URD TECNICA INFORMACION

download URD TECNICA INFORMACION

of 52

Transcript of URD TECNICA INFORMACION

  • 8/2/2019 URD TECNICA INFORMACION

    1/52

    Copyright 2010

    Use of this document is subject to the disclaimer on ETSA Utilities website:www.etsautilities.com.au

    TECHNICAL STANDARD - TS-100

    ELECTRICAL DESIGN STANDARD

    FOR

    UNDERGROUND DISTRIBUTION

    CABLE NETWORKS

    REVISION NOTICE:

    DATE EXPLANATION

    May 2006 Modifications to Sections; 3, 4.2, 4.3, 5.1, 5.4,

    5.12, 6.1 & Table 1.

    October 2006 Modifications to Sections; 4.2, 5.2, 5.4, 5.9 &

    5.10.

    March 2010

    Restructured the document to currentstandard

    Added and Updated all Sections

    Section 5 upgraded by incorporating detailsfrom TS-103 - Section 7

    Appendix B incorporated from TS-103

    Added Appendices C, D and E

    Added new Sections 5.3 and 6.5

    ISSUED: MARCH 2010

  • 8/2/2019 URD TECNICA INFORMACION

    2/52

  • 8/2/2019 URD TECNICA INFORMACION

    3/52

    TS-100 Elec trical Design Standard for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 3 of 52

    Disclaimer refer to website: www.etsautilities.com.au

    6.6 Plan of Division Changes.......................................................237. HIGH VOLTAGE NETWORK.............................................. 24

    7.1 High Voltage Cables Selec tion ............................................247.1.1 Underg round HV XLPE Insula ted Cable Ratings.........................26

    7.2 Design Conside ration for a Transformer and Switc hingCub ic le....................................................................................277.2.1 Padmount Transformer Spec ification/ Rating :.............................277.2.2 Switc hing Cubic le (RMU) Spec ification/ Rating : .........................287.2.3 Underground HV Switc hing Point Req uirem ents: .......................287.2.4 Transformer and/ or Switc hing Cub ic le Loc ations......................29

    7.2.4.1 Transformer a nd/ or Switching Cubic le Setbac k ........317.2.5 A Loop ed High Vo ltage Network .................................................31

    7.3 Other Considerations/ Requirements ...................................327.3.1 Ferroresonanc e .............................................................................327.3.2 Surge Arrestors...............................................................................327.3.3 Earthing (Ground ing ) ....................................................................327.3.4 Cable Numbering System ............................................................327.3.5 Unde rground Cabling Deta il ........................................................337.3.6 Clearanc e to Othe r Servic es........................................................337.3.7 Easement Requirement ................................................................337.3.8 Infrastruc ture Risk Assessment Req uirem ent ..............................33

    8. LOW VOLTAGE NETWORK............................................... 348.1 Low Voltage Cables Selec tion .............................................34

    8.1.1 Underground Low Voltage Cable Rating ....................................358.1.2 Low Voltage Paralle l Ca ble Term ina tion.....................................35

    8.2 After Diversity Maximum Demand (ADMD).........................368.3 Underground Low Voltage Drop...........................................378.4 Low Vo ltage Balanc ed Loads...............................................378.5 Number of Low Vo ltage Feeders per Transformer..............378.6 Low Vo ltage Feeders Ties......................................................388.7

    Service Pillar and Pit Informa tion for Residentia l Supply ....39

    8.7.1 Service Pillar and Pit Selection Priorities......................................39

  • 8/2/2019 URD TECNICA INFORMACION

    4/52

    TS-100 Elec trical Design Standard for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 4 of 52

    Disclaimer refer to website: www.etsautilities.com.au

    8.7.2 Servic e Pillar Design Information .................................................408.7.2.1 Servic e Pilla r Setback ...................................................41

    8.7.3 Footpath Servic e Pits.....................................................................418.8 Commerc ial/ Industrial Low Voltage Supply .......................428.9 Low Voltage Distribution Cabinet.........................................42

    9. TRENCHING AND CONDUIT DESIGN .............................. 4310. PUBLIC LIGHTING DESIGN............................................... 4311. SUPPLY ARRANGEMENTS FOR LARGE LOADS................ 4312. PROVISION FOR FUTURE STAGES.................................... 43APPENDIX A: TABLES........................................................... 44

    Shee t A1: 3 Phase Vo ltag e Drop Table o f ADMD/ No. of

    Customers...............................................................................44Sheet A2: Table of ADMD for Averag e Dwelling Sizes...............45

    APPENDIX B: CADDSMAN LINE DESIGN LAYERS............... 46Sheet B1: Ca ddsman Line Design Laye r Convention ................46

    APPENDIX C: STANDARD DRAWING SYMBOLOGY........... 47Sheet C1: Standard Drawing Sym bols Overhead ...................47Sheet C2: Standard Drawing Sym bols Underground ..............48Sheet C3: Standard Drawing Sym bols Pub lic Lighting ............49Sheet C4: Standard Drawing Sym bols General Info ...............50

    APPENDIX D: TYPICAL UG HV CIRCUIT DIAGRAM ............ 51Shee t D1: Typ ical Underground High Voltage Diag ram ............51

    APPENDIX E: DRAWINGS ISSUING FLOW CHART............... 52Sheet E1: Design Draw ings Issuing Proc ess Flow Chart .............52

  • 8/2/2019 URD TECNICA INFORMACION

    5/52

    TS-100 Elec trical Design Standard for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 5 of 52

    Disclaimer refer to website: www.etsautilities.com.au

    1. PURPOSE

    This Technical Standard is to be applied to any Design involving the installation

    of underground cables that will become a component of the ETSA Utilities

    distribution network It clarifies the responsibilities of Designers, Engineers, Internal

    and External Contractors and Customers of ETSA Utilities in carrying out their

    duties in providing a safe, reliable and cost effective ETSA Utilities underground

    distribution network design.

    This Technical Standard sets out the design requirements for the installation of

    plant and equipment for the underground reticulation of the distribution

    network. It provides specifications for:

    Underground Residential (URD) and Underground Industrial Development(UID) Plan Preparation;

    Single Customer and PLEC Installations; Public Lighting;

    Underground High and Low Voltage Network Design Requirements; and

    CAD Drawing Standard Symbology and Plan Preparation.

    Furthermore, Appendices A, B, C, D and E provide tables, diagrams and flow

    chart which will assist:

    Low Voltage Drop based on ADMD versus Number of Customers;

    Caddsman Line Design Layer Convention;

    Typical Underground High Voltage Circuit Diagram; and

    Drawings Issuing Flow Chart.

    2. SCOPE

    This Technical Standard is applicable to all specifications issued from the dateof this publication. Designs prepared prior to the publication of this standard will

    be accepted to the current specification at that time.

    This Technical Standard is limited to installations external to any substation

    boundary. Cabling within the substation boundary needs to comply with the

    ETSA Utilities Tec hnica l Sta ndard - Substa tion Design, Substa tion Co nstruction

    Sta ndardand AS/NZS standards, other specifications or obligatory requirements

    that shall be relevant.

    This Technical Standard shall be read in conjunction with our Network

    Information for Customers and Contractors brochures: NICC-401, NICC-404,NICC-052and our other Technical Standards: TS-085, TS-087, TS-101, TS-102, TS-

    103, TS-104, TS-105-Append ix A (Forms), TS-107, TS-108 and shall consider the

    references supplied in Section 3 of this document and also refer to any other

    specifications or obligatory requirements that shall be relevant.

    All Technical Standards are available via:

    DaNM/DES Intranet website; andETSA Utilities Internet website: www.etsautilities.com.au

  • 8/2/2019 URD TECNICA INFORMACION

    6/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 6 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    The use of this document is subject to the disclaimer on ETSA Utilities website:

    www.etsautilities.com.au for further assistance and more informationconcerning this technical standard please contact the relevant ETSA Utilities

    Manager.

    3. REFERENCESNOTE: Always check and refer to current relevant publications for any further

    amendments before implementing any of the following mentioned references.

    Electricity Act 1996 and Electricity (General) Regulations 1997;SA OHS&W Act 1986 and Regulations 1995;Energy Network Association (ENA) - ENA NENS 04 - National Guidelines For

    Safe Approach Distances To Electrical and Mechanical Apparatus;

    AS/NZS 1158 - Lighting for Roads and Public Spaces;AS/NZS 2067 - Substations and High Voltage Installations exceeding 1 kV

    A.C.;AS/NZS 3000 - Electrical Installations - Wiring Rules;AS 4026 - Electric Cables - For Underground Residential Distribution

    Systems;

    AS 4799 - Installation of underground utility services and pipelines withinrailway boundaries;

    AS 60038 - Standard Voltages (modified and including the full text of IEC60038);

    IEEE Std 142 - Green Book - Grounding of Industrial and Commercial PowerSystems;

    DTEI - Specification for Works on RoadsExcavation and Reinstatement of Road Pavement.Environment Protection Act 1993 and Environment Protection (General)

    Regulations 1994;

    SA Aboriginal Heritage Act 1988;SA Native Vegetation Act 1991;SA Heritage Act 1993;SA National Parks and Wildlife Act 1972;SA Natural Resources Management Act 2004; andAS/NZS ISO 14001 Environmental Management Systems.

