METRADOSOBRA: CONSTRUCCION DE PISTAS Y VEREDAS CALLE NAYLAMPUBICACIN:LOCALIDADDISTRITOPROVINCIA DEPARTAMENTODIMENSIONES/ELEMENTOSN REPET.ELEMMETRADOFACTOR CANT.LONGANCHO ALTOESPESORAREAVOLUMENNPART.DESCRIPCION(m)(m)(m)(m)(m2)(m3)UNIDADPARCIALTOTALHU.1OBRAS PROVISIONALES,TRABAJOS PRELIMINARES,SEGURIDAD Y SALUDHU.1.1TRABAJOS PRELIMINARESHU.1.1.1LIMPIEZA DEL TERRENOHU.1.1.1.1.ELIMINACION DE BASURA Y ELEMENTOS SUELTOS Y LIVIANOSPAVIMENTO CALLE NAYLAMP(AREA CAD)1.00420.481.00(m2)420.48ESTACIONAMIENTO(AREA CAD)1.0041.155.00205.751.00(m2)205.75626.23HU.1.2DEMOLICIONESVEREDAS(AREA CAD)CALLE GRAU-VEREDA1.002.000.1078.657.871.00(m3)7.87CALLE SUCRE-VEREDA1.002.000.10115.8311.581.00(m3)11.58PASAJE1.003.000.10130.2413.021.00(m3)13.02CALLE NAYLAMP-VEREDA1.002.000.10158.2215.821.00(m3)15.8248.29HU.1.3TRAZOS,NIVELES Y REPLANTEOHU.1.3.1TRAZOS,NIVELES Y REPLANTEO PRELIMINARVEREDAS(AREA CAD)CALLE GRAU-VEREDA1.0078.651.00(m2)78.65CALLE SUCRE-VEREDA1.00115.831.00(m2)115.83PASAJE1.00130.241.00(m2)130.24PAVIMENTO CALLE NAYLAMP(AREA CAD)1.00420.481.00(m2)420.48ESTACIONAMIENTO(AREA CAD)1.0041.155.00205.751.00(m2)205.75950.95HU.1.3.2REPLANTEO DURANTE EL PROCESO1.001.00(m2)VEREDAS(AREA CAD)CALLE GRAU-VEREDA1.0078.651.00(m2)78.65CALLE SUCRE-VEREDA1.00115.831.00(m2)115.83PASAJE1.00130.241.00(m2)130.24PAVIMENTO CALLE NAYLAMP(AREA CAD)1.00420.481.00(m2)420.48ESTACIONAMIENTO(AREA CAD)1.0041.155.00205.751.00(m2)205.75950.95HU.2PISTAS Y VEREDASHU.2.1MOVIMIENTO DE TIERRAHU.2.1.1CORTE CON ELIMINACION LATERAL VEREDAS(AREA CAD)CALLE GRAU-VEREDA1.000.2078.651.00(m3)15.73CALLE SUCRE-VEREDA1.000.20115.831.00(m3)23.17PASAJE1.000.20130.241.00(m3)26.05PAVIMENTO CALLE NAYLAMP(AREA CAD)1.000.40420.481.00(m3)168.19ESTACIONAMIENTO(AREA CAD)1.0041.155.000.40205.751.00(m3)82.30JARDINES(MATERIAL)1.000.2058.4411.691.00(m3)11.69327.12

HU.2.1.3ELIMINACION DE MATERIAL EXCEDENTE 1.25ESP.315.431.00(m3)394.29394.29

HU.2.2BASEHU.2.2.1BASE O AFIRMADO(PAVIMENTO+ESTACIONAMIENTO)ESTACIONAMIENTO1.000.20205.751.00(m2)205.75PAVIMENTO1.000.20420.481.00(m2)420.48626.23

