Metrado San Nicolás Estructuras Polideportivo

Post on 11-Sep-2015

226 views 0 download

description

Polideportivo

Transcript of Metrado San Nicolás Estructuras Polideportivo

POLIDEPORTIVOPROYECTO: ADECUACIN, MEJORAMIENTO Y SUSTITUCION DE LA INFRAESTRUCTURA EDUCATIVA DE LA I. E. " SAN NICOLAS"

OBRA: POLIDEPORTIVOESTRUCTURAS 02.04TRAZO Y REPLANTEO GENERAL PARA TODO EL TERRENO CODDESCRIPCIONUnd.CantidadLAHreaMETRADOTOTAL02.04.01TRAZO Y REPLANTEO C/EQUIPOm21,755.62 40.4843.371,755.62

03MOVIMIENTO DE TIERRAS03.02EXCAVACIONES03.02.01EXCAVACION DE ZANJAS Y ZAPATAS RT= 2.0 KG/CM2 H=2.0 mm3518.13ZapatasZ-116.002.402.301.25110.40Z-24.001.701.901.2516.15Z-312.001.301.301.2525.35Z-42.006.202.251.2534.88Z-52.004.901.401.2517.15Z-62.002.302.301.2513.23CimentacionesEJE AK1.0018.440.601.4015.49EJE AJ1.0019.590.601.2014.101.002.150.401.100.951.004.731.001.205.67

EJE AH1.0027.900.400.859.491.005.551.000.854.721.000.670.184.100.48

EJE AA1.0018.440.601.4015.491.003.000.401.101.322.000.780.781.101.32

EJE AB1.0019.590.601.2014.101.001.980.401.100.871.003.150.401.101.391.001.001.001.101.101.001.000.501.100.55

EJE AC1.0027.900.400.859.491.005.551.000.854.721.000.670.184.100.48

EJE A11.0016.100.601.4013.52EJE A81.005.150.601.404.33EJE A101.009.250.401.104.071.000.780.781.100.661.001.001.001.101.101.001.001.181.101.29

EJE A111.006.470.401.102.851.0022.651.254.15117.501.003.951.002.108.301.000.780.781.100.661.001.000.501.100.55

EJE A41.003.770.401.101.661.009.450.601.106.24EJE A51.002.430.401.101.071.009.450.601.106.24

SECCION X-X y SECCION Y - Y1.001.400.400.600.342.000.550.400.600.262.000.500.400.600.246.000.300.400.600.432.003.000.400.601.442.002.750.400.601.322.002.100.400.601.01Interiores Seccin C-C4.003.880.401.106.824.000.880.401.101.544.000.850.401.101.49SECCION A-A1.0019.000.551.0010.452.001.750.551.001.931.001.200.551.000.662.001.200.551.001.32

03.03RELLENO03.03.01RELLENO C/MATERIAL PROPIO PARA RELLENAR ZANJASm368.67ZapatasreaEje A-A1.001.300.500.65Interiores4.002.720.505.441.002.320.501.161.002.070.501.041.001.360.500.68Exteriores1.003.480.652.266.002.070.658.071.003.410.652.22Eje A-B2.000.480.500.483.000.390.500.581.000.360.500.181.002.850.501.43Eje A -C1.006.200.503.101.002.010.501.001.006.200.654.03Eje 1d1.001.630.500.821.004.070.652.65Eje 1e1.002.290.501.141.002.290.651.49Eje 1f1.002.290.501.141.002.290.651.49Eje 1g1.006.200.654.031.001.630.500.82Eje A-J2.000.480.500.483.000.390.500.581.000.360.500.18Eje A-K1.001.300.500.65Interiores4.002.720.505.441.002.320.501.161.002.070.501.041.001.360.500.68Exteriores1.003.480.652.266.002.070.658.071.003.410.652.22

03.03.03RELLENO CON AFIRMADO E=4" PARA PISOS INTERIORES Y EXTERIORESm3hrea410.13Graderas4.002.000.753.6421.86Nota: Se ha considerado las alturas por cada rea que4.001.000.4510.0018.00representa un paso de las graderas4.002.000.4510.2436.864.001.000.4510.0618.104.001.000.457.2313.014.001.000.5046.9493.89reas de ambientes de Polideportivorea0.0SS.HH. Discapacitados Hombres1.001.005.740.150.86SS.HH. Hombres1.001.0023.390.153.51Almacen1.001.0015.820.152.37Topico1.001.0011.920.151.79Ingreso1.001.0027.750.154.16Duchas+Camerino+Vestuario+SS.HH. Discapacitados1.001.0062.870.159.43Ingreso N 011.001.0039.620.155.94Almacen 1.001.0018.050.152.71Vestidores1.001.0014.580.152.19Escenario1.001.00155.340.1523.30Vestidores1.001.0014.580.152.19Hall de Servicio+Plataforma de Ingreso1.001.0038.820.155.82Vestuario Mujeres+Camerino+Duchas+SS.HH. Discapac.1.001.0090.140.1513.52Ingreso N 021.001.0027.750.154.16Administracin1.001.0028.220.154.23SS.HH. Mujeres1.001.0026.430.153.96SS.HH. Discapacitados1.001.005.560.150.83Hall1.001.0015.640.152.35Area deportiva1.001.00738.720.15110.81Ingreso Principal1.001.0028.510.154.28

03.05ELIMINACION DE MATERIAL EXEDENTE03.05.02ACARREO INTERNO, MATERIAL PROCEDENTE DE DEMOLICIONm3539.34Volumen de excavacin estruc. Proyectada1.20449.45539.34

03.05.02ELIMINACION DE MATERIAL EXEDENTEm3539.34Volumen de excavacin estruc. Proyectada1.20449.45539.34Volumen de excavacin excedente de excavacion masiva c/maquinaria1.15-ERROR:#REF!ERROR:#REF!

04OBRAS DE CONCRETO SIMPLE04.01SOLADOS04.01.01SOLADO PARA CIMIENTOS CORRIDOS E=4" MEZCLA 1:12 CEMENTO:HORMIGONm2271.10ZapatasZ-116.002.402.3088.32Z-24.001.701.9012.92Z-312.001.301.3020.28Z-42.006.202.2527.90Z-52.004.901.4013.72Z-62.002.302.3010.58CimientosEJE A81.0019.000.5510.45EJE AH2.0013.600.4010.881.001.75EJE AJ1.0038.390.6023.03EJE AC2.0013.600.4010.88EJE AB1.0038.390.6023.03EJE 11.0015.281.2519.10

04.01.02FALSO CIMIENTO F'C=80 KG/CM2 + 30% P.G. MX=6"m365.66Corte C2-C21.002.951.101.003.251.004.731.101.005.20Corte F-F1.004.301.001.556.671.004.301.001.556.67Seccin 1-11.0022.651.551.2543.88

04.02CIMIENTOS CORRIDOS03.03.00CIMIENTO CORRIDO: CONCRETO f'c=100 kg/cm2 +30% P.G.m3195.39Seccin BBEje AH y Eje AC8.005.530.400.8014.148.000.800.400.802.054.001.300.400.801.66Seccin CCEje AB y Eje AJ2.003.830.400.802.452.000.880.400.800.562.000.850.400.800.542.003.680.400.802.351.001.890.400.800.601.002.420.400.800.772.003.830.400.802.452.000.880.400.800.562.000.850.400.800.541.003.680.400.801.181.001.790.400.800.571.002.430.400.800.78Eje AA1.003.000.400.800.96Eje AB1.003.150.400.801.01Eje A111.003.600.400.801.151.002.880.400.800.92Secciones cuadradas1.000.780.780.400.241.001.000.630.800.50Seccin DDGraderas4.004.530.600.808.694.005.330.600.8010.224.0010.620.600.8020.39rea4.000.801.254.01Seccin EEEje AJ, entre Eje A09 y Eje 101.002.180.400.800.70Eje AB, entre Eje A09 y Eje 101.001.980.400.800.63Eje A10, entre Eje AA y Eje AB1.003.600.400.801.151.001.001.000.800.801.000.780.780.800.48Seccin FFSeccin AC y AD1.003.381.000.802.70Seccin AH y AI1.001.001.180.800.941.004.301.000.803.441.000.671.180.800.63Seccin C1-C10.0Eje A10, entre Eje AB y Eje AC1.002.700.500.801.08Eje A10, entre Eje AI y Eje AJ1.003.080.500.801.23Seccin C2-C20.0Eje AJ, entre Eje A10 y Eje A111.004.731.000.502.36Eje A11, entre Eje AI y Eje AJ1.002.951.000.501.48Seccin 1-10.0Eje A11, entre Eje AC y Eje AI1.0022.651.250.8022.65Seccin X-Xrea2.002.751.9910.922.002.101.998.341.001.801.993.57Seccin Y-Yrea10.001.401.9927.792.000.551.992.184.000.501.993.978.000.301.994.762.000.601.992.382.003.001.9911.91

04.03SOBRECIMIENTOS04.03.01CONCRETO f'c=175 kg/cm2 PARA SOBRECIMIENTOm32.03Seccin CCInterior entre Eje A1 y Eje A22.000.730.150.200.042.000.550.150.200.032.000.750.150.200.052.002.500.150.200.155.003.750.150.200.562.002.500.150.200.152.000.400.150.200.022.000.550.150.200.032.000.850.150.200.052.002.500.150.200.152.003.700.150.200.221.000.650.150.200.022.003.400.150.200.20Seccin XX2.002.750.150.200.172.002.100.150.200.131.001.550.150.200.05

04.03.02SOBRECIMIENTO, ENCOFRADO Y DESENCOFRADOm227.00Seccin CCInterior entre Eje A1 y Eje A24.000.730.200.584.000.550.200.444.000.750.200.604.002.500.202.0010.003.750.207.504.002.500.202.004.000.400.200.324.000.550.200.444.000.850.200.684.002.500.202.004.003.700.202.962.000.650.200.264.003.400.202.72Seccin XX4.002.750.202.204.002.100.201.682.001.550.200.62

05CONCRETO ARMADO05.01ZAPATA CORRIDA05.01.01CONCRETO EN ZAPATAS CORRIDAS f'c=210 kg/cm2m386.86Z-116.002.402.300.5044.16Z-24.001.701.900.506.46Z-312.001.301.300.5010.14Z-42.006.202.250.5013.95Z-52.004.901.400.506.86Z-62.002.302.300.505.29

