GOBERNACION DE CORDOBA SECRETARIA DE INFRAESTRUCTURACONSTRUCCIN Y DOTACIN DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E HOSPITAL SAN JERONIMO DE MONTERIA

REQUERIMIENTOS DE EQUIPOS PARA LA DOTACION DE LA UNIDAD MATERNO INFANTIL E.S.E HOSPITAL SAN JERONIMO DE MONTERIA PRESUPUESTO OFICIALSERVICIO UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA UCI OBSTETRICA EQUIPOS REQUERIDOS SUCCIONADOR DE PARED CAMA UCI MONITOR DE SIGNOS VITALES VENTILADOR FLUJOMETROS DOBLES DE OXIGENO AMBU DESFIBRILADOR ELECTROCARDIOGRAFO VENTILADOR DE TRANSPORTE ASPIRADORES PORTATILES CARRO DE PARO VENTILADORES DE RESPUESTO MONITORES DE RESPUESTO EQUIPO DE ORGANO DE LOS SENT LARINGOSCOPIO - JUEGO DE VALVA CANT.PROY 20 20 20 20 40 20 1 1 1 2 1 2 2 1 3 COSTO UNIT. 950,000 6,380,000 6,500,000 40,000,000 250,000 700,000 25,000,000 5,634,000 40,000,000 2,700,000 5,684,000 40,000,000 6,500,000 3,000,000 3,000,000 COSTO TOTAL 19,000,000 127,600,000 130,000,000 800,000,000 10,000,000 14,000,000 25,000,000 5,634,000 40,000,000 5,400,000 5,684,000 80,000,000 13,000,000 3,000,000 9,000,000 1,287,318,000 93,578,000 51,780,000 90,000,000 35,000,000 36,000,000 3,500,000 1,400,000 6,000,000 11,368,000 25,000,000 5,634,000 5,000,000 5,500,000 20,900,000 18,000,000 850,000 19,500,000 25,000,000 3,000,000 3,000,000 2,700,000 5,684,000 77,556,000 37,500,000 4,000,000 2,980,000 10,000,000 140,000,000 740,430,000 25,000,000 3,000,000 3,000,000 5,684,000 7,160,000 22,360,000

URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA URG GINECOLOGICA

MESA DE CIRUGIA LAMPARA CIELITICA MAQUINA DE ANESTESIA ELECTOBISTURI O ELECTROCAUTERIO MONITOR DE SIGNOS VITALES CON CAPNOGRAFO SUCCIONADOR AMBU LARINGOSCOPIO - JUEGO DE VALVA CARRO DE PARO DESFIBRILADOR ELECTROCARDIOGRAFO CAMILLAS DE TRANSPORTE FLUJOMETROS DOBLES SUCCIONADORES DE PARED MONITOR DE SIGNOS FETALES DOPPLER MONITORES DE SIGNOS VITALES DESFIBRILADOR LARINGOSCOPIO CON JUEGO DE VAL EQUIPO DE ORGANO DE LOS SENTID ASPIRADORES PORTATILES CARRO DE PARO CAMAS SERVOCUNAS CAMILLAS SILLAS DE RUEDA CAMILLA PARA TRASLADO DE PTES ECOGRAFO

2 2 2 2 2 2 2 2 2 1 1 2 22 22 1 1 3 1 1 1 1 1 23 5 2 5 4 1

46,789,000 25,890,000 45,000,000 17,500,000 18,000,000 1,750,000 700,000 3,000,000 5,684,000 25,000,000 5,634,000 2,500,000 250,000 950,000 18,000,000 850,000 6,500,000 25,000,000 3,000,000 3,000,000 2,700,000 5,684,000 3,372,000 7,500,000 2,000,000 596,000 2,500,000 140,000,000

UNID CUID INT. NEO UNID CUID INT. NEO UNID CUID INT. NEO UNID CUID INT. NEO UNID CUID INT. NEO UNID CUID INT. NEO

DESFIBRILADOR LARINGOSCOPIO CON JUEGO DE VAL EQUIPO DE ORGANO DE LOS SENTID CARRO DE PARO LAMPARA DE FOTOTERAPIA INCUBADORA DE TRANSPORTE

1 1 1 1 2 2

25,000,000 3,000,000.0 3,000,000 5,684,000 3,580,000 11,180,000

GOBERNACION DE CORDOBA SECRETARIA DE INFRAESTRUCTURACONSTRUCCIN Y DOTACIN DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E HOSPITAL SAN JERONIMO DE MONTERIA

REQUERIMIENTOS DE EQUIPOS PARA LA DOTACION DE LA UNIDAD MATERNO INFANTIL E.S.E HOSPITAL SAN JERONIMO DE MONTERIA PRESUPUESTO OFICIALSERVICIO UNID CUID INT. NEO UNID CUID INT. NEO UNID CUID INT. NEO UNID CUID INT. NEO EQUIPOS REQUERIDOS SERVOCUNA-CUNA DE CALOR RAD INCUBADORAS SUCCIONADORES DE PARED MONITORES DE SIGNOS VITALES CANT.PROY 8 8 16 2 COSTO UNIT. 7,500,000 11,180,000 950,000 6,500,000 COSTO TOTAL 60,000,000 89,440,000 15,200,000 13,000,000 243,844,000 5,684,000 67,440,000 130,000,000 25,000,000 3,000,000 3,000,000 234,124,000

UNID CUID INT. PED UNID CUID INT. PED UNID CUID INT. PED UNID CUID INT. PED UNID CUID INT. PED UNID CUID INT. PED

CARRO DE PARO CAMAS MONITORES DE SIGNOS VITALES DESFIBRILADOR LARINGOSCOPIO CON JUEGO DE VAL EQUIPO DE ORGANO DE LOS SENTID

1 20 20 1 1 1

5,684,000 3,372,000 6,500,000 25,000,000 3,000,000.0 3,000,000

TOTAL INVERSION

2,505,716,000

GOBERNACION DE CORDOBA SECRETARIA DE INFRAESTRUCTURA CONSTRUCCIN Y DOTACIN DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E HOSPITAL SAN JERONIMO DE MONTERIA PRESUPUESTO OFICIALITEM DESCRIPCION UNIDAD CANTIDAD VALOR UNITARIO VALOR TOTAL

CAPTULO 1: PRELIMINARES 1.1 1.2 Descapote a maquina Excavacion maquina (H=1 - 1.5 canal abierto) Localizacin. trazado. demarcacin. nivelacin. replanteo del terreno y de la estructura existente y la nueva, confrontacin de medidas. Incluye: Equipo de topografa. personal experto. hiladeros y sealizacin necesaria. Caseta en madera (24 M2) Bao provisional para obreros (4M2) Cerramiento provisional en polisombra Acarreo interno, cargue. transporte y la correcta disposicin del material producto del descapote M3 M3 405.89 150.00 22,263.51 26,924.80 9,036,536.07 4,038,720.00

1.3

DIA

8.00

370,000.00

2,960,000.00

1.4 1.5 1.6 1.7

GL GL ML M3

1.00 1.00 240.00 555.89

3,180,744.36 1,224,975.84 16,500.09 22,500.35

3,180,744.36 1,224,975.84 3,960,021.53 12,507,719.56

CAPTULO 2 : EXCAVACIONES , RELLENOS Y RETIROS DE MATERIAL 2.1 2.2 Excavacin manual entre 0-1,50 mts en cualquier tipo de suelo Acarreo interno, cargue. transporte y la correcta disposicin del material producto de la excavaciones en botadero oficial. Rellenos en recebo para remplazos y ajustes promedio 20 cm. alrededor de estructuras de concreto, redes de alcantarillado y canal. utilizando mtodos mecnicos o manuales para su compactacin. la ejecucin se har en capas no mayores de 0.15 m. M3 M3 216.00 216.00 13,185.65 22,500.35 2,848,101.10 4,860,075.60

2.3

M3

40.50

38,474.54

1,558,218.95

CAPITULO 3 : CIMIENTOS Y ESTRUCTURA EN CONCRETO 3.1 3.2 3.3 3.4 3.5 3.6 3.7 3.8 3.9 3.10 3.11 3.12 Suministro y colocacion de concreto para solado en concreto 2000 PSI. Espesor 5 cm. Construccion pilotes con concreto de 3000 PSI Construccion zapatas con concreto de 3000 PSI Construccion de columnas en concreto 4000 PSI Construccion de vigas cimentacion con concreto de 3000 PSI Construccion de losa de entrepiso con concreto de 3000 PSI, lamina metaldeck 2" cal. 16, e= 14 cms Construccion de vigas aereas con concreto de 3000 PSI Construccion de viga perimetral losas en concreto 3000 PSI Construccion de placa de piso e = 10 cms 3000 psi Hierro de refuerzo A-37 Y 60000 PSI Viga metalica 4"x6" calibre 16 para soporte de losa. Incluye platinas y pernos para asegurar a viga de concreto Mallas electrosoldadas D-84 y D-50 para losa y piso M2 M3 M3 M3 M3 M2 M3 M3 M2 KG KG KG 57.83 131.20 72.00 118.35 115.65 3,641.87 234.92 4.32 1,482.30 81,139.71 6,274.07 4,878.14 17,676.32 425,879.13 352,054.63 492,616.04 394,842.20 154,925.00 608,590.49 587,784.49 46,888.33 3,826.55 15,099.65 4,036.88 1,022,221.71 55,875,341.92 25,347,933.36 58,301,108.33 45,663,499.85 564,216,720.68 142,970,077.32 2,539,228.99 69,502,567.85 310,485,481.86 94,736,269.23 19,692,483.85

CAPITULO 4: MAMPOSTERIA , PAETES Y ACABADOS 4.1 4.2 4.3 Suministro y colocacion de bloques para muros fachadas catalan indural COLOR Mamposteria en bloque 0.10 x 0.20 x 0.40 m. para levantar muros de particin internos, que luego seran revocados por ambas caras. Mamposteria en bloque 0.15 x 0.20 x 0.40 m. para levantar muros de particin internos, externos, ajustes, aticos y tabiques, que luego seran revocados por ambas caras. Muros en DryWall . Para levantar muros de particin internos, externos, ajustes y tabiques, que luego seran macillados por ambas caras. Incluye aislante termoacustico tipo frescasa o similar Revoque liso en muros interiores utilizando mortero 1:4 Suministro y aplicacin a llana de estuco acrilico en pasta tipo interior calidad Pintuco o Textuco sobre muros. Aplicacin pintura vinilo tipo 1 en superficies estucadas internas. Dos manos Aplicacin pintura tipo acrlica hidro - repelente en muros externos, vigas, columnas y sillares de fachadas y patios. tipo Koraza Plastica calidad Pintuco colores institucional. Sistema completo de acabados de muros en zona aseptica con pintura epoxicapoliamida + poliuretano calidad Pintuco aplicada con pistola o rodillo. Base agua M2 M2 M2 1,359.75 990.06 443.50 70,355.35 32,216.53 37,876.55 95,665,683.70 31,896,300.73 16,798,248.96

4.4 4.5 4.6 4.7 4.8

M2 M2 M2 M2 M2

3,816.02 2,875.12 1,818.66 1,818.66 180.00

52,552.52 20,002.52 4,395.80 7,984.19 16,674.19

200,541,467.37 57,509,633.23 7,994,465.54 14,520,518.35 3,001,353.35

4.9

M2

2,182.30

19,117.21

41,719,482.15

CAPTULO 5: CUBIERTA. IMPERMEABILIZACIONES Y CIELORASOS

5.1

Suministro y colocacin cieloraso a junta perdida con placas de yeso tipo Gyplac u similar de espesor 1/2" Incluye: armazn de soporte necesario en perfil de lamina galvanizada. Suspendido con cuelgas, fijaciones necesarias, cinta y resane para juntas, remate lateral contra muros con moldura de poliuretano inyectado con desarrollo de 0.08 m. Con forma de media caa calidad Romoplak. Ademas perforaciones necesarias para lamparas, aire acondicionado, registros para llaves de contencin y rejillas plasticas de registro de 60 x 60 cm. para llaves de control de gases medicinales, red de abastos y perforaciones necesarias para empotrar lamparas con marco perimetral en perfil de aluminio color blanco, rejillas de aire acondicionado, red de incendio y remates laterales en angulo contra ventanas, vacios y escalas. Acabado final del cielorasos con pintura de acabado acrlica tipo base solvente calidad Pintuco o su similar. La pintura antes especificada se aplicara con pistola o rodillo. Suministro y colocacion de cielo raso en placa plana 60x60 fibra mineral. Incluye estructura soporte

