CRONO.xls

4
CRONOGRAMA VALORIZADO PROYECTO: “MEJORAMIENTO DEL PASAJE ANCASH, DE LA LOCALIDAD DE PARIAHUANCA, PROVINCIA DE CARHUAZ, ANCASH LOCALIDAD PARIAHUANCA DISTRITO PARIAHUANCA PROVINCIA CARHUAZ REGION ANCASH FECHA JUNIO 2014 Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) SEMANA1 SEMANA2 SEMANA3 SEMANA4 SEMANA5 SEMANA6 SEMANA7 SEMANA8 01 OBRAS PROVISIONALES S/. 4,699.90 01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40M X 3.60M. und 1.00 2,128.15 S/. 2,128.15 ### 01.02 ALAMCEN Y OFICINA m2 25.00 102.87 S/. 2,571.75 ### 02 PAVIMENTO S/. 75,499.68 02.01 OBRAS PRELIMINARES S/. 3,488.10 02.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIENTAS GLB 1.00 3,000.00 S/. 3,000.00 ### 02.01.02 TRAZO, NIVELACION Y REPLANTEO KM 0.10 3,096.34 S/. 309.63 S/. 309.63 02.01.03 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA KM 1.00 178.47 S/. 178.47 S/. 178.47 02.02 MOVIMIENTO DE TIERRAS S/. 38,799.22 02.02.01 CORTE HASTA EL NIVEL DE SUBRASANTE CON MAQUINARIA m3 123.20 3.54 S/. 436.13 S/. 436.13 02.02.02 COMPACTADO SUBRASANTE EN ZONA DE CORTE m2 363.00 7.29 S/. 2,646.27 ### 02.02.03 SUB - BASE AFIRMADO DE 0.15 M. FACTOR DE COMPACTACION 1.2 m2 363.00 80.58 S/. 29,250.54 ### ### 02.02.04 BASE GRANULAR E=0.20 M REND.=2310 M2/DIA FACT. COMPACT.=1.20 m2 122.40 31.41 S/. 3,844.58 ### 02.02.05 ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO D=4KM m3 135.00 19.42 S/. 2,621.70 ### 02.03 OBRAS DE CONCRETO S/. 29,382.08 02.03.01 ENCOFRADO DE PAVIMENTO RIGIDO m2 61.20 52.07 S/. 3,186.68 ### 02.03.02 CONCRETO F'C=210 KG/CM2. EN PAVIMENTO RIGIDO m3 56.70 441.67 S/. 25,042.69 ### ### 02.03.03 CURADO EN PAVIMENTO RIGIDO m3 56.70 20.33 S/. 1,152.71 ### 02.04 JUNTAS DE DILATACION S/. 3,241.33 02.04.01 JUNTAS DE CONTRACCION, e=2.0 cm m 396.25 8.18 S/. 3,241.33 ### 02.05 SEÑALIZACION S/. 588.95 02.05.01 SEÑALIZACION CON CINTAS DE SEGURIDAD m2 10.20 57.74 S/. 588.95 S/. 588.95 03 VEREDAS DE CONCRETO S/. 7,557.65 03.01 OBRAS PRELIMINARES S/. 619.27 03.01.01 TRAZO, NIVELACION Y REPLANTEO KM 0.20 3,096.34 S/. 619.27 S/. 619.27 03.02 MOVIMIENTO DE TIERRAS S/. 1,188.05 03.02.01 CORTE SUPERFICIAL MANUAL HASTA 0.20 MT m3 15.27 5.28 S/. 80.63 S/. 80.63 03.02.02 NIVELACION Y COMPACTACION DE SUBRASANTE CON EQUIPO LIVIANO m2 50.90 7.29 S/. 371.06 S/. 371.06 03.02.03 RELLENO CON MATERIAL GRANULAR COMPACTADO m3 15.27 25.89 S/. 395.34 S/. 395.34 03.02.04 ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO D=4KM m3 17.56 19.42 S/. 341.02 S/. 341.02 03.03 OBRAS DE CONCRETO S/. 5,142.17 03.03.01 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 30.54 23.71 S/. 