PIC Presentation 417 Widening

download PIC Presentation 417 Widening

of 16

Transcript of PIC Presentation 417 Widening

  • 8/13/2019 PIC Presentation 417 Widening

    1/16

    Highway 417 Expansion East

    Nicholas Street to Ottawa Road 174GWP 4091-07-00 & GWP 4320-06-00

  • 8/13/2019 PIC Presentation 417 Widening

    2/16

    GWP 4091-07-00 & GWP 4320-06-00

    Outline

    Project OverviewHighway 417 Widening

    Bridge Rapid Replacements

    Traffic & Incident Management

    Project Timelines

  • 8/13/2019 PIC Presentation 417 Widening

    3/16

    GWP 4091-07-00 & GWP 4320-06-00

    Project Overview

    Project Limits

    Lees AvenueUnderpass

    Lees AvenueUnderpass

    Vanier ParkwayUnderpass

    Vanier ParkwayUnderpass

    Belfast RoadUnderpass

    Belfast RoadUnderpass

    Nicholas StreetUnderpass

    Nicholas StreetUnderpass

    Central TransitwayOverpass

    Central TransitwayOverpass

    HurdmanBridge

    HurdmanBridge

    St-Laurent BlvdUnderpass

    St-Laurent BlvdUnderpassEast Transitway

    Overpass

    East TransitwayOverpass

    MTO Bridges

    City of Ottawa Bridges

    Rapid Bridge Replacement Sites

  • 8/13/2019 PIC Presentation 417 Widening

    4/16

    GWP 4091-07-00 & GWP 4320-06-00

    Scope of Work Highway 417 Widening

    Single lane widening (outside) between Nicholas

    Street and 417/OR 174 interchangeRapid bridge replacements of Lees Avenue, VanierParkway and Belfast Road underpasses

    Reconstruction and widening of Hurdman Bridge

    Widening of Central Transitway (north side) and St-Laurent overpasses (both sides)

    New retaining walls between Vanier Parkway and St-

    Laurent BoulevardNoise wall upgrade at Lees Avenue

  • 8/13/2019 PIC Presentation 417 Widening

    5/16

    GWP 4091-07-00 & GWP 4320-06-00

    Highway 417 Stages I & II

    STAGE II: MEDIANRECONSTRUCTION

    STAGE I: HIGHWAY WIDENINGON OUTSIDE EDGES SHOULDERS, BARRIERS, AND

    RETAINING WALLS

    CONSTRUCTIONACCESS/EGRESS

    ON-RAMPSCL

    ON-RAMPSCL

  • 8/13/2019 PIC Presentation 417 Widening

    6/16

    GWP 4091-07-00 & GWP 4320-06-00

    Scope of Work Bridge Rapid Replacements

    Lees Avenue, Vanier Parkway and Belfast Road

    Establish fenced construction staging areas Construct new decks in staging areas

    Widening of abutments / construction of substructure

    Removal / reinstatement of decks using rapid replacement

    technology Demolition of existing bridge decks in staging area

    Restoration of impacted areas

    Lees Avenue: 750mm grade raise

    Vanier Parkway: 350mm grade raise

    Belfast Road: no grade raise

  • 8/13/2019 PIC Presentation 417 Widening

    7/16

    GWP 4091-07-00 & GWP 4320-06-00

    Staging Area Lees Avenue Underpass

    Lees AvenueUnderpass

    Lees AvenueUnderpass

    LeesStaging Area

    LeesStaging Area

    Source: Aerial photo from Google Maps

  • 8/13/2019 PIC Presentation 417 Widening

    8/16

    GWP 4091-07-00 & GWP 4320-06-00

    Rapid Replacement Lees Underpass

    Single overnight 17-hour full closure of Highway 417for bridge removal

    Lees Avenue to be closed for period of 10 to 12weeks for abutment and substructure construction

    Single overnight 17-hour full closure of Highway 417for bridge installation

    17-hour closure period from 6PM Saturday to 11AM Sunday

    Highway 417 closed from Nicholas Street to Vanier Parkway

    Ramp closures:

    Lees S-E (Long Duration)

