7/28/2019 HRS Presentation
1/24
IRPMU
NORTH CENTRAL RAILWAY
PROGRESS OF WORKS
ON
HATHRAS YARD
AS ON 08-06-2013
7/28/2019 HRS Presentation
2/24
Name of work
The work of addition and alteration
to signalling gears in connection with
yard remodeling and provision ofSolid State Interlocking (SSI) at
Hathras station
Plan HeadPH 16 (Traffic Facility Plan Head)
Allocation DF(3)
First included in the PB2008-09
PB Item No. (2012-13)
46 (Traffic Facility-Yard remodelling
and Others)
Sanctioned Estimated CostRs.11.15 Cr.
Date of award of Tenders/Contract
SSI being done as part of KfW project
alongwith Yard remodelling
SSI WORK AT HATHRAS (HRS)
7/28/2019 HRS Presentation
3/24
Sl. No. CabinsPresent No.
of Levers
Status of Cabins after
introduction of SSI
1 East Cabin 42 levers Cabin will not be required
2 West Cabin 35 levers Cabin will not be required
DETAILS OF HATHRAS STATION
Hathras Jn. is a 'B' class station interlocked with Colour light signaling,
having 2 cabins for train working along with automatic block working
with adjoining stations Pora on East (Kanpur side), Sasni on West (Delhi)
side and staff working .
7/28/2019 HRS Presentation
4/24
Summary for Solid State Interlocking at HATHRAS(Routes- 103)
Present
working
Hathras yard is operated through 2 cabins with lever frames
Scope Complete Indoor & Outdoor works as per approved plans
All Indoor works to be carried out in SER (ECU-36)
Comparison of various existing gears with new plan
Functions As per existing SIP As per SIP for SSI
a. Main signals 15 20b. Shunt Signals 07 19
c. Calling On Signals Nil 04
d. Routing signals 03 04
e Points Machines 26 32
f Siding points Nil 01
F Track Circuits 23 49
g No of Routes Nil 103
/
7/28/2019 HRS Presentation
5/24
SSI/HRS
Summary of the progress
CRS sanction received on 20.03.13
S&T works progress
Indoor works All the Indoor work completed, All 8 Microlocks powered Up,
Simulation wiring completed
Testing
Logic testing completed by IRPMU.
2nd round of FAT testing by IRPMU completed.
Outdoor work90% work completed.
P. Way works - Total 28 new Points to be inserted in the work (15 in Before Pre NI,
12 in Pre NI and 1 in Post NI). Total 22 points to be dismantled in the work (10in
Before Pre NI, 12 in Pre NI)
.OHE & Elect. Works Total 140 masts (including portals) to be erected.
Out of these, 125 masts erected. Old masts 10 no to be dismantled which shall becarried out in Pre-NI/NI period.
7/28/2019 HRS Presentation
6/24
SSI HRS working
MAIN ITEMS
FOR Pre Pre-NI
Engg. works S&T works Elect. & OHEworks
Before
Pre NI
Points /Turn-
outs
Insertion of 15 new
points, Dismantlingof 10 points
Fixing of 15 Point
m/cs, dismantling ofmech fittings and DC
track ckt
Associated works
like provision ofCatenary wires
and Insulators
Pre NI
12 days
Points /Turn-
outs
Insertion of 12 new
points, Dismantling
of 12 Points
Fixing of 12 Pointm/cs,
Associated works
like provision of
Catenary wiresand Insulators
NI 01
days
Points /Turn-
outs
Nil Commissioning of
SSI
Nil
Post NI
07 days
Points /Turn-
outs
Dismantling of
West Cabin and
Linking of line 3,4
and misc works
Insertion of 1 new
Point
Dismantling of
existing mech fittings
and DC track Ckt
connections Insertion
of 1 new Point
Associated works
like provision of
Catenary wires
and Insulators
7/28/2019 HRS Presentation
7/24
Detailed Scope of work along with progress for Indoor activities
Sl.
No.Description Total Qty Qty done Remarks
1 Installation of LCP TwoTwo (To be
reprogrammed
as per SSI)
To bereprogrammed
with SSI
2Erection of relays racks, CT racks, M Lock
racks13 racks 13 racks
Completed
3 Termination in CT rack, Wiring/jumpering ofrelays, Wiring of M Lock rack
13 racks 13 racks Completed
4Installation of power supply (IPS) along with
AT1 set at ECU-36 Completed Completed
5 Supply of Data Logger & installation One Maint. PC NilTo be done with
SSI
6 Block instrument installation & wiring N/A N/A
Train Staff
system between
Hathras and
Hathras Qila
7 Fixing of Telecom Equipments 1 Set
Completed
with Auto
Signalling
Completed
7/28/2019 HRS Presentation
8/24
Detailed Scope of work along with progress for Indoor activities
Sl.No.
Description Total Qty Qty done Remarks
08 Simulation Testing (SAT) 01 Lot (103 routes)To be done
after FAT
To start on 10.06.13
09 Testing by Operating Deptt. 01 Lot (103 routes)To be done
after SAT
To be done after SAT
7/28/2019 HRS Presentation
9/24
7/28/2019 HRS Presentation
10/24
ADVANTAGES OF SSI
The major advantages of commissioning of HRS SSI can be divided in the
following parts:-
Safety Benefits
Manpower saving
Operational Benefits
Maintenance Benefits
1. Safety Benefits
Removal of worn out lever frames and mechanical rodding.
