.11

TOTAL DEL PRECIO UNITARIO $267.31

(* DOSCIENTOS SESENTA Y SIETE PESOS 31/100 M.N. *)

OPERACIÓN DE MEZCLADO, TENDIDO Y COMPACTACIÓN EN LA CONSTRUCCIÓN DE BASES (INCISO 074-H.01): B) BASES: 1) CUANDO SE EMPLEE UN (1) MATERIAL PETREO: 1) COMPACTADO AL 95% INCLUYE SUMINSTROS DE "BASE HIDRAULICA", AGUA Y ACARREOS HASTA 30 KMS

Page 9: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: PAAS022 M2 1,258.0700 $503.23

BARRIDO A MANO DE LA SUPERFICIE A TRATAR.

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.001592 $0.31

SUBTOTAL: MANO DE OBRA $0.31

TIPO 5

%MO1 HERRAMIENTA MENOR % $0.31 0.030000 $0.01

SUBTOTAL: TIPO 5 $0.01

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $0.31 0.030000 $0.01

SUBTOTAL: TIPO 6 $0.01

COSTO DIRECTO $0.33

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.02

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.02

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $0.37

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $0.37

% DE COSTO DE UTILIDAD 9.1667% $0.03

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $0.40

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 0.31 $0.00

TOTAL DEL PRECIO UNITARIO $0.40

(* PESOS 40/100 M.N. *)

Page 10: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: AP020040 LT 1,887.1100 $16,266.89

MATERIALES

365-ASF-0108 EMULSION ASFALTICA CATIONICA ECI -45 LT $6.70 0.600000 $4.02

SUBTOTAL: MATERIALES $4.02

EQUIPO Y HERRAMIENTA

EQPETRO CAMION PETROLIZADORA DE 1105 GALONES HOR $347.41 0.009084 $3.16

SUBTOTAL: EQUIPO Y HERRAMIENTA $3.16

COSTO DIRECTO $7.18

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.35

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.36

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $7.89

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $7.89

% DE COSTO DE UTILIDAD 9.1667% $0.72

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $8.61

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 0.46 $0.01

TOTAL DEL PRECIO UNITARIO $8.62

(* OCHO PESOS 62/100 M.N. *)

RIEGO ASFALTICO DE IMPREGNACION CON EMULSION ASFALTICA CATIONICA DE ROMPIMIENTO LENTO ECI-45 A RAZON DE 1.5 LTS/M2, INCLUYE ACARREOS DE 30 KM.

Page 11: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: PIADC007 M2 1,258.0700 $2,818.08

POREO CON ARENA PARA PROTECCION DE EMULSION

MATERIALES

301-ARE-0101 ARENA DE MINA M3 $125.00 0.007000 $0.88

SUBTOTAL: MATERIALES $0.88

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.004777 $0.92

SUBTOTAL: MANO DE OBRA $0.92

TIPO 5

%MO1 HERRAMIENTA MENOR % $0.92 0.030000 $0.03

SUBTOTAL: TIPO 5 $0.03

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $0.92 0.030000 $0.03

SUBTOTAL: TIPO 6 $0.03

COSTO DIRECTO $1.86

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.09

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.09

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $2.04

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $2.04

% DE COSTO DE UTILIDAD 9.1667% $0.19

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $2.23

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 0.92 $0.01

TOTAL DEL PRECIO UNITARIO $2.24

(* DOS PESOS 24/100 M.N. *)

Page 12: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: AP020041 LT 754.8400 $6,506.72

MATERIALES

365-ASF-0108 EMULSION ASFALTICA CATIONICA ECI -45 LT $6.70 0.600000 $4.02

SUBTOTAL: MATERIALES $4.02

EQUIPO Y HERRAMIENTA

EQPETRO CAMION PETROLIZADORA DE 1105 GALONES HOR $347.41 0.009084 $3.16

SUBTOTAL: EQUIPO Y HERRAMIENTA $3.16

COSTO DIRECTO $7.18

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.35

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.36

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $7.89

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $7.89

% DE COSTO DE UTILIDAD 9.1667% $0.72

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $8.61

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 0.46 $0.01

TOTAL DEL PRECIO UNITARIO $8.62

(* OCHO PESOS 62/100 M.N. *)

RIEGO DE LIGA CON EMULSION ASFALTICA TIPO ECR-65 A RAZON DE 0.5 A 0.7 LT/M2, INCLUYE BARRIDO DE SUPERFICE SUMINISTRO DE MATERIALES, MANO DE OBRA, ACARREOS, (P.U.O.T.)

Page 13: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: AP020010 M2 1,258.0700 $257,879.19

MATERIALES

365-ASF-0102 MEZCLA ASFALTICA M3 $2,312.00 0.065000 $150.28

SUBTOTAL: MATERIALES $150.28

MANO DE OBRA

2A CUADRILLA No 4 (2 AYUDANTE GENERAL) JOR $384.61 0.027461 $10.56

SUBTOTAL: MANO DE OBRA $10.56

EQUIPO Y HERRAMIENTA

EQCAMION CAMION DE VOLTEO DE 7 M3 HOR $205.02 0.012874 $2.64

EQ815F COMPACTADOR DE TAMBOR DE PISONES 815F HOR $251.49 0.012874 $3.24

EQMOTO MOTONIVELADORA CAT. 120 H DE 140 HP HOR $260.32 0.012874 $3.35

SUBTOTAL: EQUIPO Y HERRAMIENTA $9.23

TIPO 5

%MO1 HERRAMIENTA MENOR % $10.56 0.030000 $0.32

SUBTOTAL: TIPO 5 $0.32

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $10.56 0.030000 $0.32

SUBTOTAL: TIPO 6 $0.32

COSTO DIRECTO $170.71

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $8.34

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $8.59

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $187.64

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $187.64

% DE COSTO DE UTILIDAD 9.1667% $17.20

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $204.84

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 11.73 $0.14

TOTAL DEL PRECIO UNITARIO $204.98

(* DOSCIENTOS CUATRO PESOS 98/100 M.N. *)

CARPETA DE CONCRETO ASFALTICO MODIFICADA DE 5 CM DE ESPESOR COMPACTADO AL 95%. (NO INCLUYE RIEGOS) INCLUYE: ACARREOS, NORMA SCT (INCISO 081-H.01)

Page 14: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 2 Análisis No.:

Análisis: DENT001 M 11.3300 $1,967.45

MATERIALES

303-ARF-1101 KG $15.50 0.050000 $0.78

305-M3A-0503 PZA $413.79 0.134300 $55.57

305-M3A-0101 PZA $25.13 0.146000 $3.67

305-M3A-0201 BARROTE DE PINO DE 3a, DE 1 1/2"x3 1/2"x8' PZA $36.21 0.229000 $8.29

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.005000 $0.00

359-CMB-0101 DIESEL LT $8.46 0.180000 $1.52

301-ARE-0101 ARENA DE MINA M3 $125.00 0.033000 $4.13

302-CEM-0102 TON $1,950.00 0.015600 $30.42

GRAVA GRAVA DE MINA T.M.A. 9 MM Ø (3/8"), M3 M3 $182.00 0.039000 $7.10

SUBTOTAL: MATERIALES $111.48

MANO DE OBRA

1A1P CUADRILLA No 5 (1 ALBAÑIL+1 PEON) JOR $431.36 0.037040 $15.98

1A5P CUADRILLA No 22 (1 ALBAÑIL + 5 PEONES) JOR $1,198.98 0.005000 $5.99

SUBTOTAL: MANO DE OBRA $21.97

EQUIPO Y HERRAMIENTA

EQREV HOR $18.88 0.030000 $0.57

EQVIB VIBRADOR PARA CONCRETO HOR $18.22 0.500000 $9.11

SUBTOTAL: EQUIPO Y HERRAMIENTA $9.68

TIPO 5

%MO1 HERRAMIENTA MENOR % $21.97 0.030000 $0.66

SUBTOTAL: TIPO 5 $0.66

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $21.97 0.030000 $0.66

SUBTOTAL: TIPO 6 $0.66

COSTO DIRECTO $144.45

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $7.06

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $7.27

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $158.78

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $158.78

% DE COSTO DE UTILIDAD 9.1667% $14.55

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $173.33

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 27.19 $0.32

TOTAL DEL PRECIO UNITARIO $173.65

(* CIENTO SETENTA Y TRES PESOS 65/100 M.N. *)

CONSTRUCCION DE DENTELLON TRANVERSAL PARA CONFINAMIENTO DE ADOQUIN O CONCRETO. A BASE DE CONCRETO SIMPLE F´c=150 KG/CM² CON UNA SECCION DE 15 x 40 CM. A CADA 8.00 M. INCLUYE: EXCAVACION, CIMBRA, ACARREO DEL MATERIAL SOBRANTE HASTA 20 MTS.

