THE STATE ATOMIC ENERGY CORPORATION ROSATOM
2019
Rosatom América Latina
Simpósio – A Energia Nuclear no Brasil
Ruan Nunes de SouzaVice Presidente
A Tecnologia Nuclear
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein. 2
ROSATOM is the world’s only company of a complete nuclear power cycle
Uranium
Mining
Enrichment
and Conversion
Fuel
Fabrication
Operation and
Maintenance
Back End
Equipment
Manufacturing
Power
Generation
Nuclear
Medicine Gamma
Irradiation
Research
Reactors
Isotopes
U-
235
Nuclear
icebreaker
fleet
ENERGY
SECTOR
NON-
ENERGY
SECTOR
NPP Construction
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein. 3
ROSATOM: energy major with global outreach
29.1 GW
OF INSTALLED
CAPACITIES OPERATED
IN RUSSIA
18.9 %
OF TOTAL RUSSIAN
ELECTRICITY
GENERATED BY
ROSATOM
14 %OF GLOBAL
URANIUM EXTRACTION
№1BY NPP UNITS
IN INTERNATIONAL
BACKLOG
36 % OF GLOBAL
ENRICHMENT
MARKET
U-235
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein. 4
ROSATOM global: VVER success story
77VVER UNITS
CONSTRUCTED
6
INDIA
IRAN
RUSSIA
UKRAINESLOVAKIA
CZECH
REPUBLIC
BULGARIA
ARMENIA
GERMANY
HUNGARYCHINA
FINLAND
6
6
2
41
2
215
6
4
23
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein. 5
ROSATOM: keeping the pace
IN IMPLEMENTATION
PORTFOLIO OVERSEAS
36
Bangladesh, Rooppur
NPP, VVER-1200
Hungary, Paks NPP
VVER-1200
India, Kudankulam NPP
VVER-1200
VVER
UNITSChina, Tianwan NPP
VVER-1200
Belarus, Ostrovets NPP
VVER-1200
Turkey, Akkuyu NPP
VVER-1200
The content of this presentation is for discussion purposes only, shall not be considered as an offer and doesn’t lead to any obligations to Rosatom and its affiliated companies. Rosatom disclaims all responsibility for any and all mistakes, quality and completeness of the information.
World’s first floating nuclear power plant FNPP Akademik Lomonosov
THE FIRST-OF-A-KIND
PROJECT
AKADEMIK LOMONOSOV
FNPP THE FIRST-OF-A-KIND
PROJECT
2019COMMISSIONING DATE:
After commissioning FNPP will replace
aging power generating capacities
providing electrical power to the city
of Pevek, one of the major Arctic ports in
the North-East of Russia
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein. 7
Flexible, tailor-made small NPP solutions, based on RITM series SMR
TECHNICAL PARAMETRS
Electric capacity 100 MW
Refueling cycle up to 10 years
Design life 60 years
Displacement 12,000 m tons
Length 112 m
Beam 25 m
Draught 4.5 m
TECHNICAL PARAMETRS
Electric capacity 114 MW (2 x 57 MW)
Thermal capacity 350 MW (2 x 175 MW)
Refueling cycle up to 6 years
Design life 60 years
Capacity factor 90%
Plant area 13 acres (0.05 km2)
Construction
period3 - 4 years
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein.
Potential models of cooperation
Rosatom EPC projects portfolio:
ROSATOM IS FLEXIBLE IN THE PROJECT IMPLEMENTATION MODELS
Rosatom BOO projects portfolio:
EPC: ENGINEERING,
PROCUREMENT, CONSTRUCTION
EPC turnkey design and construction
The constructed object is handled
to the customer for operation
Financing is arranged by the customer
(project financing)
NPP vendor and other parties become
shareholders of the JV
JV attracts investments for the project implementation
ROI is realized by a PPA mechanism with
the government or a major generation/
transmission / consumer company
NPP vendor shares operational and project
management & completion risks with the local
investors
The customer is responsible for licensing,
site and infrastructure
ROSATOM PROPOSES THE FOLLOWING CONTRACTING MODELS
WITHIN FOREIGN PROJECTS IMPLEMENTATION:
BOO:BUILD, OWN, OPERATE
8
Belarus
Egypt
India
Bangladesh
Hungary
Finland Turkey
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein.
