VOLCAN COMPAÑÍA MINERA S.A.A. PROTOCOLO DE INSTALACION DE ESTRUCTURAS PROYECTO: FABRICACIÓN Y MONTAJE DE TECHOS DE GALPON PTAD ANDAYCHA No.: PTAD -T PLANO Y COD. MARCA: VyP-PTAD-TO-02/ TE FECHA: ACEPTABLE CODIGO DE MARCAS AJUSTE Y GROUTEO NIVELACION Y PLOMADA TORQUEO DE PERNOS ACABADO DE PINTURA APARIENCIA FINAL Comentarios: Esquema de Estructura: ITEM MATERIAL CANTIDAD 1.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 447 - 4 2.73 2.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 1945 - 4 11.87 3.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 3525 - 2 21.51 4.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 848 - 4 5.17 5.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 878 - 4 5.36 6.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 1223 - 4 7.46 7.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 1398 - 2 8.53 8.0 PLATE-ASTM_A36-1/4" 47.101 200 126 4 1.19 Peso Total estructura (Kg): PESO ESPECIF. (Kg/m ó Kg/m2) LONGITUD (mm) ANCHO (mm) PESO UNITARIO (Kg) Supervisor VCM: Nombre: ........................................ ............................................ Fecha: ......................................... .............................................. Supervisor Contratista: Nombre: ................................. ......................................... Fecha: .................................. ......................................... N UDO 1 NU DO 2 NU DO 4 N UDO 4 NUD O 5 N UDO 4 NUD O 2 NUD O 1 N UDO 3 x TIJE R A LE S EX NUDO 1 NUDO 2 NUDO 3 NUDO 4 NUDO 5 P L 1/4" P L 1/4" P L 1/4" P L 1/4" TE 2 und

description

p.m.

Transcript of Prot. Montaje t.o.

Page 1: Prot. Montaje t.o.

VOLCAN COMPAÑÍA MINERA S.A.A.

PROTOCOLO DE INSTALACION DE ESTRUCTURAS

PROYECTO: FABRICACIÓN Y MONTAJE DE TECHOS DE GALPON PTAD ANDAYCHAGUA No.: PTAD -TO-01

PLANO Y COD. MARCA: VyP-PTAD-TO-02/ TE FECHA: 5/14/2014

ACEPTABLE ACEPTABLE

CODIGO DE MARCAS AJUSTE Y GROUTEO

NIVELACION Y PLOMADA TORQUEO DE PERNOS

ACABADO DE PINTURA APARIENCIA FINAL

Comentarios:

Esquema de Estructura:

ITEM MATERIAL CANTIDAD

1.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 447 - 4 2.73 10.91

2.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 1945 - 4 11.87 47.47

3.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 3525 - 2 21.51 43.01

4.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 848 - 4 5.17 20.69

5.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 878 - 4 5.36 21.43

6.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 1223 - 4 7.46 29.85

7.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 1398 - 2 8.53 17.06

8.0 PLATE-ASTM_A36-1/4" 47.101 200 126 4 1.19 4.75

Peso Total estructura (Kg): 195.16

PESO ESPECIF.(Kg/m ó Kg/m2)

LONGITUD(mm)

ANCHO(mm)

PESO UNITARIO(Kg)

PESO TOTAL(Kg)

Supervisor VCM:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Supervisor Contratista:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

NUDO 1

NUDO 2

NUDO 4NUDO 4

NUDO 5

NUDO 4

NUDO 2

NUDO 1

NUDO 3

x

x

TIJERALES EXTREMOS

NUDO 1 NUDO 2 NUDO 3 NUDO 4 NUDO 5

PL 1/4" PL 1/4"PL 1/4"

PL 1/4"

TE

2 und

Page 2: Prot. Montaje t.o.

VOLCAN COMPAÑÍA MINERA S.A.A.