05.01.02ZAPATAS. ACERO Fy=4,200 kg/cm2KGNvecesLONG.TRANSV.NvecesKG/MLMETRADO976.50 Z-112.002.2511.001.55204.602.1512.001.55223.20Z-24.001.559.001.5555.801.758.001.5549.60Z-38.001.156.001.5574.401.156.001.5574.40Z-42.006.0511.001.5534.102.1031.001.5596.10Z-52.004.757.001.5521.701.2524.001.5574.40Z-62.002.1511.001.5534.102.1511.001.5534.10

05.03VIGAS DE CIMENTACION05.03.01VIGAS DE CIMENT.- FC=210 kg/cm2 - INCLUYE CURADOm39.60EJE A11.003.400.250.700.601.002.850.250.700.501.004.250.250.700.741.003.900.250.700.681.002.850.250.700.501.003.400.250.700.601.002.930.250.700.511.005.050.250.700.881.002.930.250.700.51Eje 1d y 1e2.002.650.250.700.93Entre Eje A1 y Eje A22.002.750.150.400.332.000.450.150.400.052.000.750.150.400.092.000.730.150.400.095.003.750.150.401.132.002.500.150.400.302.002.500.150.400.302.000.550.150.400.072.000.850.150.400.102.000.400.150.400.05EJE A82.004.000.150.400.48Corte E-E1.002.800.150.400.17

05.03.02VIGAS DE CIMENT..- ENCOF. Y DESENCOFm293.59EJE A12.003.400.704.762.002.850.703.992.004.250.705.952.003.900.705.462.002.850.703.992.003.400.704.762.002.930.704.102.005.050.707.072.002.930.704.10Eje 1d y 1e4.002.650.707.42Seccin C-C4.002.750.404.404.000.450.400.724.000.750.401.204.000.730.401.1610.003.750.4015.004.002.500.404.004.002.500.404.004.000.550.400.884.000.850.401.364.000.400.400.64EJE A84.004.000.406.40Corte E-E2.002.800.402.24

05.03.03VIGAS DE CIMENT.- ACERO Fy=4,200 kg/cm2KGNvecesLONG.TRANSV.NvecesKG/MLMETRADO1,189.10Eje A1 5/8"2.0015.376.001.55285.88 3/8"2.0013.872.000.5631.07Estribos 3/8"2.001.8464.000.56131.89 5/8"1.0014.426.001.55134.11 3/8"1.0012.422.000.5613.91Estribos 3/8"1.001.8468.000.5670.07Eje 1d y 1e 5/8"2.004.426.001.5582.21 3/8"2.003.422.000.567.66 3/8"2.001.8418.000.5637.09Eje A8 5/8"2.006.126.001.55113.83 3/8"2.005.122.000.5611.47 3/8"2.001.8424.000.5649.46Entre Eje A1 y Eje A2 3/8"4.004.274.000.5638.26Estribos 1/4"4.001.0423.000.2523.92 3/8"4.001.474.000.5613.17Estribos 1/4"4.001.047.000.257.28 3/8"4.001.454.000.5612.95Estribos 1/4"4.001.047.000.257.28 3/8"5.004.624.000.5651.74Estribos 1/4"5.001.0422.000.2528.60 3/8"2.003.474.000.5615.55Estribos 1/4"2.001.0417.000.258.84Tramo de seccin E-E 3/8"1.003.424.000.567.66Estribos 1/4"1.001.0420.000.255.20

05.04SOBRECIMIENTO REFORZADO05.04.01SOBRECIMIENTO REFORZADO FC=210 kg/cm2 - INCLUYE CURADOm30.61Corte C1-C11.003.400.151.200.610.005.04.02SOBRECIMIENTO REFORZADO - ENCOFRADO Y DESENCOFRADOm28.162.003.401.208.160.0

05.04.03SOBRECIMIENTO REFORZADO - ACERO DE REFUERZO F'Y=4200 KG/CM2kg49.77Eje A10, entre Eje AB y AC (Corte C1-C1)1.002.9214.000.9940.471.003.325.000.569.300.005.05COLUMNAS05.05.01COLUMNAS.- FC=210 kg/cm2 - INCLUYE CURADOm3113.79TipoC16.000.600.2510.159.14C28.000.600.5010.1524.368.000.600.5013.1531.56C32.001.500.2511.158.36C42.000.600.256.551.97C52.0013.150.607.44C616.000.250.2511.0511.0520.000.250.254.806.00C77.000.500.306.857.19CA-0136.000.150.253.454.66CA-0210.000.150.403.452.07

05.05.02COLUMNAS.- ENCOFRADO Y DESENCOFRADOm2Tipo1,150.33C16.000.600.2510.15103.53C28.000.600.5010.15178.648.000.600.5013.15231.44C32.001.500.2511.1578.05C42.000.600.256.5522.27C52.0013.150.6049.57C616.000.250.2511.05176.8020.000.250.254.8096.00C77.000.500.306.8576.72CA-0136.000.150.253.4599.36CA-0210.000.150.403.4537.95

05.05.03COLUMNAS.- ENCOFRADO Y DESENCOFRADOKG18,943.65Tipo C-1longitudinal 5/8"6.0012.3310.001.551,146.23estribos 01 3/8"6.000.520.1757.000.56314.09estribos 02 3/8"6.000.3257.000.5661.29

Tipo C-2longitudinal 3/4"8.0012.338.002.241,766.91longitudinal 5/8"8.0012.338.001.551,222.64estribos 01 3/8"16.000.370.4257.000.56939.72estribos 02 3/8"16.000.5757.000.56291.11longitudinal 3/4"8.0015.338.002.242,196.99longitudinal 5/8"8.0015.338.001.551,520.24estribos 01 3/8"16.000.370.4266.000.561,088.10estribos 02 3/8"16.000.5766.000.56337.08

Tipo C-3longitudinal 3/4"2.0015.334.002.24274.62longitudinal 5/8"2.0015.3312.001.55570.09estribos 01 3/8"4.001.7566.000.56258.72estribos 02 3/8"2.001.2066.000.5688.70estribos 03 3/8"8.000.3266.000.5694.62

Tipo C-4longitudinal 5/8"2.0015.338.001.55380.06estribos 3/8"2.000.520.1766.000.56121.23

Tipo C-5DIAMETROlongitudinal 5/8"2.0014.5512.001.55541.26estribos 3/8"2.002.0380.000.56387.72

Tipo C-6longitudinal 5/8"16.0013.234.001.551,311.92estribos 3/8"16.000.170.1760.000.56505.34longitudinal 5/8"20.006.984.001.55864.90estribos 3/8"20.000.170.1739.000.56410.59

Tipo C-7longitudinal 5/8"7.009.0310.001.55979.21estribos 3/8"7.000.420.4244.000.56334.61

Tipo CA-01 3/8"36.005.634.000.56453.60 1/4"36.000.070.1744.000.25293.04

Tipo CA-02 3/8"10.005.636.000.56189.00 1/4"10.000.070.3244.000.25114.4005.07VIGAS05.07.01VIGAS.- FC=210 kg/cm2 - INCLUYE CURADOm333.59

EJE A1 VP-01 (25X30)38.900.250.302.92

EJE A2 VP-102 (25X40)8.950.250.400.908.950.250.400.901.100.250.400.11

EJE A3 VP-102 (25X40)8.950.250.400.908.950.250.400.901.100.250.400.11

EJE A4 VP-102 (25X40)8.950.250.400.908.950.250.400.901.100.250.400.11

EJE A5 VP-102 (25X40)8.950.250.400.908.950.250.400.901.100.250.400.11

EJE A6 VP-102 (25X40)8.950.250.400.908.950.250.400.901.100.250.400.11

EJE A7 VP-102 (25X40)8.950.250.400.908.950.250.400.901.100.250.400.11EJE A8 VP-102 (25X40)5.200.250.400.525.200.250.400.52

EJE A9 VP-102 (25X30)4.000.250.300.309.000.250.300.68

EJE A10 VP-102 (25X30)8.600.250.300.654.000.250.300.30EJE A11 VP-102 (25X30)8.600.250.300.6521.300.250.301.604.000.250.300.30

EJE AA V-103 (25X40)35.000.250.403.50

EJE AA V-103 (25X30)4.300.250.300.32

EJE AB VS-01 (25X20)10.250.250.200.5110.250.250.200.51

EJE AB V-105 (25X30)7.400.250.300.56

EJE AC V-105 (25X30)7.450.250.300.56

EJE AD V-102 (25X40)7.450.250.400.75

EJE AH V-102 (25X40)7.450.250.400.75

EJE AI V-105 (25X30)7.450.250.300.56

EJE AJ VS-01 (25X20)10.250.250.200.51

EJE AJ VP-105 (25X30)7.400.250.300.56

EJE AK V-102 (25X30)35.000.250.302.63

VIGA (V-101 25X50)5.500.250.500.695.500.250.500.695.500.250.500.69

05.07.02VIGAS.- ENCOFRADO Y DESENCOFRADOm2322.23

EJE A1 VP-01 (25X30)3.400.250.302.892.850.250.302.423.900.250.303.3212.000.250.3010.203.900.250.303.322.850.250.302.423.400.250.302.89

EJE A2 VP-102 (25X40)3.550.250.403.733.950.250.404.153.950.250.404.153.550.250.403.730.850.250.400.89

EJE A3 VP-102 (25X40)3.550.250.403.733.950.250.404.153.950.250.404.153.550.250.403.730.850.250.400.89

EJE A4 VP-102 (25X40)3.550.250.403.733.950.250.404.153.950.250.404.153.550.250.403.730.850.250.400.89

EJE A5 VP-102 (25X40)3.550.250.403.733.950.250.404.153.950.250.404.153.550.250.403.730.850.250.400.89

EJE A6 VP-102 (25X40)3.550.250.403.733.950.250.404.153.950.250.404.153.550.250.403.730.850.250.400.89

EJE A7 VP-102 (25X40)3.550.250.403.733.950.250.404.153.950.250.404.153.550.250.403.730.850.250.400.89

EJE A8 VP-102 (25X40)4.000.250.404.204.000.250.404.20

EJE A9 VP-102 (25X30)3.400.250.302.893.400.250.302.89

EJE A10 VP-102 (25X30)4.000.250.303.403.400.250.302.893.400.250.302.894.000.250.303.40

EJE A11 VP-102 (25X30)4.300.250.303.663.400.250.302.895.020.250.304.275.020.250.304.275.020.250.304.275.020.250.304.273.450.250.302.93