ALAMBRE RECOCIDO CAL. 16, (1.59 mm Ø), KG, 0.016 KG/M

TRIPLAY DE PINO P/CIMBRA DE 16 MM, HOJA DE 1.22x2.44 M.

DUELA DE PINO DE 3a DE 3/4"x4"x8' ( 0.019x0.10x2.44 m)

CEMENTO (GRIS) PORTLAND TIPO II PUZOLANICO, TONELADA

REVOLVEDORA P/CONCRETO DE 1 SACO 8 DE HP

Page 15: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 3 Análisis No.:

Análisis: APO30021 PZA 3.0000 $2,891.64

MATERIALES

310-TAB-0202 TABIQUE ROJO RECOCIDO DE 6x13x26 CM. MIL $1,590.00 0.250000 $397.50

302-CEM-0102 TON $1,950.00 0.020000 $39.00

301-ARE-0101 ARENA DE MINA M3 $125.00 0.048800 $6.10

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.012000 $0.01

SUBTOTAL: MATERIALES $442.61

MANO DE OBRA

1A1P CUADRILLA No 5 (1 ALBAÑIL+1 PEON) JOR $431.36 0.781602 $337.15

SUBTOTAL: MANO DE OBRA $337.15

TIPO 5

%MO1 HERRAMIENTA MENOR % $337.15 0.030000 $10.11

SUBTOTAL: TIPO 5 $10.11

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $337.15 0.030000 $10.11

SUBTOTAL: TIPO 6 $10.11

COSTO DIRECTO $799.98

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $39.07

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $40.25

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $879.30

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $879.30

% DE COSTO DE UTILIDAD 9.1667% $80.60

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $959.90

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 337.15 $3.98

TOTAL DEL PRECIO UNITARIO $963.88

(* NOVECIENTOS SESENTA Y TRES PESOS 88/100 M.N. *)

RENIVELACION DE POZO DE VISITA HASTA 50 CMS. CON TABIQUE ROJO COMUN INCLUYE REPELLADO ACABADO PULIDO, MATERIAL MANO DE OBRA HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION

CEMENTO (GRIS) PORTLAND TIPO II PUZOLANICO, TONELADA

Page 16: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 3 Análisis No.:

Análisis: APO30022 PZA 3.0000 $3,586.44

SUMINISTRO Y COLOCACION DE BROCAL Y TAPA DE CONCRETO, CON MORTERO DE CEMENTO-ARENA DE 1:4.

MATERIALES

309-BRO-0101 BROCAL P/POZO DE VISITA CON TAPA PZA $882.37 1.000000 $882.37

301-ARE-0101 ARENA DE MINA M3 $125.00 0.043200 $5.40

302-CEM-0102 TON $1,950.00 0.014400 $28.08

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.010800 $0.01

SUBTOTAL: MATERIALES $915.86

MANO DE OBRA

1A1P CUADRILLA No 5 (1 ALBAÑIL+1 PEON) JOR $431.36 0.174282 $75.18

SUBTOTAL: MANO DE OBRA $75.18

TIPO 5

%MO1 HERRAMIENTA MENOR % $75.18 0.030000 $2.26

SUBTOTAL: TIPO 5 $2.26

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $75.18 0.030000 $2.26

SUBTOTAL: TIPO 6 $2.26

COSTO DIRECTO $995.56

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $48.63

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $50.09

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $1,094.28

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $1,094.28

% DE COSTO DE UTILIDAD 9.1667% $100.31

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $1,194.59

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 75.18 $0.89

TOTAL DEL PRECIO UNITARIO $1,195.48

(* UN MIL CIENTO NOVENTA Y CINCO PESOS 48/100 M.N. *)

CEMENTO (GRIS) PORTLAND TIPO II PUZOLANICO, TONELADA

Page 17: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 3 Análisis No.:

Análisis: APO30001 PZA 28.0000 $14,449.12

MATERIALES

346-PHD-1103 PZA $39.41 1.000000 $39.41

339-DIC-0693 CINTA TEFLON (3/4x260") 4111.3 DICA PZA $5.20 1.000000 $5.20

346-PHD-1510 POLIDUCTO 19 MM M $12.15 15.000000 $182.25

SUBTOTAL: MATERIALES $226.86

MANO DE OBRA

1P1E CUADRILLA No 20 (1 PLOMERO+ 1 AY.ESP.) JOR $432.56 0.439106 $189.94

SUBTOTAL: MANO DE OBRA $189.94

TIPO 5

%MO1 HERRAMIENTA MENOR % $189.94 0.030000 $5.70

SUBTOTAL: TIPO 5 $5.70

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $189.94 0.030000 $5.70

SUBTOTAL: TIPO 6 $5.70

COSTO DIRECTO $428.20

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $20.92

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $21.54

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $470.66

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $470.66

% DE COSTO DE UTILIDAD 9.1667% $43.14

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $513.80

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 189.94 $2.24

TOTAL DEL PRECIO UNITARIO $516.04

(* QUINIENTOS DIECISEIS PESOS 04/100 M.N. *)

REPARACION DE TOMAS DOMICILIARIAS EXCAVACION, DESALOJO, RELLENO, COMPACTADO, CON MATERIAL DE TERRACERIA INCLUYE: TODO EL MATERIAL DE REPARACION, MANO DE OBRA Y HERRAMIENTA

ABRAZADERA PVC P/TOMA SAL ROSC 60x13 DURALON

Page 18: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 3 Análisis No.:

Análisis: APO300221 PZA 28.0000 $8,845.76

MATERIALES

100354 SLANT DE CONCRETO DE 20 CM PZA $44.00 1.050000 $46.20

301-ARE-0101 ARENA DE MINA M3 $125.00 0.020000 $2.50

302-CEM-0102 TON $1,950.00 0.010560 $20.59

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.020000 $0.01

SUBTOTAL: MATERIALES $69.30

MANO DE OBRA

1A2P CUADRILLA 3 (1 ALBAÑIL + 2 PEONES) JOR $597.87 0.303283 $181.32

SUBTOTAL: MANO DE OBRA $181.32

TIPO 5

%MO1 HERRAMIENTA MENOR % $181.32 0.030000 $5.44

SUBTOTAL: TIPO 5 $5.44

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $181.32 0.030000 $5.44

SUBTOTAL: TIPO 6 $5.44

COSTO DIRECTO $261.50

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $12.77

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $13.16

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $287.43

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $287.43

% DE COSTO DE UTILIDAD 9.1667% $26.35

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $313.78

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 181.32 $2.14

TOTAL DEL PRECIO UNITARIO $315.92

(* TRESCIENTOS QUINCE PESOS 92/100 M.N. *)

REPARACION DE DESCARGA DOMICILIARIA, EXCAVACION, DESALOJO DE AGUA, RELLENO COMPACTADO, CON MATERIAL DE TERRACERIA, INCLUYE: TODO EL MATERIAL DE

CEMENTO (GRIS) PORTLAND TIPO II PUZOLANICO, TONELADA

Page 19: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 3 Análisis No.:

Análisis: TOMA01-1 PZA. 28.0000 $26,801.04

MATERIALES

346-URR-3708 LLAVE NARIZ FIG.18N DE 13 SIN PULIR URREA PZA $78.28 1.000000 $78.28

346-PHD-1103 PZA $39.41 1.000000 $39.41

318-GAR-0003 ABRAZADERA S/FIN REF. R-12 17 A 32 MM. PZA $5.69 1.000000 $5.69

346-PHD-2701 PZA $22.70 1.000000 $22.70

339-DIC-0693 CINTA TEFLON (3/4x260") 4111.3 DICA PZA $5.20 1.000000 $5.20

346-PHD-1510 POLIDUCTO 19 MM M $12.15 15.000000 $182.25

346-PHD-1687 LLAVE DE CUADRO CON ROSCA DE 19 MM PZA $92.90 1.000000 $92.90

346-PHD1746 TUBO DE FoGo DE 19 MM M $44.53 1.000000 $44.53

346-PHD-1867 CODO DE FoGo DE 19 MM PZA $9.87 4.000000 $39.48

SUBTOTAL: MATERIALES $510.44

MANO DE OBRA

1P1E CUADRILLA No 20 (1 PLOMERO+ 1 AY.ESP.) JOR $432.56 0.620749 $268.51

SUBTOTAL: MANO DE OBRA $268.51

TIPO 5

%MO1 HERRAMIENTA MENOR % $268.51 0.030000 $8.06

SUBTOTAL: TIPO 5 $8.06

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $268.51 0.030000 $8.06

SUBTOTAL: TIPO 6 $8.06

COSTO DIRECTO $795.07

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $38.83

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $40.00

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $873.90

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $873.90

% DE COSTO DE UTILIDAD 9.1667% $80.11

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $954.01

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 268.51 $3.17

TOTAL DEL PRECIO UNITARIO $957.18

(* NOVECIENTOS CINCUENTA Y SIETE PESOS 18/100 M.N. *)

TOMA DOMICILIARIA DE POLIETILENO DE ALTA DENSIDAD Y Fo. Go. A UNA DISTANCIA DE 15 M. INCLUYE: EXCAVACION, RELLENO, ABRAZADERA DE P.V.C. 2 1/2" X 3/4", ADAPTADOR DE INSERCION EN BRONCE, ABRAZADERA DEL No. 12, POLIDUCTO DE 3/4" H.D.P., LLAVE DE CUADRO CON ROSCA PARA CONEXION GALVANIZADA, CODOS DE Fo.Go. DE 3/4", TUBO DE Fo.Go. DE 3/4" Y LLAVE DE NARIZ DE 3/4".

ABRAZADERA PVC P/TOMA SAL ROSC 60x13 DURALON

ADAPTADOR ESPIGA HIDRAULICO ANGER SI 38 MM DURALON

Page 20: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 3 Análisis No.:

Análisis: AP030003 PZA 28.0000 $30,999.64

MATERIALES

309-TUB-0103 TUBO DE CONCRETO SIMPLE DE 8" 20 CM. PZA $37.00 7.000000 $259.00

100174 CODO DE CONCRETO DE 20x45 GRADOS PZA $45.00 1.050000 $47.25

100354 SLANT DE CONCRETO DE 20 CM PZA $44.00 1.050000 $46.20

301-ARE-0101 ARENA DE MINA M3 $125.00 0.020000 $2.50

302-CEM-0102 TON $1,950.00 0.010560 $20.59

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.020000 $0.01

SUBTOTAL: MATERIALES $375.55

MANO DE OBRA

1A2P CUADRILLA 3 (1 ALBAÑIL + 2 PEONES) JOR $597.87 0.855410 $511.42

SUBTOTAL: MANO DE OBRA $511.42

TIPO 5

%MO1 HERRAMIENTA MENOR % $511.42 0.030000 $15.34

SUBTOTAL: TIPO 5 $15.34

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $511.42 0.030000 $15.34

SUBTOTAL: TIPO 6 $15.34

COSTO DIRECTO $917.65

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $44.82

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $46.17

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $1,008.64

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $1,008.64

% DE COSTO DE UTILIDAD 9.1667% $92.46

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $1,101.10

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 511.42 $6.03

TOTAL DEL PRECIO UNITARIO $1,107.13

(* UN MIL CIENTO SIETE PESOS 13/100 M.N. *)

DESCARGA DOMICILIARIA CON 7MTS DE TUBO DE CONCRETO SIMPLE DE 20 CM DE DIAMETRO, JUNTEADO CON MORTERO CEMENTO-ARENA 1:3, CODO Y SLANT, INCLUYE; EXCAVACIÓN A MANO, SUMINISTROS, ACARREOS, RELLENO, MANO DE OBRA Y HERRAMIENTA.

CEMENTO (GRIS) PORTLAND TIPO II PUZOLANICO, TONELADA

Page 21: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 3 Análisis No.:

Análisis: LIM005 M2 1,258.0700 $11,146.50

LIMPIEZA GENERAL DURANTE LA OBRA INCLUYE ACARREOS DE ESCOMBROS, ETC.

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.025670 $4.93

SUBTOTAL: MANO DE OBRA $4.93

EQUIPO Y HERRAMIENTA

EQCAMION CAMION DE VOLTEO DE 7 M3 HOR $205.02 0.010260 $2.10

SUBTOTAL: EQUIPO Y HERRAMIENTA $2.10

TIPO 5

%MO1 HERRAMIENTA MENOR % $4.93 0.030000 $0.15

SUBTOTAL: TIPO 5 $0.15

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $4.93 0.030000 $0.15

SUBTOTAL: TIPO 6 $0.15

COSTO DIRECTO $7.33

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.36

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.37

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $8.06

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $8.06

% DE COSTO DE UTILIDAD 9.1667% $0.74

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $8.80

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 5.24 $0.06

TOTAL DEL PRECIO UNITARIO $8.86

(* OCHO PESOS 86/100 M.N. *)

Page 22: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 4 Análisis No.:

Análisis: PINT068 ML 304.4200 $6,867.72

MATERIALES

337-PTF-2301 SOLVENTE 6032 CUBETA $440.00 0.005000 $2.20

337-PTF-2302 CUBETA $1,646.55 0.008000 $13.17

SUBTOTAL: MATERIALES $15.37

MANO DE OBRA

1P1A CUADRILLA No 8 (1 PINTOR + AYUDANTE) JOR $431.76 0.007421 $3.20

SUBTOTAL: MANO DE OBRA $3.20

TIPO 5

%MO1 HERRAMIENTA MENOR % $3.20 0.030000 $0.10

SUBTOTAL: TIPO 5 $0.10

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $3.20 0.030000 $0.10

SUBTOTAL: TIPO 6 $0.10

COSTO DIRECTO $18.77

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.92

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.94

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $20.63

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $20.63

% DE COSTO DE UTILIDAD 9.1667% $1.89

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $22.52

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 3.2 $0.04

TOTAL DEL PRECIO UNITARIO $22.56

(* VEINTIDOS PESOS 56/100 M.N. *)

SUMINISTRO Y APLICACION DE PINTURA TIPO TRAFICO MCA. COMEX COLOR AMARILLO EN GUARNICIONES DE 35 CM. DE DESARROLLO. INCLUYE LIMPIEZA Y DESPERDICIOS. MATERIALES, MANO DE OBRA Y HERRAMIENTA.

PINTURA PARA TRAFICO BASE SOLVENTE, PT-355 VIA, (6853) AMARILLO

Page 23: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 4 Análisis No.:

Análisis: PAAS025 M 148.2500 $1,237.89

LINEA BLANCA DE 10 CM DE ANCHO HECHA A MANO PINTURA TIPO TRANSITO MCA. COMEX COLOR BLANCO.

