EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES 39 Presupuesto Presupuesto Costo al 11/12/2012 Lugar CORRALES - TUMBES - TUMBES Item Descripción Und. Metrado Precio S/. Parcial S/. 01 OBRAS PRELIMINARES 140,131.53 01.01 CARTEL PARA OBRA (3.60m x 2.40m) und 1.00 713.61 713.61 01.02 MOVILIZACION Y DESMOVILIZACION EQUIPOS und 8.00 997.59 7,980.72 01.03 CONTROL DE NIVELES TOPOGRÁFICOS DIA 60.00 393.50 23,610.00 01.04 GUARDIANÍA DE EQUIPOS día 60.00 1,797.12 107,827.20 02 MOVIMIENTO DE TIERRAS 1,320,404.78 02.01 m3 220,385.40 5.07 1,117,353.98 02.02 m3 10,275.85 19.76 203,050.80 Costo Directo 1,460,536.31 Gastos Generales 146,053.63 Utilidad 146,053.63 --------------------------- Sub Total 1,752,643.57 IGV 315,475.84 ================== Total Presupuesto 2,068,119.41 SON : DOS MILLONES SESENTA Y OCHO MIL CIENTO DIECINUEVE CON 41/100 NUEVOS SOLES EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL ESTABLE LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL INESTABLE

description

topografia

Transcript of 7 Metrados

Page 1: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

39

Presupuesto

Presupuesto

Costo al 11/12/2012Lugar CORRALES - TUMBES - TUMBES

Item Descripción Und. Metrado Precio S/. Parcial S/.

01 OBRAS PRELIMINARES 140,131.53

01.01 CARTEL PARA OBRA (3.60m x 2.40m) und 1.00 713.61 713.61

01.02 MOVILIZACION Y DESMOVILIZACION EQUIPOS und 8.00 997.59 7,980.72

01.03 CONTROL DE NIVELES TOPOGRÁFICOS DIA 60.00 393.50 23,610.00

01.04 GUARDIANÍA DE EQUIPOS día 60.00 1,797.12 107,827.20

02 MOVIMIENTO DE TIERRAS 1,320,404.78

02.01 m3 220,385.40 5.07 1,117,353.98

02.02 m3 10,275.85 19.76 203,050.80

Costo Directo 1,460,536.31

Gastos Generales 146,053.63

Utilidad 146,053.63

---------------------------

Sub Total 1,752,643.57

IGV 315,475.84

==================

Total Presupuesto 2,068,119.41

SON : DOS MILLONES SESENTA Y OCHO MIL CIENTO DIECINUEVE CON 41/100 NUEVOS SOLES

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL ESTABLE

LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL INESTABLE

Page 2: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

53

Análisis de precios unitarios

Presupuesto

Fecha presupuesto 11/12/2012

Partida 01.01 CARTEL PARA OBRA (3.60m x 2.40m)

Rendimiento und/DIA 1.0000 EQ. 1.0000 Costo unitario directo por : und 713.61

Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.

Mano de Obra

0147010002 OPERARIO hh 0.1250 1.0000 15.55 15.55

0147010004 PEON hh 0.3000 2.4000 11.16 26.78

42.33

Materiales

0202010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg 2.0000 4.70 9.40

0221000000 CEMENTO PORTLAND TIPO I (42.5KG) bol 2.0000 20.35 40.70

0238000000 HORMIGON m3 0.6700 25.00 16.75

0239050000 AGUA m3 0.1000 10.60 1.06

0243010003 MADERA TORNILLO p2 30.0000 4.50 135.00

0244030022 TRIPLAY DE 1.20 X 2.40 X 6 mm und 3.0000 38.75 116.25

0298010094 GIGANTOGRAFÍA DE 3.6 x 2.5 und 1.0000 350.00 350.00

669.16

Equipos

0337010001 HERRAMIENTAS MANUALES %MO 5.0000 42.33 2.12

2.12

Partida 01.02 MOVILIZACION Y DESMOVILIZACION EQUIPOS

Rendimiento und/DIA 1.5000 EQ. 1.5000 Costo unitario directo por : und 997.59

Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.

Mano de Obra

0147010002 OPERARIO hh 1.0000 5.3333 15.55 82.93

0147010004 PEON hh 1.0000 5.3333 11.16 59.52

142.45

Equipos

0337010001 HERRAMIENTAS MANUALES %MO 3.0000 142.45 4.27

0348040010 CAMION PLATAFORMA 4 X 2 122 HP 8 ton hm 1.0000 5.3333 159.54 850.87

855.14

Partida 01.03 CONTROL DE NIVELES TOPOGRÁFICOS

Rendimiento DIA/DIA 1.0000 EQ. 1.0000 Costo unitario directo por : DIA 393.50

Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.

Mano de Obra

0147000032 TOPOGRAFO hh 1.0000 8.0000 15.22 121.76

0147010004 PEON hh 2.0000 16.0000 11.16 178.56

300.32

Equipos

0337010001 HERRAMIENTAS MANUALES %MO 5.0000 300.32 15.02

0337540001 MIRAS Y JALONES hm 1.0000 8.0000 2.00 16.00

0349190003 NIVEL TOPOGRAFICO CON TRIPODE he 1.0000 8.0000 7.77 62.16

93.18

Partida 01.04 GUARDIANÍA DE EQUIPOS

Rendimiento día/DIA 1.0000 EQ. 1.0000 Costo unitario directo por : día 1,797.12

Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.

