OFICINAS PISO 1 W/m2 Pot AREA TECHADA 841.6 m2 50 42,080 PISO 2 W/m2 Pot AREA TECHADA 782.4 m2 50 39,120 OFICINA 2 W/m2 Pot AREA TECHADA 126.854 m2 50 6,343 COMEDOR W/m2 Pot AREA TECHADA 324.57 m2 30 9,737 EXTERIOR W/m2 Pot AREA 2714.1117 m2 10 27,141 CARGAS Pot BOMBA DE AGUA 1hp 1492 LAVADORA (X2) 1200 SECADORA D ROPA 4000 CALEFACCION(X6) 4000 24000 10000 14000 ALIMENTADOR FASES N2XOH 0.6/1 kV 3-1x95mm2 (R-B-N) NEUTRO N2XOH 0.6/1 Kv 1x50mm2 AMARILLO

description

calculo bisa

Transcript of Calculo ver01

Page 1: Calculo ver01

OFICINASPISO 1

W/m2 Pot F.D.AREA TECHADA 841.6 m2 50 42,080 1

PISO 2W/m2 Pot F.D.

AREA TECHADA 782.4 m2 50 39,120 1

OFICINA 2

W/m2 Pot F.D.AREA TECHADA 126.854 m2 50 6,343 1

COMEDOR

W/m2 Pot F.D.AREA TECHADA 324.57 m2 30 9,737 1

EXTERIOR

W/m2 Pot F.D.AREA 2714.1117 m2 10 27,141 1

CARGAS Pot F.D.BOMBA DE AGUA 1hp 1492 1LAVADORA (X2) 1200 1SECADORA D ROPA 4000 1CALEFACCION(X6) 4000 24000

10000 114000 0.75

total

In

Id

AIREALIMENTADOR FASES N2XOH 0.6/1 kV 3-1x95mm2 (R-B-N) 375

NEUTRO N2XOH 0.6/1 Kv 1x50mm2 AMARILLO 240

TRANSFORMADOR TRIFASICO 200KVA 10/0.40-0.23 KV

Page 2: Calculo ver01

M.D.42,080

M.D.39,120

M.D.6,343

M.D.9,737

M.D.27,141

M.D.1,4921,2004,000

10,00010,500

151,613 w fdp 0.8

230.35 A VA 189,516

287.94 A Selecc. 200,000 VA

DUCTO330 A230 A

ver tabla indeco