Vartak College - Presentation

download Vartak College - Presentation

of 70

Transcript of Vartak College - Presentation

  • 8/8/2019 Vartak College - Presentation

    1/76

    1

    JIT

    &

    Supply Chain Excellence

    S. K. Jena

    Mahindra & Mahindra Ltd

  • 8/8/2019 Vartak College - Presentation

    2/76

    2

    Nashik PPC

    DEALERS

    CENTRAL PPC OFFICE

    Kandivali PPC Igatpuri PPC Haridwar PPC

    Zaheerabad PPC

    DCM

  • 8/8/2019 Vartak College - Presentation

    3/76

    3

    KANDIVALI PLANT

    Manufacturing

    Shop

    Procurement

    Cell

    Suppliers

  • 8/8/2019 Vartak College - Presentation

    4/76

    4

    Production Planning

    Marketing

    Production

    PPC

    Procurement

    CPPC

  • 8/8/2019 Vartak College - Presentation

    5/76

    5

    Marketing releases various dispatch plans onthe basis of forecasting, Area office inputs &

    dealers projections viz..

    Yearly Plan

    Monthly plan ( 1mth firm, 2nd mth tentative)

    Weekly feasibility

    Input from Marketing

  • 8/8/2019 Vartak College - Presentation

    6/76

    6

    Plan

    Source Make Deliver

    Supplier

    Plan

    Customer Customers

    Customer

    Suppliers

    Supplier

    Make DeliverSource MakeSource DeliverMakeSourceDeliver SourceDeliver

    (internal or external) (internal or external)

    Your Company

    Supply Chain

    Flow of Material

    Flow of information

  • 8/8/2019 Vartak College - Presentation

    7/76

    Traditional View of Manufacturing

    A key objective was to fully utilize production

    capacity so that more products were produced.

    This thinking led to large queues of in-processinventory waiting at work centers.

    Large queues meant workers and machines never

    had to wait for product to work on.

    This resulted in products spending most of their time

    in manufacturing just waiting, an arrangement that is

    unacceptable in todays time-based competition.

  • 8/8/2019 Vartak College - Presentation

    8/76

    Time-Based Competition

    It is not enough for firms to be high-quality and

    low-cost producers

    Today, they must also be first in getting products

    and services to the customer fast

    To compete in this new environment, the order-

    to-delivery cycle must be drastically reduced

    JIT (Just in Time) is the weapon of choice todayto reduce the elapsed time of this cycle

  • 8/8/2019 Vartak College - Presentation

    9/76

    Order-to-Delivery CycleOrder-to-Delivery Cycle

    DistriDistri--

    bution andbution and

    CustomerCustomer

    ServiceService

    CustoCusto--

    mermer

    PlacesPlaces

    OrderOrder

    OrderOrder

    EntryEntry

    EngiEngi--neeringneering

    DesignDesign

    SchedSched--

    ulinguling

    ManufacturingManufacturing

    Lead TimesLead Times

    PurchasingPurchasing

    Lead TimesLead Times

    ManufacturingManufacturing

    Cumulative Lead TimeCumulative Lead Time

    OrderOrder--toto--Delivery CycleDelivery Cycle

  • 8/8/2019 Vartak College - Presentation

    10/76

    Process

    BProcess

    A

    Fin. Goods

    Raw

    MatlSupplier Customer

    Part Flow

    Process

    C

    PUSHSYSTEM

    Information Flow

    WIPWIP

    Execution - Parts completed to schedule without any downstream considerations

    Replenishment - Based on projected demand (forecasts)

    Shop Floor Control - System, transactions, paperwork

    Problems - Hidden

    Reaction to changes and problems - Through system - rescheduling

    Linkage - Operations are NOT physically linked

  • 8/8/2019 Vartak College - Presentation

    11/76

    Process

    B

    Process

    AFin. GoodsRaw

    MatlSupplier Customer

    Information Flow

    Part Flow

    Kanban

    Locations

    Process

    C

    PULL SYSTEM

    Execution - Parts produced upstream as signaled from the downstream operation or customer

    Replenishment - Based on consumption

    Shop Floor Control - Automatic - visible

    Problems - Exposed - creates urgency

    Reaction to changes and problems - Immediate - on-line and visible

    Linkage - Operations ARE physically linked

  • 8/8/2019 Vartak College - Presentation

    12/76

    JIT: A Pull System

    In a push system, we look at the schedule

    to determine what to produce next

    In a pull system, such as JIT, we look only

    at the next stage of production and

    determine what is needed there, and then

    we produce only that

  • 8/8/2019 Vartak College - Presentation

    13/76

    JIT Manufacturing Philosophy

    The main objective of JIT manufacturing is to

    reduce manufacturing lead times.

