Trab Prel"PABELLON 03"

1.02.00.00 TRABAJOS PRELIMINARES

1.02.01.00 LIMPIEZA DE TERRENOUBICACINN ELEM.LONG.ANCHON VECESREA ( m )TOTAL( m )6.5520.751.00135.91

135.91

1.02.02.00 TRAZO, NIVEL Y REPLANTEO PRELIMINARUBICACINN ELEM.LONG.ANCHON VECESREA ( m )TOTAL( m )

135.91

1.02.03.00 LIMPIEZA PERMANENTE EN OBRAUBICACINN ELEM.LONG.ANCHON VECESREA ( m )TOTAL( m )

135.91

&"Arial,Negrita Cursiva"AMPLIACIN Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. N 14132, DEL DISTRITO DE LAS LOMAS PROVINCIA DE PIURA

&"Arial,Negrita Cursiva"&8Consorcio Tres Marias&"Arial,Negrita Cursiva"&8Jorge Antonio Ulloque RodrguezReg. OSCE N C-0944

Mov Tie

01.04.00.00 MOVIMIENTO DE TIERRAS

1.04.03.00 EXCAVACION DE ZANJAS P/CIMIENTOS Y ZAPATASDESCRIPCINN ELEM.LONG.ANCHOALTURAN VECESVOLUMEN (m3)TOTAL( m3 )

Direccion " X "EJE " M " / 6 Y 7117.750.601.00110.6521.501.201.0027.20EJE " N " / 6 Y 7117.150.601.00110.2921.801.501.00210.80Direccion " Y "EJE " 1 " y "5" / A Y C15.730.751.0028.6EJE " 3 " / A Y C15.730.951.0015.44

52.98

1.04.04.00 BASE GRANULAR COMPACT. C/PLANCHA VIB. e= 0.10mDESCRIPCINN ELEM.LONG.ANCHOALTURAN VECESAREA(m3)TOTAL( m2 )En interior de aulasInterior de A1110.006.25162.5Pintos en Columnas10.100.272-0.0510.100.874-0.3510.250.272-0.1410.100.332-0.07Interior de A2110.006.25162.5Pintos en Columnas10.100.272-0.0510.100.874-0.3510.250.272-0.1410.100.332-0.07

123.78

1.04.05.00 RELLENO C/MATERIAL PROPIO COMPACT. C/PLANCHA VIB.DESCRIPCINN ELEM.LONG.ANCHOALTURAN VECESVOLUMEN (m3)TOTAL( m3 )

ExcavacionesAREADireccion " X "EJE " M " y "N" / 6 Y 7117.750.350.4012.496.212511.500.950.4021.141.425EJE " N" / 1 Y 5117.750.350.4012.496.212511.251.800.4021.82.25Direccion " Y "EJE " 1 " y "5" / A Y C15.730.500.4022.292.865EJE " 3 " / M Y N15.730.750.7013.014.297523.2625

13.22

1.04.06.00 REFINE, NIVELACION Y COMPACTACIONUBICACINN ELEM.LONG.ANCHOALTURAN VECESREA ( m )TOTAL ( m )DE BASE GRANULAR123.78DE RELLENO -23.26100.52

1.04.07.00 ACARREO DE MATERIAL EXCEDENTE (EXC ZANJAS)DESCRIPCINN ELEM.LONG.ANCHOALTURAN VECESVOLUMEN (m3)TOTAL( m3 )Excavaciones66.23Rellenos-16.53El TOTAL est incluyendo el 25% de esponjamiento49.70

1.04.08.00 ELIMINACION DE MATERIAL EXCEDENTE Dmax=7.5 KmDESCRIPCINN ELEM.LONG.ANCHOALTURAN VECESVOLUMEN (m3)TOTAL( m3 )

El TOTAL est incluyendo el 25% de esponjamiento49.70

1.04.06.00 RELLENO SELECCIONADO COMPACT. C/PLANCHA VIB. EN CAPAS DE e= 0.10mDESCRIPCINN ELEM.LONG.ANCHOALTURAN VECESVOLUMEN (m3)TOTAL( m3 )En interior de aulasInterior de A1110.006.250.60137.5Pintos en Columnas10.100.270.6020.0310.100.870.6040.2110.250.270.6020.0810.100.330.6020.04Interior de A2110.006.250.60137.5Pintos en Columnas10.100.270.6020.0310.100.870.6040.2110.250.270.6020.0810.100.330.6020.04

75.72

&"Arial,Negrita Cursiva"AMPLIACIN Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. N 14132, DEL DISTRITO DE LAS LOMAS PROVINCIA DE PIURA

&"Arial,Negrita Cursiva"&8Consorcio Tres Marias&"Arial,Negrita Cursiva"&8Jorge Antonio Ulloque RodrguezReg. OSCE N C-0944

