OBRA : PUENTE CARROZABLE CAHUISH (SUPERESTRUCTURA) FECHA : AGOSTO 2005
HECHO : JB
PART. Descripción Cantidad
ACERO LONGITUD TOTAL
DiametroN° SUB. TOT (Kg)
Varillas Longitud TOTAL (Kg)
VIGAS PRINCIPAL04.01.03 ACERO f'y = 4200 Kg/cm2 p/viga 598.63
ACERO(+)3 D=1" 2 1" 3 8.00 48 192.003 D=1" 2 1" 3 6.00 36 144.00
2 D=1/2" 2 1/2" 2 4.00 16 16.32
ACERO TORSION2 D=1/2" 2 1/2" 2 8.00 32 32.64
ACERO(-)2 D=1/2" 2 1/2" 4 8.00 64 65.28
ESTRIBOSD=3/8" 2 3/8" 55 1.90 209.00 148.39
VIGA DIAGRAGMA04.02.03 ACERO f'y = 4200 Kg/cm2 237.67
ACERO(+)2 D=1/2" 4 1/2" 2 2.60 20.8 21.22
TORCION2 D=1/2" 4 1/2" 2 2.60 20.8 21.22
ACERO(-)2 D=1/2" 4 1/2" 2 2.60 20.8 21.22
ESTRIBOSD=3/8" 2 3/8" 57 2.15 245.10 174.02
LOSAS DE CONCRETO04.03.03 ACERO f'y = 4200 Kg/cm2 1325.22
CAPA SUPERIORTRASNV. D=3/8"@0.25 1 3/8" 61 3.00 183.00 129.93LONG. D=1/2"@0.20 4 1/2" 15 8.00 488 497.76
CAPA INFERIORTRASNV. D=3/8"@0.25 1 3/8" 61 3.00 183.00 129.93LONG. D=1/2"@0.20 4 1/2" 15 8.00 488 497.76
BORDES2 3/8" 4 8.00 64.00 45.442 1/4" 61 0.80 98 24.40
UBICACIÓN : DIST: JANGAS PROV: HUARAZ
f 1/4 " f 3/8 " f 1/2 " f 5/8 " f 3/4 " f 1"
PLANILLA DE METRADOSOBRA PUENTE PEATONAL JAULINCA FECHA : ABRIL 2007
YAUYA - CARLOS F. FITZCARRALD - ANCASH HECHO : JB
PART. DESCRIPCION UND CANT. AREADIMENSIONES CANTIDAD
LARGO ANCH0 ALTO PARCIAL TOTAL
01.00 OBRAS PRELIMINARES
01.00 LIMPIEZA DE ZONA DE TRABAJO 1 20.00 6.00 120.00 120.00
01.02 TRAZO NIVELES Y REPLANTEO DURANTE EL PROCESO M2 120.00PUENTE 1 10.00 6.00 60.00FALSO PUENTE 1 10.00 6.00 60.00
01.03 CASETA-ALMACEN M2 1 6.00 7.00 42.00 42.00
01.04 CARTEL DE IDENTIFICACION DE OBRA UND 1 1.00 1.00 1.00
01.05 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1 1.00 1.00 252.03
02.00 MOVIMIENTO DE TIERRAS
02.01 EXCAVACION ROCA SUELTA A MANO M3 23.568(ESTRIBO LADO IZQUIERDO)
Area de la base del estribo 1 19.64 1.2 23.568
02.01 EXCAVACION EN ROCA DURA m3 1.08(ESTRIBO LADO DERECHO - CONSTRUCCION CAJUELA) 1 3.00 0.60 0.60 1.08
02.02 RELLENO CON MATERIAL DE PRESTAMO m3 48.62(ESTRIBO LADO IZQUIERDO)
area de perfil longitudinal del rellenoç 1 8.84 5.50 48.62 48.62
03.00 CONCRETO SIMPLE
03.01. ESTRIBOS
03.01.01 ENCOFRADO Y DESENCOFRADO ESTRIBOS M2 37.06 ESTRIBO IZQUIERDO
CARA LATERAL 2 6.53 13.06CARA TRASNVERSAL 2 4.00 3.00 24.00
03.01.02 CONCRETO CICLOPEO F'C=175 KG/CM2+30% P.G M3 19.59 19.59 ESTRIBO IZQUIERDO