EJE AA V-103 (25X40)4.250.250.404.464.500.250.404.734.500.250.404.734.500.250.404.734.500.250.404.734.500.250.404.734.250.250.404.46EJE AA V-103 (25X30)3.700.250.303.15

EJE AB VS-01 (25X20)4.750.250.203.094.750.250.203.094.750.250.203.094.880.250.203.17

EJE AB V-105 (25X30)2.800.250.302.383.700.250.303.15

EJE AC V-105 (25X30)2.800.250.302.383.700.250.303.15

EJE AD V-102 (25X40)2.800.250.402.944.150.250.404.36

EJE AH V-102 (25X40)2.800.250.402.944.150.250.404.36EJE AI V-105 (25X30)2.800.250.302.384.150.250.303.53

EJE AJ VS-01 (25X20)4.750.250.203.094.750.250.203.094.750.250.203.094.880.250.203.17EJE AJ VP-105 (25X30)2.800.250.302.383.700.250.303.15

EJE AK V-102 (25X30)4.250.250.303.614.500.250.303.834.500.250.303.834.500.250.303.834.500.250.303.834.500.250.303.834.250.250.303.61

VIGA (V-101 25X50)4.700.250.505.884.700.250.505.884.700.250.505.88

05.07.03VIGAS.- ACERO F'y=4,200 kg/cm2KG3,453.08

EJE A1 VP-01 (25X30)longitudinal 1/2"1.0039.904.001.00159.60estribos 3/8"1.000.170.22196.000.56107.56

EJE A2 VP-102 (25X40)longitudinal 1/2"1.009.504.001.0038.00estribos 3/8"1.000.170.17138.000.5668.01

EJE A3 VP-102 (25X40)longitudinal 1/2"1.009.504.001.0038.00estribos 3/8"1.000.170.17138.000.5668.01

EJE A4 VP-102 (25X40)longitudinal 1/2"1.009.504.001.0038.00estribos 3/8"1.000.170.17138.000.5668.01

EJE A5 VP-102 (25X40)longitudinal 1/2"1.009.504.001.0038.00estribos 3/8"1.000.170.17138.000.5668.01

EJE A6 VP-102 (25X40)longitudinal 1/2"1.009.504.001.0038.00estribos 3/8"1.000.170.17138.000.5668.01

EJE A2 VP-102 (25X40)longitudinal 1/2"1.0010.354.001.0041.40estribos 3/8"1.000.170.17138.000.5668.01

EJE A3 VP-102 (25X40)longitudinal 1/2"1.0010.354.001.0041.40estribos 3/8"1.000.170.17138.000.5668.01

EJE A4 VP-102 (25X40)longitudinal 1/2"1.0010.354.001.0041.40estribos 3/8"1.000.170.17138.000.5668.01

EJE A5 VP-102 (25X40)longitudinal 1/2"1.0010.354.001.0041.40estribos 3/8"1.000.170.17138.000.5668.01

EJE A6 VP-102 (25X40)longitudinal 1/2"1.0010.354.001.0041.40estribos 3/8"1.000.170.17138.000.5668.01

EJE AJ VS-01 (25X20)longitudinal 1/2"2.0010.254.001.0082.00estribos 3/8"2.000.170.1753.000.5652.24

EJE AB VS-01 (25X20)longitudinal 1/2"2.0010.254.001.0082.00estribos 3/8"2.000.170.1753.000.5652.24

EJE AA V-103 (25X40)longitudinal 5/8"1.0039.304.001.56245.23estribos 3/8"1.000.170.3226.000.5617.18

EJE Ak V-103 (25X40)longitudinal 5/8"1.0035.004.001.56218.40estribos 3/8"1.000.170.3223.000.5615.20

EJE A8 V-102 (25X40)longitudinal 5/8"2.004.004.001.5649.92estribos 3/8"2.000.170.3223.000.5630.40

EJE A9 V-102 (25X40)longitudinal 5/8"2.003.404.001.5642.43estribos 3/8"2.000.170.3222.000.5629.08

EJE A10 V-105 (25X30)longitudinal 1/2"2.007.404.001.0059.20estribos 3/8"2.000.170.2241.000.5645.00

EJE A11 V-105 (25X30)longitudinal 1/2"2.007.404.001.0059.20estribos 3/8"2.000.170.2241.000.5645.00

EJE A11 V-102 (25X40)longitudinal 5/8"2.0021.304.001.56265.82estribos 3/8"2.000.170.22110.000.56120.74

EJE AB V-105 (25X30)longitudinal 1/2"1.006.854.001.0027.40estribos 3/8"1.000.170.22110.000.5660.37

EJE AC V-105 (25X30)longitudinal 1/2"1.006.854.001.0027.40estribos 3/8"1.000.170.22110.000.5660.37

EJE AD V-105 (25X40)longitudinal 1/2"1.006.904.001.0027.60estribos 3/8"1.000.170.32110.000.5672.69

EJE AH V-102 (25X30)longitudinal 5/8"1.006.854.001.5642.74estribos 3/8"1.000.170.22110.000.5660.37

EJE AJ V-105 (25X40)longitudinal 5/8"1.006.904.001.5643.06estribos 3/8"1.000.170.32110.000.5672.69

V-101 (15X50)longitudinal 1/2"1.005.904.001.0023.60longitudinal 3/8"1.005.902.000.566.61estribos 3/8"1.000.170.32110.000.5672.69

05.10MUROS DE CONTENCION05.10.01CONCRETO f'c=210 kg/cm2 PARA MUROSm360.53Corte 1-14.005.030.252.1010.55Seccin AA1.0018.600.152.055.722.001.350.152.050.832.001.600.152.050.981.001.400.152.050.43291639Corte C2-C21.003.400.252.652.251.003.700.252.652.45Corte Y-Y2.003.000.101.801.0810.001.400.101.802.526.000.300.101.800.322.000.550.101.800.202.000.500.101.800.18Corte D-D4.000.158.004.804.000.980.153.101.824.001.050.153.101.958.004.750.153.1017.674.000.630.153.101.16Corte F-F2.002.050.302.052.522.002.500.302.053.08

05.10.02ENCOFRADO Y DESENCOFRADO NORMAL DE MUROSm2696.53Seccin AA8.005.032.1084.42Seccin AA2.0018.602.0576.264.001.352.0511.074.001.602.0513.122.001.402.055.74Corte C2-C22.003.402.6518.022.003.702.6519.61Corte Y-Y4.003.001.8021.6020.001.401.8050.4012.000.301.806.484.000.551.803.964.000.501.803.60Corte D-D8.008.0064.008.000.983.1024.308.001.053.1026.0416.004.753.10235.608.000.633.1015.50Corte F-F4.002.052.0516.81

05.10.03ACERO CORRUGADO FY=4200 KG/CM2 PARA MUROSKGNvecesLONG.TRANSV.NvecesKG/MLMETRADO3,409.02Acero en seccin 1-11.003.2487.000.56157.611.0021.7218.000.56218.94Acero en seccin A-A1.002.6774.000.56110.641.0018.7210.000.56104.831.002.676.000.568.971.001.4710.000.568.231.002.678.000.5611.961.002.0210.000.5611.311.002.677.000.5610.471.001.6710.000.569.35Acero en seccin C2-C21.004.1222.000.5650.761.003.5715.000.5629.991.003.3615.000.5628.221.004.4222.000.5654.451.003.5715.000.5629.991.003.3615.000.5628.22Acero en seccin Y-Y2.003.168.000.5628.312.002.4212.000.5632.5210.001.628.000.5672.5810.002.426.000.5681.316.000.568.000.5615.056.002.422.000.5616.262.000.768.000.566.812.002.423.000.568.13Acero en seccin D-D8.002.5611.000.56126.168.004.199.000.56168.748.0011.3111.000.56557.368.004.1945.000.56843.708.005.227.000.56163.708.003.0621.000.56287.88Acero en seccin F-F2.002.767.000.5621.642.002.9211.000.5635.972.003.377.000.5626.422.002.9213.000.5642.52

05.12LOSAS MACIZAS05.12.01CONCRETO f'c=210 kg/cm2 PARA LOSAS MACIZASM31.0031.610.257.907.90

05.12.02ENCOFRADO Y DESENCOFRADO NORMAL DE LOSAS MACIZASM231.611.0031.61

05.12.03ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSAS MACIZASKG604.67longitudinales1.001/2"12.7023.331.00296.33transversales1.001/2"3.7083.331.00308.33

05.14GRADERIAS05.14.01CONCRETO f'c=210 kg/cm2 PARA GRADERIASm3442.38

contrapasos4.0013.100.150.6011.0051.88pasos4.0013.100.650.1511.00374.66

gadas de relleno4.001.200.300.2311.0015.84

05.14.02ENCOFRADO Y DESENCOFRADO NORMAL DE GRADERIASm2886.14vecescontrapasos4.0013.100.4511.00259.38pasos4.0013.100.9511.00547.58

FRISO A LOS COSTADOS 8.0010.000.8064.00

gadas de relleno4.001.200.300.2311.0015.18

05.14.03ACERO CORRUGADO FY=4200 KG/CM2 PARA GRADERIASKG5,619.01contrapasosverticales 3/8"4.000.8565.5011.000.561,371.83horizontales 3/8"4.0013.503.0011.000.56997.92

pasosN pasoslongitudinales 3/8"4.0013.503.0011.000.56997.92transversales 3/8"4.001.2265.5011.000.561,968.98

parapetoN pasosverticales 3/8"4.001.1065.501.000.56161.39horizontales 3/8"4.0013.504.001.000.56120.96

06.02TIJERALES06.02.01TIJERAL T-01 L=37.70mUnd.7.007.00

06.02.02TIJERAL T-02 L=24.50m1.001.00

06.02.03TIJERAL T-03, L=8.60 m3.003.00

06.02.04VIGUETAS METALICAS 3X6 L=34.00m37.0037.00

06.02.05TENSORES DE 3/4" L=7.700m48.0048.00

PolideportivoPgina &P&Uplanilla de metrado

BOLETERIAPROYECTO: ADECUACIN, MEJORAMIENTO Y SUSTITUCION DE LA INFRAESTRUCTURA EDUCATIVA DE LA I. E. " SAN NICOLAS"OBRA: BOLETERIAESTRUCTURAS