C Simp

1.05.00.00 OBRAS DE CONCRETO SIMPLE

1.05.01.00 CIMIENTOS CORRIDOS 1.10 ( C-H ) + 30% P.G.UBICACINN ELEM.LONG.ANCHOALTURAN VECESVOLUMEN ( m3 )TOTAL ( m3 )Direccin X-XEje "A" 118.250.600.6016.57Eje "C"117.650.600.6016.35Direccion " Y "EJE " 1 " / A Y C15.350.750.6012.41EJE " 3 " / A Y C15.350.950.6013.05EJE " 5 " / A Y C15.350.750.6012.41

20.79

1.05.02.00 CONCRETO f'c = 100 Kg/cm2 SOLADO e = 0.10 mDESCRIPCINN ELEM.LONG.ANCHOALTURAN VECESREA ( m )TOTAL( m )

Direccion " X "EJE " M " / 1 Y 511.501.2023.6EJE " N" / 1 Y 511.801.5025.4

9.00

1.05.03 .00 CONCRETO 1:8 ( C-H) FALSO PISO e = 0.10 mDESCRIPCINLONG.ANCHOALTURAN VECESREA ( m )TOTAL( m )En interior de aulasInterior de A1110.006.25162.5Pintos en Columnas10.100.272-0.0510.100.874-0.3510.250.272-0.1410.100.332-0.07Interior de A2110.006.25162.5Pintos en Columnas10.100.272-0.0510.100.874-0.3510.250.272-0.1410.100.332-0.07

123.78

1.05.04.00 JUNTA DE DILATACION e=1/2" ,h= 0.10mDESCRIPCINN ELEM.LONG.ANCHOALTURAN VECESREA ( m )TOTAL( m )

(EJES M-N / 6-7)CONTORNO234.10168.20CENTRICO25.55111.10

79.30

&"Arial,Negrita Cursiva"AMPLIACIN Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. N 14132, DEL DISTRITO DE LAS LOMAS PROVINCIA DE PIURA

&"Arial,Negrita Cursiva"&8Consorcio Tres Marias&"Arial,Negrita Cursiva"&8Jorge Antonio Ulloque RodrguezReg. OSCE N C-0944

CE Zap

1.06.00.00 OBRAS DE CONCRETO ARMADO

1.06.01.00 ZAPATAS

1.06.01.01 CONCRETO f'c = 210 Kg/cm - ZAPATASUBICACINN ELEM.LONG.ANCHOALTURAN VECESVOLUMEN ( m3 )TOTAL( m3 )

Direccion " X "EJE " M " / 1 Y 511.501.200.5021.8EJE " N" / 1 Y 511.801.500.5022.7

4.50

4.01.02 ENCOFRADO Y DESENCOFRADO - ZAPATASUBICACINN ELEM.LONG.ANCHOALTURAN VECESAREA ( m )TOTAL( m )

Direccion " X "EJE " M " / 1 Y 5121.230.50221.23EJE " N" / 1 Y 5121.230.50221.23

42.46

4.01.04 TRATAMIENTO DE SUPERFICIES - ZAPATASUBICACINN ELEM.LONG.ANCHOALTURAN VECESAREA ( m )TOTAL( m )

Direccion " X "EJE " M " / 1 Y 5121.230.60112.74EJE " N" / 1 Y 5121.230.60112.74

25.48

4.01.05 CURADO DE ESTRUCTURAS - ZAPATASUBICACINN ELEM.LONG.ANCHOALTURAN VECESVOLUMEN ( m3 )TOTAL( m )

&"Arial,Negrita Cursiva"AMPLIACIN Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. N 14132, DEL DISTRITO DE LAS LOMAS PROVINCIA DE PIURA

&"Arial,Negrita Cursiva"&8Consorcio Tres Marias&"Arial,Negrita Cursiva"&8Jorge Antonio Ulloque RodrguezReg. OSCE N C-0944

As Zapatas

1.06.01.02 ACERO Fy = 4,200 Kg/cm - ZAPATASTipos de AceroDescripcinUbicacin - EjesDiseo de fierroN Elementos igualesN de piezas/elementoLongitud por piezaLongitudes por abcdeLt1/4"3/8"1/2"5/8"3/4"1"

Direccion "X"EJE " M " / 1 Y 5Z-1Tipo I1/2"261.351.3516.20Tipo II1/2"271.051.0514.70EJE " N" / 1 Y 5Z-2Tipo I1/2"271.651.6523.10Tipo II1/2"281.351.3521.60

Long. Total/0.000.0075.600.000.000.00Peso Kg/m0.250.560.991.552.243.97TOTAL ( Kg )0.000.0074.840.000.000.0074.84

&"Arial,Negrita Cursiva"AMPLIACIN Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. N 14132, DEL DISTRITO DE LAS LOMAS PROVINCIA DE PIURA&"Arial,Negrita Cursiva"&8Reg. OSCE N C-0944

&"Arial,Negrita Cursiva"&8Consorcio Tres Marias&"Arial,Negrita Cursiva"&8Jorge Antonio Ulloque RodrguezReg. OSCE N C-0944

Tipo I:Tipo II:Tipo I:Tipo II:Tipo I :Tipo I:Tipo I:Tipo I:TIPO II :TIPO III :TIPO IV :TIPO V :TIPO VI:

CE V-C

1.06.02.00 VIGA DE CIMENTACION

1.06.02.01 CONCRETO f'c = 210 Kg/cm - VIGA DE CIMENTACIONUBICACINN ELEM.LONG.ANCHOALTURAN VECESVOLUMEN ( m3 )TOTAL( m3 )

Direccion " X "EJE " A " / 1 Y 5VC117.170.250.4011.72EJE " C" / 1 Y 5VC-2117.170.250.4011.72

3.44

1.06.02.02 ENCOFRADO Y DESENCOFRADO - VIGA DE CIMENTACIONUBICACINN ELEM.LONG.ANCHOALTURAN VECESAREA ( m2 )TOTAL( m )

Direccion " X "EJE " A " / 1 Y 5VC117.170.40213.74EJE " C" / 1 Y 5VC117.170.40213.74

27.48

&"Arial,Negrita Cursiva"AMPLIACIN Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. N 14132, DEL DISTRITO DE LAS LOMAS PROVINCIA DE PIURA

&"Arial,Negrita Cursiva"&8Consorcio Tres Marias&"Arial,Negrita Cursiva"&8Jorge Antonio Ulloque RodrguezReg. OSCE N C-0944

As V-C

1.06.02.03 ACERO Fy = 4,200 Kg/cm - VIGA DE CIMENTACIONTipos de AceroDescripcinUbicacin - EjesDiseo de fierroN Elementos igualesN de piezas/elementoLongitud por piezaLongitudes por abcdeLt1/4"3/8"1/2"5/8"3/4"1"

Direccion " X "EJE " A " / 1 Y 5VC-2Tipo I5/8"1620.690.900.6022.19133.14Tipo III3/8"1690.340.190.101.2686.94EJE " C" / 1 Y 5VC-2Tipo I5/8"1620.690.900.8022.39134.34Tipo III3/8"1690.340.190.101.2686.94

Long. Total/0.00173.880.00267.480.000.00Peso Kg/m0.250.560.991.552.243.97TOTAL ( Kg )0.0097.370.00414.590.000.00511.96

&"Arial,Negrita Cursiva"AMPLIACIN Y MEJORAMIENTO DE LA INFRAESTRUCTURA DE LA I.E. N 14132, DEL DISTRITO DE LAS LOMAS PROVINCIA DE PIURA

&"Arial,Negrita Cursiva"&8Consorcio Tres Marias&"Arial,Negrita Cursiva"&8Jorge Antonio Ulloque RodrguezReg. OSCE N C-0944

Tipo I:Tipo II:Tipo I:Tipo II :Tipo III :Tipo IV :Tipo V :Tipo VI :Tipo VII :Tipo VIII :Tipo IX:Tipo X:Tipo XI:

CE SR

1.06.03.00 SOBRECIMIENTO REFORZADO

1.06.03.01 CONCRETO f'c = 210 Kg/cm - SOBRECIMIENTOUBICACINN ELEM.LONG.ANCHOALTURAN VECESVOLUMEN ( m3 )TOTAL( m3 )

Direccion " X "EJE " M " / 1 Y 5117.170.150.9512.45EJE " N" / 1 Y 5117.170.150.9512.45Direccion " Y "EJE " 1 " / M Y N12.920.251.3521.97EJE " 3 " / M Y N12.920.251.3521.97EJE " 5 " / M Y N12.920.251.3521.97

10.81

1.06.03.02 ENCOFRADO Y DESENCOFRADO - SOBREC. REF.UBICACINN ELEM.LONG.ANCHOALTURAN VECESAREA ( m2 )TOTAL( m )

Direccion " X "EJE " A " / 1 Y 5117.170.95232.62EJE " C" / 1 Y 5117.170.95232.62Direccion " Y "EJE " 1 " / M Y N22.921.35215.77EJE " 3 " / M Y N22.921.35215.77EJE " 5 " / M Y N22.921.35215.77

112.55

4.02.04 CURADO DE ESTRUCTURAS - SOBREC. REF.UBICACINN ELEM.LONG.ANCHOALTURAN VECESAREA ( m2 )TOTAL( m )

ITEM 4.02.021112.55112.55

112.55

1.06.02.00 VIGA DE CIMENTACION

1.06.02.01 CONCRETO f'c = 210 Kg/cm - VIGA DE CIMENTACIONUBICACINN ELEM.LONG.ANCHOALTURAN VECESVOLUMEN ( m3 )TOTAL( m3 )

Direccion " X "EJE " A " / 1 Y 5VC117.170.250.4011.72EJE " C" / 1 Y 5VC-2117.170.250.4011.72

3.44

1.06.02.02 ENCOFRADO Y DESENCOFRADO - VIGA DE CIMENTACIONUBICACINN ELEM.LONG.ANCHOALTURAN VECESAREA ( m2 )TOTAL( m )

Direccion " X "EJE " A " / 1 Y 5VC117.170.40213.74EJE " C" / 1 Y 5