724.10 S/. 724.10 03.03.02 CONCRETO F'C=140 KG/CM2 m3 15.27 289.33 S/. 4,418.07 ### 03.04 JUNTAS DE DILATACION S/. 608.16 03.04.01 JUNTAS ASFALTICAS m 120.81 4.22 S/. 509.82 03.04.02 PINTURA CON ESMALTE EN EXTERIOR m2 30.54 3.22 S/. 98.34 04 MURO DE CONTENCION S/. 218,917.44 04.01 TRAZO, NIVELACION Y REPLANTEO KM 0.06 3,096.34 S/. 185.78 S/. 185.78 04.02 EXCAVACION PARA ESTRUCTURAS m3 471.41 9.02 S/. 4,252.12 ### 04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 512.40 23.71 S/. 12,149.00 ### ### ### 04.04 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 15,526.69 4.35 S/. 67,541.10 ### ### 04.05 JUNTAS ASFALTICAS m 132.17 4.22 S/. 557.76 S/. 557.76 04.06 CONCRETO F'C=210 KG/CM2, m3 204.96 453.04 S/. 92,855.08 ### ### ### ### 04.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS S/. 16,199.32 04.07.01 TRAZO, NIVELACION Y REPLANTEO KM 0.11 3,096.34 S/. 340.60 S/. 340.60 04.07.02 EXCAVACION MANUAL DE ZANJAS 0.40 X 1.20 m3 52.80 3.86 S/. 203.81 S/. 203.81 04.07.03 REFINE Y NIVELACION EN TERRENO NORMAL m2 44.00 1.79 S/. 78.76 S/. 78.76 04.07.04 CAMA DE APOYO DE ARENA e=0.15 M m3 6.60 159.14 S/. 1,050.32 ### 04.07.05 DOBLE PRUEBA HIDRAULICA m3 52.80 0.69 S/. 36.43 S/. 36.43 04.07.06 RELLENO Y COMPACTADO CON MATERIAL SELECCIONADO m3 52.80 24.05 S/. 1,269.84 ### 04.07.07 SUMINISTRO E INSTALACION DE TUBERIA P.V.C. C10 D= 2" m 110.00 88.59 S/. 9,744.90 ### ### ### 04.07.08 TUBERIA DE PVC A-10 SP D=1/2" INC.ELEM.UNION+2% DESPER m 50.00 3.12 S/. 156.00 S/. 156.00 04.07.09 CONEXIONES DOMICILIARIAS DE AGUA pza 18.00 184.37 S/. 3,318.66 ### ### 04.08 CANAL DE CONCRETO S/. 25,177.28 04.08.01 EXCAVACION MANUAL DE ZANJAS m3 50.22 3.86 S/. 193.85 S/. 193.85 04.08.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 54.00 1.79 S/. 96.66 S/. 96.66 04.08.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 216.00 23.71 S/. 5,121.36 ### ### 04.08.04 CONCRETO f'c=175 kg/cm2 m3 17.10 359.98 S/. 6,155.66 ### ### 04.08.05 CONCRETO F'C=210 KG/CM2, m3 10.80 453.04 S/. 4,892.83 ### ### 04.08.06 JUNTAS DE CONTRACCION, e=2.0 cm m 17.00 8.18 S/. 139.06 S/. 139.06 04.08.07 JUNTAS DE DILATACION, e=2.0 cm m 27.20 15.78 S/. 429.22 S/. 429.22 04.08.08 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,873.25 4.35 S/. 8,148.64 ### ### 05 CONTROL DE CALIDAD DEL CONCRETO S/. 1,050.04 05.01 DISEÑO DE MEZCLAS und 2.00 305.00 S/. 610.00 S/. 610.00 05.02 ENSAYOS DE DENSIDAD DE CAMPO und 2.00 36.67 S/. 73.34 S/. 73.34 05.03 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 10.00 36.67 S/. 366.70 S/. 183.35 S/. 183.35