    Lees W-S

    Nicholas N-E

    Vanier Pkwy N-W

    Vanier Pkwy S-W

  • 8/13/2019 PIC Presentation 417 Widening

    9/16

    GWP 4091-07-00 & GWP 4320-06-00

    Rapid Replacement Detour Lees

    Highway 417 WB traffic will

    exit at Vanier Parkway and

    follow Detour D-2

    Detour D-2 Ends

    at Bronson

    N/S-W ramp

    Highway 417 EB traffic will

    exit at Metcalfe Street and

    follow Detour D-1

    Detour D-1 Ends

    at Vanier PkwyS-E ramp

    Traffic to/from Gatineau will use

    Vanier Pkwy-St Patrick-King Edward

    Detour D-3

  • 8/13/2019 PIC Presentation 417 Widening

    10/16

    GWP 4091-07-00 & GWP 4320-06-00

    Staging Area Vanier Parkway Underpass

    Source: Aerial photo from Google Maps

    Vanier ParkwayStaging Area

    Vanier ParkwayStaging Area

    Vanier ParkwayUnderpass

    Vanier ParkwayUnderpass

  • 8/13/2019 PIC Presentation 417 Widening

    11/16

    GWP 4091-07-00 & GWP 4320-06-00

    Rapid Replacement Vanier Pkwy Underpass

    Single overnight 17-hour full closure of Highway 417for bridge replacement

    Closure period from 6PM Saturday to 11AM Sunday

    Highway closure at Vanier Parkway interchange only

    Vanier Parkway will be closed for 36 hours to allowfor approach slab construction

    Closure period from 6PM Saturday to 6AM Monday

    Road closure from Tremblay Road to Coventry Road

    Ramp closures:

    Lees S-E (Long Duration)

    Vanier Pkwy N-E

    Vanier Pkwy S-W

    Vanier Pkwy N-W - up tofour 15-minute closures

    (for bridge moves)

  • 8/13/2019 PIC Presentation 417 Widening

    12/16

    GWP 4091-07-00 & GWP 4320-06-00

    Rapid Replacement Detour Vanier Parkway

    Highway 417 WB traffic will

    exit at Vanier Parkway andre-enter highway via N-W ramp

    S-E rampHighway 417 EB traffic will

    exit at Vanier Parkway and

    re-enter highway via S-E ramp

    N-W ramp

  • 8/13/2019 PIC Presentation 417 Widening

    13/16

    GWP 4091-07-00 & GWP 4320-06-00

    Staging Area Belfast Road Underpass

    Source: Aerial photo from Google Maps

    Belfast Road(Bridge)

    Staging Area

    Belfast Road(Bridge)

    Staging Area

    Belfast RoadUnderpass

    Belfast RoadUnderpass

    Rapid ReplacementRoute Distance:

    1,000m

    Rapid ReplacementRoute Distance:

    1,000m

  • 8/13/2019 PIC Presentation 417 Widening

    14/16

    GWP 4091-07-00 & GWP 4320-06-00

    Rapid Replacement Belfast Road Underpass

    Single overnight 17-hour full closure of Highway 417

    for bridge replacement Closure period from 6PM Saturday to 11AM Sunday

    Vanier Parkway to St-Laurent Boulevard interchanges

    Belfast Road will be closed for 36 hours to allow forapproach slab construction

    Closure period from 6PM Saturday to 6AM Monday

    Road closure from Tremblay Road to Coventry Road

    Ramp closures: Lees S-E (Long Duration)

    Vanier Pkwy N-E

    Vanier Pkwy S-E

    St-Laurent N-W

    St-Laurent S-W

    417 WB at 417/174 split

    (At exit 113B Aviation

    Parkway)

  • 8/13/2019 PIC Presentation 417 Widening

    15/16

    GWP 4091-07-00 & GWP 4320-06-00

    Rapid Replacement Detour Belfast

    Detour D-2 Ends

    at Vanier Parkway

    N-W ramp

    Highway 417 EB Traffic will

    exit at Vanier Parkway and

    follow Detour D-1Trucks travelling on 417 WB will

    exit at Innes Road and follow

    Detour D-3 to D-2

    OR 174 WB traffic will

    exit at St-Laurent and

    follow Detour D-2

    Detour D-1 Ends

    at St-Laurent

    S-E ramp

    Highway 417 WB traffic will

    exit at Aviation Pkwy

    follow Detour D-2

    417 WB CLOSED

    at Exit 113B

  • 8/13/2019 PIC Presentation 417 Widening

    16/16

    GWP 4091-07-00 & GWP 4320-06-00

    Traffic & Incident Management Coordination

    Incident Management Team (IMT) in place for duration of

    Contract Key players: MTO Operations Centre, City of Ottawa Traffic Control Centre,Emergency Services, Contractor and Heavy Lift Specialist

    Extensive coordination and continuous contact between IMT key playersduring the rapid replacement operations

    Pre-rapid lift coordination meetings and dry run meetingscheduled in advance of rapid replacement weekend

    Advance notification & PVMS on Highway 417 and arterial roadsto notify motorists of construction operations and closure details

    Media releases, newspaper ads, radio, and use of social mediato inform the public of the full closure

    Traffic detours in effect during the rapid replacement weekends