MATERIALES

337-PTF-2301 SOLVENTE 6032 CUBETA $440.00 0.005000 $2.20

337-PTF-2303 CUBETA $1,646.55 0.001000 $1.65

SUBTOTAL: MATERIALES $3.85

MANO DE OBRA

1P1A CUADRILLA No 8 (1 PINTOR + AYUDANTE) JOR $431.76 0.006714 $2.90

SUBTOTAL: MANO DE OBRA $2.90

TIPO 5

%MO1 HERRAMIENTA MENOR % $2.90 0.030000 $0.09

SUBTOTAL: TIPO 5 $0.09

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $2.90 0.030000 $0.09

SUBTOTAL: TIPO 6 $0.09

COSTO DIRECTO $6.93

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.34

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.35

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $7.62

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $7.62

% DE COSTO DE UTILIDAD 9.1667% $0.70

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $8.32

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 2.9 $0.03

TOTAL DEL PRECIO UNITARIO $8.35

(* OCHO PESOS 35/100 M.N. *)

PINTURA PARA TRAFICO BASE SOLVENTE, PT-355 VIA, (6851) BLANCO

Page 24: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 4 Análisis No.:

Análisis: AP060001 M 3.8100 $166.80

MATERIALES

337-PTF-2301 SOLVENTE 6032 CUBETA $440.00 0.014316 $6.30

337-PTF-2303 CUBETA $1,646.55 0.014316 $23.57

SUBTOTAL: MATERIALES $29.87

MANO DE OBRA

1P1A CUADRILLA No 8 (1 PINTOR + AYUDANTE) JOR $431.76 0.014316 $6.18

SUBTOTAL: MANO DE OBRA $6.18

TIPO 5

%MO1 HERRAMIENTA MENOR % $6.18 0.030000 $0.19

SUBTOTAL: TIPO 5 $0.19

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $6.18 0.030000 $0.19

SUBTOTAL: TIPO 6 $0.19

COSTO DIRECTO $36.43

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $1.78

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $1.83

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $40.04

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $40.04

% DE COSTO DE UTILIDAD 9.1667% $3.67

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $43.71

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 6.18 $0.07

TOTAL DEL PRECIO UNITARIO $43.78

(* CUARENTA Y TRES PESOS 78/100 M.N. *)

RAYA DE ALTO TIPO M-6 DE 30 CM DE ANCHO, UBICADA EN INTERSECCIONES INCLUYE: SUMINISTRO Y APLICACIÓN DE PINTURA COLOR BLANCO SEGÚN EL PATRON DEL COLOR DE MANUAL DE DISPOSITIVOS PARA EL CONTROL DEL TRANSITO DE LA SCT Y TODO LO NECESARIO PARA SU CORRECTA EJECUCIÓN

PINTURA PARA TRAFICO BASE SOLVENTE, PT-355 VIA, (6851) BLANCO

Page 25: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 4 Análisis No.:

Análisis: PAAS023 M 18.0000 $975.60

RAYA PARA CRUCE PEATONAL DE 60 CM. DE ANCHO CON PINTURA TIPO TRANSITO MCA. COMEX COLOR AMARILLO.

MATERIALES

337-PTF-2301 SOLVENTE 6032 CUBETA $440.00 0.017726 $7.80

337-PTF-2302 CUBETA $1,646.55 0.017726 $29.19

SUBTOTAL: MATERIALES $36.99

MANO DE OBRA

1P1A CUADRILLA No 8 (1 PINTOR + AYUDANTE) JOR $431.76 0.017726 $7.65

SUBTOTAL: MANO DE OBRA $7.65

TIPO 5

%MO1 HERRAMIENTA MENOR % $7.65 0.030000 $0.23

SUBTOTAL: TIPO 5 $0.23

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $7.65 0.030000 $0.23

SUBTOTAL: TIPO 6 $0.23

COSTO DIRECTO $45.10

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $2.20

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $2.27

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $49.57

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $49.57

% DE COSTO DE UTILIDAD 9.1667% $4.54

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $54.11

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 7.65 $0.09

TOTAL DEL PRECIO UNITARIO $54.20

(* CINCUENTA Y CUATRO PESOS 20/100 M.N. *)

PINTURA PARA TRAFICO BASE SOLVENTE, PT-355 VIA, (6853) AMARILLO

Page 26: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 4 Análisis No.:

Análisis: 090-C.02E PZA 2.0000 $2,553.26

SEÑAL DE INFORMACION GENERAL SIG-11 DE 0.35 X 1.17

MATERIALES

375-MOU-0213 LAMINA GALVANIZADA CALIBRE 16 M2 $1,065.98 0.500000 $532.99

375-MOU-0214 M2 $584.12 0.500000 $292.06

318-GAR-0920 TORNILLO HEXAGONAL CON TUERCA 6 x 64 MM. MIL $540.00 0.100000 $54.00

SUBTOTAL: MATERIALES $879.05

MANO DE OBRA

1CO1A CUADRILLA No. 12 (1 COLOCADOR + 1 AY.) JOR $432.04 0.400000 $172.82

SUBTOTAL: MANO DE OBRA $172.82

TIPO 5

%MO1 HERRAMIENTA MENOR % $172.82 0.030000 $5.18

SUBTOTAL: TIPO 5 $5.18

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $172.82 0.030000 $5.18

SUBTOTAL: TIPO 6 $5.18

COSTO DIRECTO $1,062.23

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $51.88

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $53.45

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $1,167.56

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $1,167.56

% DE COSTO DE UTILIDAD 9.1667% $107.03

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $1,274.59

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 172.82 $2.04

TOTAL DEL PRECIO UNITARIO $1,276.63

(* UN MIL DOSCIENTOS SETENTA Y SEIS PESOS 63/100 M.N. *)

PELICULA REFLEJANTE GRADO INGENIERIA IMPRESA EN VINIL

Page 27: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 4 Análisis No.:

Análisis: 090-C.03B PZA 1.0000 $1,726.18

SEÑAL DE INFORMATIVA DE IDENTIFICACION SII-6 DE 0.30 X 1.20 DOBLE BANDERA

MATERIALES

375-MOU-0161 PZA $600.00 1.000000 $600.00

375-MOU-0213 LAMINA GALVANIZADA CALIBRE 16 M2 $1,065.98 0.469052 $500.00

375-MOU-0214 M2 $584.12 0.427994 $250.00

318-GAR-0920 TORNILLO HEXAGONAL CON TUERCA 6 x 64 MM. MIL $540.00 0.003000 $1.62

SUBTOTAL: MATERIALES $1351.62

MANO DE OBRA

1CO1A CUADRILLA No. 12 (1 COLOCADOR + 1 AY.) JOR $432.04 0.188120 $81.28

SUBTOTAL: MANO DE OBRA $81.28

TIPO 5

%MO1 HERRAMIENTA MENOR % $81.28 0.030000 $2.44

SUBTOTAL: TIPO 5 $2.44

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $81.28 0.030000 $2.44

SUBTOTAL: TIPO 6 $2.44

COSTO DIRECTO $1,437.78

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $70.23

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $72.34

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $1,580.35

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $1,580.35

% DE COSTO DE UTILIDAD 9.1667% $144.87

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $1,725.22

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 81.28 $0.96

TOTAL DEL PRECIO UNITARIO $1,726.18

(* UN MIL SETECIENTOS VEINTISEIS PESOS 18/100 M.N. *)

PEDESTAL GALVANIZADO PARA SEÑAL DE LAMINA DE 2"x3 M

PELICULA REFLEJANTE GRADO INGENIERIA IMPRESA EN VINIL

Page 28: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: 1005 01 M2 121.7700 $770.80

LIMPIA TRAZO Y NIVELACION EN EL AREA DE TRABAJO.

