Hoja1ITEMDESCRIPCINCANT.MEDIDASPARCIALTOTALUNIDVECESLARGO(L)ANCHO(B)ALTO(H)01.00.00OBRAS PROVISIONALES01.01.00CARTEL DE IDENTIFICACION DE OBRA DE 3.60x2.401UND1---1.00
01.02.00CASETA DE ALMACEN, GUARDIANIA Y VESTIDORES60.00M2110.006.00-60.00
01.03.00SERVICIOS HIGIENICOS2.00UND2---2.00
01.04.00CERCO PERIMETRICO DE ESTERAS56.00M156.0056.00
01.05.00AGUA PARA LA OBRA1.00GLB11.00
01.06.00MOVILIZACION Y DESMOBILIZACION DE HERRAMIENTAS Y EQUIPOS1.00GLB11.00
02.00.00TRABAJOS PRELIMINARES02.01.00LIMPIEZA DE TERRENO MANUAL144.00M2112.0012.00144.00
02.02.00TRAZO, NIVELES Y REPLANTEO144.00M2112.0012.00144.00
03.00.00SEGURIDAD Y SALUD03.01.00ELABORACION, IMPLEMENTACION Y ADMINISTRACION DE SEGURIDAD Y SALUD EN EL TRABAJO1.00GLB11.00
03.02.00EQUIPOS DE PROTECCION INDIVIDUAL60.00UND6060.00
03.03.00EQUIPOS DE PROTECCION COLECTIVA1.00GLB11.00
03.04.00SEALIZACION TEMPORAL DE SEGURIDAD1.00GLB11.00
03.05.00CAPACITACION SOBRE SALUD Y SEGURIDAD1.00GLB11.00
03.06.00RECURSOS DE RESPUESTA DE EMERGENCIA1.00GLB11.00
04.00.00MOVIMIENTO DE TIERRAS04.01.00EXCAVACIN PARA CIMIENTOS12.01M3EJE 1-112.680.600.901.45ENTRE EJE B-C
EJE 1-2ENTRE EJE A-B, C-DPARALELOGRAMO22.450.600.902.65TRIANGULO RECTANGULO20.150.090.900.02
EJE 2-3ENTRE EJE A-B, C-DPARALELOGRAMO22.450.600.902.65TRIANGULO RECTANGULO20.150.090.900.02
EJE 3-312.680.600.901.45ENTRE B-C
EJE 3'-3'12.640.500.901.19ENTRE B-C
EJE 3-421.070.600.901.16ENTRE EJE B-B, C-C
EJE 4-413.190.500.901.43ENTRE EJE B-C
04.02.00EXCAVACIN PARA ZAPATAS14.30M3Z-161.501.500.859.85Z-220.900.700.854.45
05.00.00CONCRETO SIMPLE05.01.00CIMIENTO05.02.00SOBRECIMIENTO05.02.01Encofrado
05.02.02Concreto0.67M3EJE 1-113.070.150.350.16ENTRE EJE B-C
EJE 1-223.070.150.350.16ENTRE EJE A-B, C-D
EJE 2-340.630.150.350.03ENTRE EJE A-B, C-D
EJE 3-310.630.150.350.03ENTRE B-C
EJE 3-3'10.450.150.350.02ENTRE B-C10.110.150.350.0110.600.150.350.0310.270.150.350.01
EJE 3'-3'11.620.150.350.09ENTRE B-C11.270.150.350.07
EJE 3-420.520.150.350.05ENTRE EJE B-B, C-C
EJE 4-413.370.150.350.18ENTRE EJE B-C
05.03.00SOLADOS PARA ZAPATAS
05.04.00PISOS FALSOS e=10148.16M2AULA HEXAGONALLADOAREATRIANGULOS EQUILATEROS64.167.48186.70
DESCONTAR ESPACIOS COLUMNASRECTANGULO-124.001.00-48.00TRIANGULO-120.050.01-0.01
LAVAMANOSRECTANGULO10.350.250.09RECTANGULO10.890.500.45
CLOSET11.700.500.85PUERTAS20.900.150.27
BAO7.81BAO14.031.757.05DESCONTAR ESPACIOS COLUMNAS-20.100.10-0.02CLOSET10.890.600.53DESCONTAR ESPACIOS COLUMNAS-10.250.10-0.03PUERTAS20.900.150.27
06.00.00CONCRETO ARMADO06.01.00ZAPATAS06.01.01Concreto fc= 210kg/cm213.60M3Z-161.501.500.509.50Z-220.900.700.504.10
06.01.03Acero
06.02.00COLUMNAS06.02.01EncofradoPERIMETRO ALTO:55.79M2C-161.812.9532.04C-221.002.905.80C-3190.701.3517.96
06.02.02Concreto3.96M3AREAALTOC-160.162.952.83TRAPECIO (B+b/2)*h20.08-0.16
C-220.250.252.900.36
C-3190.200.151.350.77
06.02.03Acero