    ETSA Utilit ies Doc um ents:

    ETSA Utilities Service and Installation Rules;NICC 401 - Information on Network Design and Installation by an ExternalContractor;

    NICC 402 - Information on Network Public Lighting Design by an ExternalContractor;

    NICC 404 - Information on Contractor Access and Working in The VicinityOf The Electricity Network;

    NICC 451 - Council/Transport SA Design and Public Lighting AgreementDocument;

    NICC 802 - 11kV to Low Voltage Padmount Transformers (Information andRequirements for Customers);

    NICC 803 - Information Bulletin - ETSA Service Pits and Pillars;NICC 804 - Customers Guide to Supply Arrangements for Large CustomerLoads;

  • 8/2/2019 URD TECNICA INFORMACION

    7/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 7 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    TS 085 - Trenching and Conduit Standard;TS 087 - Construction Standard for Underground Cable Networks;TS 101 - Public Lighting Design Standard;TS 102 - An Easement Standard for Distribution Networks;TS 103 - General Standard for Contestable Works Gaining Connection To

    The Electricity Networks;TS 105 - Testing Standard Appendix A - Forms;TS 107 - Overhead Line Design Standard;TS 108 - Technical Standard for Distribution Transformer Rooms; andETSA Utilities Relevant E-drawing Manuals.

    4. DEFINITIONS

    In the interpretation of this Technical Standard unless the context shall otherwise

    require or admit, the Words defined in the Works Agreement and NICC 0052 -

    Terms and Cond itions for Netw ork Insta llations (Ad d itiona l Contrac to r

    Annexure) - N52have the same meaning.

    Accredited Designer - means a designer who has satisfied ETSA Utilities Terms

    and Conditions to undertake an electrical design.

    Applicant-Person applying for access to the ETSA Utilities network.

    AS/ NZS 3000 Wiring Rules - means the current version of the Wiring Rules

    published by Standards Australia.

    Bush Fire Risk Area - The ETSA Utilities Bush Fire Risk Area is any area in South

    Australia so defined in the latest revision of the Regulations under the ETSA ActAmendment Act - 1988.

    Backbone Feeder - is defined as the HV conductors bearing the significant

    proportion of feeder load, generally including Tee offs, where four or five

    overhead transformers or 2 padmount transformers and a major customer exist.

    Cable - means an insulated conductor, or two or more such conductors, laid

    together, whether with or without fillings, reinforcements or protective

    coverings. (Note: Cable for the purpose of this manual also means aerial

    bundled cables).

    Conductor -means a wire, cableor form of metal designed for carrying electric

    current.

    CCADDDS - means Central CAD Drawing Deposit System used for sending

    CAD drawings electronically between ETSA Utilities depots and Facilities

    Records.

    Contractor - includes but is not limited to licensed subcontractors, consultants

    and sub consultants and engaged by the Applicant.

    Council - means the local government authority for the site of theDevelopment.

  • 8/2/2019 URD TECNICA INFORMACION

    8/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 8 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    Connection Point - has the meaning given to that term in the Electricity

    (General) Regulations 1997, namely a connection point to a transmission or

    distribution network. For the purpose of this document connection point also

    has the same meaning as Point of Supply as defined in AS/NZS 3000.

    CST - Common Service Trench.

    Development - means the development proposed by the Applicant on the

    Land and any land external to that land but included in the Applicant's

    proposal.

    Distributor - means a person who holds a Distribution Licence, or who is

    exempted from holding a licence of the Electricity Industry Act.

    A Distributor is also known as the Distribution Network Service Provider(DNSP).

    For the purpose of this document ETSA Utilities is the Distributor.

    DTEI -means the Department for Transport, Energy and Infrastructure.

    Earthed - means connected to the general mass of earth by a conductor to

    ensure and maintain the effective dissipation of electrical energy.

    MEN -meansMultiple Earthed Neutral Systems.

    CMEN -meansCommon Multiple Earthed Neutral Systems.

    ETSA Utilities - ETSA Utilities means Distribution Lessor Corporation subject to a

    two hundred year lease to the partnership of companies trading as ETSA Utilitiesor ETSA Utilities in its own right.

    ETSA Utilities, ABN 13 332 330 749, a partnership of -CKI Utilities Development Limited, ABN 65 090 718 880;

    HEI Utilities Development Limited, ABN 82 090 718 951;

    Each incorporated in The Bahamas.

    Spark Infrastructure SA (No.1) Pty Ltd, ABN 54 091 142 380;

    Spark Infrastructure SA (No.2) Pty Ltd, ABN 19 091 143 038;

    Spark Infrastructure SA (No.3) Pty Ltd, ABN 50 091 142 362;

    Each incorporated in Australia.

    1 Anzac Highway, Keswick, South Australia, 5035.

    ETSA Utilitie s' Manager - The ETSA Utilities' Manager or the authorised Officer

    serving that area of the customers installation. For specific Asset Manager

    Areas and their contact details please refer to ETSA Utilities internet website

    www.etsautilities.com.au Contractors and Designers browse for Serviceand Installation Rules (S&IR) and check in Section 3.0 - Asset Manager Areas

    and Contac t Details.

    Elec tric al Connec tion Works - inc ludes:

    Those works required for the connection of the proposed extension to ETSAUtilities distribution network; and

    Any works (electrical or non-electrical) that involve work on, around, underor above the existing network.

  • 8/2/2019 URD TECNICA INFORMACION

    9/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 9 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    Elec trical Works - inc ludes:

    All cable laying, cable jointing and street lighting required to service theApplicant, and any works required to connect the Applicant to the ETSA

    Utilities distribution network but does not include low voltage electricity

    reticulation beyond the point of supply;

    Padmount transformer and switching cubicle installation; and Includes trenching, excavation, backfilling, conduits, pits, footings andrestoration.

    Easement Standard -means the Easement Standard for Distribution Networks TS

    102, issued by ETSA Utilities as varied from time to time.

    High Voltage or High Voltage - means a nominal voltage exceeding 1,000

    volts alternating current or exceeding 1,500 volts direct current.

    Licensed Contractor - means an individual who is registered as a Restricted

    Electrical Worker in accordance with The Plumbers, Gas Fitters and ElectriciansAct 1995, for the relevant endorsements of "Limited to works on overhead lines"

    or "Limited to cable jointing and underground distribution systems up to

    consumers terminals excluding (or including) lead".

    Low Voltage or Low Voltage - means a nominal voltage exceeding 50 volts

    alternating current or 120 volts direct current, but not exceeding 1000 volts

    alternating current or 1500 volts direct current.

    Must - is to be understood as mandatory.

    Mains Side - The side of the street on which low voltage distributor cables areinstalled.

    Network Project Officer (NPO) -The person normally responsible for managing

    the applicants connection.

    Overcurrent Protec tion -Protection which operates when the current exceeds a

    predetermined value.

    Overvoltage Protec tion -Protection that operates at a predetermined voltage

    level which is greater than normal.

    Padmount Transformer -is typically 11kV to Low Voltage transformer enclosed in

    a metal cabinet and mounted at ground level on a concrete pad for a neat

    and compact ground level installation. They shall be capable of supplying a

    customer with 3 phase 230/400V at up to 2500A, in sizes ranging from 300kVA up

    to and including 2000kVA. This style of transformer is the most suitable

    installation in an underground area supplied by cables, within a building

    structure or where a transformer has to be sited on the applicants land.

    Point o f Supply -Refer to Connection Point.

    Primary Plant -means Electrical apparatus on the ETSA Utilities Network which isdesigned to carry electrical energy.

  • 8/2/2019 URD TECNICA INFORMACION

    10/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 10 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    Plan of Division - means the Applicant's Plan of the proposed division of the

    land into residential allotments, public roads, reserves and the like as varied

    from time to time.

    Projec t Mana ge r (PM) -Also referred to as Network Project Officer (NPO).

    Protection - An apparatus or combination of protective equipments designed

    to initiate, under predetermined abnormal conditions, the disconnection of an

    element of a power system.

    Servic e Side -means the non-distributor side of the street.

    Service Mains - The electricity cable connecting the Customer's first point of

    supply to ETSA Utilities connection point.

    Shall- is to be understood as mandatory.

    Should- is to be understood as nonmandatory, i.e. advisory or recommended.

    Suitable (or suitably) - means to the satisfaction of the relevant ETSA Utilities

    Manager.

    Substation - The part of a power system, concentrated in a given place

    including mainly the terminations of transmission or distribution lines switchgear

    and housing which also include transformers. It generally includes facilities

    necessary for system security and control. (E.g. the protective devices).

    Terms and Conditions -means ETSA Utilities publication Terms and Conditionsfor External Contractor Construction, as amended from time to time.

    URD - means underground residential distribution for the supply of electricity.

    UID - means underground industrial distribution for the supply of electricity.