01.00.00BOLETERIACODDESCRIPCIONUnd.CantidadLAREAHMETRADOTOTAL 02.04.01TRAZO Y REPLANTEO C/EQUIPO14.3314.3314.33

03MOVIMIENTO DE TIERRAS03.02EXCAVACIONES03.02.01EXCAVACION DE ZANJAS Y ZAPATAS RT= 2.0 KG/CM2 H=2.0 mm36.09ZONA CIRCULAR3.300.401.101.456.680.401.102.94ZONA RECTA2.130.401.100.941.730.401.100.76

04OBRAS DE CONCRETO SIMPLE04.02CIMIENTOS CORRIDOS04.02.01CONCRETO PARA CIMIENTOS CORRIDOS f'c=100kg/cm2m24.43ZONA CIRCULAR3.300.400.801.066.680.400.802.14ZONA RECTA2.130.400.800.681.730.400.800.55

04.03SOBRECIMIENTOS04.03.01CONCRETO PARA SOBRE CIMIENTOS CORRIDOS f'c=175kg/cm2m20.97ZONA CIRCULAR3.300.150.500.256.680.150.500.50ZONA RECTA0.950.150.500.072.000.150.500.15

04.03.02ENCOFRADO DE SOBRECIMIENTOS m212.933.300.502.003.306.680.502.006.680.950.502.000.952.000.502.002.00

05CONCRETO ARMADO05.02CIMIENTOS REFORZADOS05.02.01CONCRETO EN CIMIENTOS REFORZADOSm30.78ZONA CIRCULAR3.300.150.400.206.680.150.400.40ZONA RECTA0.950.150.400.062.000.150.400.12

05.02.02CIMIENTOS CORRIDOS, ENCOF. Y DESENCOF.m210.343.300.402.002.646.680.402.005.340.950.402.000.762.000.402.001.60

05.02.03CIMIENTOS REFORZADOS - ACERO Fy=4,200 kg/cm2KG106.62

ZONA CIRCULAR1.003.304.000.567.391.007.584.000.5616.98ZONA RECTA1.000.954.000.562.131.002.004.000.564.48ESTRIBOS4.001.2461.000.2575.64

05.05COLUMNAS05.05.01COLUMNAS.- FC=210 kg/cm2 - INCLUYE CURADOm30.411.002.000.200.153.200.191.002.000.200.153.700.22

05.05.02COLUMNAS.- ENCOFRADO Y DESENCOFRADOm27.592.002.000.203.202.561.002.000.153.200.962.002.000.203.702.961.002.000.153.701.11

05.05.03COLUMNAS - ACERO F'y=4,200 kg/cm2kg42.53 1/2"2.004.004.840.9938.29Estribos 1/4"2.0016.000.530.254.24 1/2"2.004.005.340.9942.25Estribos 1/4"2.0019.000.530.255.04

05.07VIGAS05.07.01VIGAS.- FC=210 kg/cm2 - INCLUYE CURADOm21.35V-101 (15X50)3.300.150.500.256.680.150.500.50

0.950.150.500.072.000.150.500.15

VB-1(10X20)18.850.100.200.3805.07.02VIGAS.- ENCOFRADO Y DESENCOFRADOm224.29V-101 (15X50)3.300.150.503.806.680.150.507.68

0.950.150.501.092.000.150.502.30

VB-1(10X20)18.850.100.209.43

05.07.03VIGAS.- ACERO F'y=4,200 kg/cm2KG183.92

V-101 (15X50)3/8"1.0013.632.000.5615.271/2"1.0013.632.001.0027.265/8"1.0013.632.001.5642.53ESTRIBOS1.001.4460.000.5648.38

VB-1(15X20)3/8"1.0013.634.000.5630.53ESTRIBOS1.000.8495.000.2519.95

05.10MUROS ARMADOS05.10.01CONCRETO f'c=210 kg/cm2 PARA MUROSm310.28ZONA CIRCULAR3.300.155.302.626.680.155.305.31ZONA RECTA0.950.155.300.762.000.155.301.59

05.10.02ENCOFRADO Y DESENCOFRADO NORMAL DE MUROSm252.393.144.302.0027.020.954.302.008.172.004.302.0017.20

05.10.03ACERO CORRUGADO FY=4200 KG/CM2 PARA MUROSKG679.14VERTICALES 1/2"2.0040.005.301.00424.00HORIZONTALES 3/8"1.0012.5228.670.56200.99COLUMAS DE EXTREMOLONG. 1/2"2.004.005.301.0042.40ESTRIBOS 1/4"2.000.9425.000.2511.75

05.12LOSA MACIZA05.12.01CONCRETO EN LOSA MACIZA f'c= 210 kg/cm2m30.2026.425.28

05.12.02ENCOFRADO Y DESENCOFRADO DE LOSA MACIZAm326.4226.42

05.12.03ACERO EN LOSA MACIZA fy= 4200 kg/cm2 3/8"KG287.44

LONG. 3/8"1.002.152.000.562.411.002.992.000.563.351.003.602.000.564.031.004.072.000.564.561.004.472.000.565.011.004.802.000.565.381.005.072.000.565.681.005.302.000.565.941.005.492.000.566.151.005.642.000.566.321.005.782.000.566.471.005.872.000.566.571.005.942.000.566.651.005.982.000.566.701.005.942.000.566.651.005.872.000.566.571.005.782.000.566.471.005.642.000.566.321.005.492.000.566.151.005.302.000.565.941.005.072.000.565.681.004.802.000.565.381.004.472.000.565.011.004.072.000.564.561.003.602.000.564.031.002.992.000.563.351.002.152.000.562.41TRANSV. 3/8"1.002.152.000.562.411.002.992.000.563.351.003.602.000.564.031.004.072.000.564.561.004.472.000.565.011.004.802.000.565.381.005.072.000.565.681.005.302.000.565.941.005.492.000.566.151.005.642.000.566.321.005.782.000.566.471.005.872.000.566.571.005.942.000.566.651.005.982.000.566.701.005.942.000.566.651.005.872.000.566.571.005.782.000.566.471.005.642.000.566.321.005.492.000.566.151.005.302.000.565.941.005.072.000.565.681.004.802.000.565.381.004.472.000.565.011.004.072.000.564.561.003.602.000.564.031.002.992.000.563.351.002.152.000.562.41

BoleteraPgina &P&Uplanilla de metrado

GIMNASIOPROYECTO: ADECUACIN, MEJORAMIENTO Y SUSTITUCION DE LA INFRAESTRUCTURA EDUCATIVA DE LA I. E. " SAN NICOLAS"OBRA: GIMNASIOESTRUCTURAS

CODDESCRIPCIONUnd.CantidadLAHMETRADOTOTAL 02.04TRAZO Y REPLANTEO GENERAL PARA TODO EL TERRENO02.04.01TRAZO Y REPLANTEO C/EQUIPOm2369.60 19.2519.20369.60

03MOVIMIENTO DE TIERRAS03.02EXCAVACIONES03.02.01EXCAVACION DE ZANJAS Y ZAPATAS RT= 2.0 KG/CM2 H=2.0 mm384.54ZapatasZ-098.001.701.501.4028.56Z-102.002.101.901.4011.17Excavacin para cimentacionEJE BA1.0015.800.600.908.53EJE BA'1.003.200.600.901.73EJE BB1.002.250.400.900.81EJE BC'1.003.200.600.901.73EJE BE1.0015.800.600.908.53EJE B11.002.880.600.901.561.003.000.600.901.621.003.000.600.901.621.002.880.600.901.56EJE B51.002.670.600.901.441.002.600.600.901.401.002.800.600.901.511.002.880.600.901.56SECCION CC1.002.680.400.600.641.002.920.400.600.701.003.200.400.600.771.006.130.400.601.471.009.100.400.602.18SECCION XX0.860.700.300.181.000.700.300.211.000.700.300.211.250.700.300.261.250.700.300.260.650.700.300.141.250.700.300.260.650.700.300.141.580.700.300.330.780.700.300.161.150.700.300.241.150.700.300.241.030.700.300.221.000.700.300.211.100.700.300.230.850.700.300.181.120.700.300.240.500.700.300.111.120.700.300.241.000.700.300.210.870.700.300.181.580.700.300.331.600.700.300.341.000.700.300.210.580.700.300.12

03.03RELLENOS03.03.03RELLENO CON AFIRMADO E=4" PARA PISOS INTERIORES Y EXTERIORESm3336.30DEPOSITO8.808.80GIMNASIO281.38281.38VESTIDOR HOMBRES19.3019.30VESTIDOR DISCAPACITADOS7.347.34VESTIDOR MUJERES19.4819.48

03.05ELIMINACION DE MATERIAL EXEDENTE03.05.01ACARREO INTERNO, MATERIAL PROCEDENTE DE DEMOLICIONm3101.44Volumen de excavacin estruc. Proyectada1.2084.54101.44Volumen de excavacin excedente de excavacion masiva c/maquinaria1.15-ERROR:#REF!ERROR:#REF!

03.05.02ELIMINACION DE MATERIAL EXEDENTEm3101.44Volumen de excavacin estruc. Proyectada1.2084.54101.44Volumen de excavacin excedente de excavacion masiva c/maquinaria1.15-ERROR:#REF!ERROR:#REF!