MATERIALES

302-CAL-0102 CALHIDRA, TONELADA TON $1,400.00 0.000328 $0.46

305-M3A-0101 PZA $25.13 0.016124 $0.41

303-ARF-0201 VARILLA R-42 DEL No. 3, (3/8" Ø), KG, 0.557 KG/M KG $12.60 0.007477 $0.09

301-ARE-0101 ARENA DE MINA M3 $125.00 0.000160 $0.02

GRAVA GRAVA DE MINA T.M.A. 9 MM Ø (3/8"), M3 M3 $182.00 0.000110 $0.02

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.040000 $0.02

302-CEM-0102 TON $1,950.00 0.000013 $0.03

SUBTOTAL: MATERIALES $1.05

MANO DE OBRA

1T2E-U CUADRILLA No. 75 (1 TOPOGRAFO + 2 AY ESP) JOR $645.40 0.001709 $1.10

1A5P CUADRILLA No 22 (1 ALBAÑIL + 5 PEONES) JOR $1,198.98 0.000417 $0.50

SUBTOTAL: MANO DE OBRA $1.60

EQUIPO Y HERRAMIENTA

EQEST ESTACION TOTAL STS5R DE 5" DE PREC ANGUL HOR $75.01 0.033329 $2.50

EQREV HOR $18.88 0.000571 $0.01

SUBTOTAL: EQUIPO Y HERRAMIENTA $2.51

TIPO 5

%MO1 HERRAMIENTA MENOR % $1.60 0.030000 $0.05

SUBTOTAL: TIPO 5 $0.05

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $1.60 0.030000 $0.05

SUBTOTAL: TIPO 6 $0.05

COSTO DIRECTO $5.26

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.26

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.26

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $5.78

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $5.78

% DE COSTO DE UTILIDAD 9.1667% $0.53

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $6.31

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 1.61 $0.02

TOTAL DEL PRECIO UNITARIO $6.33

(* SEIS PESOS 33/100 M.N. *)

DUELA DE PINO DE 3a DE 3/4"x4"x8' ( 0.019x0.10x2.44 m)

CEMENTO (GRIS) PORTLAND TIPO II PUZOLANICO, TONELADA

REVOLVEDORA P/CONCRETO DE 1 SACO 8 DE HP

Page 29: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: DEM006 M3 25.1100 $6,186.35

DEMOLICION A MANO DE CONCRETO SIMPLE EN GUARNICIONES.

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 1.000000 $191.91

SUBTOTAL: MANO DE OBRA $191.91

TIPO 5

%MO1 HERRAMIENTA MENOR % $191.91 0.030000 $5.76

SUBTOTAL: TIPO 5 $5.76

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $191.91 0.030000 $5.76

SUBTOTAL: TIPO 6 $5.76

COSTO DIRECTO $203.43

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $9.94

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $10.24

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $223.61

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $223.61

% DE COSTO DE UTILIDAD 9.1667% $20.50

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $244.11

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 191.91 $2.26

TOTAL DEL PRECIO UNITARIO $246.37

(* DOSCIENTOS CUARENTA Y SEIS PESOS 37/100 M.N. *)

Page 30: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: 1010 02 M3 73.0600 $4,407.71

EXCAVACIÒN A MANO EN ZANJA, MATERIAL COMÙN SECO, CUALQUIER ZONA, PROFUNDIDAD DE 0.00 A 2.00 MTS.

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.244906 $47.00

SUBTOTAL: MANO DE OBRA $47.00

TIPO 5

%MO1 HERRAMIENTA MENOR % $47.00 0.030000 $1.41

SUBTOTAL: TIPO 5 $1.41

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $47.00 0.030000 $1.41

SUBTOTAL: TIPO 6 $1.41

COSTO DIRECTO $49.82

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $2.43

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $2.51

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $54.76

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $54.76

% DE COSTO DE UTILIDAD 9.1667% $5.02

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $59.78

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 47 $0.55

TOTAL DEL PRECIO UNITARIO $60.33

(* SESENTA PESOS 33/100 M.N. *)

Page 31: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: 1130 01 M3 6.0900 $339.64

PLANTILLA APISONADA AL 85% PROCTOR EN ZANJAS CON MATERIAL PRODUCTO DE LA EXCAVACIÒN.

MATERIALES

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.200000 $0.10

SUBTOTAL: MATERIALES $0.10

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.171956 $33.00

SUBTOTAL: MANO DE OBRA $33.00

EQUIPO Y HERRAMIENTA

EQBAILAR BAILARINA DE 4.5 HP HOR $27.68 0.433526 $12.00

SUBTOTAL: EQUIPO Y HERRAMIENTA $12.00

TIPO 5

%MO1 HERRAMIENTA MENOR % $33.00 0.030000 $0.99

SUBTOTAL: TIPO 5 $0.99

COSTO DIRECTO $46.09

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $2.25

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $2.32

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $50.66

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $50.66

% DE COSTO DE UTILIDAD 9.1667% $4.64

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $55.30

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 40.25 $0.47

TOTAL DEL PRECIO UNITARIO $55.77

(* CINCUENTA Y CINCO PESOS 77/100 M.N. *)

Page 32: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: 9030 01 M3 76.1800 $3,238.41

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.172581 $33.12

SUBTOTAL: MANO DE OBRA $33.12

TIPO 5

%MO1 HERRAMIENTA MENOR % $33.12 0.030000 $0.99

SUBTOTAL: TIPO 5 $0.99

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $33.12 0.030000 $0.99

SUBTOTAL: TIPO 6 $0.99

COSTO DIRECTO $35.10

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $1.71

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $1.77

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $38.58

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $38.58

% DE COSTO DE UTILIDAD 9.1667% $3.54

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $42.12

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 33.12 $0.39

TOTAL DEL PRECIO UNITARIO $42.51

(* CUARENTA Y DOS PESOS 51/100 M.N. *)

ACARREO HORIZONTAL SIN PENDIENTE, DE TIERRA, ARENA, CASCAJO, PRODUCTO DE LA EXCAVACIÒN, ETC. EN CARRETILLA DE 3.5 FT3 A 20.00 M INCLUYE CARGA Y DESCARGA DEL MATERIAL.

Page 33: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: CAR003 M3 76.1800 $511.17

CARGA DE CAMIÒN CON MÀQUINA MATERIAL I Y II.

EQUIPO Y HERRAMIENTA

EQTRAXC CARGADOR SOBRE LLANTAS CAT 920 HOR $441.66 0.012679 $5.60

SUBTOTAL: EQUIPO Y HERRAMIENTA $5.60

COSTO DIRECTO $5.60

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.27

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.28

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $6.15

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $6.15

% DE COSTO DE UTILIDAD 9.1667% $0.56

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $6.71

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 0.38 $0.00

TOTAL DEL PRECIO UNITARIO $6.71

(* SEIS PESOS 71/100 M.N. *)

Page 34: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: 9000 05 M3 76.1800 $687.14

EQUIPO Y HERRAMIENTA

EQCAMION CAMION DE VOLTEO DE 7 M3 HOR $205.02 0.036582 $7.50

SUBTOTAL: EQUIPO Y HERRAMIENTA $7.50

COSTO DIRECTO $7.50

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.37

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.38

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $8.25

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $8.25

% DE COSTO DE UTILIDAD 9.1667% $0.76

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $9.01

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 1.1 $0.01

TOTAL DEL PRECIO UNITARIO $9.02

(* NUEVE PESOS 02/100 M.N. *)

ACARREO A 1ER. KM. DE MATERIALES PRODUCTO DE LA EXCAVACION EN CAMION VOLTEO Y DESCARGA, EN ZONA URBANA TRANSITO NORMAL.

Page 35: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: 9002 05 M3/KM 1,066.5200 $2,559.65

ACARREO KM. SUBSECUENTES AL 1° DE MATERIALES PRODUCTO DE EXCAVACION EN ZONA URBANA TRANSITO NORMAL.

EQUIPO Y HERRAMIENTA

EQCAMION CAMION DE VOLTEO DE 7 M3 HOR $205.02 0.009755 $2.00

SUBTOTAL: EQUIPO Y HERRAMIENTA $2.00

COSTO DIRECTO $2.00

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.10

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.10

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $2.20

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $2.20

% DE COSTO DE UTILIDAD 9.1667% $0.20

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $2.40

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 0.29 $0.00

TOTAL DEL PRECIO UNITARIO $2.40

(* DOS PESOS 40/100 M.N. *)

Page 36: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: CIMB039 M2 182.6500 $8,021.99

CIMBRADO Y DECIMBRADO CON CHAROLAS METÀLICAS A DOS CARAS .