M2

4,903.71

57,773.00

283,302,037.83

5.2

M2

0.00

87,237.66

0.00

GOBERNACION DE CORDOBA SECRETARIA DE INFRAESTRUCTURA CONSTRUCCIN Y DOTACIN DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E HOSPITAL SAN JERONIMO DE MONTERIA PRESUPUESTO OFICIALITEM 5.3 5.4 5.5 DESCRIPCION Construccin cubierta en teja Standing Seam doble capa con aislamiento en Fibra de Vidrio de 1" de ancho 50 cm, de espesor en la F. Vidrio 38mm, sello interior en lamina plana Cal 26 Suministro e instalacion de estructura metalica para cubierta Suministro e instalacion de manto 3 mm mas capa aluminio al 80 UNIDAD M2 KG M2 CANTIDAD 505.00 9,100.00 2,000.00 VALOR UNITARIO 130,000.00 15,100.47 26,050.02 VALOR TOTAL 65,650,000.00 137,414,317.95 52,100,032.50

CAPTULO 6: ENCHAPES DE MUROS Y PISOS 6.1 Suministro , colocacin y compactacion de entresuelo (Recebo) espesor variable entre 0.20 - 0.40 m. incluye capa de aislamiento con polietileno de alta densidad espesor 8 micras Suministro y colocacin baldosn cermico de 20.5 x 30.5 cm. para instalar sobre pared, calidad Corona o su similar en baos publicos, baos y lavamanos de consultorios, bao y mesones en acero inoxidable de estar personal, cuarto aseo. Suministro y colocacin de piso en baldosa de grano 33x33 tipo alfa u similar, pulida y brillada Guardaescoba recto Guardaescoba media caa Suministro y colocacin de mediacaa sintetica tipo vinilo para area aseptica. Incluye todo lo necesario para su correcto funcionamiento. M2 1,982.06 40,334.54 79,945,482.32

6.2

M2

993.18

44,986.31

44,679,500.39

6.3 6.4 6.5 6.6

M2 ML ML ML

4,142.06 477.44 1,768.19 1,180.18

73,966.43 29,405.32 52,879.15 27,000.00

306,373,411.47 14,039,274.91 93,500,384.24 31,864,857.64

CAPTULO 7: CARPINTERIA METLICA Y ACCESORIOS METALICOS 7.1 7.2 7.3 7.4 7.5 7.6 7.7 Suministro y colocacin marcos y puertas de aluminio y vidrio natural esmerilado, sin guardacamilla. VER CUADRO DE PUERTAS Suministro y colocacin marcos y puertas de aluminio y vidrio natural esmerilado, con guardacamilla. VER CUADRO DE PUERTAS Suministro y colocacin marcos y puertas de aluminio. VER CUADRO DE PUERTAS Suministro y colocacion de puerta plegable. VER CUADRO DE PUERTAS Suministro y colocacin de ventanas tipo V-01 con perfileria en aluminio. VER CUADRO DE VENTANAS. Suministro y colocacin de ventanas tipo V-02 con perfileria en aluminio. VER CUADRO DE VENTANAS. Suministro y colocacion de ventanas tipo perfileria y persianas en aluminio. Suministro e instalacin Barra lateral de inodoro para discapacitados rebatible sencilla de 60 cm x 18,5 cm marca Ferrum distribuido por Franz Viegener. Incluye: Soportes y bases de fijacin al muro tornillos de fijacin M2 M2 M2 M2 M2 M2 M2 375.46 285.58 17.64 430.92 104.40 156.60 11.02 450,000.00 550,000.00 450,000.00 750,000.00 350,000.00 350,000.00 294,000.00 168,957,000.00 157,069,000.00 7,938,000.00 323,190,000.00 36,540,000.00 54,810,000.00 3,239,880.00

7.8

UN

8.00

490,000.00

3,920,000.00

CAPTULO 8: CARPINTERA MADERA. MUEBLES Y DIVISIONES MODULARES Suministro e instalacin de guardacamilla de alto impacto de plastico reforzado marca IPC ancho 15 cm referencia 1600 i . Incluye esquineros internos y externos de proteccin, terminales, esquineros de alto impacto en los filetes de altura 1.22 m, referencia 164 BN, accesorios y fijaciones necesarias. Suministro y colocacin de superficie o mostrador de atencin al publico de ancho variable entre 0.30 - 0.60 cm. de granito natural referencia institucional espesor 2 cm. Incluye: Regrueses con remate en toro completo, estructura de soporte y obra civil, pegante , mortero de pega, sellado de placas con pigmentos para evitar ataque de acidos, sellado de juntas, perforaciones para pasa cables y anclajes necesarios para su correcto funcionamiento. (ESTACION DE ENFERMERIA)

8.1

ML

332.80

110,500.00

36,774,400.00

8.2

ML

93.06

1,500,000.00

139,590,000.00

CAPTULO 9 : EQUIPOS Y OBRAS VARIOS 9.1 Suministro e instalacin topellantas prefabricados en concreto reforzado de 0.30 x 0.60 m. Para zona de parqueadero. Suministro y colocacin concreto de fc 17.5 Mpa para anden perimetral a las fachadas con acabado antideslizante con espesor 0.10 m. Incluye: recebo con espesor variable entre 0.15-0.30 m. Dilataciones en varilla de madera 2" x 2" cada m., para ser retirada y resane posterior con un mortero elstico fludo 1:3. UN 6.00 19,532.94 117,197.64

9.2

M2

184.10

53,827.49

9,909,641.13

CAPTULO 10 : SISTEMAS ELECTRICOS, TELECOMUNICACIONES, VOZ Y DATOS

10.1 10.2 10.3 10.4 10.5 10.6 10.7 10.8 10.9 10.10 10.11

Suministro e instalacion de salida 120v para luces y tomas y en tuberia pvc, certificado Un Suministro e instalacion de salida 120v con en tuberia de 1/2" IMC, certificado Suministro de toma corriente doble grado hospitalario, certificado Suministro de toma corriente doble tierra aislada + grado hospitalario, certificado Suministro de toma corriente doble GFCI + grado hospitalario, certificado Suministro e instalacion de toma corriente 220v-20A certificado Tierra aislada Suministro de Lampara Fluorescente 1x32 W y 2x13w Suministro e instalacion luminaria ojo de buey 1x13w cerrada Suministro e instalacion luminaria especular 60x60cm Suministro de suiche sencillo y doble Suministro de Toma corriente doble con pt normal PROTECCIONES, TABLEROS DE DISTRIBUCION SUMINISTRO E INSTALACION DE GABINETE DE DISTRIBUCION G1 1500A, SEALIZACION BARRAJES, MEDIDA Y PROTECCIONES Un Un Un Un Un Un Un Un Un Un

532.00 330.00 102.00 253.00 6.00 7.00 142.00 194.00 18.00 85.00 150.00

116,100.00 212,300.00 41,000.00 42,500.00 140,200.00 165,500.00 95,000.00 53,000.00 180,000.00 7,500.00 5,000.00

61,765,200.00 70,059,000.00 4,182,000.00 10,752,500.00 841,200.00 1,158,500.00 13,490,000.00 10,282,000.00 3,240,000.00 637,500.00 750,000.00

10.12

Un

1.00

35,537,500.00

35,537,500.00

GOBERNACION DE CORDOBA SECRETARIA DE INFRAESTRUCTURA CONSTRUCCIN Y DOTACIN DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E HOSPITAL SAN JERONIMO DE MONTERIA PRESUPUESTO OFICIALITEM 10.13 10.14 10.15 10.16 10.17 10.18 10.19 10.20 10.21 10.22 10.23 DESCRIPCION SUMINISTRO E INSTALACION DE GABINETE DE DISTRIBUCION GNR 150A, SEALIZACION BARRAJES Y PROTECCIONES SUMINISTRO E INSTALACION DE GABINETE DE DISTRIBUCION G2 1000A, SEALIZACION BARRAJES Y PROTECCIONES SUMINISTRO E INSTALACION DE GABINETE DE DISTRIBUCION GL 80A, SEALIZACION BARRAJES Y PROTECCIONES SUMINISTRO E INSTALACION DE GABINETE DE DISTRIBUCION GLE 50A, SEALIZACION BARRAJES Y PROTECCIONES SUMINISTRO E INSTALACION DE GABINETE DE DISTRIBUCION G1R 150A, SEALIZACION BARRAJES Y PROTECCIONES SUMINISTRO E INSTALACION DE GABINETE DE DISTRIBUCION G3 280A, SEALIZACION BARRAJES Y PROTECCIONES SUMINISTRO E INSTALACION DE BANCO DE CONDENSADORES 100 KVAR INCLUYE ACOMETIDA Suministro e instalacion de Tablero de distribucion 36 ctos- 220v-3-5 H, Certificado, Suministro e instalacion de Tablero de distribucion 24 ctos- 220v-3-5 H, Certificado, Suministro e instalacion de Tablero de distribucion 18 ctos- 220v-3-5 H, Certificado, Suministro e instalacion de Tablero de distribucion 8 ctos- 220v-3-5 H, Certificado, SUBESTACION DE DISTRIBUCION Y REDES DE MEDIA TENSION PROTECCIONES SUMINISTRO E INSTALACION DE SUBESTACION TIPO SECO EN GABINETE 400KVA-13,2KV/220V GRADO IP5 SUMINISTRO E INSTALACION DE RED DISTRIBUCION 13,2KV EN CONDUTOR 1/0 ACSR INCLUYE MEDIDA SUMINISTRO E INSTALACION DE ACOMETIDA TRIFASICA SUBTERRANEA 13,2 KV EN CABLE XLP 1/0 COBRE SUMINISTRO E INSTALACION TERMINALES PREMOLDEADAS TIPO EXTERIOR Y INTERIOR 13,2 KV EN CABLE XLP 1/0 COBRE ACOMETIDAS, BANDEJAS PORTACABLES PARA VOZ Y DATO, BANDEJAS PARA CONDUCTORES ELECTRICOS SUMINISTRO E INSTALACION DE ACOMETIDA 220V 3x3 # 500kcm EN CARCAMO DE 50X50X50CM INTERNA SUMINISTRO E INSTALACION DE ACOMETIDA 220V 1x3 # 400kcm EN CARCAMO DE 50X50X50CM INTERNA SUMINISTRO E INSTALACION DE ACOMETIDA 220V 3x3 # 300kcm EN CARCAMO DE 50X50X50CM INTERNA SUMINISTRO E INSTALACION DE ACOMETIDA 220V 3x1 # 300kcm EN CARCAMO DE 50X50X50CM INTERNA SUMINISTRO E INSTALACION DE ACOMETIDA 220V 3x1 # 2 AWG EN TUBO PVC 1 1/2" SUBTERRANEO SUMINISTRO E INSTALACION DE ACOMETIDA 220V 3x1 # 4 AWG EN TUBO PVC 1 1/2" SUBTERRANEO SUMINISTRO E INSTALACION DE ACOMETIDA 220V 2x1 # 6 AWG EN TUBO PVC 1 " SUBTERRANEO SUMINISTRO E INSTALACION DE ACOMETIDA 220V 2x1 # 8 AWG EN TUBO PVC 3/4 " SUBTERRANEO SUMINISTRO E INSTALACION DE ACOMETIDA 220V 3x1 # 8 AWG EN TUBO PVC 1 " SUBTERRANEO SUMINISTRO E INSTALACION DE ACOMETIDA 220V 3x1 # 10 AWG EN TUBO PVC 3/4 " SUBTERRANEO SUMINISTRO E INSTALACION DE ACOMETIDA 220V 1x3 # 400kcm EN TUBO PVC 3" SUMINISTRO E INSTALACION DE ACOMETIDA 220V 1x3 # 250kcm EN TUBO PVC 3" SUMINISTRO E INSTALACION DE BANDEJA TIPO MALLA PARA CABLES DE ENERGIA 54X600mm INCLUYE SOPORTES SUMINISTRO E INSTALACION DE BANDEJA TIPO MALLA PARA VOZ, DATO Y SONIDO 54X600mm INCLUYE SOPORTES RED DE INTERNET, TELEFONIA Y SONIDO 10.42 10.43 Suministro e instalacion salida para red de Voz y datos Suministro e instalacion de pacht panel, swiche concentrador y acsesorios en Rakc GENERADOR DE EMERGENCIA 10.44 Suministro e instalacion planta de emergencia 375 KVA Incluye trasnferencias SUMINISTRO E INSTALACION DE UPS Y TABLERO DE AISLAMIENTO 10.45 10.46 10.47 10.48 10.49 10.50 SUMINISTRO E INSTALACION DE UPS 10 KVA BIFASICA SUMINISTRO E INSTALACION DE UPS 25 KW TRIFASICA SUMINISTRO E INSTALACION DE UPS 3 KVA BIFASICA SUMINISTRO E INSTALACION DE UPS 5 KVA BIFASICA SUMINISTRO E INSTALACION DE TABLERO DE AISLAMIENTO 3KVA-2F-4H SUMINISTRO E INSTALACION DE TABLERO DE AISLAMIENTO 5KVA-2F-4H CONSTRUCCION DE SISTEMA DE PUESTA A TIERRA 10.51 10.52 SUMINISTRO E INSTALACION DE SISTEMA DE PUESTA A TIERRA SUB ESTACION un CASETA SUBESTACION NORMA EPM 6m x 12m mas 2m x 2m combustible m2 1.00 76.00 3,200,000.00 1,000,000.00 3,200,000.00 76,000,000.00 un un un un un un 1.00 1.00 3.00 3.00 10.00 5.00 20,475,000.00 36,137,500.00 5,175,000.00 9,675,000.00 15,137,500.00 30,206,250.00 20,475,000.00 36,137,500.00 15,525,000.00 29,025,000.00 151,375,000.00 151,031,250.00 un 2.00 230,946,750.00 un un 84.00 3.00 179,900.00 2,701,250.00 15,111,600.00 8,103,750.00 0.00 461,893,500.00 UNIDAD Un Un Un Un Un Un Un Un Un Un Un CANTIDAD 1.00 1.00 1.00 1.00 1.00 1.00 1.00 1.00 2.00 9.00 2.00 VALOR UNITARIO 3,520,000.00 20,737,500.00 3,445,000.00 2,340,000.00 2,592,500.00 13,863,750.00 25,034,250.00 1,116,250.00 831,250.00 641,250.00 451,250.00 VALOR TOTAL 3,520,000.00 20,737,500.00 3,445,000.00 2,340,000.00 2,592,500.00 13,863,750.00 25,034,250.00 1,116,250.00 1,662,500.00 5,771,250.00 902,500.00