HU.2.3VEREDASLOSACALLE GRAU-VEREDAHU.2.3.1CONCRETO FC=175KG/CM2 1.0078.651.00(m2)78.65HU.2.3.2ENCOFRADO Y DESENCOFRADO DE VEREDAS UA32.930.4013.171.00(m2)13.17TRANSVERSALES CADA 3 ML2.000.100.2011.00(m2)2.2015.37HU.2.3.3SELLADO DE JUNTAS EN VEREDAS1.0032.931.00(m)32.93HU.2.3.4PISO FROTACHADO CEMENTO PULIDO EN VEREDAS1.0032.932.9095.501.00(m2)95.50UACALLE GRAU-VEREDAHU.2.3.1CONCRETO FC=175KG/CM2 1.0032.930.206.591.00(m2)6.59LOSACALLE SUCRE-VEREDAHU.2.3.1CONCRETO FC=175KG/CM2 1.00115.831.00(m2)115.83HU.2.3.2ENCOFRADO Y DESENCOFRADO DE VEREDAS1.0052.700.105.271.00(m2)5.27 UA52.700.4021.081.00(m2)21.08TRANSVERSALES CADA 3 ML2.130.100.2117.57(m2)3.7424.82HU.2.3.3PISO FROTACHADO CEMENTO PULIDO EN VEREDAS1.0052.702.13112.251.00(m2)112.25HU.2.3.4SELLADO DE JUNTAS EN VEREDAS1.0052.701.00(m)52.70UACALLE SUCRE-VEREDAHU.2.3.1CONCRETO FC=175KG/CM2 1.0052.700.2010.541.00(m2)10.54LOSAPASAJEHU.2.3.1CONCRETO FC=175KG/CM2 1.00130.241.00(m2)130.24HU.2.3.2ENCOFRADO Y DESENCOFRADO DE VEREDAS1.0033.410.103.341.00(m2)3.34 UA33.410.4013.361.00(m2)13.36TRANSVERSALES CADA 3 ML3.000.100.3011.14(m2)3.3416.71HU.2.3.3PISO FROTACHADO CEMENTO PULIDO EN VEREDAS1.0033.413.00100.231.00(m2)100.23HU.2.3.4SELLADO DE JUNTAS EN VEREDAS1.0033.411.00(m)33.41UACALLE SUCRE-VEREDAHU.2.3.1CONCRETO FC=175KG/CM2 1.0033.410.206.681.00(m2)6.68RESUMENCONCRETO FC=175KG/CM2 (m2)348.53ENCOFRADO Y DESENCOFRADO DE VEREDAS(m2)56.90PISO FROTACHADO CEMENTO PULIDO EN VEREDAS(m2)307.98SELLADO DE JUNTAS EN VEREDAS(m)119.04

HU.2.4PISTASHU.2.4.1PAVIMENTO DE CONCRETO+ESTACIONAMIENTOHU.2.2.3CONCRETO F'C=210KG/CM2 PARA PAVIMENTO+ESTACIONAMIENTO1.00626.231.00(m2)626.23626.23HU.2.2.4ENCOFRADO Y DESENCOFRADO PAOS PAVIMENTO+ESTACIONAMIENTO1.00459.250.2091.851.00(m2)91.8591.85HU.2.4.2SELLADO DE JUNTAS EN PAVIMENTO+ESTACIONAMIENTO1.00459.251.00(m)459.25459.25

HU.2.5SARDINELESHU.2.5.1CONCRETO PARA SARDINEL1.00153.630.150.306.911.00(m3)6.916.91HU.2.5.2ENCOFRADO PARA SARDINEL1.00153.630.2030.731.00(m2)30.7330.73HU.2.5.3TARRAJEO EN CARA INTERIOR Y EXTERIOR DE SARDINELES1.00153.630.1523.041.00(m2)23.0423.04HU.2.5.3SELLADO DE JUNTAS EN SARDINEL1.00153.631.00(m)153.63153.63

HU.2.6BARANDAS DE ESCALERAS DE TUBERIA DE 3"1.0025.481.00(m)25.4825.48

HU.2.7RAMPAS

HU.2.7.1CONCRETO F'C=175KG/CM2 EN RAMPASRAMPA CALLE SUCRE P=10%1.001.502.900.150.331.00(m3)0.33RAMPA CALLE SUCRE P=12%(MARTILLO)1.001.251.000.150.091.00(m3)0.09RAMPA CALLE GRAU P=10%1.001.502.900.150.331.00(m3)0.33RAMPA CALLE GRAU P=10%1.005.202.290.432.541.00(m3)2.54RAMPA CALLE NAYLAMP P=10%(MARTILLO)1.002.301.000.230.261.00(m3)0.26RAMPA CALLE NAYLAMP P=10%1.001.701.000.250.211.00(m3)0.21RAMPA CALLE NAYLAMP P=10%1.003.401.000.490.841.00(m3)0.84RAMPA PASAJE P=6.3%1.003.0010.000.639.451.00(m3)9.4514.06