PROTOCOLO DE INSTALACION DE ESTRUCTURAS

PROYECTO: FABRICACIÓN Y MONTAJE DE TECHOS DE GALPON PTAD ANDAYCHAGUA No.: PTAD -TO-01

PLANO Y COD. MARCA: VyP-PTAD-TO-02/ TE FECHA: 5/14/2014

ITEM MATERIAL CANTIDAD

9.0 PLATE-ASTM_A36-1/4" 47.101 353 359 4 5.97 23.88

10.0 PLATE-ASTM_A36-1/4" 47.101 332 126 4 1.97 7.88

11.0 PLATE-ASTM_A36-1/4" 47.101 390 126 6 2.31 13.89

12.0 PLATE-ASTM_A36-1/4" 47.101 300 200 2 2.83 5.65

13.0 ANGULO - AISC - L 2 X 2 X 1/4 4.747 95 - 8 0.45 3.61

14.0 ANGULO - AISC - L 2 X 2 X 1/4 4.747 45 - 12 0.21 2.56

15.0

16.0

Peso Total estructura (Kg): 57.47

PESO ESPECIF.(Kg/m ó Kg/m2)

LONGITUD(mm)

ANCHO(mm)

PESO UNITARIO(Kg)

PESO TOTAL(Kg)

Supervisor VCM:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Supervisor Contratista:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Page 3: Prot. Montaje t.o.

VOLCAN COMPAÑÍA MINERA S.A.A.

PROTOCOLO DE INSTALACION DE ESTRUCTURAS

PROYECTO: FABRICACIÓN Y MONTAJE DE TECHOS DE GALPON PTAD ANDAYCHAGUA No.: PTAD -TO-02

PLANO Y COD. MARCA: VyP-PTAD-TO-02/ TM FECHA: 5/14/2014

ACEPTABLE ACEPTABLE

CODIGO DE MARCAS AJUSTE Y GROUTEO

NIVELACION Y PLOMADA TORQUEO DE PERNOS

ACABADO DE PINTURA APARIENCIA FINAL

Comentarios:

Esquema de Estructura:

ITEM MATERIAL CANTIDAD

1.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 447 - 4 2.73 10.91

2.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 1945 - 4 11.87 47.47

3.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 3525 - 2 21.51 43.01

4.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 848 - 4 5.17 20.69

5.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 878 - 4 5.36 21.43

6.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 1223 - 4 7.46 29.85

7.0 ANGULO - AISC - L 2 1/2 X 2 1/2" X 1/4 6.101 1398 - 2 8.53 17.06

8.0 PLATE-ASTM_A36-1/4" 47.101 200 126 4 1.19 4.75

Peso Total estructura (Kg): 195.16

PESO ESPECIF.(Kg/m ó Kg/m2)

LONGITUD(mm)

ANCHO(mm)

PESO UNITARIO(Kg)

PESO TOTAL(Kg)

Supervisor VCM:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Supervisor Contratista:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

NUDO 1

NUDO 2

NUDO 4NUDO 4

NUDO 5

NUDO 4

NUDO 2

NUDO 1

NUDO 3

TM

2 und

NUDO 1 NUDO 2 NUDO 3 NUDO 4 NUDO 5

PL 1/4" PL 1/4"PL 1/4"

PL 1/4"

Page 4: Prot. Montaje t.o.

VOLCAN COMPAÑÍA MINERA S.A.A.

PROTOCOLO DE INSTALACION DE ESTRUCTURAS

PROYECTO: FABRICACIÓN Y MONTAJE DE TECHOS DE GALPON PTAD ANDAYCHAGUA No.: PTAD -TO-02

PLANO Y COD. MARCA: VyP-PTAD-TO-02/ TM FECHA: 5/14/2014

ITEM MATERIAL CANTIDAD

1.0 PLATE-ASTM_A36-1/4" 47.101 353 359 4 5.97 23.88

2.0 PLATE-ASTM_A36-1/4" 47.101 332 126 4 1.97 7.88

3.0 PLATE-ASTM_A36-1/4" 47.101 390 126 6 2.31 13.89

4.0 PLATE-ASTM_A36-1/4" 47.101 300 200 2 2.83 5.65

5.0 ANGULO - AISC - L 2 X 2 X 1/4 4.747 95 - 8 0.45 3.61

6.0 ANGULO - AISC - L 2 X 2 X 1/4 4.747 98 - 8 0.47 3.72

7.0 ANGULO - AISC - L 2 X 2 X 1/4 4.747 91 - 12 0.43 5.18

8.0

Peso Total estructura (Kg): 63.81

PESO ESPECIF.(Kg/m ó Kg/m2)

LONGITUD(mm)

ANCHO(mm)

PESO UNITARIO(Kg)

PESO TOTAL(Kg)

Supervisor VCM:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Supervisor Contratista:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Page 5: Prot. Montaje t.o.

VOLCAN COMPAÑÍA MINERA S.A.A.