10.24 10.25 10.26 10.27

Un Un ML UN

1.00 1.00 120.00 9.00

71,785,500.00 49,176,200.00 139,500.00 836,750.00

71,785,500.00 49,176,200.00 16,740,000.00 7,530,750.00

10.28 10.29 10.30 10.31 10.32 10.33 10.34 10.35 10.36 10.37 10.38 10.39 10.40 10.41

ML ML ML ML ML ML ML ML ML ML ML ML ML ML

12.00 10.00 35.00 16.00 125.00 105.00 208.00 950.00 70.00 500.00 30.00 75.00 310.00 250.00

1,315,175.00 403,575.00 877,875.00 414,875.00 80,325.00 58,225.00 35,910.00 28,500.00 32,100.00 24,350.00 264,575.00 184,075.00 118,875.00 118,875.00

15,782,100.00 4,035,750.00 30,725,625.00 6,638,000.00 10,040,625.00 6,113,625.00 7,469,280.00 27,075,000.00 2,247,000.00 12,175,000.00 7,937,250.00 13,805,625.00 36,851,250.00 29,718,750.00

GOBERNACION DE CORDOBA SECRETARIA DE INFRAESTRUCTURA CONSTRUCCIN Y DOTACIN DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E HOSPITAL SAN JERONIMO DE MONTERIA PRESUPUESTO OFICIALITEM DESCRIPCION UNIDAD CANTIDAD VALOR UNITARIO VALOR TOTAL

CAPITULO 11: INSTALACIONES HIDROSANITARIAS RED AGUAS SANITARIAS 11.1 Suministro e instalacion de tuberia para red exterior aguas residuales 6", incluye excavacin, material granular para cimentacin de la tuberia. Suministro, transporte e instalacin de tubera PVC-S 4" para aguas residuales. Incluye limpiador, soldadura, accesorios como codos, yees, tees, abrazaderas y todos los elementos necesarios para su correcta instalacin y funcionamiento. Suministro, transporte e instalacin de tubera PVC-S 2" para aguas residuales. Incluye limpiador, soldadura, accesorios como codos, yees, tees, abrazaderas y todos los elementos necesarios para su correcta instalacin y funcionamiento. Salidas sanitarias en tuberia PVC-S para desagues de piso. Incluye 1.50 ml de tuberia, limpiador, soldadura, rejilla en bronce latn de 3" x 2", accesorios y todos los elementos necesarios para su correcta instalacin y funcionamiento. Salidas sanitarias en tuberia PVC-S 4". Incluye 1.50 ml de tuberia, limpiador, soldadura, abrazadera, accesorios y todos los elementos necesarios para su correcta instalacin y funcionamiento. Salidas sanitarias en tuberia PVC-S 2". Incluye 1.50 ml de tuberia, limpiador, soldadura, abrazadera, accesorios y todos los elementos necesarios para su correcta instalacin y funcionamiento. Suministro y colocacion de Bajante aguas residuales 4" Construccin de caja de inspeccin de 0,80 x 0,80 m. Incluye tapa y herraje. RED DE AGUAS LLUVIAS 11.9 11.10 11.11 11.12 11.13 Suministro e instalacion de tuberia para red exterior aguas lluvias 8", incluye excavacin, material granular para cimentacin de la tuberia. Suministro e instalacion de tuberia para red exterior aguas rlluvias 6", incluye excavacin, material granular para cimentacin de la tuberia. Suministro e instalacion de tuberia para red exterior aguas lluvias 4", incluye excavacin, material granular para cimentacin de la tuberia. Suministro y colocacion de Bajante aguas lluvias 4" Construccin de caja de inspeccin de 0,80 x 0,80 m. Incluye tapa y herraje. RED HIDRAULICA Suministro, trasnporte y colocacin de tubera interiores de acueducto. = ". = ". = 1. ". = 1". = 2". Suministro, transporte e instalacin de vlvula Red White, de cierre 1" Suministro, transporte e instalacin de valvula Red White, cierre 3/4" Suministro e instalacin de salidas 1/2" para aparatos como lavamanos, bocamangueras, duchas, lavaescobas y todas las salidas que se generen en el desarrollo de la obra. Suministro e instalacin de salidas 1" para sanitarios Suministro e instalacion de llave terminal para jardin de PVC para intalaciones ML ML ML ML ML UN UN 11.06 99.19 34.46 339.75 111.80 36.00 4.00 5,258.20 5,954.01 21,119.03 9,015.05 38,497.95 72,653.00 56,003.00 58,155.65 590,577.77 727,761.83 3,062,862.97 4,304,070.35 2,615,508.00 224,012.00 ML ML ML ML UN 31.61 57.57 90.67 314.00 5.00 91,321.62 77,558.08 26,346.45 19,514.13 314,317.12 2,886,676.25 4,465,018.73 2,388,832.98 6,127,435.67 1,571,585.59 ML 84.82 77,558.08 6,578,476.44

11.2

ML

422.30

26,346.45

11,126,107.49

11.3

ML

224.71

10,438.02

2,345,528.43

11.4

UN

84.00

44,982.51

3,778,530.48

11.5

UN

79.00

70,738.32

5,588,327.56

11.6 11.7 11.8

UN ML UN

133.00 85.00 26.00

47,150.68 23,699.36 314,317.12

6,271,040.89 2,014,445.80 8,172,245.04

11.14 11.15 11.16 11.17 11.18 11.19 11.20

11.21

UN

160.00

18,119.45

2,899,111.62

11.22 11.23

UN UN

78.00 5.00

19,061.66 38,875.00

1,486,809.68 194,375.00

CAPTULO 12: APARATOS HIDROSANITARIOS 12.1 12.2 12.3 12.4 Suministro y colocacin de sanitario con fluxometro. Suministro y colocacin de sanitario infantil. Incluye: taza, tanque, tapa, mueble, grifera y valvula fluidmaster y llave de regulacin cromada de " calidad Grival. Suministro y colocacin de orinal Suministro y colocacion de lavamanos sobreponer de accionar electrnicamente (de sensor). Incluye: lavamanos, griferia manos libres y 1 mt meson marmol Suministro y colocacin mesn en lmina de acero inoxidable calibre 18 referencia AISI-304 ancho 60 cm, con salpicadero o espaldar de altura 0.12 m. Incluye: Babero o solapa frontal en acero inoxidable de 20 cm de altura. Pozuelo incorporado al mesn de 0.60 x 0.40 x profundidad variable entre 0.25 m.- 0.40 m. Las esquinas del mesn sern redondeadas, canastilla de 4" plstica y conexin a red A.R. con sifn registro en p.v.c de 2", pie de amigos de apoyo en acero inoxidable cada metro lineal y refuerzo internos de apoyo con tiras en acero inoxidable calibre 20. Suministro y colocacion de divisiones en acero inoxidable en unidades sanitarias publicas Teleducha UN UN UN UN 55.00 2.00 2.00 24.00 1,080,527.80 389,015.91 604,315.91 1,860,953.60 59,429,029.26 778,031.81 1,208,631.81 44,662,886.49

12.5

ML

119.70

307,750.00

36,837,675.00

12.6 12.7

M2 UN

56.00 2.00

407,750.00 121,775.00

22,834,000.00 243,550.00

CAPTULO 13: GASES MEDICINALES

Suministro e instalacin de Tubera de cobre Tipo K, soportada, pintada, marcada, soldada y probada en los siguientes dimetros: (Incluye accesorios)