Mano de Obra

0147010003 OFICIAL hh 18.0000 144.0000 12.48 1,797.12

1,797.12

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

Page 3: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

54

Presupuesto

Fecha presupuesto 11/12/2012

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

Partida 2.01 LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL

ESTABLE

Rendimiento m3/DIA 560.0000 EQ. 560.0000 Costo unitario directo por : m3 5.07

Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.

Mano de Obra

0147010003 OFICIAL hh 1.0000 0.0143 12.48 0.18

0147010004 PEON hh 1.0000 0.0143 11.16 0.16

0147010005 CONTROLADOR hh 1.0000 0.0143 15.55 0.22

0.56

Equipos

0337010001 HERRAMIENTAS MANUALES %MO 5.0000 0.56 0.03

0349040022 RETROEXCAVADORA SOBRE ORUGAS 170 - 250 HP hm 1.0000 0.0143 313.56 4.48

4.51

Partida 2.02 LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL

INESTABLE

Rendimiento m3/DIA 144.0000 EQ. 144.0000 Costo unitario directo por : m3 19.76

Código Descripción Recurso Unidad Cuadrilla Cantidad Precio S/. Parcial S/.

Mano de Obra

0147010003 OFICIAL hh 1.0000 0.0556 12.48 0.69

0147010004 PEON hh 1.0000 0.0556 11.16 0.62

0147010005 CONTROLADOR hh 1.0000 0.0556 15.55 0.86

2.17

Materiales

0243010004 MADERA ROLADA DE D = 12", L = 6 m p2 0.0107 4.24 0.05

0.05

Equipos

0337010001 HERRAMIENTAS MANUALES %MO 5.0000 2.17 0.11

0349040022 RETROEXCAVADORA SOBRE ORUGAS 170 - 250 HP hm 1.0000 0.0556 313.56 17.43

17.54

Page 4: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

43

Precios y cantidades de recursos requeridos por tipoObra

Lugar CORRALES- TUMBES - TUMBES

Código Recurso Unidad Cantidad Precio S/. Parcial S/.

MANO DE OBRA

0147000032 TOPOGRAFO hh 480.0000 15.22 7,305.600147010002 OPERARIO hh 43.6664 15.55 679.010147010003 OFICIAL hh 12,362.8485 12.48 154,288.35

0147010004 PEON hh 4,727.9141 11.16 52,763.52

0147010005 CONTROLADOR hh 3,722.8489 15.55 57,890.30

272,926.78

MATERIALES

0202010005 CLAVOS PARA MADERA CON CABEZA DE 3" kg 2.0000 4.70 9.40

0221000000 CEMENTO PORTLAND TIPO I (42.5KG) bol 2.0000 20.35 40.70

0238000000 HORMIGON m3 0.6700 25.00 16.75

0239050000 AGUA m3 0.1000 10.60 1.06

0243010003 MADERA TORNILLO p2 30.0000 4.50 135.00

0243010004 MADERA ROLADA DE D = 12", L = 6 m p2 109.9516 4.24 466.19

0244030022 TRIPLAY DE 1.20 X 2.40 X 6 mm und 3.0000 38.75 116.25

0298010094 GIGANTOGRAFÍA DE 3.6 x 2.5 und 1.0000 350.00 350.00

1,135.35

EQUIPOS

0337010001 HERRAMIENTAS MANUALES %MO 8,222.99

0337540001 MIRAS Y JALONES hm 480.0000 2.00 960.00

0348040010 CAMION PLATAFORMA 4 X 2 122 HP 8 ton hm 42.6664 159.54 6,807.00

0349040022 RETROEXCAVADORA SOBRE ORUGAS 170 - 250 HP hm 3,722.8485 313.56 1,167,336.38

0349190003 NIVEL TOPOGRAFICO CON TRIPODE he 480.0000 7.77 3,729.60

1,187,055.97Total S/. 1,461,118.10

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

Page 5: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

45

Fórmula Polinómica

Presupuesto

Fecha Presupuesto 9/12/2012

Moneda NUEVOS SOLES

Ubicación Geográfica

0.141*(Jr / Jo) + 0.565*(EQr / EQo) + 0.294*(GGr / GGo)

Monomio Factor Símbolo Indice Descripción

1 0.132### M 47 MANO DE OBRA INC. LEYES SOCIALES2 0.574### M 49 MAQUINARIA Y EQUIPO IMPORTADO3 0.294### I 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

CORRALES - TUMBES - TUMBES

K =

(%)

