RESUMEN DE VALORIZACION MENSUAL N° 01 PERIODO DEL 18 DE MARZO DE 2,010 AL 31 DE MARZO DE 2010 PROCESO: A.M.C. Nº 010-2010-MDS OBRA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA CONTRATISTA: CONSTRUCTORA ARFIAS E.I.R.L. SUPERVISOR: ING. CARLA GUILLEN MALAGA FECHA: 5-Apr-10 FORMULA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA DESCRIPCION MONTO VALORIZACION % CONTRATO ANTERIOR ACTUAL ACUMULADO AVANCE (SIN IGV) ACUMULADO A VALORIZACION CONTRACTUAL GENERAL 82,434.73 0.00 8,368.20 8,368.20 10.15% TOTAL (A) 82,434.73 0.00 8,368.20 8,368.20 10.15% AVANCE FISICO DE OBRA 0.00% 10.15% 10.15% B REAJUSTES GENERAL 0.00 84.77 84.77 TOTAL (B) 0.00 84.77 84.77 VALORIZACION BRUTA (VB=A+B) 0.00 8,452.97 8,452.97 C DEDUCCIONES DEDUC. AD. DIRECTO 0.00 0.00 0.00 DEDUC. AD MATERIALES 0.00 0.00 0.00 GENERAL 0.00 0.00 0.00 TOTAL (C) 0.00 0.00 0.00 D AMORTIZACIONES AMORT. AD.DIRECTO 0.00 0.00 0.00 AMORT. AD.MATERIALES 0.00 0.00 0.00 GENERAL 0.00 0.00 0.00 TOTAL (D) 0.00 0.00 0.00 VALORIZACION NETA (VN=VB-D-C) 0.00 8,452.97 8,452.97 E RETENCIONES GASTOS DE LICITACION 0.00 0.00 0.00 MULTA POR ATRASO DE OBRA 0.00 0.00 0.00 TOTAL (E) 0.00 0.00 0.00 F MONTO A PAGAR AL CONTRATISTA EN EFECTIVO (VN-E) 0.00 8,452.97 8,452.97 EN IGV (19%*VN) 0.00 1,606.06 1,606.06 TOTAL (F) 0.00 10,059.03 10,059.03 TOTAL COMPROMISO A SOLICITAR S/.: 0.00 10,059.03 10,059.03

description

cosotos

Transcript of Valorización 01

Page 1: Valorización 01

RESUMEN DE VALORIZACION MENSUAL N° 01

PERIODO DEL 18 DE MARZO DE 2,010 AL 31 DE MARZO DE 2010

PROCESO: A.M.C. Nº 010-2010-MDS

OBRA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

CONTRATISTA: CONSTRUCTORA ARFIAS E.I.R.L.