GOBERNACION DE CORDOBA SECRETARIA DE INFRAESTRUCTURA CONSTRUCCIN Y DOTACIN DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E HOSPITAL SAN JERONIMO DE MONTERIA PRESUPUESTO OFICIALITEM 13.1 13.2 13.3 13.4 13.5 13.6 13.7 13.8 Flexible de 5/8" Rgida de 1/2" Rgida de 3/4" Rgida de 1" Rgida de 1 1/4" Rgida de 1 1/2" Rgida de 2" Rgida de 2 1/2" Totales TUBERIA Suministro e instalacin de Vlvula de tres cuerpos, en acero inoxidable, desmontable, cuatro tornillos, soldada en sus extremos en los siguientes dimetros: 13.9 13.10 13.11 13.12 1/2" 3/4" 1" 1 1/4" Totales VLVULAS Suministro e instalacin de Caja de control de zona, Nacional, con vlvulas de tres cuerpos, desmontable, en acero inoxidable, soldada en sus extremos tapa acrlica de los siguientes casos: 13.13 13.14 13.15 2 Gases 3 Gases 4 Gases Totales CAJAS DE CONTROL Suministro e instalacin de Alarma Importada para monitoreo constante de Gases 13.16 13.17 13.18 Alarma de rea de 2 Gases Alarma de rea de 3 Gases Alarma Combinada 4 Gases 10 Puntos Totales ALARMAS Suministro e instalacin de Tomas para Gases Medicinales, Importadas, con doble cheque, de pared QC y cielticas DISS. 13.19 13.20 13.21 13.22 Tomas QC de Oxgeno Tomas QC de xido nitroso Tomas QC de Aire Tomas QC de Vaco Totales TOMAS DE GASES Suministro e Instalacin de Manifold para la distribucin de Gases Medicinales, Importados 13.23 13.24 13.25 13.26 Manifold semi automtico Oxgeno 10x10 Cilindros Manifold simplex Aire 1x12 Cilindros Manifold semi Automtico de xido Nitroso 1x1 Totales MANIFOLD Suministro e Instalacin Compresor de Aire Medicinal de 10 HP Duplex con capacidad de producir 36,7 scfm@ 50psig por cabeza, tanque de 200 galones 13.27 Totales Produccin Aire Medicinal Suministro e Instalacin Bomba de vaco de 7,5 HP Duplex con capacidad de producir 52,0 scfm@ 19"Hg por cabeza, tanque de 200 galones. 13.28 Totales Produccin vaco Medicinal un 1.00 1.00 61,644,000.00 61,644,000.00 un un un un 1.00 1.00 1.00 3.00 1.00 105,380,000.00 105,380,000.00 13,930,000.00 7,400,000.00 7,360,000.00 13,930,000.00 7,400,000.00 7,360,000.00 un un un un 142.00 2.00 79.00 142.00 165,000.00 165,000.00 165,000.00 165,000.00 23,430,000.00 330,000.00 13,035,000.00 23,430,000.00 un un un 1.00 1.00 1.00 3.00 3,955,000.00 5,266,000.00 7,467,000.00 3,955,000.00 5,266,000.00 7,467,000.00 un un un 3.00 3.00 1.00 7.00 527,100.00 806,190.00 795,636.00 1,581,300.00 2,418,570.00 795,636.00 un un un un 80.00 40.00 1.00 1.00 122.00 82,700.00 105,525.00 143,400.00 168,000.00 6,616,000.00 4,221,000.00 143,400.00 168,000.00 DESCRIPCION UNIDAD ml ml ml ml ml ml ml ml CANTIDAD 186.90 798.00 864.15 400.05 231.00 218.40 113.40 131.25 2,943.15 VALOR UNITARIO 32,100.00 32,100.00 50,891.00 66,842.00 91,762.00 108,238.00 152,880.00 234,946.00 VALOR TOTAL 5,999,490.00 25,615,800.00 43,977,457.65 26,740,142.10 21,197,022.00 23,639,179.20 17,336,592.00 30,836,662.50

CAPTULO 14: RED CONTRA INCENDIOS

150,000,000.00

CAPTULO 15: SISTEMA DE AIRE ACONDICIONADO SISTEMA AIRE ACONDICIONADO PUESTA EN SITIO, INSTALACION Y ARRANQUE DE ENFRIADOR DE AGUA CONDENSADO CON AIRE DE 50 TR A 220 3 FASES MARCA TRANE, CARRIER O YORK ENFRIADOR DE AGUA CONDENSADO CON AIRE DE 70 TR A 220 3 FASES MARCA TRANE, CARRIER O YORK BOMBA MONOBLOW DE 220 3F DE 20 HP EQUIPOS 15.4 15.5 15.6 15.7 15.8 FANCOIL DE AGUA HELADA DE 2TR TRANE, CARRIER O YORK FANCOIL DE AGUA HELADA DE 3TR TRANE, CARRIER O YORK FANCOIL DE AGUA HELADA DE 4TR TRANE, CARRIER O YORK MANEJADORA DE AGUA HELADA DE 1 TR 3F 220V TRANE, CARRIER O YORK MANEJADORAS DE AGUA HELADA DE 4 TR 3F 220V TRANE, CARRIER O YORK UN UN UN UN UN 1.00 2.00 2.00 1.00 4.00 3,074,000.00 3,456,800.00 3,712,000.00 5,568,000.00 14,812,040.00 3,074,000.00 6,913,600.00 7,424,000.00 5,568,000.00 59,248,160.00

15.1 15.2 15.3

UN UN UN

2.00 1.00 3.00

114,492,000.00 146,160,000.00 11,600,000.00

228,984,000.00 146,160,000.00 34,800,000.00

GOBERNACION DE CORDOBA SECRETARIA DE INFRAESTRUCTURA CONSTRUCCIN Y DOTACIN DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E HOSPITAL SAN JERONIMO DE MONTERIA PRESUPUESTO OFICIALITEM 15.9 15.10 15.11 15.12 15.13 15.14 15.15 15.16 15.17 15.18 15.19 15.20 15.21 15.22 15.23 15.24 15.25 15.26 15.27 15.28 15.29 15.30 15.31 15.32 15.33 15.34 15.35 15.36 15.37 15.38 15.39 15.40 15.41 15.42 15.43 DESCRIPCION MANEJADORAS DE AGUA HELADA DE 5 TR 3F 220V TRANE, CARRIER O YORK MANEJADORAS DE AGUA HELADA DE 10 TR 3F 220V TRANE, CARRIER O YORK MANEJADORAS DE AGUA HELADA DE 25 TR 3F 220V TRANE, CARRIER O YORK FILTROS HEPA DE 99% DE EFICIENCIA PREFILTROS MANOMETRO MAGNAHELIE EXTRACTORES VEL 1 50 CFM VEL 1 100 CFM VEL 1 150 CFM VEL 1 200 CFM VEL 1 250 CFM VEL 1 300 CFM VEL 1 400 CFM VEL 1 450 CFM VEL 1 550 CFM VEL 1 750 CFM VEL 1 1000 CFM MANMETROS Y TERMMETROS PARA LA RED DE AGUA HELADA MANOMETRO 0-160 PSIg TERMOMETRO DE BULBO TERMOSTATO PROPORCIONAL DE AMBIENTE RABO DE PUERCO CON SU VALVULA DE 1/4 PARA MANOMETRO VALVULAS EN GENERAL PARA LA RED DE AGUA HELADA VALVULA COMPUERTA DE 3 VALVULA GLOBO DE 3 VALVULA COMPUERTA DE 2 VALVULA GLOBO DE 2 VALVULA COMPUERTA DE 1 VALVULA GLOBO DE 1 VALVULA COMPUERTA DE 3/4 VALVULA GLOBO DE 3/4 VALVULA DE 3 VIAS 1 VALVULA DE 3 VIAS 3/4 CHEQUES 3 FILTROS ELIMINADORES DE VIBRACION DUCTERIA LAMINA GALVANIZADA RECUBIERTA EN DUC WRAP DUCTERIA LAMINA GALVANIZADA RECUBIERTA CON DUC WRAP DIFUSORES DE SUMINISTRO DIFUSOR DE TECHO CON ELEMENTO CENTRAL REMOVIBLE Y DAMPER ALETA OPUESTA DF 4V CD 8*6 DF 4V CD 8*8 DF 4V CD 12*12 DF 4V CD 14*14 DF 4V CD 16*16 DF 4V CD 18*18 REJILLAS DE RETORNO Y/O EXTRACCION TIPO CUBO 15.51 15.52 15.53 15.54 15.55 15.56 15.57 15.58 15.59 15,60. 15.61 15.62 15.63 15.64 15.65 15.66 RRTC 6*6 RRTC 8*6 RRTC 10*8 RRTC 14*12 RRTC 18*16 RRTC 12*12 RRTC 24*24 RRTC 34*30 RRTC 40*36 REJILLAS TOMA AEREA EXTERIOR LRF CD 4*4 LRF CD 8*8 LRF CD 14*12 LRF CD 10*8 LRF CD 6*6 LRF CD 20*20 LRF CD 24*24 TUBERIAS Y ACCESORIOS EN PVC RIGIDO RDE21 PARA AGUA HELADA. CON AISLAMIENTO TERMICO EN POLIURETANO Y ALUMINIO 15.67 15.68 15.69 TUBERIA DE 3 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA TUBERIA DE 2 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA TUBERIA DE 2 1/2 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA ML ML ML 219.00 177.00 13.00 85,613.80 68,793.80 61,897.60 18,749,422.20 12,176,502.60 804,668.80 UN UN UN UN UN UN UN 2.00 6.00 2.00 3.00 2.00 4.00 2.00 32,490.79 32,480.00 70,760.00 35,960.00 32,480.00 158,920.00 225,040.00 64,981.58 194,880.00 141,520.00 107,880.00 64,960.00 635,680.00 450,080.00 UN UN UN UN UN UN UN UN UN 59.00 4.00 2.00 9.00 3.00 20.00 4.00 3.00 15.00 35,960.00 44,080.00 59,160.00 102,080.00 174,000.00 89,320.00 321,320.00 402,520.00 780,680.00 2,121,640.00 176,320.00 118,320.00 918,720.00 522,000.00 1,786,400.00 1,285,280.00 1,207,560.00 11,710,200.00 M2 2,524.00 127,600.00 322,062,400.00 UN UN UN UN UN UN UN UN UN UN UN UN UN 7.00 6.00 7.00 7.00 7.00 7.00 6.00 6.00 14.00 4.00 3.00 3.00 3.00 1,248,624.00 1,673,590.00 370,040.00 494,508.00 100,920.00 73,370.00 104,052.00 73,370.00 167,240.68 267,774.40 388,878.40 755,970.84 151,380.00 8,740,368.00 10,041,540.00 2,590,280.00 3,461,556.00 706,440.00 513,590.00 624,312.00 440,220.00 2,341,369.52 1,071,097.60 1,166,635.20 2,267,912.52 454,140.00 UN UN UN UN 23.00 23.00 15.00 23.00 155,277.60 406,603.20 213,440.00 26,013.00 3,571,384.80 9,351,873.60 3,201,600.00 598,299.00 UN UN UN UN UN UN UN UN UN UN UN 4.00 5.00 4.00 2.00 1.00 1.00 1.00 1.00 2.00 2.00 2.00 330,600.00 330,600.00 330,600.00 668,160.00 668,160.00 668,160.00 932,640.00 932,640.00 932,640.00 970,050.00 1,067,200.00 1,322,400.00 1,653,000.00 1,322,400.00 1,336,320.00 668,160.00 668,160.00 932,640.00 932,640.00 1,865,280.00 1,940,100.00 2,134,400.00 UNIDAD UN UN UN UN UN UN CANTIDAD 1.00 1.00 6.00 40.00 18.00 18.00 VALOR UNITARIO 14,940,800.00 20,137,600.00 38,976,000.00 1,730,720.00 110,200.00 570,720.00 VALOR TOTAL 14,940,800.00 20,137,600.00 233,856,000.00 69,228,800.00 1,983,600.00 10,272,960.00

15.44 15.45 15.46 15.47 15.48 15.49 15,50.