Page 6: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

41

ANALISIS DE GASTOS GENERALES

COSTO DIRECTO 1,460,536.31

Descripción Und Cantidad P.U. Parcial Subtotal Total

GASTOS GENERALES FIJOS 32,917.28

Campamento para el contratista 14,250.00

Computadoras Und 3.00 3,500.00 10,500.00

Muebles de campamento en obra Glb 1.00 3,750.00 3,750.00

Gastos administrativos 3,500.00

Gastos legales Glb 1.00 3,500.00 3,500.00

Otros 15,167.28

Utiles de oficina, teléfono y otros Glb 1.00 4,800.00 4,850.00

Fotocopias de planos e informes técnicos finales Glb 1.00 4,217.28 4,217.28

ITF Glb 1.00 2,500.00 2,500.00

Equipo de seguridad (botas, cascos, etc.) Glb 1.00 3,600.00 3,600.00

GASTOS GENERALES VARIABLES 113,136.35

Alquiler de oficinas y campamento 17,700.00

Oficina Contratista mes 2.00 1,500.00 3,000.00

Almacen mes 2.00 850.00 1,700.00

Mantenimiento mes 2.00 2,300.00 4,600.00

Seguridad mes 2.00 4,200.00 8,400.00

Dirección técnica y administrativa en obra 49,800.00

Personal profesionalIngeniero Residente mes 2.00 5,500.00 11,000.00

Ingeniero Mecanico mes 2.00 4,500.00 9,000.00

Personal técnicoMecánico m-h 2.00 3,000.00 6,000.00

Aasistente técnico mes 2.00 1,500.00 3,000.00

Personal administrativo y auxiliarAdministrador m-h 2.00 3,000.00 6,000.00

Almacenero m-h 2.00 1,500.00 3,000.00

Choferes m-h 2.00 1,400.00 2,800.00

Guardianes m-h 6.00 1,500.00 9,000.00

Equipos no incluidos en los costos directos 12,160.00

Camioneta Pick-Up doble cabina mes 2.00 1,400.00 2,800.00

Equipo de radio Und 6.00 1,560.00 9,360.00

Gastos financieros 33,476.35

Cartas fianzasAdelanto en efectivo Glb 1.00 26,289.65 26,289.65

Fiel cumplimiento Glb 1.00 3,500.00 3,500.00

Seguros de obra Glb 1.00 3,686.70 3,686.70

TOTAL GASTOS GENERALES 146,053.63

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE

TUMBES

Page 7: 7 Metrados

CRONOGRAMA DE EJECUCION DE OBRA

PresupuestoEXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

Cliente PEBPT

Lugar CORRALES TUMBES TUMBES

Item DescripciónDuración 1º Mes Duración 2ª Mes

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58

01 OBRAS PRELIMINARES x x x x x x x x x x x x x x x x x x x x x x x x x x x x x01.01 CARTEL PARA OBRA (3.60m x 2.40m) 01 Días o o01.02 MOVILIZACION Y DESMOVILIZACION EQUIPOS 05 Días o01.03 CONTROL DE NIVELES TOPOGRÁFICOS 60 Días o o o o o o o o o o o o o o o o o o o o o o o o o o o o o01.04 GUARDIANÍA DE EQUIPOS 60 Días o o o o o o o o o o o o o o o o o o o o o o o o o o o o o02 MOVIMIENTO DE TIERRAS

02.01LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL ESTABLE

60 Días o o o o o o o o o o o o o o o o o o o o o o o o o o o o o02.02 LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL INESTABLE

51 Días o o o o o o o o o o o o o o o o o o o o o o o o o

EQUIPO MINIMO

ITEM EQUIPO MÍNIMO A DOBLE TURNO CANTIDAD 1 Retroexcavadora sobre oruga 170 - 250 HP 04 2 Camión plataforma 04

Page 8: 7 Metrados

CRONOGRAMA DE EJECUCION DE OBRA

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

Duración 2ª Mes

60

x

ooo

o

Page 9: 7 Metrados

OBRA:

ENTIDAD: PROYECTO ESPECIAL BINACIONAL PUYANGO TUMBES

CALENDARIO DE DESEMBOLSOS

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) QUINCENA 01 QUINCENA 02 QUINCENA 03 QUINCENA 04

01 OBRAS PRELIMINARES 398,896.58

01.01 CARTEL PARA OBRA (3.60m x 2.40m) und 1.00 1,392.62 1,392.62 1,392.62

01.02 MOVILIZACION Y DESMOVILIZACION EQUIPOS und 8.00 9,964.62 79,716.96 39,858.48 39,858.48

01.03 CONTROL DE NIVELES TOPOGRÁFICOS DIA 60.00 464.51 27,870.60 6,967.65 6,967.65 6,967.65 6,967.65

01.04 GUARDIANÍA DE EQUIPOS día 60.00 4,831.94 289,916.40 72,479.10 72,479.10 72,479.10 72,479.10

02 MOVIMIENTO DE TIERRAS 832,675.6402.01

m3 220,385.40 3.16 696,417.86 174,104.47 174,104.47 174,104.47 174,104.47

02.02m3 10,275.85 13.26 136,257.77 34,064.44 34,064.44 34,064.44 34,064.44

COSTO DIRECTO 1,231,572.21 328,866.76 287,615.66 287,615.66 327,474.14

GASTOS GENERALES 20% 246,314.44 65,773.35 57,523.13 57,523.13 65,494.83

SUB TOTAL 1,477,886.65 394,640.11 345,138.79 345,138.79 392,968.97

IGV 18% SOLO A MATERIALES Y EQUIPOS 124,758.23 31,189.56 31,189.56 31,189.56 31,189.56

TOTAL 1,602,644.88 425,829.67 376,328.35 376,328.35 424,158.52

100.00% 26.57% 23.48% 23.48% 26.47%

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL ESTABLE

LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL INESTABLE

Page 10: 7 Metrados

OBRA:

ENTIDAD: PROYECTO ESPECIAL BINACIONAL PUYANGO TUMBES

CRONOGRAMA VALORIZADO

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) QUINCENA 01 QUINCENA 02 QUINCENA 03 QUINCENA 04

01 OBRAS PRELIMINARES 398,896.5801.01 CARTEL PARA OBRA (3.60m x 2.40m) und 1.00 1,392.62 1,392.62 1,392.6201.02 MOVILIZACION Y DESMOVILIZACION EQUIPOS und 8.00 9,964.62 79,716.96 39,858.48 39,858.4801.03 CONTROL DE NIVELES TOPOGRÁFICOS DIA 60.00 464.51 27,870.60 6,967.65 6,967.65 6,967.65 6,967.6501.04 GUARDIANÍA DE EQUIPOS día 60.00 4,831.94 289,916.40 72,479.10 72,479.10 72,479.10 72,479.1002 MOVIMIENTO DE TIERRAS 832,675.64