    Wate rcourse - means any of the following whether permanent, overflow or wet

    weather catchment only and as defined in Environment Protection (Water

    Quality) Policy 2003:

    a river, creek or other natural watercourse (whether modified or not);a dam or reservoir that collects water flowing in a watercourse;a lake, wetland or other body of water through which water flows;the Coorong;an artificial channel;a public stormwater disposal system; andpart of a watercourse.

    Works -means the term Works as defined in the Works Agreement.

    Works Agreement - means the Agreement for the Design, Construction and

    Testing of Electrical Services entered into by ETSA Utilities and the Applicant forthe Development of the Land.

  • 8/2/2019 URD TECNICA INFORMACION

    11/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 11 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    5. SPECIFICATION AND DESIGN INFORMATION

    ETSA Utilities will supply the specification information relating to the project

    which will enable an ETSA Utilities recognised design contractor to undertake

    the design on behalf of the Applicant. The information will be in accordance

    with the TS-103- Gene ra l Sta ndard for Contesta b le Work Ga ining Co nnec tion to

    the Electricity Network.

    The designer shall prepare an electrical design layout in a form acceptable to

    ETSA Utilities that is in accordance with Technical Standards, E-drawings and

    other relevant specifications. If the construction is to be contestable the work to

    be undertaken by both the contractor and ETSA Utilities shall be clearly defined

    on the design drawing. The design needs to reflect the requirement that any

    equipment that is to be installed must be to the ETSA Utilities specification.

    The design drawing shall also specify that the contractor undertakes maximum

    work with the parameters being, unless otherwise specified by ETSA Utilities, thatany work on an existing asset will be undertaken by ETSA Utilities. Refer to TS-

    087; Section 9.0 for information on Ac c ess Permits and Connec tion to ETSA

    Utilities Existing Equipment and TS-105; Section 6.8 for Network Ac c ess Permits.

    The electrical design layout is to be submitted by email unless otherwise

    specified by ETSA Utilities. If an email submission is not possible then the design

    should be submitted on a data disk. Design data enclosed with the application

    must be clearly labelled with the following information:

    Applicant's Name and Application Date;

    Development Name, Development Number and ETSA Utilities NotificationNumber;

    Disk Number and Total Number of Related Disks (e.g. Disk 1 of 1);CAD File Name (e.g. PROJECT2.DWG);Drawing Scale (drawing must have written Scale, Scale Bar and Sheet

    Size); and

    Drawing Status (e.g. Preliminary, For Construction or As Constructed).

    5.1 Basic Spec ification Informa tion

    The information will include but not be limited to:

    ETSA Utilities Network system requested works associated with theApplicants Works;

    Design After Diversity Maximum Demand kVA (ADMD); Current Earthing System (MEN or CMEN);Any special Conduit requirements including spares;Any special requirements for Bushfire Risk Areas;Other requirements (e.g. provisions for the future development);

    and

    Hard copies of feeder plans and GIS information as required.ETSA Utilities will from time to time have specific requirements for

    placement of the electrical works that will be vested to ETSA Utilitiesand will inform the Designer of these requirements.

  • 8/2/2019 URD TECNICA INFORMACION

    12/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 12 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    The design contractor shall prepare an electrical design layout in a

    form acceptable to ETSA Utilities. In accordance with Chapter 3.3 of the

    SA Distribution Code, ETSA Utilities is not obliged to accept a design or

    construction if it is not undertaken in such a manner that is compatible

    with the ETSA Utilities Network.

    5.2 Design Req uirem ents

    The Designer needs to ensure the design addresses any requirement

    associated with references in Section 3 of this document and also

    consider any other standards/regulatory/obligatory requirements that

    are relevant.

    Consider risk impacts as a part of the design process. Refer toSection 7.3.8 in this document;

    For any extension within an ETSA Utilities MEN earthing area toestablish the soil resistivity/earth resistance readings. Refer toSection 7.3.3 in this document;

    Evaluate site plan details, services and their locations. Otherservices, their locations and specific clearance requirements must

    be taken into account in designing the electrical infrastructure.

    Refer to Section 7.3.6 in this document;

    Transformer load and cable rating must not exceed values asstated in Section 7.2 and 7.1.1 respectively in this document;

    Must acquire all necessary documents such as CouncilAcceptance, ETSA Utilities Approval and other Approvals as

    necessary. i.e. DTEI;

    Must consider all requirements specified in this and otherdocuments that shall be appropriate to a design;

    It is the responsibility of the Applicant or an agent of the Applicanti.e. the designer to ensure that during the course of the project

    that anything that impacts or changes the design of the Electrical

    Works is reflected in a notification to all relevant parties including

    the Network Project Officer. A Design revision will be required. For

    more details refer to Section 6 Design Process in this document;

    During For Construction stage, it is theBuilder/Contractor/Installers responsibility to verify the actual on-

    site details, mark the changes and notify the designer to ensure

    the As Constructed matches the electrical installation;ETSA Utilities may request additional data, which should includeengineering calculation sheets for pole strengths, footing details

    and tension calculations for overhead lines and cable pull

    tensions for underground lines;

    Any non-standard design will require written approval by the ETSAUtilities Manager Engineering Standards and Regulatory Reset

    (MES&RR); and

    For multi stage URD/UID development a proposed high voltagenetwork design is required for all stages as a component of the

    preliminary design submission for the first stage.

  • 8/2/2019 URD TECNICA INFORMACION

    13/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 13 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    5.3 Design Princ iples

    5.3.1E Drawings

    The design should reference a specific E drawing to ensure the right

    assembly is ordered and installed. The relevant E drawing should be

    referenced where there needs to a specific / specification /installation. An example is public lighting, overhead construction

    assemblies or specific service pits or pillars.

    5.3.2Contestab le Works

    A designer needs to be aware that many designs for a Network

    extension can be built by either ETSA Utilities or an accredited

    external electrical contractor. The Works that an electrical

    contractor can normally undertake is limited to new installations that

    are remote (not connected) to the ETSA Utilities Network. The

    relevant ETSA Utilities Manager will be able to inform you of theextent of work a contractor can undertake.

    A design can include a mix of contestable and non contestable

    work and there may be works that ETSA Utilities needs to undertake

    during the construction to assist the Contractor, i.e. access into an

    existing transformer or switching cubicle for a cable installation.

    The design needs to specify the extent of works that can be

    undertaken by a contractor and the extent of works that can only

    be undertaken by ETSA Utilities.

    Where a Network Access Permit (NAP) is required and work needs to

    be undertaken by ETSA Utilities during the construction phase the

    design needs to be labelled with a unique identifier.

    NAP 1, 2, 3 etc is the unique identifier for each specific accessrequest location. For some projects, i.e. a URD there may be a

    number of NAPs required. Each one must detail the work to be

    carried out and who undertakes the work. It is preferable that the

    information is linked and close to the identifier.

    The designer also needs to highlight the works to be undertaken at

    the connection point(s) by ETSA Utilities. This level of detail assists in

    scoping, costing and delineates responsibilities.

    NAP 1 NAP 2

  • 8/2/2019 URD TECNICA INFORMACION

    14/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 14 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    5.3.3Underground Residentia l Deve lopment (URD)

    A URD is a multi lot Torrens Titled development that can front a road

    reserve or be contained within a Greenfield site with created roads.

    Council can specify that an area is to be an underground

    development within its approval process.

    The design is based on the Network Specification that will specify the

    After Diversity Maximum Demand (ADMD), supply point(s) and any

    other specific requirements that ETSA Utilities may require.

    While any industrial or commercial load, i.e. school, shopping centre,

    office complex, etc, within the development may be treated as a

    separate project it can be advantageous from a costing perspective

    to incorporate the installation of cables and equipment into the

    overall URD layout.

    Please discuss a URD with a mix of residential and commercial

    allotments with the relevant ETSA Utilities Manager.

    Refer to TS -101 Pub lic Lighting Design Sta ndard for Underground

    and Overhead Networks for public lighting options.

    It is paramount that Council receives and accepts the form NICC -

    451 Council Design and Public Lighting Agreement Document at

    the preliminary design phase as a Council can have specific public

    lighting requirements.

    5.3.4Industrial Deve lopment

    An Industrial Development is a multi allotment Torrens Title industrial

    or commercial subdivision that will be sold on the open market. The

    electrical installation can be with overhead or underground mains.

    Council can specify that an area is to be an underground

    development within its approval process and can also specify that

    each allotment is serviced.

    There shall be two levels of installation that ETSA Utilities will in general

    consider. The designer needs to verify with the Applicant the level of

    servicing that is required.

    5.3.4.1 A Service d Industrial DevelopmentA design needs to encompass the agreed supply loads

    within the Development.

    If the load requirements within the development are

    unknown, ETSA Utilities will accept a design for the

    electrical infrastructure in a commercial or light industrial

    area and that provides the following:

  • 8/2/2019 URD TECNICA INFORMACION

    15/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 15 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    Generally a minimum of an 80 ampere three phaseservice for each allotment;

    Installation of additional spare conduits to meet thecapability of accepting a future 11kV supply upgrade to

    every allotment;

    Transformer(s) capable of handling the agreed loadcapacity; and

    Public lighting in accordance with Council and theapplicants requirements.