0.00 UN UN UN UN UN UN 16.00 56.00 58.00 17.00 14.00 14.00 56,840.00 71,920.00 106,720.00 132,240.00 162,400.00 186,760.00 909,440.00 4,027,520.00 6,189,760.00 2,248,080.00 2,273,600.00 2,614,640.00

GOBERNACION DE CORDOBA SECRETARIA DE INFRAESTRUCTURA CONSTRUCCIN Y DOTACIN DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E HOSPITAL SAN JERONIMO DE MONTERIA PRESUPUESTO OFICIALITEM 15,70. 15.71 15.72 15.73 15.74 15.75 15.76 15.77 15.78 15.79 15,80. 15.81 15.82 15.83 15.84 15.85 15.86 15.87 DESCRIPCION TUBERIA DE 1 1/4 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA TUBERIA DE 1 1/2 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA TUBERIA DE 1 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA TUBERIA DE 3/4 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA TEE DE 3 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA TEE DE 2 1/2 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA TEE DE 2 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA TEE DE 1 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA TEE DE 1 1/2 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA TEE DE 1 1/4 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA CODO DE 3 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA CODO DE 2 1/2 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA CODO DE 2 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA CODO DE 1 DIAMETRO EN PVC PARA CIRCUITO AGUA HELADA BUJES Y MATERIALES PRIMER PISO BUJES Y MATERIALES SEGUNDO Y TERCERO TANQUE DE EXPANSION TANQUE PULMON O DE EXPANSION DE 500 LTS Y ACCESORIOS TBERIA DE SUMINISTRO DE 3 PVC PUESTA EN SITIO, INSTALACION Y ARRANQUE DE SISTEMA DE BOMBEO 15.88 INSTALACION DELSISTEMA DE BOMBEO PRINCIPAL Y PRUEBAS BALANCEO DE LOS SISTEMAS DE AIRE AGUA HELADA PRUEBA HIDROSTATICA Y BALANCEO DEL SISTEMA DE AGUA HELADA PRIMER PISO PRUEBA HIDROSTATICA Y BALANCEO DEL SISTEMA DE AGUA HELADA SEGUNDO Y TERCER PISO INGENIERIA E INSTALACION 15.91 LABOR DE INGENIERIA E INSTALACION DEL SISTEMA IZADA Y TRANALADO VERTICAL 15.92 IZADA DE EQUIPO CON GRUA Y MONTACARGA, TRANSPORTES, FLETES GL 3.00 11,600,000.00 34,800,000.00 GL 3.00 11,600,000.00 34,800,000.00 GL 3.00 11,600,000.00 34,800,000.00 UN ML 3.00 27.00 3,016,000.00 85,613.80 9,048,000.00 2,311,572.60 UNIDAD ML ML ML ML UN UN UN UN UN UN UN UN UN UN gl gl CANTIDAD 10.00 17.00 275.00 77.00 10.00 1.00 6.00 1.00 3.00 2.00 16.00 3.00 3.00 11.00 1.00 2.00 VALOR UNITARIO 112,694.00 59,206.40 55,506.00 47,560.00 90,003.24 81,055.00 54,741.56 45,240.00 41,760.00 43,878.16 89,987.00 65,598.00 52,695.32 39,695.20 5,800,000.00 9,280,000.00 VALOR TOTAL 1,126,940.00 1,006,508.80 15,264,150.00 3,662,120.00 900,032.40 81,055.00 328,449.36 45,240.00 125,280.00 87,756.32 1,439,792.00 196,794.00 158,085.96 436,647.20 5,800,000.00 18,560,000.00

15.89 15.90

GL GL

1.00 2.00

17,400,000.00 11,600,000.00

17,400,000.00 23,200,000.00

CAPTULO 16: ASCENSOR CAMERO PUERTA 1.20 M Suministro e instalacion de ascensor camero puerta de 120 cm de 4 paradas ANDINO U SIMILAR

16.1

GL

1.00

83,180,000.00

83,180,000.00

CAPTULO 17: MANTENIMIENTO HABITACIONES MATERNAS E INFANTILES BLOQUE B 17.1 17.2 17.3 17.4 17.5 17.6 17.7 17.8 17.9 17.10 SUMINISTRO Y APLICACION A LLANA DE ESTUCO ACRILICO EN PASTA TIPO INTERIOR CALIDAD PINTUCO O TEXTUCO SOBRE MUROS 10,484,460.00 M2 2,385.00 4,396.00 APLICACION PINTURA TIPO 1 EN SUPERFICIES ESTUCADAS INTERNAS. DOS MANOS M2 SUMINISTRO Y COLOCACION DE BALDOSIN CERAMICO 20x20 cm EN MUROS DE BAOS M2 SUMINISTRO Y COLOCACION DE BALDOSIN CERAMICO 20x20 cm EN PISOS DE BAOS M2 BRILLADA DE BALDOSA EN GRANO PULIDO M2 2,385.00 900.00 157.50 990.00 7,984.00 44,986.00 44,986.00 7,701.00 19,041,840.00 40,487,400.00 7,085,295.00 7,623,990.00

22,050,000.00 SUMINISTRO E INSTALACION BARRA LATERAL DE INODORO PARA DISCAPACITADOS SENCILLA 60 cm INCLUYE SOPORTES, BASES DE FIJACION AL MURO Y TORNILLOS DE F UN 45.00 490,000.00 18,176,850.00 SUMINISTRO E INSTALACION DE UNIDADES SANITARIAS LAVAMANOS REF. AQUAJET CORONA U SIMILAR45.00 UN 0 Y SANITARIO AS ELONGADO BL (ARO PARTIDO) 403,930.00 SUMINISTRO DE LAMPARA FLUORESCENTE CIELO RASO SUSPENDIDO EN DRYWALL UN M2 90.00 1,170.00 45.00 95,000.00 87,238.00 3,100,000.00 8,550,000.00 102,068,460.00 139,500,000.00 8,419,788,813.0 15% 5% 10% 30% 1,262,968,322.0 420,989,441.0 841,978,881.0 2,525,936,644.0 10,945,725,457.0 2,505,716,000.0 13,451,441,457.0

SUMINISTRO E INSTALACION DE SISTEMA DE AIRE ACONDICIONADO 24.000 BTU MINI SPLIT UN

VALOR TOTAL COSTO DIRECTO ADMINISTRACIN IMPREVISTOS UTILIDAD VALOR COSTOS INDIRECTOS DEL PROYECTO (AIU) VALOR TOTAL OBRA CIVIL VALOR ADQUISICION DE EQUIPOS VALOR TOTAL INVERSION

SALARIO MINIMO SALARIO MINIMO AUXILIO TRANPORTE PRESTACIONES CESANTIA MENSUAL PRIMA VACACIONES INTERESES CESANTIA MENSUAL APORTES SENA APORTE ORDINARIO FIC (un SMMLV por cada 40 trabajadores) 2.00% 2.50% 10.00% 8.33% 4.17% 12%*(10%*(SAL+AUX)) OTROS APORTES ICBF CAJA COMP. FAMILIAR 535,600 63,600 SEGURIDAD PENSION SALUD RIESGOS

MANO DE OBRA POR OCUPACION / HORA Ayudante raso Ayudante entendido Oficial 2a Obra Negra Ayudante raso Oficial 1a Obra Negra Operador Equipo Mediano Oficial 1a Obra Blanca Oficial de Plomeria

BASICO MES 535,600 623,663 768,480 535,600 928,337 938,807 864,116 928,337

AUX. SALARIO + AUX. TRANSPORTE TRANSPORTE 63,600 599,200 63,600 687,263 63,600 832,080 63,600 599,200 63,600 991,937 63,600 1,002,407 63,600 927,716 63,600 991,937

MANO DE OBRA POR ACTIVIDAD / UNIDAD MEDIDA

UND

VALOR ACTIVIDAD SIN PRESTACIONES

MANO DE OBRA INSTALACION SANITARIO MANO DE OBRA CARGUE VOLQUETA Y BOT. ESCOMBROS CORTE Y FIG. DE REFUERZO COLOCACION DE REFUERZO MANO DE OBRA ARMADA ESTRUC. METALICA CONST. MURO BLOQUE MANO DE OBRA MURO DRYWALL MANO DE OBRA CIELO RASO DRYWALL MANO DE OBRA CIELO RASO PLACAS MANO DE OBRA INSTAL. CUBIERTA CLIMATIZADA MANO DE OBRA ENCHAPE CER COLOCACION PISO BALDOSA PULIDA PISO BRILLADA PISO MANO DE OBRA COLOC. ZOC.GR. PULIDO

UND M3 KG KG KG UND M2 M2 M2 M2 M2 M2 M2 M2 ML

12,807 5,386 324 281 3,332 599 15,142 15,000 12,979 3,332 11,954 7,679 5,668 7,701 6,403

7,074 2,975 179 155 1,840 331 8,364 8,285 7,169 1,840 6,603 4,242 3,130 4,254 3,537

MANO DE OBRA COLOC. MEDIA CANA MANO DE OBRA INSTALACION PUERTAS MANO DE OBRA INSTALACION VENTANAS MANO DE OBRA INSTALACION BARRA DISCAPACITADOS MANO DE OBRA INSTALACION GUARDACAMILLAS MANO DE OBRA INSTALACION VALVULAS MANO DE OBRA INSTALACION LLAVE JARDIN MANO DE OBRA INSTAL. SANITARIO FLUXOMETRO MANO DE OBRA INSTALACION LAVAMANOS SOBREPONER MANO DE OBRA INSTALACION MESON ACERO MANO DE OBRA INSTALACION DIVISION ACERO MANO DE OBRA INSTALACION TELEDUCHA

ML M2 M2 UND ML UND UND UND UND ML ML UND

7,905 15,000 14,000 50,000 10,000 4,500 7,500 35,000 25,000 55,000 55,000 7,500

4,366 8,285 7,733 27,617 5,523 2,486 4,143 19,332 13,808 30,378 30,378 4,143

Notas *Para Salarios Bsicos mayores a 2 SMMLV no se debe incluir el subsidio de transporte ni la dotaci *El valor de la dotacin es considerado a partir de los precios comerciales de los implementos y no *Durante el perodo de disfrute de vacaciones no se paga el subsidio de transporte. *El pago del FIC es un salario mnimo mensual legal vigente por cada 40 trabajadores o proporcionFUENTE CAMACOL ANTIOQUIA 2011

DOTACION 12.00% 8.50% 6.96% DOTACION BOTAS Y OVEROL $ VALOR COMERCIAL 90,000

3.00% 4.00%

PRESTACIONES SEG. SOCIAL 139,358 160,229 194,551 139,358 232,437 234,918 217,217 232,437 147,076 171,258 211,025 147,076 254,921 257,796 237,286 254,921

AP. SENA 24,102 25,863 28,760 24,102 31,957 32,166 30,672 31,957

OTROS TOTAL DOTACION TOTAL MES APORTES DIA 37,492 22,500 969,728 32,324 43,656 22,500 1,088,270 36,276 53,794 22,500 1,320,209 44,007 37,492 22,500 947,228 31,574 64,984 22,500 1,576,236 52,541 65,716 22,500 1,593,004 53,100 60,488 22,500 1,473,379 49,113 64,984 22,500 1,576,236 52,541

TOTAL HORA 4,041 4,534 5,501 3,947 6,568 6,638 6,139 6,568

PORCENTAJE DE VALOR PRESTACIONES TOTAL SOCIALES ACTIVIDAD 81.05% 5,733 2,411 145 126 1,491 268 6,779 6,715 5,810 1,491 5,351 3,438 3,447 3,447 2,866 12,807 5,386 324 281 3,332 599 15,142 15,000 12,979 3,332 11,954 7,679 6,578 7,701 6,403

3,539 6,715 6,267 22,383 4,477 2,014 3,357 15,668 11,192 24,622 24,622 3,357

7,905 15,000 14,000 50,000 10,000 4,500 7,500 35,000 25,000 55,000 55,000 7,500

nsporte ni la dotacin. s implementos y no puede compensarse en dinero , se entrega en especie. orte. dores o proporcional por fraccin.

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM : OBRA: MATERIALESNOMBRE

DESCAPOTE A MAQUINACONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SANCANTIDADincluye desperdicio

No.

1.1.

UNIDAD:

M3

UNIDAD

PRECIO U.

V/R. TOTAL

0.00 0.00 0.00 0.00 0.00 SUBTOTAL MATERIALES EQUIPODESCRIPCION buld.rip.standar cater d8k-76v TIPO TARIFA/HORA 363,650 RENDIMIENTO V/R UNITARIO

-

0.06

21,819.00

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

0.05

21,819.00 202.05 22,021.05

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

AYUDANTE RASO

1,809

2,232

0.06

4,041.00

242.46

SUBTOTAL MANO DE OBRA

242.46 22,263.51 % 15% 5% 10% VALOR 3,339.53 1,113.18 2,226.35 6,679.05

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES

TOTAL COSTO

TOTAL PRECIO UNITARIO

28,942.56

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

EXC. A MAQ. (h=1-1.5 c. abierto)CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

1.2.

OBRA: MATERIALESNOMBRE

UNIDAD:

M3

UNIDAD

PRECIO U.