    This is primarily achieved by drastic reductions

    in work-in-process (WIP).

    100% capacity utilization is not the predominant

    objective.

    The result is a smooth, uninterrupted flow ofsmall lots of products throughout production.

  • 8/8/2019 Vartak College - Presentation

    14/76

    Successful JIT Applications

    Most successful JIT applications have

    been in repetitive manufacturing, where

    batches of standard products are

    produced at high speeds and in high

    volumes.

    Successful use of JIT is rare in large,

    highly complex job shops whereproduction planning and control is

    extremely complicated.

  • 8/8/2019 Vartak College - Presentation

    15/76

    Elements of JIT Manufacturing

    Eliminating waste

    Enforced problem solving and continuousimprovement

    Total Quality Management (TQM) Parallel processing

    Kanban production control

    Reducing inventories

  • 8/8/2019 Vartak College - Presentation

    16/76

    (1) Waste from overproduction

    (2) Waste of waiting time

    (3) Transportation waste

    (4) Inventory waste

    (5) Processing waste

    (6) Waste of motion

    (7) Waste from product defects

    Waste--Operations

  • 8/8/2019 Vartak College - Presentation

    17/76

    Changes Required for JIT

    JIT requires certain changes to the factory

    and the way it is managed:

    S

    tabilize production schedules Make the factories more focused

    Increase work center capacities

    Improve product quality

    Cross-train workers

    Reduce equipment breakdowns

    Develop long-term supplier relations

  • 8/8/2019 Vartak College - Presentation

    18/76

    Problem Solving and

    Continuous Improvement JIT is a system of enforced problem

    solving.

    One approach is to lower inventorygradually to expose problems and force

    their solution.

    Continuous improvement - a practice the

    Japanese call kaizen - is central to the

    philosophy of JIT.

  • 8/8/2019 Vartak College - Presentation

    19/76

    Uncovering Production

    Problems

    QualityQuality

    ProblemsProblems

    MaterialMaterial

    ShortagesShortages

    MachineMachine

    BreakdownsBreakdowns

    WorkloadWorkload

    ImbalancesImbalances

    WorkerWorker

    AbsenteeismAbsenteeism

    OutOut--ofof--SpecSpec

    MaterialsMaterials

    QualityQuality

    ProblemsProblems

    InIn--ProcessProcess

    InventoryInventory

    We must lower the water level!We must lower the water level! Visible ProductionVisible ProductionProblems are OnlyProblems are Only

    5% of the Total!5% of the Total!

  • 8/8/2019 Vartak College - Presentation

    20/76

    Kanban Production Control

    At the core of JIT manufacturing at Toyota

    is Kanban, an amazingly simple system of

    planning and controlling production

  • 8/8/2019 Vartak College - Presentation

    21/76

    Japanese word for card

    Pronounced kahn-bahn (not can-ban)

    Authorizes production from downstream

    operations

    Pulls material through plant

    May be a card, flag, verbal signal etc.