    5.3.4.2 A Service ab le Industrial Deve lopmentA serviceable development design will encompass the

    installation of a backbone high voltage cable network

    within the subdivision, (but individual service points for

    each allotment are not provided) additional spare

    conduit installations for each property to assist in any

    future servicing arrangement and public lighting inaccordance with Council and the applicants

    requirements.

    This design approach should be favoured if individual

    customer characteristics are unknown, or if individual

    customer loads have the potential to vary significantly. An

    applicant is required to inform purchasers that the blocks

    shall not be serviced but can be serviced at the

    purchasers cost.

    5.3.5Community Title

    A Community Title residential or industrial/commercial development

    is deemed to be one property and the basis for servicing is via a

    single supply point. Where a development is of such a size that

    multiple transformers are required a back up or looped high voltage

    supply may be specified.

    The method of supply for a residential Community Title development

    is via a grouped metering arrangement with the Applicant being

    responsible for low voltage supply within the development. Up to 18

    residential meters per group meter board is acceptable before asecond board will be required. The group meter board must be

    located on common land.

    Refer to the ETSA Utilities Service and Installation rules for more

    information on a metering location.

    A multi dwelling development on one title, i.e., a retirement village

    can be designed utilizing the same design principle. As some

    community titled developments can be gated it is important that the

    designer ensures the ETSA Utilities requirement of access over a full

    24hour period is achieved.

  • 8/2/2019 URD TECNICA INFORMACION

    16/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 16 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    5.3.6Redeve lopm ents

    A redevelopment (sometimes called a Brownfield development)

    encompasses an area which has, or had, an existing electrical

    distribution infrastructure designed to supply power to a customers

    metered supply point. The extent of a redevelopment will vary. Some

    examples:

    A total redevelopment site which will require the existing ETSAinfrastructure to be removed. An underground system will

    generally replace the old asset;

    A partial redevelopment with a mixture of old and newinfrastructure; and

    Allotment layout changes only and the existing infrastructureremaining.

    A redevelopment design needs to capture the extent of the works tobe undertaken, particularly in reference to the limitation of

    contestable works on existing assets. Refer to Section 5.3.2

    Contestable Works in this section.

    5.3.7 ETSA Designer Ac c reditation and Intellec tual

    Property

    An External designer needs to be accredited prior to ETSA Utilities

    issuing a Specification Compliance. The requirements are

    documented in NICC 401 Information on Network Design and

    Insta lla tion b y a n External Contrac to r .

    The utilisation of any ETSA Utilities specification for any electrical

    installation other then an installation designed to be vested and

    connected to the ETSA Utilities Network without our approval is an

    offence. ETSA Utilities views such misuse seriously and will take legal

    action for any breach.

    If a designer wishes to utilise an ETSA Utilities Specification for a design

    that is not being vested to ETSA Utilities please contact the ETSA

    Utilities Manager Engineering Standards and Regulatory Reset

    (MES&RR) on 8404 5077 to discuss an agreement.

    5.4 Design Drawing Prep aration Req uirem ents

    The layout is to closely replicate a relevant standard ETSA drawing

    sheet. The Network Project Officer (NPO) is to be consulted for advice if

    the required drawing layout is uncertain. The design shall include the

    following:

    Drawing Title; Designer details in the bottom right hand side of thedrawing sheet above the drawing sheet details;

    Single Line Diagram (SLD) of the proposed high voltage extension;

  • 8/2/2019 URD TECNICA INFORMACION

    17/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 17 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    Access permits points shall be numbered and the extents of theContractor works and ETSA Utilities works must be fully detailed.

    Refer Section 5.3.2;

    Easement location(s) utilising a dashed line. It is not essential thatthe easement is to scale. The width must be dimensioned and

    depth when appropriate, i.e. transformers, switching cubicles,centre line of cables;

    North Point Top right side of drawing, oriented between 9 and 3Oclock;

    Bar Scale, Written Scale and Sheet Size;Road and Street Names, Street Numbers and Lot Numbers where

    available;

    DCDBs Plan Parcel Identification Numbers(for country areas);Suburb/Town Name/Hundred (for country areas);Standard Symbols and Styles as per the Caddsman Line design

    package Refer to AppendixC for the required ETSA Utilities

    standard drawing symbology;Legend describing only the symbols and line styles used on thedrawing;

    Standard notes to conform with the purpose of the drawing andprovide relevant background information;

    Feeder Plan Reference; Grid Reference in GDA94 MGA projection(easting and northing) for the centre point of each design

    drawing sheet;

    AMG Map Reference - e.g. 6628-41-VI; Filing Reference whereapplicable - e.g. A08 (local reference);

    Drawing Number (CS or AW Notification number; CAD file to benamed with to this number also); Reference Drawings Noted;The scope of works to be undertaken by ETSA Utilities;

    Cross Sections to comprehensively provide trenching detail, assetdepths and conduit use for underground installations;

    Transformer details showing high and low voltage arrangements(padmount transformers only); Switching Cubicle details showing

    high voltage arrangements;

    Applicants Name; Development Number and Name (ifapplicable);

    Asset ownership details;Drawing status (e.g. Preliminary, For Construction, As Constructed);Revision Identifier, Description, Reviser and Revision Date;Project name and ETSA Utilities project managers name;Construction completion date on As Constructed drawings with

    details of constructor if it is not ETSA Utilities;

    Dimensioned positions and alignments of installed or altered ETSAUtilities assets and identification of abandoned and removed

    assets (on As Constructed drawings); and

    Identification of all open points between low voltage transformerareas.

    The initial preliminary design is to be submitted to ETSA Utilities relevant

    PM/NPO as stated in Section 6.5.

  • 8/2/2019 URD TECNICA INFORMACION

    18/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 18 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    5.5 Spec ific ations for CAD Layering and Styles

    The design CAD file must be compatible with ETSA Utilities systems and

    processes including (but not limited to) checking, verification, archiving,

    analysis and planning requirements. For this purpose, the design data

    must meet the following criteria when imported into ETSA Utilities'

    Caddsman CAD software:

    The design data and subdivision layout must be drawn using truemodel distances in CAD (1:1 scale) and the correct plotting scale

    (e.g. 1:500) must be set and displayed on the drawing sheets

    along with bar scales and sheet sizes;

    The symbology, line styles and colours used to display the designdata must appear the same as if the design was produced by

    ETSA Utilities using CAD and the URD application software. Refer to

    Appendix C for the required ETSA Utilities standard drawing

    symbology; and

    The different CAD data classes must be displayed on separatelayers (see Appendix B B-Sht 1 - for the Caddsman Line Design

    Layer Convention as an example). A layer index must be included

    on a separate layer that is invisible and excluded from plotting

    (while retaining the option to activate the layer for viewing or

    plotting if necessary).

    ETSA Utilities reserves the right to reject any outdated, non-compliant or

    non-compatible design data and to require revision and re-submissionof the data in a form acceptable to ETSA Utilities.

    5.6 Spec ific ation for Elec tronic File Format

    Where possible the design CAD file which is supplied to ETSA Utilities

    must be in Caddsman format (versions 4.4 to Modeller SJ acceptable).

    For requirements regarding the Non-Caddsman electronic files refer to

    Section 5.7 - Spec ifica tion fo r Non-Ca ddsma n Elec tronic File Format.

    5.7 Spec ification for Non-Ca ddsman Elec tronic File Forma t

    Where it is not possible to supply electronic files in Caddsman format(versions 4.4 to Modeller SJ), the electronic file should be supplied in

    *.dxf or *.dwg format provided that the file format version is compatible

    with Caddsman Modeller SJ software. To meet this requirement, the

    following is a suggested guide for consultants converting files from

    AutoCAD.

    All information for each drawing shall be contained within a single file.

    This means that where the consultant has employed a combination of

    paper and model space such that the drawing sheet and main body

    of the drawing must be contained in separate files, the files shall be

    merged together such that drawing in its entirety is contained in asingle file in model space.

  • 8/2/2019 URD TECNICA INFORMACION

    19/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 19 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    The drawing shall be reduced to basic elements such as lines, curves

    and text. This means that where the drawing contains complex

    elements such as blocks or dimensions, the associations between the

    elements shall be dropped (e.g. in the case of blocks, the blocks shall

    be exploded).

    Where the drawing is in *.dwg format it shall be saved as an AutoCAD

    version between releases 7 and 2005 inclusive. Where the file supplied is

    a *.dxf file, the file must be similar to those created from AutoCAD

    releases 7 to 13. Where a file conversion is attempted from any other

    format such as MicroStation or CivilCAD the principles of file conversion

    indicated above shall be adhered to.

    Any files or entities linked to the CAD drawing (e.g. font files, pattern

    files, symbols, Xrefs) must be included with the submitted CAD drawing

    so that it can be viewed and plotted in its entirety without requiring any

    significant re-linking or reconstructive work when received by ETSAUtilities. Packaging the CAD file and the associated linked files into a

    *.zip file for submission is recommended.