V/R. TOTAL

0.00 0.00 0.00 0.00 0.00 SUBTOTAL MATERIALES EQUIPODESCRIPCION buld.rip.standar cater d8k-76v cargador bobcat s175 (con operador) TIPO TARIFA/HORA 363,650 RENDIMIENTO V/R UNITARIO

-

66,200

0.06 0.06 EQUIPO H. MENOR SUBTOTAL EQUIPO

21,819.00 3,972.00 25,791.00 227.00 26,018.00

0.05

TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

AYUDANTE ENTENDIDO

2,029.72

2,504.28SUBTOTAL MANO DE OBRA

0.20

4,534.00

906.80 906.80 26,924.80

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 4,038.72 1,346.24 2,692.48

8,077.44

TOTAL PRECIO UNITARIO

35,002.24

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

LOCALIZACION Y REPLANTEO

No.

1.3.

OBRA: MATERIALESNOMBRE

CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE UNIDAD: MONTERIA.CANTIDADincluye desperdicio

DIA

UNIDAD

PRECIO U.

V/R. TOTAL

clavo corriente

lb

2,500

1.000

2,500 0 0 0 0 2,500.00

SUBTOTAL MATERIALES EQUIPODESCRIPCION equipo topografico TIPO TARIFA/HORA 350,000 RENDIMIENTO V/R UNITARIO

1.00

350,000 0 350,000.00 17,500.00 367,500.00

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA V/R TOTAL

5%

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO

-

V/R TOTAL

SUBTOTAL MANO DE OBRA

370,000.00 % 15% 5% 10% VALOR 55,500 18,500 37,000 111,000.00

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES

TOTAL COSTO

TOTAL PRECIO UNITARIO

481,000.00

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

CASETA EN MADERA (24 M2)CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA. NOMBRE UNIDAD und m3 m3 m3 lb und und und PRECIO U. 28,000 50,000 306,240 35,000 2,500 14,500 29,000 16,250CANTIDADincluye desperdicio

No.

1.4.

OBRA: MATERIALES

UNIDAD:

GB

V/R. TOTAL

teja ond. eternit # 8 gris piedra concr.3500 psi(3/4 pulg ) arenilla triturada clavo corriente 2 pulg can 2x8pulg mad.comun sin cep.(3m) telera 135cmx90cm mad.comun sin cep. media telera135x45cm mad.comun sin cep.

12.00 4.80 2.45 1.21 1.10 16.16 32.32 16.16

336,000.00 240,000.00 749,216.16 42,420.00 2,750.00 234,320.00 937,280.00 262,600.00 0.00 0 2,804,586.16

SUBTOTAL MATERIALES EQUIPODESCRIPCION TIPO TARIFA/HORA RENDIMIENTO V/R UNITARIO

0 0 EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA V/R TOTAL

5%

17,483.72 17,483.72

tte.agregados m3/km

6

1,500

9,000

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO

9,000.00

OFICIAL 2a OBRA NEGRA AYUDANTE ENTENDIDO

2,462.55 2,029.92

3,038.32 2,504.53SUBTOTAL MANO DE OBRA

24.00 48.00

V/R UNITARIO 5,500.87 4,534.45

V/R TOTAL

132,020.88 217,653.60 349,674.48 3,180,744.36

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 477,111.65 159,037.22 318,074.44

954,223.31

TOTAL PRECIO UNITARIO

4,134,967.67

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

BAO PROVISIONAL OBREROS (4 M2)CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

1.5.

OBRA: MATERIALESNOMBRE teja ond. eternit # 8 gris sanitario fluxometro 2650 piedra concr.2500 psi(1.1/2 pulg ) premez. mortero 1:7 en obra lad.perf.hzontal liso 10-20-40 arenilla triturada codo 90-1/4 cxc 4 pulg pavco sifon c/tapon 1.1/2 pulg sanitaria pav tub.concr.u.m. 4 pulg ind.dique

UNIDAD:

GB

UNIDAD und und m3 m3 m3 und m3 und und m

PRECIO U. 28,000 300,000 34,800 258,332 145,456 1,300 18,745 8,658 3,423 7,621

V/R. TOTAL

2.02 1.01 0.80 0.42 0.51 234.60 0.20 1.00 1.00 20.00

56,560.00 303,000.00 27,840.00 108,499.44 73,767.94 304,980.00 3,786.49 8,658.00 3,423.00 152,420.00 1,042,934.87

SUBTOTAL MATERIALES EQUIPODESCRIPCION TIPO TARIFA/HORA RENDIMIENTO V/R UNITARIO

0 0 EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA V/R TOTAL

5%

8,668.62 8,668.62

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO

-

OFICIAL 2a OBRA NEGRA AYUDANTE ENTENDIDO MANO OBRA INST. SANIT

2,462.55 2,029.92 5,733.37

3,038.32 2,504.53 7,073.86SUBTOTAL MANO DE OBRA

16.00 16.00 1.00

V/R UNITARIO 5,500.87 4,534.45 12,807.23

V/R TOTAL

88,013.92 72,551.20 12,807.23 173,372.35 1,224,975.84

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 183,746.38 61,248.79 122,497.58

367,492.75

TOTAL PRECIO UNITARIO

1,592,468.59

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

CERRAMIENTO PROVISIONALCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

1.6

OBRA: MATERIALESNOMBRE Malla de cerramiento verde 2.10m Larguero 2x4pulg mad.comun sin cep.(3m) Clavo corriente

UNIDAD:

ML

UNIDAD m m lb

PRECIO U. 4,293 5,900 2,500

V/R. TOTAL

1.10 1.50 0.20

4,721.99 8,850.00 500.00 14,071.99

SUBTOTAL MATERIALES EQUIPODESCRIPCION TIPO TARIFA/HORA RENDIMIENTO V/R UNITARIO

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

5%

115.62 115.62

V/R TOTAL

tte.agregados m3/km

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO

-

OFICIAL 2a OBRA NEGRA AYUDANTE RASO AYUDANTE ENTENDIDO MANO OBRA INST. SANIT

2,462.55 1,809.02

3,038.32 2,231.98

0.20 0.30

V/R UNITARIO 5,500.87

V/R TOTAL

4,041.00

SUBTOTAL MANO DE OBRA

1,100.17 1,212.30 2,312.47 16,500.09

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 2,475.01 825.00 1,650.01

4,950.03

TOTAL PRECIO UNITARIO

21,450.12

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

ACARREO INTERNO Y EXTERNO MAT. EXCAV.CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

1.7

OBRA: MATERIALESNOMBRE

UNIDAD:

M3

UNIDAD

PRECIO U.

V/R. TOTAL

SUBTOTAL MATERIALES EQUIPODESCRIPCION TIPO TARIFA/HORA RENDIMIENTO V/R UNITARIO

0.00

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

5%

0.00 471.35 471.35

V/R TOTAL

Tte. A botadero oficial

1

12,602

12,602

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO

12,602.00

AYUDANTE RASO MANO DE OBRA CARGUE VOLQUETA

1,809.02 2,411.13

2,231.98 2,974.87SUBTOTAL MANO DE OBRA

1.00 1.00

V/R UNITARIO 4,041.00 5,386.00

V/R TOTAL

4,041.00 5,386.00 0.00 9,427.00 22,500.35

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 3,375.05 1,125.02 2,250.04

6,750.11

TOTAL PRECIO UNITARIO

29,250.46

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

EXCAVACION MANUAL 0-1.50 MTCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

2.1.

OBRA: MATERIALESNOMBRE

UNIDAD:

M3

UNIDAD

PRECIO U.

V/R. TOTAL

SUBTOTAL MATERIALES EQUIPODESCRIPCION TIPO TARIFA/HORA RENDIMIENTO V/R UNITARIO

-

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

0.05

627.89 627.89

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

AYUDANTE RASO AYUDANTE ENTENDIDO

1,809.02 2,029.92

2,231.98 2,504.53 SUBTOTAL MANO DE OBRA

1.20 1.70

4,041.00 4,534.45

4,849.20 7,708.57 12,557.77 13,185.65

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 1,977.85 659.28 1,318.57

3,955.70

TOTAL PRECIO UNITARIO

17,141.35

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

RELLENO EN RECEBOCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

2.3.

OBRA: MATERIALESNOMBRE Material de lleno

UNIDAD:

M3

UNIDAD m3

PRECIO U. 18,745

V/R. TOTAL

1.30

24,368.50

SUBTOTAL MATERIALES EQUIPODESCRIPCION vibrocompactador (rana) TIPO TARIFA/HORA 21,500 RENDIMIENTO 0.19 V/R UNITARIO

24,368.50

4,042.00

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

5%

4,042.00 325.39 4,367.39

V/R TOTAL

acarreo interno material

1

3,231

3,230.81

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO

3,230.81

V/R TOTAL

AYUDANTE RASO AYUDANTE ENTENDIDO

1,766.84 2,029.92

2,179.94 2,504.53SUBTOTAL MANO DE OBRA

0.50 1.00

3,946.78 4,534.45

1,973.39 4,534.45 6,507.84 38,474.54

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 5,771.18 1,923.73 3,847.45

11,542.36

TOTAL PRECIO UNITARIO

50,016.90

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

SOLADO E=5CMCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

3.1.

OBRA: MATERIALESNOMBRE concr.1500 psi

UNIDAD:

M2

UNIDAD m3

PRECIO U. 242,324

V/R. TOTAL

0.05

12,722.01

SUBTOTAL MATERIALES EQUIPODESCRIPCION TIPO TARIFA/HORA RENDIMIENTO V/R UNITARIO

12,722.010

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

0.05

235.920 235.920

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

OFICIAL OBRA NEGRA AYUDANTE ENTENDIDO

2,940.12 2,029.92

3,627.53 2,504.53SUBTOTAL MANO DE OBRA

0.43 0.43

6,567.65 4,534.45

2,791.251 1,927.141 4,718.393 17,676.322

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 2,651.45 883.82 1,767.63

5,302.897

TOTAL PRECIO UNITARIO

22,979.219

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

CONST. PILOTESCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

3.2.

OBRA: MATERIALESNOMBRE concr.3000 psi

UNIDAD:

M3

UNIDAD m3

PRECIO U. 280,024

V/R. TOTAL

1.10

308,026.40

SUBTOTAL MATERIALES EQUIPODESCRIPCION malacate pluma 250 kg TIPO

308,026.40

dia

TARIFA/HORA 36,400.00

RENDIMIENTO

V/R UNITARIO

0.65

24,375.00

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

0.05

24,375.00 4,451.32 28,826.32

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

OFICIAL DE 1a OBRA NEGRA AYUDANTE ENTENDIDO OPERADOR EQUIPO MEDIANO

2,940.12 2,029.92 2,971.39

3,627.53 2,504.53 3,666.13SUBTOTAL MANO DE OBRA

5.00 8.00 3.00

6,567.654,534.45 6,637.52

32,838.25 36,275.60 19,912.56 89,026.41 425,879.13

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 63,881.87 21,293.96 42,587.91

127,763.74

TOTAL PRECIO UNITARIO

553,642.87

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

ZAPATAS Y PEDESTALCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA. NOMBRE UNIDAD kg m3 m PRECIO U. 2,250 280,024 7,500CANTIDADincluye desperdicio

No.

3.3.

OBRA: MATERIALES

UNIDAD:

M3

V/R. TOTAL

alambron 40 3/8 pulg liso concr.3000 psi tabla 2cmx10pulg mad.comun sin cep.(3m)

0.83 1.08 0.50

1,867.50 302,425.92 3,750.00

SUBTOTAL MATERIALES EQUIPODESCRIPCION telera en madera 0.90x1.35 vibrador electrico TIPO

308,043.42

dia hr

TARIFA/HORA 400.00

RENDIMIENTO

V/R UNITARIO

4,307

4.00 0.75 EQUIPO H. MENOR SUBTOTAL EQUIPO

1,600.00 3,230.25 4,830.25 1,865.76 6,696.01

5%

TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA V/R TOTAL

vaciado concreto zapatas

1

37,315

37,315.20

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO

37,315.20

V/R TOTAL

SUBTOTAL MANO DE OBRA

352,054.63 % 15% 5% 10% VALOR 52,808.19 17,602.73 35,205.46 105,616.39

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES

TOTAL COSTO

TOTAL PRECIO UNITARIO

457,671.02

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

CONSTRUCCION COLUMNAS 50*50CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.

