P AUL ORELL ANA CS0301 RUTAS CRÍTICAS EL PROGRAMA TERMINA A LAS 22 SEMANAS RUTA CRITICA : B-C-F-H-J ACTIVIDAD ES ACTIVIDADES PRECEDENTES TIEMPO A 5 B 4 C B 3 D A,C 2 E D 6 F C 5 G F 3 H F 4 I B 4 J H,E,G 6
-