    Used often with fixed-size containers

    Add or remove containers to change

    production rate

    Kanban

  • 8/8/2019 Vartak College - Presentation

    22/76

  • 8/8/2019 Vartak College - Presentation

    23/76

    Sample Kanban Card

  • 8/8/2019 Vartak College - Presentation

    24/76

    Determining Number of

    Kanbans

    wherewhere

    NN = number of kanbans or containers= number of kanbans or containersdd = average demand over some time period= average demand over some time period

    LL = lead time to replenish an order= lead time to replenish an order

    SS = safety stock= safety stock

    CC = container size= container size

    No. of Kanbans =No. of Kanbans =average demand during lead time + safety stockaverage demand during lead time + safety stock

    container sizecontainer size

    NN ==dLdL ++ SS

    CC

  • 8/8/2019 Vartak College - Presentation

    25/76

    Determining the Number of

    Kanbansdd = 150= 150 partsparts per hourper hour

    LL = 30 minutes = 0.5 hours= 30 minutes = 0.5 hours

    SS = 0.10(150 x 0.5) = 7.5= 0.10(150 x 0.5) = 7.5

    CC = 25= 25 partsparts

    Round up to 4 (to allow some slack) orRound up to 4 (to allow some slack) or

    down to 3 (to force improvement)down to 3 (to force improvement)

    NN = == =

    = = 3.3 kanbans or containers= = 3.3 kanbans or containers

    dLdL ++ SS

    CC

    (150 x 0.5) + 7.5(150 x 0.5) + 7.5

    252575 + 7.575 + 7.5

    2525

  • 8/8/2019 Vartak College - Presentation

    26/76

    KanbanKanban SystemSystem

    Each container must have a cardEach container must have a card

    Assembly always withdraws fromAssembly always withdraws fromfabrication (pull system)fabrication (pull system)

    Containers cannot be movedContainers cannot be movedwithout awithout a kanbankanban

    Containers shouldcontain theContainers shouldcontain thesame number of partssame number of parts