Potential models of cooperation
ROSATOM PROPOSES THE FOLLOWING CONTRACTING MODELS
WITHIN FOREIGN PROJECTS IMPLEMENTATION:
Co-engineering modelWet leasing of FNPP
Rosatom provides design and
manufacturing of NPP
NPP vendor and other parties
form a project company
Project company owns NPP,
provides maintenance
Co-engineering implies high level of local
labor and manufacturing involvement
SMR
NPPbusiness
models
Rosatom owns NPP,
maintains and manages
fuel campaign
Rosatom bears NPP
transportation and operational
risks
Customer guaranties purchase
of electrical power, confirms power grid
connection, operation and security of NPP
9
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein. 10
ROSATOM: team of professionals
More than 3300 employees
with PhD and Doctor Degrees
47% employees involved
in educational programs
138 mln USD
for Rosatom internal
social programs
More than 31% of young
specialists of employees
aged under 35
255 000 employees
All data per 2017 (Rosatom financial report) converted from RUB
ROSATOM’s
GLOBAL SUCCESS -
IS A TEAMWORK OF
PROFESSIONALS
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein. 11
Young specialists and professors:Basis of National HRD Program
11
Preparation Course
Bachelor Degree
Master Degree
Specialist Degree
PhD DegreeLONG-RUN PROGRAMS
SHORT-RUN PROGRAMS1-6-month short-term programmes for
personnel with various backgrounds
Practical training at lab sites of the Corporation and partner universities
Training at lab sites of the Corporation and partner universities
Summer/winter specialized schools
Open lectures
Conferences and workshops in partner countries
Trainings and technical tours for
professors
1st year 2d year 3d year 4th year 5th year 6th year 7th year 8th year 9th year 10th year
ROSATOM KEY APPROACH to personnel training – EMBRACES ALL
STAGES OF HUMAN RESOURCES DEVELOPMENT – from higher
specialized education (technical college – university) to training for positions
This approach provides for career
planning for every employee – from
line personnel to top managers.
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein. 12
Response to Nuclear Energy Opponents
After Fukushima accident nuclear power came
under severe criticism in mass media500over
governmental organizationsand activists groups oppose nuclear energy globally
In most cases the arguments of nuclear critics are far-fetched or groundless
ROSATOM HAS RICH EXPERIENCE IN DISPUTES WITH NUCLEAR NAYSAYERS
AND KNOWS HOW TO ADDRESS CRITICISM EFFICIENTLY
NOWADAYS NUCLEAR POWER PROJECTS FACE STRONG CRITICISM FROM GROUPS OF
ENVIRONMENTAL ACTIVISTS, LOBBYISTS GROUPS OF INTERESTS AND COMPANIES
PROMOTING OTHER POWER GENERATING TECHNOLOGIES INCLUDING RENEWABLES
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein. 13
Fukushima Lessons Learnt
ALL VVER BASED NPPs IN OPERATION OR UNDER CONSTRUCTION
ARE IN COMPLIANCE WITH THE LATEST SAFETY REQUIREMENTS
Long-term cooling of reactor core without power supply
Long-term residual heat removal independent of primary ultimate heat sink (natural or artificial water body, air)
Maintaining reactor containment integrity after a potential
core meltdown accident
All technical means for management DEC should
be protected from the effects of accidents by
using mobile means stored in a safe places.
Safety systems of a single unit of an
NPP must be independent from the
safety systems of another unit deployed
on the same site
The defense-in-depth concept and
the practical elimination of
accidents with early or large
release are fully applicable to the
spent fuel pool
The content of this presentation is for discussion purposes only. It does not constitute an offer of services, nor does it impose, or lead to, any obligations on Rosatomor its affiliates. Rosatom expressly disclaims responsibility for any errors, inaccuracies or omissions in respect of the information contained herein.
RESULT ROSATOM’S RESPONSE
14
Crisis Management
Response Plan Crisis Sommunications SchemeCritic Situation Analysis
IN CASE OF AN UNEXPECTED EMERGENCY, ROSATOM WILL DELIVER A FAST RESPONSE
THE KUDANKULAM NUCLEAR POWER PLANT (INDIA) CASE STUDY
The local community rallied to
block the Kudankulam NPP
construction site
Rosatom arranged a tour for the
local anti-nuclear activists to the
Tianwan NPP, convincing them
that the Russian nuclear
technologies comply with the
highest safety standards
CRISIS1 2 3
Two units of the Kudankulam
NPP are currently online
Lack of knowledge instills fears.
Rosatom educates people on
how safe NPP’s are, dispelling
those fears and earning loyalty of
the local population.
Nowadays, sailors use the
Kudankulam NPP as a beacon,
but, once commisioned, the plant
will serve a much greater cause