02.01 m3 220,385.40 3.16 696,417.86 174,104.47 174,104.47 174,104.47 174,104.47

02.02 m3 10,275.85 13.26 136,257.77 34,064.44 34,064.44 34,064.44 34,064.44

COSTO DIRECTO 1,231,572.21 328,866.76 287,615.66 287,615.66 327,474.14GASTOS GENERALES 20% 246,314.44 65,773.35 57,523.13 57,523.13 65,494.83SUB TOTAL 1,477,886.65 394,640.11 345,138.79 345,138.79 392,968.97IGV 18% solo a materiales y equipos 124,758.23 31,189.56 31,189.56 31,189.56 31,189.56

TOTAL 1,602,644.88 425,829.67 376,328.35 376,328.35 424,158.52

100.00% 26.57% 23.48% 23.48% 26.47%

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL ESTABLE

LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL INESTABLE

Page 11: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

METRADOS

01 OBRAS PROVISIONALES

01.01 CARTEL DE IDENTIFICACIÓN DE OBRA (3.60m x 2.40m)

Unidad = 1.00 ===========

1.00 Unid

1.02 MOVILIZACION Y DESMOVILIZACION EQUIPOS

Unidad = 8.00 ===========

8.00 Unid

01.03 CONTROL DE NIVELES TOPOGRÁFICOS

N° DíasDias 1.00 x 60.000 = 60.00

===========60.00 Días

01.04 GUARDIANÍA DE EQUIPOS

N° DíasDias 1.00 x 60.000 = 60.00

===========60.00 Días

02.00 MOVIMIENTO DE TIERRAS

02.01 LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL ESTABLE

N° Vol.(m3) Vol.(m3)Dren Corrales 0+000 al 6+460.5 1 x 54186.627 = 54,186.63 Dren La Canela 0+000 al 1+487 1 x 24938.220 = 24,938.22 Dren El Piojo 0+000 al 5+850 1 x 141260.550 = 141,260.55

=========== 220,385.40 m3

02.02 LIMPIEZA Y DESCOLMATACIÓN CON RETROEXCAVADORA EN DRENES TRABAJANDO EN BERMA DE MATERIAL INESTABLE

N° Vol.(m3) Vol.(m3)Dren El Piojo 5+580 al 6+854 1 x 10275.848 = 10,275.85

=========== 10,275.85 m3

Page 12: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

PLANILLA DE MOVIMIENTO DE TIERRAS

DREN: CORRALES

AREAS PUNTUALES AREAS MEDIAS VOLUMENESPROG. DIST. CORTE RELLENO CORTE RELLENO CORTE RELLENO

0+000.000 2.712 3.4020+050.000 50.00 6.831 2.909 4.771 3.155 238.55 157.750+100.000 50.00 8.521 4.511 7.676 3.710 383.80 185.500+150.000 50.00 9.119 6.623 8.820 5.567 441.00 278.350+200.000 50.00 2.013 13.472 5.566 10.048 278.30 502.400+250.000 50.00 8.131 8.196 5.072 10.834 253.60 541.700+300.000 50.00 13.041 7.278 10.586 7.737 529.30 386.850+350.000 50.00 6.969 11.262 10.005 9.270 500.25 463.500+400.000 50.00 9.300 8.003 8.134 9.632 406.70 481.600+450.000 50.00 4.484 11.610 6.892 9.806 344.60 490.300+500.000 50.00 5.400 10.188 4.942 10.899 247.10 544.950+550.000 50.00 8.219 7.256 6.809 8.722 340.45 436.100+600.000 50.00 7.305 10.395 7.762 8.825 388.10 441.250+650.000 50.00 9.102 13.266 8.203 11.830 410.15 591.500+700.000 50.00 6.787 15.629 7.944 14.447 397.20 722.350+750.000 50.00 8.603 14.419 7.695 15.024 384.75 751.200+800.000 50.00 14.079 8.053 11.341 11.236 567.05 561.800+850.000 50.00 16.640 0.000 15.360 2.013 768.00 100.650+900.000 50.00 19.307 9.926 17.973 2.482 898.65 124.100+950.000 50.00 14.541 10.017 16.924 9.971 846.20 498.551+000.000 50.00 13.764 10.477 14.152 10.247 707.60 512.351+100.000 100.00 13.062 15.696 13.413 13.086 1,341.30 1,308.601+150.000 50.00 17.929 7.347 15.496 11.522 774.80 576.101+200.000 50.00 21.160 11.946 19.544 9.647 977.20 482.351+250.000 50.00 19.368 9.623 20.264 10.785 1,013.20 539.251+300.000 50.00 17.230 11.509 18.299 10.566 914.95 528.301+350.000 50.00 16.267 10.309 16.749 10.909 837.45 545.451+400.000 50.00 17.672 5.525 16.970 7.917 848.50 395.851+450.000 50.00 11.885 14.472 14.779 9.999 738.95 499.951+500.000 50.00 14.078 13.586 12.982 14.029 649.10 701.451+550.000 50.00 12.021 12.713 13.050 13.150 652.50 657.501+600.000 50.00 15.926 14.576 13.973 13.645 698.65 682.251+650.000 50.00 6.027 14.323 10.977 14.450 548.85 722.501+700.000 50.00 8.473 13.068 7.250 13.696 362.50 684.801+750.000 50.00 7.594 12.196 8.033 12.632 401.65 631.601+800.000 50.00 8.205 8.817 7.900 10.507 395.00 525.351+850.000 50.00 8.795 10.103 8.500 9.460 425.00 473.001+900.000 50.00 9.141 12.769 8.968 11.436 448.40 571.801+950.000 50.00 8.326 12.647 8.733 12.708 436.65 635.402+000.000 50.00 5.687 12.771 7.007 12.709 350.35 635.452+050.000 50.00 5.391 12.122 5.539 12.447 276.95 622.352+100.000 50.00 4.684 11.756 5.037 11.939 251.85 596.952+150.000 50.00 5.775 14.118 5.230 12.937 261.50 646.852+200.000 50.00 7.173 12.467 6.474 13.293 323.70 664.652+250.000 50.00 2.831 49.973 5.002 31.220 250.10 1,561.002+300.000 50.00 3.827 18.579 3.329 34.276 166.45 1,713.802+350.000 50.00 2.631 14.630 3.229 16.605 161.45 830.252+400.000 50.00 0.000 32.463 0.658 23.547 32.90 1,177.352+450.000 50.00 7.005 20.978 1.751 26.720 87.55 1,336.002+500.000 50.00 7.283 19.736 7.144 20.357 357.20 1,017.852+550.000 50.00 4.276 26.254 5.780 22.995 289.00 1,149.752+600.000 50.00 2.148 24.274 3.212 25.264 160.60 1,263.202+650.000 50.00 2.731 28.148 2.440 26.211 122.00 1,310.55

