PRACTICA DIRIGIDA N ° 01_IICURSO: METRADOSDOCENTE: L. ANTONIO APARICIO V. Ingeniero CivilTEMA: METRADOS EN ESTRUCTURAS MOV. TIERRAS Y CONCRETO
INGA SULUCO PEDROMOVIMIENTO DE TIERRAS
DESCRIPCION N° de Veces Largo (m) Ancho (m) Altura (m) SUB - TOTAL TOTAL
TRAZO NIVEL Y REPLANTEO (m2) (m2)
AREA PRIMER PISO 1 119.15
AREA SEGUNDO PISO PISO 1 103.60
AREA AZOTEA 1 104.88
AREA SISTERNA 1 1.86
AREA TANQUE ELEVADO 1 4.50
333.99
EXCAVACION MANUAL DE ZANJAS (m3) m3
CIMIENTOS m3
EJE A-A ENTRE 1Y9 10.03 0.70 2.00 14.04
EJE D-D ENTRE 1Y9 8.78 0.70 2.00 12.29
EJE B" ENTRE 1Y3 2.03 0.60 1.95 2.38
EJE C" ENTRE 9Y9A 0.80 0.50 1.95 0.78
EJE 9-9 ENTRE AYD 2.64 0.70 2.00 3.70
EJE 3-3 ENTRE AYB 1.88 0.60 1.95 2.20
EJE 1-1 ENTRE AYD 0.40 0.70 1.15 0.32
35.71
ZAPATAS
Z-1 17 1.10 1.10 1.55 31.88
Z-2 1 1.20 1.20 1.55 2.23
Z-3 2 1.10 1.70 1.55 5.80
Z-4 1 1.10 2.00 1.55 3.41
Z-5 2.00 0.90 0.90 1.55 2.51
VIGA DE CIMENTACION
EJE 8 ENTRE AYC 2.23 0.20 0.45 0.20
EJE 7-6-5Y4 ENTRE AYD 4 3.74 0.20 0.45 1.35
EJE3-2Y1 ENTRE CYD 3 0.97 0.20 0.45 0.26
![Page 2: Metrado de Vivienda](https://reader036.fdocuments.es/reader036/viewer/2022082518/563dbb8b550346aa9aae1ac4/html5/thumbnails/2.jpg)
PRACTICA DIRIGIDA N ° 01_IICURSO: METRADOSDOCENTE: L. ANTONIO APARICIO V. Ingeniero CivilTEMA: METRADOS EN ESTRUCTURAS MOV. TIERRAS Y CONCRETO