    Only goodparts are passedalongOnly goodparts are passedalong

    Production shouldnot exceedProduction shouldnot exceedauthorizationauthorization

  • 8/8/2019 Vartak College - Presentation

    27/76

    StorageStorage

    areaarea

    Empty containersEmpty containers

    Full containersFull containers

    KanbanKanban SystemSystem

    Receiving postReceiving postKanban card forKanban card for

    product 1product 1

    Kanban card forKanban card for

    product 2product 2

    FabricationFabricationcellcell

    OO11

    OO22

    OO33

    OO22

    Assembly line 1Assembly line 1

    Assembly line 2Assembly line 2

  • 8/8/2019 Vartak College - Presentation

    28/76

    StorageStorage

    areaarea

    Empty containersEmpty containers

    Full containersFull containers

    KanbanKanban SystemSystem

    Receiving postReceiving postKanban card forKanban card for

    product 1product 1

    Kanban card forKanban card for

    product 2product 2

    FabricationFabricationcellcell

    OO11

    OO22

    OO33

    OO22

    Assembly line 1Assembly line 1

    Assembly line 2Assembly line 2

  • 8/8/2019 Vartak College - Presentation

    29/76

    StorageStorage

    areaarea

    Empty containersEmpty containers

    Full containersFull containers

    KanbanKanban SystemSystem

    Receiving postReceiving postKanban card forKanban card for

    product 1product 1

    Kanban card forKanban card for

    product 2product 2

    FabricationFabricationcellcell

    OO11

    OO22

    OO33

    OO22

    Assembly line 1Assembly line 1

    Assembly line 2Assembly line 2

  • 8/8/2019 Vartak College - Presentation

    30/76

    StorageStorage

    areaarea

    Empty containersEmpty containers

    Full containersFull containers

    KanbanKanban SystemSystem

    Receiving postReceiving postKanban card forKanban card for

    product 1product 1

    Kanban card forKanban card for

    product 2product 2

    FabricationFabricationcellcell

    OO11

    OO22

    OO33

    OO22

    Assembly line 1Assembly line 1

    Assembly line 2Assembly line 2

  • 8/8/2019 Vartak College - Presentation

    31/76

    StorageStorage

    areaarea

    Empty containersEmpty containers

    Full containersFull containers

    KanbanKanban SystemSystem

    Receiving postReceiving postKanban card forKanban card for

    product 1product 1

    Kanban card forKanban card for

    product 2product 2

    FabricationFabricationcellcell

    OO11

    OO22

    OO33

    OO22

    Assembly line 1Assembly line 1

    Assembly line 2Assembly line 2

  • 8/8/2019 Vartak College - Presentation

    32/76

    StorageStorage

    areaarea

    Empty containersEmpty containers

    Full containersFull containers

    KanbanKanban SystemSystem

    Receiving postReceiving postKanban card forKanban card for

    product 1product 1

    Kanban card forKanban card for

    product 2product 2

    FabricationFabricationcellcell

    OO11

    OO22

    OO33

    OO22

    Assembly line 1Assembly line 1

    Assembly line 2Assembly line 2

  • 8/8/2019 Vartak College - Presentation

    33/76

    Operational BenefitsOperational Benefits

    yy Reduce space requirementsReduce space requirements

    yy Reduce inventory investmentReduce inventory investment

    yy Reduce lead timesReduce lead times

    yy Increase labor productivityIncrease labor productivityyy Increase equipment utilizationIncrease equipment utilization

    yy Reduce paperwork andsimplifyReduce paperwork andsimplify

    planning systemsplanning systems

    yy Validpriorities for schedulingValidpriorities for scheduling

    yy Workforce participationWorkforce participation

    yy Increase service/product qualityIncrease service/product quality

  • 8/8/2019 Vartak College - Presentation

    34/76

    Reducing Inventories

    through Setup Time Reduction

    Smaller lot sizes result in more machine

    setups

    More machine setups, if they are lengthy,result in:

    Increased production costs

    Lost capacity (idle machines during setup)

    The answer is: REDUCE MACHINE

    SETUP TIMES

  • 8/8/2019 Vartak College - Presentation

    35/76

    Benefits of JIT

    Inventory levels are drastically reduced:

    frees up working capital for other projects

    less space is needed

    customer responsiveness increases

    Total product cycle time drops

    Product quality is improved

    Scrap and rework costs go down

    Forces managers to fix problems and

    eliminate waste .... or it wont work!

  • 8/8/2019 Vartak College - Presentation

    36/76

    Parts operated on JIT at

    Mahindra Chassis 21 types of chassis of Max, F/bed , S/cab,

    BMT CL , CDR , CNG etc

    Seats

    24 types of seats of Max , S/cab , Powerstrg, BMT, CL, CDR , CNg etc.

  • 8/8/2019 Vartak College - Presentation

    37/76

    JIT operating Procedure

    Stock of these JIT parts is kept for 4 to 5

    hours ( in case of chassis ) & 5 to 6 hours

    ( for seats )

    3 days schedule is followed to release the

    material requirement of JIT items.

    Model wise , sequence is given to the

    vendor for the supplies of the parts .

    Daily monitoring is reqd. for these JIT

    parts.

  • 8/8/2019 Vartak College - Presentation

    38/76

    Direct-On-Line

    Material Supply

  • 8/8/2019 Vartak College - Presentation

    39/76

    Traditional Process

    StoresVendorProduction

    Shop

    Vendor Supplies the material to Stores

    Stores department then stores it and supplies it to production shop as

    and when required

    Inventory Inventory

  • 8/8/2019 Vartak College - Presentation

    40/76

    Direct Online

    Vendor delivered material Directly on shopfloor.