Page 13: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

DREN: CORRALES

AREAS PUNTUALES AREAS MEDIAS VOLUMENESPROG. DIST. CORTE RELLENO CORTE RELLENO CORTE RELLENO

2+700.000 50.00 2.873 27.678 2.802 27.913 140.10 1,395.652+750.000 50.00 1.841 27.856 2.357 27.767 117.85 1,388.352+800.000 50.00 2.034 31.627 1.938 29.742 96.90 1,487.102+850.000 50.00 1.267 32.383 1.651 32.005 82.55 1,600.252+900.000 50.00 8.907 26.817 5.087 29.600 254.35 1,480.002+950.000 50.00 5.733 22.773 7.320 24.795 366.00 1,239.753+000.000 50.00 5.256 26.568 5.494 24.670 274.70 1,233.503+050.000 50.00 7.820 25.452 6.538 26.010 326.90 1,300.503+100.000 50.00 9.676 24.941 8.748 25.196 437.40 1,259.803+150.000 50.00 1.904 28.418 5.790 26.680 289.50 1,334.003+200.000 50.00 7.022 28.361 4.463 28.390 223.15 1,419.503+250.000 50.00 4.791 22.627 5.906 25.494 295.30 1,274.703+300.000 50.00 9.663 20.710 7.227 21.668 361.35 1,083.403+350.000 50.00 8.815 21.379 9.239 21.044 461.95 1,052.203+400.000 50.00 7.835 19.538 8.325 20.458 416.25 1,022.903+450.000 50.00 7.949 18.785 7.892 19.161 394.60 958.053+500.000 50.00 7.949 21.133 7.949 19.959 397.45 997.953+550.000 50.00 6.484 21.499 7.216 21.316 360.80 1,065.803+600.000 50.00 5.297 21.942 5.890 21.720 294.50 1,086.003+650.000 50.00 2.943 21.787 4.120 21.864 206.00 1,093.203+700.000 50.00 5.384 22.357 4.164 22.072 208.20 1,103.603+750.000 50.00 10.580 19.305 7.982 20.831 399.10 1,041.553+800.000 50.00 6.794 21.529 8.687 20.417 434.35 1,020.853+850.000 50.00 3.080 22.818 4.937 22.173 246.85 1,108.653+900.000 50.00 3.090 19.185 3.085 21.001 154.25 1,050.053+950.000 50.00 2.534 22.297 2.812 20.741 140.60 1,037.054+000.000 50.00 4.194 19.013 3.364 20.655 168.20 1,032.754+050.000 50.00 6.327 26.071 5.260 22.542 263.00 1,127.104+100.000 50.00 7.663 20.675 6.995 23.373 349.75 1,168.654+150.000 50.00 6.208 17.947 6.935 19.311 346.75 965.554+200.000 50.00 6.326 21.626 6.267 19.786 313.35 989.304+250.000 50.00 11.298 20.078 8.812 20.852 440.60 1,042.604+300.000 50.00 6.706 18.671 9.002 19.374 450.10 968.704+350.000 50.00 7.002 19.755 6.854 19.213 342.70 960.654+400.000 50.00 8.721 15.673 7.861 17.714 393.05 885.704+450.000 50.00 9.234 16.975 8.978 16.324 448.90 816.204+500.000 50.00 8.311 19.916 8.773 18.446 438.65 922.304+550.000 50.00 9.982 20.037 9.146 19.977 457.30 998.854+600.000 50.00 10.915 22.758 10.449 21.397 522.45 1,069.854+650.000 50.00 8.510 21.122 9.713 21.940 485.65 1,097.004+700.000 50.00 12.397 20.334 10.454 20.728 522.70 1,036.404+750.000 50.00 9.500 23.920 10.949 22.127 547.45 1,106.354+800.000 50.00 10.275 21.638 9.888 22.779 494.40 1,138.954+850.000 50.00 13.739 18.202 12.007 19.920 600.35 996.004+900.000 50.00 12.336 19.422 13.038 18.812 651.90 940.604+950.000 50.00 12.327 18.776 12.331 19.099 616.55 954.955+000.000 50.00 8.994 23.943 10.660 21.359 533.00 1,067.955+050.000 50.00 7.425 21.300 8.209 22.622 410.45 1,131.105+100.000 50.00 5.315 24.612 6.370 22.956 318.50 1,147.805+150.000 50.00 6.086 25.422 5.701 25.017 285.05 1,250.855+200.000 50.00 9.168 23.196 7.627 24.309 381.35 1,215.455+250.000 50.00 7.303 23.773 8.235 23.484 411.75 1,174.205+300.000 50.00 9.440 25.376 8.371 24.574 418.55 1,228.705+350.000 50.00 4.689 17.820 7.065 21.598 353.25 1,079.905+400.000 50.00 8.320 12.544 6.505 15.182 325.25 759.105+450.000 50.00 8.171 16.039 8.246 14.292 412.30 714.60

