ANALISIS DE PRECIOS UNITARIOSDATOS GENERALES
ITEM CARPETA ASFALTICA
CANTIDAD: 1.00 MONEDA: DOLARES AMERICANOS
UNIDAD: M3
1. MATERIALES
DESCRIPCION UNIDAD CANTIDAD
CEMENTO ASFALTICO Tn 0.12 1,350.00 162.00
AGREGADO GRUESO M3 0.40 20.50 8.20
AGREGADO FINO M3 0.60 20.50 12.30
ARENA M3 0.50 17.20 8.60
TOTAL MATERIALES 191.10
2. MANO DE OBRA
DESCRIPCION UNIDAD CANTIDAD
ENCARGADO DE PLANTA Hr 0.03 7.37 0.22
MECANICO DE PLANTA Hr 0.03 4.50 0.14
OPERADOR DE PLANTA Hr 0.03 4.20 0.13
CAPATAZ Hr 0.03 4.50 0.14
OPERADOR DE EQUIPO Hr 0.03 3.90 0.12
CHOFER Hr 0.03 3.30 0.10
AYUDANTE Hr 0.03 2.40 0.07
PEON Hr 0.06 2.00 0.12
SUB TOTAL MANO DE OBRA 1.03
BENEFICIOS SOCIALES (55-77.18%) X1 60.00% 0.62
IMPUESTOS IVA MANO DE OBRA (14.94%) X1+X2 14.94% 0.25
TOTAL MANO DE OBRA 1.89
3. EQUIPO MAQUINARIA Y HERRAMIENTAS
DESCRIPCION UNIDAD CANTIDAD %PRODUC %IMPRODUC
PLANTA DE ASFLATO Hr 0.03 100.00 0.00 82.52 29.76 2.48
PAVIMENTADOR Hr 0.03 100.00 0.00 31.50 11.21 0.94
COMPAC. RODILLO LISO Hr 0.03 77.58 22.42 29.01 10.51 0.75
COMPAC. NEUMATICO Hr 0.03 55.53 44.47 30.67 10.98 0.66
CARGADOR FRONTAL Hr 0.03 87.64 12.36 43.15 17.01 1.20
VOLQUETE Hr 0.03 43.90 56.10 52.07 14.30 0.93
ESCOBA MECANICA Hr 0.03 100.00 0.00 13.81 2.47 0.41
HERRAMIENTAS - % DEL TOTAL DE LA MANO DE OBRA 6.00% 0.44
TOTAL EQUIPO MAQUINARIA Y HERRAMIENTAS 7.80
4. GASTOS GENERALES Y ADMINISTRATIVOS
GASTOS GENERALES - % DE ( 1 + 2 + 3 ) 8.00% (1+2+3) 200.79
TOTAL GASTOS GENERALES Y ADMINISTRATIVOS 16.06
5. UTILIDAD
UTILIDAD - % DE (1 + 2 + 3 + 4 ) 10.00% (1+2+3+4) 216.85
TOTAL UTILIDAD 21.69
6. IMPUESTOS
IMPUESTOS IT - % DE ( 1 + 2 + 3 + 4 + 5 ) 3.09% 238.54
TOTAL IMPUESTOS 7.37
PRECIO PRODUCTIVO
COSTO
TOTAL
PRECIO PRODUCTIVO
COSTO
TOTAL
PRECIO PRODUCTIVO
COSTO IMPRODUC
COSTO
TOTAL
TOTAL PRECIO UNITARIO 1 + 2 + 3 + 4 + 5 + 6 245.91
PRECIO UNITARIO ($us) 245.91
ANALISIS DE EQUIPO
VOLQUETE
43.90 34.59 56.59 79.05 50.09 50.00 43.90
Nº DE MAQUINAS 1.00 1.00 1.00 1.00 1.00 2.00 1.00
% PRODUCTIVO 100.00 100.00 77.58 55.53 87.64 43.90 100.00
% IMPRODUCTIVO 0.00 0.00 22.42 44.47 12.36 56.10 0.00
PLANTA DE ASFALTO
PAVIMENTADOR
COMPAC. ROD. LISO
COMPAC. NEUMATICO
CARGADOR FRONTAL
ESCOBA MECANICA
PRODUCCION HORARIA
PLANILLA DNR
EquipoValor Residual Costo Operación Costo Horario
% ($us) Materiales
140 10 2000 220000 20% 44000 12% 1 0.53 17.01 11.00 12.91 2.23 43.15 17.01
285 10 2000 185000 20% 37000 12% 1 0.53 14.30 9.25 26.28 2.23 52.07 14.30
110 10 2000 136000 20% 27200 12% 0.9 0.53 10.51 6.12 10.14 2.23 29.01 10.51
120 10 2000 142000 20% 28400 12% 0.9 0.53 10.98 6.39 11.07 2.23 30.67 10.98
360 10 2000 385000 20% 77000 12% 0.9 0.53 29.76 17.33 33.20 2.23 82.52 29.76
125 10 2000 145000 20% 29000 12% 0.9 0.53 11.21 6.53 11.53 2.23 31.50 11.21
90 10 2000 32000 20% 6400 12% 0.5 0.53 2.47 0.80 8.30 2.23 13.81 2.47
SALARIO MENSUAL OPERADOR 400 SusFACTOR DE COSTO DE MATERIAL 0.174 Sus
POTENCIA [Hp]
Vida Util (años)
"n"
Hrs.trab por año
Costo equipo Vt
[$us]
Interes anual "i"
Coef. "k"
Costo litro diesel
Depreciación "P"
Mantenimiento "M" Mano de
obraProductivo
($us)Improductivo
($us)
CARGADOR FRONTAL
CAT938F
VOLQUETA 12 M3
COMPACTADOR RODILLO
LISO
COMPACTADOR NEUMÁTICO
PLANTA DE ASFALTO 120
Ton/hra
TERMINADORA DE C.
ASFÁLTICO
ESCOBA MECÁNICA