SUPERVISOR: ING. CARLA GUILLEN MALAGA

FECHA: 5-Apr-10

FORMULA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

DESCRIPCION

MONTO VALORIZACION % SALDO

CONTRATOANTERIOR ACTUAL ACUMULADO

AVANCE POR

(SIN IGV) ACUMULADO VALORIZAR

A VALORIZACION CONTRACTUAL

GENERAL 82,434.73 0.00 8,368.20 8,368.20 10.15% 74,066.53

TOTAL (A) 82,434.73 0.00 8,368.20 8,368.20 10.15% 74,066.53

AVANCE FISICO DE OBRA 0.00% 10.15% 10.15% 89.85%

B REAJUSTES

GENERAL 0.00 84.77 84.77

TOTAL (B) 0.00 84.77 84.77

VALORIZACION BRUTA (VB=A+B) 0.00 8,452.97 8,452.97

C DEDUCCIONES

DEDUC. AD. DIRECTO 0.00 0.00 0.00

DEDUC. AD MATERIALES 0.00 0.00 0.00

GENERAL 0.00 0.00 0.00

TOTAL (C) 0.00 0.00 0.00

D AMORTIZACIONES

AMORT. AD.DIRECTO 0.00 0.00 0.00

AMORT. AD.MATERIALES 0.00 0.00 0.00

GENERAL 0.00 0.00 0.00

TOTAL (D) 0.00 0.00 0.00

VALORIZACION NETA (VN=VB-D-C) 0.00 8,452.97 8,452.97

E RETENCIONES

GASTOS DE LICITACION 0.00 0.00 0.00

MULTA POR ATRASO DE OBRA 0.00 0.00 0.00

TOTAL (E) 0.00 0.00 0.00

F MONTO A PAGAR AL CONTRATISTA

EN EFECTIVO (VN-E) 0.00 8,452.97 8,452.97

EN IGV (19%*VN) 0.00 1,606.06 1,606.06

TOTAL (F) 0.00 10,059.03 10,059.03

TOTAL COMPROMISO A SOLICITAR S/.: 0.00 10,059.03 10,059.03

Page 2: Valorización 01

VALORIZACION DE AVANCE DE OBRA Nº 01 - MES DE MARZO DE 2010

PROCESO: A.M.C. Nº 010-2010-MDS

OBRA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

CONTRATISTA: CONSTRUCTORA ARFIAS E.I.R.L.

SUPERVISOR: ING. CARLA GUILLEN MALAGA

FECHA: 4/5/2010

FORMULA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

PARTIDA DESCRIPCION Und Metrado

AVANCESALDO POR VALORIZAR

ANTERIOR ACTUAL ACUMULADO

Metrado Monto Metrado Monto Metrado Monto % Metrado Monto %

01 OBRAS PROVISIONALES 3,409.58 0.00 0.00 0.00 3,409.58

01.01 CAMPAMENTO PROVISIONAL DE LA OBRA glb 1.00 2,690.30 2,690.30 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 1.00 2,690.30 100.00%

01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m u 1.00 719.28 719.28 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 1.00 719.28 100.00%

02 OBRAS PRELIMINARES 2,404.66 0.00 767.74 767.74 1,636.93

02.01 SEÑALIZACION DURANTE LA OBRA m 548.00 2.16 1,183.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 548.00 1,183.68 100.00%

02.02 MOVILIZACION DE MAQUINARIAS HERRAMIENTAS PARA LA OBRA glb 1.00 906.49 906.49 0.00 0.00 0.50 453.25 0.50 453.25 50.00% 0.50 453.25 50.00%

02.03 TRAZO Y REPLANTEO OBRAS DE PAVIMENTACION km 0.27 1,164.79 314.49 0.00 0.00 0.27 314.49 0.27 314.49 100.00% 0.00 0.00 0.00%

03 MOVIMIENTO DE TIERRAS 21,890.61 0.00 6,773.09 0 6,773.09 15,117.52

03.01 CORTE DE MATERIAL SUELTO R=460 m3/día m³ 376.46 4.24 1,596.19 0.00 0.00 376.46 1,596.19 376.46 1,596.19 100.00% 0.00 0.00 0.00%

03.02 CORTE EN ROCA SUELTA m³ 41.83 55.96 2,340.81 0.00 0.00 41.83 2,340.81 41.83 2,340.81 100.00% 0.00 0.00 0.00%

03.03 PERFILADO Y COMPACTADO DE SUB-RASANTE EN ZONAS-CORTE R=2820 m2/día m² 1,807.41 1.41 2,548.45 0.00 0.00 1,807.41 2,548.45 1,807.41 2,548.45 100.00% 0.00 0.00 0.00%

03.04 RELLENO CON MATERIAL PROPIO m³ 36.00 7.99 287.64 0.00 0.00 36.00 287.64 36.00 287.64 100.00% 0.00 0.00 0.00%

03.05 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 15 km m³ 496.96 30.42 15,117.52 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 496.96 15,117.52 100.00%

04 BASE GRANULAR 0.20 M 17,477.04 0.00 0.00 0 0.00 17,477.05

04.01 BASE GRANULAR E=0.20 m R = 2340 m2/día FACTOR COMPACTACION = 1.20 m² 469.93 17.32 8,139.19 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 469.93 8,139.19 100.00%

04.02 TRANSPORTE A LA OBRA R=239 m3/día m³ 469.93 14.52 6,823.38 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 469.93 6,823.38 100.00%

04.03 CARGUIO R= 750 m3/día m³ 469.93 2.12 996.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 469.93 996.25 100.00%