After commissioning of SSI, existing East & West Cabins and SM
Slide Frame will be removed completely and all the operations shall bedone from the LCPs provided in the ASM room of HRS station.
After SSI complete yard and all the running will be DC track circuited
from Home to Home. Presently Hathras Qila side branch line, line no 5
and 6 are non- track circuited.
2. Manpower saving
Complete elimination of operation from the East and West cabins will
result in saving of manpower involved in operation at these cabins
round the clock.
7/28/2019 HRS Presentation
11/24
7/28/2019 HRS Presentation
12/24
Maintenance Benefits
After commissioning of SSI at HRS, all departments will bebenefitted from maintenance point of view.
1. S&T Department
Improvement in cable maintenance after laying of New cables in theentire yard.
Improvement in maintenance of points after provision of point
machines in place of old & worn out rod operated mechanical points.
Replacement of steel/wooden turnouts by PRC turnouts having better
reliability of points.
Maintenance PC/Data logger for the entire system facilitating
predictive maintenance & monitoring.
Provision of Stabilised power supply in 1+1 configuration through IPS,
having 100% standby.Provision of glued joints for track circuiting.
2. Engg DepartmentReplacement of steel/wooden turnouts by PRC turnouts having betterreliability.
3. TRD Department
Change in sub section plan of OHE of the yard having more flexibility
from operation and maintenance point of view.
7/28/2019 HRS Presentation
13/24
Before Pre-Pre-NI( Blocking of line no 5
and 6)
Work involved
Insertion of 8 points, fixing of point machines and its testing
electrically by 110 V i.e. 213, 283, 285 A, 285 B, 287 A, 287 B,
289 A, 289 B( As per proposed SIP)
Dismantling of two points i.e. 33 E and 7 E ( As per existing
SIP)
Energization of 12 track circuits
7/28/2019 HRS Presentation
14/24
Works done Before Pre Pre-NI
(Blocking of line no . 5 and 6)Day Point (s)
already
inserted
Point (s) already
dismantled
Track circuit
already
energized ( in
nos)
Signal already
erected (in
nos)
Blockingof line
no. 5
and 6
213, 283, 285A, 285 B, 287 A,
287 B, 289 A,
289 B (Total 8
nos.)
33E, 7E (Twonos.) C3T, 3T, CLT1,CLT2, CLT3,
285T, 283T,
289 AT, 297
AT, 287T,
CL3T2, CL3T3
(12 nos.)
14
7/28/2019 HRS Presentation
15/24
7/28/2019 HRS Presentation
16/24
Works involved during Pre Pre-NI
Day Point (s) to be
inserted
Point (s) to be
dismantled
Track circuit
energized
Signal
erection
D-23 291A 7E/Lock8 (east
end)
--
D-22 209 B 28L27(E) CL2T1, CL2T2,CL2T3
D-21 209A 11L10, 19L22 209 BT S-13
D-20 211,296 11L10
D-19 215 K-1/1-K 8T,215T
D-18 207 21/Lock 20 205T
7/28/2019 HRS Presentation
17/24
7/28/2019 HRS Presentation
18/24
During Pre NI ( 12 days)
Work Involved
Insertion of 8 point, fixing of point machines and its testing
electrically by 110 V i.e. 201b, 299b on line no. 1 and 201a,
203, 295a,295 b, 297b, 299a on line no. 2.
Dismantling of 8 points i.e. Pt29E, Pt25WL29E on line no 1,
Pt29EL22, Pt28EL32E, Pt25EL24E, Pt19WL18W, Pt28WL24W,
Pt25WL20W on line no. 2.
Energization of 17 no of track circuits.
7/28/2019 HRS Presentation
19/24
7/28/2019 HRS Presentation
20/24
Day Point (s) to be
inserted
Point (s) to be
dismantled
Track circuit
energized
Signal
erection
D-6 295 B Pt 29 Trailing 295BT
D-5 295 A, 203 -- 295AT, 203T
D-4 25 W connected
to line no. 1
D-3 25 W connected
to line no. 2
297 BT
D-2 28W connected
to line no. 2
298 BT
D-1 -- Pt 25(line 2) eastend, Pt 28 (line
2) east end, Pt
28 (line 3) west
end
298 AT,202BT, 202AT
7/28/2019 HRS Presentation
21/24
7/28/2019 HRS Presentation
22/24
7/28/2019 HRS Presentation
23/24
Post NI ( 7 days)
Work Involved
Dismantling of West Cabin building
Dismantling of 35 levers and associatedroddings.
Insertion of Point no. 291 A
7/28/2019 HRS Presentation
24/24
Works involved during Post NIDay Point (s) to be inserted
Point (s) to be dismantled
Track circuit
energized
Remarks
D+1 Dismantling of West Cabin,
Dismantling of 32 levers and its
associated rod dings, Linking of
line no 3 and 4 at west end.
Testing of line no. 3 , 4, 5 and 6.
Line no. 4 will
remain
suspended
due to
obstruction
of West cabin
and levers,
roddings etc
D+2
D+3
D+4 291T,295BT
D+5
D+6
D+7 Testing of Line no 4