No.

3.4.

OBRA: MATERIALESNOMBRE concr.3000 psi

UNIDAD:

M3

UNIDAD m3

PRECIO U. 280,024

CANTIDADincluye desperdicio

V/R. TOTAL

1.05

294,025.20

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 chapeta tensora 3/8 cua tapa colum.2.4x0.50 metal. tensor de 3/8 cua en t form.columna taco metal.largos 4.50 mts malacate 2000 lb vibrador electrico TIPO da da da da da da da h TARIFA/HORA 801 151 2,100 100 27 460 82,824 4,307 RENDIMIENTO 0.37 5.00 2.08 5.00 6.50 6.50 0.25 1.30 V/R UNITARIO

294,025.20

296.37 755.00 4,368.00 500.00 175.50 2,990.00 20,706.00 5,599.10 0.05 35,389.97 7,771.47 43,161.44

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

OFICIAL DE 1a OBRA NEGRA AYUDANTE ENTENDIDO

2,940.12 2,029.92

3,627.53 2,504.53SUBTOTAL MANO DE OBRA

14.00 14.00

6,567.65 4,534.45

91,947.10 63,482.30 155,429.40 492,616.04

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 73,892.41 24,630.80 49,261.60

147,784.81

TOTAL PRECIO UNITARIO

640,400.85

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

CONSTRUCCION VIGAS DE FUNDACION 50*50CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

3.5.

OBRA: MATERIALESNOMBRE concr.3000 psi tabla 2cmx10pulg mad.comun sin cep.(3m)

UNIDAD:

M3

UNIDAD m3 m

PRECIO U. 280,024 7,500

V/R. TOTAL

1.08 4.12

302,425.92 30,900.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 333,325.92

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 chapeta tensora 3/8 cua tapa colum.2.4x0.50 metal. tensor de 3/8 cua en t form.columna taco metal.largos 4.50 mts malacate 2000 lb vibrador electrico TIPO da da da da da da da h TARIFA/HORA RENDIMIENTO V/R UNITARIO

4,307

0.75

0.00 0.00 0.00 0.00 0.00 0.00 0.00 3,230.25 0.05 3,230.25 2,775.53 6,005.78

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO

0.00

V/R TOTAL

OFICIAL DE 1a OBRA NEGRA AYUDANTE ENTENDIDO

2,940.12 2,029.92

3,627.53 2,504.53SUBTOTAL MANO DE OBRA

5.00 5.00

6,567.65 4,534.45

32,838.25 22,672.25 55,510.50 394,842.20

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 59,226.33 19,742.11 39,484.22

118,452.66

TOTAL PRECIO UNITARIO

513,294.85

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

CONSTRUCCION LOSA ENTREPISO 14 cms CON No. LAMINA METALDECKCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

3.6.

OBRA: MATERIALESNOMBRE concr.3000 psi Lmina colaborante 2" cal 16

UNIDAD:

M3

UNIDAD m3 m2

PRECIO U. 280,024 44,314

V/R. TOTAL

0.17 1.00

46,203.96 44,314.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 90,517.96

SUBTOTAL MATERIALES EQUIPODESCRIPCION can hasta 2.80 m m.c. telera en madera 0.45x1.35 telera en madera 0.90x1.35 vigas metalicas de 3m taco metal.largos 4.50 mts malacate 2000 lb vibrador electrico TIPO da da da da da da h TARIFA/HORA 285 270 400 280 460 82,824 4,307 RENDIMIENTO 2.90 5.00 7.20 2.80 2.50 0.03 0.40 V/R UNITARIO

826.50 1,350.00 2,880.00 784.00 1,150.00 2,070.60 1,722.80 0.00 0.05 10,783.90 2,553.48 13,337.38

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO

0.00

V/R TOTAL

OFICIAL DE 1a OBRA NEGRA AYUDANTE ENTENDIDO

2,940.12 2,029.92

3,627.53 2,504.53SUBTOTAL MANO DE OBRA

4.60 4.60

6,567.65 4,534.45

30,211.19 20,858.47 51,069.66 154,925.00

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 23,238.75 7,746.25 15,492.50

46,477.50

TOTAL PRECIO UNITARIO

201,402.50

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA CORDOBA

ITEM :

CONSTRUCCION VIGAS AEREAS 50*50CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

3.7.

OBRA: MATERIALESNOMBRE concr.3000 psi

UNIDAD:

M3

UNIDAD m3

PRECIO U. 280,024

V/R. TOTAL

1.08

302,425.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 302,425.92

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 can hasta 2.80 m m.c. chapeta tensora 3/8 cua telera en madera 0.45x1.35 telera en madera 0.90x1.35 tensor de 3/8 cua en t form.columna vigas metalicas de 3m taco metal.largos 4.50 mts malacate 2000 lb vibrador electrico TIPO da da da da da da da da da da h TARIFA/HORA 801 285 151 270 400 100 27 280 460 82,824 4,307 RENDIMIENTO 2.13 22.00 18.00 32.00 32.00 19.00 32.00 16.00 20.00 0.25 1.25 V/R UNITARIO

1,702.13 6,270.00 2,718.00 8,640.00 12,800.00 1,900.00 864.00 4,480.00 9,200.00 20,706.00 5,383.75 0.05 74,663.88 11,023.84 85,687.72

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO

0.00

V/R TOTAL

OFICIAL DE 1a OBRA NEGRA AYUDANTE ENTENDIDO

2,940.12 2,029.92

3,627.53 2,504.53SUBTOTAL MANO DE OBRA

17.00 24.00

6,567.65 4,534.45

111,650.05 108,826.80 220,476.85 608,590.49

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 91,288.57 30,429.52 60,859.05

182,577.15

TOTAL PRECIO UNITARIO

791,167.63

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

CONSTRUCCION VIGA PERIMETRAL PARA LOSA No.CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA. NOMBRE UNIDAD m3 PRECIO U. 280,024CANTIDADincluye desperdicio

3.8.

OBRA: MATERIALES

UNIDAD:

M3

V/R. TOTAL

concr.3000 psi

1.08

302,425.92 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 302,425.92

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 can hasta 2.80 m m.c. chapeta tensora 3/8 cua telera en madera 0.45x1.35 telera en madera 0.90x1.35 tensor de 3/8 cua en t form.columna vigas metalicas de 3m taco metal.largos 4.50 mts vibrador electrico TIPO da da da da da da da da da h TARIFA/HORA 801 285 151 270 400 100 27 280 460 4,307 RENDIMIENTO 2.13 22.00 18.00 32.00 32.00 18.00 32.00 16.00 20.00 1.25 V/R UNITARIO

1,702.13 6,270.00 2,718.00 8,640.00 12,800.00 1,800.00 864.00 4,480.00 9,200.00 5,383.75 5% 53,857.88 11,023.84 64,881.72

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

OFICIAL DE 1a OBRA NEGRA AYUDANTE ENTENDIDO

2,940.12 2,029.92

3,627.53 2,504.53SUBTOTAL MANO DE OBRA

17.00 24.00

6,567.65 4,534.45

111,650.05 108,826.80 220,476.85 587,784.49

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 88,167.67 29,389.22 58,778.45

176,335.35

TOTAL PRECIO UNITARIO

764,119.83

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

CONSTRUCCION PLACA DE PISO E=10CMSCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

3.9.

OBRA: MATERIALESNOMBRE concr.3000 psi

UNIDAD:

M3

UNIDAD m3

PRECIO U. 280,024

V/R. TOTAL

0.11

29,402.52 0 0 0 0 0 0 0 0 29,402.52

SUBTOTAL MATERIALES EQUIPODESCRIPCION TIPO TARIFA/HORA RENDIMIENTO V/R UNITARIO

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

5%

832.66 832.66

V/R TOTAL

0

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

OFICIAL DE 1a OBRA NEGRA AYUDANTE ENTENDIDO

2,940.12 2,029.92

3,627.53 2,504.53SUBTOTAL MANO DE OBRA

1.50 1.50

6,567.65 4,534.45

9,851.48 6,801.68 16,653.15 46,888.33

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 7,033.25 2,344.42 4,688.83

14,066.50

TOTAL PRECIO UNITARIO

60,954.83

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

HIERRO REFUERZO 60000psiCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

3.10.

OBRA: MATERIALESNOMBRE acero corrugado 60000 psi alambre negro

UNIDAD:

KG

UNIDAD kg kg

PRECIO U. 3,000 2,400

V/R. TOTAL

1.03 0.04

3,090.00 100.80 0 0 0 0 0 0 0 3,190.80

SUBTOTAL MATERIALES EQUIPODESCRIPCION TIPO TARIFA/HORA RENDIMIENTO V/R UNITARIO

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

5%

30.27 30.27

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

CORTE Y FIGURACION COLOCACION REFUERZO

145.26 125.79

179.22 155.21

1.00 1.00

324.48 281.00

SUBTOTAL MANO DE OBRA

324.48 281.00 605.48 3,826.55

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 573.98 191.33 382.66

1,147.97

TOTAL PRECIO UNITARIO

4,974.52

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

VIGA METALICA SOPORTE DE LOSA ENTREPISO No.CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

3.11

OBRA: MATERIALESNOMBRE Perfil estructural C 4"x6" calibre 16 galv. Soldadura

UNIDAD:

KG

UNIDAD kg kg

PRECIO U. 3,964 6,087

V/R. TOTAL

2.78 0.06

11,018.97 365.20 0.00 11,384.18

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 can hasta 2.80 m m.c. TIPO TARIFA/HORA 801 285 RENDIMIENTO 0.20 0.20 V/R UNITARIO

160.20 57.00 0.00 0.05 217.20 166.58 383.78

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE MANO DE OBRA PRESTACIONES JORNAL T.

-

1,491.49

1,840.20

RENDIMIENTO 1.00

V/R UNITARIO 3,331.69

V/R TOTAL

SUBTOTAL MANO DE OBRA

3,331.69 3,331.69 15,099.65

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 2,264.95 754.98 1,509.97

4,529.90

TOTAL PRECIO UNITARIO

19,629.55

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

MALLA ELECTROSOLDADA D-84 D-50CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

3.12

OBRA: MATERIALESNOMBRE Malla electrosoldada D-84 D-50 Alambre negro

UNIDAD:

KG

UNIDAD kg kg

PRECIO U. 2,988 2,400

V/R. TOTAL

1.10 0.03

3,286.80 72.00 0.00 3,358.80

SUBTOTAL MATERIALES EQUIPODESCRIPCION TIPO TARIFA/HORA RENDIMIENTO V/R UNITARIO

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

5%

32.29 32.29

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE Oficial de 1a obra negra Ayudante entendido PRESTACIONES JORNAL T.