MATERIALES

365-VAR-0104 CIMBRA METALICA PARA PAVIMENTOS KG $28.00 0.468571 $13.12

303-ARF-0201 VARILLA R-42 DEL No. 3, (3/8" Ø), KG, 0.557 KG/M KG $12.60 0.075000 $0.95

303-ARF-1101 KG $15.50 0.050000 $0.78

SUBTOTAL: MATERIALES $14.85

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.107977 $20.72

SUBTOTAL: MANO DE OBRA $20.72

TIPO 5

%MO1 HERRAMIENTA MENOR % $20.72 0.030000 $0.62

SUBTOTAL: TIPO 5 $0.62

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $20.72 0.010000 $0.21

SUBTOTAL: TIPO 6 $0.21

COSTO DIRECTO $36.40

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $1.78

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $1.83

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $40.01

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $40.01

% DE COSTO DE UTILIDAD 9.1667% $3.67

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $43.68

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 20.72 $0.24

TOTAL DEL PRECIO UNITARIO $43.92

(* CUARENTA Y TRES PESOS 92/100 M.N. *)

ALAMBRE RECOCIDO CAL. 16, (1.59 mm Ø), KG, 0.016 KG/M

Page 37: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: 4030 02 M3 33.4900 $43,145.50

MATERIALES

301-ARE-0101 ARENA DE MINA M3 $125.00 0.540000 $67.50

GRAVA GRAVA DE MINA T.M.A. 9 MM Ø (3/8"), M3 M3 $182.00 0.640000 $116.48

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.250000 $0.13

302-CEM-0102 TON $1,950.00 0.310000 $604.50

SUBTOTAL: MATERIALES $788.61

MANO DE OBRA

1A5P CUADRILLA No 22 (1 ALBAÑIL + 5 PEONES) JOR $1,198.98 0.207698 $249.03

SUBTOTAL: MANO DE OBRA $249.03

EQUIPO Y HERRAMIENTA

EQVIB VIBRADOR PARA CONCRETO HOR $18.22 0.500000 $9.11

EQREV HOR $18.88 0.500000 $9.44

SUBTOTAL: EQUIPO Y HERRAMIENTA $18.55

TIPO 5

%MO1 HERRAMIENTA MENOR % $249.03 0.030000 $7.47

SUBTOTAL: TIPO 5 $7.47

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $249.03 0.030000 $7.47

SUBTOTAL: TIPO 6 $7.47

COSTO DIRECTO $1,071.13

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $52.32

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $53.89

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $1,177.34

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $1,177.34

% DE COSTO DE UTILIDAD 9.1667% $107.92

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $1,285.26

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 258.87 $3.05

TOTAL DEL PRECIO UNITARIO $1,288.31

(* UN MIL DOSCIENTOS OCHENTA Y OCHO PESOS 31/100 M.N. *)

FABRICACIÒN Y COLOCACIÒN DE CONCRETO VIBRADO Y CURADO HECHO EN OBRA DE RESISTENCIA NORMAL F`c= 150 KG/CM2, REVENIMIENTO DE 10 CMS AGREGADO MAXIMO 3/4".

CEMENTO (GRIS) PORTLAND TIPO II PUZOLANICO, TONELADA

REVOLVEDORA P/CONCRETO DE 1 SACO 8 DE HP

Page 38: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: PICAC006 ML 608.8400 $3,129.44

ACABADO CON VOLTEADOR METALICO EN ARISTAS O JUNTAS DE GUARNICIONES, FIRMES, O PISOS DE CONCRETO.

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.020843 $4.00

SUBTOTAL: MANO DE OBRA $4.00

TIPO 5

%MO1 HERRAMIENTA MENOR % $4.00 0.030000 $0.12

SUBTOTAL: TIPO 5 $0.12

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $4.00 0.030000 $0.12

SUBTOTAL: TIPO 6 $0.12

COSTO DIRECTO $4.24

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.21

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.21

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $4.66

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $4.66

% DE COSTO DE UTILIDAD 9.1667% $0.43

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $5.09

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 4 $0.05

TOTAL DEL PRECIO UNITARIO $5.14

(* CINCO PESOS 14/100 M.N. *)

Page 39: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: RELL010 M3 39.5700 $7,714.96

MATERIALES

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.150000 $0.08

TEPETATE TEPETATE PUESTO EN OBRA, M3 M3 $115.98 1.150000 $133.38

SUBTOTAL: MATERIALES $133.46

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.074973 $14.39

SUBTOTAL: MANO DE OBRA $14.39

EQUIPO Y HERRAMIENTA

EQBAILAR BAILARINA DE 4.5 HP HOR $27.68 0.500000 $13.84

SUBTOTAL: EQUIPO Y HERRAMIENTA $13.84

TIPO 5

%MO1 HERRAMIENTA MENOR % $14.39 0.030000 $0.43

SUBTOTAL: TIPO 5 $0.43

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $14.39 0.010000 $0.14

SUBTOTAL: TIPO 6 $0.14

COSTO DIRECTO $162.26

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $7.93

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $8.16

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $178.35

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $178.35

% DE COSTO DE UTILIDAD 9.1667% $16.35

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $194.70

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 22.76 $0.27

TOTAL DEL PRECIO UNITARIO $194.97

(* CIENTO NOVENTA Y CUATRO PESOS 97/100 M.N. *)

RELLENO EN ZANJAS COMPACTADO AL 85% PROCTOR CON COMPACTADOR VIBRATORIO EN CAPAS DE 20 CM. CON MATERIAL DE BANCO. ( TEPETATE ), PRESENTANDO LA PRUEBA DE CONTROL DE CALIDAD DE LA COMPACTACION.

Page 40: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 5 Análisis No.:

Análisis: LIM005 M2 121.7700 $1,078.88

LIMPIEZA GENERAL DURANTE LA OBRA INCLUYE ACARREOS DE ESCOMBROS, ETC.

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.025670 $4.93

SUBTOTAL: MANO DE OBRA $4.93

EQUIPO Y HERRAMIENTA

EQCAMION CAMION DE VOLTEO DE 7 M3 HOR $205.02 0.010260 $2.10

SUBTOTAL: EQUIPO Y HERRAMIENTA $2.10

TIPO 5

%MO1 HERRAMIENTA MENOR % $4.93 0.030000 $0.15

SUBTOTAL: TIPO 5 $0.15

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $4.93 0.030000 $0.15

SUBTOTAL: TIPO 6 $0.15

COSTO DIRECTO $7.33

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.36

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.37

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $8.06

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $8.06

% DE COSTO DE UTILIDAD 9.1667% $0.74

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $8.80

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 5.24 $0.06

TOTAL DEL PRECIO UNITARIO $8.86

(* OCHO PESOS 86/100 M.N. *)

Page 41: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: 1005 01 M2 450.5400 $2,851.92

LIMPIA TRAZO Y NIVELACION EN EL AREA DE TRABAJO.

MATERIALES

302-CAL-0102 CALHIDRA, TONELADA TON $1,400.00 0.000328 $0.46

305-M3A-0101 PZA $25.13 0.016124 $0.41

303-ARF-0201 VARILLA R-42 DEL No. 3, (3/8" Ø), KG, 0.557 KG/M KG $12.60 0.007477 $0.09

301-ARE-0101 ARENA DE MINA M3 $125.00 0.000160 $0.02

GRAVA GRAVA DE MINA T.M.A. 9 MM Ø (3/8"), M3 M3 $182.00 0.000110 $0.02

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.040000 $0.02

302-CEM-0102 TON $1,950.00 0.000013 $0.03

SUBTOTAL: MATERIALES $1.05

MANO DE OBRA

1T2E-U CUADRILLA No. 75 (1 TOPOGRAFO + 2 AY ESP) JOR $645.40 0.001709 $1.10

1A5P CUADRILLA No 22 (1 ALBAÑIL + 5 PEONES) JOR $1,198.98 0.000417 $0.50

SUBTOTAL: MANO DE OBRA $1.60

EQUIPO Y HERRAMIENTA

EQEST ESTACION TOTAL STS5R DE 5" DE PREC ANGUL HOR $75.01 0.033329 $2.50

EQREV HOR $18.88 0.000571 $0.01

SUBTOTAL: EQUIPO Y HERRAMIENTA $2.51

TIPO 5

%MO1 HERRAMIENTA MENOR % $1.60 0.030000 $0.05

SUBTOTAL: TIPO 5 $0.05

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $1.60 0.030000 $0.05

SUBTOTAL: TIPO 6 $0.05

COSTO DIRECTO $5.26

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.26

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.26

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $5.78

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $5.78

% DE COSTO DE UTILIDAD 9.1667% $0.53

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $6.31

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 1.61 $0.02

TOTAL DEL PRECIO UNITARIO $6.33

(* SEIS PESOS 33/100 M.N. *)