Transcript of CRONO.xls

Page 1: CRONO.xls

CRONOGRAMA VALORIZADOPROYECTO:

“MEJORAMIENTO DEL PASAJE ANCASH, DE LA LOCALIDAD DE PARIAHUANCA, PROVINCIA DE CARHUAZ, ANCASH

LOCALIDAD PARIAHUANCADISTRITO PARIAHUANCAPROVINCIA CARHUAZREGION ANCASH FECHA JUNIO 2014

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) SEMANA1 SEMANA2 SEMANA3 SEMANA4 SEMANA5 SEMANA6 SEMANA7 SEMANA801 OBRAS PROVISIONALES S/. 4,699.90

01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40M X 3.60M. und 1.00 2,128.15 S/. 2,128.15 S/. 2,128.15

01.02 ALAMCEN Y OFICINA m2 25.00 102.87 S/. 2,571.75 S/. 2,571.75

02 PAVIMENTO S/. 75,499.68

02.01 OBRAS PRELIMINARES S/. 3,488.10

02.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIENTAS GLB 1.00 3,000.00 S/. 3,000.00 S/. 3,000.00

02.01.02 TRAZO, NIVELACION Y REPLANTEO KM 0.10 3,096.34 S/. 309.63 S/. 309.63

02.01.03 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA KM 1.00 178.47 S/. 178.47 S/. 178.47

02.02 MOVIMIENTO DE TIERRAS S/. 38,799.22

02.02.01 CORTE HASTA EL NIVEL DE SUBRASANTE CON MAQUINARIA m3 123.20 3.54 S/. 436.13 S/. 436.13

02.02.02 COMPACTADO SUBRASANTE EN ZONA DE CORTE m2 363.00 7.29 S/. 2,646.27 S/. 2,646.27

02.02.03 SUB - BASE AFIRMADO DE 0.15 M. FACTOR DE COMPACTACION 1.2 m2 363.00 80.58 S/. 29,250.54 S/. 14,625.27 S/. 14,625.27

02.02.04 BASE GRANULAR E=0.20 M REND.=2310 M2/DIA FACT. COMPACT.=1.20 m2 122.40 31.41 S/. 3,844.58 S/. 3,844.58

02.02.05 ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO D=4KM m3 135.00 19.42 S/. 2,621.70 S/. 2,621.70

02.03 OBRAS DE CONCRETO S/. 29,382.08

02.03.01 ENCOFRADO DE PAVIMENTO RIGIDO m2 61.20 52.07 S/. 3,186.68 S/. 3,186.68

02.03.02 CONCRETO F'C=210 KG/CM2. EN PAVIMENTO RIGIDO m3 56.70 441.67 S/. 25,042.69 S/. 12,521.35 S/. 12,521.35

02.03.03 CURADO EN PAVIMENTO RIGIDO m3 56.70 20.33 S/. 1,152.71 S/. 1,152.71

02.04 JUNTAS DE DILATACION S/. 3,241.33

02.04.01 JUNTAS DE CONTRACCION, e=2.0 cm m 396.25 8.18 S/. 3,241.33 S/. 3,241.33

02.05 SEÑALIZACION S/. 588.95

02.05.01 SEÑALIZACION CON CINTAS DE SEGURIDAD m2 10.20 57.74 S/. 588.95 S/. 588.95

03 VEREDAS DE CONCRETO S/. 7,557.65

03.01 OBRAS PRELIMINARES S/. 619.27

03.01.01 TRAZO, NIVELACION Y REPLANTEO KM 0.20 3,096.34 S/. 619.27 S/. 619.27

03.02 MOVIMIENTO DE TIERRAS S/. 1,188.05

03.02.01 CORTE SUPERFICIAL MANUAL HASTA 0.20 MT m3 15.27 5.28 S/. 80.63 S/. 80.63

03.02.02 NIVELACION Y COMPACTACION DE SUBRASANTE CON EQUIPO LIVIANO m2 50.90 7.29 S/. 371.06 S/. 371.06

03.02.03 RELLENO CON MATERIAL GRANULAR COMPACTADO m3 15.27 25.89 S/. 395.34 S/. 395.34

03.02.04 ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO D=4KM m3 17.56 19.42 S/. 341.02 S/. 341.02

03.03 OBRAS DE CONCRETO S/. 5,142.17

03.03.01 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 30.54 23.71 S/. 724.10 S/. 724.10