    For further information regarding ETSA Utilities electronic file

    requirements, first consult the relevant Network Project Officer (NPO).

    The NPO should seek further consultation from ETSA Utilities Facilities

    Records Co-ordinator (FRC).

    6. DESIGN PROCESS

    There are three stages to a design, each serving a function as a project movesthrough from concept to completion. The Electrical Constructor is reliant on the

    design being correctly labelled and approved.

    6.1 Preliminary Design Req uirem ents

    The initial drawing that needs to be submitted to the Network Project

    Officer (NPO) must be marked as a Preliminary Drawing only. This shall

    be placed in a prominent box near the title block, as a watermark

    across the design or in the revision box at the bottom lefts side of the

    sheet.

    At this point the design can be issued to the Applicant for approval, to

    key stakeholder parties for notification of pending work for

    comment/approval and for external consultation.

    Where Council and DTEI have an interest, the design needs to be

    submitted with the form NICC-451 Counc il/ Department of Transport,

    Energy and Infrastructure (DTEI) Design and Pub lic Lighting Ag reeme nt

    Document for approval/acceptance if there are Works within a road

    reserve or any public lighting installations within a road reserve.

    The Network Project Officer (NPO) will verify that the design addresses

    any specific requests issued in the ETSA Utilities project specification and

    satisfies other ETSA specifications.

  • 8/2/2019 URD TECNICA INFORMACION

    20/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 20 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    6.2 For Construction Design Requirements

    The designer can issue a For Construction design only upon receipt of

    the Specification Compliance from ETSA Utilities. The Specification

    Compliance confirms the following have been satisfied:

    Any non-standard design arrangement is approved;Council/DTEI has accepted/approved the works in any road

    reserve and any public lighting installation and tariff and ETSA is in

    receipt of that agreement;

    The offer has been signed and accepted by the customer; andAny easement requirement is either lodged with the LTO or ETSA

    Utilities is in receipt of an Agreement to Grant an Easement. (Refer

    to TS -102).

    It is the responsibility of the design contractor to ensure that all the ETSA

    Utilities specification requirements shall be met. The preliminary design isevaluated against the specification for compliance. This initial

    evaluation is a component of the specification, administration and

    inspection fee.

    A non compliance will be issued if the design does not meet

    specification. ETSA Utilities may issue a charge for any specification re-

    compliance that is required.

    The Authority to Proceed - Construction confirmation letter and the

    Specification Compliance to the Applicant/s agent is the signal to an

    electrical contractor and the customer that the relevant checks andapprovals have been completed. The Designer needs to be in receipt

    of the Specification Compliance letter prior to marking a design as

    approved with the notation For Construction.

    6.3 As Construc ted Design Req uirem ents

    The As Constructed drawing is a critical document that is a

    prerequisite to ETSA Utilities accepting the Certificate of Electrical

    Compliance and ultimately undertaking the vesting and connection.

    The As Constructed drawing must be an accurate record of the

    completed construction/installation including all of the changes

    agreed to and signed off by the Network Project Officer/Project

    Manager.

    For most projects the As Constructed Drawing can be prepared well

    in advance of the final electrical tests. The relevant number of As

    Constructed drawings must be on site at the time the tests are

    witnessed by the Compliance Officer. Refer Section 6.5.3 and Appendix

    - E Issuing Proc ess fo r Design Drawing in this document.

    The drawings will then be installed in all relevant ETSA Utilities plant to

    assist ETSA Utilities personnel in the switching and customer connection.

  • 8/2/2019 URD TECNICA INFORMACION

    21/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 21 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    The legend and feature symbology should remain as proposed

    however any proposed references must be removed from the title

    block. The design must be prominently marked As Constructed and

    the change to As Constructed status must be included in the revision

    block.

    The As Constructed design drawing shall comply with the relevant

    specifications detailed throughout this Standard (e.g. Section 5.4), with

    particular regard to the following:

    Public roads MUST have street names in place at this point;All joints and equipment positions (high and low voltage) must be

    accurately located and dimensioned;

    Earth stake locations external to equipment must be clearly shownand dimensioned;

    Any easement has critical location dimensions included on theexpanded easement diagram and/or main design;The primary electrical Contractors name must be included, e.g. inthe notes section; and

    The date of completion.It is important that ETSA Utilities has all the relevant data on the

    constructed Works. ETSA Utilities will only accept the Certificate of

    Electrical Compliance if the As Constructed design reflects the

    installations and the required copies have been forwarded to ETSA

    Utilities. Refer to Section 6.5.

    6.4 Revisions/ Cha nges to a Design

    Any changes to a design (other than minor deviations) must be

    submitted to the Network Project Officer for approval. Minor changes

    will not necessarily require a For Construction drawing to be revised

    on the proviso that all changes must be incorporated into the As

    Constructed design and have been approved.

    The relevant ETSA Utilities Network Project Officer/Project Manager is to

    be consulted to resolve any uncertainties regarding incorporation of

    changes into the design drawing. Designer must be aware that any

    changes/revisions made to the Preliminary, For Construction andAs Constructed design will be in accordance with the following

    requirements:

    All design changes impacting on the design drawing shall beincorporated into the Master Design Drawing. The Revision

    Identifier, Description, Reviser and Revision Date must be logged in

    the revisions block for a minimum of the last five drawing revisions;

    All revision details shall be clearly and unambiguouslymarked/specified (e.g. public light changes, additional cable

    installations, additional road crossings, high voltage cable loopsinto easements etc.);

  • 8/2/2019 URD TECNICA INFORMACION

    22/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 22 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    Changes to earthing requirements shall be clearly detailed. (e.g. ifchanged from CMEN to MEN or vice versa);

    Where it may not be possible to singularly itemise all changes as adesign moves from a Preliminary design to a For Construction

    design, the critical changes and particularly the ones that may

    impact any quotation (remembering that the Preliminary designmay have been released for quoting purposes), must be noted;

    and

    Revised drawings must be issued to ETSA Utilities as stated infollowing Section 6.5 - Proc ess for Issuing a Design Drawing in this

    document.

    6.5 Proc ess for Issuing a Design Drawing

    An outdated or unapproved design can result in equipment ordering

    and installation errors, increased risks, introduction of life threatening

    hazards or significant additional cost variations. Design changes mustbe clearly and correctly communicated to ensure that all relevant

    parties shall be working with the correct information.

    The designer must ensure that all relevant parties shall be in receipt of

    the latest information and drawing, throughout the life of the project

    (i.e. Preliminary, For Construction, As Constructed stages including all

    revisions made during these stages), by following the design drawing

    issuing process.

    Refer to Appendix - E Drawings Issuing Flow Chart for the details.

    6.5.1Designers Role

    It is the Designers responsibility to ensure that design drawings shall

    be issued to all relevant parties (as specified below) upon revision of

    the design drawing.

    Forward a hard copy or PDF file at the Preliminary Stage toETSA Utilities NPO/ PM;

    At the For Construction and As Construc ted stages,forward(1 Electronic CAD file + 1 PDF format copy) to ETSA Utilities

    relevant NPO/ PM; and

    Forward Copies (Numbers as required) either via Email or ashard c opies appropriately to all other relevant recipients.

    Refer to Appendix - E Drawings issuing Flow Chart for thedetails.

  • 8/2/2019 URD TECNICA INFORMACION

    23/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 23 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    NOTES:

    If submission of an electronic CAD drawing is not possible viaemail then submission of the CAD drawing on Data Disks should

    be permitted. Data Disks must be clearly labelled as specified in

    Section 5 in this document and must contain a PDF copy of thedrawing; and

    If an ETSA Utilities NPO/PM or any other responsible ETSA UtilitiesOfficer is acting as Designer then they must also fulfil the

    Designers role in the issue of drawings.

    6.5.2Network Projec t Offic ers/ Projec t Ma nagers Role

    On receipt of new or revised design drawings from the Designer, It is

    ETSA Utilities NPO/PMs responsibility to ensure that design drawings

    shall be further issued as specified below:

    Forward a hard copy or PDF file at the Preliminary Stage toETSA Utilities Fac ilities Rec ords Co- ordina tor;

    During the For Construction and As Constructed stagesforward 1 Electronic CAD file + 1 PDF format copy via CCADDDS

    to ETSA Utilities Facilities Records Co-ordinator. If CCADDDS is

    not accessible the files should be sent via email/internal mail;

    and

    1 Hard c opy (at the Preliminary and at the For Constructionstages) and 2 Hard copies (at the As Constructed stage) to

    the ETSA Utilities Comp lianc e Co-ordinator.

    NOTE:

    It is the specific requirement of Facilities Records that they mustbe in receipt of the latest drawing revision throughout the life of

    the project.

    6.6 Plan of Division Changes

    If the position of any transformer/switching cubicle or underground

    cable is to be altered at any time during the design process or the

    execution of the Works, the survey plan must be amended to reflect the

    change and satisfy the requirements in TS-102 - Easement Sta ndard fo r

    Distribut ion Networks.