04.04 ESPARCIDO Y COMPACATADO R=4367 m2/día m² 1,807.41 0.84 1,518.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 1,807.41 1,518.22 100.00%

05 CARPETA ASFALTICA EN FRIO E= 2 PULG 22,668.52 0.00 0.00 0 0.00 22,668.52

05.01 IMPRIMACION R = 5700 m2/día PROPORCION 0.30 gl/m2 m² 1,807.41 3.33 6,018.68 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 1,807.41 6,018.68 100.00%

05.02 PREPARACION DE LA MEZCLA ASFALTICA EN FRIO R=4367 m2/día m² 1,807.41 6.21 11,224.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 1,807.41 11,224.02 100.00%

05.03 TRANSPORTE A LA OBRA R=239 m3/día m³ 180.74 14.52 2,624.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 180.74 2,624.34 100.00%

05.04 ESPARCIDO Y COMPACATADO R=4367 m2/día m³ 1,807.41 0.84 1,518.22 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 1,807.41 1,518.22 100.00%

05.05 ARENADO DE BASE IMPRIMADA m² 1,807.41 0.71 1,283.26 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 1,807.41 1,283.26 100.00%

06 VARIOS 6,433.84 0.00 0.00 0 0.00 6,433.84

06.01 ENCIMADO DE BUZONES u 1.00 637.57 637.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 1.00 637.57 100.00%

06.02 REACOMODO DE BUZONES DE DESAGUE glb 4.00 150.00 600.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 4.00 600.00 100.00%

06.03 PINTADO DE LAS MARCAS R= 400 m/día u 450.00 1.33 598.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 450.00 598.50 100.00%

06.04 TRANQUERAS DE MADERA 1.20X1.10 m PARA DESVIO TRANSITO VEHICULAR m 6.00 77.11 462.66 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 6.00 462.66 100.00%

06.05 ENSAYOS DE CALIDAD u 3.00 800.00 2,400.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 3.00 2,400.00 100.00%

06.06 LIMPIEZA FINAL DE LA OBRA m² 1,807.41 0.96 1,735.11 0.00 0.00 0.00 0.00 0.00 0.00 0.00% 1,807.41 1,735.11 100.00%

COSTO DIRECTO 74,284.25 0.00 7,540.82 7,540.82 66,743.44

GASTOS GENERALES 16.30% 12,110.00 0.00 1,229.32 1,229.32 10,880.68

UTILIDAD 7.00% 5,199.90 0.00 527.86 527.86 4,672.04

SUB-TOTAL 91,594.15 0.00 9,298.00 9,298.00 82,296.16

FACTOR DE RELACIÓN 0.90 82,434.73 0.00 8,368.20 8,368.20 74,066.54

IGV (19 %) 19.00% 15,662.60 0.00 1,589.96 1,589.96 14,072.64

TOTAL 98,097.33 0.00 9,958.16 9,958.16 10.15% 88,139.18

Precio Unitario S/.

Precio Parcial S/.

Page 3: Valorización 01

CALCULO DEL COEFICIENTE DE REAJUSTE (K)

PROCESO: A.M.C. Nº 010-2010-MDS

OBRA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

CONTRATISTA: CONSTRUCTORA ARFIAS E.I.R.L.

SUPERVISOR: ING. CARLA GUILLEN MALAGA

FECHA: 4/5/2010

FORMULA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

K= 0,083*( ASr / ASo ) + 0,119*( MOr / MOo ) + 0,152*( AGr / AGo ) + 0,198*( MNr /MNo )+ 0,222*( MIr / MIo )+ 0,226*( GGUr / GGUo )

MON. CONCEPTO INDICE SIMBOLO C %Io Ir

KOct-09 Feb-10

1 ASFALTO 13 AS 0.083 100.000% 1,187.54 1,265.36 0.088

2 MANO DE OBRA 47 MO 0.119 100.000% 413.41 415.58 0.120

3 AGREGADO GRUESO 05 AG 0.152 100.000% 599.88 604.03 0.153

4 MAQUINA Y EQUIPO NACIONAL 48 MN 0.198 100.000% 330.43 334.95 0.201

5 MAQUINARIA Y EQUIPO IMPORTADO 49 MI 0.222 100.000% 246.98 245.24 0.220

6 INDICE GENERAL DE PRECIOS AL CONSUMIDOR 39 GGU 0.226 100.000% 346.74 349.61 0.228

1.000 1.010

Page 4: Valorización 01

REINTEGRO POR REAJUSTE

(CONTROL DE VALORIZACIONES Y REAJUSTES)

CONTRATO PRINCIPAL

PROCESO: A.M.C. Nº 010-2010-MDS

OBRA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

CONTRATISTA: CONSTRUCTORA ARFIAS E.I.R.L.