04CONCRETO SIMPLE04.01SOLADOS04.01.01SOLADO PARA CIMIENTOS CORRIDOS E=4" MEZCLA 1:12 CEMENTO:HORMIGONm265.71Zapatas Z-98.001.701.5020.40Z-102.002.101.907.98CimientosEJE BA1.0015.800.609.48EJE BA'1.003.200.601.92EJE BB1.002.250.400.90EJE BC'1.003.200.601.92EJE BE1.0015.800.609.48EJE B11.002.880.601.731.003.000.601.801.003.000.601.801.002.880.601.73EJE B51.002.670.601.601.002.600.601.561.002.800.601.681.002.880.601.7311.104.02CIMIENTOS CORRIDOS04.02.01CIMIENTO CORRIDO: CONCRETO f'c=100 kg/cm2 +30% P.G.m311.21SECCION CC1.002.680.400.600.641.002.920.400.600.701.003.200.400.600.771.006.130.400.601.471.009.100.400.602.18SECCION XX0.860.700.300.181.000.700.300.211.000.700.300.211.250.700.300.261.250.700.300.260.650.700.300.141.250.700.300.260.650.700.300.141.580.700.300.330.780.700.300.161.150.700.300.241.150.700.300.241.030.700.300.221.000.700.300.211.100.700.300.230.850.700.300.181.120.700.300.240.500.700.300.111.120.700.300.241.000.700.300.210.870.700.300.181.580.700.300.331.600.700.300.341.000.700.300.210.580.700.300.12

05OBRAS DE CONCRETO ARMADO05.01ZAPATA CORRIDA05.01.01CONCRETO EN ZAPATAS CORRIDAS f'c=210 kg/cm2m314.19 Z-98.001.701.500.5010.20Z-102.002.101.900.503.99

05.01.02ZAPATAS. ACERO Fy=4,200 kg/cm2KG327.60 Z-98.002.2510.001.56124.802.1511.001.56137.28Z-102.002.0510.001.5631.201.9511.001.5634.32

05.02CIMIENTOS REFORZADOS05.02.01CONCRETO EN CIMIENTOS REFORZADOSm3EJE BA1.0015.800.600.807.5852.07EJE BA'1.003.200.600.801.54EJE BB1.002.250.400.800.72EJE BC'1.003.200.600.801.54EJE BE1.0015.800.600.807.58EJE B11.002.880.600.801.381.003.000.600.801.441.003.000.600.801.441.002.880.600.801.38EJE B51.002.670.600.801.281.002.600.600.801.251.002.800.600.801.341.002.880.600.801.38SECCION CC1.002.680.400.800.861.002.920.400.800.931.003.200.400.801.021.006.130.400.801.961.009.100.400.802.91SECCION XX0.860.700.800.481.000.700.800.561.000.700.800.561.250.700.800.701.250.700.800.700.650.700.800.361.250.700.800.700.650.700.800.361.580.700.800.880.780.700.800.441.150.700.800.641.150.700.800.641.030.700.800.581.000.700.800.561.100.700.800.620.850.700.800.481.120.700.800.630.500.700.800.281.120.700.800.631.000.700.800.560.870.700.800.491.580.700.800.881.600.700.800.901.000.700.800.560.580.700.800.32

05.02.02CIMIENTOS CORRIDOS, ENCOF. Y DESENCOF.m3336.64

EJE BA1.0013.800.251.5044.85EJE BB1.002.250.151.507.09EJE BC'1.003.200.151.5010.08EJE BE1.0013.800.151.5043.47EJE B11.002.880.251.509.361.003.000.251.509.751.003.000.251.509.751.002.880.251.509.36EJE B51.002.670.251.508.681.002.600.251.508.451.002.800.251.509.101.002.880.251.509.36SECCION CC1.002.680.151.508.441.002.920.151.509.201.003.200.151.5010.081.006.130.151.5019.311.009.100.151.5028.67SECCION XX1.000.860.151.502.711.001.000.151.503.151.001.000.151.503.151.001.250.151.503.941.001.250.151.503.941.000.650.151.502.051.001.250.151.503.941.000.650.151.502.051.001.580.151.504.981.000.780.151.502.461.001.150.151.503.621.001.150.151.503.621.001.030.151.503.241.001.000.151.503.151.001.100.151.503.471.000.850.151.502.681.001.120.151.503.531.000.500.151.501.581.001.120.151.503.531.001.000.151.503.151.000.870.151.502.741.001.580.151.504.981.001.600.151.505.041.001.000.151.503.151.000.580.151.501.83

05.02.03CIMIENTOS REFORZADOS - ACERO Fy=4,200 kg/cm2KG1,917.76EJE BA1.0017.3014.000.56135.634.4069.001.00303.60EJE BE1.0017.3014.000.56135.634.4069.001.00303.60EJE B11.004.3814.000.5634.344.4021.001.0092.401.004.5014.000.5635.284.4018.001.0079.201.004.5014.000.5635.284.4018.001.0079.201.004.3814.000.5634.344.4021.001.0092.40EJE B51.004.1714.000.5632.694.4016.001.0070.401.004.1014.000.5632.144.4016.001.0070.401.004.3014.000.5633.714.4017.001.0074.801.004.3814.000.5634.344.4021.001.0092.40SECCION CC1.003.380.404.000.565.411.1633.000.259.5727.531.003.620.404.000.565.791.1635.000.2510.151.003.900.404.000.566.241.1637.000.2510.731.006.830.404.000.5610.931.1662.000.2517.981.009.800.404.000.5615.681.1681.000.2523.49

05.04SOBRECIMIENTO REFORZADO05.04.01SOBRECIMIENTO REFORZADO CONCRETO FC=210 kg/cm2 - INCLUYE CURADOm3EJE BA1.0013.800.251.505.1829.26EJE BB1.002.250.151.500.51EJE BC'1.003.200.151.500.72EJE BE1.0013.800.151.503.11EJE B11.002.880.251.501.081.003.000.251.501.131.003.000.251.501.131.002.880.251.501.08EJE B51.002.670.251.501.001.002.600.251.500.981.002.800.251.501.051.002.880.251.501.08SECCION CC1.002.680.151.500.601.002.920.151.500.661.003.200.151.500.721.006.130.151.501.381.009.100.151.502.05SECCION XX1.000.860.151.500.191.001.000.151.500.231.001.000.151.500.231.001.250.151.500.281.001.250.151.500.281.000.650.151.500.151.001.250.151.500.281.000.650.151.500.151.001.580.151.500.361.000.780.151.500.181.001.150.151.500.261.001.150.151.500.261.001.030.151.500.231.001.000.151.500.231.001.100.151.500.251.000.850.151.500.191.001.120.151.500.251.000.500.151.500.111.001.120.151.500.251.001.000.151.500.231.000.870.151.500.201.001.580.151.500.361.001.600.151.500.361.001.000.151.500.231.000.580.151.500.13

05.05COLUMNAS05.05.01COLUMNAS.- FC=210 kg/cm2 - INCLUYE CURADOm340.50C-110.000.600.3010.4518.81C-26.000.250.4010.456.27CA-125.000.200.1510.457.84CA-214.000.250.1510.455.49CA-2 (CONTINUA DESPUES DE SEGUNDO NIVEL)28.000.250.152.002.10

05.05.02COLUMNAS.- ENCOFRADO Y DESENCOFRADOm2684.34C-110.000.600.3010.45188.10C-26.000.250.4010.4581.51CA-125.000.250.1510.45209.008.45CA-214.000.400.1510.45160.93CA-1 (CONTINUA DESPUES DE SEGUNDO NIVEL)28.000.250.152.0044.80

05.05.03COLUMNAS - ACERO F'y=4,200 kg/cm2KG4,660.27Tipo C1longitudinal 5/8"10.0011.2010.001.561,747.20estribos 3/8"10.000.520.1744.000.56389.31Tipo C2longitudinal 1/2"6.0011.204.001.00268.80estribos 3/8"6.000.170.1744.000.56130.10Tipo CA-01longitudinal 3/8"25.0011.204.000.56627.20estribos 1/4"25.000.090.1944.000.25209.00Tipo CA-02longitudinal 1/2"14.0011.204.001.00627.20estribos 1/4"14.000.090.24145.000.25436.45

CA-01 (CONTINUA DESPUES DE SEGUNDO NIVEL)longitudinal 3/8"28.002.404.000.56150.53estribos 1/4"28.000.090.1914.000.2574.48

05.07VIGAS05.07.01VIGAS.- FC=210 kg/cm2 - INCLUYE CURADOm315.28VIGAS NIVEL +6.25mEJE B1 V-101 (25X40)18.000.250.401.80EJE B5 V-101 (25X40)18.000.250.401.80EJE BA VP-102 (25X40)18.000.250.401.80EJE BE V-103 (25X40)18.000.250.401.80EJE BA' VA-01 (25X20)3.650.250.200.18EJE BB VA-02 (15X20)3.650.250.200.18EJE BC' V-105 (25X30)3.650.250.200.18CORTE YY3.620.100.200.079.450.100.200.193.620.100.200.07VIGAS NIVEL +6.25mEJE B1 V-101 (25X40)18.000.250.401.80EJE B5 V-101 (25X40)18.000.250.401.80EJE BA VP-102 (25X40)18.000.250.401.80EJE BE V-103 (25X40)18.000.250.401.80

04.06.01VIGAS.- ENCOFRADO Y DESENCOFRADOm2163.32VIGAS NIVEL +6.25mEJE B1 V-101 (25X40)18.000.250.4018.90EJE B5 V-101 (25X40)18.000.250.4018.90EJE BA VP-102 (25X40)18.000.250.4018.90EJE BE V-103 (25X40)18.000.250.4018.90EJE BA' VA-01 (25X20)3.650.250.202.37EJE BB VA-02 (15X20)3.650.250.202.37EJE BC' V-105 (25X30)3.650.250.202.37CORTE YY3.620.100.201.099.450.100.202.843.620.100.201.09VIGAS NIVEL +6.25mEJE B1 V-101 (25X40)18.000.250.4018.90EJE B5 V-101 (25X40)18.000.250.4018.90EJE BA VP-102 (25X40)18.000.250.4018.90EJE BE V-103 (25X40)18.000.250.4018.90

04.06.03ACERO fy=4200 kg/cm2 GRADO 60 en VIGASKG1,671.31VIGAS NIVEL +6.25mEJE B1 V-101 (25X40)longitudinal 5/8"1.0018.404.001.56114.82estribos 3/8"1.000.170.321.38102.000.5678.83EJE B5 V-101 (25X40)longitudinal 1/2"1.0018.404.001.56114.82estribos 3/8"1.000.170.321.38102.000.5678.83EJE BA V-101 (25X40)longitudinal 1/2"1.0018.404.001.56114.82estribos 3/8"1.000.170.321.38102.000.5678.83EJE BE V-101 (25X40)longitudinal 1/2"1.0018.404.001.56114.82estribos 3/8"1.000.170.321.38102.000.5678.83EJE BA' VA-01 (25X20)longitudinal 3/8"1.004.054.000.569.07estribos 1/4"1.000.210.161.1429.000.258.27EJE BB VA-02 (15X20)longitudinal 3/8"1.004.054.000.569.07estribos 1/4"1.000.210.161.1429.000.258.27EJE BC' VA-01 (25X20)longitudinal 3/8"1.003.654.000.568.18estribos 1/4"1.000.210.161.1427.000.257.70VS-02longitudinal 1/2"1.0016.694.001.0066.76estribos 1/4"1.000.210.160.2578.000.254.88VIGAS NIVEL +6.25mEJE B1 V-101 (25X40)longitudinal 1/2"1.0018.404.001.56114.82estribos 3/8"1.000.170.321.38102.000.5678.83EJE B5 V-101 (25X40)longitudinal 1/2"1.0018.404.001.56114.82estribos 3/8"1.000.170.321.38102.000.5678.83EJE BA VP-101 (25X40)longitudinal 1/2"1.0018.404.001.56114.82estribos 3/8"1.000.170.321.38102.000.5678.83EJE BE V-101 (25X40)longitudinal 1/2"1.0018.404.001.56114.82estribos 3/8"1.000.170.321.38102.000.5678.8305.09LOSAS ALIGERADAS05.09.01LOSA ALIGERADA.- FC=210 kg/cm2 - INCLUYE CURADOM32.20Nro.LOSA (m)LADRILLO (m)SUB TOTALTOTALVECESAREA ESPESOR LARGO ANCHOESPESOR (m3) (m3)16.650.200.300.300.150.58118.450.200.300.300.151.62