Page 14: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

DREN: CORRALES

AREAS PUNTUALES AREAS MEDIAS VOLUMENESPROG. DIST. CORTE RELLENO CORTE RELLENO CORTE RELLENO

5+500.000 50.00 5.139 17.535 6.655 16.787 332.75 839.355+550.000 50.00 8.178 11.775 6.658 14.655 332.90 732.755+600.000 50.00 9.003 10.339 8.590 11.057 429.50 552.855+650.000 50.00 9.925 12.591 9.464 11.465 473.20 573.255+700.000 50.00 12.646 11.265 11.286 11.928 564.30 596.405+750.000 50.00 10.332 6.201 11.489 8.733 574.45 436.655+800.000 50.00 2.535 39.424 6.433 22.813 321.65 1,140.655+850.000 50.00 9.762 23.610 6.148 31.517 307.40 1,575.855+900.000 50.00 10.061 25.543 9.912 24.576 495.60 1,228.805+950.000 50.00 4.562 35.327 7.312 30.435 365.60 1,521.756+000.000 50.00 6.078 28.710 5.320 32.018 266.00 1,600.906+050.000 50.00 4.813 13.387 5.445 21.048 272.25 1,052.406+100.000 50.00 7.100 25.284 5.956 19.335 297.80 966.756+150.000 50.00 7.431 14.553 7.266 19.918 363.30 995.906+200.000 50.00 20.253 10.371 13.842 12.462 692.10 623.106+250.000 50.00 19.197 9.799 19.725 10.085 986.25 504.256+300.000 50.00 7.235 9.574 13.216 9.686 660.80 484.306+350.000 50.00 5.708 15.550 6.472 12.562 323.60 628.106+400.000 50.00 7.442 6.074 6.575 10.812 328.75 540.606+450.000 50.00 18.495 11.892 12.968 8.983 648.40 449.156+460.500 10.50 15.454 44.957 16.974 28.424 178.23 298.45

TOTAL 54,186.63 113,924.90

Page 15: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

PLANILLA DE MOVIMIENTO DE TIERRASDREN: CANELA

AREAS PUNTUALES AREAS MEDIAS VOLUMENESPROG. DIST. CORTE RELLENO CORTE RELLENO CORTE RELLENO

0+000.000 0.017 6.1147

0+010.000 10.00 14.4980 6.3799 7.257 6.247 72.57 62.470+020.000 10.00 24.1108 19.4327 19.304 12.906 193.04 129.060+030.000 10.00 24.4400 24.275 9.716 242.75 97.160+040.000 10.00 30.5716 9.1733 27.506 4.587 275.06 45.870+041.800 1.80 9.0559 24.5259 19.814 16.850 35.66 30.330+051.800 10.00 15.0888 19.4595 12.072 21.993 120.72 219.930+061.800 10.00 7.7657 13.8123 11.427 16.636 114.27 166.360+080.500 18.70 5.7174 8.0231 6.742 10.918 126.07 204.16

TOTAL 1,180.16 955.34

PLANILLA DE MOVIMIENTO DE TIERRASDREN: CANELA

AREAS PUNTUALES AREAS MEDIAS VOLUMENESPROG. DIST. CORTE RELLENO CORTE RELLENO CORTE RELLENO

TOTAL

Page 16: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

7.257 6.247

19.304

Page 17: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

PLANILLA DE MOVIMIENTO DE TIERRASDREN: EL PIOJO (0+000 - 5+850)