SUPERVISOR: ING. CARLA GUILLEN MALAGA

FECHA: 4/5/2010

FORMULA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

N° MES

VALORIZACION

K-1

REINTEGRO DEDUCCION

PROGRAMADO EJECUTADO PROGRAMADO EJECUTADO EFECTIVO MATERIALES

1 Mar-10 10,050.70 8,368.20 0.010 101.82 84.77 84.77 0.00 0.00 84.77

SUBTOTAL 10,050.70 8,368.20 101.82 84.77 84.77 0.00 0.00 84.77

REINTEGRO ACTUAL S/. 84.77

REINTEGRO BRUTO

AUTORIZADO

REINTEGRO NETO

AUTORIZADO

Page 5: Valorización 01

CRONOGRAMA VALORIZADO DE EJECUCIÓN DE OBRA

PROCESO: A.M.C. Nº 010-2010-MDS

OBRA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

CONTRATISTA: CONSTRUCTORA ARFIAS E.I.R.L.

SUPERVISOR: ING. CARLA GUILLEN MALAGA

FECHA: 4/5/2010

FORMULA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

PLAZO DE EJECUCIÓN

Ítem Descripción Und. Metrado Precio (S/.) Parcial (S/.) Quincena 1 Quincena 2 Quincena 3

01 OBRAS PROVISIONALES

01.01 CAMPAMENTO PROVISIONAL DE LA OBRA glb 1.00 2,690.30 2,690.30 2,690.30

01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60 X 2.40 m u 1.00 719.28 719.28 719.28

02 OBRAS PRELIMINARES - -

02.01 SEÑALIZACION DURANTE LA OBRA m 548.00 2.16 1,183.68 1,183.68

02.02 MOVILIZACION DE MAQUINARIAS HERRAMIENTAS PARA LA OBRA glb 1.00 906.49 906.49 906.49

02.03 TRAZO Y REPLANTEO OBRAS DE PAVIMENTACION km 0.27 1,164.79 314.49 314.49

03 MOVIMIENTO DE TIERRAS - -

03.01 CORTE DE MATERIAL SUELTO R=460 m3/día m³ 376.46 4.24 1,596.19 798.10 798.10

03.02 CORTE EN ROCA SUELTA m³ 41.83 55.96 2,340.81 1,170.41 1,170.41

03.03 PERFILADO Y COMPACTADO DE SUB-RASANTE EN ZONAS-CORTE R=2820 m2/día m² 1,807.41 1.41 2,548.45 1,274.23 1,274.23

03.04 RELLENO CON MATERIAL PROPIO m³ 36.00 7.99 287.64 287.64 -

03.05 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 15 km m³ 496.96 30.42 15,117.52 15,117.52 -