RELLENO COMPACTADO CON MATERIAL PROPIO (m3) m3
CIMIENTOS
EJE A-A ENTRE 1Y9 10.03 0.50 0.55 2.76
EJE D-D ENTRE 1Y9 8.78 0.50 0.55 2.41
EJE B" ENTRE 1Y3 2.03 0.50 0.55 0.56
EJE C" ENTRE 9Y9A 0.80 0.50 0.55 0.22
EJE 9-9 ENTRE AYD 2.64 0.50 0.55 0.73
EJE 3-3 ENTRE AYB 1.88 0.50 0.55 0.52
EJE 1-1 ENTRE AYD 0.40 0.50 0.55 0.11
PARA LLEGAR AL FONDO DE FALSO PISO m3
Sumatoria del Relleno Compactado = m30.8 por Compactacion = m3
Volumen de Material Excavado = m3Coef. 25% por Esponjamiento = m3
V. ELIM. MAT. EXCEDENTE = V.EXC*(1+%ESPONJ)-V.RELL.*(1+%ESPONJ)/COEF.COMP.
ELIMINACION DE MATERIAL EXCEDENTE (m3) m3
![Page 3: Metrado de Vivienda](https://reader036.fdocuments.es/reader036/viewer/2022082518/563dbb8b550346aa9aae1ac4/html5/thumbnails/3.jpg)
PRACTICA DIRIGIDA N ° 01_IICURSO: METRADOSDOCENTE: L. ANTONIO APARICIO V. Ingeniero CivilTEMA: METRADOS EN ESTRUCTURAS MOV. TIERRAS Y CONCRETO
CONCRETO SIMPLE
DESCRIPCION N° de Veces Largo (m) Ancho (m) Altura (m) SUB - TOTAL TOTAL
CIMIENTOS CORRIDOS, Cº 1:10 + 30% de Piedra Grande (m3) m3
CIMIENTOS m3
FALSO PISO, Concreto 1:10, Espesor = 0.10 m. (m2) m2
FALSO PISO m2
SOLADO, Concreto 1:12, Espesor = 0.10 m. (m2) m2
ZAPATAS m2
VIGA DE CIMENTACION m2
![Page 4: Metrado de Vivienda](https://reader036.fdocuments.es/reader036/viewer/2022082518/563dbb8b550346aa9aae1ac4/html5/thumbnails/4.jpg)
PRACTICA DIRIGIDA N ° 01_IICURSO: METRADOSDOCENTE: L. ANTONIO APARICIO V. Ingeniero CivilTEMA: METRADOS EN ESTRUCTURAS MOV. TIERRAS Y CONCRETO
CONCRETO ARMADO
DESCRIPCION N° de Veces Largo (m) Ancho (m) Altura (m) SUB - TOTAL TOTAL
ZATAPAS, Concreto f´c = 210 Kg/cm2 (m3) m3
ZAPATAS m3
VIGA DE CIMENTACION, Concreto f´c = 210 Kg/cm2 (m3) m3
VIGA DE CIMENTACION m3
SOBRECIMIENTO, Concreto f´c = 175 Kg/cm2 (m3) m3
SOBRECIMIENTOS m3EJE C ENTRE 1-2 3.05 0.15 0.40 0.18
EJE 1 ENTRE A,B,C 3.40 0.25 0.40 0.34
EJE 1 ENTRE A,B,C 3.90 0.25 0.40 0.39
EJE 1 ENTRE 1-1' 2.97 0.15 0.40 0.18
EJE 1-2 ENTRE A-1' 0.95 0.15 0.40 0.06
EJE 2-3 ENTRE C-C 3.30 0.15 0.40 0.20
EJE 2-3 ENTRE C-C 1.98 0.15 0.40 0.12
EJE 3 2.30 0.25 0.40 0.23
EJE 4-C 1.10 0.25 0.40 0.11
0.00
1.81
![Page 5: Metrado de Vivienda](https://reader036.fdocuments.es/reader036/viewer/2022082518/563dbb8b550346aa9aae1ac4/html5/thumbnails/5.jpg)
PRACTICA DIRIGIDA N ° 01_IICURSO: METRADOSDOCENTE: L. ANTONIO APARICIO V. Ingeniero CivilTEMA: METRADOS EN ESTRUCTURAS MOV. TIERRAS Y CONCRETO
SOBRECIMIENTO, Encofrado y Desencofrado (m2) m2
SOBRECIMIENTOS m2EJE 1-1 / A,B,C 2 7.50 . 1.00 15.00
EJE C ENTRE 1-2 Y A-2 2 3.98 . 0.60 4.78
EJE A ENTRE 1-1 2 0.80 . 1.00 1.60
EJE C ENTRE 2,3,4 2 5.05 . 0.60 6.06
EJE 3 2 3.03 . 1.00 6.06
EJE 4 ENTRE C-B 2 1.70 . 1.00 3.40
EJE 3-3 ENTRE A" A' A 2 3.90 . 1.00 7.80
EJE B' ENTRE 3-4 2 1.70 . 0.60 2.04
EJE 4 -A' 2 1.70 . 1.00 3.40
EJE 4 ENTRE B'-A" 2 2.20 . 0.60 2.64
EJE 4-A" 2 0.85 . 0.60 1.02
EJE A ENTRE B' B A" 2 1.80 . 1.00 3.60
EJE A-A 2 2.45 . 0.60 2.94
EJE 2-2 ENTRE 2-3 2 0.35 . 1.00 0.70 61.04
![Page 6: Metrado de Vivienda](https://reader036.fdocuments.es/reader036/viewer/2022082518/563dbb8b550346aa9aae1ac4/html5/thumbnails/6.jpg)
SOLUCION PRACTICA DIRIGIDA N ° 01_VERSION 02CURSO: METRADOS
DOCENTE: L. ANTONIO APARICIO V. Ingeniero CivilTEMA: METRADOS EN ESTRUCTURAS ACERO
DESCRIPCION DIAMETRO N° deCANTIDAD
LONGITUD 1/4" 3/8" 1/2" 5/8" 3/4" TOTAL(Pulg.) VECES (ml.) 0.256 0.560 0.994 1.552 2.235 (Kg.)