AREAS PUNTUALES AREAS MEDIAS VOLUMENESPROG. DIST. CORTE RELLENO CORTE RELLENO CORTE RELLENO

0+000.000 1.419 18.1780+050.000 50.00 3.527 30.261 2.473 24.220 123.65 1,211.000+100.000 50.00 2.100 31.942 2.813 31.102 140.65 1,555.100+150.000 50.00 5.784 17.465 3.942 24.703 197.10 1,235.150+200.000 50.00 4.365 18.902 5.075 18.183 253.75 909.150+250.000 50.00 6.622 30.783 5.493 24.843 274.65 1,242.150+300.000 50.00 7.122 25.945 6.872 28.364 343.60 1,418.200+350.000 50.00 6.822 7.002 6.972 16.474 348.60 823.700+400.000 50.00 0.000 35.032 3.411 21.017 170.55 1,050.850+450.000 50.00 4.720 21.885 2.360 28.459 118.00 1,422.950+500.000 50.00 10.214 10.466 7.467 16.176 373.35 808.800+550.000 50.00 4.795 12.333 7.505 11.399 375.25 569.950+600.000 50.00 5.253 4.408 5.024 8.370 251.20 418.500+650.000 50.00 2.959 16.185 4.106 10.296 205.30 514.800+700.000 50.00 6.525 13.156 4.742 14.670 237.10 733.500+750.000 50.00 9.711 17.141 8.118 15.148 405.90 757.400+800.000 50.00 7.044 2.006 8.377 9.573 418.85 478.650+850.000 50.00 9.485 11.971 8.264 6.988 413.20 349.400+900.000 50.00 8.355 3.255 8.920 7.613 446.00 380.650+950.000 50.00 10.665 14.872 9.510 9.064 475.50 453.201+000.000 50.00 13.337 5.777 12.001 10.325 600.05 516.251+050.000 50.00 9.300 7.088 11.319 6.433 565.95 321.651+100.000 50.00 29.156 35.666 19.228 21.377 961.40 1,068.851+150.000 50.00 17.053 0.135 23.104 17.900 1,155.20 895.001+200.000 50.00 16.405 3.112 16.729 1.623 836.45 81.151+250.000 50.00 12.733 3.739 14.569 3.425 728.45 171.251+300.000 50.00 8.565 2.255 10.649 2.997 532.45 149.851+350.000 50.00 11.710 5.550 10.137 3.903 506.85 195.151+400.000 50.00 9.742 11.557 10.726 8.553 536.30 427.651+450.000 50.00 15.597 6.510 12.669 9.033 633.45 451.651+500.000 50.00 11.716 12.081 13.657 9.296 682.85 464.801+550.000 50.00 23.480 2.459 17.598 7.270 879.90 363.501+600.000 50.00 15.406 5.393 19.443 3.926 972.15 196.301+650.000 50.00 3.415 12.856 9.410 9.124 470.50 456.201+700.000 50.00 10.051 4.450 6.733 8.653 336.65 432.651+750.000 50.00 15.228 5.797 12.639 5.124 631.95 256.201+800.000 50.00 11.183 4.010 13.206 4.903 660.30 245.151+850.000 50.00 16.609 10.789 13.896 7.399 694.80 369.951+900.000 50.00 5.339 11.366 10.974 11.077 548.70 553.851+950.000 50.00 0.776 26.628 3.058 18.997 152.90 949.852+000.000 50.00 22.279 5.488 11.528 16.058 576.40 802.902+050.000 50.00 22.225 8.862 22.252 7.175 1,112.60 358.752+100.000 50.00 12.662 6.601 17.443 7.731 872.15 386.552+150.000 50.00 10.893 8.065 11.777 7.333 588.85 366.652+200.000 50.00 25.456 2.639 18.174 5.352 908.70 267.602+250.000 50.00 19.871 2.270 22.663 2.455 1,133.15 122.752+300.000 50.00 12.728 0.598 16.299 1.434 814.95 71.702+350.000 50.00 11.541 6.249 12.134 3.423 606.70 171.152+400.000 50.00 21.910 0.054 16.725 3.152 836.25 157.602+450.000 50.00 18.761 5.503 20.335 2.779 1,016.75 138.952+500.000 50.00 15.381 0.767 17.071 3.135 853.55 156.752+550.000 50.00 34.090 0.769 24.735 0.768 1,236.75 38.402+600.000 50.00 49.926 0.324 42.008 0.546 2,100.40 27.302+650.000 50.00 29.093 4.893 39.509 2.609 1,975.45 130.452+700.000 50.00 22.559 12.927 25.826 8.910 1,291.30 445.502+750.000 50.00 9.839 10.349 16.199 11.638 809.95 581.902+800.000 50.00 21.648 8.712 15.743 9.531 787.15 476.552+850.000 50.00 21.933 10.851 21.790 9.782 1,089.50 489.10