HU.2.7.2ENCOFRADO PARA RAMPASRAMPA CALLE SUCRE P=10%1.001.490.150.112.00(m2)0.22RAMPA CALLE SUCRE P=12%(MARTILLO)1.001.240.150.092.00(m2)0.19RAMPA CALLE GRAU P=10%1.001.490.150.112.00(m2)0.23RAMPA CALLE GRAU P=10%1.005.180.150.402.00(m2)0.79RAMPA CALLE NAYLAMP P=10%(MARTILLO)1.002.290.230.262.00(m2)0.53RAMPA CALLE NAYLAMP P=10%1.001.680.250.212.00(m2)0.41RAMPA CALLE NAYLAMP P=10%1.003.360.490.822.00(m2)1.65RAMPA PASAJE P=6.3%1.009.980.633.142.00(m2)6.2910.30HU.2.7.3BRUAS DE 2CM CADA 0.15M1.002.905.00(m)14.501.001.004.17(m)4.171.002.905.00(m)14.501.002.2917.33(m)39.691.001.007.67(m)7.671.001.005.67(m)5.671.001.0011.33(m)11.331.0010.0010.00(m)100.00197.53

HU2.8JARDINES(MATERIAL)1.000.2058.4411.691.00(m3)11.6911.69

HU3.0.GRADASHU3.0.1CONCRETO F'C=175KG/CM2 EN GRADAS1.0011.850.250.080.251.00(m3)0.251.002.371.500.150.531.00(m3)0.531.009.680.250.080.201.00(m3)0.201.002.421.200.150.441.00(m3)0.441.006.480.500.230.761.00(m3)0.761.003.241.100.150.531.00(m3)0.532.71

HU3.0.2ENCOFRADO PARA GRADAS1.001.502.373.561.00(m2)3.561.001.202.422.901.00(m2)2.901.001.103.243.562.00(m2)7.1313.59

RESUMEN DE METRADOSOBRA: CONSTRUCCION DE PISTAS Y VEREDAS CALLE NAYLAMPUBICACIN:LOCALIDADDISTRITOPROVINCIA DEPARTAMENTOMETRADO

NPART.DESCRIPCIONUNIDADTOTALHU.1OBRAS PROVISIONALES,TRABAJOS PRELIMINARES,SEGURIDAD Y SALUDHU.1.1TRABAJOS PRELIMINARESHU.1.1.1LIMPIEZA DEL TERRENOHU.1.1.1.1.ELIMINACION DE BASURA Y ELEMENTOS SUELTOS Y LIVIANOS(m2)626.23HU.1.2DEMOLICIONES(m3)48.29HU.1.3TRAZOS,NIVELES Y REPLANTEOHU.1.3.1TRAZOS,NIVELES Y REPLANTEO PRELIMINAR(m2)950.95HU.1.3.2REPLANTEO DURANTE EL PROCESO(m2)950.95HU.2PISTAS Y VEREDASHU.2.1MOVIMIENTO DE TIERRAHU.2.1.1CORTE CON ELIMINACION LATERAL (m3)327.12HU.2.1.3ELIMINACION DE MATERIAL EXCEDENTE (m3)394.29

HU.2.2BASEHU.2.2.1BASE O AFIRMADO(PAVIMENTO+ESTACIONAMIENTO)(m2)626.23HU.2.3VEREDASCONCRETO FC=175KG/CM2 (m2)348.53ENCOFRADO Y DESENCOFRADO DE VEREDAS(m2)56.90PISO FROTACHADO CEMENTO PULIDO EN VEREDAS(m2)307.98SELLADO DE JUNTAS EN VEREDAS(m)119.04

HU.2.4PISTASHU.2.4.1PAVIMENTO DE CONCRETO+ESTACIONAMIENTOHU.2.2.3CONCRETO F'C=210KG/CM2 PARA PAVIMENTO+ESTACIONAMIENTO(m2)626.23HU.2.2.4ENCOFRADO Y DESENCOFRADO PAOS PAVIMENTO+ESTACIONAMIENTO(m2)91.85HU.2.4.2SELLADO DE JUNTAS EN PAVIMENTO+ESTACIONAMIENTO(m)459.25

HU.2.5SARDINELESHU.2.5.1CONCRETO PARA SARDINEL(m3)6.91HU.2.5.2ENCOFRADO PARA SARDINEL(m2)30.73HU.2.5.3TARRAJEO EN CARA INTERIOR Y EXTERIOR DE SARDINELES(m2)23.04HU.2.5.3SELLADO DE JUNTAS EN SARDINEL(m)153.63

HU.2.6BARANDAS DE ESCALERAS DE TUBERIA DE 3"(m)25.48

HU.2.7RAMPAS

HU.2.7.1CONCRETO F'C=175KG/CM2 EN RAMPAS(m3)14.06

HU.2.7.2ENCOFRADO PARA RAMPAS(m2)10.30HU.2.7.3BRUAS DE 2CM CADA 0.15M(m)197.53

HU2.8JARDINES(MATERIAL)(m3)11.69

HU3.0.GRADASHU3.0.1CONCRETO F'C=175KG/CM2 EN GRADAS(m3)2.71

HU3.0.2ENCOFRADO PARA GRADAS(m2)13.59