04 BASE GRANULAR 0.20 M - -

04.01 BASE GRANULAR E=0.20 m R = 2340 m2/día FACTOR COMPACTACION = 1.20 m² 469.93 17.32 8,139.19 8,139.19 -

04.02 TRANSPORTE A LA OBRA R=239 m3/día m³ 469.93 14.52 6,823.38 6,823.38 -

04.03 CARGUIO R= 750 m3/día m³ 469.93 2.12 996.25 996.25 -

04.04 ESPARCIDO Y COMPACATADO R=4367 m2/día m² 1,807.41 0.84 1,518.22 1,518.22 -

05 CARPETA ASFALTICA EN FRIO E= 2 PULG - -

05.01 IMPRIMACION R = 5700 m2/día PROPORCION 0.30 gl/m2 m² 1,807.41 3.33 6,018.68 6,018.68

05.02 PREPARACION DE LA MEZCLA ASFALTICA EN FRIO R=4367 m2/día m² 1,807.41 6.21 11,224.02 11,224.02

05.03 TRANSPORTE A LA OBRA R=239 m3/día m³ 180.74 14.52 2,624.34 2,624.34

05.04 ESPARCIDO Y COMPACATADO R=4367 m2/día m³ 1,807.41 0.84 1,518.22 1,518.22

05.05 ARENADO DE BASE IMPRIMADA m² 1,807.41 0.71 1,283.26 1,283.26

06 VARIOS -

6.01 ENCIMADO DE BUZONES u 1.00 637.57 637.57 637.57

6.02 REACOMODO DE BUZONES DE DESAGUE glb 4.00 150.00 600.00 600.00

6.03 PINTADO DE LAS MARCAS R= 400 m/día u 450.00 1.33 598.50 598.50

6.04 TRANQUERAS DE MADERA 1.20X1.10 m PARA DESVIO TRANSITO VEHICULAR m 6.00 77.11 462.66 462.66

6.05 ENSAYOS DE CALIDAD u 3.00 800.00 2,400.00 2,400.00

6.06 LIMPIEZA FINAL DE LA OBRA m² 1,807.41 0.96 1,735.11 1,735.11

COSTO DIRECTO 74,284.25 9,056.97 36,124.93 29,102.36

GASTOS GENERALES 3.97202% 16.30% 12,110.00 1,476.49 5,889.17 4,744.34

UTILIDADES 7% 7.00% 5,199.90 633.99 2,528.74 2,037.17

SUB TOTAL 91,594.14 11,167.44 44,542.84 35,883.86

FACTOR DE RELACIÓN 0.90 82,434.73 10,050.70 40,088.56 32,295.48

IGV 19% 19.00% 15,662.60 1,909.63 7,616.83 6,136.14

TOTAL 98,097.33 11,960.33 47,705.38 38,431.62

TOTAL ACUMULADO 11,960.33 59,665.71 98,097.33

PORCENTAJE DE AVANCE 12.19% 48.63% 39.18%

PORCENTAJE ACUMULADO 12.19% 60.82% 100.00%

Page 6: Valorización 01

PLANILLA DE METRADOS

PROCESO: A.M.C. Nº 010-2010-MDS

OBRA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

CONTRATISTA: CONSTRUCTORA ARFIAS E.I.R.L.

SUPERVISOR: ING. CARLA GUILLEN MALAGA

FECHA: 4/5/2010

FORMULA: PAVIMENTACION ASFALTICA CALLE 1, CALLE 2 Y CALLE 4 ASOCIACION PEQUEÑOS INDUSTRIALES SAN FERNANDO DE SOCABAYA

ITEM DESCRIPCION UND

CantidadDIMENSIONES

de PARCIAL TOTAL

tipos LARGO ANCHO ALTO

(1) (2) 3) (4) 1x2x3x4

02.00.00 TRABAJOS PRELIMINARES

02.02.00 MOVILIZACION MAQUINARIA Y HERRAMIENTAS PARA L GLB 0.50 1.00 1.00 0.50

02.03.00 TRAZO Y REPLANTEO OBRAS DE PAVIMENTACION KM 1.00 0.27

Calle 1 0.100 0.10

Calle 4 0.093 0.09

Calle 2 0.081 0.08

03.00.00 MOVIMIENTO DE TIERRAS (metrado explanac)

03.01.00 CORTE EN MATERIAL SUELTO M3 376.46

Calle 1 1.00 150.75 150.75

Calle 4 1.00 121.06 121.06

Calle 2 1.00 104.65 104.65

03.02.00 CORTE EN ROCA SUELTA M3 41.83

Calle 1 1.00 16.75 16.75

Calle 4 1.00 13.45 13.45

Calle 2 1.00 11.63 11.63

03.03.00 PERFILADO Y COMPACTADO SUBRASANTE M2 1,807.41

Calle 1 1.00 100.00 6.60 660.00

Calle 4 1.00 92.55 6.60 610.83

Calle 2 1.00 81.30 6.60 536.58

03.02.00 RELLENO CON MATERIAL PROPIO M3 36.00

Calle 4 1.00 36.00 36.00