Page 18: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

DREN: EL PIOJO (0+000 - 5+850)AREAS PUNTUALES AREAS MEDIAS VOLUMENES

PROG. DIST. CORTE RELLENO CORTE RELLENO CORTE RELLENO2+900.000 50.00 27.300 9.703 24.616 10.277 1,230.80 513.852+950.000 50.00 29.976 9.485 28.638 9.594 1,431.90 479.703+000.000 50.00 36.020 6.234 32.998 7.859 1,649.90 392.953+050.000 50.00 18.081 1.477 27.051 3.856 1,352.55 192.803+100.000 50.00 37.094 2.634 27.588 2.056 1,379.40 102.803+150.000 50.00 45.544 0.000 41.319 0.659 2,065.95 32.953+200.000 50.00 24.944 0.839 35.244 0.210 1,762.20 10.503+250.000 50.00 26.746 1.809 25.845 1.324 1,292.25 66.203+300.000 50.00 38.740 1.773 32.743 1.791 1,637.15 89.553+350.000 50.00 38.502 5.088 38.621 3.431 1,931.05 171.553+400.000 50.00 52.997 0.000 45.750 1.272 2,287.50 63.603+450.000 50.00 57.072 0.000 55.034 0.000 2,751.70 0.003+500.000 50.00 46.590 0.039 51.831 0.010 2,591.55 0.503+550.000 50.00 54.011 2.478 50.300 1.258 2,515.00 62.903+600.000 50.00 42.429 2.121 48.220 2.300 2,411.00 115.003+650.000 50.00 59.527 1.691 50.978 1.906 2,548.90 95.303+700.000 50.00 42.601 8.384 51.064 5.038 2,553.20 251.903+750.000 50.00 5.060 16.831 23.831 12.608 1,191.55 630.403+800.000 50.00 68.390 0.990 36.725 8.910 1,836.25 445.503+850.000 50.00 45.072 0.000 56.731 0.247 2,836.55 12.353+900.000 50.00 49.336 0.451 47.204 0.113 2,360.20 5.653+950.000 50.00 57.269 0.000 53.303 0.113 2,665.15 5.654+000.000 50.00 55.436 0.340 56.353 0.085 2,817.65 4.254+050.000 50.00 62.231 0.000 58.833 0.085 2,941.65 4.254+100.000 50.00 54.742 0.102 58.486 0.026 2,924.30 1.304+150.000 50.00 56.330 0.766 55.536 0.434 2,776.80 21.704+200.000 50.00 58.004 0.000 57.167 0.191 2,858.35 9.554+250.000 50.00 55.769 0.236 56.887 0.059 2,844.35 2.954+300.000 50.00 42.722 0.491 49.245 0.363 2,462.25 18.154+350.000 50.00 29.912 0.211 36.317 0.351 1,815.85 17.554+400.000 50.00 42.974 1.490 36.443 0.850 1,822.15 42.504+450.000 50.00 49.068 0.826 46.021 1.158 2,301.05 57.904+500.000 50.00 34.341 1.885 41.704 1.355 2,085.20 67.754+550.000 50.00 16.542 5.511 25.441 3.698 1,272.05 184.904+600.000 50.00 32.129 4.662 24.335 5.087 1,216.75 254.354+650.000 50.00 0.000 75.699 8.032 40.180 401.60 2,009.004+700.000 50.00 1.614 32.801 0.403 54.250 20.15 2,712.504+750.000 50.00 9.513 18.232 5.563 25.516 278.15 1,275.804+800.000 50.00 16.310 17.353 12.912 17.792 645.60 889.604+850.000 50.00 32.664 5.212 24.487 11.283 1,224.35 564.154+900.000 50.00 15.018 13.199 23.841 9.206 1,192.05 460.304+950.000 50.00 32.472 3.981 23.745 8.590 1,187.25 429.505+000.000 50.00 27.801 4.162 30.137 4.072 1,506.85 203.605+050.000 50.00 20.720 10.778 24.261 7.470 1,213.05 373.505+100.000 50.00 21.869 17.948 21.295 14.363 1,064.75 718.155+150.000 50.00 20.192 21.235 21.031 19.592 1,051.55 979.605+200.000 50.00 26.050 14.064 23.121 17.650 1,156.05 882.505+250.000 50.00 28.708 8.333 27.379 11.199 1,368.95 559.955+300.000 50.00 30.369 15.990 29.538 12.162 1,476.90 608.105+350.000 50.00 30.937 19.364 30.653 17.677 1,532.65 883.855+400.000 50.00 26.313 17.886 28.625 18.625 1,431.25 931.255+450.000 50.00 33.684 11.910 29.999 14.898 1,499.95 744.905+500.000 50.00 44.181 16.479 38.933 14.194 1,946.65 709.705+550.000 50.00 41.240 11.057 42.710 13.768 2,135.50 688.405+600.000 50.00 24.588 23.579 32.914 17.318 1,645.70 865.905+650.000 50.00 23.683 24.539 24.136 24.059 1,206.80 1,202.955+700.000 50.00 20.149 26.186 21.916 25.362 1,095.80 1,268.105+750.000 50.00 20.469 31.070 20.309 28.628 1,015.45 1,431.405+800.000 50.00 22.965 30.462 21.717 30.766 1,085.85 1,538.305+850.000 50.00 24.538 26.745 23.752 28.604 1,187.60 1,430.20

Page 19: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

DREN: EL PIOJO (0+000 - 5+850)AREAS PUNTUALES AREAS MEDIAS VOLUMENES

PROG. DIST. CORTE RELLENO CORTE RELLENO CORTE RELLENOTOTAL 141,260.55 58,880.45

Page 20: 7 Metrados

EXPEDIENTE TECNICO: DESCOLMATACIÓN DE LOS DRENES CORRALES, LA CANELA Y EL PIOJO – MARGEN IZQUIERDA DEL RÍO TUMBES, DISTRITO DE CORRALES, PROVINCIA Y DEPARTAMENTO DE TUMBES

PLANILLA DE MOVIMIENTO DE TIERRASDREN: EL PIOJO (5+850 - 5+854)

AREAS PUNTUALES AREAS MEDIAS VOLUMENESPROG. DIST. CORTE RELLENO CORTE RELLENO CORTE RELLENO

5+850.000 24.538 26.7455+900.000 50.00 24.332 24.165 24.435 25.455 1,221.75 1,272.755+950.000 50.00 21.571 31.585 22.951 27.875 1,147.55 1,393.756+000.000 50.00 19.765 26.471 20.668 29.028 1,033.40 1,451.406+050.000 50.00 15.101 48.416 17.433 37.443 871.65 1,872.156+100.000 50.00 4.845 81.842 9.973 65.129 498.65 3,256.456+150.000 50.00 0.394 42.713 2.620 62.278 131.00 3,113.906+200.000 50.00 1.613 44.457 1.004 43.585 50.20 2,179.256+250.000 50.00 0.000 75.033 0.403 59.745 20.15 2,987.256+300.000 50.00 10.598 27.515 2.650 51.274 132.50 2,563.706+350.000 50.00 22.881 21.853 16.740 24.684 837.00 1,234.206+400.000 50.00 0.716 43.755 11.799 32.804 589.95 1,640.206+450.000 50.00 0.000 56.803 0.179 50.279 8.95 2,513.956+500.000 50.00 11.542 35.584 2.885 46.193 144.25 2,309.656+550.000 50.00 0.000 87.998 2.885 61.791 144.25 3,089.556+600.000 50.00 0.552 77.709 0.138 82.853 6.90 4,142.656+650.000 50.00 0.401 109.011 0.477 93.360 23.85 4,668.006+700.000 50.00 5.315 68.303 2.858 88.657 142.90 4,432.856+750.000 50.00 7.398 58.465 6.357 63.384 317.85 3,169.206+800.000 50.00 4.251 104.381 5.825 81.423 291.25 4,071.156+847.000 47.00 89.213 4.502 46.732 54.441 2,196.40 2,558.736+854.000 7.00 43.771 4.348 66.492 4.425 465.44 30.97

TOTAL 10,275.85 53,951.70