-

2,940.12 2,029.92

3,627.53 2,504.53

RENDIMIENTO 0.05 0.07

V/R UNITARIO 6,567.65 4,534.45

V/R TOTAL

SUBTOTAL MANO DE OBRA

328.38 317.41 645.79 4,036.88

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 605.53 201.84 403.69

1,211.07

TOTAL PRECIO UNITARIO

5,247.95

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

MAMPOSTERIA BLOQUE ARQUITECTONICO (CATALAN ROJO)CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

4.10

OBRA: MATERIALESNOMBRE mortero 1:5 en obra bloque catalan indural 15x10x30 blanco

UNIDAD:

M2

UNIDAD m3 und

PRECIO U. 189,750 1,300

V/R. TOTAL

0.01 36.30

2,504.70 47,190.00 0.00 0 0 49,694.70

SUBTOTAL MATERIALES EQUIPODESCRIPCION cortadora adobe-ladr.elect. s/disco andamio tramo completo 1.5x1.5 TIPO da da TARIFA/HORA 11,020 801 RENDIMIENTO 0.40 1.00 V/R UNITARIO

4,408.00 801.00 0 5% 5,209.00 666.13 5,875.13

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL tpte DISTANCIA M/KM. 11.00 TARIFA 133

V/R TOTAL

1,463.00

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO

1,463.00

V/R TOTAL

OFICIAL DE 1a OBRA NEGRA AYUDANTE ENTENDIDO

2,940.12 2,029.92

3,627.53 2,504.53SUBTOTAL MANO DE OBRA

1.20 1.20

6,567.65 4,534.45

7,881.18 5,441.34 13,322.52 70,355.35

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 10,553.30 3,517.77 7,035.53

21,106.60

TOTAL PRECIO UNITARIO

91,461.95

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

MAMPOSTERIA 10 BLOQUE CONCRETOCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA. NOMBRE UNIDAD m3 und PRECIO U. 189,750 1,269CANTIDADincluye desperdicio

No.

4.2

OBRA: MATERIALES

UNIDAD:

M2

V/R. TOTAL

mortero 1:5 en obra bloque 10x20x40

0.02 13.13

3,130.88 16,655.63 0.00 0.00 0.00 19,786.50

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 can hasta 2.80 m m.c. TIPO TARIFA/HORA 801 285 RENDIMIENTO 0.13 0.24 V/R UNITARIO

100.13 68.40 0.00 0.05 168.53 374.51 543.03

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL tpte lad.hueco 12*24*40 z.urb. DISTANCIA M/KM. 13 TARIFA 335.00

V/R TOTAL

4,396.88

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO

4,396.88

V/R TOTAL

CONST. MURO BLOQUE

268.25

330.96SUBTOTAL MANO DE OBRA

12.50

599.21

7,490.13 7,490.13 32,216.53

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 4,832.48 1,610.83 3,221.65

9,664.96

TOTAL PRECIO UNITARIO

41,881.49

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

MAMPOSTERIA 15 BLOQUE CONCRETOCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

4.3

OBRA: MATERIALESNOMBRE mortero 1:5 en obra bloque 15x20x40

UNIDAD:

M2

UNIDAD m3 und

PRECIO U. 189,750 1,549

V/R. TOTAL

0.03 13.13

6,147.90 20,330.63 0.00 0.00 0.00 26,478.53

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 can hasta 2.80 m m.c. TIPO TARIFA/HORA 801 285 RENDIMIENTO 0.21 0.24 V/R UNITARIO

170.61 68.40 0.00 0.05 239.01 374.51 613.52

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL tpte lad.hueco 12*24*40 z.urb. DISTANCIA M/KM. 13.13 TARIFA 251

V/R TOTAL

3,294.38

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO

3,294.38

V/R TOTAL

CONST. MURO BLOQUE

268.25

330.96SUBTOTAL MANO DE OBRA

12.50

599.21

7,490.13 7,490.13 37,876.55

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 5,681.48 1,893.83 3,787.65

11,362.96

TOTAL PRECIO UNITARIO

49,239.51

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

MAMPOSTERIA LIVIANA (DRYWALL)CONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

4.4

OBRA: MATERIALESNOMBRE Perfil paral cal 26 2.44 m Perfil canal de amarre cal 26 2.44 Tornillo con chazo Tornillo 7*7/16" Tornillo 6 * 1" Lana de vidrio de 18m2 Supermastico interiores 28Kg cuet Cinta papel 48 mm *40 m Placa de yeso cartn 1/2" ST Placa de yeso cartn 1/2" RH

UNIDAD:

M2

UNIDAD und und und und und rl gl rl und und

PRECIO U. 5,900 4,800 380 19 17 98,000 36,500 12,000 30,000 32,000

V/R. TOTAL

0.77 0.34 2.00 3.00 23.00 0.06 0.06 0.01 0.34 0.34

4,543.00 1,632.00 760.00 57.00 391.00 5,880.00 2,190.00 120.00 10,200.00 10,880.00 36,653.00

SUBTOTAL MATERIALES EQUIPODESCRIPCION TIPO TARIFA/HORA RENDIMIENTO V/R UNITARIO

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

5%

757.12 757.12

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

MANO DE OBRA DRYWALL

6,778.74

8,363.66

1.00

15,142.40

SUBTOTAL MANO DE OBRA

15,142.40 15,142.40 52,552.52

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 7,882.88 2,627.63 5,255.25

15,765.76

TOTAL PRECIO UNITARIO

68,318.28

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

REVOQUE IMPERMEABILIZADOCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

4.5

OBRA: MATERIALESNOMBRE mortero 1:4 en obra Sika 1 (2 kg)

UNIDAD:

M2

UNIDAD m3 kg

PRECIO U. 218,183 6,879

V/R. TOTAL

0.02 0.88

5,018.21 6,053.52 0.00 0 0 11,071.73

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 can hasta 2.80 m m.c. TIPO da da TARIFA/HORA 801 285 RENDIMIENTO 0.26 0.24 V/R UNITARIO

204.26 68.40 0 5% 272.66 412.29 684.95

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

V/R TOTAL

0

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

OFICIAL DE 1a OBRA BLANCA AYUDANTE ENTENDIDO

2,748.26 2,029.92

3,390.82 2,504.53SUBTOTAL MANO DE OBRA

0.90 0.60

6,139.08 4,534.45

5,525.17 2,720.67 8,245.84 20,002.52

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 3,000.38 1,000.13 2,000.25

6,000.75

TOTAL PRECIO UNITARIO

26,003.27

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

ESTUCO EN MUROSCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

4.6

OBRA: MATERIALESNOMBRE Estucor corona

UNIDAD:

M2

UNIDAD kg

PRECIO U. 1,140

V/R. TOTAL

0.88

1,003.20 0.00 0.00 0.00 0.00 1,003.20

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 TIPO da TARIFA/HORA 801 RENDIMIENTO 0.04 V/R UNITARIO

30.44

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

0.05

30.44 160.10 190.54

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T.

-

OFICIAL DE 1a OBRA BLANCA AYUDANTE ENTENDIDO

2,748.26 2,029.92

3,390.82 2,504.53

RENDIMIENTO 0.30 0.30

V/R UNITARIO 6,139.08 4,534.45

V/R TOTAL

SUBTOTAL MANO DE OBRA

1,841.72 1,360.34 3,202.06 4,395.80

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 659.37 219.79 439.58

1,318.74

TOTAL PRECIO UNITARIO

5,714.54

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

VINILO TIPO 1 EN MUROSCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA. NOMBRE UNIDAD gl PRECIO U. 48,100CANTIDADincluye desperdicio

No.

4.7

OBRA: MATERIALES

UNIDAD:

M2

V/R. TOTAL

Viniltex pintuco

0.10

4,810.00 0.00 0.00 0.00 0.00 4,810.00

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 can hasta 2.80 m m.c. TIPO da da TARIFA/HORA 801 285 RENDIMIENTO 0.13 0.12 V/R UNITARIO

100.13 34.20 0.00 0.05 134.33 144.76 279.08

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

OFICIAL DE 1a OBRA BLANCA AYUDANTE ENTENDIDO

2,748.26 2,029.92

3,390.82 2,504.53SUBTOTAL MANO DE OBRA

0.25 0.30

6,139.08 4,534.45

1,534.77 1,360.34 2,895.11 7,984.19

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 1,197.63 399.21 798.42

2,395.26

TOTAL PRECIO UNITARIO

10,379.44

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

PINTURA TIPO ACRILICA EN MUROS EXTERIORESCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA. NOMBRE UNIDAD gl PRECIO U. 90,000CANTIDADincluye desperdicio

No.

4.8

OBRA: MATERIALES

UNIDAD:

M2

V/R. TOTAL

Pintura acrlica koraza

0.15

13,500.00 0.00 0.00 0.00 0.00 13,500.00

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 can hasta 2.80 m m.c. TIPO da da TARIFA/HORA 801 285 RENDIMIENTO 0.13 0.12 V/R UNITARIO

100.13 34.20 0.00 0.05 134.33 144.76 279.08

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

OFICIAL DE 1a OBRA BLANCA AYUDANTE ENTENDIDO

2,748.26 2,029.92

3,390.82 2,504.53SUBTOTAL MANO DE OBRA

0.25 0.30

6,139.08 4,534.45

1,534.77 1,360.34 2,895.11 16,674.19

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 2,501.13 833.71 1,667.42

5,002.26

TOTAL PRECIO UNITARIO

21,676.44

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

PINTURA EPOXICA BIOCIDACONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA. NOMBRE UNIDAD gl PRECIO U. 145,000CANTIDADincluye desperdicio

No.

4.9

OBRA: MATERIALES

UNIDAD:

M2

V/R. TOTAL

Pintura epoxica biocida

0.10

14,500.00 0.00 0.00 0.00 0.00 14,500.00

SUBTOTAL MATERIALES EQUIPODESCRIPCION andamio tramo completo 1.5x1.5 can hasta 2.80 m m.c. TIPO da da TARIFA/HORA 801 285 RENDIMIENTO 0.13 0.12 V/R UNITARIO

100.13 34.20 134.33 213.47 347.80

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

5%

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

OFICIAL DE 1a OBRA BLANCA AYUDANTE ENTENDIDO

2,748.26 2,029.92

3,390.82 2,504.53SUBTOTAL MANO DE OBRA

0.40 0.40

6,139.08 4,534.45

2,455.63 1,813.78 4,269.41 19,117.21

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 2,867.58 955.86 1,911.72

5,735.16

TOTAL PRECIO UNITARIO

24,852.37

ARQ. CESAR AUGUSTO ARBELAEZ C.DEPARTAMENTO DE CORDOBA MUNICIPIO DE :

ANALISIS DE PRECIOS UNITARIOS MONTERIA cordoba

ITEM :

CIELO RASO SUSPENDIDO DRYWALLCONSTRUCCION Y DOTACION DE LA UNIDAD MATERNO INFANTIL Y MANTENIMIENTO DE LAS UNIDADES DE APOYO UBICADAS EN EL BLOQUE B DE LA E.S.E. HOSPITAL SAN JERONIMO DE MONTERIA.CANTIDADincluye desperdicio

No.

5.1

OBRA: MATERIALESNOMBRE Tornillo 7*7/16" Tornillo 6 * 1" Supermastico interiores 28Kg cuet Perfil omega cal 26 2.44m Cinta papel 48 mm *40 m Placa de yeso cartn 1/2" ST Perfil ngulo perimetral Perfil vigueta cal 26 2.44m

UNIDAD:

M2

UNIDAD und und gl und rl und und und

PRECIO U. 19 17 36,500 5,000 12,000 18,900 3,100 4,300

V/R. TOTAL

6.00 11.00 0.76 0.70 0.01 0.34 0.55 0.53

114.00 187.00 27,740.00 3,500.00 72.00 6,426.00 1,705.00 2,279.00 0 42,023.00

SUBTOTAL MATERIALES EQUIPODESCRIPCION TIPO TARIFA/HORA RENDIMIENTO V/R UNITARIO

EQUIPO H. MENOR SUBTOTAL EQUIPO TRANSPORTESMATERIAL DISTANCIA M/KM. TARIFA

5%

750.00 750.00

V/R TOTAL

SUBTOTAL TRANSPORTE MANO DE OBRANOMBRE PRESTACIONES JORNAL T. RENDIMIENTO V/R UNITARIO V/R TOTAL

-

MANO DE OBRA CIELO RASO

6,715.00

8,285.00

1.00

15,000.00

SUBTOTAL MANO DE OBRA

15,000.00 15,000.00 57,773.00

TOTAL COSTO DIRECTO COSTOS INDIRECTOS DESCRIPCION ADMINISTRACION IMPREVISTOS UTILIDADES % 15% 5% 10% TOTAL COSTO VALOR 8,665.95 2,888.65 5,777.30

17,331.90

TOTAL PRECIO UNITAR