    StoresVendorProduction

    Shop

    Body Shop Stores

    Area : 16,751 Sq. Ft

    Manpower : 53

  • 8/8/2019 Vartak College - Presentation

    41/76

    Part no. ABC Qty /Veh Vendor Location Store Qty Perbin Shop qtymax AfterQTY

    90382 A 1 Shear Bend Goregaon 36 36 40

    0101BC0210N A 1 Shear Bend Goregaon 36 36 40

    0101DC0100N C 2 Penetrical Kandivli 200 100 80

    91185 C 2 NAB-IDBI Poly. Ambarnat 240 150 80

    94636 C 1 Shear Bend Goregaon 200 50 4039325 C 1 Sushmi engg Dahisar 1000 150 500

    0101DC0080N C 1 Penetrical Kandivli 200 150 40

    0101DC0070N C 1 Penetrical Kandivli 200 50 40

    87582 C 2 Ramkrishna Iron Shahapur 100 150 80

    75344 C 2 Press N Fab Dahisar 600 150 80

    91188 C 2 Press N Fab Dahisar 400 150 80

    0101EC0190N C 2 Penetrical Kandivli 200 100 80

    0101EC0210N C 1 Penetrical Kandivli 100 50 40

    0101EC0200N C 1 Penetrical Kandivli 100 50 40

    33258 C 2 KVL Press Shop AS-KND 300 150 80

    11237 C 1 KVL Press Shop AS-KND 150 50 40

    Data Collection

  • 8/8/2019 Vartak College - Presentation

    42/76

    HML Analysis ofSingle Cab Welding

    AreaValue in Rs. Vendor Press shop Total parts %

    H (> 50) 26 25 51 38%

    M ( 20-50 ) 25 1 26 19%

    L (

  • 8/8/2019 Vartak College - Presentation

    43/76

  • 8/8/2019 Vartak College - Presentation

    44/76

    Line Side DOL Racks

  • 8/8/2019 Vartak College - Presentation

    45/76

    DOL Racks for Big Bins

  • 8/8/2019 Vartak College - Presentation

    46/76

    Area :

    CL / CDR Re-spot

    No. of Parts : 16

    No. of Vendors : 7

    No. of Parts : 19

    No. of Vendors : 9

    Area :

    Single Cab Cowl Stage

  • 8/8/2019 Vartak College - Presentation

    47/76

    BeforeAfter ( Removed )

  • 8/8/2019 Vartak College - Presentation

    48/76

    Benefits of DOL

    Inventory carrying cost reduced

    Inventory days reduced

    Stores space saved and in process of

    being utilizedfor in house cargo painting.

    Double handling of parts eliminated

    Possibility ofparts getting damaged due to

    double handling reduced.

    Supply module strength reduced

  • 8/8/2019 Vartak College - Presentation

    49/76

    49

    Logistics

  • 8/8/2019 Vartak College - Presentation

    50/76

    50

    INBOUND

    Customer

    Other Units

    OUTBOUND

    Supplier

    SCRAP

    OEM

  • 8/8/2019 Vartak College - Presentation

    51/76

    51

    Logistics Cost Reduction

    The Classification

    Appropriate Vehicle Selection

    Optimum Utilization of Vehicles

    Pallet / Fixture and Packaging Modification

    Vendor Base Related Initiatives

    Milk Run Implementation

  • 8/8/2019 Vartak College - Presentation

    52/76

    52

    Appropriate Vehicle Selection

  • 8/8/2019 Vartak College - Presentation

    53/76

    53

    Appropriate Vehicle Selection: The Concept

    BODY P.U. FENDER MOVEMENT , DOOR MOVEMENT

    CARGO MOVEMENT , BODY SHELL MOVEMENT

    TRANSMISSION P U NGT 520 GEARBOX

    TRAILER

    TRUCK

    1 2 3 4 5 6

    1 2 3 4 5 6 7 8

    INCREASE IN NUMBER OF FENDERS TRANSPORTED PER UNIT COST BY

  • 8/8/2019 Vartak College - Presentation

    54/76

    54

    INCREASEINNUMBER OF FENDERS TRANSPORTED PER UNIT COSTBY

    USINGTRAILERS FOR FENDER MOVEMENT

    Fenders per Truck: 48

    Freight Incurred (Rs.): 5466

    Freight per Fender (Rs.): 114

    Freight Saving per Fender (Rs.): 39 (35%)

    Fenders per Trailer: 96Freight Incurred (Rs.): 7200

    Freight per Fender (Rs.): 75

    Annualised Cost Saving for the Initiative (Rs.): 11 Lacs

    BEFORE AFTER

    Implementation: February, 2007

    INCREASE IN NUMBER OF GEAR BOXES TRANSPORTED PER UNIT COST

  • 8/8/2019 Vartak College - Presentation

    55/76

    55

    INCREASEINNUMBER OFGEAR BOXES TRANSPORTED PER UNIT COST

    BYUSINGTRAILERS FOR GEAR BOXMOVEMENT

    BEFORE AFTER

    Gear Boxes per Truck: 84

    Freight Incurred (Rs.): 5466

    Freight per Gear Box (Rs.): 65

    Freight Saving per Gear Box (Rs.): 8 (13 %)

