SITUACION ACTUAL DE LA ACTIVIDAD: MANTENIMIENTO DE CANAL SECTOR KILKA DISTRITO DE COPORAQUE-ESPINAR-CUSCO
SUB GERENCIA DE INFRAESTRUCTURA PUBLICA
DEPARTAMENTO DE OBRAS PUBLICAS
AREA DE MANTENIMIENTO
• Ingeniero Inspector: Ing. Elías Oliver Diaz Cahuana
• Ingeniero Residente: Ing. David R. Paredes Luque
• Asistente Técnico: • Asistente Administrativo: Sr. Agustín Thea Zamabrano
• Maestro de Obra: Sr. Serapio Qquehue Qquehue
PERSONAL TECNICO:
PRESUPUESTO DE OBRA
PROYECTO:
UBICACIÓN:Departamento : CUSCOProvincia : ESPINARDistrito : COPORAQUE
TIEMPO DE EJECUCION 90 Dias Calendario ( 3 Meses )
ITEM DESCRIPCION COSTO TOTAL S/.
CD COSTO DIRECTO DE OBRA 234,213.18
GG GASTOS GENERALES 20.77% 48,646.08
P_O PRESUPUESTO DE OBRA 282,859.26
GS GASTOS DE SUPERVISIÓN 3.90% 9,134.31
GL GASTOS DE LIQUIDACIÓN 1.28% 2,997.93
GE GASTOS DE ELABORACION DEL EXP. TECNICO 2.73% 6,394.02
GE GASTOS DE EVALUACION DE EXPEDIENTE 1.34% 3,138.46
CF COSTO TOTAL FINANCIAMIENTO MUNICIPAL 304,523.98
GG = CD x 20.77%CF = CD + GG + GS + GL + GE GS = P_O x 3.90%
GL = P_O x 1.28%GE = P_O x 2.73%GE = P_O x 1.34%
RESUMEN
PRESUPUESTO DE INVERSION
: "MANTENIMIENTO DE CANAL SECTOR KILKA COMUNIDAD URINSAYA DISTRITO COPORAQUE - ESPINAR - CUSCO"
METAS DEL PROYECTO
Descripción Und. Cantidad
Captación tipo Bocatoma und 1
Desarenador Und. 1
Canal trapezoidal Mtl. 1,420.00
Toma parcelario Und. 12
Pase vehicular Und. 1
Pase peatonal Und. 1
RESUMEN DE AVANCE
FISICO
S/. % S/. % S/. % S/. %
INICIO 1,667,480.97 0.00% 0.00%
MES 1 AGOSTO 61,647.80 3.70% 61,647.80 3.70% 26,299.43 1.58% 26,299.43 1.58% -2.12%
MES 2 SETIEMBRE 193,675.65 11.61% 255,323.45 15.31% 37,829.07 2.27% 64,128.50 3.85% -11.47%
MES 3 OCTUBRE 412,293.31 24.73% 667,616.76 40.04% 58,783.99 3.53% 122,912.49 7.37% -32.67%
MES 4 NOVIEMBRE 531,604.89 31.88% 1,199,221.66 71.92% 59,505.64 3.57% 182,418.13 10.94% -60.98%
MES 5 DICIEMBRE 303,018.39 18.17% 1,502,240.04 90.09% 0.00% 182,418.13 10.94% -79.15%
MES 6 ENERO 165,240.92 9.91% 1,667,480.97 100.00% 0.00% 182,418.13 10.94% -89.06%
TOTAL C.D.1,667,480.97 1,667,480.97 100.00% 182,418.13 10.94%
VALORIZACION FISICO PROGRAMADO VALORIZACION FISICO EJECUTADAPROG. DEL MES ACUMULADO VAL. DEL MES ACUMULADO VAR. %MES
PTO APROBAD.
RESUMEN DE AVANCE FINANCIERO
S/. % S/. % S/. % S/. %
INICIO 1,917,689.29 0.00% 0.00%
MES 1 AGOSTO 145,944.97 7.61% 145,944.97 7.61% 124,617.63 6.50% 124,617.63 6.50% -1.11%
MES 2 SETIEMBRE 223,882.83 11.67% 369,827.80 19.29% 98,784.42 5.15% 223,402.05 11.65% -7.64%
MES 3 OCTUBRE 442,500.49 23.07% 812,328.29 42.36% 149,543.75 7.80% 372,945.80 19.45% -22.91%
MES 4 NOVIEMBRE 561,812.07 29.30% 1,374,140.36 71.66% 489,315.69 25.52% 862,261.49 44.96% -26.69%
MES 5 DICIEMBRE 333,225.56 17.38% 1,707,365.92 89.03% 0.00% 862,261.49 44.96% -44.07%
MES 6 ENERO 210,323.37 10.97% 1,917,689.29 100.00% 0.00% 862,261.49 44.96% -55.04%
TOTAL C.D.1,917,689.29 1,917,689.29 100.00% 862,261.49 44.96%
PTO APROBAD.
VALORIZ. FINANCIERO PROGRAMADO VALORIZACION FINANCIERO EJECUTADAVAR. %PROG. DEL MES ACUMULADO VAL. DEL MES ACUMULADOMES
PANEL FOTOGRAFICO DEL PROCESO CONSTRUCTIVO
Se Observa la charla de InducciónAntes del Inicio de los trabajos
Se Observa los Trabajos de Excavación de zanja para canal de Rectangular.