  • 8/2/2019 URD TECNICA INFORMACION

    24/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 24 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    7. HIGH VOLTAGE NETWORK

    7.1 High Voltag e Ca bles Selec tion

    Cable sizes will be based on the summation of the nameplate rating of

    individual padmount transformers in a loop system while also taking into

    consideration extended high loading during summer periods (Refer toSection 7.1.1 in this document for more details). If future expansion is

    expected, then 300mm2 cable will be the minimum size.

    Refer to Appendix D: D-Sht 1 - Typica l Underground High Voltag e

    Circ uit Diagram in this document as a reference for an explanation of

    various scenarios in making an underground high voltage cable

    selection. Where cabling space is restricted, the following 6.35/ 11kV

    cables shall be used in the CBD and Comm ercia l/ Industrial

    Developments:

    TABLE 1: Cable Sizes for 6.35/11kV in CBD and with approvalCommercial/ Industrial Develop ments:

    Cable Desc ription: ETSA Utilities Supply Item Nos.

    6.35/ 11kV Al. Cond . Cu. Cond .

    240mm2, 3c, XLPE/HDPE

    Individual Cu Screens-- CK3240

    185mm2, 3c, XLPE/HDPE

    Individual Cu Screens-- CK3185

    The following 19/33kV cables shall be used in the CBD and

    Commercial/Industrial Developments:

    TABLE 2: Cable Sizes for 19/ 33kV in CBD and with approvalCommercial/ Industrial Develop ments:

    Cable Desc ription: ETSA Utilities Supply Item Nos.

    19/ 33kV Al. Cond. Cu. Cond.

    240mm2, 1c, XLPE/HDPE, Cu Screen -- CK8240

    70mm2, 1c, XLPE/HDPE, Cu Screen -- CK8070

  • 8/2/2019 URD TECNICA INFORMACION

    25/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 25 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    TABLE 3: Ca ble Sizes for 11kV New URD Residential Land Divisions:

    Purpose: Cable Desc rip tion:ETSA Utilities

    Supply Item

    Nos.

    11kVAl.

    Cond.

    Cu.

    Cond.

    630mm2, 1c, XLPE/HDPE, Cu Screen;

    ORCK6039 --11 kV Substation Feeder

    Exits to the

    First Switching Cubicle 630mm2, 1c, XLPE/HDPE, Cu Screen -- CK6050

    630mm2, 1c, XLPE/HDPE, Cu Screen

    (Backbone);

    OR

    CK6039 --

    Main Feeders from theFirst Switching Cubicle300mm2, 1c, XLPE/HDPE, Cu Screen

    (Not Bac kbone)CK6025 --

    Main Feeders Connecting

    Padmount Transformers300mm2, 1c, XLPE/HDPE, Cu Screen CK6025 --

    Substation Ties Between

    adjacent 11kV feeders.

    (Start and End of Feeder)

    630mm2, 1c, XLPE/HDPE, Cu Screen CK6039 --

    630mm2, 1c, XLPE/HDPE, Cu Screen;

    ORCK6039 --Substation Ties Between

    adjacent 11kV feeders.

    (at the Open Point) 300mm2, 1c, XLPE/HDPE, Cu Screen CK6025 --

    95mm2, 1c, XLPE/HDPE, Cu Screen;

    ORCK6005 --

    Looped Cables

    within a Feeder 95mm2, 3x1c, Bundled XLPE/HDPE,

    Cu Screen

    CK6006

    (Triplex)--

    630mm2, 1c, XLPE/HDPE, Cu Screen;

    ORCK6039 --

    11kV Feeders Backbone to

    End of Feeder

    300mm2

    , 1c, XLPE/HDPE, Cu Screen CK6025 --

    95mm2, 1c, XLPE/HDPE, Cu Screen,

    ORCK6005 --

    Laterals and Radials95mm2, 3x1c, Bundled XLPE/HDPE,

    Cu Screen

    CK6006

    (Triplex)--

    NOTES:

    Equivalent Copper (Cu) sized cable can be used.Refer Appendix - D - Typ ic a l UG HV Circ uit Diagram

  • 8/2/2019 URD TECNICA INFORMACION

    26/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 26 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    7.1.1Underground HV XLPE Insula ted Ca ble Ratings

    Designers shall ensure the maximum operational ratings of cables

    shall not be exceeded. Particular attention shall be given to

    Extended high load ing during summer periods (i.e. Summ er

    Emergenc y Rating) for any given cable in determining cable ratings.

    Designers shall calculate using an appropriate de-rating formula

    based on the following parameters and/or actual specific criteria

    which will include but not be restricted to:

    Soil thermal resistivity:1.2 C m/W for summer emergency continuous rating; and0.9 C m/W for winter emergency continuous rating.

    NOTE:

    Where practicable soil thermal resistivity testsshould be done for direct buried applications.

    Spacing of cables:100 mm for horizontal formation; andTouching for trefoil formation.

    Ground temperatures:25 C for summer; and12 C for winter.

    Conductor (maximum) XLPE insulation temperature:90 C for normal conditions; and120 C for emergency conditions.

    Cable burial depth:910 mm.

    Number of circuits;Direct buried versus conduited systems; and

    Heat from nearby cables/circuits.IEC 60287 and AS/NZS 3008.1.1 explain the cable rating calculation

    method and Cable manufacturers data should also be referred to.

    For further information on cable rating requirements consult ETSA

    Utilities relevant Project Manager/Network Project Officer.

  • 8/2/2019 URD TECNICA INFORMACION

    27/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 27 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    7.2 Design Consideration for a Transformer and Switc hing

    Cubicle

    The Padmount Transformer and Switching Cubicle (RMU) with technical

    specification/rating stated in section 7.2.1 and 7.2.2 shall also be

    suitable for continuous trouble free operation when subjected to theenvironmental operating conditions.

    The environmental operating conditions stated below shall be not

    restricted to and should be used as Guide only:

    Installation: Outdoor/Indoor;Sola r Radiation: Up to 1.1kW/m2;Max. Altitude/Site Elevation (above mean sea level): 1000m;Ambient Air Temp.: From - 5C to + 50C and Max. 24hr avg. 40C;Black Body Temp. in Sunlight: 85C;Max. Temp. inside Enclosure: 65C;Dust: Concentrations Up to 10g/m;Humidity: Max. relative humidity up to 90% over 24 hr periods; andPollution: Areas of coastal spray and medium level industrial

    pollution with equivalent salt deposit density up to 30mg/m2 per

    month.

    When an electrical design does not satisfy the specification/rating

    requirements, the design must be assessed by ETSA Utilities and a

    dispensation should be given in writing from the relevant ETSA Utilities

    NPO/PM.

    7.2.1Padmount Transformer Spec ific ation/ Rating:

    Transformer specification/rating must be capable of supplying the

    maximum customer demand during extreme heatwave conditions.

    The Transformer load (specified kVA multiplied by the number of

    customers) must not exceed:

    85% of the name plate cyclic rating of the transformer wherethe transformer installed supplies more than one customer; and

    100% of the name plate cyclic rating of transformer only for aSingle Commercial/Industrial customer installation, on the

    proviso that all customers installations that shall be connected

    to this transformer have been fitted with a load limiting control

    device equivalent to the agreed service capacity as per the

    ETSA Service and Installation Rules 6.7.2.1.

    For a URD, the Transformer Size shall NOT exceed 300kVA and

    associated cable ratings must also be taken into consideration.

  • 8/2/2019 URD TECNICA INFORMACION

    28/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 28 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    7.2.2Switching Cubic le (RMU) Spec ification/ Rating:

    Switching devices within a Switching Cubicle (RMU) must be graded

    to offer protection for the ETSA Utilities infrastructure under maximum

    demand loadings, i.e. extreme heatwave conditions.

    85% of the rated current of the switching device where theSwitching Cubicle is installed and exposed to the direct

    sunlight.

    7.2.3Underground HV Switching Point Requirements:

    High voltage switching locations shall be determined such that the

    maximum load switched at a given point shall not exceed the

    capacity of the 3-phase ganged switch.

    The maximum number of transformers between switching points shall

    be limited to the load breaking capabilities of the switching devices

    on the feeder.

    In a high voltage looped system, the open point of the transformer

    must have a provision for remote switching capabilities (i.e. remotely

    operable Ring Main Unit (RMU)) in a transformers high voltage

    compartment (or a Switching Cubicle).

    A remotely operable RMU shall be used at all open points between

    adjacent feeders.

    NOTES:

    All final high voltage open points using switches (as nominatedby ETSA Utilities) shall be at a transformer with a Ring Main Unit

    (RMU) or a free standing switching cubicle (RMU) with a Load

    Switch (LS);

    All final feeder tie points (as nominated by ETSA Utilities) shallhave remote operation functionality i.e. switching cubicle

    (RMU);

    The use of a circuit breaker (CB) within a switching cubicle asan open point of any feeder backbone is NOT permitted; and

    With a transformer, a transformer with RMU or a switchingcubicle, the following shall NOT be permitted as open points:

    Circuit Breaker (CB);Fuse (F); andLoad Switch Fuse (LSF).

