20140301 SCADA Presentationl

17
www.dongfang-china.com SCADA FOR MP TRANSMISSION SYSTEM Dongfang Electronics Co., Ltd. Dated: 3 th Mar 2014 1

description

presentation

Transcript of 20140301 SCADA Presentationl

  • Agenda

  • Present Status Jabalpur Temporary Master Station:

    *

    DeviceStatusRemarkServerDelivered by 4 MarDell PVT Customer ClearanceWorkstationTesting DF8000 at FactoryDeliver to site by 10 MarNetwork DeviceTesting at FactoryDeliver to site by 10 Mar

  • Present Status Communication for Pilot:

    *

    Service ProviderStatusRemark & SupportBSNLWait BSNL to start work for TCC link construction as per AMR in SLDCMPPTCL help to push BSNL the progress.Finish by 10 Mar at latestRelienceAsk for permission of erection roof top of tower at 23 Jan but denied by MPPTCL at 21 Feb.Consider to erect tower outside Meeting with MPPTCL at 3 Mar and request the permission from MPPTCL again

  • Present Status S/s for Pilot:

    *

    NameStatusRemark & Support132 KV MadhotalAll cable laying and wiring; 7 feeder with local testing;Arrange AE or JE to supervise and provide support during testing220 KV BhopalShift the material at 3 Mar400 KV IndoreShift the material at 3 Mar

  • Present Status S/s for Pilot:

    *

    NameStatusRemark & Support132 KV MadhotalAll cable laying and wiring; 7 feeder with local testing;Arrange AE or JE to supervise and provide support during testing220 KV BhopalShift the material at 3 Mar400 KV IndoreShift the material at 3 Mar

  • Present Status S/s :

    Finished 45 S/s Site survey by 25Feb. Finished 38 S/s Site survey report by 1 Mar

    Finished manufacture 50 S/s RTU module

    Finished some material PO for the first phase *

  • Agenda1

  • Plan of Next 6 Months for First Phase20140301 project plan by 28 Sep 2014 V3.xlsx*

  • Agenda131

  • Method of Site Survey.

    ProcedureDetail1. SLDUPDATE & MODIFIED SLD ALONG WITH MPPTCL REPRESENTATIVECHECK ALL FEEDERS NAME & CONNECTIVITY ON SLD2. Control Room LayoutCONFIRM THE LOCATION OF DFE RTU & LDMS ALONG WITH MPPTCL REPRESENTATIVECHECK THE CABLE TRENCH ROUTE FOR LAYING THE CABLESPREPARE CONTROL ROOM LAYOUT3. Interface PointNOTE ALL INTERFACE POINTS AS PER SIGNAL LIST FROM EACH C&R PANEL.CONFIRM THE PLACE FOR RING TYPE CT TO INSTALL INSIDE THE ACDB PANELCONFIRM THE PLACE FOR DEVICES & TBs TO INSTALL INSIDE C&R PANEL.GET PERMISSION ON LAYOUT & SLD THROUGH MPPTCL REPRESENTATIVE SIGNATURE

  • Agenda1314

  • I & C Schedule*

    Power cable & DO & Communication cable Laying Reel Fixing & Drilling CMR Looping & CMR fixingUpdate the wiring schedule RTU termination ( DO,Communication,PS)CT.PT DI,DO,PS TB Fixing DO & MFM Communication Looping termination in FeederDI Cable Laying & TerminationDI termination in RTUMFM Fixing & Termination &OLTC Panel Wiring & Termination & ACDB( Ring Type CT ),DC TransducerOthers ( Pending Work & Power ON)Local Testing

  • Procedure of Test*Local test of LDMS End to End Test from LDMS and Control CenterSite Acceptance Test such as function test

    MPTTCL_SCADA_SAT_V2.0 .pdf MPTTCL_LDMS_SAT_V1.1 .pdf RTU Commissioning Check List V2.pdf

  • Agenda1315

  • Support from MPPTCL*

    MPPTCL Arrange AE or JE to supervise and provide support during testing at EHV S/s

    2. Permanent Control center at 220KV sub-station Jabalpur must be ready before 1-Aug,2014. 3. 2 MBPS leased line between CC and Remote viewer to be established by MPPTCL

  • Q & A *

    *7. as a conclusion: scope of the work is as below: it is a Turn key project including SCADA CC hardware & Software, Remote view terminals and RTU system integration, training and AMC.****

    T**