VOLUMEN . =VOLUMEN. DE _VOLUMEN. DE DE CONCRETO LOSA ALIGERADALADRILLOS

05.09.02LOSA ALIGERADA.- ENCOFRADO Y DESENCOFRADOM3125.1025.1025.10

05.09.03LOSA ALIGERADA.- LADR. HUECO 15x30x30Und.209.08Nro.LOSA (m2)LADRILLO
Lilian: PISFIL:EN 1 M2 ENTRAN 8 ,33 LADRILLOSSUB TOTALTOTALVECESAREA CANTIDAD EN 1 M2125.108.33209.08

05.09.04LOSA ALIGERADA.- ACERO F'y=4,200 kg/cm2KG67.50longitudinales1.003/8"3.8021.000.5644.69bastones1.003/8"1.9421.000.5622.81

06.02TIJERALES06.02.06TIJERAL TG-01 L=16.80mUnd.5.005.005.00

06.02.07VIGUETAS CORREAS L= 17.50m17.0017.0017.00

06.02.08TENSORES DE 5/8" L=5.00m44.0044.0044.00

GimnasioPgina &P&Uplanilla de metrado

CISTERNAPROYECTO: ADECUACIN, MEJORAMIENTO Y SUSTITUCION DE LA INFRAESTRUCTURA EDUCATIVA DE LA I. E. " SAN NICOLAS"OBRA: CISTERNAESTRUCTURAS

01.00.00TRABAJOS PRELIMINARESCODDESCRIPCIONUnd.CantidadLAHMETRADOTOTAL02.01TRAZO Y REPLANTEO GENERAL PARA TODO EL TERRENO02.01.01TRAZO Y REPLANTEO TOPOGRAFICO.m226.28 7.33.6026.28

03MOVIMIENTO DE TIERRAS03.02EXCAVACIONES03.02.01EXCAVACION DE ZANJAS Y ZAPATAS MANUAL, Rt=0.84 kg/cm2, Df=1.90mm363.08

4.83.602.8449.082.52.002.8014.00

03.03RELLENOS01.03.02RELLENO COMPACTADO C/EQUIPO MAT/PRESTAMO AFIRMADO E=0.15 mm32.234.83.600.101.7282.52.000.100.5

03.04ELIMINACION DE EXCAVACIONES03.04.01ACARREO INTERNO DE MATERIAL PROCEDENTE DE DEMOLICIONES Y EXCAVACIONESm372.54Volumen de excavacin estruc. Proyectada1.1563.0872.54

03.04.02ELIMINACION DE DESMONTE,P/DEMOLICION DE ESTRUCT. CONCR, LADRIL. DIST.=5 KMm372.54Volumen de excavacin estruc. Proyectada1.1563.0872.54

04OBRAS DE CONCRETO SIMPLE04.01SOLADOS11.104.01.01SOLADO PARA CIMIENTOS Y ZAPATAS: CONCRETO C:H 1:12 e=20 cm.m322.284.83.6017.282.52.005.00

05OBRAS DE CONCRETO ARMADO05.05COLUMNAS05.05.01CONCRETO EN COLUMNAS f'c=210 kg/cm2m30.73

70.200.202.600.73

05.05.02ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNASm27.84

70.200.202.807.84

05.05.03ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNAS KG255.7C-2LONGITUDINAL 5/8"73.004.001.56131.04ESTRIBOS 3/8"71.0630.000.56124.656

05.17CISTERNA05.17.01CONCRETO EN CISTERNA F'C=280KG/CM2m317.62LOSA DE FONDO EJE ENTRE 2- 2 Y AC1.004.803.600.203.46EJE ENTRE 3- 2 Y AB1.002.502.000.201.00paredes verticalesEJE A-A16.70.22.22.948EJE B-B12.20.22.20.968EJE C-C14.50.22.21.98EJE 3-311.60.22.20.704EJE 2-211.60.22.20.704EJE 1-113.20.22.21.408TAPAEJE ENTRE 2- 2 Y AC1.004.803.600.203.46EJE ENTRE 3- 2 Y AB1.002.502.000.201.00

05.17.02ENCOFRADO Y DESENCOFRADO PARA CISTERNAm2124.14

paredes verticalesEJE A-A17.32.14231.244EJE B-B12.42.14210.272EJE C-C14.92.14220.972EJE 3-3122.1428.56EJE 2-213.62.14215.408EJE 1-113.62.14215.408tapa14.83.601.0017.2812.52.001.005

05.17.03ACERO CORRUGADO FY=4200 KG/CM2 PARA CISTERNAKG1773.15CISTERNALOSA DE FONDO LONGITUDINALES 3/8"SUPERIOR1.004.8016.000.5643.01INFERIOR1.004.8016.000.5643.011.001.3016.000.5611.65

TRANSVERSALES 3/8"SUPERIOR1.004.2024.000.5656.45INFERIOR1.004.2024.000.5656.45

PAREDES VERTICALES

EJE A y C 3/8"VERTICALES4.003.3024.000.56177.41HORIZONTALES4.005.5016.000.56197.12

EJE 1 Y 2 3/8"VERTICALES4.003.3024.000.56177.41HORIZONTALES4.004.5016.000.56161.28

TAPALONGITUDINALESSUPERIOR 1.005.3016.001.0084.80INFERIOR1.005.3016.001.0084.80TRANSVRSALESSUPERIOR 1.003.9016.001.0062.40INFERIOR1.003.9022.001.0085.80

CAJA DE VALVULA

LOSA DE FONDO LONGITUDINALES 3/8"SUPERIOR1.002.9010.000.5616.24INFERIOR1.002.9010.000.5616.241.001.3010.000.567.28TRANSVERSALES 3/8"SUPERIOR1.002.6013.000.5618.93INFERIOR1.002.6013.000.5618.93

PAREDES VERTICALESEJE A y B 3/8"VERTICALES4.003.3014.000.56103.49HORIZONTALES4.002.9016.000.56103.94

EJE 3 3/8"VERTICALES2.003.3014.000.5651.74HORIZONTALES2.002.6016.000.5646.59

TAPALONGITUDINALESSUPERIOR 1.002.9013.001.0037.70INFERIOR1.002.9013.001.0037.70TRANSVRSALESSUPERIOR 1.002.6014.001.0036.40INFERIOR1.002.6014.001.0036.40

CisternaPgina &P&Uplanilla de metrado

ESTACION ELECTRICAPROYECTO: ADECUACIN, MEJORAMIENTO Y SUSTITUCION DE LA INFRAESTRUCTURA EDUCATIVA DE LA I. E. " SAN NICOLAS"OBRA: ESTACION ELECTRICAESTRUCTURAS 02TRABAJOS PRELIMINARES GENERALES02.01TRAZO Y REPLANTEO GENERAL PARA TODO EL TERRENO02.01.01TRAZO Y REPLANTEO C/EQUIPOm219.17 5.813.3019.17

03MOVIMIENTO DE TIERRAS03.02EXCAVACIONES03.02.01EXCAVACION DE ZANJAS Y ZAPATAS RT= 2.0 KG/CM2 H=2.0 mm37.61EJE CA1.003.620.400.951.38EJE CA'1.002.750.400.951.05EJE CB1.002.750.400.951.05EJE C11.005.100.400.951.94EJE C21.005.810.400.952.21

03.03RELLENOS03.03.03RELLENO CON AFIRMADO E=4" PARA PISOS INTERIORES Y EXTERIORESm31.721.2014.320.101.72

03.05ELIMINACION DE MATERIAL EXEDENTEUnd.CantidadLM3HMETRADOTOTAL03.05.01ACARREO INTERNO, MATERIAL PROCEDENTE DE DEMOLICIONm38.75Volumen de excavacin estruc. Proyectada1.157.618.75Volumen de excavacin excedente de excavacion masiva c/maquinaria1.15-ERROR:#REF!ERROR:#REF!

03.05.02ELIMINACION DE MATERIAL EXEDENTEm38.75Volumen de excavacin estruc. Proyectada1.157.618.75

04CONCRETO SIMPLE04.02CIMIENTOS CORRIDOSUnd.CantidadLAHMETRADOTOTAL04.02.01CIMIENTO CORRIDO: CONCRETO f'c=100 kg/cm2 +30% P.G.m36.41EJE CA1.003.620.400.801.16EJE CA'1.002.750.400.800.88EJE CB1.002.750.400.800.88EJE C11.005.100.400.801.63EJE C21.005.810.400.801.86

05OBRAS DE CONCRETO ARMADO05.04SOBRECIMIENTO REFORZADO05.04.01SOBRECIMIENTO REFORZADO CONCRETO FC=210 kg/cm2 - INCLUYE CURADOm31.57EJE CA1.002.860.150.750.32EJE CA'1.001.450.150.750.16EJE CB1.002.860.150.750.32EJE C11.002.050.150.750.23EJE C21.004.730.150.750.53

05.04.02SOBRECIMIENTO REFORZADO - ENCOFRADO Y DESENCOFRADOm220.93EJE CA1.002.860.754.29EJE CA'1.001.450.752.18EJE CB1.002.860.754.29EJE C11.002.050.753.08EJE C21.004.730.757.10

05.04.03SOBRECIMIENTO REFORZADO - ACERO DE REFUERZO F'Y=4200 KG/CM2KG98.36EJE CALONGITUDINAL 3/8"1.003.806.000.5612.77ESTRIBOS 1/4"1.001.1624.000.256.96EJE CA'LONGITUDINAL 3/8"1.002.456.000.568.23ESTRIBOS 1/4"1.001.1619.000.255.51EJE CBLONGITUDINAL 3/8"1.003.806.000.5612.77ESTRIBOS 1/4"1.001.1622.000.256.38EJE C1LONGITUDINAL 3/8"1.003.056.000.5610.25ESTRIBOS 1/4"1.001.1622.000.256.38EJE C2LONGITUDINAL 3/8"1.005.736.000.5619.25ESTRIBOS 1/4"1.001.1634.000.259.86