  • 8/2/2019 URD TECNICA INFORMACION

    29/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 29 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    Examples:Refer to Appendix D: D-Sht 1 - Typica l Unde rground High Voltag e

    Circ uit Diagram for the explanation of following scenarios.

    Sc ena rio 1: Looped Circuits on the same FeederIf the looped circuits shall be on the same feeder then there must be

    an open point. At this open point the switches must be able to

    operate remotely. To achieve this remote operating capability

    either:

    a RMU shall be installed at the padmount transformers highvoltage compartment; or

    a Switching Cubicle (RMU) shall be installed nearby.Cables shall be a minimum size of 95mm2Al.

    Sc ena rio 2: Looped Circ uits with an Open p oint

    separating two main Feed ersIf the looped circuits with an open point separating two main

    feeders then Scenario 1 condition shall apply except that cables

    shall be a minimum size of 300mm2.

    Sc enario 3: Radial CircuitsIt must be noted that for radial circuits, if any future

    extension/connection is required then it shall be to the same existing

    feeder. Where a radial circuit could become a looped circuit then

    Scenario 1 applies.

    Cables shall be a minimum size of 95mm2 Al.

    7.2.4Transformer and/ or Switching Cubic le Loc ations

    For a land development with multi customers a transformer location

    must take into account the low voltage feeder distribution network

    and be located as close as practicable in the centre of the load. If

    this requirement is not satisfied then ETSA Utilities will not provide a

    Specification Compliance for a design with a transformer location.

    Where the customer is required to make provisions for the

    transformer, switching cubicle and/or other service protection

    devices, the position provided shall be free of obstruction and

    access must be continuously available for ETSA Utilities to safely

    operate on the device or devices at all hours.

    The location of the padmount transformer must not breach the

    requirements of relevant standards, environment and locations of

    other services such as fire booster cabinets, water, sewer services

    and infrastructure etc.

  • 8/2/2019 URD TECNICA INFORMACION

    30/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 30 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    A Designer must conduct a risk assessment prior to commencing any

    design and follow the requirements as mentioned below:

    Evaluate site plan details and establish where existing andproposed services shall be located in areas in the vicinity of

    ETSA equipment;

    Suitability of the terrain in the vicinity of any installation andfuture accessibility to ETSA equipment;

    Eliminate equipment placement conflicts and any breach ofcompliance issues;

    Assessments must be presented with the preliminary design;Vicinity of equipment nearby a watercourse addressed. (Refer

    Section 7.3.8 in this document for the detail).

    Equipment for a development or a single customer is only to be

    installed in locations that allow ETSA Utilities to adequately access

    the equipment. ETSA must have access to a transformer, switching

    cubicle and a service pillar at ALL times i.e. 24 hours / 7 days a week

    from the date of energisation.

    Equipment location should need to be located on a property

    boundary facing a road reserve to achieve this. Transformer and

    switching cubicles can be sited on:

    Reserves;Very large building allotments likely to be developed as high

    density residential sites;

    Local shopping centres; andAt the rear and side of residential corner allotments.

    NOTE:

    This equipment shall NOT be located in road reserves withoutconsultation from ETSA Utilities Network Project Officer/Project

    Manager. NPO/PM will assist in seeking written approval from

    Manager Network Asset (MNA).

    Also refer to NICC 802 - 11kV to Low Volta ge Padmo unt Transforme rs

    - Information and Requirements for Customers which provides

    additional information for single customer transformer installations.

  • 8/2/2019 URD TECNICA INFORMACION

    31/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 31 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    7.2.4.1 Transformer and/ or Switching Cub ic le Setbac kDesigners need to be vigilant when selecting locations for

    above ground equipment in developments, car parks and

    private roadways, taking into account the boundary to

    kerb dimension and final development

    designs/environment.

    For a Transformer and/or Switching Cubicle the following

    design requirements shall be included:

    A minimum set back of 1.0m from the back of a kerb andthe installation of bollards on any side exposed to

    vehicular traffic;

    The installation of bollards on any side exposed tovehicular traffic that does not have a suitable form of

    protective device;

    An exemption for bollard installation should be consideredfor set backs greater then 1.0m and will depend on

    location, traffic and additional protective devices, e.g.

    the installation of a 200mm high concrete kerb; and

    On the proviso that the set back is 1.0m, a centre bollardin front of the doors is not required.

    For further information on setback requirements please

    contact and consult ETSA Utilities relevant ProjectManager/Network Project Officer.

    7.2.5A Loop ed High Voltage Network

    The installation of three or more transformers on a radial tee off will

    require the extension to become a looped high voltage network. If a

    multi stage development already has three transformers installed,

    any future stage which increases that number must be a looped

    network design.

    Consideration should be given to a future looped system on theproviso there is a master-plan and staged construction proposal that

    has written agreement from the ETSA Utilities relevant Project

    Manager/Network Project Officer.

    Any switching cubicle or transformer located in such a way that it

    unnecessarily deviates the high voltage cable route and requires

    additional lengths of high voltage cable will be deemed to be

    installed at the request of the developer and at the developers cost.

    Refer to Appendix D: D-Sht 1 - Typica l Unde rground High Voltag e

    Circ uit Diagram.

  • 8/2/2019 URD TECNICA INFORMACION

    32/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 32 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    7.3 Other Considerations/ Req uirem ents

    The site shall be well compacted. Any site that is not level as defined in

    Section 3 of TS -085 should need a retaining wall.

    E drawing E1982 sheet 3.3 specifies that the height from the ground

    level to the top of the pad base shall be 75mm and E1981 sheet 3.0

    specifies 150mm for a switching cubicle vault. This is to ensure the

    switchgear and fuses shall still at the correct height for operational

    purposes and the vault is not compromised.

    7.3.1Ferroresonance

    When designing a high voltage network, consider the possibility of

    ferroresonance occurring due to the combination of underground

    cables and a transformer. To eliminate the likelihood of ferroresonant

    over-voltages, 3-phase Ganged Switching Devices (i.e. Load Switch

    (LS)) must be used at all switching points.

    For various 3-phase Ganged Switching Device arrangements refer to

    appropriate E-drawing as per Manual No. 4 - Underground

    Constructionand for over to under on the pole type arrangements

    refer to Manual No. 3 - Overhea d Construct ion.

    7.3.2Surge Arrestors

    Surge Arrestors shall be required for protecting primary plant against

    damage from lighting and/or switching overvoltage. For over to

    under (O/U) cabling arrangement, surge arrestors shall be installedon any over to under (O/U) pole.

    7.3.3Earthing (Grounding)

    For an MEN earthing area, the designer needs to arrange for soil

    resistivity/earth resistance tests. The design needs to consider these

    tests in relation to the minimum readings required at the time of

    installation and factor in earthing standards as stated in E-drawing E-

    1905 series, relevant E-drawing manuals and AS/NZS 3000.

    For sites with difficult earthing conditions, the design shall considerthe location of equipment and the installation of additional earthing

    facilities. Additional earthing facilities can be achieved in a number

    of ways and there are specialist firms that can provide advice.

    7.3.4Cable Numb ering System

    The layout plan must detail a switching cubicle and a padmount

    transformer showing high and low voltage cable destinations and

    labelling/numbering showing the destination of each exit that must

    satisfies the protocol specified in TS-105 Section 5. ETSA Utilities

    approved symbols for feeder equipment must be used.

  • 8/2/2019 URD TECNICA INFORMACION

    33/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 33 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    7.3.5Underground Cabling Detail

    The Designer will need to consider the level of detail needed for a

    conduit and cable installation. Complex installations will need to be

    detailed in cross sections at various points along the common service

    trench (CST) route.

    7.3.6Clearanc e to Other Servic es

    It is the designers responsibility to take into account the safe

    clearance from other services. For the vertical and horizontal

    separation between other services such as Gas pipes, SA Water,

    Telecommunications Services, Private Sewer/Water etc. Refer to TS

    085 - Trenc hing a nd Cond uit Sta ndard fo r Underground Ca b le

    Networks or contact the relevant authority if confirmation is

    required.

    As an example AS 2419.1-2005 Fire Hyd rant Insta lla tionsSyste m

    Design, Installation and Commissioning, specifies a minimum

    requirement for the location of fire hydrants from any high voltage

    electrical distribution equipment to be 10m. For the consumers

    mains clearance/installation requirements refer to Service and

    Installations Rules and AS/NZS 3000.

    7.3.7Easem ent Req uirem ent

    Easements shall be required for ETSA Utilities equipment. Details

    concerning easements are contained in the Technical Standard TS

    102 - An Easem ent Sta ndard for Distribution Netw orks. Alleasements shall be indicated on the design drawings as

    enlargements showing all dimensions and appropriate cadastral

    information so that the surveyor for the Applicant can include ETSA

    Utilities easement requirements on the Final Plan for the Land Division.

    7.3.8Infrastructure Risk Assessment Requirem ent

    The Designer is to provide a risk assessment matrix report as a part of

    a specification compliance requirement.