03.03.02 CONCRETO F'C=140 KG/CM2 m3 15.27 289.33 S/. 4,418.07 S/. 4,418.07

03.04 JUNTAS DE DILATACION S/. 608.16

03.04.01 JUNTAS ASFALTICAS m 120.81 4.22 S/. 509.82

03.04.02 PINTURA CON ESMALTE EN EXTERIOR m2 30.54 3.22 S/. 98.34

04 MURO DE CONTENCION S/. 218,917.44

04.01 TRAZO, NIVELACION Y REPLANTEO KM 0.06 3,096.34 S/. 185.78 S/. 185.78

04.02 EXCAVACION PARA ESTRUCTURAS m3 471.41 9.02 S/. 4,252.12 S/. 4,252.12

04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 512.40 23.71 S/. 12,149.00 S/. 4,049.67 S/. 4,049.67 S/. 4,049.67

04.04 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 15,526.69 4.35 S/. 67,541.10 S/. 33,770.55 S/. 33,770.55

04.05 JUNTAS ASFALTICAS m 132.17 4.22 S/. 557.76 S/. 557.76

04.06 CONCRETO F'C=210 KG/CM2, m3 204.96 453.04 S/. 92,855.08 S/. 23,213.77 S/. 23,213.77 S/. 23,213.77 S/. 23,213.77

04.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS S/. 16,199.32

04.07.01 TRAZO, NIVELACION Y REPLANTEO KM 0.11 3,096.34 S/. 340.60 S/. 340.60

04.07.02 EXCAVACION MANUAL DE ZANJAS 0.40 X 1.20 m3 52.80 3.86 S/. 203.81 S/. 203.81

04.07.03 REFINE Y NIVELACION EN TERRENO NORMAL m2 44.00 1.79 S/. 78.76 S/. 78.76

04.07.04 CAMA DE APOYO DE ARENA e=0.15 M m3 6.60 159.14 S/. 1,050.32 S/. 1,050.32

04.07.05 DOBLE PRUEBA HIDRAULICA m3 52.80 0.69 S/. 36.43 S/. 36.43

04.07.06 RELLENO Y COMPACTADO CON MATERIAL SELECCIONADO m3 52.80 24.05 S/. 1,269.84 S/. 1,269.84

04.07.07 SUMINISTRO E INSTALACION DE TUBERIA P.V.C. C10 D= 2" m 110.00 88.59 S/. 9,744.90 S/. 3,248.30 S/. 3,248.30 S/. 3,248.30

04.07.08 TUBERIA DE PVC A-10 SP D=1/2" INC.ELEM.UNION+2% DESPER m 50.00 3.12 S/. 156.00 S/. 156.00

04.07.09 CONEXIONES DOMICILIARIAS DE AGUA pza 18.00 184.37 S/. 3,318.66 S/. 1,659.33 S/. 1,659.33

04.08 CANAL DE CONCRETO S/. 25,177.28

04.08.01 EXCAVACION MANUAL DE ZANJAS m3 50.22 3.86 S/. 193.85 S/. 193.85

04.08.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 54.00 1.79 S/. 96.66 S/. 96.66

04.08.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 216.00 23.71 S/. 5,121.36 S/. 2,560.68 S/. 2,560.68

04.08.04 CONCRETO f'c=175 kg/cm2 m3 17.10 359.98 S/. 6,155.66 S/. 3,077.83 S/. 3,077.83

04.08.05 CONCRETO F'C=210 KG/CM2, m3 10.80 453.04 S/. 4,892.83 S/. 2,446.42 S/. 2,446.42

04.08.06 JUNTAS DE CONTRACCION, e=2.0 cm m 17.00 8.18 S/. 139.06 S/. 139.06

04.08.07 JUNTAS DE DILATACION, e=2.0 cm m 27.20 15.78 S/. 429.22 S/. 429.22

04.08.08 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,873.25 4.35 S/. 8,148.64 S/. 4,074.32 S/. 4,074.32

05 CONTROL DE CALIDAD DEL CONCRETO S/. 1,050.04

05.01 DISEÑO DE MEZCLAS und 2.00 305.00 S/. 610.00 S/. 610.00

05.02 ENSAYOS DE DENSIDAD DE CAMPO und 2.00 36.67 S/. 73.34 S/. 73.34

05.03 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 10.00 36.67 S/. 366.70 S/. 183.35 S/. 183.35