Zapatas, Acero Grado 60° - f`y = 4,200 Kg/cm2.
TOTAL DE ACERO EN METROS = ml.TOTAL DE ACERO EN KILOS = Kilogramos
Viga de Cimentacion, Acero Grado 60° - f`y = 4,200 Kg/cm2.
Longitudinal
Transversal
TOTAL DE ACERO EN METROS = ml.TOTAL DE ACERO EN KILOS = Kilogramos
![Page 7: Metrado de Vivienda](https://reader036.fdocuments.es/reader036/viewer/2022082518/563dbb8b550346aa9aae1ac4/html5/thumbnails/7.jpg)
SOLUCION PRACTICA DIRIGIDA N ° 01_VERSION 02CURSO: METRADOS
DOCENTE: L. ANTONIO APARICIO V. Ingeniero CivilTEMA: METRADOS EN ESTRUCTURAS ACERO
DESCRIPCION DIAMETRO N° deCANTIDAD
LONGITUD 1/4" 3/8" 1/2" 5/8" 3/4" TOTAL(Pulg.) VECES (ml.) 0.256 0.560 0.994 1.552 2.235 (Kg.)
Sobrecimientos, Acero Grado 60° - f`y = 4,200 Kg/cm2.
Longitudinal
Transversal
TOTAL DE ACERO EN METROS = ml.TOTAL DE ACERO EN KILOS = Kilogramos
TOTAL ACERO EN KILOS = Kg.
![Page 8: Metrado de Vivienda](https://reader036.fdocuments.es/reader036/viewer/2022082518/563dbb8b550346aa9aae1ac4/html5/thumbnails/8.jpg)
UNIVERSIDAD “ALAS PERUANAS”
INGENIERIA CIVIL – "Costos y Presupuestos” EXAMEN
Alumno……..……………………………………………………………………………………..……………..…(Apellidos y Nombres)
VALOR REFERENCIAL
OBRA : CONSTRUCCION DE "DOS AULAS" - PIURA.PROPIETARIO : MINISTERIO DE EDUCACIONFECHA : OCTUBRE DEL 2,010.
PRECIO
ITEM PARTIDA UNIDAD CANTIDAD UNITARIO
( S/. )
3.00.00 MOVIMIENTO DE TIERRAS
3.01.00 Excavación manual de zanjas, h= 1.00 m. m3.
3.02.00 Relleno compactado con material Propio m3.
3.03.00 Eliminación de mat. excedente, a 5 Km. m3.
4.00.00 OBRAS DE CONCRETO SIMPLE
4.01.00 Cimientos corridos, concreto 1:10+30% P.G. m3.
4.02.00 Falso piso, concreto 1:10, espesor = 10 cm. m2.
4.02.00 Solado para zapatas, concreto 1:12, espesor = 10 cm. m2.
5.00.00 OBRAS DE CONCRETO ARMADO
5.01.01 Concreto en Zapatas, f`c= 210 Kg/cm2. m3.
5.01.02 Acero para Zapatas, fy= 4,200 Kg/cm2. kg.
5.02.01 Concreto en Vigas de Cimentación, f`c= 210 Kg/cm2. m3.
5.02.02 Encofrado y desencofrado de Vigas de Cimentación m2.
5.02.03 Acero para Vigas de Cimentación, fy= 4,200 Kg/cm2. kg.
5.03.01 Concreto en Sobrecimientos, f`c= 175 Kg/cm2. m3.
5.03.02 Encofrado y desencofrado de Sobrecimientos m2.
5.03.03 Acero para Sobrecimientos, fy= 4,200 Kg/cm2. kg.