    Gear Boxes per Trailer: 126

    Freight Incurred (Rs.): 7200

    Freight per Gear Box (Rs.): 57

    Annualised Cost Saving for theInitiative (Rs.): 3

    Lacs

  • 8/8/2019 Vartak College - Presentation

    56/76

    56

    OptimumUtilization of Vehicles: The Concept

    2 LAYER LOADING

    3RD LAYER ADDED

    SCORPIO AXLES TRANSPORTATIONFROM TWO LAYERS TO THREE

  • 8/8/2019 Vartak College - Presentation

    57/76

    57

    SCORPIOAXLES TRANSPORTATIONFROMTWO LAYERS TO THREE

    LAYERS

    Axles per Truck: 24

    Freight Incurred (Rs.): 5466

    Freight per Axle (Rs.): 228

    Freight Saving per Axle (Rs.): 62 (27%)

    Axles per Truck: 36

    Freight Incurred (Rs.): 5466

    Freight per Axle (Rs.): 166

    Annualised Cost Saving for theInitiative (Rs.): 38

    Lacs

    BEFORE AFTER

  • 8/8/2019 Vartak College - Presentation

    58/76

    58

    TRANSPORTATIONOF 25 MAXITRUCK CARGOESINSTEAD OF 15

    Cargoes per Truck: 15

    Freight Incurred (Rs.): 7615

    Freight per Cargo (Rs.): 508

    Freight Saving per Cargo (Rs.): 186 (36%)

    Cargoes per Truck: 25

    Freight Incurred (Rs.): 8059

    Freight per Cargo (Rs.): 322

    Annualised Cost Saving for theInitiative (Rs.): 28

    Lacs

    BEFORE AFTER

  • 8/8/2019 Vartak College - Presentation

    59/76

    59

    CHANGEINPACKAGINGFOR TRANSAXLE TRANSPORTATIONTO HARIDWAR

    Trans Axle per Truck: 144

    Freight Incurred (Rs.): 48000

    Freight per Trans Axle (Rs.): 333

    Freight Saving per Trans Axle (Rs.): 253 (75%)

    Trans Axle per Truck: 300

    Freight Incurred (Rs.): 24000

    Freight per Trans Axle (Rs.): 80

    Annualised Cost Saving for the Initiative (Rs.): 40 Lacs

    BEFORE AFTER

  • 8/8/2019 Vartak College - Presentation

    60/76

    BACK HAULINGOF RAWMATERIAL IN VENDORS VEHICLE

  • 8/8/2019 Vartak College - Presentation

    61/76

    61

    BACK HAULINGOF RAWMATERIALINVENDORS VEHICLE

    MAHINDRA & MAHINDRA,

    KANDIVLI

    A. R. INDS, FARIDABAD EATA PLAST, MULUND

    Net Logistic CostSaving: 2.00 Lacs

    Implementation: May, 2006

  • 8/8/2019 Vartak College - Presentation

    62/76

    62

    Logistics Activities

    Cost Reduction through negotiations with transporter Sourcing of Alternate transporter

    Better fleet utilization by loading material during return

    trip

    Optimum utilization of vehicle both in terms of volume

    & weight

    Co-ordination with 3PL (Third party logistics) operators

    & TSG (Transport Solution Group) for smooth flow of

    materials

    Design & Implementation of Milk runs

  • 8/8/2019 Vartak College - Presentation

    63/76

    63

    Implementation

    ofMilk Runs

  • 8/8/2019 Vartak College - Presentation

    64/76

    64

    Milk Run:The Concept

    POINT OF

    CONSUMPTION

    V1V2

    V3

    V4

    Considerable

    Distance

    A & B Category Parts

    Sequential Movement of Vehicle

  • 8/8/2019 Vartak College - Presentation

    65/76

    65

    Why Milk Run

    Inventory Control forHigh Value Parts

    Smooth flow of Material to eliminate

    procurement uncertainties and hassles

    Logistics Cost Reduction through optimum

    utilization of vehicles

    Eliminate obsolescence creation

    Z Sh t li t d

  • 8/8/2019 Vartak College - Presentation

    66/76

    66

    Zones Short-listed

    CHENNAI

  • 8/8/2019 Vartak College - Presentation

    67/76

    67

    Milk Run: Implementation Method

    Candidate suppliers for each location were identified Free delivery / Ex-works suppliers were segregated.