05.05COLUMNAS05.05.01COLUMNAS.- FC=210 kg/cm2 - INCLUYE CURADOm31.51EJE C1C-12.000.250.253.000.38C-21.000.300.253.000.23CA-011.000.250.153.000.11EJE C2C-12.000.250.253.400.43C-21.000.300.253.400.26EJE CA'CA-011.000.250.153.100.12 05.05.02COLUMNAS.- ENCOFRADO Y DESENCOFRADOm224.72EJE C1C-12.000.250.253.006.00C-21.000.300.253.003.30CA-011.000.250.153.002.40EJE C2C-12.000.250.253.406.80C-21.000.300.253.403.74EJE CA'CA-011.000.250.153.102.48

05.05.03COLUMNAS.- ENCOFRADO Y DESENCOFRADOKG178.87EJE C1C-1LONGITUDINAL 1/2"2.004.104.001.0032.80ESTRIBOS 1/4"2.001.0630.000.2515.90C-2LONGITUDINAL 1/2"1.004.104.001.0016.40ESTRIBOS 1/4"1.001.1630.000.258.70CA-01LONGITUDINAL 3/8"1.004.104.000.569.18ESTRIBOS 1/4"1.000.8630.000.256.45EJE C2C-1LONGITUDINAL 1/2"2.004.104.001.0032.80ESTRIBOS 1/4"2.001.0630.000.2515.90C-2LONGITUDINAL 1/2"1.004.104.001.0016.40ESTRIBOS 1/4"1.001.1630.000.258.70EJE CA'CA-01LONGITUDINAL 3/8"1.004.104.000.569.18ESTRIBOS 1/4"1.000.8630.000.256.45

05.07VIGAS05.07.01VIGAS.- FC=210 kg/cm2 - INCLUYE CURADOm31.69EJE C11.005.350.250.200.27EJE C21.006.050.250.200.30EJE CA1.003.400.250.200.17EJE CA'1.004.300.250.200.22EJE CB1.004.300.250.200.22VA-101 15X201.0016.700.200.150.501.000.760.200.150.02

05.07.02VIGAS.- ENCOFRADO Y DESENCOFRADOm215.21EJE C11.005.350.250.203.48EJE C21.006.050.250.203.93EJE CA1.003.400.250.202.21EJE CA'1.004.300.250.202.80EJE CB1.004.300.250.202.80

05.07.03VIGAS.- ACERO F'y=4,200 kg/cm2KG141.49EJE C1LONGITUDINAL 3/8"1.005.754.000.5612.88ESTRIBOS 1/4"1.000.9634.000.258.16EJE C2LONGITUDINAL 3/8"1.006.454.000.5614.45ESTRIBOS 1/4"1.000.9640.000.259.60EJE CALONGITUDINAL 3/8"1.003.804.000.568.51ESTRIBOS 1/4"1.000.9625.000.256.00EJE CA'LONGITUDINAL 3/8"1.004.704.000.5610.53ESTRIBOS 1/4"1.000.9631.000.257.44EJE CBLONGITUDINAL 3/8"1.004.704.000.5610.53ESTRIBOS 1/4"1.000.9631.000.257.44VA-101 15X201.0016.704.000.5637.411.000.7645.000.258.55

05.09LOSAS ALIGERADAS05.09.01LOSA ALIGERADA.- FC=210 kg/cm2 - INCLUYE CURADOM31.50Nro.LOSA (m)LADRILLO (m)SUB TOTALTOTALVECESAREA ESPESOR LARGO ANCHOESPESOR (m3) (m3)117.130.200.300.300.151.50

VOLUMEN . =VOLUMEN. DE _VOLUMEN. DE DE CONCRETO LOSA ALIGERADALADRILLOS

05.09.02LOSA ALIGERADA.- ENCOFRADO Y DESENCOFRADOM217.13suma de areas de paos117.13

05.09.03LOSA ALIGERADA.- LADR. HUECO 15x30x30Und.142.69Nro.LOSA (m2)LADRILLO
Lilian: PISFIL:EN 1 M2 ENTRAN 8 ,33 LADRILLOSSUB TOTALTOTALVECESAREA CANTIDAD EN 1 M2117.138.33142.69

05.09.04LOSA ALIGERADA.- ACERO F'y=4,200 kg/cm2KG67.20

longitudinales1.003/8"4.6015.000.5638.64bastones1.003/8"3.4015.000.5628.56

Estacin ElctricaPgina &P&Uplanilla de metrado

RESUMENMETRADO RESUMENDESCRIPCIONUnd.METRADOPU1.00CASETA1.01TRAZO Y REPLANTEO GENERAL PARA TODO EL TERRENO 01.01.01transporte de materialesglbERROR:#REF!01.01.02demolicionesm2ERROR:#REF!01.01.03ERROR:#REF!M2ERROR:#REF!01.01.04TRAZO Y REPLANTEO C/EQUIPOM21,755.621.02MOVIMIENTO DE TIERRAS01.02.01EXCAVACION DE ZANJAS Y ZAPATAS RT= 2.0 KG/CM2 H=2.0 mM3518.1301.02.02ERROR:#REF!M3ERROR:#REF!01.02.03RELLENO CON AFIRMADO E=4" PARA PISOS INTERIORES Y EXTERIORESM3410.1301.02.04ERROR:#REF!M3ERROR:#REF!01.02.05RELLENO C/MATERIAL PROPIO PARA RELLENAR ZANJASM268.6701.02.06ELIMINACION DE MATERIAL EXEDENTEM3539.341.03OBRAS DE CONCRETO SIMPLE01.03.01SOLADO PARA CIMIENTOS CORRIDOS E=4" MEZCLA 1:12 CEMENTO:HORMIGONM2271.1001.03.02ERROR:#REF!M2ERROR:#REF!01.03.03ERROR:#REF!M2ERROR:#REF!01.03.04ERROR:#REF!M3ERROR:#REF!01.03.05sardinel f'c=140kg/cm2MLERROR:#REF!1.04CONCRETO ARMADO01.04.01CONCRETO EN ZAPATAS CORRIDAS f'c=210 kg/cm2M386.8601.04.02ZAPATAS. ACERO Fy=4,200 kg/cm2KG976.5001.04.03ERROR:#REF!M3ERROR:#REF!01.04.04ERROR:#REF!KGERROR:#REF!01.04.05VIGAS DE CIMENT..- ENCOF. Y DESENCOFM293.5901.04.06COLUMNAS.- FC=210 kg/cm2 - INCLUYE CURADOM3113.7901.04.07COLUMNAS.- ENCOFRADO Y DESENCOFRADOKG18943.647954401.04.08ERROR:#REF!M2ERROR:#REF!01.04.09CONCRETO f'c=210 kg/cm2 PARA LOSAS MACIZASM37.9001.04.10ENCOFRADO Y DESENCOFRADO NORMAL DE LOSAS MACIZASM231.6101.04.11ERROR:#REF!UNDERROR:#REF!01.04.12ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSAS MACIZASKG604.666666666701.04.13viga I W8X24 L=4.90mUNDERROR:#REF!1.05ERROR:#REF!01.05.01ERROR:#REF!M2ERROR:#REF!01.05.02ERROR:#REF!KGERROR:#REF!1.06ERROR:#REF!01.06.01ERROR:#REF!M2ERROR:#REF!01.06.02ERROR:#REF!M2ERROR:#REF!01.06.03ERROR:#REF!M2ERROR:#REF!01.06.04ERROR:#REF!MLERROR:#REF!01.06.05ERROR:#REF!M2ERROR:#REF!1.07ERROR:#REF!01.07.01ERROR:#REF!M2ERROR:#REF!01.07.02ERROR:#REF!M2ERROR:#REF!1.08ERROR:#REF!01.08.01ERROR:#REF!UNDERROR:#REF!01.08.02ERROR:#REF!UNDERROR:#REF!1.09ERROR:#REF!01.09.01ERROR:#REF!PIE2ERROR:#REF!1.10ERROR:#REF!01.10.01ERROR:#REF!M2ERROR:#REF!01.10.02ERROR:#REF!M2ERROR:#REF!01.10.03ERROR:#REF!M2ERROR:#REF!1.11OTROS01.11.01sembrio de grassm2ERROR:#REF!2.00 BUZONES2.01ERROR:#REF!02.01.01demolicion del buzon 1glb102.01.02ERROR:#REF!M2ERROR:#REF!02.01.03ERROR:#REF!M2ERROR:#REF!2.02ERROR:#REF!02.02.01Excavacion manualM3ERROR:#REF!02.02.02Eliminacion de material exedenteM3ERROR:#REF!

2.03OBRAS DE CONCRETO SIMPLE02.03.01CONCRETO PARA CIMIENTOS CORRIDOS f'c=100kg/cm2M2ERROR:#REF!2.04CONCRETO ARMADO02.04.01ERROR:#REF!02.04.01.01CONCRETO EN CIMIENTOS REFORZADOSM3ERROR:#REF!02.04.01.02ERROR:#REF!M3ERROR:#REF!02.04.01.03ERROR:#REF!M3ERROR:#REF!02.04.01.04ERROR:#REF!M3ERROR:#REF!02.04.01.05CIMIENTOS REFORZADOS - ACERO Fy=4,200 kg/cm2KGERROR:#REF!02.04.01.06CIMIENTOS CORRIDOS, ENCOF. Y DESENCOF.M2ERROR:#REF!02.04.01.07tapa de fierro para buzonUNDERROR:#REF!02.04.01.08escalera de gatoUNDERROR:#REF!02.04.01.09tapa metalica en buzonUNDERROR:#REF!2.05ERROR:#REF!02.05.01ERROR:#REF!M2ERROR:#REF!

