PUENTE TINGO

Transcript of Metrado Mes Junio Puente Tingo.xlsx

Hoja1CLIENTE: CHUNGAR SINERSACOSSULTORA: COLPEX PROJECT S.A.PROYECTO: CENTRALES HIDROELECTRICAS CHANCAY - RUCUYZONA:Puente TingoPROGRESIVAS:Estribo Izquierdo - DerechoFECHA: 20 JUNIO 2014VALORIZACIN MES DE JUNIO 2014EXCAVACION PUENTE TINGODIST.AREA (m)VOLUMEN (m)PROGRESIVA(m)RELLENOCORTERELLENOCORTE(m)(m)(m)(m)

ESTRIBO IZQUIERDO00000.00 + 0.00.00.00.00.000000.38 + 0.3810.971.0400004.53 + 4.1511.4846.5800008.68 + 4.159.5843.7000008.96 + 0.280.00.67ESTRIBO DERECHO00000.00 + 0.00.00.000000.45 + 0.4518.402.0700004.60 + 4.1514.0567.3300008.75 + 4.1513.2756.6900009.11 + 0.360.01.19VOLUMEN TOTAL219.28