EJEMPLO PRESUPUESTO SENCICO

2
HOJA DEL PRESUPUESTO UNIDAD METRADO COSTO P. COSTO T. S/ 1 1.1 m2 420 S/. 0.64 S/. 268.3 2 2.1 m3 130 S/. 16.48 S/. 2,142.4 2.2 m2 80 S/. 24.72 S/. 1,977.6 2.3 m3 283.5 S/. 8.84 S/. 2,504.9 3 3.1 m3 210 S/. 200.65 S/. 42,136.5 3.2 m2 420 S/. 0.49 S/. 207.6 COSTO DIRECTO S/. 49,237.4 GASTOS GENERALES 42.67 % C. S/. 21,012.5 UTILIDAD 20% CD S/. 9,847.4 SUBTOTAL S/. 80,097.5 I.G.V. 19 % S/. 15,218.5 PRESUPUESTO S/. S/. 95,316.0 ANALISIS DE COSTOS UNITARIOS 1.1 TRAZO Y REPLANTEO m2/dia UNIDAD m2 MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTAL TOPOGRAFO h.h 0.016 10.000 0.16 OFICIAL h.h 0.016 8.000 0.128 PEON h.h 0.032 6.000 0.192 0.48 EQUIPO NIVEL TOPOG. h.m. 0.016 8.403 0.134 H.M. 0.030 0.480 0.014 0.149 MATERIALES PINTURA ESMALTE gal 0.001 10.084 0.010 total 0.639 2.1 EXCAVACION EN MATERIAL SUELTO 3 m3/dia UNIDAD m3 MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTAL PEON h.h 1 2.667 6.000 16.000 16.000 EQUIPO H.M. 0.030 16.000 0.480 MATERIALES total 16.480 EXCAVACION EN MATERIAL COMPACTO RENDIMIENTO CURADO ESTRUCTURAS PRESUPUESTO RENDIMIENTO VACIADO DE CONCRETO OBRAS PRELIMINARES ELIMINACION DE MATERIAL EXCEDENTE TRAZO Y REPLANTEO MOVIMIENTO DE TIERRAS EXCAVACION EN MATERIAL SUELTO

Transcript of EJEMPLO PRESUPUESTO SENCICO

Page 1: EJEMPLO PRESUPUESTO SENCICO

5/13/2018 EJEMPLO PRESUPUESTO SENCICO - slidepdf.com

http://slidepdf.com/reader/full/ejemplo-presupuesto-sencico 1/2

 

HOJA DEL PRESUPUESTO

UNIDAD METRADO COSTO P. COSTO T. S/

1

1.1 m2 420 S/. 0.64 S/. 268.3

2

2.1 m3 130 S/. 16.48 S/. 2,142.4

2.2 m2 80 S/. 24.72 S/. 1,977.6

2.3 m3 283.5 S/. 8.84 S/. 2,504.9

3

3.1 m3 210 S/. 200.65 S/. 42,136.5

3.2 m2 420 S/. 0.49 S/. 207.6

COSTO DIRECTO S/. 49,237.4

GASTOS GENERALES 42.67 % C. S/. 21,012.5

UTILIDAD 20% CD S/. 9,847.4

SUBTOTAL S/. 80,097.5

I.G.V. 19 % S/. 15,218.5

PRESUPUESTO S/. S/. 95,316.0

ANALISIS DE COSTOS UNITARIOS

1.1 TRAZO Y REPLANTEO

m2/dia UNIDAD m2

MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTAL

TOPOGRAFO h.h 0.016 10.000 0.16

OFICIAL h.h 0.016 8.000 0.128

PEON h.h 0.032 6.000 0.192

0.48

EQUIPO

NIVEL TOPOG. h.m. 0.016 8.403 0.134H.M. 0.030 0.480 0.014

0.149

MATERIALES

PINTURA ESMALTE gal 0.001 10.084 0.010

total 0.639

2.1 EXCAVACION EN MATERIAL SUELTO

3 m3/dia UNIDAD m3

MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTALPEON h.h 1 2.667 6.000 16.000

16.000

EQUIPO

H.M. 0.030 16.000 0.480

MATERIALES

total 16.480

EXCAVACION EN MATERIAL COMPACTO

RENDIMIENTO

CURADO

ESTRUCTURAS

PRESUPUESTO

RENDIMIENTO

VACIADO DE CONCRETO

OBRAS PRELIMINARES

ELIMINACION DE MATERIAL EXCEDENTE

TRAZO Y REPLANTEO

MOVIMIENTO DE TIERRAS

EXCAVACION EN MATERIAL SUELTO

Page 2: EJEMPLO PRESUPUESTO SENCICO

5/13/2018 EJEMPLO PRESUPUESTO SENCICO - slidepdf.com

http://slidepdf.com/reader/full/ejemplo-presupuesto-sencico 2/2

 

2.2 EXCAVACION EN MATERIAL COMPACTO

2 m3/dia UNIDAD m3

MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTAL

PEON h.h 1 4.000 6.000 24.000

24.000

EQUIPO

H.M. 0.030 24.000 0.720

0.720

total 24.720

2.3 ELIMINACION DE MATERIAL EXCEDENTE D=5 km

850 m3/dia UNIDAD m3

MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTAL

OFICIAL h.h 1 0.009 8.000 0.075

PEON h.h 1 0.009 6.000 0.056

0.132

EQUIPO

CARGADOR FRONTAL h.m. 1 0.009 168.067 1.582

CAMION VOLQUETE 15 m3 h.m. 5 0.047 151.261 7.118

H.M. 0.030 0.132 0.0048.704

total 8.836

3.1 VACIADO DE CONCRETO CICLOPEO 1:8 + 40% P.G.

15 m3/dia UNIDAD m3

MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTAL

OPERARIO h.h 2 1.067 10.000 10.667

OFICIAL h.h 3 1.600 8.000 12.800

PEON h.h 10 5.333 6.000 32.000

55.467

EQUIPO

H.M. 0.030 55.467 1.664

MEZCLADORA DE CONCRETO DE 9 -11P3 h.m 1 0.533 6.723 3.586

5.250

MATERIALES

CEMENTO PORTLAND TIPO I (42.5KG) bolsa 3.220 21.849 70.354

HORMIGON m3 0.720 58.824 42.353

PIEDRA GRANDE m3 0.540 50.420 27.227

total 200.650

3.2 CURADO

100 m2/dia UNIDAD m2

MANO DE OBRA UNIDAD CUADRILLA CANTIDAD COSTO TOTAL

PEON h.h 1 0.080 6.000 0.480

0.480

EQUIPO

H.M. 0.030 0.480 0.014

total 0.494

RENDIMIENTO

RENDIMIENTO

RENDIMIENTO

RENDIMIENTO