Page 2: CRONO.xls

06 VARIOS S/. 34,392.88

06.01 REPOSICION Y CAMBIO DE TUBERIAS AVERIADAS m 110.00 70.44 S/. 7,748.40 S/. 7,748.40

06.02 MODIFICACION DE NIVELES DE TAPA DE BUZONES und 4.00 2,611.12 S/. 10,444.48 S/. 5,222.24 S/. 5,222.24

06.03 FLETE TERRESTRE GLB 1.00 2,600.00 S/. 2,600.00 S/. 650.00 S/. 650.00 S/. 650.00 S/. 650.00

06.04 REPOSICION DE MUROS DE ABOBE GLB 1.00 2,500.00 S/. 2,500.00 S/. 2,500.00

06.05 DESBROSE Y DESQUINCHE POR ENSANCHE DE VIA (PROPIEDAD DE TERCERGLB 1.00 11,100.00 S/. 11,100.00 S/. 5,550.00 S/. 5,550.00

S/. 31,965.76 S/. 33,750.47 S/. 79,207.41 S/. 66,584.06 S/. 46,610.50 S/. 28,355.94 S/. 23,771.53 S/. 31,263.77

Page 3: CRONO.xls

CRONOGRAMA GANTTPROYECTO:

“MEJORAMIENTO DEL PASAJE ANCASH, DE LA LOCALIDAD DE PARIAHUANCA, PROVINCIA DE CARHUAZ, ANCASH

LOCALIDAD PARIAHUANCADISTRITO PARIAHUANCAPROVINCIA CARHUAZREGION ANCASH

FECHA JUNIO 2014

MES1 MES2

Item Descripción Und. Metrado SEMANA1 SEMANA2 SEMANA3 SEMANA4 SEMANA5 SEMANA6 SEMANA7 SEMANA801 OBRAS PROVISIONALES

01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40M X 3.60M. und 1.00 7 DIAS

01.02 ALAMCEN Y OFICINA m2 25.00 7 DIAS

02 PAVIMENTO

02.01 OBRAS PRELIMINARES

02.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y HERRAMIENTAS GLB 1.00 7 DIAS

02.01.02 TRAZO, NIVELACION Y REPLANTEO KM 0.10 7 DIAS

02.01.03 TRAZO Y REPLANTEO DURANTE LA EJECUCION DE OBRA KM 1.00 7 DIAS

02.02 MOVIMIENTO DE TIERRAS

02.02.01 CORTE HASTA EL NIVEL DE SUBRASANTE CON MAQUINARIA m3 123.20 7 DIAS

02.02.02 COMPACTADO SUBRASANTE EN ZONA DE CORTE m2 363.00 7 DIAS

02.02.03 SUB - BASE AFIRMADO DE 0.15 M. FACTOR DE COMPACTACION 1.2 m2 363.00 7 DIAS 7 DIAS

02.02.04 BASE GRANULAR E=0.20 M REND.=2310 M2/DIA FACT. COMPACT.=1.20 m2 122.40 7 DIAS

02.02.05 ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO D=4KM m3 135.00 7 DIAS