DUELA DE PINO DE 3a DE 3/4"x4"x8' ( 0.019x0.10x2.44 m)

CEMENTO (GRIS) PORTLAND TIPO II PUZOLANICO, TONELADA

REVOLVEDORA P/CONCRETO DE 1 SACO 8 DE HP

Page 42: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: DEM009 M3 45.0500 $11,098.97

DEMOLICION A MANO DE CONCRETO SIMPLE EN FIRMES, PISOS Y BANQUETAS.

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 1.000000 $191.91

SUBTOTAL: MANO DE OBRA $191.91

TIPO 5

%MO1 HERRAMIENTA MENOR % $191.91 0.030000 $5.76

SUBTOTAL: TIPO 5 $5.76

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $191.91 0.030000 $5.76

SUBTOTAL: TIPO 6 $5.76

COSTO DIRECTO $203.43

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $9.94

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $10.24

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $223.61

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $223.61

% DE COSTO DE UTILIDAD 9.1667% $20.50

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $244.11

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 191.91 $2.26

TOTAL DEL PRECIO UNITARIO $246.37

(* DOSCIENTOS CUARENTA Y SEIS PESOS 37/100 M.N. *)

Page 43: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: 1010 02 M3 90.1100 $5,436.34

EXCAVACIÒN A MANO EN ZANJA, MATERIAL COMÙN SECO, CUALQUIER ZONA, PROFUNDIDAD DE 0.00 A 2.00 MTS.

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.244906 $47.00

SUBTOTAL: MANO DE OBRA $47.00

TIPO 5

%MO1 HERRAMIENTA MENOR % $47.00 0.030000 $1.41

SUBTOTAL: TIPO 5 $1.41

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $47.00 0.030000 $1.41

SUBTOTAL: TIPO 6 $1.41

COSTO DIRECTO $49.82

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $2.43

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $2.51

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $54.76

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $54.76

% DE COSTO DE UTILIDAD 9.1667% $5.02

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $59.78

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 47 $0.55

TOTAL DEL PRECIO UNITARIO $60.33

(* SESENTA PESOS 33/100 M.N. *)

Page 44: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: PLAN024 M3 45.0500 $11,292.23

MATERIALES

TEPETATE TEPETATE PUESTO EN OBRA, M3 M3 $115.98 1.150000 $133.38

SUBTOTAL: MATERIALES $133.38

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.300000 $57.57

SUBTOTAL: MANO DE OBRA $57.57

EQUIPO Y HERRAMIENTA

EQBAILAR BAILARINA DE 4.5 HP HOR $27.68 0.500000 $13.84

SUBTOTAL: EQUIPO Y HERRAMIENTA $13.84

TIPO 5

%MO1 HERRAMIENTA MENOR % $57.57 0.030000 $1.73

SUBTOTAL: TIPO 5 $1.73

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $57.57 0.030000 $1.73

SUBTOTAL: TIPO 6 $1.73

COSTO DIRECTO $208.25

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $10.17

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $10.48

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $228.90

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $228.90

% DE COSTO DE UTILIDAD 9.1667% $20.98

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $249.88

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 65.94 $0.78

TOTAL DEL PRECIO UNITARIO $250.66

(* DOSCIENTOS CINCUENTA PESOS 66/100 M.N. *)

PLANTILLA APISONADA AL 85% PROCTOR CON COMPACTADOR VIBRATORIO CON MATERIAL DE BANCO ( TEPETATE ). PRESENTANDO LA PRUEBA DE CONTROL DE CALIDAD DE LA COMPACTACION (INCLUYE ACARREO DE MATERIAL A LA ZANJA).

Page 45: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: 9030 01 M3 175.7100 $7,469.43

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.172581 $33.12

SUBTOTAL: MANO DE OBRA $33.12

TIPO 5

%MO1 HERRAMIENTA MENOR % $33.12 0.030000 $0.99

SUBTOTAL: TIPO 5 $0.99

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $33.12 0.030000 $0.99

SUBTOTAL: TIPO 6 $0.99

COSTO DIRECTO $35.10

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $1.71

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $1.77

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $38.58

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $38.58

% DE COSTO DE UTILIDAD 9.1667% $3.54

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $42.12

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 33.12 $0.39

TOTAL DEL PRECIO UNITARIO $42.51

(* CUARENTA Y DOS PESOS 51/100 M.N. *)

ACARREO HORIZONTAL SIN PENDIENTE, DE TIERRA, ARENA, CASCAJO, PRODUCTO DE LA EXCAVACIÒN, ETC. EN CARRETILLA DE 3.5 FT3 A 20.00 M INCLUYE CARGA Y DESCARGA DEL MATERIAL.

Page 46: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: CAR003 M3 175.7100 $1,179.01

CARGA DE CAMIÒN CON MÀQUINA MATERIAL I Y II.

EQUIPO Y HERRAMIENTA

EQTRAXC CARGADOR SOBRE LLANTAS CAT 920 HOR $441.66 0.012679 $5.60

SUBTOTAL: EQUIPO Y HERRAMIENTA $5.60

COSTO DIRECTO $5.60

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.27

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.28

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $6.15

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $6.15

% DE COSTO DE UTILIDAD 9.1667% $0.56

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $6.71

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 0.38 $0.00

TOTAL DEL PRECIO UNITARIO $6.71

(* SEIS PESOS 71/100 M.N. *)

Page 47: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: 9000 05 M3 175.7100 $1,584.90

EQUIPO Y HERRAMIENTA

EQCAMION CAMION DE VOLTEO DE 7 M3 HOR $205.02 0.036582 $7.50

SUBTOTAL: EQUIPO Y HERRAMIENTA $7.50

COSTO DIRECTO $7.50

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.37

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.38

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $8.25

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $8.25

% DE COSTO DE UTILIDAD 9.1667% $0.76

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $9.01

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 1.1 $0.01

TOTAL DEL PRECIO UNITARIO $9.02

(* NUEVE PESOS 02/100 M.N. *)

ACARREO A 1ER. KM. DE MATERIALES PRODUCTO DE LA EXCAVACION EN CAMION VOLTEO Y DESCARGA, EN ZONA URBANA TRANSITO NORMAL.

Page 48: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: 9002 05 M3/KM 2,459.9400 $5,903.86

ACARREO KM. SUBSECUENTES AL 1° DE MATERIALES PRODUCTO DE EXCAVACION EN ZONA URBANA TRANSITO NORMAL.