3.00ELECTRODUCTOS3.01ERROR:#REF!M2ERROR:#REF!3.01ERROR:#REF!M2ERROR:#REF!3.01ERROR:#REF!M3ERROR:#REF!3.01relleno y compactacion con afirmado en zanja de electroductosM3139.8743.01relleno y compactacion con material propio sellecionado en zanja de elctroductosM3ERROR:#REF!3.01acero de refuerzo fy=4200kg/cm2 linea de electroductokgERROR:#REF!3.01tubera ISO 4435 - S25 U/F de 160mm - ELECTRODUCTO matriz 2X3ml17053.01tubera ISO 4435 - S25 U/F de 160mm - ELECTRODUCTO matriz 2X2ml234.563.01dado de concreto 175kg/cm2 para electroducto 1000x800mmm324.363.01dado de concreto 175kg/cm2 para electroducto 900x650mmm3297.9553.01dado de concreto 175kg/cm2 para electroducto 650x650mmm326.6812

RESUMEN 01RESUMEN DE METRADOS

PROYECTO: ADECUACION, MEJORAMIENTO Y SUSTITUCION DE LA INFRAESTRUCTURA EDUCATIVA DE LA I.E. " SAN NICOLAS"ESPECIALIDAD: ESTRUCTURASCONSULTOR: ING. MANUEL ANTONIO CRUZ DAVILAItemDescripcinUndPOLIDEPOTIVOBOLETERIAGIMNASIOCISTERNAESTACION ELECTRICAMETRADO

01OBRAS PROVISIONALES01.01CARTEL DE IDENTIFICACION DE OBRA DE 2.40 x 3.60 m.und0.001.02ALMACEN, COMEDOR, OFICINA Y GUARDIANIm20.001.03SS.HH. PORTATILES PARA LA OBRAmes0.001.04ENERGIA ELECTRICA PROVISIONALmes0.002TRABAJOS PRELIMINARES GENERALES0.002.01 TRAZO Y REPLANTEO GENERAL PARA TODO EL TERRENO0.002.01.01 TRAZO Y REPLANTEO TOPOGRAFICO.m21,755.6214.33369.6026.2819.172,185.0002.01.03 LIMPIEZA PERMANENTE DE LA OBRAmes0.003MOVIMIENTO DE TIERRAS0.003.01 CORTE DE TERRENO0.003.01.01 CORTE DE TERRENO HASTA 0.20 m.m20.003.02 EXCAVACIONES0.003.02.01 EXCAVACION DE ZANJAS Y ZAPATAS MANUAL, Rt=0.84 kg/cm2, Df=1.90mm3518.136.0984.5463.087.61679.4403.03 RELLENOS0.003.03.01 RELLENO C/MATERIAL PROPIO PARA RELLENAR ZANJASm368.6768.6703.03.02 RELLENO COMPACTADO C/EQUIPO MAT/PRESTAMO AFIRMADO E=0.15 mm3410.13336.302.231.72750.3803.03.03 RELLENO COMPACTADO C/EQUIPO MAT/PRESTAMO OVER E=0.20 mm30.003.04 NIVELACION INTERIOR Y APISONADO0.003.04.01 NIVELACION INTERIOR Y APISONADOm20.003.05 ELIMINACION DE EXCAVACIONES0.003.05.01 ACARREO INTERNO DE MATERIAL PROCEDENTE DE DEMOLICIONES Y EXCAVACIONESm3539.34101.4472.548.75722.0803.05.02 ELIMINACION DE DESMONTE,P/DEMOLICION DE ESTRUCT. CONCR, LADRIL. DIST.=5 KMm3539.34101.4472.548.75722.0804CONCRETO SIMPLE0.004.01 SOLADOS0.004.01.01 SOLADO PARA CIMIENTOS Y ZAPATAS: CONCRETO C:H 1:12 e=20 cm.m2271.1065.7122.28359.0804.01.02 FALSO CIMIENTO F'C=80 KG/CM2 + 30% P.G. MX=6"m365.6604.02CIMIENTO CORRIDO0.004.02.01CIMIENTO CORRIDO: CONCRETO C:H 1:10+30% P.G. m3195.394.4311.216.41217.4404.03 SOBRECIMIENTO0.004.03.01 CONCRETO f'c=175 kg/cm2 PARA SOBRECIMIENTOm32.030.972.9904.03.02 ENCOFRADO Y DESENCOFRADO NORMAL SOBRECIMIENTOm227.0012.9339.9304.04 FALSO PISO0.004.04.01 FALSO PISO: MEZCLA 1:8 e=4" m20.004.05 LOSA DEPORTIVA0.004.05.01 CONCRETO F'C=175 KG/CM2 EN PLATAFORMA DEPORTIVAm30.004.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN PLATAFORMA DEPORTIVAm20.005CONCRETO ARMADO0.005.01.ZAPATA CORRIDA0.005.01.01 CONCRETO EN ZAPATAS CORRIDAS f'c=210 kg/cm2m386.8614.19101.0505.01.02 ACERO CORRUGADO FY=4200 KG/CM2 PARA ZAPATAS CORRIDASkg976.50327.601,304.1005.02CIMIENTOS REFORZADOS05.02.01 CONCRETO EN CIMIENTOS REFORZADOSm30.7852.0705.02.02 CIMIENTOS CORRIDOS, ENCOF. Y DESENCOF.m210.34336.6405.02.03 CIMIENTOS REFORZADOS - ACERO Fy=4,200 kg/cm2kg106.621,917.7605.03 VIGA DE CIMENTACION 0.005.03.01 CONCRETO EN VIGAS DE CIMENTACION f'c=210 kg/cm2m39.609.6005.03.02 ENCOFRADO Y DESENCOFRADO EN VIGA CIMENTACIONm293.5993.5905.03.03 ACERO CORRUGADO FY=4200 KG/CM2 PARA VIGA CIMENTACIONkg1,189.101,189.1005.04 SOBRECIMIENTO REFORZADO0.005.04.01 CONCRETO EN SOBRECIMIENTO REFORZADO f'c=210 kg/cm2m30.6129.261.5731.4405.04.02 ENCOFRADO Y DESENCOFRADO EN SOBRECIMIENTO REFORZADOm28.1620.9329.0905.04.03 ACERO CORRUGADO FY=4200 KG/CM2 PARA SOBRECIMIENTO REFORZADOkg49.7798.36148.1305.05 COLUMNAS0.005.05.01 CONCRETO EN COLUMNAS f'c=210 kg/cm2m3113.790.4140.500.731.51156.9405.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNASm21,150.337.59684.347.8424.721,874.8205.05.03 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNASkg18,943.6542.534,660.27255.70178.8724,081.0105.06 COLUMNETAS0.005.06.01 CONCRETO EN COLUMNETAS f'c=210 kg/cm2m30.005.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN COLUMNETASm20.005.06.03 ACERO fy=4200 kg/cm2 GRADO 60 en COLUMNETASkg0.005.07 VIGAS0.005.07.01 CONCRETO EN VIGAS f'c=210 kg/cm2m333.591.3515.281.6951.9105.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGASm2322.2324.29163.3215.21525.0605.07.03 ACERO fy=4200 kg/cm2 GRADO 60 en VIGASkg3,453.08183.921,671.31141.495,449.8005.08 VIGUETAS0.005.08.01 CONCRETO EN VIGUETAS f'c=210 kg/cm2m30.005.08.02 ENCOFRADO Y DESENCOFRADO NORMAL EN VIGUETASm20.005.08.03 ACERO fy=4200 kg/cm2 GRADO 60 en VIGUETASkg0.005.09 LOSAS ALIGERADAS0.005.09.01LOSA ALIGERADA.- FC=210 kg/cm2 - INCLUYE CURADOm32.201.503.7005.09.02LOSA ALIGERADA.- ENCOFRADO Y DESENCOFRADOm225.1017.1342.2305.09.04LOSA ALIGERADA.- LADR. HUECO 15x30x30u209.08142.69351.7805.09.03LOSA ALIGERADA.- ACERO F'y=4,200 kg/cm2kg67.5067.20134.7005.10MUROS DE CONCRETO0.005.10.01 CONCRETO f'c=210 kg/cm2 PARA MUROSm360.5310.2870.8105.10.02 ENCOFRADO Y DESENCOFRADO NORMAL DE MUROSm2696.5352.39748.9205.10.03 ACERO CORRUGADO FY=4200 KG/CM2 PARA MUROSkg3,409.02679.144,088.1605.11ESCALERAS0.005.11.01 CONCRETO f'c=210 kg/cm2 PARA ESCALERASm30.005.11.02 ENCOFRADO Y DESENCOFRADO NORMAL DE ESCALERASm20.005.11.03 ACERO CORRUGADO FY=4200 KG/CM2 PARA ESCALERASkg0.005.12LOSAS MACIZAS0.005.12.01 CONCRETO f'c=210 kg/cm2 PARA LOSAS MACIZASm37.905.2813.1905.12.02 ENCOFRADO Y DESENCOFRADO NORMAL DE LOSAS MACIZASm231.6126.4258.0305.12.03 ACERO CORRUGADO FY=4200 KG/CM2 PARA LOSAS MACIZASkg604.67287.44892.1005.13PLACAS DE CONCRETO0.005.13.01 CONCRETO f'c=210 kg/cm2 PARA PLACAS DE CONCRETOm30.005.13.02 ENCOFRADO Y DESENCOFRADO NORMAL DE PLACAS DE CONCRETOm20.005.13.03 ACERO CORRUGADO FY=4200 KG/CM2 PARA PLACAS DE CONCRETOkg0.005.14GRADERIAS0.005.14.01 CONCRETO f'c=210 kg/cm2 PARA GRADERIASm3442.38442.3805.14.02 ENCOFRADO Y DESENCOFRADO NORMAL DE GRADERIASm2886.14886.1405.14.03 ACERO CORRUGADO FY=4200 KG/CM2 PARA GRADERIASkg5,619.015,619.0105.17CISTERNA0.005.17.01 CONCRETO EN CISTERNA F'C=280KG/CM2m317.6217.6205.17.02 ENCOFRADO Y DESENCOFRADO PARA CISTERNAm2124.14124.1405.17.03 ACERO CORRUGADO FY=4200 KG/CM2 PARA CISTERNAkg1,773.151,773.1506.00OTROS0.006.01 LLORADEROS0.006.01.01 TUBO PVC 2" @ 3.00 m.m0.006.02 TIJERALES METALICOS0.006.02.01 TIJERAL T-01 L=37.70mund7.007.0006.02.02 TIJERAL T-02 L=24.50mund1.001.0006.02.03 TIJERAL T-03 L=8.60mund3.003.0006.02.04 VIGUETAS METALICAS 3X6 L=34.00mund37.0037.0006.02.05 TENSORES DE 3/4" L=7.700mund48.0048.0006.02.06 TIJERAL TG-01 L=16.80mund0.05.005.0006.02.07 VIGUETAS CORREAS L= 17.50mund0.017.0017.0006.02.08 TENSORES DE 5/8" L=5.00mund0.044.0044.00