02.03 OBRAS DE CONCRETO

02.03.01 ENCOFRADO DE PAVIMENTO RIGIDO m2 61.20 7 DIAS

02.03.02 CONCRETO F'C=210 KG/CM2. EN PAVIMENTO RIGIDO m3 56.70 7 DIAS 7 DIAS

02.03.03 CURADO EN PAVIMENTO RIGIDO m3 56.70 7 DIAS

02.04 JUNTAS DE DILATACION

02.04.01 JUNTAS DE CONTRACCION, e=2.0 cm m 396.25 7 DIAS

02.05 SEÑALIZACION

02.05.01 SEÑALIZACION CON CINTAS DE SEGURIDAD m2 10.20 7 DIAS

03 VEREDAS DE CONCRETO

03.01 OBRAS PRELIMINARES

03.01.01 TRAZO, NIVELACION Y REPLANTEO KM 0.20 7 DIAS

03.02 MOVIMIENTO DE TIERRAS

03.02.01 CORTE SUPERFICIAL MANUAL HASTA 0.20 MT m3 15.27 7 DIAS

03.02.02 NIVELACION Y COMPACTACION DE SUBRASANTE CON EQUIPO LIVIANO m2 50.90 7 DIAS

03.02.03 RELLENO CON MATERIAL GRANULAR COMPACTADO m3 15.27 7 DIAS

03.02.04 ELIMINACION DE DESMONTE,PROV.DEL MOV.EN TERRENO D=4KM m3 17.56 7 DIAS

03.03 OBRAS DE CONCRETO

03.03.01 ENCOFRADO Y DESENCOFRADO DE VEREDAS m2 30.54 7 DIAS

03.03.02 CONCRETO F'C=140 KG/CM2 m3 15.27 7 DIAS

03.04 JUNTAS DE DILATACION

03.04.01 JUNTAS ASFALTICAS m 120.81

03.04.02 PINTURA CON ESMALTE EN EXTERIOR m2 30.54 PARTIDAS CRITICAS

04 MURO DE CONTENCION

04.01 TRAZO, NIVELACION Y REPLANTEO KM 0.06 7 DIAS

04.02 EXCAVACION PARA ESTRUCTURAS m3 471.41 7 DIAS

04.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 512.40 7 DIAS 7 DIAS 7 DIAS

04.04 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 15,526.69 7 DIAS 7 DIAS

04.05 JUNTAS ASFALTICAS m 132.17 7 DIAS

04.06 CONCRETO F'C=210 KG/CM2, m3 204.96 7 DIAS 7 DIAS 7 DIAS 7 DIAS

04.07 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS

04.07.01 TRAZO, NIVELACION Y REPLANTEO KM 0.11 7 DIAS

04.07.02 EXCAVACION MANUAL DE ZANJAS 0.40 X 1.20 m3 52.80 7 DIAS

04.07.03 REFINE Y NIVELACION EN TERRENO NORMAL m2 44.00 7 DIAS

04.07.04 CAMA DE APOYO DE ARENA e=0.15 M m3 6.60 7 DIAS

04.07.05 DOBLE PRUEBA HIDRAULICA m3 52.80 7 DIAS

04.07.06 RELLENO Y COMPACTADO CON MATERIAL SELECCIONADO m3 52.80 7 DIAS

04.07.07 SUMINISTRO E INSTALACION DE TUBERIA P.V.C. C10 D= 2" m 110.00 7 DIAS 7 DIAS 7 DIAS

04.07.08 TUBERIA DE PVC A-10 SP D=1/2" INC.ELEM.UNION+2% DESPER m 50.00 7 DIAS

04.07.09 CONEXIONES DOMICILIARIAS DE AGUA pza 18.00 7 DIAS 7 DIAS

04.08 CANAL DE CONCRETO 7 DIAS

04.08.01 EXCAVACION MANUAL DE ZANJAS m3 50.22 7 DIAS

04.08.02 REFINE Y NIVELACION EN TERRENO NORMAL m2 54.00 7 DIAS

04.08.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 216.00 7 DIAS 7 DIAS

04.08.04 CONCRETO f'c=175 kg/cm2 m3 17.10 7 DIAS 7 DIAS

04.08.05 CONCRETO F'C=210 KG/CM2, m3 10.80 7 DIAS 7 DIAS

04.08.06 JUNTAS DE CONTRACCION, e=2.0 cm m 17.00 7 DIAS

04.08.07 JUNTAS DE DILATACION, e=2.0 cm m 27.20 7 DIAS

04.08.08 ACERO DE REFUERZO fy=4,200 kg/cm2 kg 1,873.25 7 DIAS 7 DIAS

05 CONTROL DE CALIDAD DEL CONCRETO

05.01 DISEÑO DE MEZCLAS und 2.00 7 DIAS

05.02 ENSAYOS DE DENSIDAD DE CAMPO und 2.00 7 DIAS

05.03 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 10.00 7 DIAS 7 DIAS

Page 4: CRONO.xls

06 VARIOS

06.01 REPOSICION Y CAMBIO DE TUBERIAS AVERIADAS m 110.00 7 DIAS

06.02 MODIFICACION DE NIVELES DE TAPA DE BUZONES und 4.00 7 DIAS 7 DIAS

06.03 FLETE TERRESTRE GLB 1.00 7 DIAS 7 DIAS 7 DIAS 7 DIAS

06.04 REPOSICION DE MUROS DE ABOBE GLB 1.00 7 DIAS

06.05 DESBROSE Y DESQUINCHE POR ENSANCHE DE VIA (PROPIEDAD DE TERCERGLB 1.00 7 DIAS 7 DIAS