Area secccion estribo=6.53 1 6.53 3.00 19.59
03.02 ALETAS
03.02.01 ENCOFRADO Y DESENCOFRADO DE ALETAS M2 72.54 72.54ALETAS (LADO IZQUIERDO)
SECCION TRASVERS. PROMEDIO ALETA Ap=4.83m2 2 4.83 9.66SECCION LONG. ALETA A=14.24m2 4 14.24 56.96
COSTADOS A=2.96m2 2 2.96 5.92
03.01.02 CONCRETO CICLOPEO F'C=175 KG/CM2+30% P.G M3 28.98 28.98ALETAS (LADO IZQUIERDO)
SECCION TRASVERS. PROMEDIO ALETA Ap=4.83m2 2 4.83 3.00 28.98
UBICACIÓN :
PLANILLA DE METRADOSOBRA PUENTE PEATONAL JAULINCA FECHA : ABRIL 2007
YAUYA - CARLOS F. FITZCARRALD - ANCASH HECHO : JB
PART. DESCRIPCION UND CANT. AREADIMENSIONES CANTIDAD
LARGO ANCH0 ALTO PARCIAL TOTAL
UBICACIÓN :
04.00 CONCRETO ARAMADO - SUPER ESTRUCTURA DE C°A°
04.01 VIGA PRINCIPAL
04.01.01 CONCRETO f'c = 280 Kg/cm2 M3 2.16VIGAS PRINCIPALES 2 8.00 0.30 0.45 2.16
04.01.02 ENCOFRADO Y DESENCOFRADO M2 20.04LONGITUD 4 8.00 0.45 14.40BASE 2 8.00 0.30 4.80COSTADOS 4 0.30 0.70 0.84
04.01.03 ACERO f'y = 4200 Kg/cm2 KG 598.63
04.02 VIGA DIAGRAGMA
04.02.01 CONCRETO f'c = 280 Kg/cm2 M3 0.56VIGA DIAFRAGMA 4 1.75 0.20 0.40 0.56
04.02.02 ENCOFRADO Y DESENCOFRADO M2 7.00LADOS 8 1.75 0.40 5.60BASE 4 1.75 0.20 1.40
04.02.03 ACERO f'y = 4200 Kg/cm2 KG 237.67
04.03. LOSA DE CONCRETO ARMADO
04.03.01 CONCRETO f'c = 280 Kg/cm2 M3 3.78LOSA 1 8.00 2.85 0.15 3.42BORDES 2 8.00 0.15 0.15 0.36
04.03.02 ENCOFRADO Y DESENCOFRADO M2 28.46BASE 1 8.00 2.85 22.80COSTADOS 2 2.85 0.15 0.86BORDES 4 8.00 0.15 4.80
04.03.03 ACERO f'y = 4200 Kg/cm2 KG 1325.22
05.0 OBRA FALSA
05.01 EXCAVACION EN ROCA DURA P/DADOS m3 4.59ESTRIBO DERECHO 1 0.64 3.00 1.92
ESTRIBO IZQUIERDO 1 0.89 3.00 2.67
05.02 FALSO PUENTE M 7.001 7.00 7.00
PLANILLA DE METRADOSOBRA PUENTE PEATONAL JAULINCA FECHA : ABRIL 2007
YAUYA - CARLOS F. FITZCARRALD - ANCASH HECHO : JB
PART. DESCRIPCION UND CANT. AREADIMENSIONES CANTIDAD
LARGO ANCH0 ALTO PARCIAL TOTAL
UBICACIÓN :
06.0 VARIOS
06.01 BARANDAS DE TUBERIA F°G°, MONTAJE, COLOCACION ML 16.002 C/U DE 11.40 ML 2 8.00 16.00
06.02 APOYO DE NEOPRENO UND 2.002 2.00
06.03 APOYOS FIJOS Y ANCLAJE TIPO DOWEL KG D=5/8" 10.958 1.55 1.40 10.95
06.04 TUBO DE DRENAJE M 4.008 0.50 4.00
06.05 JUNTA DE DILATACION M 6.002 3.00 6.00
06.06 PRUEBAS DE CONCRETO UND 4.00VIGAS PRINCIPALES 2 2.00LOSA 1 1.00VIGA DIAFRAGMA 1 1.00
07.0 FLETE
07.01 FLETE TERRESTRE GBL 1 1.00 1.0007.02 FLETE RURAL GBL 1 1.00 1.00