PROTOCOLO DE INSTALACION DE ESTRUCTURAS

PROYECTO: FABRICACIÓN Y MONTAJE DE TECHOS DE GALPON PTAD ANDAYCHAGUA No.: PTAD -TO-03

PLANO Y COD. MARCA: VyP-PTAD-TO-03/ M, N, O, Z1,Z2,Z3 FECHA: 5/14/2014

ACEPTABLE ACEPTABLE

CODIGO DE MARCAS AJUSTE Y GROUTEO

NIVELACION Y PLOMADA TORQUEO DE PERNOS

ACABADO DE PINTURA APARIENCIA FINAL

Comentarios:

Esquema de Estructura:

ITEM MATERIAL CANTIDAD

1.0 ANGULO - AISC - L 2 X 2 X 1/4 4.747 2666 - 4 12.66 50.62

2.0 ANGULO - AISC - L 2 X 2 X 1/4 4.747 2706 - 4 12.85 51.38

3.0 ANGULO - AISC - L 2 X 2 X 1/4 4.747 2191 - 4 10.40 41.60

4.0 CANAL Z ATIEZADA 4"X2"X3MM 5.22 2820 - 6 14.72 88.32

5.0 CANAL Z ATIEZADA 4"X2"X3MM 5.22 2771 - 6 14.46 86.79

6.0 CANAL Z ATIEZADA 4"X2"X3MM 5.22 2339 - 6 12.21 73.26

7.0

8.0

Peso Total estructura (Kg): 391.97

PESO ESPECIF.(Kg/m ó Kg/m2)

LONGITUD(mm)

ANCHO(mm)

PESO UNITARIO(Kg)

PESO TOTAL(Kg)

Supervisor VCM:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Supervisor Contratista:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

1 2

Z1

M L 2"x2"x1/4" N L 2"x2"x1/4"

O L 2"x2"x1/4"

Z 4" X 2" X 3mm

Z1 Z 4" X 2" X 3mm

Z2 Z 4" X 2" X 3mm

Z2 Z 4" X 2" X 3mm

Z3 Z 4" X 2" X 3mm

Z3 Z 4" X 2" X 3mm

Page 6: Prot. Montaje t.o.

VOLCAN COMPAÑÍA MINERA S.A.A.

PROTOCOLO DE INSTALACION DE ESTRUCTURAS

PROYECTO:

PLANO Y COD. MARCA: FECHA:

ACEPTABLE ACEPTABLE

CODIGO DE MARCAS AJUSTE Y GROUTEO

NIVELACION Y PLOMADA TORQUEO DE PERNOS

ACABADO DE PINTURA APARIENCIA FINAL

Comentarios:

Esquema de Estructura:

ITEM MATERIAL CANTIDAD

1.0

2.0

3.0

4.0

5.0

6.0

7.0

8.0

Peso Total estructura (Kg): 0.00

PESO ESPECIF.(Kg/m ó Kg/m2)

LONGITUD(m)

ANCHO(m)

PESO UNITARIO(Kg)

PESO TOTAL(Kg)

Supervisor VCM:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Supervisor Contratista:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Page 7: Prot. Montaje t.o.

Supervisor VCM:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Supervisor Contratista:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Page 8: Prot. Montaje t.o.

VOLCAN COMPAÑÍA MINERA S.A.A.

PROTOCOLO DE INSTALACION DE ESTRUCTURAS

PROYECTO:

PLANO Y COD. MARCA: FECHA:

ACEPTABLE ACEPTABLE

CODIGO DE MARCAS AJUSTE Y GROUTEO

NIVELACION Y PLOMADA TORQUEO DE PERNOS

ACABADO DE PINTURA APARIENCIA FINAL

Comentarios:

Esquema de Estructura:

ITEM MATERIAL CANTIDAD

1.0 P

2.0

3.0

4.0

5.0

6.0

7.0

8.0

Peso Total estructura (Kg): 0.00

PESO ESPECIF.(Kg/m ó Kg/m2)

LONGITUD(m)

ANCHO(m)

PESO UNITARIO(Kg)

PESO TOTAL(Kg)

Supervisor VCM:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Supervisor Contratista:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Page 9: Prot. Montaje t.o.

Supervisor VCM:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................

Supervisor Contratista:Nombre: ....................................................................................Fecha: .......................................................................................Firma: ........................................................................................