EQUIPO Y HERRAMIENTA

EQCAMION CAMION DE VOLTEO DE 7 M3 HOR $205.02 0.009755 $2.00

SUBTOTAL: EQUIPO Y HERRAMIENTA $2.00

COSTO DIRECTO $2.00

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.10

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.10

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $2.20

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $2.20

% DE COSTO DE UTILIDAD 9.1667% $0.20

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $2.40

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 0.29 $0.00

TOTAL DEL PRECIO UNITARIO $2.40

(* DOS PESOS 40/100 M.N. *)

Page 49: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: CIMB040 M2 22.8700 $2,591.40

CIMBRADO Y DESCIMBRADO CON MADERA DE 3a, ACABADO COMUN, EN FRONTERA DE COLADO

MATERIALES

305-M3A-0101 PZA $25.13 1.300000 $32.67

305-M3A-0201 BARROTE DE PINO DE 3a, DE 1 1/2"x3 1/2"x8' PZA $36.21 0.200000 $7.24

303-ARF-1101 KG $15.50 0.300000 $4.65

359-CMB-0101 DIESEL LT $8.46 0.300000 $2.54

305-CLA-1301 KG $10.70 0.100000 $1.07

SUBTOTAL: MATERIALES $48.17

MANO DE OBRA

1C1A CUADRILLA No 7 (1 CARP. O.N. + AYUDANTE) JOR $432.37 10.000000 $43.24

SUBTOTAL: MANO DE OBRA $43.24

TIPO 5

%MO1 HERRAMIENTA MENOR % $43.24 0.030000 $1.30

SUBTOTAL: TIPO 5 $1.30

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $43.24 0.030000 $1.30

SUBTOTAL: TIPO 6 $1.30

COSTO DIRECTO $94.01

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $4.59

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $4.73

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $103.33

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $103.33

% DE COSTO DE UTILIDAD 9.1667% $9.47

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $112.80

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 43.24 $0.51

TOTAL DEL PRECIO UNITARIO $113.31

(* CIENTO TRECE PESOS 31/100 M.N. *)

DUELA DE PINO DE 3a DE 3/4"x4"x8' ( 0.019x0.10x2.44 m)

ALAMBRE RECOCIDO CAL. 16, (1.59 mm Ø), KG, 0.016 KG/M

CLAVOS PARA MADERA DE 2 1/2" (260 pzas/kg) CAJA DE 25 KG

Page 50: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: 4030 02 M3 45.0500 $58,038.37

MATERIALES

301-ARE-0101 ARENA DE MINA M3 $125.00 0.540000 $67.50

GRAVA GRAVA DE MINA T.M.A. 9 MM Ø (3/8"), M3 M3 $182.00 0.640000 $116.48

358-AGU-0201 AGUA DE PIPA M3 $0.50 0.250000 $0.13

302-CEM-0102 TON $1,950.00 0.310000 $604.50

SUBTOTAL: MATERIALES $788.61

MANO DE OBRA

1A5P CUADRILLA No 22 (1 ALBAÑIL + 5 PEONES) JOR $1,198.98 0.207698 $249.03

SUBTOTAL: MANO DE OBRA $249.03

EQUIPO Y HERRAMIENTA

EQVIB VIBRADOR PARA CONCRETO HOR $18.22 0.500000 $9.11

EQREV HOR $18.88 0.500000 $9.44

SUBTOTAL: EQUIPO Y HERRAMIENTA $18.55

TIPO 5

%MO1 HERRAMIENTA MENOR % $249.03 0.030000 $7.47

SUBTOTAL: TIPO 5 $7.47

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $249.03 0.030000 $7.47

SUBTOTAL: TIPO 6 $7.47

COSTO DIRECTO $1,071.13

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $52.32

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $53.89

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $1,177.34

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $1,177.34

% DE COSTO DE UTILIDAD 9.1667% $107.92

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $1,285.26

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 258.87 $3.05

TOTAL DEL PRECIO UNITARIO $1,288.31

(* UN MIL DOSCIENTOS OCHENTA Y OCHO PESOS 31/100 M.N. *)

FABRICACIÒN Y COLOCACIÒN DE CONCRETO VIBRADO Y CURADO HECHO EN OBRA DE RESISTENCIA NORMAL F`c= 150 KG/CM2, REVENIMIENTO DE 10 CMS AGREGADO MAXIMO 3/4".

CEMENTO (GRIS) PORTLAND TIPO II PUZOLANICO, TONELADA

REVOLVEDORA P/CONCRETO DE 1 SACO 8 DE HP

Page 51: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: PICAC006 ML 913.2600 $4,694.16

ACABADO CON VOLTEADOR METALICO EN ARISTAS O JUNTAS DE GUARNICIONES, FIRMES, O PISOS DE CONCRETO.

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.020843 $4.00

SUBTOTAL: MANO DE OBRA $4.00

TIPO 5

%MO1 HERRAMIENTA MENOR % $4.00 0.030000 $0.12

SUBTOTAL: TIPO 5 $0.12

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $4.00 0.030000 $0.12

SUBTOTAL: TIPO 6 $0.12

COSTO DIRECTO $4.24

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.21

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.21

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $4.66

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $4.66

% DE COSTO DE UTILIDAD 9.1667% $0.43

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $5.09

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 4 $0.05

TOTAL DEL PRECIO UNITARIO $5.14

(* CINCO PESOS 14/100 M.N. *)

Page 52: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: PICAC005 M2 450.5400 $4,117.94

ACABADO ESCOBILLADO O FINO SOBRE FIRMES O PISOS DE CONCRETOY BANQUETAS

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.037153 $7.13

SUBTOTAL: MANO DE OBRA $7.13

TIPO 5

%MO1 HERRAMIENTA MENOR % $7.13 0.030000 $0.21

SUBTOTAL: TIPO 5 $0.21

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $7.13 0.030000 $0.21

SUBTOTAL: TIPO 6 $0.21

COSTO DIRECTO $7.55

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.37

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.38

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $8.30

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $8.30

% DE COSTO DE UTILIDAD 9.1667% $0.76

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $9.06

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 7.13 $0.08

TOTAL DEL PRECIO UNITARIO $9.14

(* NUEVE PESOS 14/100 M.N. *)

Page 53: Tarjetas de precios Unitarios Calle

ADMINISTRADOR UNICO: C. HECTOR MANUEL HERNANDEZ ESPINO

PROYECTOS URBANOS Y CIVILES SA DE CV

Concurso No. CI-CMOP-R33-039/2011

Obra:

Inicio Obra: 14/09/2011 Fin Obra: 13/10/2011 Duración: 30 días naturales

ANALISIS DE PRECIOS UNITARIOS

Código Concepto Unidad P. Unitario Cantidad Importe

CONSTRUCCIÓN DE PAVIMENTO DE CONCRETO ASFÁLTICO, GUARNICIONES Y BANQUETAS. UBICADO EN LA CALLE CHABACANO ENTRE CALLE DURAZNO Y TERRENO PRIVADO DE LA COLONIA LOMA BONITA CALERAS

Partida: 6 Análisis No.:

Análisis: LIM005 M2 450.5400 $3,991.78

LIMPIEZA GENERAL DURANTE LA OBRA INCLUYE ACARREOS DE ESCOMBROS, ETC.

MANO DE OBRA

1P CUADRILLA No 1 (1 PEON) JOR $191.91 0.025670 $4.93

SUBTOTAL: MANO DE OBRA $4.93

EQUIPO Y HERRAMIENTA

EQCAMION CAMION DE VOLTEO DE 7 M3 HOR $205.02 0.010260 $2.10

SUBTOTAL: EQUIPO Y HERRAMIENTA $2.10

TIPO 5

%MO1 HERRAMIENTA MENOR % $4.93 0.030000 $0.15

SUBTOTAL: TIPO 5 $0.15

TIPO 6

%MO5 EQUIPO DE SEGURIDAD % $4.93 0.030000 $0.15

SUBTOTAL: TIPO 6 $0.15

COSTO DIRECTO $7.33

% DE COSTO INDIRECTO DE OFICINAS CENTRALES 4.8844% $0.36

% DE COSTO INDIRECTO DE OFICINAS DE CAMPO 5.0314% $0.37

SUBTOTAL 1 (CD + IND OF CENTRAL + IND OF CAMPO) $8.06

% DE COSTO DE FINANCIAMIENTO 0.0000% $0.00

SUBTOTAL 2 (SUBTOTAL 1 + FINANCIAMIENTO) $8.06

% DE COSTO DE UTILIDAD 9.1667% $0.74

SUBTOTAL 3 (SUBTOTAL 2 + UTILIDAD) $8.80

% DE CARGOS ADICIONALES (ISERTP) %CA SUBTOTAL 3 1.179036% x 5.24 $0.06

TOTAL DEL PRECIO UNITARIO $8.86

(* OCHO PESOS 86/100 M.N. *)