3
MES MONTOS(Inc/IGV) PORCEN PARCIAL S/. ACUMULADO S/. PARCIAL % 0 0 0 0 1 335,605.40 335,605.40 5% 2 698,117.97 1,033,723.37 10% 3 809,678.56 1,843,401.93 12% 4 790,467.77 2,633,869.70 11% 5 1,145,325.68 3,779,195.38 16% 6 1,157,199.61 4,936,394.99 17% 7 1,091,415.65 6,027,810.64 16% 8 924,974.57 6,952,785.21 13% TOTAL 6,952,785.21 100% MES MONTOS(Inc/IGV) PORCEN PARCIAL S/. ACUMULADO S/. PARCIAL % 0 0 0 0 1 215,505.40 215,505.40 3% 2 498,017.97 713,523.37 8% 3 509,478.56 1,223,001.93 8% 4 790,437.77 2,013,439.70 12% 5 1,145,125.68 3,158,565.38 18% 6 1,157,099.61 4,315,664.99 18% 7 1,091,315.65 5,406,980.64 17% 8 924,774.57 6,331,755.21 15% TOTAL 6,331,755.21 100%

description

practico

Transcript of CURVA S

Page 1: CURVA S

MESMONTOS(Inc/IGV) PORCENTAJES

PARCIAL S/. ACUMULADO S/. PARCIAL %ACUMULADO %0 0 0 0 01 335,605.40 335,605.40 5% 5%2 698,117.97 1,033,723.37 10% 15%3 809,678.56 1,843,401.93 12% 27%4 790,467.77 2,633,869.70 11% 38%5 1,145,325.68 3,779,195.38 16% 54%6 1,157,199.61 4,936,394.99 17% 71%7 1,091,415.65 6,027,810.64 16% 87%8 924,974.57 6,952,785.21 13% 100%

TOTAL 6,952,785.21 100%

MESMONTOS(Inc/IGV) PORCENTAJES

PARCIAL S/. ACUMULADO S/. PARCIAL %ACUMULADO %0 0 0 0 01 215,505.40 215,505.40 3% 3%2 498,017.97 713,523.37 8% 11%3 509,478.56 1,223,001.93 8% 19%4 790,437.77 2,013,439.70 12% 32%5 1,145,125.68 3,158,565.38 18% 50%6 1,157,099.61 4,315,664.99 18% 68%7 1,091,315.65 5,406,980.64 17% 85%8 924,774.57 6,331,755.21 15% 100%

TOTAL 6,331,755.21 100%

Page 2: CURVA S

0 1 2 3 4 5 6 7 8 90

0.2

0.4

0.6

0.8

1

1.2

0 3%11%

19%

32%

50%

68%

85%

100%

05%

15%

27%

38%

54%

71%

87%

100%

CURVA S

PROGRAMADOEJECUTADO