    The assessment needs to consider but is not limited to the following:

    Access for operational purposes;Future removal and installation;Equipment failure impact on surrounds; Impact on third party equipment installation in the vicinity; andSoil contamination in relation to open trenching within private

    property as referred to in TS-085, clause 14.

  • 8/2/2019 URD TECNICA INFORMACION

    34/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 34 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    When a proposed transformer site is in the vicinity of a watercourse

    (refer Section 4 for the definition), as defined in the Environment

    Protection (Water Quality) Policy 2003, under the Environment

    Protection Act 1993, and the results of the risk assessment are high

    with significant consequences, then either of the following

    alternatives shall be adopted:

    Relocate the transformer site; or Install an oil containment type transformer (not dry type).

    The transformer type referred to above is a special order item. For

    details, contact the ETSA Utilities Manager Engineering Standards

    and Regulatory Reset (MES&RR). For resolving environmental related

    issues, first consult the relevant Project Manager/Network Project

    Officer. The PM/NPO should seek further consultation from ETSA

    Utilities Environmental Management Team.

    8. LOW VOLTAGE NETWORK

    8.1 Low Voltage Cables Selec tion

    The following 0.6/1.0kV cables shall be used for the low voltage

    network.

    TABLE 4: Cable Sizes for Low Voltage Ma ins:

    Cable Desc ription: ETSA Utilities Supply Item Nos.

    0.6/1.0kV Low Voltag e Al. Cond . Cu. Cond .

    150mm2, 4c, XLPE/HDPE

    (Bundled, Termite Resistant)CK5310 --

    TABLE 5: Cable Sizes for Low Vo ltage Mains - CBD Ap plications:

    Cable Desc ription: ETSA Utilities Supply Item Nos.

    0.6/1.0kV Low Voltag e Al. Cond . Cu. Cond .

    70mm2, 4c, PLY/HDPE;

    OR

    70mm2, 4c, XLPE/HDPE

    --

    CW1070;

    OR

    Non-Stock**

    185mm2, 4c, PLY/HDPE;

    OR

    185mm2, 4c, XLPE/PVC

    --

    CW1185;

    OR

    CK1185

    240mm2, 4c, XLPE/PVC -- CK1240

    300mm2, 4c, PLY/HDPE;

    OR

    300mm2, 4c, XLPE/HDPE

    --

    CW1300;

    OR

    Non-Stock**** = Refer to E4020 Sheet 2 for the details.

  • 8/2/2019 URD TECNICA INFORMACION

    35/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 35 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    TABLE 6: Cable Sizes for Low Voltage Servic es - CBD Ap plications:

    Cable Description: ETSA Utilities Supply Item Nos.

    0.6/1.0kV Low Voltag e Al. Cond . Cu. Cond .

    25mm2

    , 4c, PLY/HDPE -- CW1025

    TABLE 7: Cable Sizes for Low Volta ge Public Lighting Applications:

    Cable Desc ription: ETSA Utilities Supply Item Nos.

    450/750V Low Voltag e Al. Cond . Cu. Cond .

    2.5mm2, 2c, PVC/PVC

    (Red/Black cores-White sheath)-- CD7240

    6.0mm2, 2c, PVC/PVC

    (Red/Black cores-White sheath)-- CD7253

    6.0mm2, 1c, PVC/PVC

    (Green/Yellow cores-Black sheath)-- CD7061

    8.1.1Underground Low Voltage Cable Rating

    Refer to Section 7.1.1 in this document for design factors fordetermining de-rating factors for any cable. Designers must ensure

    the maximum operational ratings of underground low voltage cables

    shall not be exceeded and provision for spare capacity is included

    for any foreseeable demand requirements.

    IEC 60287 and AS/NZS 3008.1.1 explains the cable rating calculation

    method. Cable manufacturers data should also be referred to. For

    further information on cable rating requirements consult ETSA Utilities

    relevant Project Manager/Network Project Officer.

    8.1.2Low Voltage Parallel Cable TerminationParallel low voltage cables shall only be terminated in a Junction p it

    of P7 size (or larger). The design needs to reflect the correct

    installation. A service pillar is NOT suitable for terminating parallel low

    voltage cables.

    Where parallel cables shall be fed from transformers, they shall be

    terminated at the 1st Junction Pit from the transformer of an

    appropriate size to suit the application and the circuit shall be clearly

    labelled Parallel Cables as per ETSA Utilities Construction E-drawing

    E1921 Sheet 2.5 and 3.20.

  • 8/2/2019 URD TECNICA INFORMACION

    36/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 36 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    8.2 After Diversity Maximum Dem and (ADMD)

    The ADMD of a particular development shall not in general be less than

    8 kVA per allotment. ETSA Utilities will specify the design ADMD as a part

    of its specification. Refer to Appendix A, A-Sht 1 and A-Sht 2 for the

    details.

    The base ADMD specified by ETSA Utilities in a new housing

    development specification will be based on the ADMD Table, Refer to

    Appendix A-Sht 2 Tab le for ADMD for Averag e Dwelling Sizes .

    House sizes from ETSA Utilities research are generally in the medium to

    large range. From the Appendix A-Sht 2 Table this would indicate an

    ADMD of 8 kVA.

    The projected dwelling sizes for a development will be based on

    previous stages or the standard of housing in the vicinity. Any variationto the specified ADMD will require approval by the relevant ETSA Utilities

    Network Manager.

    The designer must take into account:

    The existing and proposed customers supplied from an existingtransformer;

    The total proposed customers load on a proposed transformer,including customers within future stages and any reinforcement of

    existing ETSA Utilities assets as specified by ETSA Utilities; and

    The total proposed customers load on proposed low voltagecables, including customers within future stages and any

    reinforcement of existing ETSA Utilities assets as specified by ETSA

    Utilities.

    The ADMD will apply to:

    Voltage drop calculations;

    Transformer load (specified ADMD multiplied by the number ofcustomers) which must not exceed values as stated in Section 7.2

    of this document; and

    Cable ratings (specified in Amperes) which must not exceed thevalues stated in current AS/NZS 3008.1.1 at a conductor

    temperature of 90 C. The expected load on a cable is to be

    determined from the specified ADMD multiplied by proposed

    numbers of customers connected to that cable.

  • 8/2/2019 URD TECNICA INFORMACION

    37/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 37 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    8.3 Underground Low Voltage Drop

    The voltage drop can be calculated using values supplied in Appendix

    A, A-Sht 1 - Low Voltage Drop Tab le in Volts for (ADMD versus. Number

    of Customers) and A-Sht 2- Tab le for ADMD for Average Dwelling

    Sizes in this document.

    For any underground low voltage feeder, the voltage drop shall NOT

    exc eed 10 Volts:

    to the last (farthest) connection point; andto the last (farthest) open point.

    The voltage drop values for mains and services at the end of each low

    voltage circuit shall be indicated on the design drawings. In some

    circumstances parallel cables (i.e. 2 circuits of 150mm2 bundled cables)

    can be used for reduction of voltage drop.

    In such cases parallel cable details must be incorporated in the design,

    refer to section 8.1.2 for the details.

    8.4 Low Voltag e Balanced Loads

    Single phase customers shall be evenly connected across all three

    phases with their phase connection identified (i.e. red (R), white (W) or

    blue (B)). The phase connections need to be Rolling e.g.

    sequential/alternating.

    Three phase customers shall have their loads evenly balanced across all

    three phases. For URD designs, unless final customer details are known,

    the design needs to take into consideration single phase connections.

    8.5 Number of Low Voltage Feeders per Transformer

    A maximum of 4 low voltage feeders shall be provided from each

    padmount transformer. The arrangement of low voltage feeders will be

    dependent on the physical arrangements of the development. The

    number of customers (normally single phase) shall be balanced over

    the three phases of each feeder.

    The open points between all low voltage feeders shall be clearly shown

    on the design drawing.

  • 8/2/2019 URD TECNICA INFORMACION

    38/52

    TS-100 Elec trical Design Standards for Underground Networks

    TS-100 Issue: MAR 2010 Authorised: Jehad Ali Date: 16/03/10 Page 38 of 52

    Disclaimer refer to website:www.etsautilities.com.au

    8.6 Low Voltage Feeders Ties

    Low voltage feeder ties shall be mandatory for a URD /UID low voltage

    networks. The open point for such ties shall be clearly indicated on the

    design drawing.

    A tie should be achieved by running a length of 150mm2 Alum. low

    voltage cable from one pillar to another with a suitable open point.

    Where low voltage cables from different transformers come within 50m

    of each other, the installation of a specific junction pit to achieve a tie

    may be necessary to ensure that there is an open point and low

    voltage switching capability.

    A pit/pillar installation as per figure (1) is not necessarily required to be

    at the end of a cable run. Refer to figure (1) for an example of a 3 way

    low voltage feeder tie.

    Figure 1: Example o f a 3 wa y Low Voltage Feeder Tie

    In a high load area with a commercial component the installation of a

    low voltage switching cabinet as per E1927 series drawings must be

    considered for feeder interconnection. Refer to Sect