    Part list and lot sizes for each of the candidate

    suppliers were determined.

    Candidate suppliers forpilot milk run from each zone

    were identified

    Identified Suppliers were communicated regarding

    the new system and the nominated transporter.

    Appropriate vehicles for the movement from each

    zone were decided upon depending upon approximate

    tonnage

  • 8/8/2019 Vartak College - Presentation

    68/76

    68

    Pune Milk Run: Scope

    Distance From Mumbai: 200 Km No. of Vendors: 24

    No of Parts Covered: 160

    Inventory on Dec 31, 2006: 8.89 Days Frequency of Milk run: Daily

    Transporter: Onkar Roadways

    Vehicle Used: 1 or 2 Pic Ups (As Needed) Transportation Lead Time: 6 Hrs

    P Milk R V d B

  • 8/8/2019 Vartak College - Presentation

    69/76

    69

    Pune Milk Run: Vendor Base

    Vendor Location No. of Parts Frequency

    SKF Chakan 42 Daily

    PremierSeals Chinchwad 5 Alternate

    Mega Fibre Chinchwad 3 Daily

    Timeken Bearing Wadi 1 Daily

    Mohan Plastics Pimpri 3 Once in 3 Days

    Lumax Industries Chakan 11 Once in 3 Days

    Tata Ficosa Hinjewadi 1 Daily

    Shreyas Auto Tahthawade 2 Weekly

    Fitwell gasket Bhosari 13 Weekly

    TOTAL 84

  • 8/8/2019 Vartak College - Presentation

    70/76

    70

    The Pune Milk Run

    No. of Vendors: 9

    Frequency of Milk run: Daily

    Average Tonnage: 3.5 T

    Consolidation Time: 2200 Hrs 2300 Hrs

    Delivery time: 0800 Hrs

  • 8/8/2019 Vartak College - Presentation

    71/76

    71

    Daily Schedule for Pune

    Vendor Pick Up time

    Tata Ficosa 1100 Hrs

    Mega Fibre 1300 Hrs

    Timken Bearing 1500 HrsSahyog Engineering 1600 hrs

    SKF India Ltd 1700 Hrs

    Mohan Plastic 1800 HrsLumax industries 1830 Hrs

    Shreyas Auto 2000 Hrs

    PremierSeals 2100 Hrs

  • 8/8/2019 Vartak College - Presentation

    72/76

    72

    Mumbai Milk Run: Scope

    No. of Zones: 5 No. of Vendors: 110

    No of Parts Covered: 1027

    Inventory on Dec 31, 2006: 9.07 Days Frequency of Milk run: Daily

    Transporter: Abhishek Transports

    Vehicle Used: Pick Up

  • 8/8/2019 Vartak College - Presentation

    73/76

    Mumbai (Zone I) Milk Run: Vendor Base

  • 8/8/2019 Vartak College - Presentation

    74/76

    74

    Mumbai (Zone I) Milk Run: Vendor Base

    Vendor Location No. of Parts Frequency

    Rainbow Industries Goregaon (E) 32 Once in 3 days

    PMP Goregaon (E) 2 Once in week

    Accurate Springs Goregaon (E) 23 Once in 3 days

    Siddhivinayak Kandivli(E) 3 Once in 3 days

    Pariwar Kandivli(E) 4 Once in 3 days

    Panetrical Kandivli(E) 31 Once in 3 Days

    Lalit Goregaon (E) 5 Once in 3 days

    Prospect Goregaon (E) 7 Once in 3 days

    Friends Malad (E) 7 Once in 3 days

    TOTAL 114

  • 8/8/2019 Vartak College - Presentation

    75/76

    75

    Benefits of a Milk Run

    Smaller lot sizes resulting in considerable

    reduction in inventory

    Smooth regular flow of material ensuring

    hassle free procurement

    Reduction in chances of obsolescence

    creation

    Reduction in Transportation Cost

  • 8/8/2019 Vartak College - Presentation

    76/76

    76

    Thank you